part 2 section 2

Embed Size (px)

Citation preview

  • 7/25/2019 part 2 section 2

    1/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 1

    PART TWO: CONSTRUCTION DESIGN & ECONOMICS

    SECTION 2: LIFE CYCLE COSTING

    Introduction

    It is becoming increasingly important that investment appraisal uses a whole

    life approach in a more systematic way than at present. Major construction

    clients are now insisting upon an analysis of life cycle costs and not just

    capital costs.

    The life cycle cost (LCC) of an asset is defined as the present value of the total

    cost of that asset over its operating life (including initial capital cost,

    occupation costs, operating costs and the cost or benefit of the eventual

    disposal of the asset at the end of its life).

    Life cycle cost techniques can be used, for example, to:

    evaluate design options at the elemental or component level;

    evaluate total building options, for example refurbishment versus new

    build;

    determine optimum maintenance strategies;

    analyse relocation strategies; and

    determine sinking fund requirements to finance planned maintenance

    programmes.

    Worked examples for the above are included in 2.2.5.

    The objective of this Section is to inform chartered surveyors of the increasing

    need to adopt life cycle costing (2.2.1) and to introduce them to the techniques

    and their application.

    2.2.1 The Client Context

    2.2.1.1 Following the recession of the early 1990s construction clients are generally

    more streamlined and competitive and some recognise that their ongoing

    property costs may provide them with the business edge they need. There is

    therefore increased attention to life cycle costing. The following Sub-sections

    expand on this trend by covering recent changes in the industry and their

    effect on LCC.

    2.2.1.2 VALUEENGINEERING

    Value engineering involves preparing structured option appraisals during the

    design process so demonstrating value for money for clients. Its use is

    I

  • 7/25/2019 part 2 section 2

    2/58

    PART2, SECTION2

    Page 2 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    increasing and with it comes the opportunity and need for LCC to be part of

    the options appraisal criteria.

    2.2.1.3 THE

    LATHAM

    REPORT

    Sir Michael Lathams report Constructing the Team1, calls for a 30% real

    reduction in construction costs. This statement includes life cycle costs. The

    report also strongly advocates the need to build right first time in which

    environment life cycle cost calculations (involving assumptions about future

    maintenance) have more credibility.

    2.2.1.4 CONSTRUCTION(DESIGN ANDMANAGEMENT) REGULATIONS1994

    The Construction (Design and Management) Regulations 1994 place a

    specific duty upon clients and their designers to consider the potential hazards

    associated with the construction process during design, and furthermore to

    consider the health and safety implications of maintaining the structure whencomplete. Such increased focus on maintenance may therefore encourage

    greater consideration of maintenance costs. This principle is enshrined in

    Regulation 13(2)(a)(i) and (ii) which states:

    (2) Every designer shall:

    (a) ensure that any design he prepares and which he is aware will be

    used for the purposes of construction work includes among the

    design considerations adequate regard to the need:

    (i) to avoid foreseeable risks to the health and safety of any

    person at work carrying out construction work or

    cleaning work in or on the structure at any time, or of

    any person who may be affected by the work of such a

    person at work,

    (ii) to combat at source risks to the health and safety of any

    person at work carrying out construction work or

    cleaning work in or on the structure at any time, or of

    any person who may be affected by the work of such a

    person at work.

    It follows that the selection of materials for certain elements of a structure that

    may involve maintenance, (particularly where access to those elements

    involves working at height), complies with the spirit of Regulation 13. For

    example, the selection of PVCu window frames with easy clean hinges

    involves limited maintenance and allows cleaning from the inside. Similarly

    marble flooring is cheaper than cork tiles over a 60-year period and while the

    decision to use marble is economically sound it also removes health hazards

    1 Latham, M., Sir, (1994),Constructing the Team: Joint Review of Procurement and Contractual

    Arrangements in the United Kingdom Construction Industry: Final Report, HMSO London

  • 7/25/2019 part 2 section 2

    3/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 3

    associated with fumes and vapour when cork has to be resealed. In purely

    capital cost terms, the selection of the materials referred to above may be more

    expensive than their traditional counterparts.

    The use of life cycle costing places initial capital cost in the context of future

    maintenance expenditure, and helps justify decisions which have beneficial

    health and safety implications.

    2.2.1.5 THEPRIVATEFINANCEINITIATIVE(PFI)

    The PFI is driven by a cash flow which is achieved by the private sector

    provider delivering a service to the client. This service will include the

    management of a building which should be heated, cooled, lighted, cleaned,

    maintained, secured, insured and renovated. This cash flow should

    sufficiently cover all costs and outgoings, leaving the provider with a surplus

    or profit which should be commensurate with his risk exposure.

    It is therefore critical that the provider accurately predicts the cost in use of the

    service or the facility over its operational life so that he can calculate the cash

    flows generated by the assets over the term of the contract. Such data is vital

    so as to negotiate the complexities of the contract to both parties satisfaction.

    To assist this process some suppliers give guaranteed long-term costs, e.g. for

    lifts and kitchen equipment. By reducing costs over this term it should be

    financially viable for the private sector to provide a service to the public sector

    and to achieve an acceptable return.

    Life cycle costs and their accurate prediction, control and reduction are critical

    to the successful performance of a PFI deal.

    2.2.1. ENERGYEFFICIENCYISSUES INRELATION TOBUILDINGPROJECTS

    Studies by the Building Research Establishment through the BRECSU

    (Building Research Energy Conservation Support Unit) Best Practice

    Programme have found that energy consumed to heat, light and service

    buildings accounts for almost half of the UKs energy bill, and there is

    considerable scope to reduce it. Office buildings were found to have the

    highest energy costs, especially prestigious, air conditioned property

    (typically 20/m2

    per year in 1991 compared to 15/m2

    for the same bestpractice office).

    There is common feeling that property overheads are too large, with energy

    bills contributing significantly to the operating costs. Energy costs are

    potentially one of the most controllable items of overheads and life cycle

    costing can be used as a tool for predicting the benefits of investment in

    energy efficiency. Typical investments for analysis would be economic

    thickness of insulation, energy efficient services, building energy

    management system installations, intelligent buildings, energy conscious

    refurbishment of buildings and passive cooling techniques versus air

    conditioned design. For example, a manufacturer can supply a light bulb some

    ten times more expensive than a normal one, however, it lasts longer, uses less

  • 7/25/2019 part 2 section 2

    4/58

    PART2, SECTION2

    Page 4 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    electricity and performs better. Similarly, condensing gas boilers can save

    1020% of fossil fuel bills with pay back in five years.

    It is also worth noting that oil is becoming increasingly harder to extract and

    environmental concerns generally will increase in the very near future.

    Sainsbury has been the first grocery retailer to produce an environmental

    report and recognises that energy probably accounts for its single biggest

    direct environmental impact. Significantly it is also the third largest

    controllable cost in running a typical supermarket.

    2.2.1.7 MECHANICAL ANDELECTRICALBUILDINGSERVICES

    The increasing capital cost significance and complexity of M & E services has

    resulted in greater cost emphasis during the early design stages. Such costing

    is increasingly carried out by a specialist Quantity Surveyor so bringing

    greater opportunity to focus on M & E life cycle costs which are a significant

    proportion of a buildings cost in use, accounted for by the operation, energy

    use and replacement costs associated with the M & E installations.

    2.2.1.8 BUILDINGSUSTAINABILITY

    If there is to be a conscious shift of opinion towards sustainable buildings i.e.

    those which have a viable life expectancy beyond their initial designed use,

    then there has to be a simultaneous re-examination of a buildings costs in use

    or perhaps more correctly costs in uses.

    Buildings have not been traditionally designed for anything beyond theirimmediate requirement. However, as more are being converted to alternative

    uses it is probably only a matter of time before investors in property call for

    properties to be constructed with a view to extending the buildings usable

    life, e.g. conversion to house a growing less mobile and aged population. Such

    consideration is more valid the shorter the predicted current building life, e.g.

    some light industrial units for English Partnerships have been designed for a

    ten-year life. Similarly, Hertfordshire County Council have housing and

    nursing homes with a 20-year life expectancy.

    Such a concept will require building layouts and structures to be more flexiblewith maintenance, re-servicing and conversion to alternative uses being

    simplified and made more economical. A cost in use study at design stage may

    justify larger bay sizes, raised flooring or greater storey heights to demonstrate

    continual viability for future generations.

    A cost in use study would explore the economics involved of using a building

    for its notional design life and for its intended use in the usual way. However,

    supplementary investigations would explore potential alternative uses for the

    building and the conversion cost (and possibly the cost in use for a further

    notional period). If sufficient consideration were to be given at the initial

    design stage for potential future uses of a building, it could be used to

    demonstrate the continued asset value of the property and go a considerable

  • 7/25/2019 part 2 section 2

    5/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 5

    way to minimising the obsolescent properties which currently dominate

    certain market sectors.

