4
34 GROUND ENGINEERING AUGUST 2007 Introduction A two-year research project, on cost-effective investigation of contaminat- ed land, aimed to demonstrate that recently developed techniques can be applied to routine commercial investigations of contaminated land to assess and improve the reliability of the measurements taken. These techniques also match the expenditure on the investigation to the specific technical and financial circumstances of that particular site. This paper aims to show how these can be easily implemented during any commercial site investigation (SI) and to highlight their benefits. Research background The measurements taken to characterise areas of potentially contaminat- ed land are important since they are one of the key initial steps in the site regeneration process. The measured values of contamination will be used to update the site conceptual model and guide the assessment of risk. Scientific considerations within an SI are usually constrained by commercial realities, however, so the financial budget restricts the number of field samples that can be taken and analysed. The measurements need to be reliable as they ultimately determine the reliability of management decisions taken. The measurements of contaminant concentration are only really estimates because there is always some level of uncertainty. To understand the concept of measurement uncertainty, imagine the measurement process of a single soil sample. A discrete mass of soil will be taken at a sampling location at a specific depth. This soil sample may be taken with the aim of representing an entire sub-area of land within a site, even though the field sample may be relatively small (<1kg). The soil sample is then sent to a laboratory where it is sub-sampled before a test portion is chemically analysed. The test portion analysed will be much smaller than the field sample (i.e. 0.001kg). Following the chemical analysis, the laboratory will report a single value of contaminant concentration for that sample. It is common for the reported value to be regarded as the “true” concentration. It is easy to imagine that if another soil sample was taken at the same nominal location and at the same depth (i.e. if the sampling process was repeated) a different value would be reported. This is mainly because of the contaminant heterogeneity present across every site and within each sampling location (Taylor et al., 2005). The variability within the laboratory procedure is another reason for the difference in reported values. Ignoring the uncertainty is difficult to justify due to the substantial financial losses that may occur, especially as remediation costs increase and the industry becomes more litigious. The important question is not “does the duplicated value differ”, but rather “how much do the values differ?” This is equivalent to asking “what is the uncertainty of each single measurement?” It has been proven that different sites produce different levels of measurement uncertainty (Taylor et al., 2005), with recorded values ranging from 30% to over 100% (Ramsey et al., 2002). Measurement uncertainty refers to individual measurements and not to the uncertainty of a number of measurements across a site or averaging area, where each individual measurement is regarded as the “true” value. For example, each individual measurement may have an uncertainty of ± 50%, within which the “true” concentration of the contaminant is found. A measured value of 100mg kg -1 with an uncertainty of ± 50% will contain the true value somewhere within the range of 50mg kg -1 and 150mg kg -1 (at the 95% confidence). The usefulness of estimating the measurement uncertainty during routine investigations of contaminated land is presented by the following case study. Case study: a comparison of two “identical” investigations of contaminated land Two separate investigations were conducted at the same site. The site covered about 27m by 30m in the south east of London, between two occupied terraced houses. The site contained two separate sub-areas of about equal size, which were used as a residential garden and an allotment. The first investigation was a routine survey conducted by a commercial consultant on behalf of the local council. The SI was repeated a few months later by the same consultancy which also applied the additional methods described below (under the supervision of the authors) to estimate and optimise the measurement uncertainty. The primary objective of both investigations was to assess the concentration of heavy metals within the soil, which was thought to comprise infill used following bomb damage sustained during the Second World War. Site investigation one The sampling strategy was wholly designed by the commercial consultancy and therefore represents a real life SI. A total of 13 window samples were removed across the site (Figure 1). Window sampling involves driving PAPER Assessing the reliability and the cost-effectiveness of routine site investigation Paul D. Taylor, Michael H. Ramsey, and Katy A. Boon, Department of Biology and Environmental Science School of Life Sciences, University of Sussex, and Joe Kelly, STConsult. 30m 22m Disused allotments Residential housing BH13* BH7* BH11 BH12 BH10 BH5 BH2 BH8 BH6* BH1* BH3 BH9 BH4 Residential housing Residential garden Residential gardens Figure 1. Schematic plan of the sampling strategy employed at the site for the two investigations. Soil samples were removed for several purposes during both investigations using window sampling equipment. The eight locations where soil samples were taken for the purpose of chemical analysis during both surveys have blue dots and are shown in bold.

