Upload
vandieu
View
215
Download
2
Embed Size (px)
Citation preview
Page 1 of 25
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No.: RES17185
RESTRUCTURING PAPER
ON A
PROPOSED RESTRUCTURING
OF THE
WEST AFRICA REGIONAL FISHERIES PROGRAM APL BI
IDA GRANT NO. H-653-GW AND GEF TRUST FUND GRANT NO. TF099597-GW
APPROVED ON MARCH 31, 2011 AND MAY 2, 2011 RESPECTIVELY
TO THE
REPUBLIC OF GUINEA BISSAU
June 7, 2016
Global Practice Environment and Natural Resource Management (GENDR)
Africa Region
This document has a restricted distribution and may be used by recipients only in the performance of their
official duties. Its contents may not otherwise be disclosed without World Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Page 2 of 25
ABBREVIATIONS AND ACRONYMS
AIS Automatic Identification System
CIPA Applied Fisheries Research Center (Centro de Investigação Pesqueira
Aplicada)
CSRP Sub-Regional Fisheries Commission (Commission Sous régional des Pêches)
EA Environmental Assessment
EU European Union
FISCAP National Commission for Fisheries Surveillance (Servico Nacional de
Fiscalizacao e Controlo das Actividades de Pesca)
FM Financial Management
GEF Global Environment Facility
IDA International Development Association
IFR Interim Unaudited Financial Report
IP Implementation Progress
M&E Monitoring and Evaluation
MCS Monitoring, Control and Surveillance
MTR Mid-Term Review
PAD Project Appraisal Document
PDO Project Development Objective
PPO Policy and Planning Office
SDR
SOP
Special Drawing Right
Series of Projects
TF Trust Fund
TURF Territorial Use Rights Fisheries
VMS Vessel Monitoring System
WARFP West Africa Regional Fisheries Program
Regional Vice President: Makhtar Diop
Country Director: Rachid Benmessaoud
Senior Global Practice Director: Paula Caballero
Practice Manager: Magda Lovei
Task Team Leaders: Berengere Prince, Asberr Natoumbi Mendy
Page 3 of 25
DATA SHEET
Republic of Guinea Bissau
West Africa Regional Fisheries Program APL B1 (P119380 / P122182)
AFRICA
Environment and Natural Resource Management (GENDR)
Report No: RES17185
Basic Information
Project ID: P119380 Lending Instrument: Adaptable Program Loan
Regional Vice President: Makhtar Diop Original EA Category: Partial Assessment (B)
Country Director: Rachid Benmessaoud Current EA Category: Partial Assessment (B)
Senior Global Practice
Director: Paula Caballero Original Approval Date: 31-Mar-2011
Practice
Manager/Manager: Magda Lovei Current Closing Date: 30-Jun-2016
Team Leader(s): Berengere P. C. Prince,
Asberr Natoumbi Mendy GEF Focal Area: International waters
Borrower: Secretary of State for Fisheries
Responsible
Agency:
Restructuring Type
Form Type: Full Restructuring Paper Decision Authority: CD Decision
Restructuring Level: Level 2
Financing ( as of 26-May-2016 )
Key Dates
Project Ln/Cr/TF Status Approval
Date Signing Date
Effectiveness
Date
Original
Closing Date
Revised
Closing Date
P119380 IDA-H6530 Effective 31-Mar-2011 02-May-2011 30-Sep-2011 30-Jun-2016 30-Jun-2016
P122182 TF-99597 Effective 02-May-2011 02-May-2011 30-Sep-2011 30-Jun-2016 30-Jun-2016
Disbursements (in Millions)
Project Ln/Cr/TF Status Currency Original Revised Cancelle
d
Disburse
d
Undisbur
sed
%
Disburse
d
Page 4 of 25
P119380 IDA-H6530 Effective USD 6.00 6.00 0.00 3.28 2.28 55
P122182 TF-99597 Effective USD 2.00 2.00 0.00 1.13 0.87 56
Policy Waivers
Does the project depart from the CAS/CPF in content or in other significant
respects? Yes [ ] No [ X ]
Does the project require any policy waiver(s)? Yes [ ] No [ X ]
A. Summary of Proposed Changes
This restructuring paper proposes a Level 2 Restructuring of the West Africa Regional Fisheries Program
(WARFP) in Guinea Bissau (WARFP SOP B1) at the request of the Government of Guinea Bissau, which
was officially communicated to the Bank by the Director General of Planning within the Ministry of
Economy and Finance on November 4, 2015. The request rests on the findings of the mission of October
2014 and further information/ observations garnered during the last World Bank implementation support
missions in July 2015 and April 2016.
The proposed changes are expected to enhance the government’s ability to achieve the original Project
Development Objective (PDO); enhance the implementing agency’s ability to measure the progress toward
achieving the original PDO; and remove complexities in project implementation. In specific, it is proposed
to:
1. Extend the project Closing Date by 12 months (from June 30, 2016 to June 30, 2017) to make up
for a 12 months suspension during the 2012 military takeover and the temporary absence of a
project coordinator in 2013 due to a decision taken within the responsible ministry.
