Performance Monitoring Hub System (PMhS) Project - Tenderers’ Frequently Asked Questions And S.P.A.D. Replies Performance Monitoring Hub System (PMhS) Project (RFP No: SPAD/RFP/001/01/2012) Tenderers’ Frequently Asked Questions And S.P.A.D. Replies QUESTION 1 Closing and submission date of tender It was stated in the RFP, that proposals shall be submitted during office hours not later than 1200 hours Malaysian Time, 9th February 2012. In the newspapers (tender advertisement), the closing date was stated on 13th February 2012 before 12 noon. Which is the correct date? ANSWER 1 Regrettably, the closing date as printed in the newspaper was an error. The actual closing and submission date for the proposal is as stated in the RFP document which is 9 February 2012. QUESTION 2 Liquidated Ascertained Damages (LAD) Can we assume that Liquidated Damages will not be applied due to delays beyond control of Contractor and Milestone starts on full agreement of detailed requirements? ANSWER 2 Mechanics of the LAD will be agreed upon signing the Memorandum of Agreement between SPAD and the successful tenderer. SPAD wants to ensure the successful tenderer is fully committed and shall observe the agreed upon work schedule as well as completion of such milestones from the work schedule. QUESTION 3 Withholding tax Please clarify that whether Withholding Tax is applicable to Malaysian Registered Companies.

Performance Monitoring Hub System (PMhS) Project - Tenderers

  • Upload
    ngominh

  • View
    217

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Performance Monitoring Hub System (PMhS) Project - Tenderers

Performance Monitoring Hub System (PMhS) Project - Tenderers’ Frequently Asked Questions And S.P.A.D. Replies

Performance Monitoring Hub System (PMhS) Project (RFP No: SPAD/RFP/001/01/2012)

Tenderers’ Frequently Asked Questions And S.P.A.D. Replies    

 

    QUESTION 1  Closing and submission date of tender  It was stated  in  the RFP,  that proposals shall be submitted during office hours not  later  than 1200 hours Malaysian Time, 9th February 2012.  In  the newspapers  (tender advertisement),  the closing date was stated on 13th February 2012 before 12 noon. Which is the correct date?  ANSWER 1  Regrettably, the closing date as printed in the newspaper was an error.  The actual closing and submission date for the proposal is as stated in the RFP document which is 9 February 2012.       

    QUESTION 2  Liquidated Ascertained Damages (LAD)  Can  we  assume  that  Liquidated  Damages  will  not  be  applied  due  to  delays  beyond  control  of  Contractor  and Milestone starts on full agreement of detailed requirements?ANSWER 2Mechanics of the LAD will be agreed upon signing the Memorandum of Agreement between SPAD and the successful tenderer.  SPAD wants to ensure the successful tenderer is fully committed and shall observe the agreed upon work schedule as well as completion of such milestones from the work schedule.       

   QUESTION 3  Withholding tax  Please clarify that whether Withholding Tax is applicable to Malaysian Registered Companies.  

Page 2: Performance Monitoring Hub System (PMhS) Project - Tenderers

ANSWER 3  Withholding tax will be applicable in accordance with Malaysian tax laws.       

    QUESTION 4  Integrity Pact   In  the RFP document, page 30, both clause 7.2.5 and clause 7.3 requires  the submission of Appendix 3 –  Integrity Pact. Do we have to include the form in both Volume 2 and Volume 3 submission?  ANSWER 4  Yes, "Integrity Pact" will need to be submitted in both Financial Proposal volume and Financial Information volume.       

    QUESTION 5  Appendix 2 Item 11 – Tempoh Pembekalan   Is this item referring information requested in item 9 and 10 of Appendix 2?  ANSWER 5  Yes.       

    QUESTION 6  Appendix 4(i) – Proven Track Record   Proven Track Record has been mentioned  to  be  local  and  regional  installation. We are working with  an European party  who  has  extensive  experience  and  installation  for  the  last  20  year  but  does  not  have  local  and  regional installation. Can their track record from European Installation be considered to meet this requirement?  ANSWER 6  Yes, tenderer may quote experience beyond the stated location.       