PAPER - Emap.com...true value somewhere within the range of 50mg kg-1 and 150mg kg-1 (at the 95% confidence). ... sustained during the Second World War. Site investigation one

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • 34 GROUND ENGINEERING AUGUST 2007

    IntroductionA two-year research project, on cost-effective investigation of contaminat-ed land, aimed to demonstrate that recently developed techniques can be applied to routine commercial investigations of contaminated land to assess and improve the reliability of the measurements taken. These techniques also match the expenditure on the investigation to the specific technical and financial circumstances of that particular site. This paper aims to show how these can be easily implemented during any commercial site investigation (SI) and to highlight their benefits.

    Research backgroundThe measurements taken to characterise areas of potentially contaminat-ed land are important since they are one of the key initial steps in the site regeneration process. The measured values of contamination will be used to update the site conceptual model and guide the assessment of risk. Scientific considerations within an SI are usually constrained by commercial realities, however, so the financial budget restricts the number of field samples that can be taken and analysed. The measurements need to be reliable as they ultimately determine the reliability of management decisions taken.

    The measurements of contaminant concentration are only really estimates because there is always some level of uncertainty.

    To understand the concept of measurement uncertainty, imagine the measurement process of a single soil sample. A discrete mass of soil will be taken at a sampling location at a specific depth. This soil sample may be taken with the aim of representing an entire sub-area of land within a site, even though the field sample may be relatively small (

  • GROUND ENGINEERING AUGUST 2007 35

    a hollow metal tube into the ground, removing the tube and collecting a portion of soil contained within the cylinder from a specified depth, such as from the fill or natural soil beneath. Window sampling was chosen to minimise the disturbance to the site.

    All of the soil samples removed from the 13 window sample locations were inspected onsite by the commercial investigator to assess the soil characteristics. A sub-set of these soil samples (n=8 as bold in Figure 1) were selected to provide general coverage of the site and sent to a laboratory and chemically analysed for heavy metals.

    Site investigation twoThe second investigation aimed to repeat the approach taken in site investigation one, and was overseen by the commercial investigator. Soil samples were taken at the same nominal locations and depths. The samples were sent for chemical analysis by the same external laboratory using the same analytical suite of heavy metals.

    As with most investigations it was very difficult to predict the extent to which the measurements and interpretation of both would differ. This study aimed to determine the differences by repeating an investigation, but by also using the Duplicate Method to estimate measurement uncertainty.

    Applying the Duplicate Method for the estimation of measurement uncertaintyThere is a simple method that allows an investigator to assess how much the measurements will differ (i.e. estimate the measurement uncertainty) for any given SI, which is called the Duplicate Method (DM) (Figure 2).

    The first investigation of this site did not implement the DM and did not, therefore, have an estimate of the uncertainty. The second investigation applied the DM by drilling a second borehole in close proximity to the original sampling location. Sampling locations where duplicate samples were taken were randomly selected and are marked by * in Figure 1.

    The distance that separated the original and duplicate samples aimed to represent the uncertainty in relocating borehole locations. For example, duplicate samples were taken in a pseudo random direction of 1m away from the original location. Put simply, it was estimated that each sampling location could be relocated to a distance of within 1m.

    Duplicate window samples were made at four of the eight original sampling locations, with two duplicate samples taken from each. For example, two soil samples were removed for analysis at the original sampling location of BH6 at depths of 300mm and 1.2m, so the duplicate samples were also taken at these depths, but 1m away. This provided a total of eight duplicate soil samples in addition to the samples taken during the investigation.

    The eight original and eight duplicate samples were both analysed chemically twice, as part of the balanced design (Figure 2) to provide an estimate of the analytical uncertainty.

