Upload
naresh-raju
View
217
Download
0
Embed Size (px)
Citation preview
8/9/2019 Part I Protection Philosophy of Electrical Equipments
1/25
Need for protection of electrical equipment
All the electrical equipment must be protected against internal and external
faults, a well a abnormal conditions which may endanger the equipment or
the system. Appropriate relays and devices have to be provided, to detect the
fault and potentially dangerous conditions and to isolate the concern
equipment at the earliest in order to minimize the damage.
The basic requirements of sensitivity, selectivity and speed
have to be met by provision of carefully selected relays and relaying
schemes. Since failure of a protection to operate cannot be ruled out, and it
can lead to damage of costly equipment, it is necessary to provide back upsin the form of redundancy of relays, local or upstream back up relay etc.
However, continuity of power generation is also of utmost importance, and it
dictates that the risk of tripping (due to maloperation of the protection) when
a tripping is not really necessary, be minimized. This risk is related directly
to te number of relays and other elements in the protection scheme and its
complexity. Therefore, superfluous relays and devices must not to be
provided, and the protection schemes must be made as simple as possible.
Redundancy and back ups must also be minimized and tendency of over-
protection checked.The protection relays must be connected to automatically isolate the
endangered equipment if the damage is imminent or short circuit has already
occurred. However, in cases where the equipment or system is not
immediately endangered and can continue in service for some more time, the
protective devices should be connected to initiate only an alarm. This would
enable the plant operator to take the corrective steps and prevent a tripping,
or to prepare for outage of equipment (by changing over to standby
provisions or bringing down the unit load).
It is also important that the control room operator is not burdened
or confused with too many alarms. The alarm fascia on the UCB is thereforeto be used for annunciating only those abnormal conditions for which the
UCB operator has to take some distinct preventive or restorative action.
While tripping of all main equipment has to be annunciated in UCB, the
cause of tripping need not to be annunciated unless the UCB operator must
know it immediately to decide his future course of action. It is generally
adequate to register the cause of DAS printout, CRT display and / or with
8/9/2019 Part I Protection Philosophy of Electrical Equipments
2/25
hand reset flags on protective and auxiliary relays in relay panels or
switchgear.
INTRODUCTION TO MOTORS:
In present there is wide range of motors and its
characteristics are taken into existence. The present day tendency is to
employ motors to limit their thermal margins and characteristics of motor
starting current to flow for time in excess of motor starting time.
Usually in most of applications we use induction motor due
to its inherent good characteristics, easy speed control and good protection
scheme. The three phase induction motor principle is that the three phase
voltage produces current in the stator windings which sets up a rotating
magnetic field. The field flux cuts the short circuited rotor conductor andinduces a current in it. The interaction of flux and current produces torque
which causes rotation. A torque increase until it reaches maximum value, the
value at this point is known as full load torque. A further increase in speed
causes the torque to decrease until it would become zero if 100% speed
could be reached. At zero speed the torque is in excess of that demanded by
the fan and hence the motor accelerates. The speed increases studily as the
excess torque is roughly the same value up to 30% speed. After 40% speed
there is a large excess of torque so that the machine accelerates quickly until
it delivers the amount of torque required by the fan. If the fan dampers wereclosed then the required torque is far less, the excess torque and therefore the
acceleration is greater and the machine runs up to speed quickly and delivers
the amount of the torque required by the fan.
The squirrel cage induction motor operation is simple to
understand as well as the speed and torque variation is simple.
The protection of motor will be so far simple. While
applying protection motor characteristics should be carefully considered.
The conditions for which motor protection is required can be divided into
two categories.
1.
External conditions2.
Internal faults
•
Unbalanced supply voltages
•
Under voltage
•
Single phasing
8/9/2019 Part I Protection Philosophy of Electrical Equipments
3/25
These are some of the external conditions due to which fault
occurs.
Internal faults occurs due to
•
Bearing failures
• Internal fault
• Earth faults
The motor should develop the protection against all the faults. The
protection applied for a particular machine depends on its size and the nature
of load to which it is connected. However, all the motors should be provided
with over load and unbalanced voltage protection. This can often be
provided in a single relay.
There are various types and sizes of motors used in a power station.These are used for various purposes as prime mover. Apart from the simple
motors used in different areas, there are HT motors used in conjunction with
various heavy duty equipments. These are FD, PA & other fans, boiler feed
pumps, CW pumps etc..These motors have certain special features like
cooling, auto starting, inter locking & controlling.
