Upload
onelson-fdfg
View
217
Download
0
Embed Size (px)
Citation preview
7/28/2019 Perception Earned Value Mgmt
1/72
PERCEPTION
Earned Value Management
For
Shipbuilding
7/28/2019 Perception Earned Value Mgmt
2/72
Earned Value Management is a project
management technique designed to:
Ensure work is properly & adequately planned,
budgeted & scheduled
Isolate problems for corrective action
Measure cost & schedule performance of work
accomplished in accordance with ANSI 748
Measure true cost condition
Forecast completion date & final cost
7/28/2019 Perception Earned Value Mgmt
3/72
PERCEPTIONTies Together All Areas of
Earned Value Management
Cost Estimating
Planning, Budgeting & Scheduling
Labor Work Order & Manpower Management
Purchasing & Inventory Control Change Order Management
Earned Value Performance Measurement
Reporting Cost & Schedule Forecasting
Cost Analysis For Future Work Estimating
7/28/2019 Perception Earned Value Mgmt
4/72
Cost Estimating
Planning,
Budgeting & Scheduling
Labor & Manpower
Purchasing & Material
Cost Management Cost Management
Earned Value
Management Reporting
Cost/Schedule Analysis
7/28/2019 Perception Earned Value Mgmt
5/72
Cost Estimating
PERCEPTIONwas developed to permit costestimating that can reflect modern ship design andproduction methods. Using product- and process-based information, cost estimates can be generated
qu c y an accurate y at any eve o eta : Parametric cost estimates based upon
modifiable ship design and mission characteristics
Shipbuilding standard interim products
Detail cost estimates based upon engineered billsof material and equipment specifications.
7/28/2019 Perception Earned Value Mgmt
6/72
Cost Tracking & Forecasting
PERCEPTIONtracks cost and scheduleperformance.
Forecasts are made by the system based
upon earned value methods Trends are developed by the system to
provide management with improved
visibility of changes to contractperformance.
7/28/2019 Perception Earned Value Mgmt
7/72
Tracking & Managing Costs andSchedules
By SWBS (Ship System)
By COA (Shipyard Organization Structure)
By CLIN (Contract Line Item)
7/28/2019 Perception Earned Value Mgmt
8/72
Contract
Project
Contract Line ItemsShip Zones
Outfit Zones
Grand Blocks
Units
Blocks
PWBS SWBS COASWBS
Groups
SWBS
Accounts
Departments
Stages
Work Centers
CLINs
Option to select
WBS for ProjectRoll-Up
Planning
Activity
Assemblies
Subassemblies
Mfg Parts
Time
Charge
A Work Order May Relate to
Multiple WBSs
A Work Order referencing more than one
element of any WBS may be setup as a
Distributed Work Order.