2. Revise several activities, namely (i) drop the leasing and purchasing of a surveillance vessel under
Component 2 and use the proceeds to finance other project activities. Specifically, the removal of
the legal covenant on the purchasing of the surveillance vessel and the extension of the due date of
a covenant for a social impact assessment for the project to account for delays in implementing
this activity; (ii) instead of preparation of new fisheries management plans for select fisheries
species, the activity will be updating of existing ones and their subsequent adoption; (the existence
of management plans for these fisheries was not accounted for during project approval); and (iii)
removal of European Union (EU) certification requirements from the list of activities under
Component 3 due to the fact that accreditation for certification of fisheries products exports to the
EU is a process which neither the project nor the Government has control of. Corresponding
changes to components’ costs are also proposed.
3. Redefine several of the PDO Level and Intermediate Results Indicators and formulate new ones in
order to:
a) Ensure correct evaluation of project performance according to the revised activities
b) Remove long term program-level indicators that are inappropriate for the project and add new
project-specific indicators, including for project coordination and Monitoring and Evaluation
(M&E) (Component 4)
c) Correct some of the baseline and reference data originally stated
4. Reallocate IDA proceeds between expenditure categories to reflect the removal of surveillance
vessel leasing and purchasing allocations and redistribute the proceeds according to a new work
plan for the remaining duration of the project.
Page 5 of 25
5. Revise the disbursement schedule to reflect the extension of the closing date by one year and the
disbursement delays encountered by the project as a result of the implementation delays.
6. Make additional minor changes to the financing agreement to ensure consistency of activities’
numbering, definitions and costing within the financing agreement and consistency with the
Project Appraisal Document (PAD).
The proposed restructuring will not revise the PDO, will not trigger new safeguard policies and will not
change the EA Category (B-Partial Assessment). The project safeguard documents will continue to be used
for the extended project duration.
Change in Implementing Agency Yes [ ] No [ X ]
Change in Project's Development Objectives Yes [ ] No [ X ]
Change in Project's Global Environmental Objectives Yes [ ] No [ X ]
Change in Results Framework Yes [ X ] No [ ]
Change in Safeguard Policies Triggered Yes [ ] No [ X ]
Change of EA category Yes [ ] No [ X ]
Other Changes to Safeguards Yes [ ] No [ X ]
Change in Legal Covenants Yes [ X ] No [ ]
Change in Loan Closing Date(s) Yes [ X ] No [ ]
Cancellations Proposed Yes [ ] No [ X ]
Change to Financing Plan Yes [ ] No [ X ]
Change in Disbursement Arrangements Yes [ ] No [ X ]
Reallocation between Disbursement Categories Yes [ X ] No [ ]
Change in Disbursement Estimates Yes [ X ] No [ ]
Change to Components and Cost Yes [ X ] No [ ]
Change in Institutional Arrangements Yes [ ] No [ X ]
Change in Financial Management Yes [ ] No [ X ]
Change in Procurement Yes [ ] No [ X ]
Change in Implementation Schedule Yes [ ] No [ X ]
Other Change(s) Yes [ X ] No [ ]
Appraisal Summary Change in Economic and Financial Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Technical Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Social Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Environmental Analysis Yes [ ] No [ X ]
Appraisal Summary Change in Risk Assessment Yes [ ] No [ X ]
B. Project Status
The Project Development Objective is to strengthen the country’s capacity to govern and manage targeted
Page 6 of 25
fisheries, reduce illegal fishing and increase local value added to fish products. The project was approved
by the World Bank Board of Directors on March 7, 2011 for a total of US$8M (US$6M IDA grant and
US$2M Global Environment Facility (GEF) grant) with a closing date of June 30, 2016. The design of the
project follows the overall WARFP design, looking to build the capacity of the Government and
stakeholders to develop and implement policies, improve the country’s fisheries Monitoring, Control and
Surveillance (MCS) systems, and increase the share of the value-added captured in the region.
The PDO and Implementation Progress (IP) are rated Moderately Satisfactory and the Global Environment
Objective (GEO) is rated Satisfactory, reflecting a 12 months delay which the project has been
experiencing as a result of the year-long suspension period in 2012 and the temporary absence of a project
coordinator in 2013 following a decision within the responsible ministry. Despite these delays, the project
has made significant progress toward achieving the PDO. With regards to the governance and fisheries
management objective the project has concluded institutional and legal framework review and the drafting
of the necessary institutional and legal instruments, incorporating international good governance and
sustainable fisheries management best practices, and they are being adopted by the Government. Illegal
fishing has been reduced thanks to project-funded surveillance support to the government, resulting in a
reduction of serious infractions from 25 to 6 percent and from 25 to 3 percent for small scale fishing boats
and industrial vessels, respectively. Recent evaluations indicate that the country has been regaining control
of its national waters and has also increased its revenues from the arrest of illegal fishing activities using
project-funded modern surveillance and communication equipment installed at the command and control
center at the Fisheries Port in Bissau and other areas along the coast. Increased local value has been
promoted by supporting the national Applied Fisheries Research Center (Centro de Investigação Pesqueira
Aplicada, CIPA) with laboratory equipment, materials and technical capacity for quality control and
inspection of fish and fishery products intended for export.
