IAEA International Atomic Energy Agency Key Activities on Construction Management October 2012 Ki Sig Kang

Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

  • Upload
    hatram

  • View
    221

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA International Atomic Energy Agency

Key Activities on Construction

Management

October 2012

Ki Sig Kang

Page 2: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Overview of Current Status

2

436 In operation

370 GWe total net installed capacity

63 Under construction

Page 3: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction of Nuclear Power

Page 4: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Number of new Npps construction

0

2

4

6

8

10

12

14

16

1 2 3 4 5 6 7 8

GW 1.03 3.4 3.3 7.6 10.5 14 15.8 1.9

No 2 4 4 7 10 14 16 4

GW

No

2004 2005 2006 2007 2008 2009 2010 2011

Page 5: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA Power Plant Engineering Page

5

Manpower and Duration

• Manpower : 4000/day, more than 80 Months

• Preparation : 40% and Implementation : 60%

Page 6: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Material & Cost

• Rebar (Ton) = 76,070

• Cable (Km) = about 4,000

• Instrumentation : 22500

• Large bore piping(m)= 120,000

• Cost : 5 Billion

• Indirect cost : 2 Billion - 40%

• Interest(32%), CPI (30%), initial fuel cost (10%), Others(28%)

• Construction : 1.2 Billion – 25$

• Equip. Procurement : 1.5 Billion – 30%

• Design/ Eng : 0.3 Billion - 5%

Page 7: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Operation / decommissioning

•Preparing for

assuming

commitments &

obligations

Commissionin

g

Nuclear power option

included within the

national energy strategy

10 – 15 years

PHASE 2 PHASE 3 PHASE 1

MILESTONE 1 Ready to make a knowledgeable

commitment to a nuclear

programme

MILESTONE 2 Ready to invite bids

for the first NPP

•MILESTONE 3 •Ready to commission and

operate the first NPP

Bidding process

Pre project Project decision making Construction

Considerations before a decision to launch a nuclear power programme is taken

Preparatory work for the construction of a NPP after a policy decision has been taken

Activities to implement a first NPP

Maintenance and continuous infrastructure

improvement

•www.pub.iaea.org/MTCD/publications/ninfrastructure.asp

Pre- Feasibility Study Feasibility Study

10/17/2012 7

Preparation

of

Infrastructure

Commissioning

and Operation

• Project Decision Making

• Feasibility Study

• Environment Impact

Analysis(EIA)

• Site Evaluation

• Bid information

Specification and Bidding

and Evaluation

• EPC contract

• Construction

• Public information and

understanding

Page 8: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Involvement of the Main Entities

Involvement of the Government

Ready to

invite bids

Ready to commission and

operate the first NPP

Ready to make a decision on whether

or not to introduce nuclear power

Phase 1 Phase 2 Phase 3

Involvement of the Regulatory Body in nuclear power activities

establishment

Involvement of the Operating Organization

establishment

1~3 years 3~7 years 7~10 years

Page 9: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA International Atomic Energy Agency

Case Study to optimise construction

duration

Page 10: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Average Duration for Past NPP Construction 1969 to

1977 in USA

Since 1972,

rapidly

increase

construction

period

Why ??

Page 11: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction Time Span

Categories 1970-1995

[month]

1996-Now

[month]

1970-1995

[year]

1996-Now

[year]

Median 80 83 6.67 6.92

Minimum 41 47 3.42 4.08

1 Quartile 67 61 5.58 5.08

3 Quartile 105.5 176 8.79 14.67

Maximum 283 302 23.58 25.17

Resource : Power Reactor Information System in the IAEA database

Page 12: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

The Shortest Construction Period

• Construction Schedule at 1350 Mwe

• From F/C to CO : 62 49 Months

• Construction Schedule at 1000 Mwe

• From F/C to C/O : 64 47 Months

• C/O: Commercial Operation

• F/C : First concrete pouring

Page 13: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction Scheudle in Gen III+ NPPs

