PAPERTECH 2010 SPB Presentation 5 June2010

  • Upload
    veerudu

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    1/23

    ADVANCESINPOWERENHANCEMENTINCOGENBATTERY

    INSESHASAYEEPAPERMILL

    DrT.G.Sundara Raman

    Seshasayee Paper & Boards Ltd.

    PAPER TECH 2010

    CII

    Hyderabad

    16 June 20101

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    2/23

    InternationalpracticeinrunningSteamturbogenerator

    [STG]battery

    GENERAL

    RunSTGofhighercycleefficiencyatincreasedloadsand

    yetmeeting

    the

    process

    steam

    demands

    OtherSTGsatlowerloadsthusactingasslave

    ChemicalRecoveryBoiler[CRB]&CoalfiredBoiler[CFB]

    Cogen units

    RunCRB

    Cogen with

    black

    liquor

    solids

    as

    fuel

    CFBCogen shallcaterto balanceload

    2

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    3/23

    HPCOGENBATTERYINPREMIERPAPERMILLS

    Mill CFB(kg/cm) CRB(kg/cm)

    APPM 64 64

    ITC 64 64

    JK* 88/106 64/88

    SPB 106 65

    WCPM 64 64

    TNPL

    * : Planned

    64 64

    3

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    4/23

    Existing HPCogen Scenerio inSPB

    CaptivePowerPlant[CPP1]

    Boiler#10

    [106

    kg/cm /510C

    AFBC

    ]&

    21MWDoubleextractioncondensingsteamturbo

    generator

    CaptivePowerPlant[CPP2]

    Boiler#11

    [65

    kg/cm /465C

    CRB]

    &

    16MWExtractionbackpressuresteamturbogenerator

    4

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    5/23

    SPECIFICATIONS OF THE 2 HP COGEN UNITSCPP Chem ic al Rec over y Cogen

    Boiler #10 Parameter Boiler #11

    AFBC Boiler Type Chemical Recovery Boiler

    117 TPHRat ed St eam

    Evaporat ion83TPH(Phase1) I140TPH(Phase2)

    106 kg/cm SOP 65 kg/cm

    510C SOT 465

    C

    135C Feed in le t t empera tur e 135C

    Imported coalFuel

    Black liquor

    @ 70% solids concn.

    21 MW- DEC STG 16 MW- EBP

    10.5/4.0 kg/cm E1/E2 10.5/4.5 kg/cm

    0.09 ata Condensing --

    20.4 MW Capac i ty 10MW(Phase1) / 16 MW(Phase2)5

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    6/23

    Boiler#10 CFB&

    Boiler#11 CRB

    STEAMINGCONDITIONS

    Parameter Blr #10 Blr #11

    Fuel ImportedCoal BlackLiquorSolids

    SteamEvaporation

    TPH 117 80/130

    [Ph1/Ph2]

    SteamPressure(kg/cm2) 106 65

    SteamTemperatureC 510 465

    FeedWaterTemperatureC 135 135

    6

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    7/23

    OPERATING LOADS

    Boiler10operatingateconomic load(85%)withImported

    coalas

    fuel

    Boiler11designedforPhase1(60%)&

    Phase 2(100%)operationwithBlack

    liquor solidsfiringinCRB

    7

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    8/23

    TurbineExtractionExhaust SteamRange

    ZONE 21MWSTG 16MWSTG

    E1[MP] 030TPH 060TPH

    E2[LP] 060TPH 30130TPH

    Condensing 2550

    TPH X

    8

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    9/23

    ENERGYDISTRIBUTIONACROSS16MWSTG

    9

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    10/23

    .

    .

    10

    POST MDP [PHASE I] FLOW CHART

    31 tph

    22 tph

    42 tph

    Falling FilmEvaporator

    8.7 MW

    EB P16M W STG

    73 tph

    95 tph

    DEC21M W STG

    15.6 MW

    0.1 MW

    Weak Black Liquor fromPulp Mill

    Strong BlackLiquor 70%

    Concentration

    Total Power : 24.4 MW

    B#11 CRB65 kg/cm2

    CW

    65 tph

    8 tph

    586 tpd

    AFBC#10106 kg/cm2

    CPP/CFB

    GRIDIMPORT

    11 kg/cm2

    Steam Header

    To ProcessStation

    Consumption

    4 kg/cm2

    Steam Header

    To ProcessStationConsumption

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    11/23

    PHILOSOPHY

    16MW

    STG

    is

    designed

    for

    both

    the

    phases

    of

    operating

    loads(60%to100%)

    Henceextractionstage(nozzle)isdesignedbyBHELtocommensuratewithratedsteamingconditionsatthe

    headerfor

    Process(11

    kg/cm2)

    Obviouslyat

    lower

    loads

    of

    operation,

    higher

    turbine

    nozzlesteamtemperaturesareunavoidable

    11

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    12/23

    .

