Name of Client Punit Ji
Flat Number P.House
Super Area 3141.8
Terrace Area
Chargable Terrace Area 50% 0
Total Chargable Area 3141.8
Per Sq.Ft. Rate (BSP) 6475
Per Sq.Ft. Rate (PLC) 500
BSP 20343155
PLC 1570900
Electricity and water Connection charges As per Actual
EDC/IDC @ Rs.285 /- 895413Covered Car Parking 350000
IFMS @ Rs.100 /- 314180
Club Membership 100000
Service Tax 835127
Total Cost 24408775
Months Amount BSP Amount IDC/EDC Amount PLC AmountClub
MemAmoun
At the Time of booking 10% 2034316
With in 60 days of booking 15% 3051473
On Date of Execution of Agreement to sell 5% 1017158 50% 447707 50% 785450
On Start of Excavation Work 10% 2034316 50% 447707 50% 785450
On Foundation Laying/Start of Construction 5% 1017158 25%
On Completion of Foundation 5% 1017158 25%
On Casting of Ground Floor 5% 1017158 25%
On Casting of First Floor 10% 2034316 25%
On Casting of Second Floor 5% 1017158
On Casting of Third Floor 5% 1017158
On Casting of Fourth Floor 5% 1017158
On Completion of Brick Work and Internal Pl 5% 1017158
On Completion of Internal Flooring 5% 1017158
On Application of Occupancy Certificate 5% 1017158
On Receipt of Occupancy Certificate 5% 1017158 100% 100000
IFMS 100%
100% 20343155 100% 895413 100% 1570900 100% 100000 100%
3. Electricity and Water Connection charges will payable as per actual and in two installments
1. In case the purchaser makes any prepayment for any of the installments as stated above, the developer has a right to retain/ refund the excess money received
such amount, an interest of 10% p.a. calculated on monthly basis for the period of prepayment of installments will be paid to the purchaser by the Developer on t
have been lying with the company for more than one year
3. Service Taxes Payable as per the prevailing rates.
Raheja Developers - Installment Payment Plan
2. If Purchaser books an apartment in between after the Ist Launch Date, The entire outstanding amount of the installments valid till that date shall have to be pai
Rate per Sqft
Corner
Revanta Independent Floor