24
EPA Vessel General Permit Overview of the Final 2013 VGP November 6, 2013

Overview of the Final 2013 VGP November 6, 2013. Presentation Overview Background EPA and the Clean Water Act VGP basics and key dates 2008 VGP Overview

Embed Size (px)

Citation preview

Page 1: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

EPA Vessel General PermitOverview of the Final 2013 VGP

November 6, 2013

Page 2: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Presentation Overview Background

EPA and the Clean Water ActVGP basics and key dates

2008 VGP Overview and Inspection Summary Final 2013 VGP - Summary of Key Conditions

Ballast WaterExhaust Gas Scrubber EffluentEnvironmentally Preferable Products Implementation/Efficiencies

State Water Quality Certifications

2

Page 3: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

3

Any “point” source”

“discharge of a pollutant”

to “waters of the U.S.”

Must obtain NPDES permit coverage (provides legal authority for those discharges of pollutants to waters of the U.S.)

The Clean Water Act (CWA) Established the National Pollutant Discharge

Elimination System (NPDES) permit program

Page 4: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

NPDES Permitting National Pollutant Discharge Elimination

System (NPDES) PermitsIndividual permits and general permitsPermit term not to exceed 5 yearsFor EPA-issued permits, State water quality

certification required

4

Page 5: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

5

NPDES Permit ComponentsCover Page

Effluent Limitations

Technology-Based

Water Quality-Based

Monitoring & ReportingRequirements

Special Conditions

Compliance SchedulesSpecial Studies,

Evaluations, and Other Requirements

Standard Conditions

• Effluent Guidelines• Best Professional Judgment (BPJ)

• Best Management Practices (BMPs)

Page 6: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Vessel General Permit - Key Dates September 18, 2006: a U.S District Court issued an order

revoking regulation (40 CFR 122.3(a)) which meant that incidental discharges from vessels were required to have NPDES permits, consistent with the Clean Water Act

December 18, 2008: EPA finalizes first Vessel General Permit (2008 VGP)

2009-2011: EPA develops technical information for next VGP and gathers information from the regulated community

November 30, 2011: EPA releases draft 2013 VGP February 21, 2012: Close of public comment period March 2012: USCG finalizes Ballast Water Discharge Standard

Regulation March 28, 2013: EPA issues 2013 VGP December 19, 2013: Effective date of the 2013 VGP

6

Page 7: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

EPA – Implements and administers the VGP USCG – Inspect vessels for compliance with

the VGP EPA – Conducts enforcement actions for the

VGP

Implementation and Enforcement

7

Page 8: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Permit Applicability Jurisdiction of the permit

Inland waters, territorial sea up to 3 nautical miles (nm)

Discharge coverage 27 discharge types incidental to the normal

operation of a non-recreational and non military vessels 79 feet or longer, except commercial fishing vessels, and all ballast water discharges, regardless of size

Has additional vessel class-specific conditions for 8 classes of vessels

Vessel discharges not eligible for coverage(e.g., sewage)

8

Page 9: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Coverage Under the Permit Notice of Intent (NOI) for coverage

For the VGP, NOI is required only for certain vessels: Greater than or equal to 300 gross tons; or Have a ballast water capacity of at least 8 cubic meters.

Visit www.epa.gov/npdes/vessels/eNOI to access system

Notice of Termination (NOT) of coveragePermittee must submit when permanently

terminating coverage under the VGPPermittees do not need to submit NOTs every time

they leave waters subject to this permit (e.g. international voyages)

9

Page 10: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

2008 VGP - Overview VGP effective February 6, 2009 Estimated to cover approx. 61,000 US flagged

commercial vessels and 8,000 foreign flagged Vessels that are greater than or equal to 300 gross tons or

with more than 8 cubic meters ballast water capacity had to submit a Notice of Intent (NOI) to EPA by September 19, 2009

New vessels or vessels newly entering US waters must submit an NOI to EPA 30 days prior to discharging into waters covered by the VGP

Currently, approximately 50,000 vessels have submitted NOIs

Reporting requirements – One Time Report and Annual Non-Compliance report

10

Page 11: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

2008 VGP – Inspection Summary

11

  TOTAL US Flag% of US

IOCForeign Flagged

% of FF IOC

Total Reported Inspection Result Items of Note (non-compliance TBD) 364

94 (25.8% of

Total) - -

270 (74.2% of

Total) - -

No NOI 184 45 47.9% 139 51.5%

Routine Visual Inspections 145 41 43.6% 104 38.5%

Ballast Water Management Plans 9 0 0.0% 9 3.3%

2.2.3.5 5 1 1.1% 4 1.5%

Corrective Action Assessment 5 2 2.1% 3 1.1%

Ballast Water and Additional Recordkeeping 4 0 0.0% 4 1.5%

Deck Washdown 3 1 1.1% 2 0.7%

Annual Inspections 3 1 1.1% 2 0.7%

Material Storage 2 0 0.0% 2 0.7%

Drydock Inspection Reports 2 2 2.1% 0 0.0%

Bilgewater 1 1 1.1% 0 0.0%

Bilgewater Additional Recordkeeping 1 0 0.0% 1 0.4%

Page 12: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

NOI requirements (No. 1 deficiency)Certifying NOIs within the eNOI system

Terminating vs. Updating NOIs Routine inspections (No. 2 deficiency)

Routine inspections; conduct before crossing the 3 mile threshold

Compliance binders

2008 VGP – Inspection Observations

12

Page 13: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

2013 Final VGP – Overview Effective December 19, 2013 Primarily applies to non-recreational, non-

military vessels generally greater than 79 feetApproximately 70,000 existing VGP vessels plus

~2,200 commercial fishing vessels greater than 79 feet (if needed)