    2.2.2 The Life Cycle Costing Calculation

    INTRODUCTION

    The calculation generally involves the appraisal of options, each option

    having different capital and future costs. To determine and analyse the future

    costs it is necessary to establish:

    the building life;

    the discount rate (which, expressed simply, is the difference between the

    interest and inflation rate and is used to convert future payments to

    present values);

    the cost and frequency of future payments (at the component, elemental

    or total building level as appropriate);

    any tax implications (see 2.2.3).

    2.2.2.1 THEBUILDINGLIFE

    An essential element of life cycle costing is defining the life cycle period to be

    adopted. An assessment must therefore be made of the life of the investment

    building life.

    Typically the relevant building life will be the period over which theorganisation, for whom the study is being conducted, will be expected to hold

    an interest in the building, and would take into account the residual value.

    At the end of the life of a building, the building (or component) and the land

    will have a residual value. In the case of relatively short life cycles or high

    value land, residual values can be very significant factors in determining the

    optimum life cycle cost options. Residual values are briefly discussed in

    Appendix A (and worked example 2.2.5.3 includes a residual value in the

    calculation).

    When the building life is assessed to be over 40 years, the precise life is notcritical for the purposes of life cycle costing (as discounting, explained below,

    minimises the effect of such future payments). In cases where calculations are

    based on a relatively short building life, say 20 years or less, the assessment of

    the time horizons must be considered with special care.

    Building life is influenced by obsolescence, the causes of which are

    summarised in Appendix B.

    2.2.2.2 THEDISCOUNTRATE

    The life cycle cost technique is concerned with the assessment of the time

    stream of costs and revenues that will flow throughout the life of a

    construction project option.

  • 7/25/2019 part 2 section 2

    6/58

    PART2, SECTION2

    Page 6 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    As money today has a different value from money tomorrow or money in

    ten years time, a technique has to be adopted that will express future costs or

    revenues in present values. The process of converting future money to

    present money is called discounting.

    Discounting involves establishing the discount rate to be used. In making the

    decision on a discount rate for a particular project, some judgement will need

    to be made about the degree of risk return (interest) and the likely levels of

    future inflation rates.

    Interest rates are particular to the client and the degree of risk. It is therefore

    essential to involve the client (and his accountant if appropriate) in the process

    and reach agreement on the discount rate to be used.

    Economists, accountants and clients will all have different views about future

    levels of inflation and interest rates. Some forecasters may take the view that

    as different categories of cost inflate at different rates, these differences

    should be taken into account in setting discount rates. These diversities of

    view before the fact make it difficult to recommend any firm guidelines for

    surveyors to adopt for selecting discount rates.

    There are two main approaches to discounting:

    (a) use a rate which implies inflation of future costs and values (in this case

    future costs and values will be priced at todays prices);

    (b) use a rate which requires an explicit treatment of inflation in relation to

    future costs and values, (in this case future costs and values will be priced at

    todays prices and adjusted by a factor to reflect future inflation).

    It is suggested that it is easier to deal with the former situation where future

    costs and values are assessed at current prices. Three approaches on the

    selection of discount rates are given for guidance purposes and in each the

    future costs are priced at current prices.

    2.2.2.3 DISCOUNTRATEMETHODS

    (a) Test Discount Rate

    In the absence of better information it is recommended that a test discount rate

    should be used.

    This recommendation is based on the assumption that when inflation rates are

    reasonably low, i.e. less than 15%, there is quite a stable relationship between

    inflation and the bank base interest rate, implying a real discount rate of

    between 4% and 5% (i.e. the interest rate is 4 to 5% greater than inflation). It

    is recommended that in the circumstances, where no better information is

  • 7/25/2019 part 2 section 2

    7/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 7

    available, a test discount rate of 4% is used. This method is often adopted in

    the public sector where minimal risk associated with the investment is

    assumed.

    (b) No risk return discount rate

    Investment in long-term Treasury Bonds can be assumed as having no risk,

    and are a good reflection of the return to be expected on other investments

    where there is no risk. Therefore the discount rate can be taken as the Treasury

    Bond rate less an allowance for the expected rate of inflation. On this basis the

    discount rate would be assessed as:

    Treasury Bond rate of return 8%

    Less

    Inflation 5%

    No risk return discount rate 3%

    (c) Average risk premium discount rate

    The average return on equities reflects the interest required on an average risk.

    The excess of this rate of return over that expected from the above Treasury

    Bonds can then be taken as the premium expected for the average risk. On this

    basis the average risk premium could therefore be calculated as:

    Average equity rate return 16%

    LessTreasury Bond rate 8%

    Average risk premium discount rate 8%

    Therefore if construction is deemed to be half as risky as equities, the discount

    rate for construction investment could be assessed as:

    No risk return 3%

    Construction premium risk (8% ) 4%

    Average construction risk return discount rate 7%

    (d) A further approach to establishing a discount rate is to analyse transactions

    involving the sale of comparable properties, and to utilise the all risks yield

    as the discount rate.

    In the examples of the calculation of discount rates, concurrent interest and

    inflation rates have been added and subtracted in order to clarify the

    methodology. This is mathematically imprecise. The actual calculation will

    need to be compounded.

  • 7/25/2019 part 2 section 2

    8/58

    PART2, SECTION2

    Page 8 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    In the no risk return discount rate method, for example, the calculation

    should be as follows:

    Treasury Bond rate of return 8%Inflation rate 5%

    Discount rate (i.e. Treasury Bond rate net of inflation

    = 0.02857

    = 2.857%

    The same methodology should be adopted for actual calculations using other

    methods. As an approximation however this may be ignored.

    (e) In summary, the effect of future payments on an LCC calculation is in

    inverse proportion to the level of discount rates i.e. the higher the discount rate

    the less effect future payments have on the LCC calculation. For example, a

    risk taking client is less likely to spend money on the building to reduce future

    costs since he can use this money to get a higher return elsewhere.

    Selection of a suitable discount rate is crucial as it can overwhelm all other

    decisions.

    Once the discount rate is established valuation tables can be used to convert

    future payments to present value. For example, the present value of 100 to be

    paid in five years time at a discount rate of 4% =

    100 0.82192 (from valuation tables at 2.2.5.7 present value of 1) =82.19

    Such conversion of future payments to present value provides a basis for

    comparing alternative expenditures.

    2.2.2.4 THECOST ANDFREQUENCY OFFUTUREPAYMENTS

    The costs are generally dealt with using current prices (using the discount rate

    to allow for inflation), with assumptions made regarding when payments will

    occur in the future. 2.2.4 includes possible sources for such data.

    Depending upon requirements, some calculations will be relatively

    straightforward (see the option appraisal exercise for internal doors as shown

    (1 = Treasury Bond rate)= 1

    (1 + Inflation rate)

    1.08= 1

    1.05

  • 7/25/2019 part 2 section 2

    9/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 9

    in the worked examples). However, all expenditure throughout the life of the

    building could be included if the total building analysis were required.

    The major categories of costs are: capital costs

    financing costs

    operation costs

    annual maintenance costs

    intermittent maintenance, replacement and alterations costs

    occupancy costs

    residual values and disposal costs.

    An expanded check list of costs is given in Appendix C.

    Estimates for these costs will be based upon assumptions about future events

    and should be clearly stated. Indeed an additional advantage of life cycle

    costing is that it requires design assumptions to be stated explicitly rather than

    implied.

    Although current costs are generally used, it is important that future cost

    assessment should reflect any expected divergence of a specific cost from the

    level of inflation allowed in the discount rate. For example, it would be unwise

    to assume that market conditions would remain unchanged for any extended

    period when tender levels for building work are very depressed. Some

    allowance should therefore be made to adjust current building prices to more

    normal market conditions when pricing future building work.

    The level of detail used will be dictated by the availability of information and

    the requirements of the client.

    The following costs for each category should be considered and where

    necessary established with the client.

    (a) Capital costs include land, building, professional fees, furniture and

    equipment, or permanent improvements thereto, which form assets for thebusiness to use in its operation, with an intended useful life of more than one

    year. The significance of any tax benefits and grants should be established

    with the client.

    (b) Financing costs the method of funding the project should include, inter

    alia, the cost effect of alternative sources of funds, the future flexibility of

    funds in terms of amounts and sources, and gearing. Consideration should also

    be given to

    the accounting effect of capital employed;

    construction period finance charges and long-term finance costs; and

    the taxation implications of the various options.

  • 7/25/2019 part 2 section 2

    10/58

    PART2, SECTION2

    Page 10 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    (c) Operation costs include estimates of rent, rates, energy costs, cleaning

    costs, building related staffing costs and other staffing costs.

    (d) Annual maintenance costs average maintenance costs are available but

    once details of design are completed, a more relevant estimate can be

    produced based on information obtained from manufacturers or maintenance

    managers.

