EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-1
PART I -- SCHEDULE
SECTION C
PERFORMANCE WORK STATEMENT
TABLE OF CONTENTS
C.1 INTRODUCTION ...................................................................................................................... 2
C.1.1. Project Purpose and Scope............................................................................................................ 2
C.1.2. Objectives and Programmatic Requirements ................................................................................ 2
C.1.3. Contractor Performance and Key Requirements .......................................................................... 3
C.2 WORK SCOPE ........................................................................................................................... 5
1.4.1.0 TRANSITION .............................................................................................................................. 5
1.4.1.1 SOIL REMEDIATION .............................................................................................................. 7
1.4.1.2 UNDERGROUND TEST AREA (UGTA) ................................................................................ 8
1.4.1.3 INDUSTRIAL SITES ............................................................................................................... 14
1.4.2.1 PROGRAM INTEGRATION ................................................................................................. 19
1.4.3.3.05 RADIOACTIVE WASTE ACCEPTANCE PROGRAM (RWAP) .............................. 35
1.4.8 POST-CLOSURE MONITORING, MAINTENANCE, AND PERMITS .......................... 37
Exhibit C-1, Regulatory Documents .................................................................................................... 40
Exhibit C-2, Information Technology Systems ................................................................................... 43
Exhibit C-3, NNSS Waste Generator Map .......................................................................................... 54
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-2
C. BACKGROUND
The U. S. Department of Energy (DOE) Nevada National Security Site (NNSS), formerly known
as the Nevada Test Site, was established in 1950 and is approximately 1,360 square miles. The
NNSS has a long history of supporting national security missions through full-scale atmospheric
and underground nuclear testing, with the last test occurring in 1992. Today the NNSS helps
ensure the security of the United States and its allies by supporting the stewardship of the nuclear
deterrent, providing emergency response capability and training, contributing to key
nonproliferation and arms control initiatives, and providing long-term environmental
stewardship. The National Nuclear Security Administration (NNSA) oversees the national
security mission and overarching management of the NNSS. The Office of Environmental
Management (EM) Nevada Program is responsible for remediating Federal Facility Agreement
and Consent Order (FFACO) (1996; as amended) sites on the NNSS and portions of the Nevada
Test and Training Range (NTTR) and the Tonopah Test Range (TTR) that were contaminated
during nuclear testing operations and for operating the NNSS radioactive waste management
facilities.
C.1 INTRODUCTION
C.1.1. Project Purpose and Scope
The Environmental Program Services (EPS) scope of work requirements include site
characterization and assessments, field services, remedial action and waste acceptance
services, program management, and Strategic Communication support. The Contractor
shall comply with the requirements of the FFACO that was agreed to by the State of
Nevada, DOE, the U.S. Department of Defense (DOD); and DOE Legacy Management
(LM). The Contractor shall provide all personnel, materials, and supplies, required to
perform under this Contract.
C.1.2. Objectives and Programmatic Requirements
The Contractor shall achieve the objectives stated below while continuing to
maintain compliance throughout performance of this Contract.
Achieve continuous cost and process improvements and optimization for contract
activities while maintaining quality standards.
While supporting continuity of on-going site cleanup operations, identify and
eliminate systems and processes that are no longer necessary, and maintain safe
configuration of the systems. Reduce systems not directly required to maintain
safety and environmental compliance. Identify ways to further streamline
implementation of requirements to perform the most cost effective approach for
environmental program services.
Develop, finalize and implement approved environmental remediation, closure,
and monitoring under the Nevada FFACO.
Maintain public and worker safety and health, and environmental protection.
Reduce the overall EM Nevada Program costs.
Comply with all applicable Federal, State, and local laws and regulations,
Executive Orders, DOE Orders (and other types of directives), and Regulatory
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-3
Permits, Agreements, Orders and Milestones (both State and Federal) (See
Section J, Requirements Sources and Implementing Documents [List A] and List
of Applicable DOE Directives [List B]).
Provide deliverables to DOE in accordance with all requirements of this Contract
and those identified in each individual task order.
C.1.3. Contractor Performance and Key Requirements
The Contractor must evaluate short-term and long-term impacts to cost, schedule, and
legal and regulatory requirements. To achieve the objectives stated below, the Contractor
shall use its best efforts to streamline implementation of requirements while continuing to
maintain compliance throughout performance of this Contract.
The Contractor shall furnish all personnel, facilities, equipment, material, services and
supplies (except as set forth in this Contract to be furnished by the Government), and
otherwise to do all things necessary to accomplish work in a safe, secure (pursuant to 10
Code of Federal Regulations 824), integrated, effective and efficient manner.
This contract reflects the application of performance-based contracting approaches and
techniques that emphasize results/outcomes and minimize “how to” performance
descriptions. The Contractor has the responsibility for total performance under this
contract, including determining the specific methods for accomplishing the work. The
Contractor shall continuously assess opportunities to eliminate systems and facilities, and
pursue consolidation of operations and personnel work areas whenever/wherever a cost
benefit is derived. The Contractor shall be responsible for planning, integrating,
managing and executing the programs, projects, operations and other activities as
described in this Performance Work Statement (PWS).
The Contractor shall provide general operations oversight and program management
functions to enable safe operations. In addition, the Contractor shall be responsible for
the operations, environment, safety, health and quality assurance within its own
organization and its subcontractors’ organizations.
The Contractor shall ensure that its technical approach and execution of work is
compliant with the applicable statutory and regulatory requirements and shall annually
certify and provide to DOE its compliance with environmental requirements. The
Contractor shall comply with and provide DOE with services necessary for its
compliance with all applicable federal, state, and local requirements and agreements
including the protection and preservation of cultural, historic, or archeological resources.
The Contractor shall be responsible for all work necessary to obtain regulatory
acceptance including supporting legal/regulatory reviews and comment resolution. No
communication with regulators is authorized without prior DOE notification. The
Contractor shall recognize and work within the constraints imposed by this Contract and
other regulatory agreements between DOE and regulatory agencies. Regulatory
documents include, but are not limited to, all applicable laws, regulations, permits, plans,
orders, and agreements.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-4
The Contractor shall integrate all activities with other DOE contractors/tenants in areas of
joint interface. This includes coordination with the NNSS Management and Operating
contractor to ensure compliance Real Estate Operations Permit procedures, cyber security
program requirements, and requirements to conduct activities as described in this PWS.
Installation and maintenance of infrastructure (e.g., repair of sump liners, maintenance
requiring earth work, etc.) is the responsibility and scope of the NNSS Management &
Operating (M&O) contractor. The Contractor shall coordinate activities on the
NTTR/TTR with the United States Air Force.
The Contractor shall provide support to DOE relating to regulatory documents and
agreements, in the form of technical experts and site specific knowledge of operations,
for regulator interactions, independent facilitation services, the development and
implementation of regulatory strategies, and the public comment process. The Contractor
shall maintain and update, as necessary, the programmatic remedial action documents.
As part of maintaining these programmatic documents, the Contract shall coordinate
working group communications, scoping meetings, information exchanges, and routine
meetings with DOE and the regulatory agencies to jointly identify necessary changes and
reach consensus on the contents of the document as part of the updating process. These
documents are listed and described in Exhibit C-1, Regulatory Documents.
If the Contractor submits a deliverable that DOE determines does not comply with the
terms of the contract/ task order or regulatory requirements, including but not limited to,
laws, regulations, orders, permits, plans, or agreements, the Contractor’s revision or
correction of the document/submittal shall be at no additional cost to DOE. This
determination shall be at DOE’s sole discretion. DOE notes that this compliance
determination does not apply to the overall quality of the document (e.g. word
processing) unless the errors impact the function and understanding of the document. If
all of the contractual requirements are met such as timing of the submittal, inclusion of
information required, factual accuracy, etc. are provided, the document will be accepted.
The applicable deliverables will be provided in Section J, Deliverables of each individual
task order. The Contractor shall comply with all deliverable dates and all regulatory
milestone dates. Regulatory milestone dates can be found in documents such as the
FFACO, Water Pollution Control Permit NEV 96021 for the E-Tunnel Waste Water
Disposal System, and regulatory permits. Deliverables without specific dates identified
shall be established by the Contractor during Contract Budget Base (CBB) development
and throughout the Contract’s period of performance as approved by DOE. Changes to
regulatory milestones do not alleviate Contractor responsibility to meet contractual or
CBB milestone dates without specific approval by DOE.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-5
C.2 WORK SCOPE
1.4.1.0 TRANSITION
The Transition period shall be 90 calendar days. The Contractor shall be prepared to fully
mobilize when the NTP is issued.
The Contractor shall perform all activities to support transition, including, but not limited to,
system walk-downs, procurement, review and acceptance of programmatic and operational
documents and procedures, and assisting DOE in verifying whether transition requirements have
been met prior to the end of Transition.
The Contractor shall perform a due diligence review of the systems and environmental
conditions within its assigned area of responsibility. The Contractor shall provide a written
declaration to DOE of its formal acceptance of responsibility for the assigned scope, systems,
and environmental/regulatory conditions.
The Contractor shall mobilize its Transition Management Team (comprised of the Program
Manager, all other Key Position personnel identified in the Contract, and the Human Resource
and Business Services personnel necessary to immediately begin transition activities) to the site
not later than 7 days after NTP. The Contractor shall determine the number of Human Resource
and Business Services personnel necessary to support transition. The objective of the Transition
period is to establish safety, operations, business, and human resources management that will
enable the Contractor to deliver requirements on time and within established funding. At a
minimum, the Contractor shall complete the following within the Transition period:
a. Transition responsibility for all facilities, facility operations, and environmental permits;
b. Perform due diligence walk downs and assessments of facilities and other areas;
c. Modify, with DOE approval (as required), existing program documents (e.g., Worker
Safety and Health Program Plan, Integrated Safety Management System description,
etc.);
d. Hire, train, and transfer of clearances for all required staff;
e. Establish procurement processes for materials, equipment, supplies, parts, and
subcontractors; and
f. Perform other actions necessary to enable the Contractor to formally accept responsibility
for the entire PWS within 90 days after NTP.
Within 48 hours following the NTP, the Contractor shall release on its own website a brief
Executive Summary of its offer and must meet the requirements of Section H, DOE-H-2048
Public Affairs – Contractor Releases of Information (OCT 2014). The purpose of this Executive
Summary is to provide immediate release of relevant information to stakeholders and the public
at large. It should include the following elements:
a. Name of Contractor, including the identification of any teaming partners and critical
subcontractors (if applicable) and a description of the experience that each brings to the
project;
b. Summary/description of Contractor’s technical approach (e.g., planned accomplishments,
cost savings anticipated);
c. Organization’s structure and identification of Key Personnel; and
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-6
d. Brief overview of Contractor’s past performance (i.e., success stories).
The Contractor shall submit a Transition Plan that describes their process for conducting an
orderly transition and minimizing any adverse impacts on continuity of operations. The plan
shall include a schedule with defined milestones, milestone risks and the proposed approach to
minimize the identified risks.
The contractor shall submit a Transition Plan for DOE approval five (5) business days after
issuance of NTP. The Transition Plan shall include a schedule and description of the activities
necessary to transition the work from the incumbent contractor in a manner that (1) ensures that
all work which the new contractor shall be responsible for under the contract is continued
without disruption; (2) provides for an orderly transfer of resources, responsibilities, and
accountability from the incumbent contractor; and (3) provides for the ability of the new
contractor to perform the work in an efficient, effective, and safe manner.
The Transition Plan shall address how all Government property, including Government furnished
and contractor-acquired property (i.e. materials) and associated records, currently assigned to the
incumbent contractor, will be transferred to the new contractor during the transition period.
The Transition Plan shall address coordination with other site entities and is required to ensure
continuation of services by the new contractor. The Transition Plan must ensure there is no loss
or degradation of the services that are provided to DOE and its contractors. The new contractor is
responsible for performing due diligence to ensure that all activities, deliverables, and actions to
be completed by the end of the transition identified in the PWS are included in the Transition
Plan.
In accordance with Section H, Integrated Work Control Systems and Reporting Requirements,
the Contractor shall submit an Initial Contractor Performance Baseline (CPB) that matches the
Contractor’s proposed total value for the initial task order and provides work planning and costs
for all PWS elements to be performed under the initial task order within seven days from the
NTP (at the lowest level WBS for cost tracking and reporting and referenced to a CLIN level).
The Contractor’s Transition Plan required shall include a description of the Contractor’s
implementation of human resource management consistent with Workforce Transition and
Contractor Human Resources Management requirements as described in Section H, Clause H.3
through H.8, including:
(a) Expected workforce composition and any immediate or anticipated workforce
restructuring;
(b) Identification of any existing issues under the National Labor Relations Act (NLRA)
and its plan for engaging with any labor representatives;
(c) A schedule for preparation and submission of any bargaining unit parameters
requests;
(d) Identification of any prevailing wage requirements, including any requirements under
section 4(c) of the Service Contract Labor Standards statute, Construction Wage Rate
Requirements statute, as well as any NLRA requirements with respect to
determination of wages and benefits;
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-7
(e) Description of processes for handling labor standards determinations for work
packages;
(f) Description of any pension and post-retirement benefit plans;
(g) A plan for identification and resolution of any legal issues regarding any of the above,
including the Contractor’s plan for engaging outside counsel as needed; and
(h) A plan for communicating and engaging with DOE on these matters.
