Upload
truongkhue
View
260
Download
6
Embed Size (px)
Citation preview
Generator Circuit-BreakersTechnical Seminar: PLN
Pankaj Khali, ABB India Limited Representing :ABB Switzerland limited, September 2016
Agenda
§ Advantages of Generator Circuit-Breakers
§ Criteria of Selection and Technical Requirements
§ ABB Portfolio Overview and Critical Design Aspects
§ New Standard: IEC/IEEE 62271-37-013
© ABB GroupSeptember 17, 2016 | Slide 2
© ABB GroupSeptember 17, 2016 | Slide 3
Advantages of GeneratorCircuit-Breakers
© ABB GroupSeptember 17, 2016 | Slide 4
Connection with Generator Circuit-BreakerUnit connection (without GeneratorCircuit-Breaker)
Introduction
G
EHV HV
MT
UT ST
AUX G
EHV HV
MT
UT STGenCB
AUX
© ABB GroupSeptember 17, 2016 | Slide 5
with Generator Circuit-Breaker
Introduction
G
EHV
MT
UTGenCB
AUX G
EHV
MT
UTGenCB
AUX
© ABB GroupSeptember 17, 2016 | Slide 6
without Generator Circuit-Breaker with Generator Circuit-Breaker
G
EHV
MT
UTSS
GenCB
SFCG
EHV HV
MT
STSS
SFC
AUX
Typical Layouts for Gas Turbine Power Plants
Introduction
© ABB GroupSeptember 17, 2016 | Slide 7
Advantages of Generator Circuit-BreakersSimplified Operational Procedures
§ During the starting-up or shutting-down of thegenerator only one circuit-breaker has to beoperated thus reducing the number of switchingoperations necessary
§ The responsibilities for the operation of the powerplant and the high-voltage grid are clearly defined
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
© ABB GroupSeptember 17, 2016 | Slide 8
§ Maximum selectivity of protection zones
§ Rapid and selective clearance of all types offaults
Bursting of the transformer tank following an internal fault inthe main or unit transformer
Advantages of Generator Circuit-BreakersImproved Protection
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
© ABB GroupSeptember 17, 2016 | Slide 9
Fault Current
Time
Advantages of Generator Circuit-BreakersInterruption of Generator-Fed Fault Currents
Interruption of Generator-Fed Fault Currents – Case without GeneratorCircuit-Breaker (Unit Connection)
IsIgGridG
Is+Ig
Ig
Interruption of HVCircuit-Breaker
tens of ms seconds
© ABB GroupSeptember 17, 2016 | Slide 10
Fault Current
Time
Advantages of Generator Circuit-BreakersInterruption of Generator-Fed Fault Currents
Interruption of Generator-Fed Fault Currents – Case with GeneratorCircuit-Breaker
IsIgGridG
Is+Ig
Ig
tens of ms seconds
Interruption of HVCircuit-Breaker
Interruption of GeneratorCircuit-Breaker
© ABB GroupSeptember 17, 2016 | Slide 11
t [ms]
2.5
2.0
1.5
1.0
0.5
Gen
erat
orC
ircui
t-Bre
aker
HV
Circ
uit-B
reak
er
P [bar]
tank withstand pressure
50 100 150 250200
fault to tank from HV winding
full winding shorted HV side
shorted winding (portion)
tap changer contact fault 15%
Tap Changer
25%30%fault across bushing
10%5%
Pressure Rise in Power Transformers
© ABB GroupSeptember 17, 2016 | Slide 12
Equipment FailuresMain Transformer Failures
Generator Transformer Failure - withoutGenerator Circuit-Breaker
Sequence of events:
t = 0 ms: earth fault atHV-side of transformer
t = 45 ms: 2-phaseshort-circuit
t = 95 ms: 3-phaseshort-circuit
t ≈ 150 ms: explosion oftransformer
© ABB GroupSeptember 17, 2016 | Slide 13
§ Maximum selectivity of protection zones
§ Rapid and selective clearance of all types offaults
Bursting of the transformer tank following an internal fault inthe main or unit transformer
Thermal destruction of the generator damper winding dueto short-time unbalanced load conditions