    (e) Intermittent maintenance, replacement and alteration costs replacement

    costs can be produced using normal cost estimating techniques.

    In seeking a realistic assessment of the life of materials and components,

    reference should be made to manufacturers, maintenance managers and other

    sources of such data (as discussed in 2.2.4).

    (f) Occupancy costs the cost of performing the function for which the

    building is intended (e.g. producing motor vehicles). Occupancy costs are

    distinguished from operation costs, as they relate to costs attributable to a

    specific process undertaken by the client, which may change within the life of

    the building. As an example, a car manufacturer may change to the production

    of heavy goods vehicles. This would impact on his occupancy costs, whereas

    his building related operation costs could be relatively unchanged. Some

    clients might not require the surveyor to take these costs into account, as not

    relating directly to the building.

    (g) Residual values and disposal costs estimate of the resale value and thecost of disposing of the building, plant, land and other assets after the expiry

    of the life cycle. Many buildings, particularly those with an open market

    value will have a significant residual value. Care should be taken in assessing

    this value as it can have a major effect on the life cycle costing calculations

    (see Appendix A).

    2.2.3 Tax Allowances, Incentives and Business Rates

    INTRODUCTION

    This Sub-section deals with the effect of taxation allowances and incentivesavailable for expenditure upon property and construction applicable in the

    United Kingdom to date, during the life of the asset. A glossary of terms is

    included in Appendix D.

    Currently, legislation offers tax relief by allowing expenditure upon certain

    assets to be depreciated, and to be offset against a private commercial

    organisations taxable profits.

    Tax relief is available on both capital and revenue expenditure. Capital costs

    receive this relief by way of capital allowances which are deductible items

    from the taxpayers taxation liability account. Maintenance costs are a charge

    on the profit and loss account, which again reduces the tax payable.

  • 7/25/2019 part 2 section 2

    11/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 11

    The significance of tax relief depends upon the amount of allowable

    expenditure. This varies considerably, being dependent upon the type and

    function of the asset, its design and sophistication (particularly in respect of

    services) and whether or not the project is a new building or a refurbishment.

    The impact of tax relief on the life cycle evaluation lessens proportionately

    with the ratio of allowable expenditure to the total expenditure and the timing

    of relief, which is dependent on the annual rate of taxation allowances. For

    example, a new oil refinery will have a greater proportion of allowance than a

    shop unit shell. It is also worth noting that capital allowances tend to be

    greater on plant than on buildings, so making the use of efficient plant more

    attractive than increasing the thermal efficiency of the building.

    The impact of tax relief should be sensitively tested at the earliest possible

    stage. A detailed estimate of the allowable expenditure should only be

    prepared if tax relief is found to be significant.

    2.2.3.1 The following example shows the net discounted cost, after tax relief, of

    1,000 spent on differing types of expenditure.

    2.2.3.2 TYPES OFALLOWANCES

    The types of allowances and rates of depreciation often change.

    Following the Finance Act 1985, capital allowances available that relate to

    Real Property were as follows:

    No relief

    Where capital

    allowances are

    allowed on 50% of

    capital expenditure

    Where capital

    allowances are

    allowed on 100%

    of capital

    expenditure

    Relief given

    on

    maintenance

    100%

    Expenditure 1,000 1,000 1,000 1,000

    Tax relief assuming 35%

    Corporation Tax

    1111 222 350

    Net discounted cost after

    tax relief

    1,000 889 778 650

    1 i.e. 50% of 1,000 25% reducing balance 35% Corporation Tax with future allowances discounted at

    10% per annum (a discounting calculation is required in order to establish the above figures).

  • 7/25/2019 part 2 section 2

    12/58

    PART2, SECTION2

    Page 12 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    Allowable expenditure Timing or percentage per annum

    Plant and machinery 25% (reducing balancing)

    Industrial buildings 4% (straight line)

    Agricultural buildings 4% (straight line)

    Dredging 4% (straight line)Scientific research 100%

    Cemeteries and crematoria Ratio based upon grave spaces used

    Dwelling houses let on assured tenancies

    only expenditure expended prior to

    1 April 1987 4% (straight line)

    Hotels 4% (straight line)

    Enterprise zone building expenditure 100%

    Mining and certain related construction works 40% plus a ratio based upon usable life

    Subsequent to the Finance Act 1997 first year allowances were changed and at

    the time of writing were still being finalised.

    In certain circumstances allowances may be at a higher rate i.e. they relate to

    specific incentives, certain assisted projects or expenditure relates to a

    transitional period e.g. terms of the Finance Act 1984 (applicable until 31

    March 1987).

    Different types of allowances, initial, first year and writing down are

    explained in the Glossary of Terms (Appendix D).

    Straight line allowances are calculated as a percentage of original cost and at

    4% the allowance is spread evenly over 25 years. A reducing balance

    computation is achieved each year by first deducting all previous allowanceamounts from original cost and then applying the allowable percentage to the

    balance, i.e. 25% in the first year, 25% of 75% in the second, and so on. While

    the building itself may be subject to a 4% straight line allowance the plant and

    machinery in the building will receive a 25% reducing balance.

    It should be noted that the significant part of capital allowance relief on a 25%

    reducing balance basis comes in the first five to seven years. This is included

    in the above example where the tax relief amount is a product of the

    incremental annual writing down allowance, discounted.

    Regional development grants (or their Northern Ireland equivalent) may also

    be available. These are not treated as taxable and may be disregarded when

    assessing the capital cost upon which tax relief is calculated.

    Currently the running and maintenance costs of an asset are deductible in full

    (i.e. 100% allowance) against taxable profits in the year of expenditure.

    2.2.3.3 VALUEADDEDTAX(VAT)

    Capital allowances are given against the net capital cost to the taxpayer.

    Therefore, as VAT is part of that capital cost, clients will incur differing

    overall capital expenditure for the same item depending upon whether theycan or cannot recover, or recover only a proportion of, the VAT.

  • 7/25/2019 part 2 section 2

    13/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 13

    2.2.3.4 CALCULATION OF THEEFFECT OFCAPITAL ANDREVENUEALLOWANCES

    Before calculating the effect of taxation allowances, certain parameters need

    to be ascertained:

    (a) the Corporation Tax and allowances rate that will be current at the date of

    construction of first use;

    (b) the future Corporation Tax and allowance rate at the date of replacement;

    (c) the Corporation Tax rate current at dates between date of construction of

    first use and the date of replacement, against which revenue running costs can

    be charged;

    (d) whether the owner will be liable to tax during the period between the date

    of construction or first use and the date of replacement, and if the owner will

    have sufficient taxable profits to use the allowances generated in any one year.

    (e) whether the items economic life will be shorter than the tax write down

    period. This will either generate an added write down amount when it is

    demolished, or if the item or building is to be sold at the end of its economic

    life, its profit or loss on cost. These circumstances will generate a taxable

    profit or loss on proceeds above or below the tax write down value and will

    attract a balancing adjustment;

    (f) the value of the balancing allowances, charges or taxable profits needs to

    be considered against the relevant Corporation Tax rate;

    (g) the impact of these adjustments therefore needs to be taken into account in

    the life cycle costing assessment.

    Caution is further necessary as there are specific restrictions. The recipient has

    to prove to the Inland Revenue that he qualifies for allowances (i.e. the

    entitlements are aimed at providing incentives for commercial organisations

    and therefore expenditure upon residential property is largely excluded.

    Entitlements are also restricted between connected persons).

    2.2.3.5 DYNAMICS

    The surveyor should therefore appreciate the variables and frequent changes

    that occur in respect to the application of taxation allowances.

    These arise because:

    (a) the Government uses taxation to impose fiscal policy and influence the

    economy and therefore statutes are introduced amending previous rates of

    depreciation, regulations and entitlements;

    (b) the interpretation of entitlement is affected by case law precedents.

  • 7/25/2019 part 2 section 2

    14/58

    PART2, SECTION2

    Page 14 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    (c) the Inland Revenue practices and extra statutory concessions develop to

    address specific issues or vagaries.

    2.2.3.6 APPLICATIONS

    Taxation allowances provide the opportunity for innovative funding

    arrangements whereby the tax relief can be exported to a party who can

    enjoy more benefit from the entitlement.

    They also need to be advised during property transfers so the relevant

    balancing adjustments can be calculated and the purchasers advised of their

    proper entitlements.

    2.2.3.7 WORKEDEXAMPLES

    Worked example 2.2.5.3 summarises the effect of capital and revenue

    allowances. Worked example 2.2.5.6 includes a detailed calculation of thecapital and revenue allowances.

    Business Rates

    Large plant and machinery regarded as an integral part of the building can

    attract additional rates which can be influenced by design niceties (such as how

    the plant is covered over). Expert advice should be sought in such a situation.

    Further reading for taxation

    Tolleys Capital Allowances, Tolley Publishing Co. Ltd generally published

    annually.