  QUESTION 5

Page 3: Performance Monitoring Hub System (PMhS) Project - Tenderers

  Appendix 4(iv)   PM is shall be base in SPAD office. We assume that the facilities shall be provided by SPAD and the tenderers need not to cost for the office space. The same question is also to be clarified for the OPTIONAL requirement for other key personnel.  ANSWER 5  Yes.       

    QUESTION 6   Integration   The integration cost between our proposed system and the existing system owned by SPAD or operators should be included in the price or not?  ANSWER 6  Yes,  however  do  note  that  integration  between  application  software  proposed  by  tenderer  is  not  included  as  the product is expected to be integrated - refer to Appendix 5, Item 1.3.1.3.       

      QUESTION 7   Optional requirement  The integration cost between our proposed system and the existing system owned by SPAD or operators should be included in the price or not?  ANSWER 7  Yes, under separate table for optional pricing, Section 2 Appendices, Schedule C, Table 3.       

    QUESTION 8   Missing items  Referring to the document - PMhS Project Proposal, for Item 5.2 Scope of Work, there are sub-items 5.2.1 to 5.2.7. However, in the document – RFP_PMhS_Appendix5_Technical Compliance, there are only items 5.2.1 to 5.2.4. Thus, should be exclude the missing portion in our price?  

Page 4: Performance Monitoring Hub System (PMhS) Project - Tenderers

ANSWER 8  No, the Appendix 5 are added on requirement to those written in Section 5.2.1 to 5.2.7.  Please refer to Section 7.1.       

      QUESTION 9   Missing items  Referring to the document - PMhS Project Proposal, for Item 5.2 Scope of Work, there are sub-items 5.2.1 to 5.2.7. However, in the document – RFP_PMhS_Appendix5_Technical Compliance, there are only items 5.2.1 to 5.2.4. Thus, should be exclude the missing portion in our price?  ANSWER 9  No, the Appendix 5 are added on requirement to those written in Section 5.2.1 to 5.2.7.  Please refer to Section 7.1.       

    QUESTION 10   5 years operational cost  Schedule D under Section 2 Appendix will not included as part of the pricing under Appendix 1 – Borang Tender? If yes, does the 5 years operation cost need to excluded from the Borang Tender ?  ANSWER 10  Yes.       

    QUESTION 11   Page 54 – Table 4 under Schedule C of Section 2 Appendix  Should  there be a  total  line after  line no. 3 ? As  the column under Price  (%)  , need  to based on which  line  total ? Further, under schedule (month)#, represent what?  ANSWER 11  Please refer to the softcopy Microsoft Excel file - Schedule C, Table 4 for complete table view with additional notes.     

  

Page 5: Performance Monitoring Hub System (PMhS) Project - Tenderers

  QUESTION 12   Page 55 – Table 1 under Schedule C of Section 2 Appendix  Is  this a continuous page from previous page as the number start with 4?  Otherwise, what  is  the different between page 53 and page 55?  ANSWER 12  Please ignore the Table 1 in Page 55 (hardcopy and scanned copy in the CD_black and white version) as it is a scan error.  Please refer to the softcopy Microsoft Excel file - Schedule C, Table 4 for complete table view with additional notes.       

      QUESTION 13   Licenses in Schedule D and Schedule C, Table 2  What is the difference between licenses in Schedule D and that of Schedule C Table 2 where category heading is also license?  ANSWER 13  The licenses in Table 5 refer to annual renewal of licenses with fees. Table 1 refers to license fees to be paid upon procurement and installation of software during project installation.       

    QUESTION 14   Section 2, Schedule D   Is tenderer allowed to change wordings of Description?  ANSWER 14  Yes, although tenderer is highly encouraged to maintain the breakdowns and flow for ease of evaluation.    

- The remainder of this page is intentionally left blank -

  

 

QUESTION 15   Video feed  The video that need to be pulled from LLM TMC and DBKL ITIS to SPAD control

Page 6: Performance Monitoring Hub System (PMhS) Project - Tenderers

centre is in continues real-time video feed or delayed video feed with certain time slot?  ANSWER 15  Video feed to be similar to the view by LLM and DBKL.       