Work Order
7/28/2019 Perception Earned Value Mgmt
9/72
Contract
Project
Contract Line ItemsShip Zones
Outfit Zones
Grand Blocks
Units
Blocks
PWBS SWBS COASWBS
Groups
SWBS
Accounts
Departments
Stages
Work Centers
CLINs
Planning
Activity
Assemblies
Subassemblies
Mfg Parts
Stock issues
Direct Purchase Materials
Owner Furnished Materials
Manufactured Parts
Work Order
Requisition
Pallet Pallet Production Material
7/28/2019 Perception Earned Value Mgmt
10/72
Tracking & Managing Costs andSchedules:
Original Estimated Costs & Schedules
Baseline Costs & Schedules
Current Plan Costs & Schedules
7/28/2019 Perception Earned Value Mgmt
11/72
Tracking & Managing Costs andSchedules:
Labor Hours
Labor Dollars
Weeks
Ahead/Behind
ver ea o ars Material Dollars
Purchased Services
Total Dollars
chedule
Forecast Finish
Date
7/28/2019 Perception Earned Value Mgmt
12/72
Multi-Ship Program ManagementCost & Schedule Consolidation
Contract
7/28/2019 Perception Earned Value Mgmt
13/72
Managing Costs & Schedule by InterimProducts and Manufacturing Process
7/28/2019 Perception Earned Value Mgmt
14/72
Multi-Shipyard Program
Management
Cost & Schedule Consolidation
PERCEPTIONmaps different shipyard WBSconfigurations to a selected WBS standard
Large U.S. Shipyards already mapped include:
Avondale Shipyards
Ingalls Shipbuilding
Bath Iron Works NASSCO
Newport News Shipbuilding
7/28/2019 Perception Earned Value Mgmt
15/72
PERCEPTIONAccommodates
Different Shipyards
& Work Breakdown Structures
Avondale *
Ingalls Shipbuilding *
NASSCO *
USCG (Modified SWBS) * *
MARAD (Weight System)
Commercial Yards US Canada
BIW * Newport News Shipbuilding *
US Navy (SWBS & ESWBS)
& Europe
Ship Repair & Conversions
Shipyard Plant Overhead
Accounts
* Work performed under the U.S. Navys Product Oriented Design & Construction
(PODAC) Project
** Work performed under the USCGs Deepwater Program.
7/28/2019 Perception Earned Value Mgmt
16/72
Tracking & Managing Costs andSchedules:
BAC: Budget At Completion
MR: Management Reserves
EAC: Estimated Cost At
Completion
BCWS: Budgeted Cost of WorkScheduled
BCWP: Budgeted Cost of Work
Performed
ACWP: Actual Cost of WorkPerformed
Planned & Actual Progress
Calendar Schedule Variance
Calendar Variance Trend for
100% Progress
7/28/2019 Perception Earned Value Mgmt
17/72
Compiling Cost & Schedule
Performance Information
7/28/2019 Perception Earned Value Mgmt
18/72
Tracking & Managing
Costs and Schedules
Rework
Change Orders
Labor Hours per 1% Progress
Production Process Rates by Stage ofConstruction
Weeks Ahead/Behind Planned Schedules
Trend Weeks Ahead/Behind for 100% Progress
Forecast & Trend Over-Run/Under-Run
7/28/2019 Perception Earned Value Mgmt
19/72
Summary Progress Reports by Any WBS
Level
7/28/2019 Perception Earned Value Mgmt
20/72
Production Work Centers
7/28/2019 Perception Earned Value Mgmt
21/72
Production Modules & Ship Zones
7/28/2019 Perception Earned Value Mgmt
22/72
Shipyard Trade/Craft
7/28/2019 Perception Earned Value Mgmt
23/72
Tracking Performance CostsTracking Performance CostsBy Percent Progress
7/28/2019 Perception Earned Value Mgmt
24/72
Tracking Performance CostsTracking Performance CostsBy Earned Value
7/28/2019 Perception Earned Value Mgmt
25/72
Tracking EAC ConfidenceTracking EAC Confidence
7/28/2019 Perception Earned Value Mgmt
26/72
Confidence in EAC is a composite of 3 factors:
F(closed) = Degree of total work completed
F(open) = Degree of work orders still open
F(performance) = Consistency of budget performance ofcompleted work orders (via normal distribution).
7/28/2019 Perception Earned Value Mgmt
27/72
Tracking ProgressTracking Progress
7/28/2019 Perception Earned Value Mgmt
28/72
Tracking & ForecastingTracking & ForecastingSchedule VarianceSchedule Variance
7/28/2019 Perception Earned Value Mgmt
29/72
Tracking & ForecastingTracking & ForecastingSchedule VarianceSchedule Variance
7/28/2019 Perception Earned Value Mgmt
30/72
Tracking & ForecastingTracking & ForecastingOverOver--Budget/Savings VarianceBudget/Savings Variance
7/28/2019 Perception Earned Value Mgmt
31/72
Tracking & ForecastingTracking & ForecastingEarned Value PerformanceEarned Value Performance
7/28/2019 Perception Earned Value Mgmt
32/72
Tracking Cost per 1% ProgressTracking Cost per 1% Progress
stper1%
consistent
rk.