    Butterworths Yellow Tax Handbook, Butterworth & Co. (Publishers) Ltd

    abstract of Statutes

    Tax Statutes and Statutory Instruments, CCH Editions Ltd incorporating

    extra statutory concessions

    2.2.4 Data Sources

    Lack of data in a suitable format for maintenance, replacement and energy

    costs is said to be a significant reason for LCC rarely being carried out at

    present. Notwithstanding this, Building Surveyors and Facility Managers will

    often have valuable in-house data. Furthermore, professional judgement

    should not be disregarded.

    LCC calculations require information regarding the durability of

    materials/components, and/or energy costs. Lack of such accurate data in a

    suitable format may affect the credibility of the LCC calculation. However,

    while historic data is useful, reality is dependent upon individual design,

    installation and usage as well as technical development.

  • 7/25/2019 part 2 section 2

    15/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 15

    Whilst the selection of data sources given in Appendix F is not

    comprehensive, it gives an indication of the level of information available.

    Trade literature which is a prime source of detailed information is not

    included.

    2.2.5 Worked Examples

    INTRODUCTION

    Life cycle costing can be used in numerous situations. The intention of this

    Sub-section is to give the reader an appreciation of its application, as used by

    surveyors in practice, and the relative complexities of associated calculations,

    ranging from a simple elemental option appraisal to complex total building

    analyses.

    The examples follow in order of complexity, worked examples 2.2.5.1 and

    2.2.5.2 will readily convey the principles of life cycle costing including

    discounting. The remainder consider more detailed scenarios.

    2.2.5.1 DESIGNOPTION: INTERNALDOORS

    This example is kindly provided by Messrs Gardiner & Theobald, Chartered

    Quantity Surveyors. The objective is to evaluate four comparative

    specifications over a building life of 60 years using a discount rate of 4% (7%

    interest rate less 3% inflation rate). The information is summarised in the table

    below with an explanation of the calculation for option 1 detailed at (a) to (d)

    below. Any tax implications are excluded.

    (a) The present value for purchasing the doors is obviously the same as the

    capital cost: 35,000

    (b) For the annual running costs:

    10.89/m2 20 m2 = 218

    218 incurred every year for 60 years at 4% discount

    = 218 22.6* = 4,927 present value

    (c) For maintenance the present cost of 6,040 for new ironmongery andrepainting taking place in, say Year 12 at 4% discount

    = 6,040 0.62459** = 3,773

    (d) The replacement cost after 40 years

    = 35,000 (present cost) 0.20828** = 7,290

    The total present value of the capital cost, annual running cost,

    maintenance and replacement costs

    = 57,037 showing option 1 is the most expensive life cycle cost

    * from valuation tables at 2.2.5.7 (years purchase or present value of 1

    per period)

    **from valuation tables at 2.2.5.7 (present value of 1)

  • 7/25/2019 part 2 section 2

    16/58

    PART2, SECTION2

    Page 16 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    PROJECT:Life Cycle Model SHEET NUMBER: LCCM5ELEMENT: Internal Doors

    Unit: 20 m2

    PROJECT LIFE 60 YearsDiscount Rate 4.00% per annum

    Discount Rate 4.00% per annum

    (Interest Rate (7%), Inflation (3%))

    COSTS

    OPTION 1

    Aluminium Glazed

    OPTION 2

    Hardwood GlazedVision Panels

    OPTION 3

    Softwood

    OPTION 4

    Metal

    Finish Life40 Years

    Finish Life30 Years

    Finish Life20 Years

    Finish Life30 Years

    MaintenancePeriod4 Years

    MaintenancePeriod4 Years

    MaintenancePeriod4 Years

    MaintenancePeriod4 Years

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    Capital CostsAluminium Glazed 1750.00 m2 35,000 35,000Hardwood Glazed

    Vision Panels 1000.00 m2 20,000 20,000

    Softwood 700.00 m2

    14,000 14,000Metal 850.00 m2 17,000 17,000Contingency

    Total Year 1 Capital Costs 35,000 20,000 14,000 17,000

    Annual Running CostsAluminium Glazed 10.89 m2 218 4,927Hardwood GlazedVision Panels 9.99 m2 200 4,520Softwood 5.90 m2 118 2,670Metal 17.99 m2 360 8,140

    Total Annual Running Costs 13,068 4,927 11,988 4,520 7,080 2,670 21,588 8,140

    Maintenance Year PresentCost

    OPTION 1 Repaint 4 340 340 291

    Repaint 8 340 340 248New ironmongery

    Repaint 12 6,040 6,040 3,773Repaint 16 340 340 182Repaint 20 340 340 155

    New ironmongeryRepaint 24 6,040 6,040 2,356Repaint 28 340 340 113Repaint 32 340 340 97

    New ironmongeryRepaint 36 6,040 6,040 1,472Repaint 40 340 340 71Repaint 44 340 340 61

    New ironmongeryRepaint 48 6,040 6,040 919Repaint 52 340 340 44

    Repaint 56 340 340 38OPTION 2 Repaint 4 300 300 256

    Repaint 8 300 300 219New ironmongery

    Repaint 12 6,000 6,000 3,748Repaint 16 300 300 160Repaint 20 300 300 137

    New ironmongeryRepaint 24 6,000 6,000 2,341Repaint 28 300 300 100Repaint 32 300 300 86

    New ironmongeryRepaint 36 6,000 6,000 1,462Repaint 40 300 300 62Repaint 44 300 300 53

  • 7/25/2019 part 2 section 2

    17/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 17

    PROJECT:Life Cycle Model (continued SHEET NUMBER: LCCM5ELEMENT: Internal Doors

    Unit: 20 m2

    PROJECT LIFE 60 Years

    Discount Rate 4.00% per annum

    Discount Rate 4.00% per annum

    (Interest Rate (7%), Inflation (3%))

    COSTS

    OPTION 1Aluminium Glazed

    OPTION 2Hardwood Glazed

    Vision Panels

    OPTION 3Softwood

    OPTION 4Metal

    Finish Life40 Years

    Finish Life30 Years

    Finish Life20 Years

    Finish Life30 Years

    MaintenancePeriod4 Years

    MaintenancePeriod4 Years

    MaintenancePeriod4 Years

    MaintenancePeriod4 Years

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    Maintenance Year PresentCost

    New ironmongeryRepaint 48 6,000 6,000 913Repaint 52 300 300 39

    Repaint 56 300 300 33OPTION 3 Repaint 4 320 320 274

    Repaint 8 320 320 234New ironmongery

    Repaint 12 3,820 3,820 2,386Repaint 16 320 320 171Repaint 20 320 320 146

    New ironmongeryRepaint 24 3,820 3,820 1,490Repaint 28 320 320 107Repaint 32 320 320 91

    New ironmongeryRepaint 36 3,820 3,820 931Repaint 40 320 320 67Repaint 44 320 320 57

    New ironmongery

    Repaint 48 3,820 3,820 581Repaint 52 320 320 42Repaint 56 320 320 36

    OPTION 4 Repaint 4 300 300 256Repaint 8 300 300 219Repaint 12 6,100 6,100 3,810Repaint 16 300 300 160Repaint 20 300 300 137Repaint 24 6,100 6,100 2,380Repaint 28 300 300 100Repaint 32 300 300 86Repaint 36 6,100 6,100 1,486Repaint 40 300 300 62Repaint 44 300 300 53Repaint 48 6,100 6,100 928Repaint 52 300 300 39

    Repaint 56 300 300 33Replacement Year Present

    Cost6,100 3,810

    OPTION 1 40 35,000 35,000 7,290OPTION 2 30 20,000 20,000 6,166OPTION 3 20 14,000 14,000 6,389

    40 14,000 14,000 2,916OPTION 4 30 17,000 17,000 5,241

    Total Maintenance/Replacement Costs 62,560 17,109 47,000 15,776 46,480 15,917 44,400 14,993

    Total Running Costs 75,628 22,037 58,988 20,297 53,560 18,586 65,988 23,132

    Total Net Present Value of Life Cycle Costs 57,037 40,297 32,586 40,132

  • 7/25/2019 part 2 section 2

    18/58

    PART2, SECTION2

    Page 18 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    2.2.5.2 BUILDINGSERVICESDESIGNOPTION: AIRCONDITIONING ANDUNDERFLOOR

    TRUNKING VERSUSHOTWATERHEATING ANDRINGMAINELECTRICS

    This example is again provided by Messrs Gardiner & Theobald. The

    objective is to evaluate the above options for a building of 3,000 m 2 floor area,

    a life of 60 years and a discount rate of 4% (7% interest less 3% inflation). The

    information is summarised overleaf with the methodology for the calculation

    being exactly as that for the previous example. Any taxation implications are

    excluded.