Transition Key Performance Milestones
Milestone Date
Executive Summary Placed on Website Within 48 hours after NTP
Complete mobilization of Transition Management Team Within 7 days after NTP
Submit Contract Transition Plan Within 15 days after NTP
Submit Initial CPB Within 7 days after NTP
Submit Transition Status Reports Weekly, through transition
Operational Responsibility Acceptance Declaration Within 90 days after NTP
1.4.1.1 SOIL REMEDIATION
The Soils Activity includes impacted sites which are the result or by product of historical
nuclear testing activities conducted at the NNSS and NTTR, including TTR, which produced
radionuclide contamination of near surface soils. The objective of the Soils Activity is to
characterize near-surface soil contamination sites and perform corrective actions, where it is
cost effective and will yield significant reduction in risk to human health and the
environment. Work scope activities are driven by the implementation of the FFACO
technical strategy. The scope encompasses characterization, assessment, corrective action
evaluation, and corrective action implementation (e.g. clean closure; closure in place,
capping, and establishing land use restrictions). Fieldwork is performed as authorized by
applicable directives, including Real Estate Operating Permits. Note: New National
Environmental Policy Act-mandated Environmental Assessment (EA) documentation will not
be required for Soils activities; the Soils Corrective Action Units (CAUs) are included in the
Environmental Impact Analysis and Record of Decision (ROD) for the NNSS Environmental
Impact Statement (EIS).
The end state is to complete the corrective actions at all sites as defined in the FFACO.
Most sites will be stabilized for restricted use (i.e., contamination remains in place)
appropriate to the risk posed by residual contamination, while others will be stabilized for
unrestricted surface use. For those sites where contamination remains in place, appropriate
long-term remedial actions will be established including but not limited to long-term
monitoring, cap inspections, and use restrictions as applicable. To facilitate closure, Soils
Corrective Action Sites (CASs) are grouped into CAUs based on geographic location,
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-8
contamination type, and investigative strategy.
Soil Remediation Requirements Documents
Document Number Title
N/A Federal Facility Agreement and Consent Order
DOE/NV--1478-REV. 1 Soils Activity Quality Assurance Plan
DOE/NV--1475-REV. 1 Soils Risk-Based Corrective Action Evaluation Process,
Revision 1
The Contractor shall perform all activities to complete project closeout documents in
accordance with all FFACO and DOE program requirements. Characterization of existing
soils remediation sites have been performed based on existing data. This data guided
appropriate investigation and corrective action tasks, as well as selecting corrective actions.
Soil Remediation Key Performance Milestones
Milestone Date
Complete Soils Closeout documents 9/30/2020
1.4.1.2 UNDERGROUND TEST AREA (UGTA)
The UGTA activity defines the hydrologic boundaries of NNSS and surrounding area
groundwater resources that may be unsafe for domestic or municipal use. Data analysis and
modeling activities allow for informed decisions to ensure risk to public health and the
environment posed by impacted groundwater are, and will remain, within protective levels.
The end state will be achieved with the completion of a modeled contaminant boundary,
negotiated regulatory boundary, and monitoring well network(s).
To facilitate closure, UGTA CASs are grouped into CAUs based on geographic location.
Work scope activities for a CAU are driven by the implementation of the FFACO technical
strategy. Modeling of CAUs is required to determine the location and potential future extent
of contaminant migration which supports how contaminant boundaries are defined in order to
design the corrective action monitoring well network. The installation of the groundwater
wells, development and testing of GW wells, characterization and sampling should be
compared against the NEPA analysis performed in the EIS and any recommendation for
additional NEPA analysis shall be performed by Contractor and provided to the DOE NCO
for review/approval. These activities will be performed at multiple sites and specific data may
need to be developed and analyzed for each of the site locations. These activities provide the
complete basis for a Corrective Action Decision Document/Corrective Action Plan
(CADD/CAP) for regulatory approval. Corrective action involves the completion of those
activities required in the CADD/CAP consistent with Exhibit C-1. Compliance with the
closure criteria leads to a Closure Report (CR) and notice of completion from Nevada
Division of Environmental Protection (NDEP). The Contractor shall conduct all activities
necessary to ascertain the information for the preparation of FFACO documents. This
includes the preparation of all regulatory documents, submittal for review and comment,
addressing all comments and final publication. Activities on the NTTR/TTR will require
coordination with the United States Air Force.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-9
UGTA Requirements Documents
Document Number Title
N/A Federal Facility Agreement and Consent Order
N/A Annotated Outline for UGTA Corrective Action
Investigation Plan
N/A Standardized FFACO Outline Underground Test Area
Corrective Action Decision Document/Corrective Action
Plan (CADD/CAP) Revision 1
N/A Standardized Federal Facility Agreement and Consent
Order (FFACO) Outline Underground Test Area (UGTA)
Closure Report (CR) Revision 1
DOE/NV--1525-REV. 1 Nevada National Security Site Integrated Groundwater
Sampling Plan
DOE/NV--1450-REV. 2 Underground Test Area Activity Quality Assurance Plan
Nevada National Security Site, Nevada
DOE/NV--343 Underground Test Area Project Waste Management Plan,
Rev. 3
DOE/NV--370-Rev.5 Fluid Management Plan for the Underground Test Area
Project
DOE/NV--1312-Rev. 2 Phase II Corrective Action Investigation Plan for Corrective
Action Units 101 and 102: Central and Western Pahute
Mesa, Nevada Test Site, Nye County, Nevada, Revision 2
with ROTC 1 and 2
DOE/NV--1566-REV. 1 Corrective Action Decision Document/Corrective Action
Plan for Corrective Action Unit 97: Yucca Flat/Climax
Mine Nevada National Security Site, Nevada, Revision 1
N/A Technical Basis Agreement Document for Underground
Test Area Corrective Action Unit 99 Rainier
Mesa/Shoshone Mountain Revision 1, January 2013
DOE/NV--1031-ROTC1 Corrective Action Investigation Plan for Corrective Action
Unit 99: Rainier Mesa/Shoshone Mountain, Nevada Test
Site, Nevada
DOE/NV--1588 Corrective Action Unit (CAU) 99: Rainier Mesa/Shoshone
Mountain Final Flow and Transport Model Report,
Revision 1, January 2018
DOE/NV--1595 Case Study Analyses of Radionuclide Transport in Variably
Saturated Media at Rainier Mesa
DOE/NV—1435 Completion Report for Well ER-EC-11 Corrective Action
Units 101 and 102: Central and Western Pahute Mesa
DOE/NV—1576 Completion Report for Well ER-4-1 Corrective Action Unit
97: Yucca Flat/Climax Mine
DOE/NV/11718—1182 Completion Report for Well ER-12-3 Corrective Action
Unit 99: Rainier Mesa – Shoshone Mountain
DOE/NV—1589 Underground Test Area Calendar Year 2016 Annual
Sampling Analysis Report Nevada National Security Site,
Nevada
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-10
1.4.1.2.02 Central and Western Pahute Mesa (CAUs 101 & 102)
The scope of work for Central and Western Pahute Mesa is defined in subsequent sections.
Central and Western Pahute Mesa (CAUs 101 & 102)
Key Performance Milestones
Milestone Date
Annual Sampling Report Consistent with issuance of Task
Order
Submit External Peer Review Report Consistent with issuance of Task
Order
Installation of groundwater wells Consistent with issuance of Task
Order
Completion of the CADD/CAP document Consistent with issuance of Task
Order
Completion of CR Consistent with issuance of Task
Order
1.4.1.2.02.02.11.06 Characterization Annual Sampling
The Contractor shall perform sampling activities to support geology, hydrology, transport
parameter, and source term data analysis activities. This includes but is not limited to:
planning; site mobilization and demobilization; site setup; installation of downhole and over
hole equipment; connecting to portable or pre-established surface power; inspection and
maintenance of sumps and sump liners; groundwater and geochemical sampling; and sample
management, analysis and reporting.
1.4.1.2.02.02.12.01 Geology
The Contractor shall compile and interpret geologic information, and revise geologic models
based on this information.
1.4.1.2.02.02.12.02 Hydrology
The Contractor shall compile and interpret hydrologic data and update the hydrologic data
documentation to be used for the flow and transport model.
1.4.1.2.02.02.12.03 Transport Parameters
The Contractor shall collect, analyze, qualify, and document chemical, geochemical, and
hydrologic data pertinent to radionuclide transport in groundwater.
1.4.1.2.02.02.12.04 Source Term
The Contractor shall analyze data pertaining to the source term. Scope may include work in a
classified environment. Classified and unclassified near-field models and reports will be
submitted. Classified modeling activities will be performed by the national laboratories.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-11
1.4.1.2.02.02.13.02 Flow and Transport Model
The Contractor shall conduct flow and transport modeling analysis, evaluation and reporting.
1.4.1.2.02.02.13.04 External Peer Review
As part of the FFACO UGTA strategy, the Contractor shall facilitate an External Peer
Review panel to review the final flow and transport model document for Pahute Mesa,
provide comments, prepare and submit a Peer Review Panel Report. The results and
recommendations of the external Peer Review Panel Report will be used by the EM Nevada
Program and the regulator to determine whether the Pahute Mesa model is acceptable to
proceed from the Corrective Action Investigation phase to the Corrective Action Decision
Document/Corrective Action Plan phase. The Contractor shall identify independent qualified
candidates for the External Peer Review Panel. The candidates shall be selected based on
experience relevant to groundwater modeling, with appropriate scientific disciplines are
represented, and no conflicts of interest compete with the independence of the review.
1.4.1.2.02.02.13.06 Risk
The Contractor shall conduct a human health risk assessment to provide additional insights
for the DOE’s understanding of the implications of the contaminated groundwater from
Pahute Mesa.
1.4.1.2.02.03.01 CADD/CAP Preparation
The Contractor shall complete a CADD/CAP document consistent with Exhibit C-1 and the
provisions of the FFACO.
1.4.1.2.02.04.01.01 Drilling
The Contractor shall conduct groundwater well installation, including but not limited to
design, planning, well construction, geophysical logging, well completion, and well
completion report documentation. Wells ranging in depth from 2,000 to 6,000 feet below
ground surface shall be installed, with well designs and drilling methods differing based on
location and intended use.
1.4.1.2.02.04.01.02 Well Development, Testing and Sampling
The Contractor shall perform well development, testing and sampling activities. This includes
but is not limited to: planning; hydraulic testing and groundwater and geochemical sampling;
sample management, analysis and reporting; site mobilization and demobilization;
installation of downhole equipment; connecting to portable or pre-established surface power;
and inspection and maintenance of sumps and sump liners.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-12
1.4.1.2.02.04.01.03 Water-Level Measurements
The Contractor shall acquire water-level measurement records. Measurement activities and
resulting data will be supplemental to data obtained directly from well drilling and
development and testing activities. Information to be acquired includes continuous water
level measurements, water temperature and barometric data required to perform detailed
analysis of aquifer response related to drilling and pumping hydraulic stress applied to
aquifers.
1.4.1.2.02.04.01.04 Evaluation Annual Sampling
The Contractor shall perform sampling activities to support model evaluation. This includes
but is not limited to: planning; site mobilization and demobilization; site setup; installation of
downhole and over hole equipment; connecting to portable or pre-established surface power;
inspection and maintenance of sumps and sump liners; groundwater and geochemical
sampling; and sample management, analysis and reporting.
1.4.1.2.02.04.04 Model Evaluation
The Contractor shall analyze, scale, and compare field data to model conceptualizations and
simulation results in order to build confidence in the site conceptual model and transport
model forecasts. Sufficient confidence must be developed in the forecasts so that the NDEP
will accept use of the model in guiding the development of the long-term monitoring network
and institutional controls for closure.
1.4.1.2.02.04.05 Prepare Closure Report
The Contractor shall complete a CR consistent with Exhibit C-1 and the provisions of the
FFACO. The goal of the CR is to establish a mutually agreed to plan by the EM Nevada
Program and NDEP for implementing the long-term monitoring phase and for handling
uncertainty during that phase of the project.
1.4.1.2.03 Yucca Flat/Climax Mine (CAU 97)
The scope of work for Yucca Flat/Climax Mine is defined in subsequent sections.
Yucca Flat/Climax Mine (CAU 97) Key Performance Milestones
Milestone Date
Completion of CR Consistent with issuance of Task
Order
Installation of groundwater wells Consistent with issuance of Task
Order
1.4.1.2.03.04.01.04 Evaluation Annual Sampling
The Contractor shall perform sampling activities to support model evaluation. This includes
but is not limited to: planning; site mobilization and demobilization; setup; installation of
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-13
downhole and overhole equipment; connecting to portable or pre-established surface power;
inspection and maintenance of sumps and sump liners; groundwater and geochemical
sampling; and sample management, analysis and reporting.
1.4.1.2.03.04.05 Prepare Closure Report
The Contractor shall complete a CR consistent with Exhibit C-1 and the provisions of the
FFACO. The goal of the CR is to establish a mutually agreed to plan by the EM Nevada
Program and NDEP for implementing the long-term monitoring phase and for handling
uncertainty during that phase of the project.
1.4.1.2.03.05.01.01 Drilling
The Contractor shall conduct groundwater well installation including but not limited to:
design, planning, well construction, geophysical logging, well completion, and well
completion report documentation. Wells ranging in depth from 2,000 to 6,000 feet below
ground surface shall be installed, with well designs and drilling methods differing based on
location and intended use.
1.4.1.2.03.05.01.02 Well Development, Testing and Sampling
The Contractor shall perform well development, testing and sampling activities. This includes
but is not limited to: planning; hydraulic testing and groundwater and geochemical sampling;
sample management, analysis and reporting; site mobilization and demobilization;
installation of downhole equipment; connecting to portable or pre-established surface power;
and inspection and maintenance of sumps and sump liners.
1.4.1.2.03.05.01.03 Water-Level Measurements
The Contractor shall acquire water-level measurement records. Measurement activities and
resulting data will be supplemental to data obtained directly from well drilling and
development and testing activities. Information to be acquired includes continuous water
level measurements, water temperature and barometric data required to perform detailed
analysis of aquifer response related to drilling and pumping hydraulic stress applied to
aquifers.