Advantages of Generator Circuit-BreakersImproved Protection
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
© ABB GroupSeptember 17, 2016 | Slide 14
Advantages of Generator Circuit-BreakersShort-Time Unbalanced Load Conditions
Single and twophase faults
Inversecomponent
interacts withdamper windings
Criticalmechanical andthermal stresses
© ABB GroupSeptember 17, 2016 | Slide 15
Equipment FailuresShort-Time Unbalanced Load Conditions
Unbalanced Load Condition – withoutGenerator Circuit-Breaker
© ABB GroupSeptember 17, 2016 | Slide 16
§ Maximum selectivity of protection zones
§ Rapid and selective clearance of all types offaults
Bursting of the transformer tank following an internal fault inthe main or unit transformer
Thermal destruction of the generator damper winding dueto short-time unbalanced load conditions
Mechanical destruction of a turbine-generator set due togenerator motoring
Advantages of Generator Circuit-BreakersImproved Protection
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
© ABB GroupSeptember 17, 2016 | Slide 17
Equipment FailuresGenerator Motoring - without Generator Circuit-Breaker
GS3~
GeneratorPn = 500 MW
Main Transformer Overhead Line(Transmission)
Coupling
Overhead Line
HV Circuit-Breaker
Internal breakdown at HV circuit-breaker, pole L1•Generator starts working as motor
•Speed is increasing again
Open command•Three-phase network interruption
•Turbine-generator unit is running down normally
Mechanical destruction of turbine-generator set•Shaft and bearings are destroyed
•Generator is lifted out of the foundation
•12 meter high explosive flame
© ABB GroupSeptember 17, 2016 | Slide 18
n [min-1] Object
250
500
750
1000
1250
1500
1750
2000
2250
2500
2750
3000
02 4 6 8 10 12 14 160 18 20 22 24 26 28 30 32
n [min -1]
t [min]
2420 Generator
870 Generator
2040
1800
20101940 Turbine
Critical Rotor Speed
normal run down
1643
2142
after mechanicaldestruction
Equipment FailuresGenerator Motoring - without Generator Circuit-Breaker
© ABB GroupSeptember 17, 2016 | Slide 19
§ Maximum selectivity of protection zones
§ Rapid and selective clearance of all types offaults
Bursting of the transformer tank following an internal fault inthe main or unit transformer
Thermal destruction of the generator damper winding dueto short-time unbalanced load conditions
Mechanical destruction of a turbine-generator set due togenerator motoring
Thermal/dynamic stress caused to the generator bysynchronising under “out-of-phase” conditions
Advantages of Generator Circuit-BreakersImproved Protection
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
© ABB GroupSeptember 17, 2016 | Slide 20
Advantages of Generator Circuit-BreakersHigher Power Plant Availability
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
IncreasedAvailability
The rapid andselective
clearance of alltypes of faults
More reliablesynchronisation
Unit auxiliariessupplies drawn
directly frommain grid
The avoidanceof changeover
switchingoperations
Simplifiedoperationalprocedures
© ABB GroupSeptember 17, 2016 | Slide 21
Advantages of Generator Circuit-BreakersEconomic Benefits
Simplifiedoperation
procedures
Improvedprotection
Higherpower plantavailability
Economicbenefits
§ Integration of all the associated items ofswitchgear into the generator circuit-breakerenclosure
§ Possible to omit the station transformer and theassociated high-voltage and medium-voltageswitchgear
