OTIA III State Bridge Delivery Program. There are three basic methods that are being used to deliver the Program. Presented by Deborah Geideman, Deputy Program Manager, BDU. Project Delivery Methods. Region Delivery In house design Outsourced design - PowerPoint PPT Presentation
Citation preview
OTIA III State Bridge OTIA III State Bridge Delivery ProgramDelivery Program
There are three basic methods that are being used to deliver the Program
Presented by Deborah Geideman, Deputy Program Manager, BDU
Project Delivery MethodsProject Delivery Methods
1. Region Delivery– In house design– Outsourced design
2. Delivery through Oregon Bridge Delivery Partners (OBDP)– Outsourced design through
subcontracts– Management of Design through Agency
ATAs (Stage 1)
3. Design-Build
A/E Contracting StructureA/E Contracting Structure
OTIA III State Bridge Delivery Program
Region Delivered Projects OBDP Delivered Projects
ODOT ATAs - BDU WOC Processing
OBDP Subcontracts(OBDP - BDU Design
WOC Processing)
Design-Build Delivered Projects
ODOT Construction Contracts
Stage 1 ODOT ATAs - BDU WOC Processing
ODOT In House Design
Summary of DeliverySummary of Delivery
• Total “Work” Bridges in the Program = 293
• The bridges have been combined “bundled” into 72 separate projects– 24 Region Delivered Bundles– 34 OBDP Delivered Bundles– 14 Design-Build Bundles
Summary of Program StagesSummary of Program Stages
• The 72 bundles are delivered in 5 Stages– Stage 1 – 14 Bundles – Stage 2 – 21 Bundles – Stage 3 – 17 Bundles– Stage 4 – 12 Bundles– Stage 5 – 8 Bundles
• All bundles in Stages 1-3 are assigned with the exception of the Willamette River Bridge
• There are 10 bundles in Stages 4 & 5 unassigned
OTIA III State Bridge Delivery Program Bundles in Each Stage
Stage 1, 14
Stage 2, 21Stage 3, 17
Stage 4, 12
Stage 5, 8
Progress Underway - DesignProgress Underway - Design
OBDP Website – Home Page OBDP Website – Home Page http://http://www.obdp.orgwww.obdp.org
OBDP Website - Procurement OBDP Website - Procurement PagePage
• BDUBeth EnosProcurement OfficerE-mail: [email protected]: (503) 986-6632
• OBDPJim ReynoldsProcurement Manager (Dept. Manager) E-mail: [email protected]: (503) 587-2906Norine AskSr. Contract ManagerE-mail: [email protected]: (503) 587-2954
Contracts Key PersonnelContracts Key Personnel
Other ThoughtsOther Thoughts
Resource Handouts: • Office of Project Delivery (OPD)
Organization Chart• OBDP/OPD Contact List• Resources for Success in OTIA III State
Bridge Program and Beyond• Business/Accounting Survival TipsWebsite:http://www.oregon.gov/ODOT/HWY/OPD/
PersonalServicesContracts.shtml
QuestionsQuestions