Steadytrackofco
progressindicates
performanceofw
7/28/2019 Perception Earned Value Mgmt
33/72
Tracking Performance Indexes
CPI: Cost Performance Index (BCWP/ACWP) SPI: Schedule Performance Index (BCWP/BCWS)
FCPI: Forecast Cost Performance Index (BAC/EAC)
CSPI: Current Schedule Performance Index(ACWP/BCWS)
CCPI: Combined Cost Performance Index (0.5 CPI x[1 + SPI + SPI x (BCWS-BCWP)/BAC]
TCPI: To-Complete Performance Index(BAC-BCWP)/(EAC-ACWP)
7/28/2019 Perception Earned Value Mgmt
34/72
Total Contract Performance
Summary
7/28/2019 Perception Earned Value Mgmt
35/72
Tracking Performance Indexes
7/28/2019 Perception Earned Value Mgmt
36/72
Tracking & Managing DollarDollar Costsand Schedules:
Direct Labor Costs
Overheads Costs
Management Reserves
7/28/2019 Perception Earned Value Mgmt
37/72
Tracking & Managing DollarDollarCosts and Schedules
Direct Labor Costs
Material & Subcontract Costs
Management Reserves
7/28/2019 Perception Earned Value Mgmt
38/72
Total Cash Budget Vs EAC
7/28/2019 Perception Earned Value Mgmt
39/72
Tracking Actual Costs
7/28/2019 Perception Earned Value Mgmt
40/72
Tracking Earned Value Costs
7/28/2019 Perception Earned Value Mgmt
41/72
7/28/2019 Perception Earned Value Mgmt
42/72
Tracking & Managing MaterialMaterialCosts and Schedules
Total Committed Costs:Purchases + Stock Used + Stock Reserved
Total Purchases
Purchases Received Purchases Used
Purchases Paid
Stock Used
Stock Reserved
7/28/2019 Perception Earned Value Mgmt
43/72
Tracking Material CostsTracking Material Costs
7/28/2019 Perception Earned Value Mgmt
44/72
OnOn--Line Reporting ofLine Reporting ofCost/Schedule StatusCost/Schedule Status
7/28/2019 Perception Earned Value Mgmt
45/72
Material Cost/Schedule Status
7/28/2019 Perception Earned Value Mgmt
46/72
Combined Labor & MaterialCost/Schedule Status
7/28/2019 Perception Earned Value Mgmt
47/72
Cost/Schedule Performance Indexes
7/28/2019 Perception Earned Value Mgmt
48/72
Cost/Schedule Variance Analysis
7/28/2019 Perception Earned Value Mgmt
49/72
Cost/Schedule Baseline Plan Status
7/28/2019 Perception Earned Value Mgmt
50/72
Tracking Manpower Requirements
As Planned in Baseline
As Currently Planned
As Actually Expended To Date
As Forecast to Complete
Manpower can be evaluated by WBS, by shipyard work
center, for one project or across multiple projects.The analysis can combine current back-log with
proposed new work.
7/28/2019 Perception Earned Value Mgmt
51/72
Tracking Manpower Requirements
(Planned Vs Actual Vs Forecast)
7/28/2019 Perception Earned Value Mgmt
52/72
New Work Manpower Modeled On Top Of
Active Work Manpower
7/28/2019 Perception Earned Value Mgmt
53/72
Measuring Work CenterPerformance
7/28/2019 Perception Earned Value Mgmt
54/72
7/28/2019 Perception Earned Value Mgmt
55/72
7/28/2019 Perception Earned Value Mgmt
56/72
7/28/2019 Perception Earned Value Mgmt
57/72
7/28/2019 Perception Earned Value Mgmt
58/72
7/28/2019 Perception Earned Value Mgmt
59/72
Measuring Estimate AtCompletion (EAC)PERCEPTIONapplies forecasting factor for EAC.