The basic principles underlying the operation of these fans are by
and large as explained in the previous sections. But the more important
factors that need attention is the start up these motors, lubrication etc.
Fans are used to produce the draught in the furnace or to handlethe pulverized fuel or to recirculate the flue gases or to provide cooling air
for various equipments.
The forced draught fan (FD) provides atmospheric air for
combustion and the induced draught fan (ID) handles the products of
combustion. Primary air fan (PA) handles cold atmospheric or hot air to
carry the pulverized fuel. Mill fans are used to produce draught in the
milling system.
8/9/2019 Part I Protection Philosophy of Electrical Equipments
4/25
Mill-7ETO ash slurrySWBD#OCB
MILL
Coal conveyor
FD fan
VFD TRFR (ID
FAN) CH2VFD TRFR (IDFAN) CH1PA FAN
BCW pump
ECW pump (SG)
ECW pump (TG)
ESP ser. Tran 1
ESP ser. Tran 2
CEP
CEPSpare Tranfeeder
BUS PT
Spare motorfeeder(1200KW)CT service tran
CW pump
UST
FEEDER PT
29 MF4
28 TIE2A
27 MF4
26 MF4
25 MF4
24 MF4
23 MF5
22 MF2
21 TRF1
20 TFR1
19 MF1A
18 MF6
17 MF9
15 TRF3
14 TRF3
13 TRF3
11 MF3
10 MFE9 TIE1A8 TRF2
7 BPT1
6 MF2
5 TRF3
4 MF1D
3 TRF2
2 FPT1
1 1FI
I N C O M E R
F R O M
U A T
T i e t o s t n .
S w b d O C A
6 . 6
K V s w i t c h
g e a r
8/9/2019 Part I Protection Philosophy of Electrical Equipments
5/25
DISCRIPTION OF SWITCH BOARD:
The given single line diagram illustrates the power distribution from
6.6 KV feeder to various sub feeders. The power generated at 6.6 KV and
step down to the 6.6 KV and from 6.6 KV feeder power distributed to 29 panels. In that many companies of ESP service transformer, ECW pump,
VFD transformer (ID fan), FD fan, coal conveyer, ash slurry switch board
and mill.
To the 6.6 KV bus there will be two supplies connected to the
vaccum circuit breakers. The switchgear is fed from a UAT(unit auxiliary
transformer ) rated 21KV/6.9KV,25MVA.The board is having an alternate
supply from station transformer source so that failure of any transformer
does not hamper the starting up/ shutting down, or normal operation of the
plant.
A proper protection is provided by using CT’s shown in single linediagram for the incomer. From the 6.6 KV bus all the equipments are
supplied through vaccum circuit breakers. Each having the protective relays
of over current, over load and the earth fault protections. CT’s are connected
so that the current in main supply is stepped down according to protective
relay magnitude so that we can give suitable protection. Economically in the
single line diagram as shown motors in pumps and mills are effectively
grounded through impedance to limit the fault current.
In ash slurry again this 6.6 KV stepped down to 433V and this
433V supply 2 degrees given to various motors. There will be five motorswhich will feed the ash and water to the ash pot which located 2 to 3 Km out
of plant. In the switch gear we also have a spare motor feeder and a spare
transformer feeder so that if there is failure of supply from UAT then it will
be fed from spare motor and transformer.
