OTIA III State Bridge Delivery Program. There are three basic methods that are being used to deliver the Program. Presented by Deborah Geideman, Deputy Program Manager, BDU. Project Delivery Methods. Region Delivery In house design Outsourced design - PowerPoint PPT Presentation

Citation preview

Page 1: OTIA III State Bridge  Delivery Program

OTIA III State Bridge OTIA III State Bridge Delivery ProgramDelivery Program

There are three basic methods that are being used to deliver the Program

Presented by Deborah Geideman, Deputy Program Manager, BDU

Page 2: OTIA III State Bridge  Delivery Program

Project Delivery MethodsProject Delivery Methods

1. Region Delivery– In house design– Outsourced design

2. Delivery through Oregon Bridge Delivery Partners (OBDP)– Outsourced design through

subcontracts– Management of Design through Agency

ATAs (Stage 1)

3. Design-Build

Page 3: OTIA III State Bridge  Delivery Program

A/E Contracting StructureA/E Contracting Structure

OTIA III State Bridge Delivery Program

Region Delivered Projects OBDP Delivered Projects

ODOT ATAs - BDU WOC Processing

OBDP Subcontracts(OBDP - BDU Design

WOC Processing)

Design-Build Delivered Projects

ODOT Construction Contracts

Stage 1 ODOT ATAs - BDU WOC Processing

ODOT In House Design

Page 4: OTIA III State Bridge  Delivery Program

Summary of DeliverySummary of Delivery

• Total “Work” Bridges in the Program = 293

• The bridges have been combined “bundled” into 72 separate projects– 24 Region Delivered Bundles– 34 OBDP Delivered Bundles– 14 Design-Build Bundles

Page 5: OTIA III State Bridge  Delivery Program

Summary of Program StagesSummary of Program Stages

• The 72 bundles are delivered in 5 Stages– Stage 1 – 14 Bundles – Stage 2 – 21 Bundles – Stage 3 – 17 Bundles– Stage 4 – 12 Bundles– Stage 5 – 8 Bundles

• All bundles in Stages 1-3 are assigned with the exception of the Willamette River Bridge

• There are 10 bundles in Stages 4 & 5 unassigned

OTIA III State Bridge Delivery Program Bundles in Each Stage

Stage 1, 14

Stage 2, 21Stage 3, 17

Stage 4, 12

Stage 5, 8

Page 6: OTIA III State Bridge  Delivery Program

Progress Underway - DesignProgress Underway - Design

Page 7: OTIA III State Bridge  Delivery Program

OBDP Website – Home Page OBDP Website – Home Page http://http://www.obdp.orgwww.obdp.org

Page 8: OTIA III State Bridge  Delivery Program

OBDP Website - Procurement OBDP Website - Procurement PagePage

Page 9: OTIA III State Bridge  Delivery Program

• BDUBeth EnosProcurement OfficerE-mail: [email protected]: (503) 986-6632

• OBDPJim ReynoldsProcurement Manager (Dept. Manager) E-mail: [email protected]: (503) 587-2906Norine AskSr. Contract ManagerE-mail: [email protected]: (503) 587-2954

Contracts Key PersonnelContracts Key Personnel

Page 10: OTIA III State Bridge  Delivery Program

Other ThoughtsOther Thoughts

Resource Handouts: • Office of Project Delivery (OPD)

Organization Chart• OBDP/OPD Contact List• Resources for Success in OTIA III State

Bridge Program and Beyond• Business/Accounting Survival TipsWebsite:http://www.oregon.gov/ODOT/HWY/OPD/

PersonalServicesContracts.shtml