1.4.1.2.06 Rainier Mesa/Shoshone Mountain (CAU 99)
The scope of work for Rainier Mesa/Shoshone Mountain is defined in subsequent sections.
Rainier Mesa (CAU 99) Key Performance Milestones
Milestone Date
Installation of groundwater wells Consistent with issuance of Task
Order
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-14
1.4.1.2.06.05.01.01 Drilling
The Contractor shall conduct groundwater well installation including but not limited to:
design, planning, well construction, geophysical logging, well completion, and well
completion report documentation. Wells range in depth from 2,000 to 6,000 feet below
ground surface, with well designs and drilling methods differing based on location and
intended use.
1.4.1.2.06.05.01.02 Well Development, Testing and Sampling
The Contractor shall perform well development, testing and sampling activities. This includes
but is not limited to: planning; hydraulic testing and groundwater and geochemical sampling;
sample management, analysis and reporting; site mobilization and demobilization;
installation of downhole equipment; connecting to portable or pre-established surface power;
and inspection and maintenance of sumps and sump liners.
1.4.1.2.06.05.01.03 Water-Level Measurement
The Contractor shall acquire water-level measurement records. Measurement activities and
resulting data will be supplemental to data obtained directly from well drilling and
development and testing activities. Information to be acquired includes continuous water
level measurements, water temperature and barometric data required to perform detailed
analysis of aquifer response related to drilling and pumping hydraulic stress applied to
aquifers.
1.4.1.3 INDUSTRIAL SITES
The Industrial Sites include impacted sites which are the result or by-product of historic testing
and support activities. The Contractor shall perform, facility characterization and corrective
action evaluation for the SAFER Plan, and corrective action field implementation or SAFER
Closure (e.g. clean closure; closure in place, capping, D&D, establishing land use restrictions,
etc.). Field characterization and D&D activities shall be evaluated against existing NNSA/EM
NEPA requirements prior to commencement of any field implementation; if circumstances or
information demonstrates these activities were not part of original EIS, then further NEPA
analysis will be required. Work scope activities are driven by the implementation of the FFACO
technical strategy.
The end state is to complete all corrective actions at all sites. Most Industrial Sites will be
available for unrestricted surface use, while others will be stabilized for restricted use (i.e.,
contamination remains in place) appropriate to the risk posed by residual contamination. For
those sites where contamination remains in place, appropriate long-term remedial actions shall
be implemented, including monitoring, cap inspections, and use restrictions as applicable.
Additional Industrial sites may be identified for investigation and closure.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-15
Industrial Sites Requirements Documents
Document Number Title
N/A Federal Facility Agreement and Consent Order
N/A Standardized Federal Facility Agreement and Consent
Order (FFACO) Outline Streamlined Approach for
Environmental Restoration (SAFER) Plan Revision 3
N/A Standardized FFACO Outline Closure Report (CR)
Revision 1
DOE/NV—372—Rev. 3 Industrial Sites Quality Assurance Project Plan
DOE/NV--1475-REV. 1 Soils Risk-Based Corrective Action Evaluation Process,
Revision 1
1.4.1.3.12.07 CAU 114, Area 25 EMAD Facility
CAU 114, Area 25 EMAD Facility, consists of the facilities identified in the CAU114
Components table below. The scope of work for this CAU is defined in subsequent sections.
CAU 114 Components
Building
Number Title
Approximate
Floor Area
(ft2) Description Comments
3900 Engine
Maintenance,
Assembly, &
Disassembly
(EMAD)
Facility
165,000 Four-story building that is 80 feet
high; the exterior is irregular in
both height and configuration, with
the walls constructed of either
concrete (with rebar), asbestos-
coated corrugated steel, or concrete
block. The interior consists of
three main floors, a partial
basement, and a one-room fourth
floor. There are approximately 44
rooms that are divided among five
functional areas: (1) the Hot Bay
Complex, (2) the Operating
Galleries and Master Control
Room, (3) the Cold Bay Complex,
(4) the Machine and Repair Shops,
and (5) the Facility Support areas.
The EMAD Facility
supported the design and
testing of nuclear powered
rockets in the Nuclear
Engine for Rocket
Vehicle Application
project (1965 to 1973).
The railroad tracks on the
exterior of Building 3900
are not included in the
scope.
N/A Manned Control
Car and Engine
Installation
Vehicle
(Railcars)
N/A The Manned Control Car and
Engine Installation Vehicle railcars
are located on the easternmost rail
spur on the north side of Building
3900.
The vehicles, originating
from CAU 566, were
verified to have no
accessible areas with
elevated radiological
readings. Diesel, gear oil,
engine oil, and coolant
were drained from the
reservoirs/tanks.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-16
CAU 114 Requirements Documents
Document Number Title
DOE/NV--1328-REV. 1 Streamlined Approach for Environmental Restoration
(SAFER) Plan for Corrective Action Unit 114: Area 25
EMAD Facility Nevada Test Site, Nevada
N/A Interim Activities at Corrective Action Unit 114: Area 25
EMAD Facility (dated 10/24/2011)
N/A Interim Activities Completed at Corrective Action Unit
114: Area 25 EMAD Facility for Fiscal Years 2012 and
2013 (dated 10/24/2013)
DOE/NV--1452
Closure Report for Corrective Action Unit 566: EMAD
Compound, Nevada National Security Site, Nevada with
ROTC-1, Revision 0 (included as reference for railcars)
CAU 114 Key Performance Milestones
Milestone Date
Complete revision of CAU 114 SAFER Plan Consistent with issuance of Task
Order
Submit Final CAU 114 Closure Report Consistent with issuance of Task
Order
1.4.1.3.12.07.03 CAU 114 SAFER Plan
The Contractor shall perform characterization of the Industrial Sites identified in the CAU 114
Components table above. The Contractor shall revise the SAFER Plan consistent with Exhibit C-
1 and the provisions of the FFACO, as applicable, and complete field characterization, sample
management, and analytical work to support characterization. The SAFER Plan includes but is
not limited to a description of the Data Quality Objective process and methodology, proposed
field characterization activities, closure objectives and activities, durations for remediation and
closure activities, reports and records to be generated, procedures for waste identification and
handling, and quality assurance/quality control activities.
The Contractor shall electronically manage all characterization data in a manner that facilitates
retrieval, is traceable to the building and process equipment, and is capable of passing an
independent validation by a third party.
1.4.1.3.12.07.04 CAU 114 SAFER Closure
The Contractor shall perform D&D of the Industrial Sites listed in the CAU 114 Components
table above. The end state is anticipated to be demolition to slab or at-grade components, and
disposal of all wastes generated. The D&D includes all manmade structures, and may include
coordinating re-routing of utilities with the contractor responsible for NNSS infrastructure,
hazardous material abatement activities, equipment removal, decontamination, and demolition of
structures/components. Removal will also include general cleanup of debris in the vicinity of the
facility compound. The work may include consideration of specific buildings for re-use. The
demolition of man-made structures shall be coordinated with site cleanup goals. The Contractor
shall coordinate its activities with other site contractors/tenants to avoid and/or mitigate any
interference with ongoing site work.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-17
Demolition will address above-grade structures. Prior to demolition some items may need to be
removed for safety, reduction of long-term risks, and/or to ensure proper disposal practices (e.g.,
items containing toxic or hazardous components may need to be removed to allow for disposal of
demolition debris as sanitary waste and/or low-level waste). Removal may include, but not be
limited to, removal of clean-out, the facility equipment, personal property/fixtures, utility service
components (including components leading up to the inactive facilities), tanks, sumps, asbestos,
low-level waste (LLW), and polychlorinated biphenyl-contaminated items in above-grade and
sub-grade areas. The Contractor shall perform appropriate activities to stabilize the area and
prevent surface water accumulation in sub-grade structures. Sub-grade areas, including but not
limited to basements, depressions, sumps, etc., are anticipated to be backfilled with an approved
material suitable to prevent surface water accumulation and groundwater infiltration.
This work scope shall be considered complete following decontamination, demolition and
disposition of all waste and material associated with the designated facilities. This shall include
all site restoration, demobilization activities, and submittal and approval of the final CR.
1.4.1.3.12.09 CAU 572, Test Cell C Ancillary Buildings and Structures
CAU 572, Test Cell C Ancillary Buildings and Structures, consists of the facilities identified in
the CAU 572 Components table below. The scope of work for this CAU is defined in subsequent
sections.
CAU 572 Components
Building
Number
Title Approximate
Floor Area (ft2)
Description Comments
3901 Engine Transport
System Maintenance
Building
5,300 Single floor, steel light frame
radiological facility in the
vicinity of EMAD.
3220 Equipment Building 6,800 Single floor, reinforced
masonry radiological facility
in the vicinity of Test Cell C.
3230 Motor Drive
Building
4,000 Single floor, steel light frame
radiological facility in the
vicinity of Test Cell C.
3231 Pump House 750 Single floor, concrete
moment frame facility in the
vicinity of Test Cell C.
3232 Cryogenic
Evaluation Lab
1,700 Single floor, steel light frame
radiological facility in the
vicinity of Test Cell C.
Ancillary Facilities N/A Reactor Cooling Station has
a capacity of 500 gallons per
minute.
Test Cell C Water Tank has a
capacity of 150,000 gallons.
Test Cell C Tower Water
Tank has a capacity of
150,000 gallons.
The scope of this
Corrective Action Site
includes investigation of
soil beneath existing
concrete pads, concrete
surfaces outside the
boundary of the existing
use restriction for the
Test Cell C Facility, and
surface and subsurface
soil within the fence
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-18
CAU 572 Components
Building
Number
Title Approximate
Floor Area (ft2)
Description Comments
Test Cell C Hydrogen Tanks
have a capacity of 55,000
gallons each. (2 tanks)
Water Process Tank has a
capacity of 25,000 gallons.
Test Cell C Liquid Hydrogen
Tanks have a capacity of
500,000 gallons each. (2
tanks)
line of the Test Cell C
Facility.
CAU 572 Requirements Documents
Document Number Title
DOE/NV--1462 Closure Report for Corrective Action Unit 116: Area 25
Test Cell C Facility, Nevada National Security Site, Nevada
(included as reference for scope of ancillary facilities)
CAU 572 Key Performance Milestones
Milestone Date
Submit CAU 572 SAFER Plan Consistent with issuance of Task
Order
Submit Final CAU 572 Closure Report Consistent with issuance of Task
Order
1.4.1.3.12.09.03 CAU 572 SAFER Plan
The Contractor shall perform characterization of sites identified in the CAU 572 Components
table above. The Contractor shall develop and submit the SAFER Plan consistent with Exhibit C-
1 and the provisions of the FFACO, and complete all field characterization, sample management,
and analytical work to support characterization. The SAFER Plan includes but is not limited to a
description of the Data Quality Objective process and methodology, proposed field
characterization activities, closure objectives and activities, durations for remediation and closure
activities, reports and records to be generated, procedures for waste identification and handling,
and quality assurance/quality control activities.
The Contractor shall electronically manage all characterization data in a manner that facilitates
retrieval, is traceable to the building and process equipment, and is capable of passing an
independent validation by a third party.
1.4.1.3.12.09.04 CAU 572 SAFER Closure
The Contractor shall perform D&D of the sites listed in the CAU 572 Components table above.
The end state is anticipated to be demolition to slab or at-grade components, and disposal of all
wastes generated. The D&D includes all manmade structures, and may include coordinating re-
routing of utilities with the contractor responsible for NNSS infrastructure, hazardous material
abatement activities, equipment removal, decontamination, and demolition of structures/
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-19
components. Removal will also include general cleanup of debris in the vicinity of the facility
compound. The work may include consideration of specific buildings for re-use. The demolition
of man-made structures shall be coordinated with site cleanup goals. The Contractor shall
coordinate its activities with other site contractors/tenants to avoid and/or mitigate any
interference with ongoing site work.
Demolition will address above-grade structures. Prior to demolition some items may need to be
removed for safety, reduction of long-term risks, and/or to ensure proper disposal practices (e.g.,
items containing toxic or hazardous components may need to be removed to allow for disposal of
demolition debris as sanitary waste and/or low-level waste). Removal may include, but not be
limited to, removal of clean-out, the facility equipment, personal property/fixtures, utility service
components (including components leading up to the inactive facilities), tanks, sumps, asbestos,
LLW, and polychlorinated biphenyl-contaminated items in above-grade and sub-grade areas.
The Contractor shall perform appropriate activities to stabilize the area and prevent surface water
accumulation in sub-grade structures, if applicable. Sub-grade areas, including but are not
limited to basements, depressions, sumps, etc., are anticipated to be backfilled with an approved
material suitable to prevent surface water accumulation and groundwater infiltration.
This work scope shall be considered complete following decontamination, demolition and
disposition of all waste and material associated with the designated facilities. This shall include
all site restoration, demobilization activities, and submittal and approval of the final CR.
1.4.2.1 PROGRAM INTEGRATION
The Contractor shall perform cross-cutting functions in support of the EM Nevada Program.
Program Integration activities include but are not limited to Administrative, Project Planning and
Controls, Health and Safety, Quality Programs, Technical and Regulatory, EM Integration, and
Regulatory and FFACO closeout.
1.4.2.1.01 Administrative
The Contractor shall provide administrative support through management, integration, and
oversight of administrative activities. These support activities include, but are not limited to,
program management support, records management, information technology systems, vehicles,
and personal property. The drivers for these activities are the applicable DOE orders, directives,
policies, and project support requirements.