  • 7/25/2019 part 2 section 2

    19/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 19

    Element:ServicesUnit: 3,000 m2

    PROJECT LIFE 60 YearsD iscount Rate 4% per annum

    Discount Rate 4.00% per annum(Interest Rate (7%), Inflation (3%)

    COSTS

    OPTION 1Air ConditioningU/Floor Trunking

    OPTION 2HW Heating &

    Ring Main Electrics

    OPTION 3 OPTION 4

    Finish Life15 Years

    Finish Life25 Years

    Finish Life Finish Life

    MaintenancePeriod5 Years

    MaintenancePeriod7 Years

    MaintenancePeriodYears

    MaintenancePeriodYears

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    EstimatedCost

    PresentValue

    Capital Cost

    Air Conditioning U/Floor Trunking 250 m2 750,000 750,000

    HW Heating & Ring Main Elec tri c 150 m2 450,000 450,000

    Contingency 5% 37,500 22,500

    Total Year 1 Capital Costs 787,500 472,500

    Annual Running Costs

    Air Conditioning U/Floor Trunking 25.00 m2 75,000 1,696,762

    HW Heating & Ring Main Electric 5.00 m2 15,000 339,352

    Total Annual Costs 4,500,000 1,696,762 900,000 339,352

    Maintenance Year Present

    Cost

    OPTION 1 5 5,000 5,000 4,110

    Overhall Equipment 10 5,000 5,000 3,378

    Overhall Equipment 15 5,000 5,000 2,776

    Overhall Equipment 20 5,000 5,000 2,282

    Overhall Equipment 25 5,000 5,000 1,876

    Overhall Equipment 30 5,000 5,000 1,542

    Overhall Equipment 35 5,000 5,000 1,267

    Overhall Equipment 40 5,000 5,000 1,041Overhall Equipment 45 5,000 5,000 856

    Overhall Equipment 50 5,000 5,000 704

    Overhall Equipment 55 5,000 5,000 578

    OPTION 2 7 2,000 2,000 1,520

    Genearl repaint/repair 14 2,000 2,000 1,155

    Genearl repaint/repair 21 2,000 2,000 878

    Genearl repaint/repair 28 2,000 2,000 667

    Genearl repaint/repair 35 2,000 2,000 507

    Genearl repaint/repair 42 2,000 2,000 385

    Genearl repaint/repair 49 2,000 2,000 293

    Genearl repaint/repair 56 2,000 2,000 222

    OPTION 3

    OPTION 4

    Replacement Year Present Cost

    OPTION 1 15 600,000 600,000 333,159

    30 600,000 600,000 184,991

    45 600,000 600,000 102,719

    OPTION 2 25 300,000 300,000 112,535

    50 300,000 300,000 42,214

    OPTION 3

    OPTION 4

    Tota l Maintenance/Replacement C osts 1,855,000 641 ,278 616,000 160,375

    Total Running Costs 6,355,000 2,338,040 1,516,000 499,728

    Total Net Present Value of Life

    Cycle Cost 3,125,540 972,228

  • 7/25/2019 part 2 section 2

    20/58

    PART2, SECTION2

    Page 20 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    2.2.5.3 MAINTENANCEOPTION: WITH/WITHOUTCLEANINGGANTRY

    This example is kindly provided by Gerald Hall.

    The following figure compares two options, firstly to provide the cleaning

    gantry and secondly to omit the gantry. The capital cost and costs associated

    with anticipated maintenance were calculated by using normal cost estimating

    techniques.

    Assumed criteria:

    Building Life 25 years

    VAT assumed to remain at current levels with the client

    being an end user under VAT rules 17.5%

    Gantry capital cost 30,000 The gantry will have a residual value 2,000

    Capital cost for opening lights in lieu of gantry 5,000

    Discount rate (assuming the interest rate will average 11%

    over 25 years and the inflation rate 6%) 5%

    Corporation Tax 33%

    Taxation Calculation

    The capital cost for plant and machinery receives a 25% reducing balance.

    Maintenance and running costs receive 100% allowance.

    Year 1 with gantry calculation:

    Capital 35,250 25% 33% = 2,908

    Maintenance 881 33% = 291

    3,199

    Year 2 with gantry calculation:

    Capital 35,250 less 25% 25% 33% = 2,181

    Maintenance 881 33% = 2912,472

    The methodology applies for the rest of the 25 years as summarised overleaf.

    The client initially considered that the gantry would pay for itself due to

    savings in maintenance and cleaning cost.

    However:

    with gantry investment 36,510 present value

    without gantry investment 26,447 present value

  • 7/25/2019 part 2 section 2

    21/58

    PART2, SECTION2

    The Surveyors Construction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 21

    COMPARATIVECOMPONENTLIFE

    CYCLECOSTING

    CLIENT:

    PROJECTTITLE:RetailDevelopment/ShoppingMall

    JOBNO:

    OPTION:Cleaningwithgantrycurta

    inwallingtonewfacace

    Year

    Costs

    TOTAL

    VAT17.5

    %

    TOTAL

    incVAT

    Lesstax

    allowance

    NETTOTAL

    Presentvalue

    of 1

    @5

    %

    PRESENT

    VALUE

    CUMULATIVE

    PRESENT

    VALUE

    Capital

    Financing

    Operation

    Maintenance

    Occupacy

    Disposal/

    residualva

    lue

    Annual

    Intermittent

    0

    30,0

    00

    30,0

    00

    5,2

    50

    35,2

    50

    0

    35,2

    50

    1.0

    00

    35,2

    50

    35,2

    50

    1

    750

    750

    131

    881

    3

    ,199

    (2,3

    18)

    0.9

    52

    (2,2

    07)

    33,0

    43

    2

    750

    750

    131

    881

    2

    ,472

    (1,5

    91)

    0.9

    07

    (1,4

    43)

    31,6

    00

    3

    750

    250

    1,0

    00

    175

    1,1

    75

    2

    ,024

    (849)

    0.8

    64

    (733)

    30,8

    66

    4

    750

    750

    131

    881

    1

    ,518

    (637)

    0.8

    23

    (524)

    30,3

    43

    5

    750

    750

    131

    881

    1

    ,211

    (330)

    0.7

    84

    (258)

    30,0

    84

    6

    750

    1,7

    50

    2,5

    00

    438

    2,9

    38

    1

    ,660

    1,2

    78

    0.7

    46

    953

    31,0

    37

    7

    750

    750

    131

    881

    808

    73

    0.7

    11

    52

    31,0

    89

    8

    750

    750

    131

    881

    679

    202

    0.6

    77

    137

    31,2

    26

    9

    750

    250

    1,0

    00

    175

    1,1

    75

    679

    496

    0.6

    45

    320

    31,5

    46

    10

    750

    750

    131

    881

    509

    372

    0.6

    14

    229

    31,7

    75

    11

    750

    750

    131

    881

    454

    427

    0.5

    85

    250

    32,0

    24

    12

    750

    1,7

    50

    2,5

    00

    438

    2,9

    38

    1

    ,092

    1,8

    46

    0.5

    57

    1,0

    28

    33,0

    52

    13

    750

    750

    131

    881

    383

    498

    0.5

    30

    264

    33,3

    16

    14

    750

    750

    131

    881

    360

    521

    0.5

    05

    263

    33,5

    80

    15

    750

    250

    1,0

    00

    175

    1,1

    75

    440

    735

    0.4

    81

    354

    33,9

    33

    16

    750

    750

    131

    881

    330

    551

    0.4

    58

    253

    34,1

    86

    17

    750

    750

    131

    881

    320

    561

    0.4

    36

    245

    34,4

    31

    18

    750

    1,7

    50

    2,5

    00

    438

    2,9

    38

    991

    1,9

    47

    0.4

    16

    809

    35,2

    39

    19

    750

    750

    131

    881

    307

    574

    0.3

    96

    227

    35,4

    67

    20

    750

    750

    131

    881

    303

    578

    0.3

    77

    218

    35,6

    85

    21

    750

    250

    1,0

    00

    175

    1,1

    75

    397

    778

    0.3

    59

    279

    35,9

    64

    22

    750

    750

    131

    881

    298

    583

    0.3

    42

    199

    36,1

    63

    23

    750

    750

    131

    881

    296

    585

    0.3

    26

    191

    36,3

    54

    24

    750

    1,7

    50

    2,5

    00

    438

    2,9

    38

    973

    1,9

    65

    0.3

    10

    609

    36,9

    63

    25

    750

    (2,0

    00)

    (1,2

    50)

    131

    (1,1

    19)

    311

    (1,4

    30)

    0.2

    95

    (422)

    36,5

    41

    TOTALPRESENTVALUEATENDOFINVESTMENTLIFE

    36,5

    41

  • 7/25/2019 part 2 section 2

    22/58

    PART2, SECTION2

    Page 22 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    CO

    MPARATIVECOMPONENTLIFE

    CYCLECOSTING

    (continuationo

    ftable

    onp

    age2

    1)

    FORE

    CASTERSASSUMPTIONS

    1

    Th

    ecapitalcostincludesallowancesfor

    preliminariesandassociatedbuilders

    work.

