  • BEM Roadshow 2014

    CCC (Certificate of Completion and Compliance)

  • 2

    CCC FRAMEWORK CFO by local authorities replaced by CCC to be

    issued by the Principal Submitting Person (PSP) on 12 April 2007

    Aim of CCC to cut short the delays caused by Local Authorities and towards self regulations by the professionals

    CCC can only be issued by PSP after:- All certifications by the respective parties

    (professionals, contractors, licensed tradesmen) based on prescribed forms (Form Gs) under the Matrix of Responsibility and Accountability are secured.

  • Master Flow-chart

    Submission by IR for Infra Works

    Planning Approved

    Pre-Comp Plan Approved

    R & D

    Submission to Technical depts

    Submission by AR/IR on Bldg Plan Street Lighting

    Landscape

    Lift Etc

    Ext Main Drains

    Earthworks

    Sewerage Ret

    Ext Water Ret

    Telecommunication

    Ext Electrical Infra

    Structural Plan

    Planning Dept

    Sub-struct/Foundation

    Int Sanitary

    Passive Fire

    Active Fire

    Int Water

    Issue CCC Liaise with Authorities to take over

    Liaise with Authorities to take over

    Completion of construction certification by contractor/tradesmen, PE, PA

  • Who can be the Principal Submitting Person?

    Either a Prof. Architect (Ar.) or a Prof. Civil Engineer (Ir.) depending on the type of projects agreed between Board of Architects and Board of Engineers. Refer to the Joint Memorandum by BAM and BEM as per BEM Circular No. 01 Appendix A Only Ar can be PSP Appendix B Only Ir. can be PSP Appendix C Either Ar. or Ir. can be PSP

  • Duties of PSP To prepare and present planning and building

    plans to PBT for approval. Inform PBT of the commencement of

    construction works on site. Supervise construction works at site and

    ensure that laws and technical conditions of the PBT are followed.

    Report building breaches, explain reasons of breach and ensure breach is rectified during construction.

  • Duties of PSP Present work resumption notice to the PBT. Ensure Form Gs are duly certified by bona fide

    Professionals practising through ACPs/ECPs registered with BAM/BEM, at various stages of the works and when all the essential services have been provided.

    Issue CCC upon satisfactory completion of the works and after all conditions have been complied with, confirming the building is safe and fit for occupation.

    Deposit a copy of the CCC to the PBT and BAM/BEM within 14 days of issue.

  • Penalties on PSP in Section 70(27) of Street, Drainage and Building Act

    Not a PSP but issues a CCC Issues a CCC without all the relevant forms Issues CCC in contravention of a direction by PBT Make any false or fraudulent declarations Uses any forged, altered or counterfeit declaration,

    certificate and application Occupies or permits to be occupied any building

    without a CCC Fine not exceeding RM 250K or to imprisonment not

    exceeding 10 years or to both.

  • UNIFORM BUILDING BY-LAWS 1984 FORM F

    CERTIFICATE OF COMPLETION AND COMPLIANCE [By -Law 25]

    Date:..

    To: *. I hereby issue the Certificate of Completion and Compliance for the building/s on Lot/s........ Section...... Jalan................................................... upon being satisfied that it has been completed in accordance with approved plan No. ................. dated ....................... I have supervised the erection and completion of the building/s and it is to the best of my knowledge and belief that such work/s is/are in accordance with the Act, Uniform Building By-laws 1984 and approved plans. I hereby certify that the building/s is/are safe and fit for occupation.

    (Principal submitting person)

  • 1. Particulars of the principal submitting person Name : ..... Address: ............ **BAM/BEM Registration No.: 2. Copy to: (a) Local Authority : . (Name of Local Authority) (b) **Board of Architects Malaysia(BAM)/Board of Engineers Malaysia (BEM)

  • FORM F FAQ Q1 Can a Form F once issued be cancelled or have a

    date change? Case 1: Ar. A requested BAM for guidance where the

    PBT had instructed him to cancel Form F issued on 24.9.2012 due to no support letter from PBT for Form G17. The PBT later conducted a site inspection and subsequently issued a Letter of Support on 24.3.2013. The PBT refused to accept Form F dated 24.9.2012 and requested for a fresh Form F to be submitted with a later date. On the other hand, Ar. A was threatened by the developer for losses and damages if Form F is issued with a later date.

    Can Conditional CCC be issued?

