Upload
others
View
14
Download
0
Embed Size (px)
Citation preview
Hugo Dummett North ZoneHugo Dummett
South Zone
1300
m
1300
m
Heruga Deposit
Open PitOyut Deposit
Hugo North Lift 1
• Mining method: Block caving• Operations: The mine will work
365 days a year with two 12-hour shifts.
• Future underground infrastructure:
- 3 maintenance shops - 2 drilling machine shops - 2 fuel stations - 1 explosives storage - 2 crushers - 1 shotcrete station
- 10 km of conveyors
Hugo North Lift 1 (First stage)
Hugo North Lift 2 (Second Stage)
The crusher is as high as a 7-story building.
The deepest shaft is the equivalent of 12 Blue Sky Towers
in depth.
The total conveyor length (10km) is as
long as the road from the Chinggis Square to
Tolgoit station.
Hugo North Lift 1
1300
m
95,000t ore per day
Fractured ore
extraction level
ventilation level
haulage level
undercutting level
Oyu Tolgoi consists of a series of deposits containing copper, gold, and silver. The deposits stretch over 12 km, from the Hugo Dummett North Zone in the north through the adjacent Hugo Dummett South Zone, down to the Oyut Deposit, extending to the Heruga Deposit in the south. Over 80 per cent of Oyu Tolgoi’s potential lies underground.
Oyu Tolgoi Underground Project
At peak operations: - 50 drilling machines- 25 loaders- 10 haulage trucks- 290 other pieces of
equipment
Total length of tunnels over the life of Hugo North Lift 1 - 200 km (height
5.5m, width 5m)
The total area of the ore body to be covered in the first stage of underground
development is 17 times as big as the area of the Chinggis Square.
The first stage of underground development will take place at Hugo North Deposit Lift 1.Construction is expected to take approximately five to seven years.
SAFETY COMES FIRSTYear
2016Year2017
Year2018
Year2019
Year2020
Year2021
Year2022
At the peak of construction, the workforce at the underground is estimated to reach more than 3,000.
0500
100015002000250030003500
Construction workforce (excluding operations workforce)
- * Figures are inclusive of open pit operations and underground construction.- All numbers are estimations and may be updated.
Year2016
Year2017
Year2018
Year2019
Year2020
Year2021
Year2022
A total of US$2.2 billion USD is projected to be paid to the Government of Mongolia through taxes and other fees
during the first stage of underground development.
0
0.1
0.2
0.3
0.4
0.5
Estimated direct payment to Government of Mongolia*
All images are for
illustrative purposes only
and not to scale.