1.4.2.1.01.01 Program Management Support
The Contractor shall provide on-site services including management, business
administration (e.g., contracting, procurement, financial and accounting), legal support,
human resources, training, and program management. Additionally, the Contractor shall
perform all activities to:
a. Support DOE in responding to Congressional, regulatory and other requests for
documents and information; examples of such include: Freedom of Information Act
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-20
requests; Privacy Act requests; and litigation document requests served upon DOE
and its current and former prime contractors. Support shall include, but not be limited
to, preparation for briefings, public presentations, and search, review, and
reproduction of documents. The Contractor shall ensure all external briefing
materials and public presentations are of the highest professional quality to present
the current and planned project achievements. The Contractor shall ensure that
sufficient time is allotted for DOE (including Headquarters) to review and comment
on any external briefing materials and public presentations. External briefing
materials and public materials shall be approved by DOE prior to public release.
b. Support DOE in the development of internal presentations, budgets, staff
development, and other related services.
c. Support DOE efforts in site reindustrialization/reutilization activities and in Natural
Resource Damage Assessments.
d. Provide legal support to DOE in connection with legal or regulatory proceedings at
DOE’s request.
e. Provide external review and support to DOE by providing support during audits and
assessments. These entities include:
i. Defense Nuclear Facilities Safety Board (DNFSB);
ii. Government Accountability Office (GAO);
iii. DOE Office of Inspector General (OIG); and
iv. Other governmental and DOE organizations.
f. The Contractor shall support the DOE in hosting staff from auditing and assessing
organizations, providing required presentations, responding to information requests,
and providing required subject matter experts to respond to questions and information
requests.
g. Support efforts to evaluate various alternatives for additional office space.
The Contractor shall review the existing procedures, program and performance
documents, and accept, modify, or develop, as necessary, for compliance performance
per DOE Order requirements and all applicable laws and regulations. The Contractor
shall complete reviews, revisions or adoption of all procedures and performance
documents and implement procedures and performance documents in compliance with
DOE Orders, no later than 90 days after Transition.
The Contractor shall, at the completion of the contract, complete all necessary aspects of
contract close-out. This will include, but not be limited to, ensuring all subcontracts are
satisfied, all necessary filings have been completed with the DOE, all filing is current and
up to date, equipment is acceptable and logs are complete, equipment is current and
government property under its cognizance is accounted for. The Contractor shall meet, as
necessary, with the follow-on contractor or the government to ensure a seamless
transition. Other duties associated with transition to a new contract or governmental
entity may be required.
At least one hundred and twenty (120) days prior to the expiration date of the final task
order issued under the contract, the Contractor shall submit a detailed Contract
Completion Transition Plan. The Contract Completion Transition Plan shall include the
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-21
approach the Contractor will take to ensure the successful transfer of responsibility at the
end of the Period of Performance (POP) in the following areas:
a. Transition of all facilities, facility operations, and environmental permits to the
follow-on contractor;
b. Support due diligence walk downs of facilities and other areas;
c. Transfer of existing program documents to include deactivation and
environmental remediation services;
d. Transfer of authorization basis documents;
e. Transition staff;
f. Transfer procurement activities for materials, equipment, supplies, parts, and
subcontractors required for a seamless transition;
g. Destruction of all non-records;
h. Transfer or retirement of all Information Technology (IT) system and
applications; and
i. Transfer of all records.
Program Management Support Key Performance Milestones
Milestone Date
Complete all reviews, revisions, and adoption of
procedures and performance documents and
implement procedures and performance documents
Within 90 days after Transition
Contract Completion Transition Plan 120 days before end of POP
1.4.2.1.01.03 Information Technology (IT) Services, Communications and Cyber Security
The Contractor shall provide an IT infrastructure that includes servers, desktop and mobile
workstations, telecommunications, network infrastructure, data collection and reporting
systems, and all other IT functions necessary to support the activities and requirements of this
contract. The Contractor’s approach to this requirement may include self-performed work,
teaming partner and/or sub-contract support, or Federal Risk and Authorization Management
Program (FedRAMP) approved, commercially-provided IT systems, (typically referred to as
“Cloud” systems); or some combination of these.
Protection of Classified and Sensitive Unclassified Information (SUI)
The Contractor shall protect any Sensitive Unclassified Sensitive Information (SUI) to include
Unclassified Controlled Nuclear Information (UCNI) generated, processed, and stored within
its facilities, under its administrative control, and/or within subcontracted areas of work
performance. Information Security (IS) and Operations Security (OPSEC) procedures shall be
developed to comply with DOE Policy 205.1B– Department of Energy Cyber Security
Program, the DOE-EM Risk Management Approach Implementation Plan (RMAIP), and with
NNSA requirements for IS and OPSEC. The Contractor shall develop these security procedures
before the end of the transition period and provide to the IT System Authorizing Official and
Contracting Officer for review and approval.
The Contractor’s Cyber Security personnel and privileged IT users, such as systems
administrators, shall obtain a DOE Q clearance or equivalent under this Contract. All Cyber
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-22
Security personnel and IT personnel who have Incident Response and Contingency Plan
responsibilities shall have a DOE Q clearance or equivalent.
Access to, use of, or management of classified electronic information is not required to execute
the scope of this contract. However, the nature of the work to be performed under this PWS and
its general proximity to classified IT information systems, indicates actionable risk for the
contamination of the Contractor’s unclassified IT systems due to inadvertent spillage of
classified information or other unplanned events. Before the end of the Transition period, the
Contractor shall develop, submit and maintain an Incident Response and Cyber Security
Contingency Plan (Contingency Plan) to specify the actions necessary to address such events
and provide to the IT System Authorizing Official and Contracting Officer for review and
approval. The Contingency Plan shall, at a minimum, address actions necessary to mitigate loss
of IT services that may arise from such an event and to prevent the further dispersal of the
unauthorized information through the Contractor’s IT systems. The plan shall include sources
of available cleared personnel which may be required to assess the severity and extent of the
event, and assist with containment and mitigation activities. The contractor may elect to utilize
a local cleared site contractor and/or cleared Federal EM-NV or NNSA employees.
Authorization of IT Systems
The Director, Environmental Consolidated Business Center (EMCBC) is the Authorizing
Official (AO) for all contractor-operated IT systems which directly supports the site activities,
under the purview of the EMCBC’s line authority for DOE-EM cleanup activities. The
Contractor shall obtain Authority to Operate (ATO) for all IT systems it operates in support of
the scope of this contract. Full ATO shall be obtained within 18 months after NTP.
Major concerns addressed in DOE’s cyber security and IT policies are the handling of SUI (to
include personally identifiable information (PII), protecting all information and information
systems from unauthorized access, and reporting to the DOE Joint Cyber Coordination Center
(JC3) any significant attempts or successful intrusions into these systems by unauthorized
individuals. The Contractor shall also implement OMB Circular No. A-130, Management of
Federal Information Resources, Appendix III, Security of Federal Automated Information
Resources, November 28, 2000
(https://www.whitehouse.gov/omb/circulars_a130_a130appendix_iiihttps://www.whitehouse.g
ov/omb/circulars_a130_a130appendix_iii) Implementation Guide.
For each IT system it intends to utilize, the contractor shall obtain an interim ATO within 90
days after NTP. The contractor shall notify DOE of a proposed date for assessment for interim
ATO of the IT system(s) and provide completed FIPS-199 Security Categorization
Assessments for each system. This interim assessment will evaluate the following NIST 800-
53 Rev. 4 Control Families for Interim ATO:
AC – Access Control;
CM – Configuration Management;
CP – Contingency Planning;
IR – Incident Response; and
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-23
PE – Physical and Environmental Protection.
Upon successful attainment of the interim ATO, the Contractor shall complete up to two
additional assessments for each IT system, covering the remaining 13 Control Families. The
schedule and family sequence for two assessments shall be negotiated and agreed to by the AO
and the contractor to attain full ATO within the specified time.
Hardware/Software Systems and Applications
The Contractor shall develop, maintain and submit a System Security Plan (SSP) to DOE at
scheduled interim and final cyber security assessments, supporting Configuration Diagrams,
and other exhibits. Where the Contractor stores or processes federally-owned data on
commercially-provided IT systems, typically referred to as “Cloud” or “SaaS” systems, the
Contractor shall use only those commercial systems which have been authorized and certified
for such use through the Federal Risk and Authorization Management Program (FedRAMP).
The Contractor shall fully document such systems in the SSP, supporting Configuration
Diagrams, and other exhibits.
The Contractor shall make provisions in the SSP(s) for its supporting subcontractors’ IT
systems. Where a direct data interchange occurs only between the Contractors IT system(s) and
a subcontractor’s System, the Contractor may apply a graded, risk-based approach to the
application of the ATO requirements of this contract to the subcontractor system. The
identification and evaluation of risks associated with the subcontractor IT systems shall be
documented in the FIPS-199 Evaluation for Security Categorization. Where a subcontractor’s
IT system directly interfaces with DOE IT systems, or provides direct public access to
government information, a separate, full ATO shall be required.
Applications purchased or developed to support the mission under this contract shall be able to
run on mandatory IT baseline security configurations without any deviations and must comply
with the appropriate controls as documented in Security and Privacy Controls for Federal
Information Systems and Organizations, National Institute of Standards and Technology
(NIST), Joint Task Force Transformation Initiative Task Force, Special Publication 800-53,
Revision 4, 2014 (or subsequent final, approved revisions). The Contractor shall deploy
compensating controls on Legacy Systems and Applications while these are in production. For
purposes of this contract, Legacy Systems and Applications are defined as network equipment,
operating systems, database management systems, commercial off-the-shelf software (COTS),
and programming languages which are no longer supported by their manufacturer or provider
for security updates and patches. Also included are custom-developed or other “in-house”
software applications which may rely one or more of the previous for their operation. Such
systems and applications shall be replaced as soon as feasible as determined by the AO. All
production legacy systems and applications shall be documented in the SSP. The Contractor
shall prepare a Plan of Action and Milestones (POAM) and submit to the AO for each legacy
system and application to be replaced.
Where cyber security, cost, and performance considerations allow, the Contractor shall give
priority to the use of federally available enterprise applications and licenses, if they exist, over
the direct purchase of commercial products, and those two categories over the development of
custom, in-house IT solutions to implement and support the Contract; including hardware or
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-24
software solutions to support cyber security. The Contractor shall obtain written authorization
from the AO prior to implementation of new software applications that contain custom, in-
house developed code or other programming that will provide data to, exchange data with, or
otherwise directly interface with DOE IT systems. The Contractor shall obtain written
authorization from the AO prior to implementation of any new systems, applications, or web
sites that are intended to provide public access to government-owned information or data.
IT Inter-connects and Services
Core network infrastructure, ISP, boundary/demarc cybersecurity protections, and
wired/wireless communications services at the Energy Way office compound and at the NNSS
proper are provided by the NNSA and its M&O contractor through MOU/ISA with the
EMCBC. The EMCBC’s general IT services network (which includes the EM-NV office staff)
is physically and logically separated from the NNSA network.
Software Systems and Applications
Exhibit C-2, Information Technology Systems, lists EM-NV software systems and applications
to be operated by the contractor. The Contractor shall provision its IT infrastructure with
coordinated access to the necessary information for contract oversight activities that will be
performed by the EM-NV, office consisting of approximately 25 Federal and support service
personnel, and other personnel within the general EMCBC organization who communicate
directly with the EM-NV through the general EMCBC IT services network. The majority of
these personnel will be housed in the same base office complex at (NNSA compound). The
Contractor shall make provisions for user and data access between the following systems and
applications where noted in Exhibit C-2.
Information Technology (IT) Services, Communications and Cyber Security
Key Performance Milestones
Milestone Date
Information Security (IS) and Operations Security (OPSEC)
procedures
Within 90 days after NTP
Incident Response and Cyber Security Contingency Plan Within 90 days after NTP
Interim ATO Request Within 90 days after NTP
Full ATO Within 18 months after NTP
System Security Plan (SSP) At scheduled interim and final cyber
security assessments
1.4.2.1.01.04 Records Management
The Contractor shall manage records (regardless of media) in accordance with 44 U.S.C. 21;
44 U.S.C. 29; 44 U.S.C. 31; 44 U.S.C. 33; 44 U.S.C. 35; 36 CFR Chapter XII,, Subchapter B,
Records Management; DOE Order 243.1B, Records Management Program; and any other
DOE requirements as directed by the Contracting Officer or incorporated into the contract.
These functions include, but are not limited to, tasks associated with creating, receiving,
maintaining, storing, preserving, protecting, inventorying, scheduling, indexing, and
dispositioning active and inactive records; managing classified records (if applicable), records
training for all employees, retrieving records from on- and off-site storage facilities, support
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-25
records management data calls by NARA and DOE-HQ and supporting ongoing requests
related to the Freedom of Information Act (FOIA), the Privacy Act, the Energy Employee
Occupational Illness Compensation Program (EEOICPA), the former worker medical
screening program, the chronic beryllium disease prevention program, congressional inquiries,
and legal discoveries.
Electronic Records Management System (ERMS)
The Contractor shall develop and implement records management controls to ensure that the
identification, maintenance and disposition of all records (regardless of media), including
electronic and email, are managed utilizing an ERMS (functionality of DoD 5015.2) in
accordance with Federal and DOE requirements and guidelines for all records, including
records from a predecessor contractor. The ERMS shall have a web interface to allow DOE
staff to view records within the ERMS.
The Contractor shall develop and implement a process to ensure records that are being scanned
to be managed in electronic format have been scanned or converted to meet National Archives
and Records Administration (NARA) requirements. If scanned records are not quality checked
at 100%, the Contractor shall develop and submit for DOE approval an Image Quality
Statistics Sampling Plan based on an industry standard. All records (regardless of media) must
be scheduled, arranged, and cutoff by collections (e.g., case file, project, chronologically,
numerically, alphabetically, etc.) for proper disposition in accordance with NARA-approved
DOE Records Disposition Schedules. The Contractor shall provide a web search capability for
the ERMS to allow record searches (for both paper and electronic records). This search
capability shall be made available to DOE.