    The difference in measured concentrations between the original and duplicate samples gives an estimate of the sampling uncertainty, which is caused mainly by the heterogeneity of the soil. The analytical uncertainty is estimated by the difference in measured concentrations between the two analyses made upon the same samples. The (total) measurement uncertainty is a sum of both the sampling and analytical uncertainty.

    ResultsBoth investigations detected elevated concentrations of several heavy metals (Table 1). The uppermost layers of soil, classified by the commercial inves-tigator as topsoil fill and fill, provided the highest measured concentrations, particularly of zinc and lead with average values of 760mg kg-1 and 3204mg kg-1 respectively. Sampling location BH1 indicated particularly high concen-trations of several heavy metals, which is thought to be due to remains of bomb remnants within this sub-area of the residential garden (Table 1).

    Rather than comparing just the individual measurements between both investigations, perhaps a more useful comparison would be to compare the classifications that are made for each contaminant.

    The consultancy completed an interpretative report that presented the 95th percentile (of the mean) value of heavy metal concentration against their

    associated threshold or site specific screen value (i.e. the Soil Guideline Value or a value estimated from a site-specific risk assessment).

    The measurements taken by the commercial investigators were reported to the client in a format that separated the interpretation into the three main soil types found at the site (i.e. the topsoil fill, the fill and the natural soil). The measurements taken within each of these three horizons were interpreted as being three separate averaging areas, as described in CLR7 guidance (Department for Environment, Food & Rural Affairs, and the Environment Agency, 2002).

    To allow a comparison between the two investigations, this type of interpretation was also undertaken for the second investigation. For the purposes of this study, a comparison will be made using the measurements taken in both investigations from soil taken within the uppermost layer of material at the site, called the topsoil fill. This is the most sensitive in terms of the pathways identified within the human health risk assessment.

    Both investigations gave the same interpretation for all of the stated contaminants when comparing the 95th percentile of the mean (US95) value against their respective threshold, for example SGV, within the topsoil fill (Table 1).

    This degree of agreement is good, particularly for measurements of lead and zinc, largely because the measured values are much greater than their screen values (i.e. the site is definitely contaminated with these metals). For the other metals, however, the measured concentrations are relatively close to their threshold values, which would be expected to lead to differences in classification between the two different surveys.

    The 95th percentile of each of the nine heavy metals exceeded their threshold value at the three different soil depths – topsoil fill, fill and natural ground – and showed an 83% agreement between the two separate investigations, for example, 20 of the 24 contaminant classifications. This good agreement of interpretation was obtained despite the majority of contaminant concentrations being relatively close to their associated threshold values, which often means that a different classification is more likely. The two “identical” investigations show that although the measured values differ, as expected, the interpretations are largely unaffected.

    Estimation of measurement uncertainty for the second investigationAs discussed, the measurement uncertainty was only estimated during the second investigation at the site using the DM (Figure 2). The measurement uncertainty was generally low (ranging from ± 17% to ± 37%) (Table 2) when compared to that found in many other SIs (> ± 80%) (Ramsey et al., 2002; Taylor et al., 2005).

    The results indicate it is the field sampling, and not the chemical analysis, that generates the largest component of measurement uncertainty (i.e. >94%, Table 2). Using lead as an example, the field sampling contributed 99.9% to the measurement uncertainty with the chemical analysis only contributing 0.1%. This is usually the case in geochemical surveys because the uncertainty introduced by the contaminant heterogeneity is much larger than the variability of the laboratory analysis. This also ignores any contribution to the uncertainty from the systematic errors, such as possible sampling bias.

    It is evident that the good agreement in interpretations/classifications between the two SIs (Table 1) is caused by the relatively low levels of measurement uncertainty (U%) generated at this site (Table 2, column 2).

    The benefits of estimating the measurement uncertaintyThis study shows that there are a number of reasons why applying the MD is beneficial. It is clear that repeating a site survey will produce different meas-ured values, which could produce different management decisions. Estimat-ing the measurement uncertainty gives an indication of how much these val-ues will vary. Because the consultant involved with the first investigation of this site did not estimate the uncertainty, it was unable to identify or provide information on how reliable its measurements and interpretations were.

