P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Embed Size (px)

Citation preview

Page 1: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

P-value method

One Proportion

Page 2: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The problemThe mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on

what used to be the city’s one and only park.

The mayor’s main opponent in the upcoming election claims that 90% of the town is angry over the mayor’s decision. In a survey of 50 residents, 44 responded that they were angry.

Evaluate the claim using the P-value method with α=.01.

Page 3: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Option to work alone and check answerIf you want to try this problem on your own and just check your answer, click on the teacher to the right. Otherwise, click away from her and we’ll work through this together.

Page 4: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Set-up

This test is about one proportion, the proportion of people in the town who are angry about the mayor’s decision.

Here’s what we know.

Populationp = ?

This is what the hypotheses will be about!

Page 5: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Set-up: sample dataSet-upThis test is about one proportion, the proportion of people in the town who are angry about the mayor’s decision.

Here’s what we know.

Populationp = ?

Samplen = 50

Page 6: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step 1:State the hypotheses and identify the claim.

We are asked to evaluate the claim that the 90% of the town’s residents are angry at the mayor. That is:

proportion who are angry = .9That’s p!

Remember to convert 90% to a decimal!

Page 7: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The Null Hypothesisp = .9

I declare this to be the Null Hypothesis! It has an equals sign in it!

Page 8: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The Alternate HypothesisStep 1𝐻0 : 𝑝=.9 (𝑐𝑙𝑎𝑖𝑚)

Whenever the Null Hypothesis is the claim, we get the Alternate Hypothesis by simply negating it.

Page 9: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step (*)

Draw the picture and mark off the observed value.

Not so fast!

Page 10: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The need to check for normalityDo we know we have a normal distribution?

With proportions, we have to investigate!

Page 11: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Verifying normalityRemember: n = 50

p = .9

Be sure to use the hypothesized value of p, not q = 1 - p

= 1 - .9 =.1

To check for normality:

np = (50)(.9) = 45 nq = (50)(.1) = 50

Page 12: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Drawing the picture: top and middle levelsStep (*) • Since we have a normal distribution, draw the picture

Top level: Area

Middle Level: Standard Units (z)

We always use z-values when working with proportions.

Page 13: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Drawing the picture: marking the center in standard unitsStep (*) • Since we have a normal

distribution, draw the picture

Top level: Area

Middle Level: Standard Units (z) 0

The center is always 0 in standard units.

Page 14: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Drawing the picture: adding the bottom levelStep (*) • Since we have a normal distribution, draw the picture

Top level: Area

Middle Level: Standard Units (z) 0

Bottom Level: Actual valuesThere are no units for proportions.

Page 15: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Drawing the picture: marking the center in actual values

Step (*) • Since we have a normal distribution, draw the picture

Top level: Area

Middle Level: Standard Units (z) 0

Bottom Level: Actual values .9

The number from the Null Hypothesis always goes in the center of the bottom level; that’s because we’re drawing the picture as if the Null is true.

Page 16: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Reminder to work bottom-upThen remember:

The -value MethodP

is ottom-upb

Page 17: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Adding the observed value to the picture

Step (*)

Standard Units (z) 0

Actual values .9

• Once we have the normal distribution, start at the Bottom level and mark off the observed value, .88.

Bottom level .88

.88 < .9 so it goes on the left side

Page 18: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Drawing in the tails

Step (*)

Standard Units (z) 0

Actual values .9.88

• Once we have the normal distribution, start at the Bottom level and mark off the observed value, .88.

Draw in the tails associated with the observed value. .88 serves as the boundary for the left tail. Since the Alternate has a sign in it, this is a two-tailed test. The right tail should be exactly the same size as the left.

Page 19: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step (2): Move up to the middle level. Convert the observed value to standard units and mark this off.

Standard Units (z) 0

Actual values .9.88

Middle level:

The observed value converted to standard units is called the test value. It goes here.

Page 20: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Calculating the test valuez =

This is the formula for the standard error in the distribution of sample proportions.

Page 21: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Calculating the test value, slide 2z =

¿.88− .9

√ ( .9 )(.1)50

= .471…

≈− .47

Page 22: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Adding the test value to the pictureLet’s add it to our picture!

Standard Units (z) 0

Actual values .9.88

Middle level: --.43-.47 .47

Note that the boundary of the right tail is .47; marking this off is optional.

Page 23: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step 3Step 3: Move up to the top level and find the area in the tails. The total area is our P-value.

Standard Units (z) 0

Actual values .9.88

-.47 .47

Top level: Area

Page 24: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Choice: Table E or the calculatorWe have two options for finding the P-value: we can use Table E or the calculator.

Table ECalculator

Click on the option you prefer.

Page 25: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Table EWe can use the left side of Table E to find the area in the left tail.

Let’s zoom in!