Site preparation : 12~18 M

Construction : 36~42 M

Start-up : 6~ 7 M

Total : 60 M

Page 14: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction Schedule of Japan NPPs

Improve Construction Method

’ 80 ’ 85 ’ 90 ’ 95 ’ 00 ’ 05 ’ 70 ’ 75

50 M

60 M

70 M

80 M

90 M

100 M

110 M

120 M

130 M

US BWR

Japan BWR

Japan ABWR

Year of Fuel Loading ’ 80 ’ 85 ’ 90 ’ 95 ’ 00 ’ 05 ’ ’

Co

nstr

uctio

n D

ura

tio

n (

mo

nth

)

40 M

50 M

60 M

70 M

80 M

90 M

100 M

110 M

120

130 M TMI

US BWR

Japan BWR

Japan ABWR

US BWR

Japan BWR

Japan ABWR

3D-CAD Drawing Plastic Model 6D-CAD

Page 15: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

USA Npps Construction Experiences

0

20

40

60

80

100

120

140

160

180

200

St.L

ucie 2

Pal

o Ver

de 1

Gra

nd Gulf

1

Wolf

Cre

ek 1

Sea

brook

1

Susq

uehhan

na

Sum

mer

1

Byro

n 1

San

Onofr

e 2

Wate

rford

3

LaSal

le

Com

anch

e Pea

k 1

Per

ry 1

McG

uire

Shore

ham 1

Mid

land 2

Cata

wba 1

Watts

Bar 1

Harr

is 1

Wash

ingto

n Nucle

ar 2

Enric

o Fer

mi 2

Limer

ick 1

Page 16: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

KEDO 1&2

Bataan Npp in

Philippines

Westinghouse 2 Loop

600 Mwe

95% completed,

Political reason

Page 17: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Cernavoda NPP, Romania

Right: Unit 1 /2 (in operation), Unit 3 (in preservation)

Left: Unit 4 and 5 (in preservation)

Page 18: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA Atucah II Npp-

Installation of Moderator Tank, June 2009

Page 19: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA 10/17/2012 19

Angra 3 NPP, Brazil

Page 20: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Olkiluoto 3 at the end of April 2009

Source: TVO

Core thermal power

Net power output

Net efficiency

4300 MWth

1577 MWel

37 %

May 2005 : First Concrete for Reactor Building

May 2007 : RPV installed,

May 2008 : Start Hot Functional Tests

Aug. 2008 : First Fuel Loading

Nov. 2008 : First Criticality

April 2009 : Start Demo-Run

OL3 construction site in February

2012

Page 21: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction site : Manpower

about 3,500 • Turbine island : Construction work

finished and system

commissioning preparations

ongoing

• Nuclear island : Main civil works

to be finished in 2011

• Installation of the main

components close to completion

• Piping and electrical installations

ongoing

Supplier(AREVA) has informed

that most of the works will be

completed in 2012.

Consequently, operation will

start during the early 2015

Page 22: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Major Concrete Dismantling and Demolishing

Project in Belene - Site Preparation

•Dismantling and Demolishing

•Reinforced Concrete 150 298 m3

•Steel Structures 8 760 t

•Excavation works 150 923 m3

•Planned Duration 18 months • Mobilization 2 months

• D&D 14 months

• Demobilization 2 months

Page 23: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

… and 10 months

after …

Site opening on

31.07.2008

Major Concrete Dismantling and Demolishing

Project in Belene - Site Preparation

Page 24: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Watts Bar Unit 2 – Delayed NPP

• Completed

partially Unit 2.

(PWR, 1100 Mwe)

• Unit 2 was about

80% completed,

stopped in 1988.

• Resumed on

October 15, 2007,

• Operation in Oct.

2012(60 M)

• $2.5 billion USD

Page 26: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Inspection Report of BNP

• Need additional $1.5 B to $2 B(2.5B $4~ 4.5 B$)

• Completion : Sep 2015 (Total : 60 M 96M)

• EPC : Bechtel

• Main reasons :TVA management did not • Perform effective warning signs of the EPC contractor

• Address certain warning known signs that the project was in

trouble.