      QUESTION 16   PMhS future expansion: Paragraph 4.2 – page 18  SPAD’s roadmap for  the  future  is  to expand the PMhS from stage bus monitoring  in Greater Kuala Lumpur  / Klang Valley, to other mode of public transportation and other cities/region. In Section 2 Appendices, Schedule C, Table 2, No 4.2.1 – page 54, are we to quote capacity and cost based on 1,000 assets only?  ANSWER 16  Tenders  are  expected  to  quote  procurement  of  OBU  of  1,000  units  for  Greater  KL/Klang  Valley  while  back-end capacity is able to handle greater number of vehicles, refer to Appendix 5, Item 2.3.5.       

    QUESTION 17   Disaster Recovery: Appendix 5, Technical Compliance, No 2.1.4 – page 39  Please clarify whether  the Disaster Recovery  (DR) will mirror  the primary site which consists of only control  centre hardware or mirror the hosting site for all servers?  ANSWER 17  Mirror Primary site's back-end to provide continuous application access especially when the system is web-based.       

    QUESTION 18   Disaster Recovery and communication link: Appendix 5, Technical Compliance, No 2.1.4 – page 39  Whether the communication link between SPAD’s office, Sentral KL / Hosting Facility and Disaster Recovery (DR) to be provided by Tenderer or SPAD?  ANSWER 18  M Optional, refer to Section 2 Appendices, Schedule C, Table 3.    

Page 7: Performance Monitoring Hub System (PMhS) Project - Tenderers

   

    QUESTION 19   Video data: Appendix 5, Technical Compliance, No 2.3.5 – page 40  Please elucidate the video data size as per below:a.   48 hours of video data for 100 CCTVb.   Video data for 1 year in production environmentc.   Video data for 7 years archive  ANSWER 19  Video data will be stored for 48 hours or longer (in terms of hours / days) but not 1 nor 7 years archive.     

    QUESTION 20   CCTV  Please elaborate on item 4.1.6 in Appendix 5 on CCTV. What will be the main function of the CCTV?  ANSWER 20  CCTV for visual monitoring and surveillance around OBU.       

    QUESTION 21   PID power source  Appendix  5,  item  4.3.1.3  stated  the  source  of  power  for  PID will  be  either  from  nearby  TNB,  stops  or  rail.  Kindly elaborate more on this and who will be responsible to communicate with the source and bear the electricity bill.  ANSWER 21  Tenderers  are  expected  to  coordinate  with  property  /  site  owner  for  approvals  and  installation  work.  SPAD  will facilitate where needed.       

  QUESTION 22   Command & Control Center  What is the main function of Command & Control Center, and do we need to propose Call Center for public to call in?

Page 8: Performance Monitoring Hub System (PMhS) Project - Tenderers

  ANSWER 22  CCC is  to be the main control hub for public  transport  tracking, monitoring and  information centralisation.  Tenderer may propose public users Call Centre as optional scope.       

      QUESTION 23   Bandwidth integration  Do we  need  to  establish  connection  from SPAD  to  External  Partner  (eg:  LLM)  for  the  integration? How much  the bandwidth required?  ANSWER 23  Please refer to Section 5.2.5.b, Page 20.       

    QUESTION 24   PID   Please elaborate more on item 1.3.4.1 in Appendix 5 “Ability to display bus information including route, estimated time arrival within 1 minute at designated PID?  ANSWER 24  Information pushed by PIS to contained bus information as stated into individual PID where the information is unique to location of PID.       

    QUESTION 25   GIS   What does  it means by “ability  to modify  timetables  logging”  in  item 1.3.4.7, Appendix 5? Does  it meant  for PID, or GIS?  ANSWER 25  It refers to GIS.      

Page 9: Performance Monitoring Hub System (PMhS) Project - Tenderers

 

  QUESTION 26   Video data or file  Appendix  5,  item  2.3.5  stated  that  all  data will  be  stored  for  1  year  and  archive  for  7  years.  Is  it  for  data  only  or inclusive of video file?  ANSWER 26  Exclude video files.       