    0

    50

    100

    150

    200

    250

    300

    350

    400

    0 5 10 15 20 25 30 35 40 45

    T

    emp(Degc)

    E1(TPH)

    16MWSTGE1flowVsNozzle steamtemperature

    Tnoz

    Tsat

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    13/23

    .

    0

    5

    10

    15

    20

    25

    30

    0 5 10 15 20 25 30 35 40 45

    H(Kcal/Kg)

    E1(TPH)

    16MWSTGE1flowVsEnthalpydifferential

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    14/23

    .

    0

    50

    100

    150

    200

    250

    0 20 40 60 80 100 120 140

    Te

    mp(DegC)

    E2(TPH)

    16MWSTGE2flowVsNozzlesteamtemperature

    Tnoz

    Tsat

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    15/23

    .

    0

    2

    4

    6

    8

    10

    12

    14

    16

    0 20 40 60 80 100 120 140

    h(Kcal/Kg)

    E2(TPH)

    16MWSTGE2flowVsEnthalpydifferential

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    16/23

    AvailableEnergyforConversionfromThermal

    16MWSteamturbogenerator

    1.5MW

    (th)

    each

    from

    turbine

    nozzles

    of

    both

    E1

    &

    E2

    upto saturationareavailable

    Equivalent

    to

    15to

    20

    %

    of

    total

    energy

    through

    reduction

    ofsteamtemperaturethroughdesuperheating alone.

    16

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    17/23

    RECOMMENDATIONS

    Splitting E1(M.P.steamextraction)flowsbetweenthe2steamturbinestobeminimized.

    EnsureentireE1flowthroughoneofthe2STGs

    AccordinglysplitE2(L.P.steamextraction)flowbetweenthe 2steamturbines

    Maximizecombinedcycleefficiencyinpowerwitheitherof

    theturbines

    acting

    as

    slave.

    17

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    18/23

    POWERGENERATIONENHANCEMENTSCHEME[PES]ThroughshiftingofE1flowstooneSTG(insteadofsplittingofflows)

    Extraction

    Steam

    flows

    Actual

    &

    Potential

    [TPH]1of2

    SPB Actual Potential16MW 21MW 16MW 21MW

    2010 E1 E1 E1 E2 E1 E2 C

    March 13 15.7 28.7 41.8 0 53 37

    April 13.7 14.9 28.6 45.6 0 49 38

    18

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    19/23

    Powergenerationenhancement(estimated)

    2of2

    SPB

    BothTG

    inopern

    E1

    Addl.Power

    estimated

    E1S

    reduction

    estimated2010 hrs TPH MW Lakh

    units

    TPH TPM

    March 694 28.7 0.31 2.2 0.44 300

    April 636 28.6 0.31 2.0 0.43 275

    19

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    20/23

    GainsfromPowerenhancementscheme

    Higherelectricalpowergenerationwithloweringof

    extraction(E1)steam

    temperature

    at

    turbine

    nozzle

    Equivalent to 0.3MW onacontinuousbasis.

    Reductionin

    spray

    quantity

    required

    for

    desuperheating

    ensuresbettersteamqualityforprocessuse.

    XCounteracted

    by

    marginal

    reduction

    in

    LP

    steam

    generation

    throughdesuperheating

    20

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    21/23

    ContributiontoPowerenhancementby

    Energyefficientmainsteampipeline

    Recommendedtogoinforhighlevelpipeline

    insulation

    for

    a

    design

    temperature

    drop

    across

    main

    steamlineconnectingboilertosteamturbinefrom

    8Cto 4C.

    Throughtheaboveschemeinplace,powergenerationincrementof0.3MWshallbeensured

    forthe

    case

    under

    study

    during

    Phase

    1operation.

    21

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    22/23

    CONCLUSIONS&WAYFORWARD

    Recommended for all Paper mills having HP Cogen Battery togo in for PES to suit process needs

    Automation of the whole turbine energy cycle with

    extraction flow limits in place is advocated

    Temperature drop from Boiler main steam outlet to turbineinlet should be minimal (

  • 8/8/2019 PAPERTECH 2010 SPB Presentation 5 June2010

    23/23

    .

    23

    .

    Conserve

    Energy

    Green the

    Mother

    Earth