  • PENGUKURAN KONVERGEN UNTUK MENILAI KESTABILANLUBANG BUKAAN BAWAH TANAH DI TAMBANG EMAS

    CIKIDANG

  • T 622. 2 WED

  • ABSTRAK

    Tambang Emas Cikidang menerapkan sistim Underhand StulledStoping yang menimbulkan bekas berupa lubang bukaan bawah tanahvertikal. Tingkat kestabilan dan faktor dari luar yang mempengaruhikestabilan perlu diketahui.

    Evaluasi dilakukan dengan pengukuran konvergen dari dindinglubang yang berhadapan menggunakan konvergen-meter. Pemantauandilakukan pada 8 lokasi; Bukit-1 dua lokasi, Bukit-2 dan Bukit-3 masing-masing 3 lokasi. Evaluasi kestabilan memakai metode kecepatanperpindahan menurut Zhenxiang (1984).

    Hasil evaluasi: 1) Bukit-2 mengalami perpindahan terbesar, dalam697 jam jarak dinding mengecil 28,39 mm. Bukit-1 mengalami perpindahanterkecil, dalam 702,25 jam jarak dinding mengecil 4,76 mm. 2) Lubangbukaan di Bukit-1 stabil, Bukit-2 relatif stabil, Bukit-3 relatif stabil sampaistabil. 3) Faktor dari luar yang meningkatkan kecepatan perpindahan:gempa bumi, peledakan sampai jarak 8,5 - 9 m di muka titik pantau, danpenggalian permuka kerja sampai jarak 11,60 - 15,50 m di muka titikpantau.

  • ABSTRACT

    Cikidang gold mine applies Underhand Stuffed Stoping system that createsvertical underground opening. Stability factor and outside factors influencing stabilityneed to be found.

    Evaluation was carried out by convergence measurement from the oppositewalls of the opening by using a convergence-meter. The observation was carried out ateight locations; two locations at Hill-1, and three locations each at Hill-2 and Hill-3.Stability evaluation used rate of displacement method from Zhenxiang (1984).

    The result of the evaluation are: 1) Hill-2 experienced the greatest displacement,in 697 hours the distance between the walls decreased by 28,39 mm. Hill-1 experiencedthe smallest displacement, in 702,25 hours the distance between the walls decreased by4,76 mm. 2) The opening in Hill-1 is stable, the opening in Hill-2 is relatively stable, andthe opening in Hill-3 is relatively stable to stable. 3) Outside factors increasing the rateof displacement are: earthquake, explesion up to 8,5-9 m above observation point, andexavation of the face up to 11,60-15,50 m in front of the observation point.