  QUESTION 27   Bus arrival medium  In  item  4.3.1.7  Appendix  5,  please  elaborate  on medium  to  be  used  to  announce  bus  arrival.  (eg:  text  display  or audio)?  ANSWER 27  Text display.     

    QUESTION 28   OBU  OBU to be 4G compliance. Do you need the current unit to be 4G enabled during the initial stage of installation, or it can be an added module to OBU once the 4G technology is available?  ANSWER 28  The OBU required being able to support future 4G by minimal change or add-on performed to the device.       

    QUESTION 29   Backup  We would like to clarify in term of backup and recovery. Backup servers will be placed in main production servers site which DR (Recovery) will be place in the site in Putrajaya, what is the expectation of the DR site?  ANSWER 29  

Page 10: Performance Monitoring Hub System (PMhS) Project - Tenderers

Yes, backup will be at Primary site, KL Sentral and DR will be at Putrajaya.       

    QUESTION 30   Bandwidth communication  There is a proposed of 5Mb, who will be using the 5Mb. What about the bandwidth that will be use to communicate with all PIS, OBU, integration parties, end user at different states, is it  included in the 5Mb? What if we find that the bandwidth may not be enough, can we quote higher?  ANSWER 30  5MB connection is expected for use of PMhS only including communication with all PID, OBU and external integration. Yes, you may quote higher bandwidth as required.       

    QUESTION 31   Intrusion detection system  Intrusion detection system, do SPAD have any requirement that it need to be a software based or hardware based?  ANSWER 31  Tenderer may quote the appropriate technology.       

    QUESTION 32   Optional CCTV built in the OBU  CCTV built  in the OBU (optional), will  it only store video in a storage device in the bus or will  it require streaming to CCC?  ANSWER 32  The video file will be stored in bus for offline offloading.     

    QUESTION 33   

Page 11: Performance Monitoring Hub System (PMhS) Project - Tenderers

Optional CCTV built in the OBU  In regard to 1.3.4.7 and 1.3.4.8, it stated (i) ability to modify timetables going (ii) Ability to perform address search on roadmap, can you explain this two features?  ANSWER 33  i) Display  timetable of each route can be changed based on external event  (e.g.  temporary road closure, diversion, flood etc)ii) It refers to GIS.       

  QUESTION 34   MyKad usage  Is  the national  registration  identity  card,  passport  number  for  identification or  registration purposes on  the OBU?  If MyKad is spoiled, how can we proceed?  ANSWER 34  The use of NRIC is for logging in by driver for each trip. Alternative logging will be manual entry e.g. key pad on OBU Appendix 5, Item 4.3.2.1.       

  QUESTION 35   OBU power  The requirement for power on OBU is 12V, what happen if the equipment was built for 24V, will it be an issue, as most of the busses have 24V system?  ANSWER 35  The exact quantity (if any) for voltage that differ from 12V will be identified during start of project with operators.       

    QUESTION 36   Server sizing  The unit must be able to support 1000 OBU connection and moving forward to about 10000 units. My questions is.. in term of server sizing, do you want to have servers that can meet future requirement, or we are looking at adding the server when time comes?    ANSWER 36  

Page 12: Performance Monitoring Hub System (PMhS) Project - Tenderers

The servers able to meet the demand of 10,000 units of OBU, refer to Appendix 5, Item 2.3.5.       

    QUESTION 37   Ability to estimate bus departure time at end station: Clause 1.3.2.4  Please elaborate on expectation of the departure time as typically the departure time is based on the pre-determined bus schedule.  Our solution can determine the delays in reaching to a destination but departure of a bus from a bus stop or a bus station could be subject to other operations (passenger on boarding or getting down from bus, cleaning, maintenance etc.) which has direct impact on the departure time of the bus from the end station?    ANSWER 37  End station refers to the final stop or depot where the scheduled departure time and compare against actual time.       

    QUESTION 38   Ability to notify unusual activities via visual warning or alarm: Clause 1.3.2.5  1)   Please clarify who needs to be notified?2)   What are the activities that can be classified as "unusual" ?3)   Who would determine that an activity is unusual enough to warrant a notification.    ANSWER 38  1. Notification to personnel in CCC.2. Example, bus stops at non-designated stops or mid way longer than usual, signal by driver due to breakdowns.3. The type of events will be defined at the start of project.       