    2

    Detailsofthemaintenancerequirement

    sandcostestimatescanbeprovided

    up

    onrequest.

    3

    Th

    elifecyclecostingisbasedonanagreedinvestmentlifeof25years.

    4

    ItisassumedthatVATwillremainataro

    und17.5%andtheclientistheend

    us

    erunderVATrules.

    5

    Th

    erearedisposalcostadvantageswiththisoption.

    6

    Capitalcostasplantandmachinerywith100%taxallowance

    i.e.1styear

    2,908

    7

    Maintenanceandrunningcostswith100%allowanceie1styear

    291

    total

    3,199

    8

    Taxationallowancesaresubjecttonegotiationandagreement.

    9

    Discountrate:

    (i)Interestrate11%averag

    eover25years;

    (ii)Inflationrate7%averageover25years;

    (1+11%)

    (1+7%)1100%=5%dis

    countrate.

  • 7/25/2019 part 2 section 2

    23/58

    COMPARATIVECOMPONENTLIFE

    CYCLECOSTING

    CLIENT:

    PROJECTTITLE:RetailDevelopment/ShoppingMall

    JOBNO:

    OPTION:Cleaningwithgantry

    curta

    inwallingtonewf

    acace

    Year

    Costs

    TOTAL

    VAT17.5

    %

    TOTAL

    incVAT

    Lesstax

    allowance

    NETTOTAL

    Presentvalue

    of 1

    @5

    %

    PRESENT

    VALUE

    CUMULATIVE

    PRESENT

    VALUE

    Capital

    Financing

    Operation

    Maintenance

    Occupacy

    Disposal/

    residualva

    lue

    Annual

    Intermittent

    0

    5,0

    00

    5,0

    00

    875

    5,8

    75

    0

    5,8

    75

    1.0

    00

    5.8

    75

    5,8

    75

    1

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.9

    52

    1,1

    24

    6,9

    99

    2

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.9

    07

    1,0

    71

    8,0

    70

    3

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.8

    64

    1,0

    20

    9,0

    90

    4

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.8

    23

    971

    10,0

    61

    5

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.7

    84

    925

    10,9

    86

    6

    1,5

    00

    1,5

    00

    3,0

    00

    263

    3,5

    25

    1

    ,163

    2,3

    62

    0.7

    46

    1,7

    63

    12,7

    49

    7

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.7

    11

    839

    13,5

    87

    8

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.6

    77

    799

    14,3

    86

    9

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.6

    45

    761

    15,1

    47

    10

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.6

    14

    725

    15,8

    72

    11

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.5

    85

    690

    16,5

    62

    12

    1,5

    00

    6,5

    00

    1,1

    38

    7,6

    38

    2

    ,521

    5,1

    17

    0.5

    57

    2,8

    49

    19,4

    11

    13

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.5

    30

    626

    20,0

    37

    14

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.5

    05

    596

    20,6

    34

    15

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.4

    81

    568

    21,2

    02

    16

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.4

    58

    541

    21,7

    42

    17

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.4

    36

    515

    22,2

    57

    18

    1,5

    00

    1,5

    00

    3,0

    00

    525

    3,5

    25

    1

    ,163

    2,3

    62

    0.4

    16

    981

    23,2

    39

    19

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.3

    96

    467

    23,7

    06

    20

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.3

    77

    445

    24,1

    51

    21

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.3

    59

    424

    24,5

    75

    22

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.3

    42

    404

    24,9

    78

    23

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.3

    26

    384

    25,3

    63

    24

    1,5

    00

    1,5

    00

    3,0

    00

    263

    3,5

    25

    1

    ,163

    2,3

    62

    0.3

    10

    732

    26,0

    95

    25

    1,5

    00

    1,5

    00

    263

    1,7

    63

    582

    1,1

    81

    0.2

    95

    349

    26,4

    44

    TOTALPRESENTVALUEATENDOFINVESTMENTLIFE

    26,4

    44

  • 7/25/2019 part 2 section 2

    24/58

    PART2, SECTION2

    Page 24 Part 2, Section 2 (4/99) Effective from 1/6/99 The Surveyors Construction Handbook

    CO

    MPARATIVECOMPONENTLIFE

    CYCLECOSTING

    (continuationo

    ftable

    onp

    age2

    3)

    FORE

    CASTERSASSUMPTIONS

    1

    Th

    ecapitalcostincludesallowancesforopeninglightsnowrequired,without

    ca

    pitalallowances.

    2

    Detailsofthemaintenancerequirement

    sandcostestimatescanbeprovided

    up

    onrequest.

    3

    Th

    elifecyclecostingisbasedonanagreedinvestmentlifeof25years.

    4

    ItisassumedthatVATwillremainataro

    und17.5%andtheclientistheend

    us

    erunderVATrules.

    5

    Th

    erearedisposalcostadvantageswiththisoption.

    6

    Capitalcostasplantandmachinerywith100%taxallowanceNIL

    7

    Maintenanceandrunningcostswith100%allowance.

    8

    Taxationallowancesaresubjecttonegotiationandagreement.

    9

    Discountrate:

    (i)Interestrate11%averag

    eover25years;

    (ii)Inflationrate7%averageover25years;

    (1+11%)

    (1+7%)1100%=5%dis

    countrate.

  • 7/25/2019 part 2 section 2

    25/58

    PART2, SECTION2

    The SurveyorsConstruction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 25

    2.2.5.4 HOUSINGSINKINGFUND(BASED UPON COSTED PLANNED MAINTENANCE)

    (a) Background

    This example is kindly provided by Ian Sloan of Armour Construction

    Consultants.

    Housing Associations and Co-operatives in Scotland generally request that

    their investment/sinking fund requirements are prepared in accordance with

    the Scottish Federation of Housing Associations (SFHA) Planned

    Maintenance and Repairs (Revised), Guidance Booklet No 3 published in

    January 1997.

    There are various ways of presenting the data. One method widely accepted is

    shown below, on two spreadsheets, a Planned Maintenance Programme, and a

    costedPlanned Maintenance Programme which establishes in this case the

    present value of future costs.

    The spreadsheets can be fine tuned to meet specific client requirements. In

    due course they can be adapted to allow historical information to be fed into

    the programme, which then allows actual costs and maintenance periods

    incurred to form the basis of the life cycle costs, thereby providing a more

    accurate projection.

    (b) Brief

    The client needed to establish the capital to be invested for a new build

    housing project to cover all maintenance and repairs for the next 60 years. The

    discount rate is 6%.

    An example of the calculation shown overleaf is:

    Year 15, total maintenance and repair expenditure at current prices

    = 9,013

    9,013 0.41726* = 3,761

    i.e. 3,761 would have to be invested now for 15 years at 6% compound

    interest in order to meet the costs in Year 15 of 9,013. In summary 24,942would have to be invested now at 6% to cover all maintenance and repairs for

    the next 60 years.

    The data could also be presented as an annual sinking fund e.g. the amount to

    be investedfor eachof 15 years at 6% compound interest in order to meet the

    costs in Year 15 of 9,013 is:

    9,013 0.04296** = 387

    * from valuation tables at 2.2.5.7 (present value of 1)

    ** from valuation tables at 2.2.5.7 (annual sinking fund)

  • 7/25/2019 part 2 section 2

    26/58

    PART2, SECTION2

    Page 26 Part 2, Section 2 (4/99) Effective from 1/6/99 The SurveyorsConstruction Handbook