UAT RATINGS:
Rated voltage : 25MVA
No load voltage :
HV side : 21KVLV side : 6.9KV
Line current
HV side : 688.1A
LV side : 2094.3A
8/9/2019 Part I Protection Philosophy of Electrical Equipments
6/25
TECHNICAL DATA OF MOTORS USED:
parameters FD fan PA Fan CEP MILL
Rating(KW) 1280 2940 962 583
Derated rating for
50C
1200 2750 900 525
Rated voltage(V) 6000 6600 6600 6600
Frequency(Hz) 50 50 50 50
Permissible
variation of
Voltage %
Freq %
+/-10.0
+/-3to5
+/-10.0
+/-3to5
+/-10.0
+/-3to5
+/-10.0
+/-3to5
Min perms starting
voltage %
80 80 85 90
Rated speed(RPM) 995 1493 1486 589
At Rated volt & freq
Full load current
(A)
No load current
126.5
42.0
273.0
59.0
96.5
31.0
68.0
33.0
p. f. at load100%
75%
50%
no load
starting
0.86
0.83
0.76
0.04
0.13
0.97
0.9
0.87
0.05
0.11
0.85
0.82
0.74
0.017
0.208
0.72
0.66
0.54
0.0179
0.356
Starting current (%)
at
100% voltage
min stating voltage
600
460at80%@
RV
600
460at80%
@RV
600
498at85%
@RV
450
405at90%
@RVEfficiency at rated
volta
100%
75%
50%
96.6
96.6
96.0
96.8
96.8
96.4
95.8
95.8
95.2
94.1
94.1
93.2
CT Ratio 150/1A 315/1A 125/1A 75/1A
8/9/2019 Part I Protection Philosophy of Electrical Equipments
7/25
LISTING OF PROTECTION RELAYS OF MOTORS:
FD FAN :
• Definite time over current alarm relay – CTU 32
• Inverse time over load relay – CDGM 12
• Instantaneous over current relay – CAG 37
• Sensitive earth fault relay – CTUM 13
PA FAN:
•
Definite time over current alarm relay – CTU 32
• Inverse time over load relay – CDGM 12
• Sensitive earth fault relay – CTUM 13
CEP:
• Definite time over current alarm relay – CTU 32
• Inverse time over load relay – CDGM 12
• Instantaneous over current relay – CAG 37
•
Sensitive earth fault relay – CTUM 13
MILL:
• Definite time over current alarm relay – CTU 32
• Inverse time over load relay – CDGM 12
• Instantaneous over current relay – CAG 37
• Sensitive earth fault relay – CTUM 13
8/9/2019 Part I Protection Philosophy of Electrical Equipments
8/25
ABBRIVATION:
FIRST LETTER – OPERATING QUANTITY:
A-
Phase angle comparison.B- Balanced currents
C-
Currents (amps)
D - Differential
E -Direction
F -Frequency
I - Directional current
K – Rate of rise of current
M - Manual
O – Oil pressure
P – Poly phase VA
R – Reactive VA
S – Slip frequency
T – Temperature
V – Potential (volts)
W – Watts (power)
X – Reactance
Y – Admittance
Z – Impedance
SECOND LETTER – MOVEMENT:
A – Attracted armature
B – Buchholz
C – Induction cup
D – Induction disc
G – Galvanometer (moving coil)
I – Transactor
J – Mixed typesM – Magnate (polarized)
P – Plug
R – Rectifier
S – Synchronous motor
T – Transistor
W – Weight
8/9/2019 Part I Protection Philosophy of Electrical Equipments
9/25
THIRD LETTER – APPLICATION:
A – Auxiliary
B – Testing
C – Carrier or counting
D – Directional
E – Earth (ground)
F – Flag and alarm indicator
G – General or generator
H – Harmonic restraint
I – Inter lockedJ – Tripping
JE – Tripping (elect – reset)
JH – Tripping (hand – reset)
JS – Tripping (self – reset)
JC – Control
K – Check alarm
L – Load limiting
M – Semaphore or motor
N – Negative sequence
O – Out of stepP – Potential
Q – Alarm
R – Reclosing
S – Synchronizing
T – Timer or transformer
U – Definite time
V – Voltage restraint
W – Pilot wire
WA – InterposingWJ – Inter Tripping
X – Supervisory
Y – Flash back (back fire)
Z – Special application
ZS – Zero sequence
8/9/2019 Part I Protection Philosophy of Electrical Equipments
10/25
FOURTH LETTER:
M – Special variations
First Figure: Indicates the number of units in the relay essential to its
operation – not including seal – in auxiliary units.
Second Figure: Indicates particular characteristics of one of a group of
similar relay e.g. CDG 11, CDG 12, CDG 13 and CDG 14 are all inverse
time over current relays but with different characteristic curves.
For example•
CDG
C-currents
D- Induction disc
G- General or Generator
• CTUM
C-current
T-Transistor
U-Definite timeM-special variations
RELAYS:A relay is a device which detects the fault and supplies information to
the breaker for circuit interruption. A typical relay circuit can be divided into
in to three parts.
1.
The primary winding of a current transformer which is connected in
series with circuit to be protected. The primary winding often
consists of main conductor itself.2. Second circuit is secondary winding of CT connected to relay
operating coil.
3.
The third circuit is tripping circuit, which consists of source of
supply, trip coil of circuit breaker and the relay stationary contacts.
Under normal load conditions, the emf of secondary winding of CT
is closed to relay contacts. This keeps the trip coil of circuit breaker
8/9/2019 Part I Protection Philosophy of Electrical Equipments
11/25
unenergized. Consequently, the contacts of breaker remain closed
and it carries the normal load current.