§ The through-fault capability required of the unittransformers is substantially reduced
§ Higher availability in turn leads to an increasednumber of the operating hours and therefore to ahigher profit for the operator of the power plant
© ABB GroupSeptember 17, 2016 | Slide 22
Availability CalculationLayout of Power Station
2 x 600 MW Power StationLayout with GeneratorCircuit -Breaker
2 x 600 MW Power StationLayout with GeneratorCircuit -Breaker andShut-Down Transformer
2 x 600 MW Power StationUnit Connection
Reference ScenarioCase 1Case 2Case 3
© ABB GroupSeptember 17, 2016 | Slide 23
Availability CalculationResults of Availability Calculation
Results of AvailabilityCalculation for one 600 MWUnit - Average PowerThroughput
Pow
er[M
W]
520
515
510
505
500
525
530
Cas
e2
Cas
e1
Cas
e3
Average Power Output of Unit (Assumed Value)
© ABB GroupSeptember 17, 2016 | Slide 24
Criteria of Selection andTechnical Requirements
© ABB GroupSeptember 17, 2016 | Slide 25
Criteria of Selection and Technical RequirementsDuties of Generator Circuit-Breakers
§ Synchronise the generator with the main system
§ Separate the generator from the main system (switching off theunloaded/lightly loaded generator)
§ Carry and interrupt load currents (up to the full load current of thegenerator)
§ Interrupt system-source short-circuit currents
§ Interrupt generator-source short-circuit currents
§ Interrupt fault currents due to out-of-phase conditions up to out-of-phase angles of 180°
© ABB GroupSeptember 17, 2016 | Slide 26
Short-Circuit Current Interruption
t [ms]50403020100-10-20-30-40
u (t)
i (t)
Characteristics of short-circuitcurrent
Characteristics of transientrecovery voltage (TRV)
separation of arcing contact
Criteria of Selection and Technical RequirementsRequirements for Generator Circuit-Breakers
© ABB GroupSeptember 17, 2016 | Slide 27
t[ms]
50403020100-10-20
-30
-40
u (t)
i (t)
Characteristics of short-circuitcurrent
Characteristics of transientrecovery voltage (TRV)
§Rate-of-rise
High technical requirements are imposed on the circuit-breaker with respect to:
§ Rated current
§ Short-circuit currents (system-source and generator-source)
§ Fault currents due to out-of-phase conditions
§ Degree of asymmetry of fault currents, fault currentswith delayed current zeros
§ Rate-of-rise of the recovery voltages
§Magnitude§Asymmetry
Criteria of Selection and Technical RequirementsStandards for Generator Circuit-Breakers
© ABB GroupSeptember 17, 2016 | Slide 28
§IEEE Std C37.013 / IEEE Std C37.013a
§IEC 62271-100
Circuit-breakers that have beendesigned and tested in
accordance with IEC 62271-100do not meet the stringentrequirements imposed on
generator circuit-breakers andtherefore are not suitable for the
use as generator circuit-breakers.
© ABB GroupSeptember 17, 2016 | Slide 29
§ Rated maximum voltage
§ Rated power frequency
§ Rated insulation level (dielectric strength): Lightning impulsewithstand voltage and power frequency withstand voltage
§ Rated peak and short-time withstand current
§ Rated current
§ Closing and making time
§ Opening and breaking (interrupting) time
§ Duty cycle (operating sequence)
§ Rated short-circuit making current (closing and latching capability)
Criteria of Selection and Technical RequirementsSelection of Generator Circuit-Breaker
© ABB GroupSeptember 17, 2016 | Slide 30
§ Rated short-circuit breaking current(system-source short-circuit breaking current):Symmetrical value, degree of asymmetry, TRV capabilities