New NOI and annual report system in developmentTarget release date – Early Fall 2013For those vessels that must submit them, NOIs must

be submitted by December 12, 2013 or 7 days before operating in U.S. waters

13

Page 14: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Expressed as instantaneous maximum

Ballast Water – Effluent Limits

Large Organisms(> 50μm)

Small Organisms(>10μ and ≤50 μm)

Toxigenic Vibrio

cholerae (O1 & O139)

Eschericia coliIntestinal

enterococci

< 10 per m3 < 10 per ml <1 cfu per 100 ml

<250 cfu per 100 ml

<100 cfu per 100 ml

14

Page 15: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Four possible options to meet limits:Use a treatment device (e.g. U.S. type approved system or an AMS) Use onshore treatmentUse public water supply water (from US and Canada only)No discharge

Implementation schedule:

Ballast Water – Implementation

15

Vessel’s Ballast Water Capacity Date Constructed Vessel’s Compliance

Date

Newvessels

After December 1,2013

On delivery

Existingvessels

Less than1500 m3

Before December 1,2013

First scheduled drydocking after January 1, 2016

1500-5000 m3 Before December 1,2013

First scheduled drydocking after January 1, 2014

Greater than5000 m3

Before December 1,2013

First scheduled drydocking after January 1, 2016

Page 16: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Monitoring requirements if using a treatment deviceFunctional

Goal is to test if the system functioning as designed (e.g., applying chlorine dose, filtering water)

Biological E. coli, enterococci, and total heterotrophic bacteria

Active substance and residuals (for systems that use them) Numeric limits for systems using chlorine, chlorine dioxide, ozone,

and peracetic acid Other parameters set at Gold Book values (if such systems were to

be developed)Reduced frequency monitoring schedule available if system is

one for which US government has high quality efficacy/toxicity type approval data from flag administration or vendor

Ballast Water - Monitoring

16

Page 17: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Interim requirements must be met until numeric limits apply Requirements fundamentally the same as the 2008 VGP

Interim requirements include: Incorporating existing U.S. Coast Guard mandatory

management and exchange requirementsMandatory saltwater flushing for all vessels with

residual ballast water and sediment (NOBOBs) coming from outside the USEEZ and 200 nm from shore

Mandatory exchange and flushing for vessels engaged in Pacific nearshore voyages

Conducting exchange as early as practicable

Ballast Water – Interim Requirements

17

Page 18: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Exhaust Gas Scrubber Effluent Exhaust gas scrubber effluent is wash water that has

been used in cleaning vessel exhaust gases Consistent with IMO voluntary guidelines

Guidelines include limits for pH, turbidity, nitrates, and one PAH compound

Require monitoring Assure systems capable of meeting limits

Currently applicable to a handful of vessels EPA trying to establish clear limits to provide certainty for system

operators and assure that discharges are not left uncontrolled

Changes from the Proposed to Final VGP: Based on comments received, EPA lowered pH limit from 6.5 to 6.0 Updated monitoring schedule and approach

18

Page 19: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Environmentally Preferable Products Increasing mandate for use of “environmentally

acceptable lubricants” (EALs) in US waters (vegetable oils, synthetic esters, and polyalkylene glycols)Stern tubes alone have been estimated to leak between

4.6 to 28.6 million liters of oil annually into ports worldwide

Oil to Sea interfaces include stern tubes, thrusters, hydraulic pitch propellers, wire rope lubrication, etc.

Must use unless technically infeasible

Minimally toxic cleaners and detergents

Phosphate free soaps and detergents

19

Page 20: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Reporting and Inspection Improvements Annual Report

Eliminate One-Time Report and Annual Non-Compliance Report and consolidate into Annual Report

Report all analytical monitoring as part of Annual ReportAll unmanned, unpowered barges and other vessels less than

300 gross tons may file a combined annual report if they meet certain conditions

Reduce duplicative reportingWhere immediate notification is reported to the National

Response Center, no longer need to also report to EPA regionsExtended Unmanned Period Inspections

Allowed for vessels in lay-up or fleeted (at the vessel owner/operator’s discretion) in lieu of routine visual inspections

20

Page 21: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

General Efficiency Improvements

Reduced NOI processing time from 30 to 7 days (for electronic filers only)

Developing electronic tools to submit all information/dataRequiring e-reporting unless specified

exemptions apply

Making data submitted to the agency in electronic form available to the public

21

Page 22: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

State Water Quality Certifications Under Section 401 of the Clean Water Act,

States have the right to add additional requirements to any U.S. Federal permit

Two “numeric” limits potentially applicable in permit term California – “no detectable living organisms”IMO D-2 equivalent (same as EPA and USCG)

Some state-specific monitoring requirements applicable for specific vessel types in certain states

See Part 6 of the VGP for State conditions

22

Page 23: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Small Vessel General Permit (sVGP)

23

Part 1 - Overview of Permit

Part 2 – Effluent Limitations and Related Requirements

Part 3 – Monitoring and Recordkeeping

Part 4 – Additional Requirements

Part 5 – State Specific Requirements

Part 6 – Definitions Part 7 – sVGP contacts Appendix A– Permit

Authorization and Record of Inspection Form

Temporary moratorium for incidental discharges from commercial fishing vessels and vessels less than 79 feet in length Moratorium originally until July 2010

(P.L. 110-299). Subsequently extended to December

19, 2013 (P.L. 111-215) and later December 19, 2014 (112-213)

In the event moratorium is not extended, EPA proposed the sVGP in November 2011 EPA intends to finalize that permit

later this year

Page 24: Overview of the Final 2013 VGP November 6, 2013. Presentation Overview  Background EPA and the Clean Water Act VGP basics and key dates  2008 VGP Overview

Questions? Contact information

Kathryn [email protected]

General VGP [email protected]/npdes/vessels

24