Upload
corby
View
39
Download
3
Embed Size (px)
DESCRIPTION
PeopleSoft Upgrades Best Practices. Tom Reznicek and Patrick Savage. Save the Date. APRIL 7-11, 2014 Sands Expo and Convention Center Las Vegas, Nevada. QuestDirect.org/COLLABORATE. - PowerPoint PPT Presentation
Citation preview
QuestDirect.org
PeopleSoft Upgrades Best Practices
Tom Reznicek and Patrick Savage
QuestDirect.org
APRIL 7-11, 2014Sands Expo and Convention CenterLas Vegas, Nevada
Save the Date
QuestDirect.org/COLLABORATE
COLLABORATE 14- Quest Forum is THE source for PeopleSoft roadmaps & news. It matters where you register! All PeopleSoft education and events run through Quest
QuestDirect.org
Agenda• Introduction of Speakers and Emtec• Project Success• Project Shortcomings and Solutions• Open Discussion
QuestDirect.org
Emtec… ‘Big enough to do the work, small enough to care’
EMTEC THE COMPANY• Serving clients for over 46 years• 14 locations, including 8 development centers• Over 1,000 full-time professionals• Voted One of the Top 100 Places to Work by Cranes
Chicago in 2012• Our consultants have an average of 14 years of
experience. Nearly 45% have advanced certifications
EMTEC SERVICES AT A GLANCE• Emtec has completed more than 1,100 Package Application
engagements, including:‑ 200+ Oracle clients with more than 415 engagements‑ 206 EPM / Hyperion & OBIEE clients and 323 engagements‑ 186 Microsoft Dynamics and more than 255 projects
• Emtec is a premier provider of SaaS and Emerging technologies consulting, including 51 Salesforce Clients with more than 75 engagements, Including Sales Cloud, Service Cloud and Custom Cloud
• Emtec has performed more than 6.3M hours of application development and maintenance work ranging from Business Analysis to Product Development
• Emtec has served more than 565 Infrastructure services clients where we have:
4
QuestDirect.org
Upgrade Projects• Distribution Company• Professional Services• Professional Association• Financial Exchange• Financial Services Company
QuestDirect.org
Project Successes
QuestDirect.org
On Time Within Budget• Kept a detailed project plan so people knew
what was expected of them and when• Had regularly scheduled meetings to review
plan, risks, and resolve issues• Kept upper management involved in project
QuestDirect.org
Final Move to Production on Time• Developed detailed task list for go-live weekend• Leveraged PeopleSoft Change Assistant• Had specific call-in times for progress reporting• Used production like hardware on the final test
move to production to get accurate timing for the real move to production
QuestDirect.org
Latest User Data Security Migration• Developed method to migrate permission lists
and roles separate from user data• Created diagrams and client deliverable to
explain security migration plan
QuestDirect.org
Trained Two Client Resources• Resources had PeopleSoft Upgrade experience
but did not execute test scripts• Allowed upgrade weekend tasks to be split
between 3 people• Documented manual steps• Documented common issues and resolutions
QuestDirect.org
Reduced Data Conversion Time (72 hours to 42 minutes)
• Identified slow processes by running Application Engine tracing and data conversion steps report
• Tech leads tuned slow processes• Multiple test moves to production
QuestDirect.org
Move to Production Completed On-Time• Used job properties in Change Assistant to record
time, file name, and issues• Let Change Assistant accept errors (i.e. duplicate
keys) and clean after scripts run• Created go-live spreadsheet with pre and post steps• Bypassed some backups saving hours
QuestDirect.org
Knowledgeable Team• Technically strong and larger than previous
upgrade teams• Two Emtec resources to go to with concerns• Knowledgeable Emtec PeopleSoft Upgrade
Specialist• Cyber Source configured without additional Cyber
Source specific consultants
QuestDirect.org
Prepared Microsoft SQL Server• Turned off database logging before scripts started• Monitored database file size• Added memory to database server• Set maximum memory usage on database to
allow for other processes on server
QuestDirect.org
Updated/Validated User Guides• Guides consolidated multiple documents into one
document per business area• Created process flow diagrams for requisition and
PO entry• New testing documents for requisition and voucher
approval, GL reports, and other processes• Created technical check printer setup document
QuestDirect.org
Minor Post Go-Live Issues• Extensive testing:
– Leveraged existing test scripts by updating menu navigation and business process changes for version 9.1
– Last round of testing done on production hardware– End users involved in system and user acceptance
testing– Testing “Cheat Sheets” were created for users
QuestDirect.org
Went Live On-Time & Within Budget• Managed issues with Excel worksheet, included
owner and resolution • Assigned close action, which identified resolutions
required for production and how to apply to production
QuestDirect.org
Functional Ch. 2 & 6 Steps Completed Quickly
• Functional users completed Ch. 2 tasks to reduce the number of transactions processed
• Wrote SQL statements to perform validation checks before conversion
• Identified Ch. 2 & 6 steps that had to be performed for A in test moves to production
QuestDirect.org
Project Shortcomings and Solutions
QuestDirect.org
Test Scripts Not as Usable as Thought
• Review test plans and scripts upfront in project• Existing data and business processes that were
not fully documented• Review any work already done
QuestDirect.org
Canadian Payroll Customization Removed and Later Re-Added
• Verify removal of customizations with the business
QuestDirect.org
Applied Large Maintenance Pack Taking Longer in Production
• Keep more careful track of how much time it takes to apply large Maintenance Pack post-upgrade so more accurate estimate could be made
QuestDirect.org
Go-Live Move to Production Fell Behind in Day 2
• Escalate issues faster when processes run behind schedule
• Document how performance issues will be investigated and have required tools ready
• Do not apply new patches after last move to production• All hand-offs should be done by phone call and e-mail
QuestDirect.org
Longer Testing Than Estimated• Test check printing earlier for MICR and signature fonts• Test nVision reports earlier in process• Have Hyperion environment refreshed and ready for
PeopleSoft testing• Test credit card transactions through to Cyborg • After initial install, test system while consultants on-site• Test on same operating system (64 bit) as production
QuestDirect.org
Open Billing and Payable Transactions in Database from 2001
• Identify open transactions early in upgrade process and clean up transactions before go-live
• Run Ch. 2 tasks to identify open transactions to clean up
QuestDirect.org
Application Engine Jobs Run Manually Instead of Running Change Assistant
• Install PeopleSoft Change Assistant on Windows Admin Server
• Workstation version does not allow for automatic processing of application engine jobs