Typical sequence of wind farm construction
Access Roads
Concrete Batch Plant (if required)
Public Road Improvements (if required)
Turbine Foundations
Electrical Collection System
Wind Turbines
Project Substation
Operations and Maintenance Facility
Wind Energy Services
2
Access Roads
Gravel roads linking wind turbine strings to existing
roads
Typical construction sequence:
• Install erosion and sediment controls where required
• Clear and grade road
• Install required drainage (i.e. culverts)
• Install base materials (i.e. geo-fabric or Geo-Grid)
• Install and compact gravel road
In sensitive areas (i.e. wetlands), the width of the road
(temporary and permanent) should be as minimal as
possible
Wind Energy Services
3
Install erosion and sediment controls
Wind Energy Services
4
Clear and Grade Road
Wind Energy Services
5
Install required drainage (i.e. culverts)
Wind Energy Services
6
Install base materials (i.e. geo-fabric or Geo-
Grid)
Wind Energy Services
7
Install and compact gravel road
Wind Energy Services
8
Concrete Batch Plant (if required)
Requires and air quality permit
Wind Energy Services
9
Public Road Improvements
Road and intersection widening
Culvert and bridge replacement
Reconstruction of previously existing roads
Often requires road permits from DOT, County and also
environmental regulatory agency
Wind Energy Services
10
Turbine Foundations
Temporary turbine workspace typically 150 – 200 foot
radius
Permanent area of disturbance typically 50 foot radius
Wind Energy Services
11
Turbine Foundations, con’t.
Wind Energy Services
12
Turbine Foundations, con’t.
Wind Energy Services
13
Turbine Foundations, con’t.
Wind Energy Services
14
Electrical Collection System
Wind Energy Services
15
Electrical Collection System, con’t.
Wind Energy Services
16
Wind Turbine Erection
Wind Energy Services
17
Wind Turbine Erection, con’t
Wind Energy Services
18
Wind Turbine Erection, con’t
Wind Energy Services
19
Wind Turbine Erection, con’t.
Wind Energy Services
20
Wind Energy Services
21
Wind Turbine Erection con’t.
Wind Energy Services
22
Project Substation
Be sure to install appropriate secondary containment in
accordance with SPCC regulations
Wind Energy Services
23
Restoration and Reclamation
Restore and reclaim
In accordance with
Issued permits and
agreements with various
agencies (i.e. agricultural)
and landowners
Wind Energy Services
24