The following describes the main results and progresses under each component, and the actions that are
still to be completed. A summary of results achieved given below reflects both P119380 and P122182 as
they are fully blended.
Component 1: Good Governance and Sustainable Management of Fisheries
This component aims to build the capacity of the Government and stakeholders to develop and implement
adequate fisheries policies by strengthening the policy and regulatory framework, assessing the economic
and biological status of key fish resources, enhancing transparency and taking initial steps to scale up
fisheries co-management (by communities and the Government). The key achievements are:
The national fisheries strategic plan was revised. The Government officially adopted it in
December 2014.
A review of the country’s policy and legal frameworks for the sector. The reports and proposed
legal instruments are being finalized.
Assessment of key demersal fish stocks as a baseline to adjusting the fishing capacity. The final
report is available.
A review of the regulatory status of co-management mechanisms and the needed political
framework for Territorial Use Rights Fisheries (TURF)
Workshops for the establishment of regional and national dashboards for key environmental,
social and economic fisheries statistics, and hiring of a consultant to establish the dashboards
Remaining/ongoing actions are:
Provision of support for the implementation of the legal reforms
Page 7 of 25
Assessment of key fisheries stocks
Updating of fisheries management plans for the target fisheries
Setting up a statistical data collection and analysis system (dashboard), based on sampling,
recruitment and training of personnel
Production of fisheries statistics
Finalization of national and regional dashboards
Component 2: Reduction of Illegal Fishing
The objective of this component is to reduce the widespread illegal fishing activities that threaten the
sustainability of marine fish resources and the wealth they generate by improving national MCS capacities
and regional MCS collaboration. The key achievements are:
Enhancement of the human and technical capacity of the national surveillance agency’s (National
Commission for Fisheries Surveillance (Servico Nacional de Fiscalizacao e Controlo das
Actividades de Pesca, FISCAP) to monitor, control and carry out surveillance operations
(ongoing).
Rehabilitation of the Bissau Fisheries Monitoring Center
Acquisition of equipment and materials for the Bissau Fisheries Monitoring Center
Surveillance operations, resulting in inspections, confiscation of fish products, arrests and paid
penalties to the Treasury.
Remaining actions are:
Investments in the repair and operationalization of existing patrol boats
Acquisition of additional equipment and materials for the Bissau Fisheries Monitoring Center
Rehabilitation of coastal monitoring stations (new activity)
Preparation of a strategic plan for sustainable MCS operations and adequate maintenance and
servicing of surveillance equipment.
Component 3: Increasing the Contribution of the Marine Fish Resources to the Local Economies
The objective of this component is to increase the country’s benefits from its marine fish resources by
establishing a public inspection and quality control entity, and by training local fishers to improve product
handling, processing/marketing transport and sanitary measures, maintenance of landing site equipment
and knowledge concerning access to local micro-finance. The key achievements are:
Provision of laboratory equipment, materials and training to CIPA for quality control and
inspection of fish and fishery products intended for export
Remaining actions are:
Establishment of a public inspection and quality control entity
Preparation and approval of a plan for the operation and maintenance of laboratory equipment and
skills
Training of local fishers, fish traders and processors
Component 4: Coordination, Monitoring and Evaluation and Program Management
This component supports the coordination of the project by a Policy and Planning Office (PPO) embedded
Page 8 of 25
within the Implementing Agency and staffed by hired specialists. The component also finances
regional/program level coordination/technical support and M&E activities by the Sub-regional Fisheries
Commission (Commission Sous-Régional des Pêches, CSRP). The PPO is staffed as planned and submits
progress reports, financial reports and audits in a timely manner and with overall good quality with the
support of the CSRP. Financial Management (FM) and procurement are rated MS due to previously
reported issues of segregation of FM duties, deficiencies in record keeping, publishing of awarded
contracts and bidding procedures. Safeguard compliance is rated MS because of delays in the carrying out
of a social impact assessment – see above implementation delays explanation in addition to delays in the
hiring of the consultant (procurement procedural delays and consultants’ health issues). The restructuring
includes a new deadline for this activity (June 27, 2016 – see below).
The disbursement rates are 51.27% of the IDA grant and 49.26% of the GEF grant as of February 29,
2016. They reflect implementation and procurement delays and are expected to pick up and reach full
disbursement by the revised closing date. A work plan and budget for the proposed extended
implementation period and the remaining funding have been developed by the Government with support
from the Bank task team.
C. Proposed Changes
Development Objectives/Results
Project Development Objectives
Original PDO
To strengthen the country's capacity to govern and manage targeted fisheries, reduce illegal fishing and
increase local value added to fish products.
Change in Project's Development Objectives
Global Environmental Objectives
Original GEO
Same as PDO: to strengthen the country's capacity to govern and manage targeted fisheries, reduce illegal
fishing and increase local value added to fish products.