Audiovisual Records
The Contractor shall implement records management requirements for the creation,
maintenance and storage of audiovisual records in accordance with 36 CFR 1237 and 36 CFR
1235.42 and NARA requirements/guidance and the NNSA Continuity of Operations Program.
The Program shall include disaster prevention mitigation and recovery of records in the event
of a records emergency/disaster where records become damaged.
Essential (Vital) Records Program
The Contractor shall develop and implement an Essential (Vital) Records Program including
essential records inventory in accordance with 36 CFR 1223 and DOE O 243.1B.
Records Ownership
Except for those defined as Contractor-owned (in accordance with DEAR 970.5204-3, “Access
to and Ownership of Records”), all records (see 44 U.S.C. 3301 for the statutory definition of a
record) acquired or generated by the Contractor (and subcontractors) in the performance of this
Contractor including, but not limited to, records from a predecessor contractor (if applicable)
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-26
and records described by the Contractor as being maintained in Privacy Act Systems of Record
shall be the property of the Government.
Creation/Receipt
The Contractor shall develop and implement recordkeeping requirements that reflect adequate
and proper documentation of all contractor (and subcontractor) records generated/received
(regardless of media) in performance of their contract as required by Federal regulations found
in 36 CFR, Subchapter B, Records Management.
Electronic Information Systems (EIS)
The Contractor shall ensure records contained in electronic information systems (EIS) are
exported into the ERMS in accordance with 36 CFR 1236 “Electronic Records Management”.
An EIS is defined as systems that automate certain business functions. The Contractor must
design and implement migration strategies to counteract hardware and software dependencies,
including proprietary file and data formats, when electronic records aren’t exported to an
ERMS and have a retention beyond the life of the information system in which the records are
originally created and captured. The Contractor shall provide a list of all EIS’ to DOE
annually utilizing a format to be provided by DOE.
Inventory and File Plan
The Contractor shall conduct records inventories for all types of records created/received (by
record series), develop a file plan based on the records inventory that provides the
identification, location, arrangement, assignment of the NARA-approved DOE Records
Disposition Schedule/Disposition Authority, and retrieval of all categories (record series) of
records created and received, including Contractor-owned.
Maintenance / Use
The Contractor shall maintain and preserve all records, including records (electronic and paper)
from a predecessor contractor stored on-site, at a Federal Records Center (FRC) and in the
ERMS. The Contractor shall be responsible for receipt (including reviewing documents for
meeting storage requirements), schedule verification/validation, importing into ERMS (paper
metadata at a minimum folder level and electronic), storage/preservation, indexing (paper),
retrieval, copying and final turnover to DOE.
Quality Assurance Records
The contractor shall ensure records classified as Quality Assurance records under American
National Standards Institute (ANSI)/American Society of Mechanical Engineers (ASME)
National Quality Assurance (NQA)-1 (Requirement 17), if applicable, are categorized
appropriately and managed in accordance with NQA-1 AND 36 CFR Chapter XII, Subchapter
B, and are traceable to the applicable item, activity, or facility.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-27
Privacy Act Records
The contractor shall ensure that records generated/received in the performance of the contract,
including records obtained from a predecessor contractor, that contain personal information
retrieved by name or another personal identifier are categorized and maintained in Privacy Act
systems of records, in accordance with FAR 52.224-2, the “Privacy Act”, and DOE Order
206.1, “DOE Privacy Program.”
Records Requests
The Contractor shall respond to records management data calls by NARA and DOE as
requested and process record requests for the FOIA, Privacy Act, former worker medical
screening program, the Chronic Beryllium Disease Prevention Program, congressional
inquiries, legal discoveries and other record requests.
Records Disposition
The Contractor shall document the disposition process, which shall include processing records
to storage (e.g., on-site, FRC) and the destruction process for records and information content.
The Contractor shall disposition all records in accordance with the NARA-approved DOE
Records Disposition Schedules and applicable federal laws and regulations. Disposition
activities include scanning to electronic (permanent to NARA), transferring of paper records to
a FRC, maintain electronically in an ERMS, and/or destroy once retention has been met and
proper approvals obtained, including the DOE EMCBC Chief Counsel and the DOE EMCBC
Records Management Field Officer.
The Contractor shall preserve and disposition records and information content in accordance
with NARA-approved DOE Record Disposition Schedules, as posted on the DOE Office of the
Chief Information Officer’s Records Management Web page. Note: Records-retention
standards are applicable for the classes of records described therein, whether or not the records
are owned by the Government or the contractor (DEAR 970.5204-3).
Records Management Key Performance Milestones
Milestone Date
Records Management Plan 60 days after NTP
Records Inventory and a Records File Plan and
Updates
Initial Plan within 6 months after NTP and
annually thereafter
Vital/Essential Records Plan and Updates Initial Plan within 6 months after NTP and
annually thereafter
Records Disposition Plan and Updates Initial Plan within 6 months after NTP and
revisions prior to implementation
Electronic Information System Initial Plan within 6 months after NTP and
annually thereafter
List of Privacy Act Systems of Records Update Annually
Records Management Close-out Plan 90 days prior to end of the POP
Final Records Turnover (if there is no follow-on
contract)
One-time; at contract transition
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-28
1.4.2.1.01.05 Fleet Management
The Contractor shall comply with Section H clause, DOE-H-2072, Use of Government
Vehicles by Contractor Employees (Oct 2014). The Contractor shall manage a fleet of GSA-
leased motorized vehicles; scheduling vehicle repair and modification services as required; and
performing record-keeping, vehicle assignment, ensuring vehicle utilization. The Contractor
shall provide excess/disposal of DOE-owned fleet vehicles and parts (not waste).
For GSA vehicles at the Nevada Field Office, the Contractor shall refuel using the Wright
Express Credit Card provided for each GSA-leased vehicle. For GSA vehicles utilized at the
NNSS, the Contractor shall use the on-site refueling stations, maintained and operated by the
NNSA M&O Contractor, for Site contractors. The NNSA M&O contractor shall be reimbursed
directly by Wright Express for any fuel purchases.
1.4.2.1.01.06 Personal Property Management
The Contractor shall manage all assigned government-owned accountable and non-accountable
personal property in accordance with the requirements listed below and in 41CFR101 and
41CFR109. Administration of personal property program is the responsibility of the
Contractor including managing an automated database of all personal property actions related
to acquisition, use and disposition as follows:
Control classified equipment and material in accordance with DOE O 471.6,
“Information Security,”;
Control high risk property in accordance with DOE Personal Property Letter 970-3,
Rev.1, dated February 3, 1998; and
Destruction or “rendering useless” of any component, equipment, and material, which are
surplus to the DOE, is the responsibility of the Contractor.
This includes establishing a system to track the assignment and status of high risk property
specifically assigned to the Contractor. Prior to property disposition, the Contractor shall
characterize the property, maintain characterization records, and provide those records at the
time of property transfer.
Personal Property Management Key Performance Milestones
Milestone Date
Reports of loss, damage, periodic physical inventory data and
inventory, & final inventory for Contract completion
Within 1 year after transition is
complete and annually thereafter
Motor Vehicle Fleet Reports (FAST) Within 1 year after transition is
complete and annually thereafter
1.4.2.1.01.07 Training and Qualifications
The Contractor shall develop and submit a Training Program Plan to ensure that the training
and qualification requirements are met and shall verify that all employees have completed the
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-29
necessary training and qualification requirements to perform their assigned tasks. The
Contractor shall list the field work and support positions to which their employees are
assigned. The Contractor shall identify the roles and responsibilities for each position (these
may be defined by procedures that are utilized in the performance of duties). The Contractor
shall define and document any education and experience requirements, previous qualifications
(i.e., union journeyman training), position skills training, safety training, facility specific
training, and any other training required for individuals to be qualified for those positions. The
Contractor shall develop and maintain a matrix that lists the individuals in each position and
the associated training requirements. These records shall be readily available for inspection
upon DOE’s request.
Training and Qualifications Key Performance Milestones
Milestone Date
Training Program Plan Consistent with issuance of Task Order
1.4.2.1.02 Project Planning and Control
The Contractor shall provide Project Planning & Control support through the development of
technical components, risk management, cost estimates, and schedules for their activities in
accordance with Section H, Integrated Work Control Systems and Reporting Requirements. The
Contractor shall establish, maintain, and use an Earned Value Management System consistent
with DOE and EM policies and guidance for work activities. The work control system shall
employ either a standardized or a tailored EVM method and shall be consistent with applicable
DOE and EM policies and guidance. All project management information developed under this
contract shall be provided electronically or be electronically accessible by DOE. This also
includes providing the required information for baseline maintenance and performance measure
tracking and reporting in the Environmental Management Information System (EMIS) and
Primavera P6 Professional Project Management software for the approved contractor work
scope. The Contractor shall establish, appropriately document, and manage the interfaces listed
in Section J, Government Furnished Services and Items.
The Contractor shall utilize a Project Control System and develop, implement and maintain a
comprehensive, resource-loaded final CBB compliant with DOE Order 413.3B Change 4. The
Contractor shall ensure the CBB remains aligned with the Contract and Task Orders terms to
include scope, cost and schedule. The Contractor shall ensure timely response to Contract Task
Order modifications and declaration of changed conditions, through the submission of Contract
change proposals and/or baseline change requests to maintain alignment of the CBB with the
Contract Task Orders.
The Contractor shall also provide financial analyst support for: coordination, validation, and
confirmation of accounting and project control related data, independent review of invoices and
account reconciliations, and validation of contract related data for funds management and
forecasting.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-30
Project Planning & Control Key Performance Milestones
Milestone Date
CPB aligned to task order value Within 3 months after issuance of task order
1.4.2.1.03 Health and Safety
The Contractor shall ensure that processes and appropriate resources are in place to implement
DOE contract requirements in the areas of worker safety and health, integrated safety
management (ISMS), radiation protection, radiological site services (RSS) and occupational
medial services, industrial hygiene, hazard communication, and emergency management. The
Contractor shall conduct activities required for compliance with all applicable laws, regulations,
permits, agreements and orders, and DOE directives including but not limited to those listed in
Section H, DOE-H-2053 Worker Safety and Health Program in Accordance with 10 CFR 851
(OCT 2014), and Section J, Requirement Sources And Implementing Documents (List A) And
List Of Applicable DOE Directives (List B). These ensure that federal and state laws and
regulations; DOE orders, standards, and recommendations; and industry standards and best
practices are incorporated into the work scope.
The Contractor shall:
a. Manage and perform work in accordance with a documented Safety Management System
per Section I DEAR clause 970.5223-1, Integration of Environment, Safety, and Health
into Work Planning and Execution (DEC 2000), which shall be submitted for DOE
approval. The Contractor shall also establish performance measures, objectives, and
commitments (PMOC’s) as required by DEAR 970.5223-1. PMOCs shall be submitted
annually for DOE approval.
b. Perform work in accordance with 10 CFR 851. The Contractor’s safety program
requirements shall include hazard analyses, work permits (as applicable), industrial
hygiene monitoring, and trained safety professionals. The Contractor shall manage and
perform work in accordance with a documented worker safety and health plan by DOE
prior to commencement of work.
c. Provide safety and health disposable Personal Protective Equipment for its employees
and subcontractors. The Contractor shall be responsible for the subsequent disposal of
such PPE. The Contractor shall be responsible for providing respirator pickup and
distribution services at the NNSS for its employees and its subcontractors.
d. The Contractor shall develop and submit a Radiation Protection Program Implementation
Plan in compliance with the NNSS Radiation Protection Program, the NNSS
Radiological Control Manual, 10 CFR 835, Occupational Radiation Protection, and DOE
Order 458.1.
e. The Contractor shall implement a compliant lock-out/tag-out program in accordance with
DOE-STD-1030-96 and all applicable regulations.
f. Provide medical screening of employees required to enter the work areas and meet the
requirements of the Worker Safety and Health Program (10 CFR 851), or Radiological
Protection Program (10 CFR 835). The Contractor shall ensure adequate access to health
programs/ambulatory care, and beryllium and radiation worker health surveillance
programs. These services are required to assess, monitor, record data, and provide
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-31
medical support for current site workers who are or may be exposed to radiological and
hazardous materials.
Health and Safety Key Performance Milestones
Milestone Date
Submit Worker Safety and Health Program
(WSHP)
Within 90 days after NTP
Submit Radiation Protection Program
Implementation Plan
Within 90 days after NTP
Contractor’s ISMS Verification Review and
Report
120 days after NTP
ISMS Annual Effectiveness Review and Report Annually after the Contractor’s ISMS
Verifications Review and Report
PMOCs 120 days after NTP, Annually thereafter
1.4.2.1.04 Quality Programs
The Contractor shall perform Quality Assurance (QA) activities to implement contract
requirements in the areas of assessments, suspect/counterfeit items, software quality,
vendors/suppliers quality, and training. These disciplines ensure that federal and state laws and
regulations; DOE Orders, standards, and recommendations; and industry standards and best
practices are incorporated into the work scope. The Contractor shall comply with 10 CFR 830,
other regulations affecting QA, and DOE O 414.1D, Change 1, and implement a DOE-approved
Quality Assurance Program (QAP) in accordance with the EM Quality Assurance Program, EM-
QA-001, Revision 1 dated June 11, 2012, prior to commencement of work affecting nuclear
safety or quality. If there is any inconsistency between the QAP and any other terms of the
contract, the more restrictive requirements apply. The Contractor shall submit a QAP to DOE
for approval within 90 days of the DOE contract being awarded, and at a minimum, annually
review and update the QAP as appropriate. The confirmation of the review and any changes
shall be submitted to DOE for approval.
The Contractor’s QAP shall describe the overall implementation of the EM QA requirements and
shall be applied to all work performed by the Contractor (e.g., research, design/engineering,
construction, operation, budget, mission, safety, and health). The Contractor shall ensure it
maintains a robust Suspect/Counterfeit Items and Software Quality Assurance program controls.