    PLANNEDMAINTENANCEPROGRAMME

    KEY

    =

    Inspec

    t/Cons

    ider

    =

    Inspec

    tand

    Remedy

    T=

    Testun

    til

    =

    Inspec

    t&

    EXAMPLE

    =

    Renewal

    /Rep

    lacemen

    t

    =

    untilReplacemen

    t

    replacemen

    t

    =

    Decora

    te

    DatePrinted

    02/12/98

    Cumulative

    CODE

    ELEMENT

    SUB-ELEMENT

    COMPONENT

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    2930

    Cost

    STRUC-

    TURE

    1.1

    STRUCTURE

    1.1.1.Roofs

    Timber

    0

    1.1.2.Floors

    Timber

    0

    1.1.3.Openings

    Concrete/Brick

    0

    1.2

    STAIRS

    1.2.1.Stairs

    Timber

    0

    1.2.2.Handrailsetc

    Timber

    0

    EXT

    FABRIC

    2.1

    ROOF

    2.1.1.RoofTilesetc

    ConcreteTiles

    0

    2.1.2.Flashings

    Lead

    0

    2.1.3.Guttersetc

    UPVC

    0

    2.2

    EXTERNALWALLS

    2.2.1.Walls

    FacingBrick

    0

    2.2.2.Rendering

    0

    2.2.3.Ventilation

    0

    2.3

    WINDOWS

    2.3.1.WindowOp

    Timber/Glass

    0

    2.3.2.Pointing

    0

    2.3.3.Painting

    0

    2.3.4.Ironmongery

    0

    2.4

    EXTERNALDOORS

    2.4.1.DoorOperation

    Timber/Metal

    0

    2.4.2.Pointing

    0

    2.4.3.Painting

    0

    2.4.4.Ironmongery

    0

    INT

    FABRIC

    3.1

    INTERNALWALLS

    3.1.1.Walls&Opens

    Brick/pboard

    0

    3.1.2.WallTiling

    Ceramic

    3.2

    CEILINGS

    3.2.1.Ceilings

    Plasterboard

    0

    3.3

    FLOORS

    3.3.1.Flooring

    Timber/Vinyl

    0

    3.3.2.Skirtings

    Timber

    0

    3.4

    DOORS

    3.4.1.DoorOperation

    Timber

    0

    3.4.2.Ironmongery

    0

    FITTS

    FURN

    4.1

    FITTINGS&FURNISH

    4.1.1.KitchenUnits

    Units/Worktops

    0

    4.1.2.Grabrailsetc

    0

    SERVICES

    5.1

    SANITARYAPPLIANCES

    5.1.1.Sanitaryware

    Wcs,b

    aths

    ,whbs

    0

    5.2

    SERVICESEQUIPMENT

    5.2.1.Kitchensinks

    Stainlesssteel

    0

    5.3

    WATERSUPPLY

    5.3.1.Waterstorage

    0

    5.3.2.

    Waterpipesetc

    T

    T

    T

    T

    T

    T

    0

    5.3.3.

    Insulation

    0

    5.4.1.

    INTERNALDRAINAGE

    5.4.2.1.Pipes&Fittns

    T

    T

    T

    T

    T

    T

    0

    5.4.2.

    DISPOSALINST

    5.4.1.1.

    Pipes&Fittns

    T

    T

    T

    T

    T

    T

    0

    5.5

    HEATSOURCE

    5.5.1.Radiators/fires

    T

    T

    T

    T

    0

    5.6

    HEATSYSTEM

    5.6.1.Boilers/equipment

    0

    5.7

    VENTILATION

    5.7.1.Fansetc

    0

  • 7/25/2019 part 2 section 2

    27/58

    PART2, SECTION2

    The SurveyorsConstruction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 27

    PLANNEDMAINTENANCEPROGRAMME

    KEY

    =

    Inspec

    t/Cons

    ider

    =

    Inspec

    tand

    Remedy

    T=

    Testun

    til

    =

    Inspec

    t&

    EXAMPLE(Con

    tinue

    d)

    =

    Renewal

    /Rep

    lacemen

    t

    =

    untilReplacemen

    t

    replacemen

    t

    =

    Decora

    te

    DatePrinted

    02/12/98

    Cumulative

    CODE

    ELEMENT

    SUB-ELEMENT

    COMPONENT

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    2930

    Cost

    SER-

    VICES

    5.8

    ELECTRICALINST

    5.8.1.Powerandlightin

    g

    0

    5.8.2.Switchgear

    0

    5.8.3.ExternalLighting

    CloseLight

    0

    5.9

    GASINSTALLATION

    5.9.1.

    Equipment&supply

    T

    T

    T

    T

    T

    0

    5.10

    LIFTINSTALLATION

    0

    5.11

    PROTECTIVEINST

    5.11

    .1.T

    Vsystemetc

    T

    T

    T

    0

    5.11

    .2.S

    mokedetectors

    0

    5.1.2

    COMMUNICATION

    5.12

    .1.D

    oorentry

    0

    5.12

    .2Telephones

    T

    T

    T

    T

    0

    EXT

    WORKS

    6.1.1

    LANDSCAPING

    6.1.1.1.Roads,footpaths

    0

    6.1.1.2.Grass/planting

    0

    6.1.2

    BOUNDARIES&

    ENCLOSURES

    6.1.2.1.

    Fencesandgate

    s

    0

    6.1.2.2.

    Wallsetc

    0

    6.1.2.3.

    Clothespoles

    0

    6.2

    DRAINAGE

    6.2.1.

    Pipes&fittings

    0

    6.2.2.

    Manholesetc

    0

    6.3

    EXTERNALSERVICES

    6.3.1.

    Ducts&cables

    0

    6.4

    OUTBUILDINGS

    6.4.1.

    Binstores/platts

    0

    COSTIN,0

    00sof

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.00

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.0

    0

    0.00

  • 7/25/2019 part 2 section 2

    28/58

  • 7/25/2019 part 2 section 2

    29/58

    PART2, SECTION2

    The SurveyorsConstruction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 29

    PLANN

    EDMAINTENANCEPROGRAMME(COSTED)(Con

    tinue

    d)

    EXAMP

    LE

    DatePrinted

    02/12/98

    Years

    Cumulative

    CODE

    ELEMENT

    SUB-ELEMENT

    COMPONENT

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    1819

    20

    21

    22

    23

    24

    25

    26

    27

    28

    29

    30

    Cost

    SER-

    VICES

    5.8.2.Switchgear

    inc

    inc

    inc

    inc

    inc

    inc

    0

    5.8.3.ExternalLighting

    CloseLight

    inc

    100

    inc

    100

    inc

    inc

    200

    5.9

    Gasinstallation

    5.9.1.

    Equipment&supply

    25

    25

    25

    25

    25

    25

    150

    5.1

    0

    Liftinstallation

    0

    5.1

    1

    Protectiveinst

    5.1

    1.1.

    TVsystemetc

    25

    150

    25

    150

    25

    150

    525

    5.1

    1.2.

    Smokedetectors

    10

    10

    10

    10

    75

    10

    10

    10

    10

    75

    10

    10

    10

    10

    75

    10

    10

    101

    0

    75

    10

    10

    10

    10

    75

    10

    10

    10

    10

    75

    690

    5.1.2

    Communication

    5.1

    2.1.

    Doorentry

    n/a

    n/a

    n/a

    n/a

    n/a

    n/an

    /a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/an/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    n/a

    0

    5.1

    2.2.

    Telephones

    10

    10

    100

    10

    10

    100

    240

    0

    EXT

    WORKS

    6.1.1

    Landscaping

    6.1.1.1.

    Roads,

    footpath

    s

    50

    50

    50

    50

    50

    50

    50

    50

    50

    50

    50

    50

    50

    50

    500

    50

    50

    505

    0

    50

    50

    50

    50

    50

    50

    50

    50

    50

    50

    500

    2,4

    00

    6.1.1.2.

    Grass/planting

    100

    100

    100

    100

    100

    1001

    00

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    100

    750

    3,6

    50

    6.1.2

    Boundaries&Enclosures

    6.1.2.1.

    Fencesandgat

    es

    10

    10

    500

    10

    10

    500

    10

    10

    500

    10

    10

    500

    10

    10

    300010

    10

    5001

    0

    10

    500

    10

    10

    500

    10

    10

    500

    10

    10

    3000

    10,2

    00

    6.1.2.2.

    Wallsetc

    50

    50

    50

    50

    50

    50

    300

    6.1.2.3.

    Clothespoles

    40

    40

    40

    40

    200

    40

    40

    40

    40

    750

    1,2

    70

    6.2

    Drainage

    6.2.1.

    Pipes&fittings

    100

    100

    100

    100

    100

    500

    1,0

    00

    6.2.2.

    Manholesetc

    inc

    inc

    inc

    inc

    inc

    inc

    0

    6.3

    Externalservices

    6.3.1.

    Ducts&cables

    25

    25

    25

    25

    25

    400

    525

    6.4

    Outbuildings

    6.4.1.

    Binstores/platts

    50

    50

    50

    50

    50

    500

    750

    TOTALCOSTPERYEAR

    518

    5181208518144812085

    18518120840685181208518518901351851812085188673104851851812081448518120851851815460

    57,9

    02

    (Yrs1

    30)

    PRESENTVALUE

    489

    461101441010828523

    44325715227227360024322937612041924231712704308144136298337114251101

    96

    2692

    21241

    Yrs1

    30)

    (atdiscountrateof6%)

    RepeatYears

    31

    32

    33

    34

    35

    36

    37

    38

    39

    40

    41

    42

    43

    44

    45

    46

    47

    484

    9

    50

    51

    52

    53

    54

    55

    56

    57

    58

    59

    6

    0(Yrs31

    60)

    CurrentCostperyr

    518

    5181208518144812085

    18518120840685181208518518901351851812085188673104851851812081448518120851851815460

    57902

    115804

    (Currentcost)

    PresentValue

    85

    80

    177

    71

    188

    148

    60

    57

    124

    395

    48

    105

    42

    40

    655

    36

    33

    743

    0

    471

    54

    25

    24

    52

    59

    20

    44

    18

    17

    469

    3701

    24942

    (PresentValue)

  • 7/25/2019 part 2 section 2

    30/58

    PART2, SECTION2

    Page 30 Part 2, Section 2 (4/99) Effective from 1/6/99 The SurveyorsConstruction Handbook

    2.2.5.5 CENTRALISATION OFOFFICESSTUDY

    (a) Brief

    This example is kindly provided by Gerald Hall.