Change in Project's Global Environmental Objectives
N/A
Change in Results Framework
Explanation:
Discussions with the Government during the MTR mission resulted in the observation that two of the three
PDO-Level Indicators were in fact relevant to the overall goal of the program rather than to the PDO of
this project, which is considered only a first step in a multi-phased program. In addition, the refocusing and
removal of several activities needed to be reflected in revised indicators, and some baseline and reference
data quoted during project approval needed to be corrected. Therefore, indicators should be revised at both
the PDO level and at the Intermediate Results level as follows:
PDO-Level Indicators: Replacement of PDO Indicator 1 on fisheries health and PDO Indicator 2 on
increased economic benefits with a governance indicator, a surveillance indicator (formerly an
Intermediate Results Indicator with a more limited definition of surveillance measures) and a local value
indicator, and maintenance of the Core Indicator on number of beneficiaries, of which female. The two
original PDO Indicators were based on the existence of a management system that is capable of controlling
Page 9 of 25
and managing access to the country’s marine resources, which was not the case when the project was
approved. By making these changes, the new PDO Indicators is better aligned with project PDO.
Intermediate Results Indicators: Revision of three indicators for better alignment with the revised project
activities, transfer of one indicator to the PDO level as indicated above, and addition of three new
indicators that measure project management performance and assess fisheries performance evaluation by
the government. Four of the original indicators and their targets are maintained
For detailed information on proposed modifications to the Results Framework, see Annex 1.
Change in Legal Covenants
Explanation:
It is proposed to mark for deletion the disbursement condition specified in the IDA financing agreement,
schedule 2, Section IV, paragraph B.1(b): “No disbursements will be made for the purchase of fisheries
patrol vessels, until and unless the Association shall have been satisfied, based on an exchange of views
with the Recipient, with the cost-efficiency, technical specifications and fiscal sustainability of the
proposed expenditures.” This change will reflect the dropping of the activity on the purchase of fisheries
patrol vessel as explained below.
It is also proposed to defer activity (i) of the covenant in Schedule 2, Section I, Paragraph E.4 of the IDA
financing agreement and Schedule, Section I, Paragraph D.4 of the GEF financing agreement: “not later
than September 30, 2012, undertake a social assessment of the impact of the Project on the management of
its fisheries resources upon terms of reference satisfactory to the Association” to June 27, 2016. This
postponement will make up for delays in carrying out this activity, as explained above. The revised
covenant will read as follows: “The Recipient shall not later than June 27, 2016, undertake a social
assessment of the impact of the Project on the management of its fisheries resources upon terms of
reference satisfactory to the Association, and implement measures satisfactory to mitigate adverse social
impacts”.
Ln/Cr/T
F
Finance
Agreement
Reference
Description of Covenant Date
Due Status
Recurre
nt
Frequen
cy Action
IDA-H65
30
Finance Agreement
:Schedule 2, Section IV,
paragraph B.1 (b) |
Description :No
disbursements will be
made for the purchase of
fisheries patrol vessels,
until IDA shall have been
satisfied with the
cost-efficiency, technical
specifications and fiscal
sustainability | Frequency
:Yearly
Complie
d with
Marked
for
Deletion
IDA-H65
30
Finance Agreement
:Schedule 2, Section I,
paragraph A.1 (a) |
Description :The
Complie
d with
No
Change
Page 10 of 25
Recipient, through its
Fisheries Secretariat,
shall maintain throughout
Project Implementation
the Policy & Planning
Office within its
structure, under terms of
reference satisfactory to
IDA | Frequency :Yearly
IDA-H65
30
Finance Agreement
:Schedule 2, Section I,
paragraph E.1 |
Description :The
Recipient shall ensure
that the Project is
implemented in
accordance with the
provisions of the ESMF,
in a manner satisfactory
to the Association. |
Frequency :Quarterly
Partially
complied
with
No
Change
IDA-H65
30
Finance Agreement
:Schedule 2, Section I,
paragraph E.4 |
Description :The
Recipient shall undertake
a social assessment of the
impact of the Project on
the management of its
fisheries resources, and
implement measures
satisfactory to mitigate
adverse social impacts |
Due Date :25-Jun-2014
Expected
soon
Revised
IDA-H65
30
Finance
Agreement
:Schedule 2,
Section I,
paragraph E.4
Finance Agreement
:Schedule 2, Section I,
paragraph E.4 |
Description :The
Recipient shall undertake
a social assessment of the
impact of the Project on
the management of its
fisheries resources, and
implement measures
satisfactory to mitigate
adverse social impacts |
Due Date :27-June-2016
27-Jun-2
016
Not yet
due
Proposed
IDA-H65
30
Finance Agreement
:Schedule 2, Section I,
Complie
d with
No
Change
Page 11 of 25
paragraph F.1, F.2 |
Description :All
monitoring, control and
surveillance activities
shall be under the control
of FISCAP and shall be
carried out by civilian
authorities under TORs
limited to fisheries
surveillance | Frequency
:Quarterly
IDA-H65
30
Finance Agreement
:Schedule 2, Section I,
paragraph F.1, F.2 |
Description :All goods,
works, services and
operating costs financed
by the Project are used
exclusively by civilian
authorities for the
purposes of the Project,
and not for any military
purpose | Frequency
:Quarterly
Complie
d with
No
Change
IDA-H65
30
Finance Agreement
:Schedule 2, Section I,
paragraph F.4 |
Description :All
monitoring, control and
surveillance activities
carried out under the
Project will be audited
periodically by the
independent panel of
experts to be established
under Project component
2.3| Frequency :Yearly
Complie
d with
No
Change
IDA-H65
30
Schedule 2,
Section I,
paragraph F.1,
F.2
In order to ensure the
proper implementation of
component 2 of the
Project and more
generally the monitoring,
control and surveillance
of its coastal fisheries in
a manner designed to
achieve the objective of
the Program, the
Recipient shall
ensure at all times that:
Complie
d with
Quarterly New
Page 12 of 25
- All monitoring, control
and surveillance activities
carried out by the
Recipient shall be under
the control of FISCAP.