When fault occurs, a large current flows through motors
•
Overload protection• Over current protection
• Earth fault protection
• Differential protection(for HT Motors)
• Locked rotor protection(for special motors)
The job of relay is to discriminate between a fault within its zone of
protection and all other system conditions. It must act energize the trip coil
of its associated circuit breaker and provide security against fault tripping for
fault outside zones. A relay is made secure and dependable by designing into
it a logical decision making capability such that it produce correct output.
When a fault occurs in a system results sudden rise in current towards
the fault associated with reduction of voltage and system. These power
signals are very high and are converted into lower level by instrument
transformer and fed to relays.
These relays decide depending on the logic built in energize trip coil
of circuit breaker whose contacts are series with faulty line, which move
apart very rapidly. As current through breaker passes through zero, the space
between contacts become a dielectric and disconnects the faulty section from
rest of the system. The entire process from time of initiation of fault through
its final clearance takes between 30 to100ms depending on protectionsystem used.
The common protective relays are Inverse time Overcurrent relay
usually fed from protective type CT. The most frequent type of fault is an
Earth fault through which phase connected. Over current relay with detect
earth fault current above relay setting. The earth fault current may be limited
in magnitude by neutral Earthing impedance or by earth connected
resistance.
8/9/2019 Part I Protection Philosophy of Electrical Equipments
12/25
ABOUT THE RELAYS USED:
1. INSTANTANEOUS OVER CURRENT RELAY (CAG 37):
Features:
• Continuously variable current setting
• High drop off/ pickup ratio
• Low transient over-reach
Application:
The type CAG 37 is a highest instantaneous
Overcurrent unit with low transient over reach and a high drop off /
pick up ratio.
Because of its infinitely variable settings and immunity
to offset transients, this relay has special advantages for protection
of feeders connected to high MV sources. Where lines are fed from
high MV sources, the impedance of the line causes a sharp
reduction in the fault current as the distance between the fault and
source increases.
Conventional instantaneous over current protection gives
good discrimination an economy on these lines, but a relay set todetect symmetrical faults at the far end will over reach and cause
tripping for off set faults which are out side the protective zone.
The over current setting must, therefore, be raised in proportion to
the reach of the relay, with consequent loss of coverage for
symmetrical faults at the far end of the line.
General description:
The relay comprises of a standard DC hinged armature
unit fed via a single phase transformer and full wave bridge
rectifier. A residual screw is fitted with armature of the relay to
achieve a high drop off / pick up ratio. A potentiometer is
connected in parallel to the relay coil and adjustment of this varies
8/9/2019 Part I Protection Philosophy of Electrical Equipments
13/25
the effective operating current of the relay over a range of 1 to 2.
The transformer primary winding is center tapped to give a further
1 to 2 adjustment of the relay operating current and together with
potentiometer give an over all adjustment of current setting of 1:4
ratio. Selection of transformer primary tapping is by means of link provided at the rare of the relay cradle. A surge diverter is
connected across the secondary winding of the transformer to limit
the secondary voltage.
8/9/2019 Part I Protection Philosophy of Electrical Equipments
14/25
ALARM TRIP
RYB
OVER CURRENT RELAY
8/9/2019 Part I Protection Philosophy of Electrical Equipments
15/25
TECHNICAL DATA:
Current ratings: 1A or 5A
Settings : 200 – 800 %, } continuously500 – 2000 %} adjustable
Operating time: See Fig 1
Drop off / pick up ratio: Not less than 80% of setting current
Thermal rating
Continuous: Min setting current subject to max of
o 20A
Short time: Max setting time for 15 sec
Burden: 200 – 800 % 500 – 2000 %
Version Version
200% 800% 500% 2000%
At Rated current 0.22VA 0.054VA 0.03VA 0.011
At setting current 1.0 VA 3.5 VA 1VA 5VA
2. INVERSE TIME OVER LOAD RELAY (CDG 12):
Features:
• Two tabs with identical time / current characteristics
•
High torque, ensuring consistent timing even under adverse condition
• Very low over shoot
•
Simple construction, easily accessible
•
Comprehensive range of auxiliary unit ratings
•
Dust tight draw out case and tropicalised finish.
8/9/2019 Part I Protection Philosophy of Electrical Equipments
16/25
Application:
Stand by earth fault protection of neutral Earthing resistance and other
applications requiring long line delay.
