OTAVI SHOW HOUSE
“HOW ONE CAN BUILD A HOUSE IN LESS THAN A WEEK”
WV Construction Otavi Show House 3
I. House design
A practical house design can be seen below. The house meets and satisfies basic needs.
Figure 1: Elevation views
Figure 2: Layout & site plan
WV Construction Otavi Show House 4
II. The Construction Process
DAY 1
Construction commences with earth clearing and preparation for the concrete slab.
Figure 3: Earthworks
Figure 4: Concrete Slab
WV Construction Otavi Show House 5
DAY 2
The steel structures are efficiently assembled on site and prepared for positioning on the
concrete slabs.
Figure 5 & 6: Steel structure assembly in the Otavi warehouse
Figure 7: Steel structure positioning on the concrete slabs
WV Construction Otavi Show House 6
DAY 3
The internal wall cladding is fastened to the structure. Simultaneous electrical and internal
plumbing installation is installed.
Figure 8: Internal wall cladding
Figure 9: Insulation installation
WV Construction Otavi Show House 7
DAY 4
The roof structure and roof sheeting is installed.
DAY 5
The plumbing reticulation is completed,
including toilet, hand wash basin, shower and
tiles are fitted. Thereafter the fibre-cement
board finishing is completed and the windows
and doors are installed.
Figure 12 & 13: Completion of the fittings and finishing
Figure 11: Roof structure with steel frame Figure 10: Roof structure
WV Construction Otavi Show House 8
DAY 6
The final paint and finishing is completed and the house is handed over.
Figure 14: Front view of the house
Figure 16: Completed house front and side views