Page 26: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Finding the area in the left tail

Note: the picture above omits a number of rows from Table E so that the remaining rows can be shown on a larger scale.

.3192

Page 27: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Adding the area to the picture• The area in the left tail is .3192.• This means the area in the right tail is also .3192.• P = total area in both tails = 2(.3192) = .6384

Standard Units (z) 0

Actual values .9.88

-.47 .47

Top level: Area

.3192 .3192

Page 28: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step 4: Decide whether or not to reject

I say we reject the sucker!

Lighten up!Let’s not reject it too hastily.

You know I hate making decisions!

Page 29: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Guidelines for making the decision• Compare P to α.• P = total area in two tails

= probability of getting .88 (or a value further from .9) if the Null is true

• α= maximum allowable probability of making a Type I error (rejecting the Null if it is true)

Page 30: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Comparing P to αP α

.6384 .01>

• The probability we would get the result we did (if the Null is true) is bigger than α.

Page 31: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The decisionDon’t reject the Null.

Told ya!

Page 32: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step 5: Answer the question.• Talk about the claim.• Since the claim is the Null

Hypothesis, continue using the language of “rejection”.

• We did not reject the Null, so we do not reject the claim.There is not enough evidence to reject the claim that 90% of the population is angry at the mayor.

Page 33: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Request for a review

Could we see that one more time?

Page 34: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Summary

Standard units (z) 0

Actual value .9

Each click will give you one step. Step (*) is broken into two clicks.

Step 1:𝐻0 :𝜇=.9(𝑐𝑙𝑎𝑖𝑚)𝐻1 :𝜇≠ .9

Step (*).88

Step 2-.47 .47

Step 3.3192 .3192

Step 4: Don’t reject the Null.

Step 5: There is not enough evidence to reject the claim.

Page 35: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

CelebrationAnd there was much rejoicing.

Page 36: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Exit the slideshowPress the escape key to exit the slide show.

If you keep clicking through the presentation, you’ll view the slides where we calculate the P-value using the calculator instead of Table E.

Page 37: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Finding P with the calculatorWith the calculator, there’s no need to round the critical value, so be sure you’ve still got the calculated critical value displayed on your screen.

Then hit the “shift” key followed by the “3” key.

Page 38: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The calculator menu

You’ll see this menu.

LEFTMIDDLE

RIGHT

Page 39: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Selecting from the calculator menu

Since our test value was negative, it is the boundary of the left tail. So type “1” to get the area to its left, which will be the area in the left tail.

LEFT

Page 40: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Entering the test value into the calculatorYou’ll see

P(

at the top of your screen. If you remembered not to delete the critical value, you’ll see it on the screen just below this. Hit the “Ans” key to enter this as the z-value.

You should get .31868.

Page 41: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Adding the area we got from the calculator to the picture• The area in the left tail is .31868.

• This means the area in the right tail is also .31868.• P = total area in both tails = 2(.31868) = .63736

Standard Units (z) 0

Actual values .9.88

-.47… .47…

Top level: Area

.31868 .31868

Page 42: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step 4: Decide whether or not to reject (after getting P using the calculator)

Step 4: Decide whether or not to reject

I say we reject the sucker!

Lighten up!Let’s not reject it too hastily.

You know I hate making decisions!

Page 43: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Guidelines for making the decision(after using the calculator to get P-value)

• Compare P to α.• P = total area in two tails

= probability of getting .88 (or a value further from .9) if the Null is true

• α= maximum allowable probability of making a Type I error (rejecting the Null if it is true)

Page 44: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Comparing P to α (using the P-value from the calculator)

P α

.63736 .01>

• The probability we would get the result we did (if the Null is true) is bigger than α.

Page 45: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

The decision (after using the calculator to get P)

Don’t reject the Null.

Told ya!

Page 46: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Step 5: Answer the question. (after using the calculator to get P)

Step 5: Answer the question.

• Talk about the claim.• Since the claim is the Null

Hypothesis, continue using the language of “rejection”.

• We did not reject the Null, so we do not reject the claim.There is not enough evidence to reject the claim that 90% of the population is angry at the mayor.

Page 47: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Request for a review (using calcultor to get P-value)

Could we see that one more time?

Page 48: P-value method One Proportion. The mayor of Pleasantville has just signed a contract allowing a biohazards company to build a waste disposal site on what

Summary (using the P-value we get from the calculator)

Standard units (z) 0

Actual value .9

Each click will give you one step. Step (*) is broken into two clicks.

Step 1:𝐻0 :𝜇=.9(𝑐𝑙𝑎𝑖𝑚)𝐻1 :𝜇≠ .9

Step (*).88

Step 2-.47… .47…

Step 3.31868 .31868

Step 4: Don’t reject the Null.

Step 5: There is not enough evidence to reject the claim.