    The client wished to investigate a centralisation (of offices) strategy as a

    means to improve business efficiency in an increasingly competitive market.

    The offices were originally spread out over three main sites.

    Three options were identified:

    do nothing, although this would require repair and refurbishment of the

    existing offices;

    centralise at location A and construct additional new offices;

    centralise at location B and construct additional new offices;

    (b) Capital Costs

    These were calculated using traditional cost estimating and included cyclical

    capital costs. The distinction between cyclical capital costs and cyclical

    maintenance costs is often vague, those costs in excess of 10,000 are

    included in the capital cost element under the assumption they would be part

    of the capital cost programme.

    Relocation costs (labour and plant required to transport office equipment,

    stores, machinery, compound materials and stationery items) are included

    under Year 0 on the assumption they would be complete within 12 months and

    a contingency for new furniture included.

    (c) Revenue Costs

    fuel: the energy manager provided existing costs which were used as the

    basis for the new proposal;

    water costs were excluded (the client was a water company);

    maintenance costs under 10,000;

    rates were not provided by the client by the deadline and are therefore

    excluded;

    cleaning costs are based on existing cleaning costs and judgement;

    security costs are based on existing security costs and judgement;

    operation costs for this client included waste removal, water coolers,sanitary hire, mail collections, fire prevention, telephones, hygiene,

    insurances. Again this was based on existing client data plus judgement.

    Even with constant staff numbers these costs reduce with centralisation;

    staffing costs were excluded as they would remain constant.

    (d) Capital Income

    Options 2 and 3 will free up existing space for sale and rent which are included

    as a deduction against expenditure.

    (e) Discount Rates

    In accordance with the client guidelines the investment horizon is 40 years and

    the discount rate 8%.

  • 7/25/2019 part 2 section 2

    31/58

    PART2, SECTION2

    The SurveyorsConstruction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 31

    (f) Tax Implications

    Tax allowances have been excluded on the basis that this study is a minor part

    of the overall company business and assumptions are not appropriate.

    However it is worth noting that:

    Value Added Tax on all capital costs would affect the financial benefits

    of options 2 and 3 which require considerable capital expenditure;

    Capital Allowances would help support options 2 and 3.

    (g) Renewal and Refurbishment Costs

    General building refurbishment has been allowed in ten-year cycles; electrical

    and mechanical plant replaced after 20 years with a refurbishment after ten

    years or mid-life; felt roofs replaced after 20 years; profiled metal decking,

    windows and doors after 30 years. All costs are calculated using traditionalcost estimating and included as present costs.

    (h) Cost Comparison

    The detailed calculation is summarised over for option 2 which is the most

    cost effective over 40 years.

    Year 0 Expenditure Year 40 Net Present Value

    Option 1 203,000 1,960,950

    Option 2 1,164,900 1,607,896

    Option 3 1,262,100 1,843,068

    (i) Sensitivity Analysis

    An analysis of different discount rates and time frame confirm option 2 as the

    most favourable.

    Discount Life Cycle Option 1 Option 2 Option 3

    Rates

    6% 0 287,900 1,164,900 1,262,100

    6% 20 1,859,000 1,593,000 1,826,1006% 40 2,444,420 1,762,522 2,047,091

    8% 0 287,900 1,164,900 1,262,1008% 20 1,614,000 1,515,000 1,721,100

    8% 40 1,960,950 1,607,896 1,843,068

    10% 0 287,900 1,164,900 1,262,100

    10% 20 1,423,000 1,451,000 1,638,10010% 40 1,632,562 1,506,721 1,709,146

  • 7/25/2019 part 2 section 2

    32/58

    PART2, SECTION2

    Page 32 Part 2, Section 2 (4/99) Effective from 1/6/99 The SurveyorsConstruction Handbook

    CLIENT

    WATERCOMPANYLIMITED

    JOBTITLE

    CENTRALISATIONOFAREAOFFICESTUDY

    JOBNO

    3985

    DATE

    29thMARCH1996

    YEAR(SEPT1996)

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    29

    30

    31

    32

    33

    34

    35

    36

    37

    38

    39

    40

    TotalValue

    000

    000

    Capi

    talCos

    ts Building

    Wor

    ks

    1176

    0

    0

    0

    0

    0

    0

    0

    0

    0

    190

    0

    0

    0

    0

    0

    0

    0

    0

    0

    300

    0

    0

    0

    0

    0

    0

    0

    0

    0

    393

    0

    0

    0

    0

    0

    0

    0

    0

    0

    310

    2,369

    Reloca

    tion

    Costs

    15.5

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    16

    Furn

    iture

    8.5

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    9

    Value

    1200

    0

    0

    0

    0

    0

    0

    0

    0

    0

    190

    0

    0

    0

    0

    0

    0

    0

    0

    0

    300

    0

    0

    0

    0

    0

    0

    0

    0

    0

    393

    0

    0

    0

    0

    0

    0

    0

    0

    0

    310

    2,393

    Capi

    talIncome A

    nnua

    lRen

    tal

    -7.5

    -7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5

    -7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5

    -7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5

    -7.5

    -7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5-7.5

    -7.5

    -308

    Land

    Sale

    -55

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    -55

    Value-6

    2.5

    -7.5

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8

    -8-8

    -8

    -363

    Revenue

    Costs

    Fuel

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.4

    1.41.4

    1.4

    57

    Water

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    Maintenance

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    12

    1212

    12

    492

    Rates

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    Cleaning

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.7

    1.71.7

    1.7

    70

    Security

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.1

    7.17.1

    7.1

    291

    Operat

    ion

    Costs

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.2

    5.25.2

    5.2

    213

    Staf

    fCos

    ts

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    0

    Value

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.427.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    27.4

    1,123

    Net

    Cash

    Flow

    1164

    .9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.919.9

    19.9

    209.919.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    319.919.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    412.919.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9

    19.9329.9

    0

    Presen

    tValueof

    1@

    8%

    1

    0.930.860.790.740.680.630.5

    80.54

    0.5

    0.460.43

    0.40.370.340.320.290.270.250.23

    0.21

    0.20.180.170.160.150.140.130.12

    0.11

    0.10.090.090.080.070.070.060.060.050.05

    0.05

    NETPRES

    ENTVALUE

    1165

    18

    17

    16

    15

    14

    13

    12

    11

    10

    97

    9

    8

    7

    7

    6

    6

    5

    5

    5

    69

    4

    4

    3

    3

    3

    3

    2

    2

    2

    41

    2

    2

    2

    1

    1

    1

    1

    1

    1

    15

    1608

    EXPENDIT

    URE

    NVP=1,607,896

  • 7/25/2019 part 2 section 2

    33/58

    PART2, SECTION2

    The SurveyorsConstruction Handbook Part 2, Section 2 (4/99) Effective from 1/6/99 Page 33

    2.2.5.6 TOTALBUILDINGOPTION: DEMOLISH ANDREBUILD VERSUSREFURBISHMENT

    (a) Brief

    The life cycle cost appraisal is to evaluate the life cycle cost effects of the

    following options:

    demolish existing building and rebuild to the clients specific

    requirements incorporatingall-airair conditioning systems;

    refurbish the existing building to meet, as far as practicable, the clients

    requirements, re-using existing systems wherever possible.

    The appraisal is to include all taxation implications for comparative purposes.

    VAT is to be included as the client is VAT-exempt.

    The following costs are to be excluded:

    costs associated with the purchase of land;

    financing charges associated with the redevelopment;

    costs associated with the removal and temporary re-housing of staff

    during the construction period;

    occupancy costs;

    residual values of land or buildings.

    (b) Discount Rate

    The building is in owner-occupation and the clients accountants have advised

    the use of a long-term government stock interest rate of 7%.

    The client has been advised that an inflation rate of 3% is a reasonable

    assessment.

    The discount rate calculation is as follows

    [(1.07)1] 100 = 3.88%

    [(1.03)1]

    The client has agreed that the discount rate can be rounded to 4%.

    (c) Building Life

    It has been agreed with the client to use a 20-year life cycle.

    (d) Description of Existing Building

    Late 1950s office block of multi-storey framed construction with curtain wall

    cladding to front and rear. Solid party walls to both sides. Single-storey

    concrete basement.

    (e) Description of Existing Engineering Services

    Gas-fired low pressure hot water boiler situated in basement serving perimeter

    convector system with warm air ventilation to central parts of the