15
Pacific Southwest Blackout on September 8, 2011 at 15:27 IEEE PES General Meeting, Vancouver, Canada, July 24 th , 2013 Dr. Milorad Papic [email protected] 1 PES GM 2013, Vancouver, Canada July 24, 2013

Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

Pacific Southwest Blackout on September 8, 2011 at 15:27

IEEE PES General Meeting, Vancouver, Canada, July 24th, 2013

Dr. Milorad Papic [email protected]

1

PES GM 2013, Vancouver, Canada July 24, 2013

Page 2: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

Outline

1. Generic Scenario for a Blackout Event

2. Impact of September 8th Blacout

3. History of WECC Disturbances

4. Lessons Learned

2

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

Page 3: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

1. Generic Scenario of a Cascading Blackout

3

1 2 6

3

5 4

0 0 – System State Before

Blackout

1 – Contingency Conditions

2 – Triggering Events

3 – Power Flow Surges, Voltage

problems, Overloads

4 – Protection System Trips

Lines, Transformers, Generators

5 – System Separation, Instability

and Voltage Collapse

6 - Blackout System State

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

Page 4: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

1. Cascading Event – Various Definitions A cascading failure is a process, in which an initiating event/failure increases the stress of other system components, resulting in their overloading above the limits for which they were designed.

NERC definition: The uncontrolled successive loss of system elements triggered by an incident at any location. Cascading results in widespread electric service interruption that cannot be restrained from sequentially spreading beyond an area predetermined by studies.

A cascading outage is defined as the event in which an abnormal cascading processes develop in power systems, when every disturbance triggers a next one, and so on, result in blackouts, i.e. mass-scale tripping of generating sources and disruption of electricity supply over large areas.

CFTF definition: Cascading Failure is a Sequence of Dependent Failures of Individual Components that successively Weakness the Power System

4

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

Page 5: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

1. Pre-Event State (state-0)

Normal (Pre-Event) Operating State In this state the operating parameters of BES lie within acceptable limits. However

noticeable deviations of parameters were observed during the blackouts

Extreme conditions (summer & winter peak)

Weakened topology (important equipment out of service)

Natural Disasters and Extreme weather

Does the system operate reliable in this state? The term “reliable operation” means operating the elements of the bulk-power system within equipment and electric system thermal, voltage and stability limits so that instability, uncontrolled separation, or cascading failures of such system will not occur as a result of a sudden disturbance or unanticipated failure of system elements.

5

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

Page 6: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

1. Triggering Events (state-3)

Various N-1 (overload, protection failure, short-circuit..) Failure of Equipment

Malfunctioning of protective devices

N-k simultaneous outages

Other Causes Extreme weather, Lighting

Human Error

Lack of situational awareness

Operational planning error

Control system error

6

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

Page 7: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

1. Cascading Event - Progression The outage of the overloaded components can progress either

slowly (steady-state progression), or quickly (transient progression).

The transient progression usually involves voltage instability, frequency instability and small signal instability (power oscillations) and its time scale is between seconds and several tens of seconds. The examples are blackouts in US-West on July 2, 1996 and the most recent one in India on August 31, 2012.

The slow progression involves line tripping between fairly large time intervals, in order of minutes. In this case the line tripping occurs either after exceeding a short-term emergency line loading limit or the line sags and short-circuit between the line and trees takes place. The examples of the slow progressing cascading is the blackout in France on December 19, 1978, initial phase of the NE US blackout on August 14th, 2003 and blackout in Italy on September 28, 2003.

IEEE PES General Meeting, Vancouver,

Canada, July 24, 2013

7

Page 8: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

2. Impact of September 8, 2011 Blackout in AZ-CA Region

About 2.7 million people affected.

7.89 GW of load interrupted

6 -12 hours to fully restore all loads.

Average load interruption time: 8.1 hours.

WECC peak load: ~130 GW.

Affected area peak load:~17 GW.