General Description:
A non directional heavily damped induction relay which has an
adjustable long inverse definite minimum time / current characteristics. The
relay has a high torque moment combined with low over shoot. The relay
disc is so shaped that, as it rotates, the driving torque increases an off sets
the changing restraining torque of the control spring. This feature combine
with the high torque of the relay induces good contact pressure given at
currents near pick up. Damping of the disc moment is by a removable high
retentivity permanent magnate.
One unique method of winding the operating coil ensures that the time /
current characteristics are identical on each of the two current taps. Selection
of the required current setting is by means of a plug setting bridge which has
a single insulated plug. The higher current tap is automatically connected
GND
R
Y
B
8/9/2019 Part I Protection Philosophy of Electrical Equipments
17/25
when the plug is with drawn from the plug, allowing the setting to be
changed while in service without risk of open circuiting the current
transformers.
The relay operating time can be adjusted by the moment of the disc
back stop which is controlled by rotating a knurled Moulded disc at the base
of graduated time multiplier scale.
Type CDG 12 is a single pole relay and is available in this version.
TECHNICAL DATA:
Current ratings: the operating coil can be supplied suitable for
Operation from 1A & 5A.
Settings: CT secondaries and the current setting available
Are 15 % and 20 % of rated current.
Starting current: 85 to 105 % of current settings.
Closing currents: 85 to 105 % of current settings.
Resetting current: The disc will completely reset at 80% or more of
Time / current characteristics given in fig.
Resetting time with time multiplier set at 1.0, the resetting
Time is 40 sec
Burden: 6.0 VA at current setting
Thermal rating: the relay will with stand twice the current setting
Continuously for 60 degree centigrade rise in coil
Temperature & 50 time the current setting for the
Operating time of the relay.
8/9/2019 Part I Protection Philosophy of Electrical Equipments
18/25
8/9/2019 Part I Protection Philosophy of Electrical Equipments
19/25
3.DEFINITE TIME OVER CURRENT RELAY (CTU 32):
Features:
•
Consistent accuracy
•
Reliability•
Low burden
•
Reduced maintenance
•
Long life
•
Immunity to transience and surges
•
Fast reset
•
Exceptionally low over shoot
Application:
Type CTU relay can be used for definite time over current
protection against phase and earth fault on medium and low voltage
distributions.
These relays are particularly suitable on systems where there is a
wide variation in source impedance.
Another important protection of CTU relay is the field of stalling
protection of motors. When thermal over load relay does not provide
protection against stalling, separate definite time over current relay like CTU
can be used to provide the same.
General Description:
The operation is illustrated by block diagram shown in figure
When the positive peak of the input signal exceeds the reference
level the time delay circuit starts and after a preset time drives the outputrelay.
8/9/2019 Part I Protection Philosophy of Electrical Equipments
20/25
Instantaneous high set unit, when fitted, uses alternate half cycle for
measurement and through a separate level detector drives a separate output
relay. The static circuitry is fully protected against high transient voltages.
TECHNICAL DATA:
A. C. Burden: 0.15 VA per phase at lowest setting.
2.0 VA per phase at highest setting.
INPUT
TRANSFORMER
HIGHSET LEVELDETECTOR
HIGHSET OUTPUT
CURRENTLEVEL
DETECTOR
TIME CONSTOUTPUT
T R A N S I E N T S U P P R E S S O
DEFINITE TIME OVER CURRENT RELAY
8/9/2019 Part I Protection Philosophy of Electrical Equipments
21/25
GN
A
50
R
Y
B
TO DDCMIS SPARE
51I1
51i2
50L
50
50N
CT
RY
B
SURGE
8/9/2019 Part I Protection Philosophy of Electrical Equipments
22/25
GN
A
V
C
B
CT
50
R
Y
B
TO DDCMIS SPARE
51i1
51i2
50
50N
RYB
87M
8/9/2019 Part I Protection Philosophy of Electrical Equipments
23/25
GN
A
RY
B
50
R
Y
B
TO DDCMIS SPARE
51I1
51i2
50
50N
CT
SURGE
8/9/2019 Part I Protection Philosophy of Electrical Equipments
24/25
52a
52Tc
51i1 51i1
86
50
50N2
86
51i1 51i2CsC N T
43SS
Tripping circuit for FD FAN, CEP & MILL
8/9/2019 Part I Protection Philosophy of Electrical Equipments
25/25
52a
52Tc
51i1 51i1
86
87 50N2
86
51I1 51i2CsC N T
43SS
Tripping circuit for PA FAN
TRIPPING CIRCUIT