As work orders close, system learns extent of costvariance for these work orders.
EAC = BAC +Factor x [Variance closed w/os
+Adjustments in-progress w/os]
As progress advances,PERCEPTIONplaces greater
emphasis on recorded cost variance for the EAC.
7/28/2019 Perception Earned Value Mgmt
60/72
Measuring Progress
From EAC and ACWP,PERCEPTIONcomputes
actual progress:
Progress = 100 x (ACWP/EAC)
7/28/2019 Perception Earned Value Mgmt
61/72
Measuring Earned Value
From Progress and BAC,PERCEPTIONcomputes
earned value, BCWP:
BCWP = [Progress x BAC]/100
7/28/2019 Perception Earned Value Mgmt
62/72
Measuring Trends
Using regression formulas
and weighting the more
PERCEPTIONtracks cost and schedule performance
week by week or month by month.
Trends provide management with an early indication of how effective
management efforts are keeping performance to budget and planned
schedules.
recent data more heavily
than older data, the system
computes trends at
completion.
7/28/2019 Perception Earned Value Mgmt
63/72
Systems Integration
Desktop
& InternetProducts
7/28/2019 Perception Earned Value Mgmt
64/72
PERCEPTIONhas been linked to various Ship Design and
Engineering systems:
ARLs ShipConstructor
Systems Integration
The NavysASSETShip Concept Model
Proteus EngineeringsFlagship suite
Intergraphs GSCAD
AutodesksAutoCAD general design system
RebisAutoPLANTpiping system design and engineering system
BentleysMicroStation general design system
7/28/2019 Perception Earned Value Mgmt
65/72
CAD interfaces can be used to down-
load detailed bills of material for Cost Estimating
Purchase Requisitions
Work Order Bills of Materials
7/28/2019 Perception Earned Value Mgmt
66/72
ShipConstructor
Cost Planning
Purchasing
Manpower
DrawingControl
MaterialControl
Performance Customer
AccountingSystems
AccountsPayable
AccountsReceivable
3rd Party Software
Estimating Scheduling Control Reporting Billings
Time Charges
PERCEPTION
Integrated Shipyard Resource Management System
7/28/2019 Perception Earned Value Mgmt
67/72
Data Import/Export Features
PERCEPTIONcan import/export data in various
formats: SQL ODBC
, , , ,
Sybase SQL Anywhere Text files (comma, tab delimited & strings)
Windows cut, copy & paste
U.S. EDI Standard X12 (XML) MicrosoftProject
7/28/2019 Perception Earned Value Mgmt
68/72
SPAR Associates, Inc.
A Full Service Company
Systems Sales, Training & Support Independent Cost Estimating
Planning & Scheduling Services
Contract Cost/Schedule Tracking &Performance Analysis
SPAR has provided systems and services to
7/28/2019 Perception Earned Value Mgmt
69/72
SPAR has provided systems and services to
the shipbuilding and ship repair industries
around the world since 1972.
Our clients are both large and small, and theydeal with commercial and/or government
work.
SPAR understands the detail nature of this
business, from the way shipyards organize
and perform their work and manage theirbusiness.
7/28/2019 Perception Earned Value Mgmt
70/72
SPAR has followed and has implemented
features in its systems to support worldclass shipbuilding practices.
These practices enable shipyards to bemuch more efficient and improve the
quality of their products and services.
7/28/2019 Perception Earned Value Mgmt
71/72
Serving Government Agencies Too
The U.S. Coast Guard
The U.S. Navy
The Federal Maritime Administration
(MARAD)These services include software developed
by SPAR, training and system support, as
well as independent cost estimating andcost realism evaluations.
7/28/2019 Perception Earned Value Mgmt
72/72
Over 35 Years Serving the Shipbuilding &Repair Industry