    QUESTION 39   Ability to track, measure and report quality of service: Clause 1.3.2.6  What is the "quality of service"? What is the frequency of the tracking, measurements and reporting?  ANSWER 39  Example of quality of service,  the  frequency, speed profile, on  time (compare against schedule) etc.  The details of tracking, measurement and reporting will be agreed at the start of project.    

Page 13: Performance Monitoring Hub System (PMhS) Project - Tenderers

   

  QUESTION 40   Ability to communicate with drivers: Clause 1.3.2.7  1)   Is this related and limited to voice communication in case of emergencies as there is a driving safety implication due to distraction?2)  Who would initiate this communication?  One way or two way?  ANSWER 40  Tenderer may propose either voice and/or text communication. Communication is generally initiated by driver.         

      QUESTION 41   Ability to store and playback bus operations: Clause 1.3.2.8  1)  Please elaborate on meaning of "Bus Operations".2)  What is the duration for storing the information about the bus operations?3) What is the expectation and purpose of "playback" of the bus operation? Is this same as ability to trace back route of a bus journey to identify if the bus remained on the predefined route or deviated from it?    ANSWER 41  1 & 3.    Using stored bus  information such as coordinates/location,  time, speed etc,  the system  is able  to  recreate (tracing) the movement/operation of bus.2.         Refer to Appendix 5, Item 2.3.5 of the RFP.       

      QUESTION 42   Ability to recall or view bus information during monitoring: Clause 1.3.3.2  What is the meaning of "Bus Information" in context of this clause? What information needs to be displayed?  ANSWER 42  Bus information stored in FMS can be displayed on screen by selecting the bus / route on screen.       

Page 14: Performance Monitoring Hub System (PMhS) Project - Tenderers

    QUESTION 43   Ability to automate data entry (bus information suc as route, driver, schedule, rostering etc): Clause 1.3.3.3  1)  Is it correct to assume that the data for "Bus Information" shall be provided by the respective "Bus Operator" and proposed solution must be able  to  integrate  these  information  in automated manner, without  requiring manual data entry?2)  Is it correct to assume that Bus Operators would have their own fleet management system from which they would provide the "Bus Information" ?  ANSWER 43  1. Yes.2. Not all operators have its own fleet management system.       

  QUESTION 44   Ability to provide zonal, stage, route, hubs and bus stops data such as GPS positioning coordinates etc: Clause 1.3.3.4  1)   Is it correct to assume that "Bus Operator" would provide this data to be integrated in the proposed solution?2)   It is correct to assume that GPS coordinates for bus stops would be provided by the respective Bus Operators?3)    Does data coming from Prasarana FMS include these information?  ANSWER 44  1.  Only bus related services and operator's information by bus operators.2. No, it will be part of tenderers' scope of service. SPAD will facilitate where necessary.3. Yes.       

      QUESTION 45   Ability to perform digital real time synchronization automatically: Clause 1.3.4.4  1) Please elaborate on real time synchronization, what information is to be synchronized?  ANSWER 45  Synchronisation of display time.       

    

Page 15: Performance Monitoring Hub System (PMhS) Project - Tenderers

QUESTION 46   Ability to modify timetables logging: Clause 1.3.4.7  1)  Please elaborate on meaning of "modify time tables logging"?2)  Is this supposed to be a feature of Journey Planner?  ANSWER 46  Display timetable of each route can be changed based on external event (e.g. temporary road closure, diversion, flood etc).         

    QUESTION 47   Ability to perform address search on road map: Clause 1.3.4.8  1)  Is this supposed to be a feature of Journey Planner?  ANSWER 47  This feature is usable by personnel in CCC.       

