p. 1Mario Deile –

TOTEMino: Infrastructure Status and Schedule

Mario Deile29.08.2006

1. Zone

2. Gas system

3. Cabling

4. Cooling water

5. Counting-Room

6. Safety

7. Schedule

Page 2: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 2Mario Deile –

Zone

Page 3: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 3Mario Deile –

Zone

Page 4: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 4Mario Deile –

Setup (Side View)

•Cables trays ready

•1 ground line per tray (both connected to the 1 common ground of the area, no loops so far)

•power outlets on the 4 support pillars and on the fence

Page 5: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 5Mario Deile –

Setup (Top View)

Page 6: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 6Mario Deile –

Gas System

Green: done by central supply group

Blue: (to be) done by F. Hahn’s group

Red: to be done by TOTEM

T2 mixing + distribution rack ready;

INOX pipes delivered to cleaning service;

pipes to be installed in mid september.

The TIS wants it.

Page 7: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 7Mario Deile –

Cooling Water

Problems:

• collection of parts

is main difficulty;

• many components

not available from

store

• need someone with

experience in

water circuit design

• tried company,

but unreliable

Page 8: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 8Mario Deile –

Cables (GEMino)

TOTEM Cable needs (GEMino)

Cable description Type SCEM OD #cond # L status comment

LV power in counting room, so no power and control cables down.

LV power from supplyLV power 2x16CEM 04.08.82.160.2 18.2 2 5 30 foresaw one for powering optohybrid cards in

rack (by Pisa/Siena), check with them if they need other power supply

2x35CEM 04.08.82.350.2 2 5 30 OK replacementsense CAB.SIG.BL 16 x 2 x 0,20mm2 STP 04.21.44.160.2 15.6 32 1 30 sense pairs individually shielded, 1 cable for

all suppliesCAB.SIG.BL 18 x 2 x 0,25mm2 (ND36) 04.21.52.025.6 OK replacement

Control/triggerLV 2x16CEM 04.08.82.160.2 18.2 2 1 30

2x35CEM 04.08.82.350.2 2 1 30 OK replacement

DataOptical Ericsson (8x12) ~15 96 1 30 OK Note: need repeater stations !!

connector cost !

HVmulticore HV 04.31.52.100.6 15.3 56 1 30 OK get from Marco Oriunno (near H8)

RadmonND100 04.21.52.050.5 24 100 1 30 Radmon =14 wires/pot 1mA maxCAB.SIG.BL.24 x 2 x 0,50mm2 (NE48) 04.21.52.150.2 48 1 30 OK replacement

SparesCAB.SIG.BL.24 x 2 x 0,50mm2 (NE48) 04.21.52.150.2 48 1 30 OKMA72 72 1 30 OK use one pair for sense of optocouplers

Page 9: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 9Mario Deile –

Cables (RPino)TOTEM Cable needs (RP Totemino)

Cable description Type SCEM OD #cond # L status comment

LV power in counting room, so no power and control cables down.

LV power from supplyLV power 2x16CEM 04.08.82.160.2 18.2 2 6 30 up to 3 pots (analog & digital)

2x35CEM 04.08.82.350.2 2 6 30 OK replacementsense 2x16CAB.SIG.BL 04.21.44.160.2 15.6 32 1 30 sense pairs individually shielded,

1 cable for all suppliesCAB.SIG.BL 18 x 2 x 0,25mm2 (ND36) 04.21.52.025.6 1 30 OK replacement

Control/triggerLV 2x16CEM 04.08.82.160.2 18.2 2 3 30

2x35CEM 04.08.82.350.2 2 1 30 OK replacement

Trigger and dataOptical Ericsson (8x12) ~15 96 1 30 OK Note: need repeater stations !!

connector cost !Fast trigger cable 2x16CAB.SIG.BL 04.21.44.160.2 15.6 32 6 30 LATERLV repeater 2x35CEM 04.08.82.350.2 25.2 2 1 30 LATER for repeater and optocouplerLV optocoupler 2x35CEM 04.08.82.350.2 25.2 2 1 30 LATER straight to counting room

HVmulticore HV NE48 04.21.52.150.2 21 48 2 30 OK

RadmonND100 04.21.52.050.5 24 100 1 30 Radmon =14 wires/pot 1mA maxCAB.SIG.BL.24 x 2 x 0,50mm2 (NE48) 04.21.52.150.2 48 1 30 OK replacement

CoolingPJ5SJ 04.08.61.560.9 16 5 2 30 LATERNE48 04.21.52.150.2 21 48 1 30 LATER

control Ethernet 1 50 OK

Motor ControlMotors NH48 21 24 1 30 control rack in beam zone, Microswitches NE48 04.21.52.150.2 21 48 1 30 steered with serial cableResolvers NE48 04.21.52.150.2 21 48 1 30 ~ ~ ~LVDT NE48 04.21.52.150.2 21 48 1 30Pressure Gauges NE48 04.21.52.150.2 21 48 1 30Spare NE48 04.21.52.150.2 21 48 1 30remote control serial (RS232) 1 30 not yet

SparesNE48 04.21.52.150.2 1 30 OKMA72 1 30 OK use one pair for sense of optocouplers

Page 10: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 10Mario Deile –

Cables (CSCino)

TOTEM Cable needs (CSC Totemino)

Cable description Type SCEM OD #cond # L status comment

flat cables ??? 50 14 30 ???

Ethernet 1 50 not yet from netops

DataOptical Ericsson (8x12) ~15 96 1 30 OK

Lemo / BNC 10 30 OK

HVmulticore HV CABLE HT 56 X 0.16MM2 4,5KV 04.31.52.100.6 15.3 56 1 30 OK get from Marco Oriunno (near H8)

LV??? ??? ??? ??? ?? 30 ???

Note for all systems: connectors still undefined / unknown to me.

Page 11: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 11Mario Deile –

Trigger Scintillators

Available:

Genova stock at CERN:

• 10x10 cm2

• 1x1 cm2

• ~ 1x6 cm2

• 3x3 mm2

CERN group:

• 5x5 cm2

• 50x50 cm2 (4 for T1; to be assembled)

2 support stands;

HV and BNC cables: enough but old

Page 12: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 12Mario Deile –

Counting-Room

Network:

• Fast Ethernet functional

• Wireless network functional

Room needs cleaning up (some ATLAS equipment and junk left; we are free to either

keep it or throw it away).

Page 13: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 13Mario Deile –

Safety

• ISIEC form submitted.

• Had first talk with Gunnar Lindell & Claude Detraz:- problem with some old BNC cables;- gas pipes need pressure test;- ground lines need better electrical connections to cable trays;- for working on high detectors, special platforms needed;- in the zone, passageways have to be > 0.9 m wide ( constraints for gas rack positions);- counting-room needs pharmacy box;- need “initial safety discussion” (11. – 14.09.);- then safety inspection after installations

• Everybody needs to have attended the safety course (levels 1 – 3) within the last 5 years.

Page 14: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 14Mario Deile –

Schedule

Main user time 31.08. – 03.09. to be given away (to 3D Si?)

Crystal channel: no access! Hurts our installation activities. Have to use MD days.

Page 15: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 15Mario Deile –

Schedule (RP)

Page 16: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 16Mario Deile –

Schedule (T1)

Page 17: P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile 29.08.2006 1.Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety

p. 17Mario Deile –

Long-Term Schedule

Next year:

• Start of SPS physics in early May.

• End still unclear

• Start thinking about our plans!