    The uncertainty, which was easily estimated during the second investigation, provided a quantitative indication of how repeatable the investigation was, which was substantiated when the two different

    Sampling locationAcross-site variance

    At least eight locations need to haveduplicates to give a useful estimate

    Sampling uncertainty(ssampling)

    Analytical uncertainty(sanalytical)

    Sample 1

    Analysis 1 Analysis 2

    Sample 2 (duplicate)

    Analysis 1 Analysis 2

    Figure 2. Illustration of the Duplicate Method (DM). The measurement uncertainty (i.e. generated by both the field sampling and chemical analysis) is estimated by appying the DM, which requires duplicate samples to be taken and analysed in duplicate.

    p34-37paperGE.indd 35 20/7/07 15:29:26

  • 36 GROUND ENGINEERING AUGUST 2007

    investigations were compared. This type of information could be very useful to regulators, landowners and insurance companies who may be interested in the reliability of an SI. Also, reporting the estimates of measurement uncertainty could also be useful when the site redevelopment and/or additional investigations are done by different organisations.

    The DM also indicates where the largest part of uncertainty is being generated. If the field sampling is the main cause, then the sampling may be modified in future investigations to reduce its effect, by, for example, taking composite samples.

    This modification of the sampling procedure to reduce uncertainty has successfully been achieved during a supplementary investigation at a different site used during this research project. Expenditure may also be allocated more optimally between the field sampling and chemical analysis to provide more acceptable levels of uncertainty.

    To reduce the costs of applying the DM, the investigator could decide against measuring analytical duplicates, an approach that has also been successfully applied during this research project, at a low value site. While this substantially reduces the extra costs necessary, it means measurement uncertainty cannot be separated into its two components of analytical and sampling uncertainty, unless estimates of analytical uncertainty are provided by the laboratory. In addition, the measurements taken from analytical duplicates can be used to assess whether the laboratory measurements comply with the precision targets set in the Monitoring Certification Scheme (Environment Agency, 2006).

    Estimating the financial implications of measurement uncertaintyEstimating the uncertainty also allows the investigator to assess the financial risk of the investigation using the Optimised Contaminated Land Investiga-tion (OCLI) method (Ramsey et al., 2002). This decision support tool can provide an objective assessment on whether the level of uncertainty pro-duces an unacceptable financial risk for any given site.

    As an example, the OCLI method has been applied to the SI discussed here. OCLI uses information on the actual level of measurement uncertainty, the costs of field sampling and laboratory analysis, and the financial consequences of misclassifying the site. The worst case scenario of litigation

    is used in this application of the method, with a particularly high penalty estimated at £1M. Further applications of the method may apply to other decision-error scenarios, such as the costs of unnecessarily remediating areas of land, erroneously classified as contaminated because of the uncertainty.

    The OCLI curve (Figure 3) shows a range of different possible values for measurement uncertainty, one of which was estimated during the SI (actual uncertainty = 200mg kg-1 Pb). Each uncertainty value has a corresponding expected financial loss (£). High levels of uncertainty are shown to cause high financial losses, due to the resultant misclassification of the land. A reduction in uncertainty requires an increase in measurement expenditure however.

    The judgment on whether the actual uncertainty is acceptable is made by comparing the actual uncertainty estimated during the SI against the uncertainty that provides the lowest possible loss, known as the optimal. A

    PAPER

    Contaminant

    Measurement uncertainty

    (U%)

    Proportion of U% from the laboratory analysis

    Proportion of U% from the

    field sampling

    Arsenic 23 1.5 98.5

    Chromium 17 1.5 98.5

    Nickel 24 6.1 93.9

    Lead 25 0.1 99.9

    Mercury 25 0.6 99.4

    Zinc 37 0.2 99.8

    Copper 19 0.3 99.7

    Table 2. Estimates of uncertainty from measurements estimated using the DM. The levels of measurement uncertainty are quite low (±17% to ±37%), compared with studies at other contaminated sites. The measurement uncertainty is generated mainly by the field sampling and not from the chemical analysis.