  • UNIFORM BUILDING BY-LAWS 1984 FORM F1

    CERTIFICATE OF COMPLETION AND COMPLIANCE [By -Law 27]

    Date:..

    To: *. I hereby issue the Partial Certificate of Completion and Compliance for the building/s on Lot/s........ Section...... Jalan................................................... upon being satisfied that it has been completed in accordance with approved plan No. ................. dated ....................... I have supervised the erection and completion of the building/s and it is to the best of my knowledge and belief that such work/s is/are in accordance with the Act, Uniform Building By-laws 1984 and approved plans. I hereby certify that the building/s is/are safe and fit for occupation.

    (Principal submitting person)

  • Form F1 (Partial Completion)

    Q2 When can Form F1 (Partial Completion) be issued? Only when phased completion of an integrated

    development has been submitted for approval by PBT at Building Plan approval stage.

    There shall be no adhoc decision to issue Form F1, if the PSP is pressured by the developer or turnkey contractor near the project end when delay is anticipated.

    Separate Form F should be issued for each phase of a housing development or a large integrated factory project, and not Form F1.

  • UNIFORM BUILDING BY-LAWS 1984 FORM G 1

    STAGE CERTIFICATION : EARTHWORKS (By-law 25 or 27)

    Project Title: ..................................................................... *1. We certify that we have supervised and/or carried out the construction and completion of the earthworks and that to the best of our knowledge and belief such works are in accordance with the Approved Earthwork Plans Ref. No. : .. and that we accept full responsibility for the same.

    Name (Individual) #Registration No. Signature (a) Contractor ............................ ........................... .................... (CIDB) (Date: ) (b) Submitting person ............................ ........................... ..................... (BEM) (Date: )

  • OR *2. I certify that this form is not applicable.

    ..................................................... ( Principal Submitting Person )

    # I.C. No., if there is no relevant body in respect of registration * Delete whichever is not applicable

  • Form G1 - Earthworks

    Q3 For a project with multiple phases, can the SP submit only ONE (1) Form G1 for all the phases?

    Need to submit Form G1 only once under Phase 1 development. For subsequent phases, insert Phase 1 EW approval reference no. and PSP to certify Not Applicable on the respective Form G1. The project title shall be the approved BP title for each phase.

  • Form G3 -Foundations

    Q4 How is Form G3 submitted if there are different Contractors for structural elements such as piling, raft foundation, pile cap, etc?

    Submit separate Form G3s in accordance with the Contractors scope of work.

  • UNIFORM BUILDING BY-LAWS 1984

    FORM G 4 STAGE CERTIFICATION : STRUCTURAL

    (By-law 25 or 27) Project Title: ......................................................................... * We certify that we have supervised and/or carried out the erection and completion of the structural works and that to the best of our knowledge and belief such works are in accordance with the Deposited Structural Plans Ref. No. : ................................. and that we accept full responsibility for the same.

    Name (Individual) #Registration No. Signature

    (a) Contractor ............................ ........................... .................... (CIDB) (Date: ) (b) Submitting person ............................ ........................... ..................... (BEM) (Date: )

  • UNIFORM BUILDING BY-LAWS 1984 FORM G 5

    STAGE CERTIFICATION : INTERNAL WATER PLUMBING (By-law 25 or 27)

    Project Title: ................................................................... *1. We certify that we have supervised and/or carried out the erection and completion of the internal water plumbing works and that to the best of our knowledge and belief such works are in accordance with the *approved plans/Deposited Plans Ref. No. : ........................................... and that we accept full responsibility for the same. Name (Individual) #Registration No. Signature (a) Trade contractor ............................ ........................... ..................... (Licensed plumber) +( ) (Date: ) (b) Submitting Person ............................ ................................ ......................... (*BAM/BEM) (Date: )

  • FORM F CERTIFICATE OF COMPLETION AND COMPLIANCE FORM F1 PARTIAL CERTIFICATE OF COMPLETION AND

    COMPLIANCE FORM G 1 (Approved Plans) STAGE CERTIFICATION : EARTHWORKS FORM G 2 (Approved Plans) STAGE CERTIFICATION : SETTING OUT

    FORM G 3 (Deposited Plans) STAGE CERTIFICATION : FOUNDATIONS FORM G 4 (Deposited Plans) STAGE CERTIFICATION : STRUCTURAL

  • FORM G 5 (Approved/Deposited Plans) STAGE CERTIFICATION : INTERNAL WATER PLUMBING FORM G 6 (Approved/Deposited Plans) STAGE CERTIFICATION : INTERNAL SANITARY

    PLUMBING FORM G 7 (Submitting persons Endorsed Plans) STAGE CERTIFICATION : INTERNAL ELECTRICAL For small projects ST registered wireman or competent person

    can submit plans to TNB but PSP must confirm his role, registration number with ST and working presence on the Form.