§ Generator-source short switching capability:Symmetrical value, degree of asymmetry, TRV capabilities
§ Out of phase current switching capability:Symmetrical value, degree of asymmetry, TRV capabilities
§ Load current switching capability:Symmetrical value, TRV capabilities
Selection of Generator Circuit-Breaker
© ABB GroupSeptember 17, 2016 | Slide 31
System-Source Short-Circuit Current
110 kVSk = 10 GVA
100 MVA110/13.8 kV
uk = 12 %
99 MVA13.8 kV
cos j = 0.8X’’dv = 13.5%
Contact parting time 50ms:
Ipk = 90.5 kA Isym = 33.2 kA a = 63.5 %
IscTS
G
© ABB GroupSeptember 17, 2016 | Slide 32
System-Source Short-Circuit Current
Characteristics of asymmetry:
=
AC /symmetrical
current
DCcurrent
Asymmetricalcurrent
+
ac
dc
IIa2
=
dcI
acI2
System-Source Short-Circuit CurrentSurvey - Terminal Fault Prospective Currents (tcs = 40 ms)
© ABB GroupSeptember 17, 2016 | Slide 33
0
50
100
150
200
250
0 500 1000 1500 2000
I SCsy
s(k
Arm
s)
Generator Rated Power (MVA)
System-Source Short-Circuit CurrentSurvey - Terminal Fault Prospective Currents (tcs = 40 ms)
© ABB GroupSeptember 17, 2016 | Slide 34
0
20
40
60
80
100
0 500 1000 1500 2000
DOA s
ys(%
)
Generator Rated Power (MVA)
Average DOAsys = 72.2%No DOAsys > 100%
© ABB GroupSeptember 17, 2016 | Slide 35
Generator-Source Short-Circuit Current
110 kVSk = 10 GVA
100 MVA110/13.8 kV
uk = 12 %
99 MVA13.8 kV
cos j = 0.8X’’dv = 13.5%
Contact parting time 50ms:
Ipk = 95.6 kA Isym = 23.8 kA a = 133.4 %
IscG
G
© ABB GroupSeptember 17, 2016 | Slide 36
Generator-Source Short-Circuit Current
Characteristics of asymmetry:
ac
dc
IIa2
=
Generator-Source Short-Circuit CurrentSurvey - Terminal Fault Prospective Currents (tcs = 40 ms)
© ABB GroupSeptember 17, 2016 | Slide 37
Salient-pole machines usually have a lower degree ofasymmetry in case of generator-fed fault currents
Gas turbines of smaller power usuallyhave a higher degree of asymmetry
ABB is testing 130% degree of asymmetry
Out-of-Phase Conditions
© ABB GroupSeptember 17, 2016 | Slide 38
110 kVSk = 10 GVA
100 MVA110/13.8 kV
uk = 12 %
99 MVA13.8 kV
cos j = 0.8X’’dv = 13.5%
Contact parting time 50ms:
Ipk = 68.2 kA Isym = 17.8 kA a = 117.2 %
Iop
G
© ABB GroupSeptember 17, 2016 | Slide 39
Criteria of Selection and Technical RequirementsOut-of-Phase Conditions
Characteristics of asymmetry:
ac
dc
IIa2
=
© ABB GroupSeptember 17, 2016 | Slide 40
Influence of out-of-phase angle
Out-of-Phase Conditions
60° out-of-phase condition
180° out-of-phase condition 120° out-of-phase condition
90° out-of-phase condition
Selection of Generator Circuit-Breakers180° Out-of-Phase Synchronisation
© ABB GroupSeptember 17, 2016 |Slide 41
* Paper submitted to the International Conference of Power Systems Transients (IPST2013) in Vancouver (CA)
§Ratio between Isc OoP 180° and Isc system fault currents asfunction of generator rated power *
Example:
HECS-130 system source breaking current - 130 kA
OoP breaking current - 112 kA
Tests180° Out-Of-Phase Tests
September 17,2016
| Slide 42© ABB
§ Tests demonstrating the capability of a GCB to interruptcurrents resulting from 180° out-of-phase conditions shallshow
§ Current magnitude higher than 85% of system-sourceshort-circuit current;
§ Rate-of-rise of the transient recovery voltage (RRRV) ≥6.3 kV/ms.
§ A test performed with
§ Current magnitude equal to 50% of system-sourceshort-circuit current;
§ RRRV equal to 5.2 kV/ms or less;
is not a proof of the capability of the tested GCB to interruptcurrents resulting from 180° out-of-phase conditions .