    Topsoil fillFirst Investigation at Site 3 by the commercial investigator

    Location depth As Cd Cr Cu Pb Hg Ni Se Zn

    BH1 100mm 45 2.4 70 234 15042 4.3 33

  • GROUND ENGINEERING AUGUST 2007 37

    more detailed explanation of the OCLI methodology can be found elsewhere (Ramsey et al., 2002).

    An initial inspection of the OCLI curve (Figure 3) suggests the measurement uncertainty for lead (Pb) is not acceptable. This is because of the large difference (a factor of 2.5) between the actual uncertainty estimated during the investigation (200mg kg-1) and the optimal value given by the OCLI method (497mg kg-1). However, a closer inspection indicates the uncertainty is really acceptable given the relatively small difference in expected loss between optimal and actual values (£11 and £62 respectively). Often, the difference can be substantial, >£10,000 (Boon et al., 2007).

    Interestingly, the actual uncertainty value is positioned to the left of the optimal value on the OCLI curve (Figure 3). This means the measurement uncertainty could actually be increased (i.e. have less precise measurements) to reach the optimal level. The OCLI method has again provided an objective assessment showing a much less precise, but more rapid and less expensive measurement strategy could be used for any supplementary surveys or at similar sites – such as in-situ Portable X-ray Fluorescence Spectrometry (Taylor et al., 2004).

    ConclusionsThe two nominally identical investigations, conducted at the same site, both showed elevated concentrations of heavy metals within the soil, particularly lead and zinc. There was an 83% agreement of the 24 classifications made in each of the two investigations (i.e. whether the US95 value exceeded the threshold/screen value).

    The measurement uncertainty was estimated during the second investigation at the site using the DM, with marginal extra expense. The measurement uncertainty values found were relatively low ranging from only ±17% to ±37%.

    The good agreement in measured concentrations between both investigations, as well as the agreement in interpretation, is consistent with what would be expected from such low values of measurement uncertainty.

    The comparison proves that estimating the uncertainty, which is easily and relatively inexpensive to achieve, gives an indication of how repeatable, and thus reliable, an SI actually is. The estimates of measurement uncertainty could be used to demonstrate to a client or regulator that the investigation was subject to extra quality assurance procedures that increased the validity and quality of the decisions made in the subsequent report.

    The estimates of measurement uncertainty can also be used to assess the likely financial loss that may arise due to misclassification. For the example used here, the OCLI method showed a low value of loss (for example, only about £60 per location) that can be used to indicate to the investigator, and to the client, that the measurements are of acceptable quality, despite a particularly high potential consequence cost of £1M.

    Applying the OCLI method to other SIs may show a likelihood of substantial losses, however, which can be used to guide the subsequent decisions taken and to design more suitable sampling strategies at that or similar sites.

    The method has also been successfully applied to five other commercial investigations at contrasting sites, conducted by different consultants. The research has demonstrated that the scientific methods used to estimate the measurement uncertainty (DM) can be easily implemented at all sites to improve the reliability of routine commercial SIs.

    The uncertainty can be estimated for different sampling methods, such as trial pits, window sampling and hand augering. An OCLI package was also successfully trialed with a commercial laboratory (ALcontrol) for one of the investigations used during this project. This allows the investigator to easily select a small proportion of samples to be analysed in duplicate as part of the DM, which are then reported in a user friendly format.

    Observing how the consultancies conduct their investigations showed the very different ways in which field samples are collected, even when using

    the same method (for example, trial pits). The sampling technique can vary greatly between different companies and individual samplers. Often, junior, member of staff are asked to complete important field sampling, sometimes without adequate training.

    Experimental studies have repeatedly shown that uncertainty from the field sampling is often substantially greater than the contribution from the laboratory analysis (Ramsey and Argyraki, 1997; Ramsey et al., 2002). Currently, attention of measurement quality is usually confined to the chemical analysis alone, but this finding suggests that the focus should now move to field sampling. It is worth remembering that a measurement is only as good as the sample upon which it is made.

    One barrier to implementing methods for estimating measurement uncertainty is the extra costs that may be required. Collaborating with other commercial organisations during this research has shown that sample duplicates are often routinely taken during their investigations, as directed by the British Standard guidance (BSI, 2001).