    FORM G 8 (Approved/Deposited Plans) STAGE CERTIFICATION : FIRE-FIGHTING (PASSIVE) FORM G 9 (Approved/Deposited Plans) STAGE CERTIFICATION : FIRE-FIGHTING (ACTIVE) FORM G 10 (Submitting persons Endorsed Plans) STAGE CERTIFICATION : MECHANICAL VENTILATION

  • FORM G 11 (Submitting persons Endorsed Plans) STAGE CERTIFICATION : LIFT/ESCALATOR

    INSTALLATION Lift supplier PE shall not sign under SP but under Contractor. FORM G 12 (Approved Plans) STAGE CERTIFICATION : BUILDING FORM G 13 (Approved Plans) STAGE CERTIFICATION : EXTERNAL WATER SUPPLY

    SYSTEM FORM G 14 (Approved Plans) STAGE CERTIFICATION : SEWERAGE RETICULATION FORM G 15 (Approved Plans) STAGE CERTIFICATION : SEWERAGE TREATMENT

    PLANT FORM G 16 (Approved Plans) STAGE CERTIFICATION : EXTERNAL ELECTRICAL

    SUPPLY SYSTEM If work is carried out by TNB, PSP shall sign below to state this

    Form is not applicable.

  • FORM G 17 (Approved/Deposited Plans) STAGE CERTIFICATION : ROAD AND DRAIN FORM G 18 (Approved/Deposited Plans) STAGE CERTIFICATION : STREET LIGHTING FORM G 19 (Approved) STAGE CERTIFICATION : EXTERNAL MAIN DRAIN FORM G 20 (Approved/Deposited Plans) STAGE CERTIFICATION : TELECOMMUNICATION If there is no telephone infrastructure (manhole and ducting) required to provide telecommunication services to small lots, PSP to sign below to say it is not applicable. FORM G 21 (Approved) STAGE CERTIFICATION : LANDSCAPE

  • 2/13/2015

    GUIDE TO FILLING UP FORMS F & F1 (Version 1 - May 2008) Form Date Address To * Details of Building 1. PSP 2. Local

    Authority Forms G-1 to G-21

    F Insert date of CCC

    1) Insert name of Developer if it is for development other than individually built building 2) Insert name of owner for an individually built building

    1) Insert Address of Building - Lot No/Nos, Section, and Road 2) Insert description of project as per Building Plan Approval adjacent or below or in place of item 1) 3) Insert BP Approval Ref and Date 4) PSP to sign off

    1) Insert full name of PSP 2) Insert Name of ACP/ECP and address 3) Insert BAM/BEM Registration no. of PSP

    Insert Name of Local Authority

    Attach Forms G-1 to G-21 together with other required enclosures before forwarding to Local Authority and BAM/BEM

    F1 Insert date of CCC

    1) Insert name of Developer if it is for development other than individually built building 2) Insert name of owner for an individually built building

    1) Insert Address of Building - Lot No/Nos, Section, and Road 2) Insert description of project as per Building Plan Approval adjacent or below or in place of item 1) 3) Insert BP Approval Ref and Date 4) PSP to sign off

    1) Insert full name of PSP 2) Insert Name of ACP/ECP and address 3) Insert BAM/BEM Registration no. of PSP

    Insert Name of Local Authority

    Attach Forms G-1 to G-21 together with other required enclosures before forwarding to Local Authority and BAM/BEM

    Notes:

    1) PSP shall notify the local authority through OSC (in writing or using prescribed form) after Forms G1-G3 are certified (i.e. after completion of Earthwork, Setting Out and Foundations)

    2) Form F/F1 and Form G-1 to G-21 shall be forwarded to the Local Authority and BAM/BEM within 14 days of the issuance of Form F/F1

  • 2/13/2015

    GUIDE TO FILLING UP FORMS G-1 TO G-21 (Version 1 - May 2008)

    FORM Project Title Item *1 Item *1 (a) Item *1 (b) Item *1(c) Item *2

    G-1 Earthwork

    Insert description of project as per BP approval

    If this item is applicable, insert LA's Approval Ref No. If not applicable, strike out Item*1