• Adequately mitigate known problems related to staffing, work

order package, timeliness and quality of information provided to

the NRC, and procurement of material that require a long time to

obtain

NRC letter : TVA has not yet been able to fully address these issues

Page 27: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA International Atomic Energy Agency

How can reduce construction duration ?

Page 28: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Site Construction

Management

support system

Modularization

with very large

crane

On-site

Work reduction)

Site Support

work efficiency

Open-top

&

parallel

construction

Work Leveling

(Peak Reduction)

Early and

Detailed

engineering

before on-site

work

Work

Efficiency

Strategies for shortening Con. period

With Modularization Method

Construction Period = 38M (actual First ABWR)

Milestones S/C R/I M/C O/C P/S RPV H/T F/L C/O F/C

Page 29: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

40

100

’ 80 ’ 85 ’ 90 ’ 95 ’ 00 ’ 05

100

60

80

40

現地工数(出

力比

) (2

F -

1

=1

00

)

燃料装荷年度

Manhour Reduction with Early Engineering

Past

Design Start

Detailed engineering completed before construction start

Construction Start CO

Design/Engineering

Construction

Reduced Site Manpower to 40%

Man

ho

ur

‘80 ‘90 ‘00 ‘85 ‘95 ‘05

Current

Design Start Design Freeze

Design/Engineering

Construction

Early finish of Engineering

Page 30: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Front-Loaded Construction Engineering

Basic Design

Detailed Design

Construction

Construction Engineering

Previous Design Process

Front-Loaded Construction Engineering

Basic Design

Detailed Design

Construction

Construction Engineering

Requirements from Construction Engineering Inputs from Plant Design

(BOQ, Composite Design, etc.)

Source : From Hitachi construction experiences

Page 31: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

建設工程

3D-model linked with Schedule

Construction Schedule with 6D

Page 32: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction Schedule with 6D

3D-model by construction area

Quantities based

on 3D-model

Assign Labor

resource

Schedule loaded with Quantities and Resource

3D-model + Quantities + Resource + Time = 6D Database

• Develop detailed and precise Construction schedule by construction area based on Quantities and Labor resource

• Simulate the schedule with 3D-model

Page 33: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

RPV

Upper Condenser Module RCCV Lower Liner Module

Lower Condensor Unit RPV Pedestal Module Base Mat Module HPU Module

Stator Upper Drywell Module RCCV Top Slab

(420 ton)

(410 ton) (460 ton) (260 ton)

630 ton) (270 ton)

(650 ton) (900 ton) (550 ton)

(270 ton)

On-site Work Reduction - Modularization Method -

Page 34: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Sep 27, 2010 Unit 1 CA01 lifting.

Page 35: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Man P

ow

er

Construction Progress

(month)

Level-off

Manpower Peak

Based on previous ABWR (Conventional Method) (a

rb.)

Manpower Peak Reduction Effort

- Construction & Module Experience-

4

3

2

1

1 6 11 16 21 26 31 36 41 (month)

Manpower Distribution

Based on Latest ABWR

Page 36: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Advanced Welding Techniques

• Quality welding is crucial and time consuming

• Advanced Techniques • Metal Arc Welding,

• Gas Tungsten Arc Welding

• Submerged Arc Welding

• Automatic welding equipment is very effective • Maintaining high quality

• Improving the working environment in narrow spaces.