    On larger projects, different consultancies are occasionally contracted to validate the main surveys by taking a small selection of additional samples for comparison, such as one sample for every 20 taken. But in these cases, the comparison in measured concentrations found between the sample duplicates are only used as qualitative indications of data reliability. This information is better employed by using statistical software – available for free from the University of Sussex – that provides a quantitative estimate of the measurement uncertainty (as shown in this case study).

    The small extra cost of applying the DM, which is required to estimate the measurement uncertainty, was shown to be cost-effective in producing overall savings of £18,000 at one site and £14,300 at another.

    The levels of measurement uncertainty can also vary greatly between sites. In the six assessed, the measurement uncertainty varied from ± 25% for lead concentrations at one site and ± 158% for arsenic at another. Using the OCLI method before a supplementary site survey (site six) was shown to substantially reduce (by 76%) the expected loss from £21,000 to £5,500 per sampling location.

    Applying the OCLI method before completing a supplementary survey was shown to be particularly beneficial for the investigation at site six. The more optimal level of measurement uncertainty achieved during the supplementary survey, as identified and designed using the OCLI method, was shown to reduce potential losses by £558,000 at one site.

    The OCLI method has been proven to be a commercially valuable decision-support tool, as it is able to estimate the probable financial cost that may arise from the uncertainty in measurements. The information provided by these methods are useful to a range of stakeholders associated with the management of contaminated land. It is argued that they can be developed further, and be adopted more widely, during routine investigations of contaminated land.

    AcknowledgementsThis research was completed as part of the research project Cost-Effective Investigation of Contaminated Land, funded jointly by CL:AIRE (Research Project RP4), and DTI (Contract number STBF/004/00034C).

    The full project report will shortly be available through CL:AIRE (Contaminated Land: Applications in the Real Environment).

    References1. K.A., Boon, P.D. Taylor, M.H. Ramsey (2007). Estimating and optimising measurement uncertainty in environmental monitoring: an example using six contrasting contaminated land investigations. Geostandards and Geoanalytical Research, (In press).2. BSI (2001). Investigation of potentially contaminated sites – Code of Practice (BS 10175:2001), British Standards Institute, pp. 75.3. Department for Environment, Food & Rural Affairs, and Environment Agency (2002). Assessment of risks to human health from land contamination: An overview of the development of soil guideline values and related research (CLR 7). DEFRA, and EA, pp. 32.EA (Environment Agency) (2006). 4. Performance standard for laboratories undertaking chemical testing of soil (MCERTs – Version 3), Environment Agency, Bristol, pp. 15.5 M.H. Ramsey, A. Argyraki (1997). Estimation of measurement uncertainty from field sampling: Implications for the classification of contaminated land. Science of the Total Environment, vol. 198, pp. 243-257.6. M.H. Ramsey, P.D. Taylor, and J.C. Lee (2002). Optimized contaminated land investigation at minimum overall cost to achieve fitness-for-purpose, Journal of Environmental Monitoring, vol. 4, pp. 809-814.7. P.D. Taylor, M.H. Ramsey, P.J. Potts P. J. (2004). Balancing measurement uncertainty against financial benefits: Comparison of in situ and ex situ analysis of contaminated land. Environmental Science & Technology, vol. 38, pp. 6824-6831.8. P.D. Taylor, M.H. Ramsey, P.J. Potts (2005). Spatial contaminant heterogeneity: quantification with scale of measurement at contrasting sites. Journal of Environmental Monitoring, vol. 7, pp. 1364-1370.

    Measurement uncertainty (smeas) (mg kg-1 Pb)

    Expe

    cted

    loss

    (£)

    0

    20

    40

    60

    80

    100

    0 100 200 300 400 500 600 700

    Optimal uncertainty497mg kg-1 Pb

    Actual uncertainty200mg kg-1 Pb

    Figure 3. The OCLI curve for the investigation at the residential garden and allotment.

    p34-37paperGE.indd 37 20/7/07 15:29:59