PES GM 2013, Vancouver, Canada July 24, 2013

8

Affected Area

Page 9: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

9

2. Affected Area Electric System

Path 49 (EOR)

Path 46 (WOR) Path 43

Path 45

Path 44 WALC

APS

IID

CFE

SDGE

Serrano Devers

PV

North Gila

Imperial V Miguel

HS

SCE Path 42

PES GM 2013, Vancouver, Canada July 24, 2013

P2

P3

P4

P5 P6

P7

P6

Page 10: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

2. Pre-Disturbance Conditions on Paths in affected area

Path in Affected Area Path rating Path Flow & ( %)

Path 44 (South of S.O.) 2,200 MW 1,302 MW (78%)

Path 45 (SDGE-CFE) 800 MW S>N, 408 MW N>S

241 MW (60%)

230 kV S Line (part of Path 46)

239 MW 90 MW (38%)

500 kV H-NG Line (part of path 49)

1,800 MW 1,397 MW (78%)

SDGE Import SOL 2,850 MW 2,539 MW (89%)

Path 42 (IID-SCE) 600 MW E>W -40 MW

10

PES GM 2013, Vancouver, Canada July 24, 2013

Page 11: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

2. Main Contributing Factors to SW Outage₁

Impact of sub-100 kV facilities

Not studying/coordinating effects of Protection Systems and RAS during contingency

Not providing effective operator tools and instructions for reclosing lines with large phase angle differences

Failure to recognize IROLs

PES GM 2013, Vancouver, Canada July 24, 2013

11

₁FERC/NERC Report

Page 12: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

3. WECC Disturbances 2002-2012

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

12

48%

12%

3%

2%

5%

1%

8%

4%

1%

1% 1%

14%

Relative Contribution to Risk by Cause (%)

Vandalism/Physical Attack

Severe Weather

Equipment Failure

Fire

High Wind

High Temperature

Separation/Islanding

Fuel Deficiency

Loss of Transmission

Cyber Attack

No Load Lost 42%

0-100 MW 10%

100-300 MW 23%

300-1000 MW 21%

1000-2000 MW 1%

2000-5000 MW 1%

> 5000 MW 1%

Uknown 1%

Relative Contribution to Risk by Size of Interrupted Load (%)

Page 13: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

3. WECC Disturbances 2002-2012

IEEE PES General Meeting, Vancouver, Canada, July 24, 2013

13

0

10

20

30

40

50

60

70

9 9 17

12

23 25 26

19

32

69

49

Dis

turb

nav

ces

Disturbnaces Reported by WECC TOs 2002-2012

0

0.5

1

1.5

2

2.5

3 Severity Risk Index

Page 14: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

4. Lessons Learned What did come from Blackouts?

• 1965 – Marked the beginning of fundamental change in the electric power industry. Regional reliability organizations and the NERC were formed to monitor and promote electric system reliability. The impetus for the EMS advanced applications came from this blackout.

• 1996 – Disturbance reports propose 32 recommendations for August 10 outage and 24 recommendations for July 2 outage. As a result of these recommendations WSCC has developed:

– new Voltage Stability Criteria, Undervoltage load shedding strategy, and reactive power reserve monitoring methodology.

– Seasonal Studies

– The impetus for the mandatory membership in reliability councils and enforced compliance with reliability criteria came from these two blackouts.

• 2003 – Task Force Final Report proposes 14 Recommendations relating to

– Strategic Initiatives (Strengthen the NERC Compliance Enforcement Program,…)

– Technical Initiatives (Improve Operator and Reliability Training…)

– Actions to Improve Reliability (Voltage and Reactive Management,…)

• 2011 – The Final Joint NERC/FERC Report propose 27 Recommendations relating to

– situational awareness; next-day planning; seasonal planning; near- and long-term planning;

– impact of sub-100-kV facilities; Interconnection Reliability Operating Limits (IROL).

14

PES GM 2013, Vancouver, Canada July 24, 2013

Page 15: Pacific Southwest Blackout on September 8, 2011 at 15:27 · 2013. 8. 8. · The slow progression involves line tripping between fairly large ... The examples of the slow progressing

Questions????

?

Note/Disclaimer Presentation represents the

views of the presenter

And does not necessarily

represent the views

Of the Idaho Power Co.

15

PES GM 2013, Vancouver, Canada July 24, 2013