IDA-H65
30
Schedule 2,
Section I,
paragraph F.4
The Recipient shall
ensure that all
monitoring, control and
surveillance activities
carried out under the
Project are audited
periodically by the
Independent Panel of
Experts to be established
under component 2.3 of
the Project and whose
qualifications, experience
and terms of reference
are satisfactory to the
Association.
Complie
d with
Yearly New
Financing
Change in Loan Closing Date(s)
Explanation:
It is proposed to extend the Closing Date of the IDA and GEF grants by 12 months from June 30, 2016 to
June 30, 2017. This will be the first extension of the grants.
The extension is expected to make up for the delays experienced during the first 2 years of the project,
which were mainly the result of the suspension of all Bank operations in Guinea Bissau because of the
military takeover in 2012, and the temporary absence of a project coordinator in 2013. The extension is
expected to allow the achievement of the PDO by providing the government with sufficient time to
consolidate the actions taken so far on Illegal, Unreported and Unregulated (IUU) fishing and on legal and
institutional reforms.
The team confirms that the requirements of BP 10.00, para 47 (Extension of Closing Date) have been met:
specifically, (i) the PDO remains achievable as measured by the revised PDO Level Indicators; (ii) the
performance of the Recipient country remains satisfactory (Government Commitment is rated Satisfactory;
and the PDO and IP are rated Moderately Satisfactory); and (iii) the Bank and the Recipient have agreed
on actions that will be undertaken to complete the Project: a work plan was agreed on for the extended
project duration, which focuses on the key activities that need to be implemented in order to achieve the
end of project targets based on the proposed revised Results Framework.
Ln/Cr/T
F Status
Original Closing
Date
Current Closing
Date
Proposed Closing
Date
Previous Closing
Date(s)
IDA-H65
30 Effective 30-Jun-2016 30-Jun-2016 30-Jun-2017 30-Jun-2016
TF-9959
7 Effective 30-Jun-2016 30-Jun-2016 30-Jun-2017 30-Jun-2016
Reallocations
Page 13 of 25
Explanation:
It is proposed to reallocate IDA grant proceeds between categories. The reallocation reflects the
distribution of the entire Lease Payments Category 2 allocation (SDR 1,450,000) and 33 percent of the
original allocation to the purchasing of a coastal surveillance civilian patrol vessel (SDR 190,000) under
Category 1 – between all the other allocations in a manner that supports the implementation of the work
plan for the extended project duration.
As a result:
The IDA allocation to Parts 1 and 4.1 of the project (good governance and sustainable fisheries
management; and national project implementation, respectively) will increase by 65 percent.
The IDA allocation to Parts 2.1 (except for the revised Part 2.1 (c)(ii)), 2.2 and 3 (MCS system,
sustainability of the operating costs of the MCS system and increasing the contribution of marine
fish resources to the local economies, respectively) will increase by 117 percent.
The IDA allocation to Parts 2.3 and 4.2 (regional MCS collaboration for and regional
coordination, respectively) will increase by 9 percent.
The IDA allocation to the revised Part 2.1(c)(ii) (hiring of a coastal surveillance civilian patrol
vessel and its crew) will be reduced by 33 percent.
The original allocation to the Lease Payment category is cancelled to reflect Government’s decision not to
lease a patrol vessel, which is costly and requires technical capacity which FISCAP currently does not
possess. The allocation of the revised Part 2.1(c)(ii) (vessel and crew hiring – originally vessel purchasing)
is smaller as it costs less to hire the vessel for the remaining project period than to purchase it.