In accordance with Section H, Quality Assurance Requirements for Work Performed by the U.S.
Department of Energy Office of Environmental Management Quality Assurance for Work
Affecting Nuclear Safety, the Contractor shall develop and implement a comprehensive Issues
Management System as defined in DOE O 226.1B using a “zero-threshold” level for the
identification, assignment of significance category, and processing of issues identified within the
Contractor’s organization. The significance assigned to the issues shall be the basis for all
actions taken by the Contractor in correcting the issue from initial causal analysis, reviews for
reporting to DOE, through completion of effectiveness reviews, if required, based on the
seriousness of the issue.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-32
The Contractor shall submit for DOE approval a Contractor Assurance System Description as
required by DOE O 226.1B, Implementation of DOE Oversight Policy. This document shall
identify and address program and performance deficiencies, opportunities for improvement, and
processes to report deficiencies to the responsible managers and authorities. The description shall
establish and effectively implement corrective and preventive actions, and share lessons learned
across all aspects of the work scope. The Contractor shall annually review and update, as
appropriate, their Contractor Assurance System Description and resubmit updates to DOE for
approval.
Quality Programs Key Performance Milestones
Milestone Date
Submit Quality Assurance Program 90 days after NTP
QAP Review and Update Initial update due 1 year after conclusion
of transition, and annually thereafter
Contractor Assurance System Description Initially due 160 days after NTP and
Annually thereafter
1.4.2.1.05 Technical & Regulatory Support
The Contractor will provide Technical & Regulatory Support to ensure that processes and
appropriate resources are in place to implement DOE contract requirements in the areas of
environmental compliance, waste operations, radiological support, analytical sample and data
management, analytical data validation, DOE regulatory compliance, National Environmental
Policy Act of 1969 (NEPA) and integrated safety management. These disciplines ensure that
federal and state laws and regulations; DOE Orders, standards, and recommendations; and
industry standards and best practices are incorporated into the work scope.
The Contractor shall participate in the DOE Consolidated Audit Program (DOECAP) by using
DOECAP audited laboratories. The Contractor shall also provide technical experts and/or
observers in support of the DOECAP program. Frequency and type of support is dependent
upon amount of projected contract laboratory effort for any given year. In addition, if the
Contractor utilizes a commercial TSDF for purposes of managing or disposing of waste
materials, the Contractor shall be required to provide auditor/s to participate on annual
DOECAP audits. Frequency of support is dependent upon amount of projected contract TSDF
effort for any given year.
Section H, National Environmental Policy Act (OCT 2014) requires that all federal agencies
consider the impacts of their projects on the human environment. The NEPA review process
ensures that the proper level of environmental review is performed before an irreversible
commitment of resources is made. The Contractor shall provide DOE with an environmental
review prior to implementation of field work that could have an impact on the human
environment. The Contractor shall include the development of the NEPA Checklists in their
planning efforts to support field implementation. The NEPA review shall include a completed
checklist submitted to the DOE EM NEPA Compliance Officer (NCO) for approval; the
checklist template is provided in Section J, EMCBC-SLA Environmental Checklist. The NCO
must approve each Checklist prior to field implementation. The checklists shall address any
possible activities that could result in an impact to the human environment. In addition to
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-33
completing the checklists, the Contractor shall propose a recommendation for either the use of a
DOE 10 CFR 1021 specific Categorical Exclusion (s) or recommendation that the impacts were
already analyzed as part of the existing NNSA Sitewide Environmental Impact Statement (EIS).
The Contractor shall review all possible resource area impacts as applicable to the proposed
project scope. This will include, but is not limited to air, noise, visual, groundwater, surface
water, floodplains, wetlands, geology, soils, ecological, biological, cultural, historical resources,
waste management and transportation resource impacts.
The checklist shall be reviewed by the NCO (or the NNSA NCO, if designated) to determine if
the activity’s environmental impacts have been addressed in a previous NEPA analysis. The
NCO must approve each checklist prior to field implementation. If a proposed project has not
been covered under any previous NEPA analysis and it does not qualify for a “Categorical
Exclusion” (per 10 CFR 1021), then a new NEPA or supplemental analysis shall be initiated.
The analysis may result in preparation of a new Environmental Assessment (EA), EIS, or
supplemental document to the existing programmatic Site-Wide Environmental Impact
Statement for the Nevada National Security Site and Offsite Locations in Nevada (NNSS
SWEIS) (U.S. Department of Energy, National Nuclear Security Administration Nevada Site
Office 2013). If an EA, EIS or SEIS is required, it will be performed by another contractor. The
Contractor shall provide project information and coordinate with the specific NEPA EA/EIS
contractor.
In addition to supporting NEPA analysis and determinations, the Contractor shall support DOE
in other environmental compliance determinations. This includes, but is not limited to, the
development of reports, correspondence, and/or recommendations that analyze compliance with
requirements such as RCRA, CERCLA, TSCA, NEPA, National Historic Preservation Act
(NHPA), NPDES, and other permits and agreements. Any excavation/penetration permits for the
project shall include an evaluation of ecological, cultural, and historic resources in advance of
work activities that involve the excavation of soil and installation/demolition of structures. The
Contractor shall stop work and notify DOE immediately if any natural, cultural or historic
resources are identified during their work activities. All field work shall adhere to all existing
Cultural and Archeological agreements that are in place for the NNSS facility.
The Contractor shall integrate with other site-wide environmental regulatory management
entities for applicable site-wide permits, permit applications, site-wide NEPA documents, site-
wide environmental reports, etc. The Contractor shall administer required programs and
generate required environmental information to support regulatory compliance, and comply in
areas under its cognizance, including NEPA. The Contractor shall provide and support services
for its projects in the areas of air, water, facility environmental monitoring, and collect, compile,
and/or integrate monitoring data from operations and activities under its control. The Contractor
shall provide project information and coordinate with the NNSS M&O contractor for
development of the Annual Site Environmental Report and integrate its environmental permitting
and regulatory compliance activities with the Nevada-wide permitting and compliance
framework.
Technical & Regulatory Support Key Performance Milestones
Milestone Date
NEPA Environmental Reviews & Checklists Prior to Implementation of Field Work
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-34
1.4.2.1.07 Environmental Management Integration
The Contractor shall provide direct support for integration of EM Nevada Program initiatives
involving the Nevada EMIS, FFACO, strategic communications, strategic planning,
classification, emergency preparedness/response, and stakeholder information needs including
the EM Consolidated Business Center (EMCBC), DOE Headquarters, EM Nevada Program,
NNSA/Nevada Field Office (NFO), LM, the Defense Threat Reduction Agency, DOD, State of
Nevada, tribal support, and others.
EMIS and FFACO support includes the day-to-day operations and maintenance of the EMIS and
FFACO databases as well as user interfaces/web applications.
Strategic communications support includes communication tools to develop and disseminate
external information for all EM Nevada Program activities. Activities will focus on
programmatic efforts for communicating with the Nevada Site Specific Advisory Board
(NSSAB); general public; media; intergovernmental agencies; national, state, local, and tribal
government entities; various oversight and public interest groups; EMCBC; DOE Headquarters;
regulatory agencies; and the Nevada business community. The Contractor is also responsible for
managing all NSSAB activities and for ensuring compliance with the Federal Advisory
Committee Act and other applicable requirements. The Contractor will participate in and provide
support for the NNSS Emergency Response Organization Joint Information Center with crisis
communications support as needed.
Classification support is performed under the guidance of the EMCBC and includes integration
between the NNSA/NFO Safeguards and Security and the EM Nevada Program; classification
review and public release approval of EM Nevada Program documents and other media (with an
emphasis on those generated by the EPS contractor) as authorized by the EMCBC Classification
Officer; coordination of safeguards and security related reviews, to ensure adequate
documentation related to safeguards and security topics are filed and maintained in an orderly
fashion; and providing direct support to the EMCBC Classification Officer.
1.4.2.1.08 Regulatory and FFACO Closeout
The Contractor shall perform activities necessary to support regulatory and FFACO closeout of
the EM Nevada Program mission. This includes general interagency coordination to achieve
alignment of roles, responsibilities, budgeting, and technical closeout objectives with entities
identified as post-closure stewards and/or future remediation leads. The Contractor will support
evaluation of site closure requirements to ensure alignment given that closure of sites has
occurred over several decades. This alignment will involve requirements review, records
assessment, technical discussions with stakeholders, legal reviews, and revisions to closure
requirements as appropriate. The Contractor will also support development of new FFACO
appendices and gaining multi-agency concurrence of the changes, as required.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-35
1.4.3.3.05 RADIOACTIVE WASTE ACCEPTANCE PROGRAM (RWAP)
The RWAP facilitates the management of radioactive waste in a safe and compliant manner by
ensuring the compliance of generator sites with the NNSS Waste Acceptance Criteria (WAC)
and the Resource Conservation and Recovery Act (RCRA) permit and maintains the protection
of the public, the workers, and the environment. Approval to ship waste to the NNSS is granted
only after the waste generator demonstrates compliance with the NNSS WAC. The Contractor
will not provide physical support/assistance to the generators by packing or shipping the
generator’s waste. The NNSS Waste Generator Map is provided as Exhibit C-3.
RWAP Requirements Documents
Document Number Title
DOE/NV--325-16-00 Nevada National Security Site Waste Acceptance Criteria
N/A Nevada Agreement in Principle
(https://ndep.nv.gov/uploads/documents/aip_2011-
2016.pdf)
1.4.3.3.05.01.02 Waste Acceptance Coordination
The Contractor shall coordinate waste acceptance activities between the generators, the M&O
contractor, EM Nevada, and NNSA/NFO. Coordination functions include: establishing and
maintaining interfaces with waste certification officials at waste generator sites; establishing and
implementing a process to share lessons learned amongst the waste generator community;
developing communication tools to track, disseminate, and inform stakeholders on waste
acceptance activities; coordinating and participating in an annual waste generator workshop;
coordinating monthly conference calls with approved waste generators; and coordinating with
new waste stream generators.
1.4.3.3.05.01.03 Waste Acceptance Facility Evaluations/Verifications
The Contractor shall provide independent oversight by performing audits to assess low-level
waste/mixed low-level waste (MLLW) generators’ compliance with the NNSS waste
certification program. Audits will be selected and scheduled based on a risk-informed process.
The Contractor may perform audits at the generators’ facilities or via desktop review when travel
to the generator facility is not required. Upon discovery of non-compliant conditions, the
Contractor shall issue findings and perform subsequent corrective action verification and/or
impromptu surveillances. Corrective action verification activities shall include: tracking of open
issues; review root cause analyses, Corrective Action Plans, and supporting documentation.
The Contractor shall conduct LLW/MLLW verifications to validate compliance of waste
containers with NNSS WAC requirements. Verifications will be selected and scheduled based on
a risk-informed process, the availability of the waste generator, and other factors considered in
the waste verification program. Verification activities will be coordinated with the NNSS M&O
Contractor.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-36
1.4.3.3.05.01.04 Waste Acceptance Review Panel (WARP)
The WARP is chartered as a technical resource panel of selected subject matter experts who
review generator waste profiles and supporting documentation. The WARP is an established
forum overseen by EM Nevada federal staff, NNSA/NFO federal staff, and NDEP staff with
representatives from the following:
RWAP Program Manager (EPS Contractor);
RWAP Coordinator (EPS Contractor);
Radioactive Waste Management Complex Operations personnel (M&O);
Performance Assessment Representative (M&O);
RWMC Nuclear Facility Manager (M&O); and
Other subject matter experts, as necessary.
The WARP is designated to review and recommend approval and/or disapproval of waste
profiles; initiate development of position papers; review generator documents; and provide
recommendations on related technical issues to EM Nevada.
The WARP also provides guidance to EM Nevada and waste generators on waste disposal
issues. It is a technical resource for review of Technical Basis Documents and position papers for
acceptability and recommendations concerning waste acceptance with regard to compliant waste
disposal. Waste profile/document support includes: technical review of profiles submitted by
generators; tracking LLW and MLLW profiles through the approval process; researching,
reviewing, and resolving issues resulting from the profile review; providing recommendations
for the verification of MLLW profiles; and drafting approval letters, memorandum for records,
and enclosures for EM Nevada signature.
The Contractor shall provide technical support and administer the activities of the WARP. The
Contractor shall coordinate, schedule and facilitate all WARP activities and review meetings,
and assign related support tasks to ensure that complete and thorough reviews are performed and
documented.
1.4.3.3.05.01.05 Waste Acceptance Support
The Contractor shall provide general support for all RWAP activities, including maintaining the
NNSS WAC and RWAP procedures. This includes ensuring the NNSS WAC is aligned with the
Area 3/Area 5 Documented Safety Analysis, Safety Evaluation Report, the NNSS RCRA Part B
Permit, and the Area 5 Disposal Authorization Statement. The Contractor shall establish and
implement a document control process, provide programmatic technical support/assistance to
waste generators, and perform informal, non-documented gap analyses (assistance) for
compliance with the NNSS WAC at the generator’s request. The Contractor will not provide
physical support/assistance to the generators by packing or shipping the generator’s waste.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-37
1.4.8 POST-CLOSURE MONITORING, MAINTENANCE, AND PERMITS
The Contractor shall maintain post-closure requirements for the EM Nevada Program as
identified in approved closure documents identified in the FFACO, Appendix IV: Closed
Corrective Action Units, and other regulatory permits. Activities on the NTTR/TTR will require
coordination with the United States Air Force. The Contractor shall develop, submit and
maintain a consolidated Long-Term Monitoring Plan. The Contractor shall support turnover of
EM Nevada Program long-term monitoring activities to the LM or NNSA, as appropriate.