Page 37: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Automatic Welding Machine

Automatic Welding Machine for RCCV Liner

Automatic Welding for Large Bore Piping

Automatic Welding for Small Bore Piping (CRD piping)

Page 38: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Four Season Construction

• Provides “Factory-like” environment for

construction during winter

• Secures environment for:

• Welding

• Concrete pouring & curing

• Protection from equipment

• Allows around the clock work

Page 39: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Improvement of Work Productivity

during winter

Buildings with the All-Weather Structure (Steel and Temporary cover)

Four Season Construction

Movable Temporary Roof

70

75

80

85

90

95

100

冬期稼働率[%]

個別養生耐候工法 全天候耐候工法

Page 40: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA International Atomic Energy Agency

Lessons Learned

Page 41: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Lessons Learned (Project Management)

• Circumstances in Europe and the USA are quite different from 1970’s • India, Japan and Korea seems to be different

• Safety requirements clearly should be understand to avoid surprises. • Understanding of regulatory practices is essential

• Vendors and their sub-contractors have lost much knowledge and skills • New type of competence is needed for new technologies.

• New advanced safety features are not easily implemented

• New sub-contractor networks from companies with proven skills

Page 42: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Lessons Learned (Project Management)

• Not underestimate the importance of proven experience • How to organize the construction site organization,

• What resources are needed and when,

• How the vendor can find competent contractors and how it should manage them,

• A real competence of manufacturers and sub-contractors is not easy to judge through auditing only

• How the owner should mange the construction according to schedule

Page 43: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

• Ensure before starting the implementation. • Licensee’s capabilities

and resources

• Vendor’s capabilities and resources

• The design has been done to a detailed level,

• Qualified subcontractors are available

Past Design Start

Construction Start CO

Design/Engineering

Construction

Current

Design Start Design Freeze

Design/Engineering

Construction

Early finish of Engineering

Lessons Learned (Design)

• Challenges from design changes

• Design standards and Material Substitution Management

• Localization and technical transfer

Page 44: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Lessons Learned (Design)

• Inadequate completion of design and engineering work prior to start of construction

• Delay the start of construction activities at full speed

• Cause continuous pressures to all involved organizations

• Lead to attempts to reschedule manufacturing and construction steps,

• Lead to reduced quality due to time pressure

Page 45: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Lessons Learned (Design)

• Inconsistency and different location in design • Different organisations in different places or even in

different countries

• Vendor’s standards and international or imported country

• Metric system and British units

Page 46: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Lessons Learned (Modularization)

• Difficulties during the module

fabrication process.

• Procurement (Fabrication)

• Welding technology

• Challenges in the process of

modularization construction

• Assembling technology

• Lifting deformation control

• Transportation plan

• Installing, measuring and

positioning technology

Biggest module : Size: 21×14×21M

Weight: 850t

Page 47: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Barakah-Unit 1, UAE

• The United Arab Emirates is the first country to start the construction

of its first nuclear power plant in 27 years, since construction was

started on China's first plant in 1985.

• As of 30 August 2012, the Barakah-Unit 1 is reported in the IAEA

Power Reactor Information System (PRIS) as "under construction

July 20 2012

Concrete

pouring

after permission

of PSAR

Page 48: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Financing and Bids invitation and evaluation

Page 49: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Construction management and technology

Page 50: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Human Resource management / Grid Reliability and

interface

Page 51: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

Once mounted on a tiger’s back, it is

hard to control him

騎 虎 難 停

Page 52: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

天下鳥 鴉 一般黑 Which tiger is easier to

control when we mount ?

All the crows and ravens

in the worlds are all

blackish in general.

The problems do not

reside in the hired

foreign company but in

ourselves

Page 53: Key Activities on Construction Management project Project decision making Construction Considerations before a decision to launch a ... Major Concrete Dismantling and Demolishing Project

IAEA

IAEA assistance package for future

NPP Owner/Operator • Nuclear Power Program Management : How to Become a

Knowledgeable Customer

• Establishment of the NPP Owner/Operator organization

• Integrated Management System for the NPP Owner/Operator

organization.

• First NPP Feasibility Study preparation

• Interfaces of NPP Owner/Operator with national Regulatory Bodies

for the first NPP licensing

• Commissioning Management of the first NPP

• First NPP site selection

• Stakeholder involvement

• NPP bidding process, including preparation of BIS for the first

NPP

• Construction Management of the first NPP Project

• Construction Technology of the first NPP Project