Ln/Cr/TF Currency Current Category of
Expenditure Allocation
Disbursement % (Type
Total)
Current Proposed Current Proposed
TF-99597 USD WKS,GDS,Non-CS,CS,T
R,OP C Parts1
2,000,000.0
0
2,000,000.0
0 77.00 77.00
Designated Account 0.00 0.00 0.00 0.00
Total: 2,000,000.0
0
2,000,000.0
0
IDA-H6530 XDR CW,GDS,NON-CS.CS,T
R,OP Part 1, 4.1 400,000.00 660,000.00 23.00 23.00
CW,GDS,NON
S,CS,TR,OP
Part2.1,2.2,3
1,150,000.0
0 2,500,000.0
0 100.00 100.00
CW,GDS,N-CS,CS,TR,O
P Part 2.3,4.2 320,000.00 350,000.00 100.00 100.00
CW,GDS,N-CS,CS,TR,O
P Part 2.1.1 (c) 580,000.00 390,000.00 100.00 100.00
DISB - OTHER 1,450,000.0
0 0.00 100.00 100.00
Designated Account 0.00 0.00 0.00 0.00
Designated Account 0.00 0.00 0.00 0.00
Total: 3,900,000.0 3,900,000.0
Page 14 of 25
0 0
Disbursement Estimates
Change in Disbursement Estimates
Explanation:
The disbursement schedule will be revised to reflect the disbursement delays, the 12 months extension of
the grants and the proposed work plan and budget for the remaining project period.
Fiscal Year Current (USD) Proposed (USD)
2011 100,000.00 0.00
2012 400,000.00 400,000.00
2013 400,000.00 190,000.00
2014 600,000.00 260,000.00
2015 1,500,000.00 1,500,000.00
2016 1,500,000.00 1,000,000.00
2017 1,500,000.00 2,650,000.00
Total 6,000,000.00 6,000,000.00
Components
Change to Components and Cost
Explanation:
Explanation:
The components' costs will be revised to reflect the reallocation of proceeds as described above and the
substitution of leasing and purchasing of patrol vessels under sub-component 2.1 with the less expensive
option of vessel and crew hiring.
Current Component
Name
Proposed Component
Name
Current Cost
(US$M)
Proposed
Cost (US$M) Action
Good Governance and
Sustainable Management
of the Fisheries 2.00 1.70 Revised
Reduction of Illegal
Fishing 4.70 4.00 Revised
Increasing the
Contribution of the
Marine Fish Resources to
the Local Economies
0.40 0.50 Revised
Coordination, Monitoring
and Evaluation and
Program Management 0.90 1.80 Revised
Total: 8.00 8.00
Other Change(s)
Page 15 of 25
Other Change(s)
Explanation:
It is proposed to make the following other changes to the IDA financing agreement:
1. Schedule 1, Part 1.1 (iv): Strengthened Policy Framework for the Use of Fish Resources: Revise
activities related to fisheries management plans to reflect the pre-existence of management plans
for coastal shrimp, cephalopods and demersal fish species. The relevant Intermediate Results
Indicator will be modified accordingly (See Annex 1 for the revised Results Framework)
2. Schedule 1, Part 2: Reduction of Illegal Fishing: Correct the numbering of activities to ensure
consistency with the sequencing of activities as described in the PAD and with references in the
financing agreement itself; change the leasing during the first two years of Project implementation
of a larger surveillance vessel to the hiring of a surveillance vessel and crew; and remove the
purchase of a coastal surveillance civilian patrol vessel. The two latter changes are required due to
the unavailability of sufficient project funding for lease and purchase of vessels (hiring is cheaper),
and the lack of technical capacity within FISCAP (the Recipient’s autonomous civilian agency
responsible for surveillance of fisheries) to operate a vessel. The proposed reallocation of proceeds
(as per the above) reflects these changes, as is the reference in the revised disbursement table
below.
3. Schedule 1, Part 3.1 (i): Updating of the Capabilities of Fish Inspection and Quality Control
Department: Remove “sanitary” from the definition of the authority and the EU certification
requirements due to the fact that accreditation for certification of fisheries products exports to the
EU is a process which neither the project nor the Government has control of. This change is also
reflected in the revised Intermediate Results Indicator (see Annex 1 for the revised Results
Framework)
4. Schedule 2, Section IV: Withdrawal of Proceeds of the Financing: correct the reference to
activities to align with the revised numbering of activities and removal of vessel purchasing:
change 2.1.1 (c)(iii) to 2.1 (c)(ii). Proposed revisions also reflect the reallocation of proceeds and
the removal of disbursement category 2.
5. Appendix, Section 1.24: Definitions: Remove the definition for “Lease payments” as this category
will be removed.
Page 16 of 25
ANNEX 1: REVISED RESULTS FRAMEWORK
Project Name: West Africa Regional Fisheries Program APL B1 Project
Stage:
Restructuring Status: DRAFT
Team Leader(s): Berengere P. C.
Prince
Asberr Natoumbi
Mendy
Requesting
Unit:
GENDR Created by: Liba C. Strengerowski-Feldblyum
Product Line: IBRD/IDA
GEF
Responsible
Unit:
GENDR Modified by: Asberr Natoumbi Mendy
Country: Republic of Guinea
Bissau
Approval
FY:
2011
Region: AFRICA Lending
Instrument:
Adaptable Program Loan
Project Development Objectives
Original Project Development Objective (unchanged):
The Project Development Objective is to strengthen the country’s capacity to govern and manage targeted fisheries, reduce illegal fishing and increase local
value added to fish products.