    1) Insert name (individual) of proprietor / partner / director of Contractor's Company & attach certified copy of Company's Form 49 to authenticate this individual (Contractor) 2) Insert Contractor's NRIC 3) Contractor to sign and date 4) Attach copy of CIDB registration of Company

    1) Fill in SP's name 2) Fill in BEM registration no. 3) Sign and date 4) SP must be a Civil Engineer

    If Item *1 is applicable, strike out Item *2. If item *1 is not applicable, PSP to sign declaration

    G-2 Setting Out

    Insert description of project as per BP approval

    If this item is applicable, insert LA's Approval Ref No. If not applicable, strike out Item*1

    1) Insert name (individual) of proprietor / partner / director of Contractor's Company & attach certified copy of Company's Form 49 to authenticate this individual (Contractor) 2) Insert Contractor's NRIC 3) Contractor to sign and date 4) Attach copy of CIDB registration of Company

    1) Fill in Licensed Land Surveyor's name 2) Fill in Surveyor Board's registration no. 3) Sign and date

    1) Fill in PSP's name 2) Fill in BAM/BEM registration no. 3) Sign and date

    If Item *1 is applicable, strike out Item *2. If item *1 is not applicable, PSP to sign declaration

    G-3 Foundation

    Insert description of project as per BP approval

    If this item is applicable, insert SP's Deposited Plans Ref No. to LA. If not applicable, strike out Item*1

    1) Insert name (individual) of proprietor / partner / director of Contractor's Company & attach certified copy of Company's Form 49 to authenticate this individual (Contractor) 2) Insert Contractor's NRIC 3) Contractor to sign and date 4) Attach copy of CIDB registration of Company

    1) Fill in SP's name 2) Fill in BEM registration no. 3) Sign and date 4) SP must be a Civil Engineer

    If Item *1 is applicable, strike out Item *2. If item *1 is not applicable, PSP to sign declaration

  • 2/13/2015

    FORM Project Title Item *1 Item *1 (a) Item *1 (b) Item *1(c)

    Item *2

    G-8 Passive Fire

    Insert description of project as per BP approval

    If this item is applicable, insert Bomba's Approval Ref No. or PSP's Deposited Plans Ref No. If not applicable, strike out Item*1

    1) Insert name (individual) of proprietor / partner / director of Contractor's Company & attach certified copy of Company's Form 49 to authenticate this individual (Contractor) 2) Insert Contractor's NRIC 3) Contractor to sign and date 4) Attach copy of CIDB registration of Company

    1) Fill in PSP's name 2) Fill in BAM/BEM registration no. 3) Sign and date 4) If an engineer, PSP must be a Civil Engineer 5) Attach Letter of Clearance from Bomba (except for residential buildings not exceeding 18 meters height)

    If Item *1 is applicable, strike out Item *2. If item *1 is not applicable, PSP to sign declaration

    G-9 Active Fire

    Insert description of project as per BP approval

    If this item is applicable, insert Bomba's Approval Ref No. or PSP's Deposited Plans Ref No. If not applicable, strike out Item*1

    1) Insert name (individual) of proprietor / partner / director of Trade Contractor's company & attach certified copy of Company's Form 49 to authenticate this individual (Contractor) 2) Insert Contractor's NRIC 3) Contractor to sign and date 4) Attach copy of CIDB registration of Company

    1) Fill in SP's name 2) Fill in BEM registration no. 3) Sign and date 4) SP must be a Mechanical Engineer 5) Attach Letter of Clearance from Bomba (except for residential buildings not exceeding 18 meters height)

    If Item *1 is applicable, strike out Item *2. If item *1 is not applicable, PSP to sign declaration

  • 2/13/2015

    FAQs

    www.acem.com.my www.bem.org.my www.iem.org.my www.lam.gov.my www.pam.org.my

  • 2/13/2015

    BEM Circular No.1 (www.bem.org.my under SERVICES tab)

    Submission of Plans classified under APPENDICES A, B & C Appendix A: No person shall submit any Building Plans, reports and specifications for the underlisted works and or services, unless he is an Architect, except for any engineering works required (excluding any standard engineering works), such engineering plans and specifications shall be submitted by a Professional Engineer.

  • WHAT IS THE STATE OF CCC CERTIFICATION AFTER 7 YEARS OF

    OPERATION?