      QUESTION 48   Primary site from SPAD's office - Sentral, Kuala LumpurDisaster recovery (DR) site from SPAD's other office premise - Menara Usahawan, Putrajaya: Clause 2.1.4  The DR site would be COLD DR (not doing active work) or HOT (doing active work) DR?  ANSWER 48  Tenderer may  propose  either  choice  by  detailing  clearly  how  the  proposed  solution  is  able  to meet  or  exceed  the required performance, Appendix 5, Item 2.3.3.       

    QUESTION 49   Leased line to back-end - 5Mbps: Clause 2.1.9  Please specify the locations between which the leased line is to be set up?  ANSWER 49

Page 16: Performance Monitoring Hub System (PMhS) Project - Tenderers

  Line connection from Primary site to DR site and external systems, DR sites to external systems.       

  QUESTION 50   Tenderers may assume (for sizing) video from external sources to be retained for 48 hours or longer based on first-in-first-out. Assume 100 CCTVs.

All data will be stored for 1 year or longer in production environment and archieve for 7 years

The PMhS is expected to also cater for not just the purchased 1,000 units of OBU and bus information from Prasarana; but also all stage buses and express buses in the country. Hence, sizing of capacity and performance will include these, estimate 10,000.

For other data, estimation will be based on tenderer's recommendation: Clause 2.3.5    QUESTION 50 (cont’d)  1)   Please provide total storage space required for Video data coming from all sources for 24 hours.2)  Is it correct to assume that network connectivity from 100 CCTV to SPAD primary office will be provided?3)   Is  it  correct  to  assume  that  after  48  hours,  video  data  is  not  required  and hence discarded  so  as  to  reuse  the storage space?4)  Per SPAD plans, the coverage for all stage and express buses in country will happen only at Y3 for which date is not specified. Hence why does SPAD want  to  invest  in  infrastructure upfront which will  remain unused  for next  few years?  ANSWER 50  1.  Tenderer is expected to perform its estimation2.  CCTV from external systems will be via leased line3.  Yes.4. Coverage of all stage buses and express buses starting with Greater KL/Klang Valley begins from Y0. Y3 refers to other public transports. Refer to Section 4.2, Fig 1, Page 17.       

    QUESTION 51  Please describe in more detail on “Timetable logging” in 1.3.4.7?  ANSWER 51  Display timetable of each route can be changed based on external event (e.g. temporary road closure, diversion, flood etc)       

    QUESTION 52

Page 17: Performance Monitoring Hub System (PMhS) Project - Tenderers

  Please describe in more detail rostering – 1.3.3.3  ANSWER 52  Rostering refers to assignment of drivers to fleet / route according to schedule.       

    QUESTION 53  For DR recovery site..Menara Usahawan Putrajaya , can proposer build a new connectivity link in to the site or need to integrate with existing current connectivity – 2.1.4  ANSWER 53  Tenderer may propose options for the connectivity.       

    QUESTION 54  Need more detail clarification on the statement ‘leased line to back end 5Mbps’ is an optional requirement – 2.1.9  ANSWER 54  Line connection from Primary site to DR site and external systems, DR sites to external systems.       

    QUESTION 55  What is the main function of Command & Control Center, and do we need to propose Call Center for public to call in?  ANSWER 55  CCC  is  to be  the main control hub  for public  transport  tracking, monitoring and  information centralisation. Tenderer may propose public users Call Centre as optional scope.       

    QUESTION 56  For system testing, does it include load/stress/penetration test?  

Page 18: Performance Monitoring Hub System (PMhS) Project - Tenderers

ANSWER 56  Yes, tenderer is required to demonstrate and proof the system ability to match the expected performance.       

      QUESTION 57  For system testing, does it include load/stress/penetration test?  ANSWER 57  Yes, tenderer is required to demonstrate and proof the system ability to match the expected performance.       

  QUESTION 58  Item 1.3.1.8_Support multi-monitors means:1.       Multi-monitors for each workstation OR2.       Different monitoring capabilities for each workstation  ANSWER 58  The application is able to optimised / leverage on multi-monitors displaying information on each workstation.       

  QUESTION 59  Item  1.3.4.4.  Ability  to  perform  digital  real  time  synchronization  automatically,  Can  you  please  elaborate  on  the meaning of “digital real time synchronization automatically”? Do you mean that all the elements in the system keep the same clock source?  ANSWER 59  Synchronisation of display time.       