Results
Core sector indicators are considered: Yes Results reporting level: Project Level
Project Development Objective Indicators
Status Indicator Name Core Unit of
Measure
Baseline Actual (Current) End Target
Marked for
deletion
Two overexploited
fisheries showing
signs
of recovery, as
measured by an
increase in total
catch
per unit of fishing
effort
□ Number of
tons of fish
caught per
fishing vessel
per year
Value - Coastal
demersal fish =
270 tons
- Coastal shrimp
= 348 tons
- Cephalopods =
492 tons
2,007 tons - Coastal demersal fish =
310 tons
- Coastal shrimp = 401
tons
- Cephalopods = 566
tons
Date March 7, 2011 December 2014 June 30, 2016
Comment Measures total
landings
of fish caught
In 2013, total annual
catch was 36,131.1 tons
of coastal demersal fish
Page 17 of 25
legally in
Guinea-Bissau’s
waters
caught by 18 licensed
demersal trawlers
licensees.
Marked for
deletion
Increase in annual
net
economic benefits
from
targeted fisheries
□ Percentage Value US$16.45 M During the MTR
mission, it was
recommended that the
project develop a
simple economic
model, as the
appropriation of a
complex model at
national level would be
difficult to achieve.
5
Date March 7, 2011 October 2014 June 30, 2016
Comment Economic model,
based on fish
landings, price,
effort
The model is not yet
developed. TOR being
developed.
Original Total number of
beneficiaries (of
which
female)
X Number
(percentage)
Value 1.6 million
(51.5%)
1.6 million (51.5%) 1.6 million (51.5%)
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment The project aims
to benefit the
country as a
whole, by
supporting
governance
reforms to
sustainably
increase the
sector’s
contribution to
economic growth
Revised end target date to
align with
extended project
closing date
New A Policy and a
Strategic Plan that
□ Yes/No Value No Yes for strategic plan.
Final draft reports on
Yes
Page 18 of 25
are fully aligned
with international
good practice
(including for
provisions for
co-management,
TURFs, etc.) are
developed and
adopted
the Policy, Legal and
Regulatory framework
submitted for expert
comments.
Date March 7, 2011 November 2015 June 30, 2017
Comment Baseline is
relevant to the
time before the
project
The National Strategic
Plan was revised and
approved by Cabinet in
December 2014. A
consortium of Agrer
and Canaest has signed
a contract to revise the
policy and the legal
framework for the
fisheries sector. A
diagnostic mission
(first phase) was
conducted in October
2014. The second phase
of the assignment
began in March 2015.
Revised
(originally an
intermediate
result indicator,
text revised to
account for all
surveillance
measures)
Proportion of fishing
vessels observed by
aerial/maritime
patrols, radar and
satellite monitoring
or by inspection at
the wharf or at the
harbour that are
committing a serious
infraction
□ Percentage Value Small scale =
20%
Industrial = 25%
Small-scale = 6%
Industrial = 3%
Small scale = 10%
Industrial = 10%
Date March 7, 2011 September 1, 2015 June 30, 2017
Comment As at Sept 2015, 782
fishing canoes have
Revised end
target date to
Page 19 of 25
license, 53 fishing
canoes were observed
committing infraction.
As at September 2015,
9 industrial fishing
vessels were observed
committing infractions
in the Exclusive
Economic Zone (EEZ)
of Guinea Bissau; a
total of 325 industrial
fishing vessels have
license for 2015.
The percentage of
fishing vessels
committing infraction
is much reduced than
targeted values for
2014 and 2015 for both
small-scale and
industrial vessels.
align with
extended project
closing date
% of total number of
vessels boarded during
routine surveillance
patrols, that are found to
be committing a serious
infraction Serious
infraction is defined as
any fishing infraction
punishable by arrest
according to current
legislation, e.g. fishing
w/o a license. The
indicator will measure
both arrests and
prosecution of penalties.
New New quantities of
target demersal fish
and fish products
destined for export
tested at the quality
control and
inspection laboratory
□ Kg Value 0 0 1,000
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment Baseline is
relevant to the
time before the
project
Testing of fish products
at the laboratory has
not commenced yet.
The laboratory is
equipped with relevant
fish quality testing
equipment; training of
personnel has started.
Page 20 of 25
Intermediate Results Indicators
Component 1
Status Indicator Name Core Unit of
Measure
Baseline Actual (Current) End Target
Revised
(changed
assessment to
number of plans
instead of
existence of
plans, defined
the fisheries as
“coastal
fisheries”, and
replaced
“prepared” with
“updated”
Number of fisheries
Management Plans
for three targeted
coastal fisheries
updated and adopted
□ Number Value 0 0 1
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment A Management
Plan for the three
fisheries was
approved in 2010
The assignment has not
started yet.
