Upload
neal-rodgers
View
217
Download
2
Tags:
Embed Size (px)
Citation preview
p. 1Mario Deile –
TOTEMino: Infrastructure Status and Schedule
Mario Deile29.08.2006
1. Zone
2. Gas system
3. Cabling
4. Cooling water
5. Counting-Room
6. Safety
7. Schedule
p. 2Mario Deile –
Zone
p. 3Mario Deile –
Zone
p. 4Mario Deile –
Setup (Side View)
•Cables trays ready
•1 ground line per tray (both connected to the 1 common ground of the area, no loops so far)
•power outlets on the 4 support pillars and on the fence
p. 5Mario Deile –
Setup (Top View)
p. 6Mario Deile –
Gas System
Green: done by central supply group
Blue: (to be) done by F. Hahn’s group
Red: to be done by TOTEM
T2 mixing + distribution rack ready;
INOX pipes delivered to cleaning service;
pipes to be installed in mid september.
The TIS wants it.
p. 7Mario Deile –
Cooling Water
Problems:
• collection of parts
is main difficulty;
• many components
not available from
store
• need someone with
experience in
water circuit design
• tried company,
but unreliable
p. 8Mario Deile –
Cables (GEMino)
TOTEM Cable needs (GEMino)
Cable description Type SCEM OD #cond # L status comment
LV power in counting room, so no power and control cables down.
LV power from supplyLV power 2x16CEM 04.08.82.160.2 18.2 2 5 30 foresaw one for powering optohybrid cards in
rack (by Pisa/Siena), check with them if they need other power supply
2x35CEM 04.08.82.350.2 2 5 30 OK replacementsense CAB.SIG.BL 16 x 2 x 0,20mm2 STP 04.21.44.160.2 15.6 32 1 30 sense pairs individually shielded, 1 cable for
all suppliesCAB.SIG.BL 18 x 2 x 0,25mm2 (ND36) 04.21.52.025.6 OK replacement
Control/triggerLV 2x16CEM 04.08.82.160.2 18.2 2 1 30
2x35CEM 04.08.82.350.2 2 1 30 OK replacement
DataOptical Ericsson (8x12) ~15 96 1 30 OK Note: need repeater stations !!
connector cost !
HVmulticore HV 04.31.52.100.6 15.3 56 1 30 OK get from Marco Oriunno (near H8)
RadmonND100 04.21.52.050.5 24 100 1 30 Radmon =14 wires/pot 1mA maxCAB.SIG.BL.24 x 2 x 0,50mm2 (NE48) 04.21.52.150.2 48 1 30 OK replacement
SparesCAB.SIG.BL.24 x 2 x 0,50mm2 (NE48) 04.21.52.150.2 48 1 30 OKMA72 72 1 30 OK use one pair for sense of optocouplers
p. 9Mario Deile –
Cables (RPino)TOTEM Cable needs (RP Totemino)
Cable description Type SCEM OD #cond # L status comment
LV power in counting room, so no power and control cables down.
LV power from supplyLV power 2x16CEM 04.08.82.160.2 18.2 2 6 30 up to 3 pots (analog & digital)
2x35CEM 04.08.82.350.2 2 6 30 OK replacementsense 2x16CAB.SIG.BL 04.21.44.160.2 15.6 32 1 30 sense pairs individually shielded,
1 cable for all suppliesCAB.SIG.BL 18 x 2 x 0,25mm2 (ND36) 04.21.52.025.6 1 30 OK replacement
Control/triggerLV 2x16CEM 04.08.82.160.2 18.2 2 3 30
2x35CEM 04.08.82.350.2 2 1 30 OK replacement
Trigger and dataOptical Ericsson (8x12) ~15 96 1 30 OK Note: need repeater stations !!
connector cost !Fast trigger cable 2x16CAB.SIG.BL 04.21.44.160.2 15.6 32 6 30 LATERLV repeater 2x35CEM 04.08.82.350.2 25.2 2 1 30 LATER for repeater and optocouplerLV optocoupler 2x35CEM 04.08.82.350.2 25.2 2 1 30 LATER straight to counting room
HVmulticore HV NE48 04.21.52.150.2 21 48 2 30 OK
RadmonND100 04.21.52.050.5 24 100 1 30 Radmon =14 wires/pot 1mA maxCAB.SIG.BL.24 x 2 x 0,50mm2 (NE48) 04.21.52.150.2 48 1 30 OK replacement
CoolingPJ5SJ 04.08.61.560.9 16 5 2 30 LATERNE48 04.21.52.150.2 21 48 1 30 LATER
control Ethernet 1 50 OK
Motor ControlMotors NH48 21 24 1 30 control rack in beam zone, Microswitches NE48 04.21.52.150.2 21 48 1 30 steered with serial cableResolvers NE48 04.21.52.150.2 21 48 1 30 ~ ~ ~LVDT NE48 04.21.52.150.2 21 48 1 30Pressure Gauges NE48 04.21.52.150.2 21 48 1 30Spare NE48 04.21.52.150.2 21 48 1 30remote control serial (RS232) 1 30 not yet
SparesNE48 04.21.52.150.2 1 30 OKMA72 1 30 OK use one pair for sense of optocouplers
p. 10Mario Deile –
Cables (CSCino)
TOTEM Cable needs (CSC Totemino)
Cable description Type SCEM OD #cond # L status comment
flat cables ??? 50 14 30 ???
Ethernet 1 50 not yet from netops
DataOptical Ericsson (8x12) ~15 96 1 30 OK
Lemo / BNC 10 30 OK
HVmulticore HV CABLE HT 56 X 0.16MM2 4,5KV 04.31.52.100.6 15.3 56 1 30 OK get from Marco Oriunno (near H8)
LV??? ??? ??? ??? ?? 30 ???
Note for all systems: connectors still undefined / unknown to me.
p. 11Mario Deile –
Trigger Scintillators
Available:
Genova stock at CERN:
• 10x10 cm2
• 1x1 cm2
• ~ 1x6 cm2
• 3x3 mm2
CERN group:
• 5x5 cm2
• 50x50 cm2 (4 for T1; to be assembled)
2 support stands;
HV and BNC cables: enough but old
p. 12Mario Deile –
Counting-Room
Network:
• Fast Ethernet functional
• Wireless network functional
Room needs cleaning up (some ATLAS equipment and junk left; we are free to either
keep it or throw it away).
p. 13Mario Deile –
Safety
• ISIEC form submitted.
• Had first talk with Gunnar Lindell & Claude Detraz:- problem with some old BNC cables;- gas pipes need pressure test;- ground lines need better electrical connections to cable trays;- for working on high detectors, special platforms needed;- in the zone, passageways have to be > 0.9 m wide ( constraints for gas rack positions);- counting-room needs pharmacy box;- need “initial safety discussion” (11. – 14.09.);- then safety inspection after installations
• Everybody needs to have attended the safety course (levels 1 – 3) within the last 5 years.
p. 14Mario Deile –
Schedule
Main user time 31.08. – 03.09. to be given away (to 3D Si?)
Crystal channel: no access! Hurts our installation activities. Have to use MD days.
p. 15Mario Deile –
Schedule (RP)
p. 16Mario Deile –
Schedule (T1)
p. 17Mario Deile –
Long-Term Schedule
Next year:
• Start of SPS physics in early May.
• End still unclear
• Start thinking about our plans!