© ABB GroupSeptember 17, 2016 | Slide 43
Criteria of Selection and Technical RequirementsShort-Circuit Current Current Interruption
t [ms]50403020100-10-20-30-40
u (t)
i (t)
Characteristics of short-circuitcurrent
Characteristics of transientrecovery voltage (TRV)
separation of arcing contact
Criteria of Selection and Technical RequirementsTransient Recovery Voltage (TRV)
© ABB GroupSeptember 17, 2016 | Slide 44
Criteria of Selection and Technical RequirementsTransient Recovery Voltage (TRV) - Surge Capacitors
§ The capacitor is connectedduring the testing of theinterrupting performance
§ The capacitor is therefore to beconsidered as an integral partof a generator circuit-breaker
© ABB GroupSeptember 17, 2016 | Slide 45
“The interrupting capability demonstrated by these tests isvalid only if capacitors of the same capacitance value asused during the tests are installed according to the tested
configuration.”
addition ofcapacitor
time delay increases with capacitance value
rate-of-rise decresaes with capacitance value
Criteria of Selection and Technical RequirementsSummary of Power Tests
© ABB GroupSeptember 17, 2016 | Slide 46
© ABB GroupSeptember 17, 2016 | Slide 47
ABB Portfolio Overview andCritical Design Aspects
ABB Generator Circuit BreakersPortfolio Overview (50/60 Hz)
© ABB
© ABB GroupSeptember 17, 2016 | Slide 49
Generator Circuit-Breaker System typeHECS-130L
© ABB GroupSeptember 17, 2016 | Slide 50
10
7
7
GCB SystemTypical single line diagram
Generator Circuit-Breaker
Series Disconnector
Capacitors
Starting Switch for SFC
Manual Short-Circuit Connection
Earthing Switches
Current Transformers
Potential Transformers
Surge Arresters
Motorized Short-Circuit Connection
G
1
2
3T
3G
6G
6T
5
4
8
8
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
9
9
Service during Tender and Project ExecutionApplication Studies Group for GCB’s
© ABB GroupSeptember 17, 2016 | Slide 51
§ Application Studies Group is able to performany kind of calculation required for the properselection and verification of GCB’s.
§ Active in the Working Groups of the mainIEC/IEEE Standards for HV breakers.
§ Active in the revision of the IEEE C37.013 forGCB’s bringing the most significant experienceof ABB in the GCB field into requirements.
Critical Design AspectsGCB Cooling System
© ABB GroupSeptember 17, 2016 | Slide 52
Natural Cooling Forced Cooling
ABB GCB portfolio
Critical Design AspectsGCB Cooling System
© ABB GroupSeptember 17, 2016 | Slide 54
Natural Cooling Forced Cooling
EnhancedCooling
Important: Which ratio of the capability isdependent on the cooling system?
The fans provide a linear andeven distribution of air inorder to enhance natural
convection.
Critical Design AspectsIndependent Cooling and Breaking
© ABB GroupSeptember 17, 2016 | Slide 55
• Cooling through air convection
• Failure of cooling does not influencebreaking capacity
• Less SF6
• Low maintenance
• High reliability
Cooling should not depend on SF6!
© ABB GroupSeptember 17, 2016 | Slide 56
HECS-XLp, XXLpInnovative passive cooling by heat pipes
Latest technology patentedby ABB for natural cooling
and 20y maintenance free inaccordance with the overhaul
concept of HECS
Interrupting chamber designSF6/SF6 vs SF6/Air
© ABB GroupSeptember 17, 2016 | Slide 57
SF6/SF6 contact systemused by ABB
arcing contacts
main contacts
SF6
SF6/Air contact systemnot used by ABB
arcing contacts
main contacts
disconnector
SF6
disconnector
§ Disconnector in series to arcing and main contacts§ Main contacts in SF6
§ «Disconnector» in series only to arcing contacs§ Main contacts in air
Commutation of current path from main contacts to arcingcontacts occurs in air.§Sparks which occur in air can lead to (commutation time 1.5-2 timeslonger :
I. a reduction of dielectric strength.II. wear of main contacts
§Problems of moisture and pollution when the air in IPB is at atmosphericpressure.