Revised end
target date to
align with
extended project
closing date
The three target fisheries
are demersal fisheries,
coastal shrimp and
cephalopods
New Assessments of
Fisheries
Performance
Indicators are
carried out and
reports available
□ Number Value 0 0 2
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment Baseline is
relevant to the
time before the
project
One assessment in 2016
and a second assessment
in 2017
Page 21 of 25
Original A biological and
economic
assessment of the
health of targeted
fish stocks is
conducted
□ Yes/No Value No/No Yes for the biological
assessment
No for economic
assessment
Yes/Yes
Date March 7, 2011 April 1, 2015 June 30, 2017
Comment The Mauritanian
Research Vessel, AL
AWAM conducted
demersal fish stocks
survey in December
2014, and the final
report was submitted in
April 2015. A
Consultant is being
selected for the
assessment of targeted
fish stocks using simple
economic model
Revised end
target date to
align with
extended project
closing date
Original An electronic
‘dashboard’ of key
environmental,
social
and economic
fisheries
statistics established
at
the Fisheries
Secretariat
□ Yes/No Value No Yes Yes
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment The development of the
Information system is
completed. Training of
Users and
Administrators
underway 75%
completed.
Revised end
target date to
align with
extended project
closing date
Dashboard
Page 22 of 25
will be linked
to regional
database
housed at the
CSRP
Component 2
Revised (revised
definition of
indicator and
conversion to
PDO Level
Indicator – (see
above)
Fishing vessels
observed by
aerial/surface patrol
or
by radar and satellite
monitoring, that are
committing a serious
infraction
□ Percentage Value Small-scale =
20%
Industrial = 25%
Small-scale = 6%
Industrial = 3%
Small-scale = 10%
Industrial = 10%
Date March 7, 2011 September 1, 2015 June 30, 2017
Comment Revised end
target date to
align with
extended project
closing date
% of total number of
vessels boarded during
routine surveillance
patrols that are found to
be committing a serious
infraction Serious
infraction is defined as
any fishing infraction
punishable by arrest
according to current
legislation, e.g. fishing
w/o a license. The
indicator will measure
both arrests and
prosecution of penalties.
Page 23 of 25
Revised
(frequency
changed from
“per month” to
“per month and
per year” and
focus changed
from “targeted
fisheries” to
“coastal waters”.
Annual targets
were added)
Total patrol days at
sea per month and
per year in Coastal
waters
□ Number per
month/per
year
Value 11/132 99 days/year1 22 days per months /150
days per year
Date March 7, 2011 September 1, 2015 June 30, 2017
Comment The value is for the
period June-Sept. 2015.
Revised end
target date to
align with
extended project
closing date
The target of 150 is
achievable according to
the government;
moreover, by the end of
the project, it is expected
that less patrol days will
be needed as the vessels
would be adhering to
regulations
Original
A fisheries
monitoring
center is equipped
and
functional
□ Yes/No Value No Yes Yes
Date March 7, 2011 March 31, 2015 June 30, 2017
Comment The fisheries
monitoring center at the
Revised end
target date to
1 As at December 2015, a total of 99-patrol days/year covering both industrial and artisanal fisheries were conducted in coastal waters of Guinea Bissau. The number of patrol day/year conducted in 2015 was below the baseline, this is due to the delay in finalizing the hiring agreement of the Senegalese naval patrol boat.
Page 24 of 25
FISCAP has been
established and
functioning. It is
equipped with
satellite-based Vessel
Monitoring System
(VMS), radar,
Automatic
Identification System
(AIS) and short and
long-range radio
equipment. Update?
align with
extended project
closing date
Center should be staffed
24 hours per day, with
electricity and
communication access to
bases and vessels
HF &VHF radios, Radar,
VMS, AIS, TV screen
Revised
(“sanitary
authority” was
revised to
“authority” and
accreditation for
certification of
fisheries
products exports
to the EU was
removed)
A competent
authority is
established and
functional
□ Yes/No Value No No Yes
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment The building that will
house the laboratory
and competent
authority has been
constructed and
equipped with tested
equipment.
A Consultant was
recruited to provide TA
to CIPA personnel and
developed an annual
work plan, a budget
and protocols for
quality and traceability
Revised end
target date to
align with
extended project
closing date
The authority should have
laboratories equipped by
the project. The degree of
the operationalization of
the laboratory will be
measured by the number
of organoleptic and
chemical analysis
conducted and verified
Page 25 of 25
standards for the
laboratory.
Original Regional database
and ‘dashboard’ of
key environmental,
economic and social
fisheries statistics
established at the
CSRP
□ Yes/No Value No No Yes
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment Revised end
target date to
align with
extended project
closing date
New Annual M&E
reports with data on
indicators of the
results framework
and M&E plan
finalized
□ Yes/No Value No Yes Yes
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment Baseline is
relevant to the
time before the
project
New Annual work plans,
budgets and
procurement plan
finalized
□ Yes/No Value No Yes Yes
Date March 7, 2011 February 3, 2016 June 30, 2017
Comment Baseline is
relevant to the
time before the
project