      QUESTION 60  Assuming that SPAD has its own PMO, does the Tenderer needs to set up another PMO? Or the Tenderer shall only offer its Project Management service?  

Page 19: Performance Monitoring Hub System (PMhS) Project - Tenderers

ANSWER 60  The PMO is dedicated for PMhS project and liaise with SPAD's project division.       

  QUESTION 61  What is the require display character height for the 3 lines and 5 lines Public Information Display?  ANSWER 61  Tenderer may quote a reasonable size of character that is visible around a stop.       

    QUESTION 62  Do we need to keep spare for the display & OBU? How many spare units that the tenderer need to provide?  ANSWER 62  Spare units will be managed by tenderer to ensure repair and replacement does not affect operations.       

      QUESTION 63  Can we get more  information on  the external systems -  like RapidKL, Prasarana's  fleet management system, LLM, IT  IS and any others  that  the new solution would have to  integrate with. Appreciate  if SPAD can share  the detailed interfaces, protocol and inbound / outbound messages that these applications currently support.  ANSWER 63  Tenderer  is  required  to  estimate  and  provide  reasonable  assumption  to  scope  and  size  the  integration  based  on available information. Specifics will be obtained by tenderer during project where SPAD will facilitate where necessary.       

    QUESTION 64  PMhS will be able to control Prasaranna's PIDs when necessary? Can you provide detailed requirement for this?  ANSWER 64  

Page 20: Performance Monitoring Hub System (PMhS) Project - Tenderers

PMhS will be able to control the content to be displayed on Prasarana's PID.       

     QUESTION 65  What is SPAD's requirement for SLAs on remediating faulty OBUs and PIDs?  ANSWER 65  The SLA will be defined and agreed with tenderer during project before rollout of devices.      

    QUESTION 66  What format will the data be fed into the SPAD system , will it be real time or batch integration?  ANSWER 66  The type of data will need to be more specific. For example, bus location information will be real time.       

    QUESTION 67  Could you please clarify the scope of predictive analysis tool in terms of modelling and data mining requirements?  ANSWER 67  The predictive ability refers to estimation time of arrival at each stops, refer to Appendix 5, Item 1.3.2.3.       

      QUESTION 68  Who will run and staff the Comand and Control Center (CCC)?  ANSWER 68  The CCC will be operated and staffed by personnel from SPAD.  

Page 21: Performance Monitoring Hub System (PMhS) Project - Tenderers

     

      QUESTION 69  The list of external system to be integrated with is not exhaustive. Could you help us in clarify which could be the “cap” in terms of number of interface and typology of integration protocols could be the best?  ANSWER 69  Reference to Section 5.2.5.b.i, Page 20 - the uncertainty in numbers of external system is other operators. At time of writing, 1 other operator have an FMS/FTS.       

      QUESTION 70  What is the expectation of number of buses and bus stops over the next five years?ANSWER 70  Estimated number of buses will be 10,000 and bus stops information is not available.       

    QUESTION 71  For item 1.3.4.6 Ability to provide journey planner accessible via other mediums, i.e. web browsers and smart phones. For smart phones, what platform that SPAD want to enable? (such as IOS, Android, Windows Mobile, Symbian?)  ANSWER 71  It should support major operating system's browsers, i.e. IOS, Android, Windows etc.       

    QUESTION 72  Appendix 5  item 4.1.6 – Could we know number of cameras,  this primary  function and DVR requirements. Are  the cameras of IP or Analogue type.  ANSWER 72  Tenderer  is  required  to  estimate  and  provide  reasonable  assumption  to  scope  and  size  the  integration  based  on available information.

Page 22: Performance Monitoring Hub System (PMhS) Project - Tenderers

       

    QUESTION 73  Appendix 4(iv) – PM is shall be base  in SPAD office. We assume that  the facilities shall be provided by SPAD and the  tenderers  need  not  to  cost  for  the  office  space.  The  same  question  is  also  to  be  clarified  for  the OPTIONAL requirement for other key personnel.  ANSWER 73  Yes.