§ «Disconnector» visibility: main contacts and disconnector
§If circuit-breaker contacts accidentally close with disconnector open, nopossibility to extinguish arcs, risk of explosion à not safe !!
§ No isolation redundancy
Contact System Design
© ABB GroupSeptember 17, 2016 | Slide 58
SF6/SF6 contact systemused by ABB
arcing contacts
main contacts
SF6
SF6/Air contact systemnot used by ABB
arcing contacts
main contacts
disconnector
SF6
Commutation of current path from main contacts to arcingcontacts occurs in SF6.§No sparks occur in air, thus eliminating the risk of a reduction ofdielectric strength.
§Problems of moisture and pollution when the air in IPB is atatmospheric pressure do not affect the safe operation.
§ Viewing windows of disconnector provide clear indication
§If circuit-breaker contacts accidentally close with disconnector open,no risk of explosion à safe !!
§ Isolation redundancy
disconnector
Design of Generator Circuit-BreakersContact System – SF6/SF6 v/s SF6/AirExample of specification
§ The circuit-breaker shall have two separate contact systems: one forcarrying load current, the other for arc interruption. Both contactsystems shall be contained in SF6 and the current commutationshall occur in SF6. Contacts in air are not acceptable. Currentcommutation in air is not acceptable.
§ A disconnector shall be provided on the transformer-side in serieswith the main and arcing contacts of the circuit-breaker. The seriesdisconnector must be able to isolate the entire circuit and allowisolation for maintenance using industry accepted practices.
© ABB GroupSeptember 17, 2016 | Slide 60
Hydraulically charged spring operating mechanism
Critical Design AspectsOperating Mechanism
in all ABBapplications
Critical Design AspectsReliability of Operating Mechanism
§ According to CIGRE survey hydro-mechanical springmechanism is more reliable than full spring mechanism.
0.00
0.05
0.10
0.15
0.20
0.25
Hydro-mechanical spring *) Spring **) Pneumatic *)
Number of Major Failures per 100 CB-years
*) source: CIGRE Session 2012, paper A3-206
**) source: CIGRE Brochure 510: Final Report of the 2004 - 2007 InternationalEnquiry on Reliability of High Voltage Equipment - Part 2 Reliability of HighVoltage SF6 Circuit Breakers
Highest reliability ofhydro-mechanicalspring operating
mechanism
New Standard:IEC/IEEE 62271-37-013
© ABB GroupSeptember 17, 2016 | Slide 63
History of Development of GCB Standard
1989IEEE StdC37.013-1989
1993IEEE StdC37.013-1993
1997IEEE StdC37.013-1997
2007IEEE StdC37.013a-2007
2008IEEE StdC37.013-1997(R2008)
2015
IEC/IEEE 62271-37-013
0
50
100
150
200
250
IEEE C37.013-1989 IEEE C37.013-1993 IEEE C37.013-1997 IEC/IEEE 62271-37-013
Number of pages of the document
More than double numberof pages compared to theprevious revision !!
© ABB GroupSeptember 17, 2016 | Slide 64
New IEC/IEEE 62271-37-013
IEEE C37.013
IEEE C37.013a
IEC/IEEE 62271-37-013
New IEC/IEEE 62271-37-013Structure of the Document
§ IEC/IEEE Joint Development Procedure.
§ The document number IEC/IEEE 62271-37-013 results from merging thenumbering system of the twoorganizations.
§ Because IEC 62271 includes the use of“High-Voltage Switchgear andControlgear – Part xxx:”, this needs tobe part of the title.
§ Document is placed in the IEC template.
§Iscg = 100 kA
New IEC/IEEE 62271-37-013Generator-Source Short-Circuit Current Ratings
§ Iscg with 110% degree ofasymmetry
§ 0.74 x Iscg with 130%degree of asymmetry
§Class G1
§ Iscg with 130% degree ofasymmetry
§Class G2
§Degree of asymmery at contact separation irrespectively of the time that contact separationoccurs
rating is assigned bythe manufacturer
§100 kA @ 110%
§74 kA @ 130%
§100 kA @ 130%
§ A degree of asymmetry of 110% is not representative of interruptingconditions in actual power plant applications.