Post-closure Monitoring, Maintenance, and Permits
Requirements Documents
Document Number Title
N/A Federal Facility Agreement and Consent Order
N/A Standardized FFACO Outline Non-Resource Conservation
and Recovery Act Corrective Action Unit (CAU) Post-
Closure Inspection Letter Report Revision 1
N/A Standardized Outline Resource Conservation and Recovery
Act Corrective Action Unit (CAU) Post-Closure Report
Revision 2
N/A Standardized FFACO Outline Tonopah Test Range (TTR)
Corrective Action Unit (CAU) Post-Closure Report
Revision 1
NEV 96021 Water Pollution Control Permit NEV 96021
N/A Submittal of Final Post-Closure Inspection Letter Report
for Corrective Action Units on the Nevada National
Security Site, May 2018
DOE/NV--1594 Post-Closure Report for Closed Resource Conservation and
Recovery Act Corrective Action Units, Nevada National
Security Site, Nevada: For Calendar Year 2017, Revision 0
DOE/NV--1591 Post-Closure Inspection Report for the Tonopah Test
Range, Nevada: For Calendar Year 2017
DOE/NV—1538-REV. 1, ROTC-2 Underground Test Area (UGTA) Closure Report for
Corrective Action Unit 98: Frenchman Flat Nevada
National Security Site, Nevada, Revision 1 ROTC-2
DOE/NV--1593 CY2017 Annual Closure Monitoring Report for Corrective
Action Unit 98, Frenchman Flat, Underground Test Area,
Nevada National Security Site, Nevada: (January 2017–
December 2017), Revision 0
DOE/NV--1586 E Tunnel Wastewater Disposal System Quarterly
Monitoring Report and Annual Summary Report, Nevada
National Security Site, Nevada, Water Pollution Control
Permit NEV 96021, Fourth Quarter and Calendar Year
2017, January 2018
DOE/NV--1590 E Tunnel Wastewater Disposal System Quarterly
Monitoring Report, Nevada National Security Site, Nevada,
Water Pollution Control Permit NEV 96021, First Quarter
2018, April 2018
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-38
1.4.8.1 EM Soil and Industrial-Type Post-Closure Surveillance and Maintenance
The Contractor shall conduct post-closure monitoring of closed contaminated soil and industrial-
type sites as identified in the FFACO, Appendix IV, Closed Corrective Action Sites. This
includes non-RCRA sites on the NNSS and TTR/NTTR. The Contractor shall complete and
submit the post-closure monitoring reports to DOE annually. The Contractor will also
coordinate maintenance and repairs as required due to follow-up actions identified during
surveillances. This may include, but is not limited to: repairs to damaged fencing and signs,
repair of animal burrows, stabilization of settling or cracking covers, surface soil studies, and
brush removal. At the NNSS, installation and maintenance of infrastructure and any post-closure
maintenance requiring earth work is the responsibility and scope of the NNSS M&O contractor.
EM Soil and Industrial-Type Post-Closure Surveillance and Maintenance
Key Performance Milestones
Milestone Date
Post-closure monitoring Report Annually
1.4.8.2 Defense Program Industrial-Type Post-Closure Surveillance and Maintenance
The Contractor shall conduct post-closure monitoring of closed contaminated industrial-type,
non-RCRA sites on the NNSS as identified in the FFACO, Appendix IV, Closed Corrective
Action Sites. The Contractor shall complete and submit the post-closure monitoring reports to
DOE annually. The Contractor will also coordinate maintenance as required due to follow-up
actions identified during surveillances. This may include, but is not limited to: repairs to
damaged fencing and signs, repair of animal burrows, stabilization of settling or cracking covers,
surface soil studies, and brush removal. Installation and maintenance of infrastructure and any
post-closure maintenance requiring earth work is the responsibility and scope of the NNSS M&O
contractor.
Defense Program Industrial-Type Post-Closure Surveillance and Maintenance Key
Performance Milestones
Milestone Date
Post-closure monitoring Report Annually
1.4.8.3 Groundwater Long-Term Monitoring
The Contractor shall acquire and maintain equipment, supplies and expendable items necessary
to maintain the monitoring network system at closed groundwater CAUs. This includes the
maintenance of equipment and instrumentation to maintain calibration schedules and ensure an
appropriate field capability with respect to instrumentation, essential equipment and supplies
necessary for typical groundwater field efforts. This scope also includes long-term post-closure
groundwater sampling and monitoring activities, inspection and documentation of the
institutional controls (e.g., use restrictions, deed restrictions, physical barriers, processes, and
procedures), and submittal of an annual Closure Monitoring report to DOE established in the CR.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-39
Groundwater Long-Term Monitoring Key Performance Milestones
Milestone Date
Closure Monitoring Report Annually
1.4.8.4 RCRA Permits
The Contractor shall conduct annual, bi-annual, and quarterly (or as required by the RCRA
permit and the approved closure document) site inspections of RCRA sites as identified in the
FFACO, Appendix IV: Closed Corrective Action Units and RCRA permits. RCRA Permits are
associated with CAU 90 Area 2 Bitcutter Containment, CAU 91 Area 3 U-3fi Injection Well,
CAU 92 Area 9 Decon Pond Facility, CAU 110 Area 3 WMD U-3ax/bl Crater, CAU 111 Area 5
WMD Retired Mixed Waste Pits, and CAU 112 Area 23 Hazardous Waste Trenches.
RCRA Permits
Key Performance Milestones
Milestone Date
Site Inspection Reports Annual, bi-annual, and quarterly or as
required by the Permit
1.4.8.5 Defense Program Permits
The Contractor shall conduct activities to maintain compliance with permit NEV 96021, E-
Tunnel Waste Water Disposal Systems.
Defense Program Permits
Key Performance Milestones
Milestone Date
E-Tunnel Wastewater Disposal Reports Annual and quarterly or as required by
the Permit
1.4.8.6 Work for Others Permits
The Contractor shall support permit-related interactions, permit maintenance support activities,
reclamation planning, and submittal of reports to DOE. The Contractor shall perform site
inspections in accordance with permit requirements, including weekly storm-water permit
inspections; surveillance of borehole sites; preparation and submittal of reports and permit
renewal applications; and payment of environmental permit renewal fees, as authorized by DOE.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-40
Exhibit C-1, Regulatory Documents
The Contractor shall prepare draft and/or final documents related to site characterization,
assessment, remediation, closure, and monitoring of Corrective Action Units (CAUs) and
Corrective Action Sites (CASs) (as appropriate) in accordance with the provisions of the
FFACO (1996; as amended).
The Contractor will conduct all activities necessary to ascertain the information for the
preparation of the documents listed. All documents must be prepared in accordance with
the provisions of the FFACO standardized outlines.
The Contractor is responsible for production, reproduction, and distribution of draft
and/or final documents for the EM Nevada Program, the Nevada Division of
Environmental Protection (NDEP), and contractor review. The Contractor shall resolve
EM Nevada Program and other reviewer comments via response on document review
forms. NDEP comments shall be addressed by the Contractor with responses approved
by EM Nevada Program and a copy of the document review sheet shall be included as an
appendix in all final documents for review by EM Nevada Program and NDEP.
Following NDEP approval, the Contractor shall prepare a Portable Document Format
conversion and a compact disc, if required, and submit final documents to the
Environmental Management Information System (EMIS), the DOE Office of Scientific
and Technical Information and the Public Reading Facilities identified in the FFACO.
Corrective Action Investigation Plan (CAIP)
A CAIP is prepared to describe all of the specific information for planning
investigation activities associated with CAUs and CASs. A CAIP may reference
information in the optional CAU work plan or other applicable documents. If a CAU
work plan is not developed, then the CAIP must include or reference all of the
management, technical, quality assurance, health and safety, Strategic
Communication, field sampling, and waste management information needed to
conduct the investigations in compliance with established procedures and protocols.
Corrective Action Decision Document (CADD)
A CADD is prepared to describe the corrective action that is selected as the result of
investigation activities and the rationale for selection. The rationale consists of an
analysis of the possible alternatives and may reflect a decision ranging from no action
to clean closure.
The Contractor will develop Corrective Action Alternatives and evaluate those
alternatives through an established process. The process will include EM Nevada
Program participation and will result in the selection of a preferred closure strategy.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-41
Corrective Action Plan (CAP)
A CAP is prepared when a CADD requires an action. The Contractor shall summarize
the results of the corrective action investigation as presented in the CADD(s) and shall
specify the details on the implementation of the correction action proposed for the
CAU.
Streamlined Approach for Environmental Restoration Plan (SAFER)
A SAFER plan is prepared if sufficient information exists at a particular CAU to plan
corrective actions prior to completion of the investigation. This SAFER plan will
contain all the necessary elements usually found in CAIPs, CADDs, and CAPs.
The Contractor shall define why the SAFER process is acceptable and appropriate for
reaching closure for a CAU and the associated CASs. The Contractor shall provide a
summary statement of the proposed corrective action and the closure options. All
CASs within the CAU must have a closure scenario established in the document.
Provide a statement of the assumptions made for this CAU and each associated CAS
to support the identified closure approach.
CADD/CAP
A CADD/CAP is prepared to document the alternatives arising as a result of a
corrective action investigation, the rationale for selection of a preferred alternative,
and the plan for implementing the preferred corrective action alternative. The
CADD/CAP uses site knowledge gained through characterization and similar
historical corrective actions to provide a plan for corrective action. The CADD/CAP
is submitted to fulfill a CADD milestone. However, if approval is granted, this
document would also fulfill the CAP milestone, and the CAP milestone would no
longer be required.
CADD/Closure Report (CR)
The CADD/CR is used for CAUs where no further corrective actions are needed
following completion of the corrective action investigation. This may include minor
corrective actions as agreed to by NDEP. The CADD/CR provides rationale for no
further corrective action, and may recommend closure with or without use restrictions
or long-term monitoring. The CADD/CR is submitted to fulfill a CADD milestone.
However, if approval is granted, this document would also fulfill the CR milestone,
and the CAP milestone would no longer be required.
Closure Report
A CR document provides an overview of the corrective actions implemented at a
CAU, the results of the corrective actions, any deviations from the approved CAP,
closure verification information, URs, and monitoring requirements (when applicable).
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-42
Long-Term Monitoring Reports
Long-term monitoring reports will present the measurements, inspections, analytical
results, and data evaluations annually or as required in the approved CR. Each report
will be transmitted to the EM Nevada Program for submittal to NDEP.
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-43
Exhibit C-2, Information Technology Systems
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
1. EMIS DOE/EM Project Information (cost, schedule,
correspondence, etc.)
Internal & external (login required for external
access)
In-house
Contractor / EM --
ASP and ASP.net
Yes
2. Adobe Acrobat
Professional
View, create, manipulate, print and manage files in
Portable Document Format (PDF).
Adobe
No
3. Adobe Creative
Cloud Desktop
Apps for
Government
Software as a service for graphic design, video
editing, web development, photography, and cloud
services.
Adobe
No
4. Adobe Creative
Suite Design
Standard
Tools for editing digital images, creating vector
graphics, and laying out top-quality print
documents with elegant typography.
Adobe
No
5. Adobe FrameMaker Document processor designed for writing and
editing large or complex documents, including
structured documents.
Adobe
No
6. Adobe Illustrator Vector-based computer drawing tool. Adobe No
7. Adobe Photoshop Imaging and design application. Adobe No
8. Adobe Premier
Elements 10
Video editing software. Adobe No
9. Alert Plus Automatically send customized, conditional E-mail
notifications and reminders in SharePoint.
Bamboo Solutions No
10. AQTESOLV
Professional
Design and analysis of aquifer tests in confined,
leaky, unconfined and fractured aquifers.
HydroSOLVE,
Inc.
No
11. ArcGIS and ArcPad
(ESRI)
An integrated collection of GIS software products
for building, deploying, and maintaining a
comprehensive geographic information system.
ESRI, Inc. No
12. Articulate Integrated package to quickly create e-learning
courses from PowerPoint and develop stunning
interactive content, quizzes, assessments, and
surveys.
Articulate No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-44
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
13. Backup Exec
Capacity Edition
Provides integrated deduplication, replication, and
disaster recovery capabilities and helps to manage
multiple backup servers and multi-drive tape
loaders.
Veritas
No
14. BestFit Fully automated Windows solution for fitting data
to the best distribution.
Palisade No
15. Camtasia Studio Used to create screen capture training videos. It is
screen recording and video editing software.
TechSmith
Corporation
Resellers
No
16. Canberra Eclipse
LB
Control & Analysis
Software
Provides analysis and control of CANBERRA
Alpha/Beta counting systems.
Canberra No
17. Cisco IOS IOS for the network switches (SMARTNet
contract)
Cisco No
18. Corpscon Allows coordinates conversion between
Geographic, State Plane, Universal Transverse
Mercator (UTM) and U.S. National Grid systems
on the North American Datum of 1927 (NAD 27),
the North American Datum of 1983 (NAD 83), and
High Accuracy Reference Networks (HARNs).
U.S. Army Corps
of Engineers
Yes
19. Crystal Ball
Professional Edition
Spreadsheet-based application for predictive
modeling, forecasting, simulation, and
optimization.
Oracle Resellers No
20. Crystal Reports A robust production reporting tool which turns
almost any data source into interactive, actionable
information that can be accessed offline or online,
from applications, portals and mobile devices.
SAP Crystal
Reports
No
21. CyberLink
PowerDirector 8
Ultra
Offers video editing and enhancement tools,
designer tools, and more timeline tracks to let you
create sideshows and great videos.
CyberLink Corp No
22. DB/Text for SQL
and DB/Text
WebPublisher Pro
An enterprise-wide scalable content management
system
Inmagic No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-45
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
23. Debenu PDF
Aerialist
Takes Acrobat to the next level with its advanced
tools for splitting, merging, stamping, bookmarks,
hyperlinks, and process automation.
