Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Breakout Session: Controls
Controls Commissioning Experience
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
First Beam
LCLS commissioned a new injector with beam
AND commissioned a new Control System
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Overview
This presentation summarizes which control system components are currently working for the injector commissioning phaseScreen shots from EPICS show functionality of each systemData from the Elog is shown to illustrate acquisitionComments on what works and what doesn’t are includedSummary includes lessons learned and what still needs to be done
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Everything is accessible from this screen
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Beam line graphic used for most GUIse.g. injector vacuum summary
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
BCS Summary status display: - Calibration of detectors not completed yet - SubBooster Interface timing “difficult”
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
MPS- working with SLC processor and timing
- ion chambers do trip beam
- several MPS inputs (limit switches on obstructions) not available yet
New optical fiberLoss monitor
screen
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Conventional facilities- interfaced to EPICS controls- gun LCW temp feedback working ok at 30 Hz
- need to add alarm interface for temperatures, flows etc.
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Timing System- see separate presentation by S. Allison
- LCLS Event system and SLC Timing working in consort
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Laser Systems- Image Acquisition and Steering Feedback
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Gun RF Feedback in Operation - closing the loop between PAD and PAC
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
RF Phase Scans
Data acquired with Matlab
Data acquired with SCP Correlation Plot
(diagnose a satellite peak from laser)
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Profile monitors - control and diagnostics through EDM screens
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Image acquisition with MatlabGun spectrometer YAG Profile Monitor Screen
• Using physicist’s scripts up till now• ImageManager package coming online now
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Beam Position Monitors- see separate presentation from S. Smith
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Asynchronous Beam Acquisition via SCPe.g. Gun charge vs. laser power
Measured on the SCP Correlation Plot
But some people still plotting data offline
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Beam Synchronous Acquisition is working through Matlab – example of orbit display
- BSAP via the SCP coming next
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Motion control-BC1 chicane movers in use
- next to be commissioned: wire scanners, collimators
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Generic Tools that are working
SCPConfiguration save and restore
EPICS Channel Watcher
Correlation plots
Strip chart toolsArchive ViewerAlarm handlerElectronic logbookMatlab for higher level applications
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Strip Tool monitoring gun temperatures during RF trips
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Electronic logbook gives instant overview
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Control Room Conditions Still a Bit Cramped (first beam to end of BC1!)
Reorganizing the control room layout
Purchasing more workstations
Injector commissioning involved 12 or more in the room, so its likely to increase as the linac and undulator systems are commissioned
Patrick Krejcik
LCLS FAC [email protected]
April 16-17, 2007
Summary and lessons learned
Remarkable commissioning achievement for the control systemControls commissioning time was squeezed
How do we ask for more?
Planned BC2–linac installation is tight Improve liaison with mechanical engineeringWe are still learning how to handle large number of IOCs and the huge number of PVs
e.g. Restoring after a reboot
Large number of EDM displays can confuse operators at times (looking for a screen that may be already open)Controls group is a great TEAM!