§ A degree of asymmetry of 130% is more appropriate.
§ Two classes for the rated generator-source short-circuit breaking currenthave been introduced:
§Most of ABB GCBsalready tested as G2 class!
New IEC/IEEE 62271-37-013Ratings – Mechanical Endurance
Two classes for the mechanical endurance have been introduced.
Standard generator circuit-breaker(normal mechanical endurance)
class M1
1000 operatingcycles
Generator circuit-breaker for special servicerequirements(extended mechanical endurance)
class M2
3000 operatingcycles
New IEC/IEEE 62271-37-013Type Tests
§ IEEE C37.013
× Test procedures are not alwayswell defined.
× This is especially true for tests inwhich the current exhibitsdelayed zero crossing.
× Customer cannot judge andevaluate objectively the validityof a test.
– § New IEC/IEEE 62271-37-013+
üA more detailed description oftest procedures is implemented.
üDetailed parameters are definedto characterize the currentwaveforms that should be tested.
üCustomer can easily judge andevaluate the validity of a test.
New IEC/IEEE 62271-37-013Type Tests – Delayed Current Zeros
Out-of-PhaseSynchronization
Generator TerminalFault
Fault at LV windingsof 3W Transformer
IEEE C37.013 IEC/IEEE 62271-37-013
New IEC/IEEE 62271-37-013Delayed Current Zeros
§ A test is not a sufficient proof of the breaking capability of the generatorcircuit-breaker with currents that exhibit delayed current zeros.
§ The test is required to derive the arc voltage vs current characteristics anddetermine the arc voltage model of the generator circuit-breaker.
§ The capability of the generator circuit-breaker to interrupt the current withdelayed zero crossings shall be ascertained by studies that take intoaccount the effect of the arc voltage..
“The capability of the generator circuit-breaker tointerrupt the current with delayed zero crossings shallbe ascertained by computations that consider theeffect of the arc voltage on the prospective short-circuit current.”
Source: IEC/IEEE 62271-37-013 Edition 1.0, 2015
New IEC/IEEE 62271-37-013Application Guide
The following studies shall be performed for each project:
§ system-source short-circuit current
§ generator-source short-circuit current
§ out-of-phase fault current
© ABB GroupSeptember 17, 2016 | Slide 71
§ unloaded
§ loaded with leading p.f
§ Loaded with lagging p.f
effect of arcvoltage
UA = 0
UA = max
UA = 0
UA = max
effect of arcvoltage
SF6or
Vacuum
© ABB GroupSeptember 17, 2016 | Slide 72
Application GuideInfluence of Capacitors - 3 Rules
1. The amount of equivalent capacitance required for breaking testsshall be given in the test report and on the nameplate.
2. The same capacitance value shall be used for all breaking tests.
3. The interrupting capability demonstrated by breaking tests is validonly if capacitors of the same capacitance value as used during thetests are installed in the generator circuit-breaker system deliveredfor a specific project.
Generator Circuit-BreakerDisconnectorEarthing switchStarting switchManually mounted short-circuiting connection
(1)(2)(3)(4)(5)
Surge capacitorCurrent transformerVoltage transformerSurge arresterMotor-operated short-circuiting link
(6)(7)(8)(9)
(10)
1 2
3 3
4 5
6 96
88
77
10
Single line diagram of a SF6 generator circuit-breaker
© ABB GroupSeptember 17, 2016 | Slide 73
Pankaj KhaliTerritory Marketing & Sales Manager: India, Sub Regions & South East AsiaProduct Group: GCB , Power Grid Division –High Voltage ProductsABB India Limited
Phone: +912667676825Mobile: +919638288666, +919997576667
email: [email protected]
Subscribe for GCB Insights today - It's free
Question ………