    WORKING VERY WELL AND WE HAVE MADE MANY

    DISCOVERIES!

  • CCC SUBMISSIONS As of 31.8.2014 BEM have received 2,741 CCC submissions Late Submissions: 197 Wrong Endorsements: 167 Submission not through an ECP: 134 Submission without Form G: 79 Cases investigated under IC: 13 Engineers deregistered: 1 Engineers suspended: - Engineers fined: 2 Engineers reprimanded: 3

  • Section 7A(1) of REA

    Notwithstanding section 7(1), a sole proprietorship, partnership or body corporate may practise as an Engineering consultancy practice and recover in any court any fee, charge, remuneration or other form of consideration for any professional engineering services rendered by it pursuant to its practice as an Engineering consultancy practice carried on by virtue of this section, if it is registered with the Board as an Engineering consultancy practice and has been issued with a certificate of registration.

  • 2/13/2015

    FORM SERVICE DISCIPLINE OF SIGNING SP

    G 1 Earthwork Civil Engineer

    G 2 Setting Out Licensed Surveyor or Civil Engineer*

    G 3 Foundation Civil Engineer

    G 4 Structure Civil Engineer

    G 5 Internal Water Plumbing Mechanical or Civil Engineer*

    G 6 Internal Sanitary Plumbing Mechanical or Civil Engineer*

    G 7 Internal Electrical Electrical Engineer

    G 8 Passive Fire Architect or Civil Engineer (only if PSP)

    G 9 Active Fire Mechanical Engineer

    G 10 Mechanical Ventilation Mechanical Engineer

    G 11 Lift/Escalator Mechanical or Electrical Engineer

    G 12 Building Architect or Civil Engineer (only if PSP)

  • 2/13/2015

    FORM SERVICE DISCIPLINE OF SIGNING SP

    G 13 External Water Supply Civil Engineer

    G 14 Sewerage Reticulation Civil Engineer

    G 15 Sewerage Treatment Plant Civil Engineer

    G 16 External Electrical Electrical Engineer

    G 17 Road and Drain Civil Engineer

    G 18 Street Lighting Electrical Engineer

    G 19 External Main Drain Civil Engineer

    G 20 Telecommunication Electrical Engineer

    G 21 Landscape Architect or Landscape Architect

    NOTES; 1)Signing SP must be a Professional Engineer registered with BEM in the correct discipline 2)SP must be attached to an ECP registered with BEM to practise in the correct discipline/s

  • First Case of Engineer deregistered for following reasons:-

    Failure to deposit copies of CCC to PBT and BEM.

    Allowed the building to be occupied without CCC.

    Falsified the receipt date stamp of PBT OSC for Form G13 to G21 in order to mislead the developer.

  • DISCOVERIES FROM CCC SUBMISSIONS

    Sole proprietor firms or individual PEs operating without ECPs registered with BEM.

    Use of forged PE stamp to sign Form Gs. Fraudulent engineers - names not on BEM list. Engineers signing Form Gs under wrong disciplines. Engineers still not knowing or bother to get

    information from BEM website on CCC process resulting in a lot of mistakes in their submissions.

    Engineers not responding in timely manner to BEM's notifications for explanations or clarifications.

  • FUTURE DIRECTION FOR CCC

    Once the revised Registration of Engineers Act is passed by Parliament, the Inspector of Works (IOW) will be registered by BEM.

    BEM will seek the revision of Form Gs to include another space for the SPs site supervision staff to sign for greater accountability.

  • End of Presentation

    THANK YOU

    Slide Number 1CCC FRAMEWORK Master Flow-chartWho can be the Principal Submitting Person?Duties of PSPDuties of PSPPenalties on PSP in Section 70(27) of Street, Drainage and Building ActSlide Number 8Slide Number 9FORM F FAQSlide Number 11Form F1 (Partial Completion)Slide Number 13Slide Number 14Form G1 - EarthworksForm G3 -FoundationsSlide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25FAQsBEM Circular No.1(www.bem.org.my under SERVICES tab)WHAT IS THE STATE OF CCC CERTIFICATION AFTER 7 YEARS OF OPERATION?CCC SUBMISSIONSSection 7A(1) of REASlide Number 31Slide Number 32First Case of Engineer deregistered for following reasons:-DISCOVERIES FROM CCC SUBMISSIONSFUTURE DIRECTION FOR CCCEnd of Presentation