Digital river
GmbH
No
24. Deltek Cobra &
Deltek wInsight
Deltek Cobra is a system for managing project
costs, measuring earned value, and analyzing
budgets, actuals, and forecasts.
Deltek wInsight is used to augment earned value
into management processes.
Deltek, Inc. No
25. EarthVision Software for 3D model building, analysis, and
visualization, with precise 3D models that can be
quickly created and updated.
Dynamic Graphics,
Inc.
No
26. Entrust Certificate
Services
An Entrust Wildcard SSL Certificate allows you to
secure a domain and all its subdomains on an
unlimited number of servers
Entrust Certificate
Services
No
27. ERI Salary Assessor Software program that reports up to the present day
competitive wage, determines salary levels,
compares employee salaries with market
benchmarks, and provides incentive survey data.
Economic
Research Institute
No
28. FortiGate/FortiOS &
FortiAnalyzer
Software
FortiOS is a network security operating system for
the FortiGate network security appliances
(firewall).
FortiAnalyzer provides centralized network
security logging and reporting.
Fortinet No
29. Groundwater
Modeling System
(GMS)
Provides an integrated and comprehensive
computational environment for simulating
subsurface flow, contaminant fate/transport, and the
efficacy and design of remediation systems.
U.S. Army Corps
of Engineers
Yes
30. GoldSim Premier Monte Carlo simulation software solution
for dynamically modeling complex systems in
business, engineering, and science.
GoldSim
Technology Group
LLC
No
31. GPS PathFinder
Office (Trimble)
(Co-termed with
TerraSync
Professional)
Software package of GNSS postprocessing tools
designed to develop GIS information that is
consistent, reliable, and accurate from GNSS data
collected in the field.
Monsen
Engineering
No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-46
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
32. Grapher Allows you to create one of more than 70 unique
graph types.
Golden Software No
33. Hydrus 1D A Microsoft Windows-based modeling
environment for analysis of water flow and solute
transport in variably saturated porous media.
USDA No
34. IBM SPSS Statistics
Base Windows 19
Software package used for interactive or logical
batched statistical analysis.
SPSS No
35. Intel Parallel Studio
XE Composer
Edition for Fortran
Windows
Simplifies the design, development, debug, and
tuning of code that utilizes parallel processing to
boost application performance.
Synnex No
36. KioWare (Kiosk
Software)
KioWare Classic Basic for Windows provides vital
lockdown security for browser-based applications,
restricting users from accessing the OS (Windows)
and desktop, and allowing customization to limit
Internet access.
KioWare Stats Tool is an add-on installed on the
KioWare PC and used to collect and view usage
stats locally on the PC.
KioWare No
37. Logger Suite Software interface between the console of the
Matrix Geophysical Logging System
(LVNE200592) and the computer.
Mount Sopris
Instruments
No
38. LoggerNet Supports programming, communication, and data
retrieval between dataloggers and a PC.
Intermountain
Environmental
No
39. LogPlot Displays geotechnical, environmental, geophysical,
mud/gas, and mining data as a graphic boring log.
RockWare No
40. ManageEngine
Desktop Central
Professional Edition
An integrated desktop and mobile management
software.
Zoho Corporation
Resellers
No
41. ManageEngine
EventLog Analyzer
10
Automates the process of managing terabytes of
machine-generated logs by collecting, analyzing,
correlating, searching, reporting, and archiving
from one central location.
Zoho Corporation
Resellers
No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-47
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
42. ManageEngine
OpManager
Essential Edition
A network monitoring software. OpManager helps
administrators troubleshoot performance
bottlenecks and resolve network outages quickly.
Zoho Corporation
Resellers
No
43. ManageEngine OS
Deployer 4
Provides central image capturing and deployment
capabilities to help standardize the entire
organization on a single/few OS.
Zoho Corporation
Resellers
No
44. ManageEngine
ServiceDesk Plus
Professional Edition
A comprehensive help desk and asset management
software that provides help desk agents and IT
managers an integrated console to monitor and
maintain the assets and IT requests generated from
the users of the IT resources in an organization.
Zoho Corporation
Resellers
No
45. McAfee EndPoint
Threat Protection
Offers essential protection using integrated
endpoint protection technologies that collaborate in
real time to analyze and combat threats, identifying
and blocking the execution of suspicious files,
websites, and potentially unwanted programs.
McAfee Resellers No
46. McAfee VirusScan
Enterprise for Linux
Uses a unique, Linux-based on-access scanner that
constantly monitors your system for potential
attacks.
McAfee Resellers No
47. MicroShield A comprehensive photon/gamma ray shielding and
dose assessment program that is widely used for
designing shields, estimating source strength from
radiation measurements, minimizing exposure to
people, and teaching shielding principles.
Grove Software,
Inc.
No
48. MiniTool Partition
Wizard
Partition manager software with comprehensive
functions which has the capability to resize and
move, extend, merge, split, create, delete and
format, copy, convert, explore, recover, hide and
unhide server and non-server partitions and much
more.
MiniTool Solution
Ltd.
No
49. Microsoft Project Project management software program that is
designed to assist a project manager in developing a
plan, assigning resources to tasks, tracking
progress, managing the budget, and analyzing
workloads.
Microsoft
Resellers
No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-48
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
50. Microsoft
SharePoint Server
2013
Enables organizations to create web sites to share
information with others, manage documents from
start to finish, and publish reports to help make
better decisions.
Microsoft
Resellers
No
51. Microsoft SQL
Server 2014
Enterprise Core
A software product with the primary function of
storing and retrieving data as requested by other
software applications—which may run either on the
same computer or on another computer across a
network (including the Internet).
Microsoft
Resellers
No
52. Microsoft Visio A diagramming and vector graphics application
which comes in Standard, Professional, and
Premium Editions. It includes stencils for business,
basic network diagrams, organization charts, basic
flowcharts, and general multi-purpose diagrams.
Microsoft
Resellers
No
53. Microsoft Visual
Studio
Used to develop computer programs for Microsoft
Windows, as well as web sites, web apps, web
services, and mobile apps.
Microsoft
Resellers
No
54. Microsoft Windows
7 Professional
Edition
A personal computer operating system shipped with
updated versions of several stock applications,
including Internet Explorer 8, Windows Media
Player, and Windows Media Center.
Microsoft
Resellers
No
55. Microsoft Windows
Server 2008 R2
Enterprise
Server operating system. Microsoft
Resellers
No
56. Microsoft Windows
Server 2012 R2
Datacenter
Delivers a highly dynamic, available, and cost-
effective server platform for the datacenter, as well
as private and hosted clouds.
Microsoft
Resellers
No
57. Microsoft Windows
Server 2012 R2
Standard
Delivers a highly dynamic, available, and cost-
effective server platform for the datacenter, as well
as private and hosted clouds
Microsoft
Resellers
No
58. MiniTool Partition
Wizard Server
Edition 9.1
Software utility which has an all-in-one safe and
fast partitioning engine with advanced security
features.
MiniTool Solution
Ltd.
No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-49
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
59. Microsoft Developer
Network
Subscription
(MSDN)
MSDN is only purchased as an add-on to a Visual
Studio license. Having an active MSDN
Subscription with Visual Studio means that you
have access to all past & future versions of Visual
Studio.
Microsoft
Resellers
No
60. Nero 9 Standard Allows you to create, rip, burn, and mount almost
anything, such as music, videos, photos, and data.
(Feature is available in Windows 10; this software
will be eliminated once we upgrade from Windows
7.)
Nero No
61. Nessus Professional
Feed
Provides vulnerability, configuration and
compliance assessments. It prevents network
attacks by identifying the vulnerabilities and
configuration issues that hackers use to penetrate a
network.
Tenable Resellers No
62. PEST++ A Parameter ESTimation and uncertainty analysis
software suite.
USGS No
63. PitStop Professional
(Enfocus)
The de facto standard for graphic arts and
publishing professionals needing to preflight, edit,
and fix PDF files.
Enfocus No
64. P6 Professional
R16.2
An implemented spectrum of Earned Value
Management Systems (EVMS) at a program level.
Plan, schedule, and control complex projects.
Track progress, monitor and visualize project
performance versus plan. Compatible with Deltek
Cobra.
Oracle Resellers No
65. Primavera P6
Enterprise Project
Portfolio
Management
(EPPM)
Provides the management of projects of any size
with robust and easy-to-use solution for globally
prioritizing, planning, managing, and executing
projects, programs, and portfolios.
Oracle Resellers Yes
66. Primavera Risk
Analysis
Integrates directly with project schedules and cost
estimates to provide quick and easy techniques to
model risks and analyze the cost and schedule
impacts of mitigating them.
Oracle Resellers No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-50
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
67. Q-Pulse An electronic quality management system. Gael Quality Ltd. No
68. QuickTime An extensible multimedia framework developed by
Apple Inc. capable of handling various formats of
digital video, picture, sound, panoramic images,
and interactivity.
Apple No
69. RealVNC VNC
Connect
Remote desktop for Linux RealVNC No
70. Red Hat Enterprise Premier operating system for open source
computing and provides core operating system
functions and capabilities for application
infrastructure.
Red Hat Resellers No
71. RESRAD A computer model designed to estimate radiation
doses and risks from RESidual RADioactive
materials.
Argonne National
Laboratories
No
72. RockWorks Is the standard in the petroleum, environmental,
geotechnical, and mining industries for subsurface
data visualization, with popular tools such as maps,
logs, cross sections, fence diagrams, solid models
and volumetrics.
RockWare No
73. Roxio Easy Media
Creator 10 Silver
Allows you to produce impressive multi-media
projects that combine photos, video and music;
share and enjoy on CD, DVD, the web or on
popular portable players and cell phones.
(Feature is available in Windows 10; this software
will be eliminated once we upgrade from Windows
7.)
Roxio No
74. RSA Authentication
Manager
Platform behind RSA SecurID® that allows for
centralized management of the RSA SecurID
environment, which includes authentication
methods, users, applications and agents across
multiple physical sites. Verifies authentication
requests. Centrally administers an organization’s
authentication policies.
Maintenance
through 4 Points
Technology
No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-51
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
75. SADA Spatial Analysis and Decision Assistance offers
tools for spatial analysis in 2 and 3 dimensions,
statistical analysis and environmental decision
support.
University of
Tennessee
No
76. Samba The standard Windows interoperability suite of
programs for Linux and Unix.
Samba
(Freeware)
No
77. SeriesSEE Is an Excel Add-In, an advanced method for
modeling water levels and estimating drawdowns.
USGS No
78. SGeMS Is a software for 3D geostatistical modeling. Stanford
University
(Open Source)
No
79. SigmaPlot Helps to quickly create exact high-quality graphs. Systat Software
Inc.
No
80. SolarWinds
Network
Configuration
Manager DL50
An automated network configuration and change
management software to standardize and protect
networks and provides powerful network
monitoring tools.
SolarWinds
Resellers
No
81. Statistica Provides the most comprehensive array of data
analysis, data management, data visualization, and
data mining procedures.
TIBCO StatSoft,
Inc.
No
82. Surfer Provides the tools to create high-quality maps to
easily communicate both simple and complex
spatial data.
Golden Software No
83. SurveyMonkey An online survey development cloud-based
("software as a service") company providing
software to create fast, easy surveys for fast, easy
feedback which can be deployed via E-mail, the
web, or survey panel and can be used to view,
analyze, and report survey results.
SurveyMonkey No
84. Symantec Endpoint
Encryption
Hard disk and removable media encryption
software.
NFO/M&O No
85. Tecplot Performs computational fluid dynamics (CFD)
visualization and analysis where data can be
Tecplot, Inc. No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-52
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
quickly explored and high-quality images and
animations are presented exactly as desired.
86. TerraSync
Professional
Designed for fast and efficient field GIS data
collection and maintenance.
Monsen
Engineering
No
87. UltraEdit Used for text editing, web development, system
administration, power and performance, desktop
development, and file compare.
IDM Computer
Solutions
88. VirtualBox (Oracle) Provides cross-platform virtualization extending the
capabilities of an existing computer so that it can
run multiple operating systems at the same time;
facilitates software installations; can be utilized for
testing and disaster recovery; and provides
infrastructure consolidation.
VirtualBox
(Oracle)
(freeware)
No
89. WebEx Meeting
Center Online
(Cisco)
Offers cost-effective enterprise video conferencing
with integrated audio, video, and content sharing
with highly secure WebEx meetings from the Cisco
Collaboration Cloud.
Cisco WebEx No
90. WinGslib A toolbox of Geostatistical software algorithms. Statios LLC No
91. WinZip A shareware zip utility for file compression,
encryption, sharing, and data backup.
WinZip
Computing, Inc.
No
92. XLSTAT-3D Plot,
XLSTAT Pro,
XLSTAT Time
XLSTAT-3DPlot is part of a statistical analysis
software suite. It facilitates the visualization of your
data by using informative three-dimensional charts
and also offers impressive color and graphic
capabilities guaranteed to make your presentations
memorable.
XLSTAT-Pro is the analytical add-in for MS Excel
and includes many statistical and data analysis
functions.
XLSTAT-Time is an Excel add-in that has been
developed to provide XLSTAT-Pro users with a
powerful solution for time series analysis and
forecasting.
Addinsoft No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-53
System /
Application Name Short Description / Purpose Use
Provider or
Vendor
DOE EM-NV
Interchange
Y/N
93. Zmanda/Amanda
(Co-termed)
Amanda Enterprise Backup Server and Zmanda are
powerful, low-cost, open source backup and
recovery software used to protect Linux, Solaris,
Windows, and Mac OS X environments using a
web-based management console.
Carbonite, Inc. No
EM Nevada EPS- Draft RFP Section C
Solicitation# 89303318REM000014
C-54
Exhibit C-3, NNSS Waste Generator Map