27

Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

FENOCPerry Nuclear Power Plant

P.O. Box97

_^ 10 Center Road

<~ ±r- m , /-T* ±- ^ Perry, Ohio 44081FirstEnergy Nuclear Operating Company y

David B. Hamilton 440-280-5382

Vice President

February 9, 2018

L-18-032

ATTN: Document Control Desk

U.S. Nuclear Regulatory Commission

Washington, DC 20555-0001

SUBJECT:

Perry Nuclear Power Plant

Docket No. 50-440, License No. NPF-58

Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 17

Enclosed is Revision 27 of the Core Operating Limits Report for the Perry Nuclear

Power Plant (PNPP). This mid-cycle revision is submitted to the Nuclear Regulatory

Commission (NRC) in accordance with PNPP Technical Specification 5.6.5, "Core

Operating Limits Report (COLR)." A summary of the revision begins on page 25 of

the COLR.

There are no regulatory commitments contained in this submittal. If there are any

questions or additional information is required, please contact Mr. Thomas A. Lentz,

Manager - Fleet Licensing, at (330) 315-6810.

Sincerely,

David B. Hamilton

Enclosure:

Core Operating Limits Report for the Perry Nuclear Power Plant Unit 1 Cycle 17

(Reload 16), Revision 27

cc: NRC Region III Administrator

NRC Resident Inspector

NRC Project Manager

Page 2: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

1 of 26

CORE OPERATING LIMITS REPORT FOR THE

PERRY NUCLEAR POWER PLANT UNIT 1

CYCLE 17 (RELOAD 16)

Functional Location (J11)

Plant Data Book

Effective Date: 1-16-18

Preparer: Pat Curran / 12-1-17

Date

Approver: Paul Bordlev / 12-7-17

Date

Page 3: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

2 of 26

1.0

2.0

3.0

3.1

3.2

3.3

4.0

4.1

4.2

4.3

4.4

5.0

5.1

5.2

5.3

5.4

6.0

TABLE OF CONTENTS

INTRODUCTION

REFERENCES

T.S. 3.2.1 -AVERAGE PLANAR LINEAR HEAT GENERATION

RATE (APLHGR)

MAPLHGR LIMITS

FLOW DEPENDENT AND POWER DEPENDENT MAPFAC

FLOW DEPENDENT AND POWER DEPENDENT MAPFAC -

SINGLE LOOP OPERATION

T.S. 3.2.2 - MINIMUM CRITICAL POWER RATIO (MCPR)

OPERATING LIMIT MCPR and MCPR LIMIT ADDER

FLOW DEPENDENT MCPRf

POWER DEPENDENT MCPRp

SINGLE LOOP OPERATION - MCPR LIMITS

T.S. 3.2.3 - LINEAR HEAT GENERATION RATE (LHGR)

LHGR LIMITS

FLOW DEPENDENT LHGRFACf

POWER DEPENDENT LHGRFACd

SINGLE LOOP OPERATION - LHGR LIMITS

T.S. 3.3.1.1 - REACTOR PROTECTION SYSTEM

INSTRUMENTATION

4

4

7

8

8

8

11

11

12

12

14

19

19

20

20

21

25

Page 4: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

3 of 26

8.0

7.0 T.S. 3.3.1.3 - OSCILLATION POWER RANGE MONITOR

(OPRM) INSTRUMENTATION

SCOPE OF REVISION

25

25

Page 5: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

4 of 26

1.0 INTRODUCTION

This Core Operating Limits Report (COLR) for the Perry Nuclear Power

Plant (PNPP) Unit 1 is prepared in accordance with the requirements of

PNPP Technical Specification Administrative Control 5.6.5. The core

operating limits presented herein were determined using NRC-approved

methods (Obligation 1 and Obligation 2). The core operating limits for the

Global Nuclear Fuel (GNF) fuel in PNPP Unit 1 for Cycle 17 are

documented in Obligations 3, 4, 5, 14, 16, 17, and 20 and summarized

herein for the following PNPP Unit 1 Technical Specifications:

1. Average Planar Linear Heat Generation Rate (APLHGR) Limits for

each fuel/lattice type, including the power and flow dependent

MAPFAC multipliers with the single loop MAPLHGR reduction

factor. (Technical Specification 3.2.1)

2. Minimum Critical Power Ratio Limit including the Operating Limit

MCPR along with the power and flow dependent MCPR curves.

(Technical Specification 3.2.2)

An additional power dependent MCPR Limit curve is provided for

operation with one pressure regulator out of service or power load

unbalance out of service.

3. Linear Heat Generation Rate (LHGR) Limits for each fuel/lattice

type, including the power and flow dependent LHGRFAC curves

with the single loop LHGRFAC reduction factor. (Technical

Specification 3.2.3)

An additional power dependent LHGRFAC curve is provided for

operation with power load unbalance out of service.

4. The simulated thermal power time constant. (Technical

Specification 3.3.1.1, SR 3.3.1.1.14)

5. Oscillation Power Range Monitor (OPRM) Instrumentation.

(Technical Specification 3.3.1.3)

Page 6: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

5 of 26

The oscillation power range monitor setpoint methods have been changed

to NEDE-33766P-A, GEH Simplified Stability Solution (GS3). The GS3

methods are a generic approach to establishing the OPRM period - based

detection algorithm setpoints. This generic approach assumes feedwater

temperature reductions are limited to 120°F anytime during the cycle.

Cycle 17 (Reload 16) core design was developed assuming feedwater

temperature reductions of 100°F during the cycle and 170°F beyond the

end of the normal fuel cycle. Plant operations will be limited to 100°F

during the cycle to account for the assumptions of the core design and

120°F beyond the end of the normal fuel cycle to account for the GS3

limitation.

For Cycle 17 (Reload 16) an additional flexibility option, Power Load

Unbalance Out Of Service (PLUOOS), was obtained. Thermal Limits

associated with PLUOOS were incorporated into Section 3 (MAPLHGR),

Section 4 (MCPR), and Section 5 (LHGR).

Calculation FM-075, Support for the Core Operating Limits Report, details

the development of the various graphs contained within this COLR.

2.0 REFERENCES

2.1 Discretionary

None

2.2 Obligations

1. General Electric Standard Application for Reactor Fuel,

NEDE-24011-P-A-23, September 2016; and the US Supplement,

NEDE-24011-P-A-23-US, September 2016

2. Reactor Stability Detect and Suppress Solutions Licensing Basis

Methodology for Reload Applications, Licensing Topical Report,

NEDO-32465-A, August 1996

3. Supplemental Reload Licensing Report for Perry 1 Reload 16 Cycle

17, GNF Document 002N6979, Revision 0, December 2016

Page 7: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

6 of 26

4. Fuel Bundle Information Report for Perry 1 Reload 16 Cycle 17,

GNF Document 002N6980, Revision 0, December 2016

5. Calculation FM-012, OPRM Device Settings and Setpoints,

Revision 5

6. Technical Specification 2.1.1.2, Safety Limit MCPR, Amendment

No. 165

7. Technical Specification 3.2.1, Average Planar Linear Heat

Generation Rate, Amendment No. 112

8. Technical Specification 3.2.2, Minimum Critical Power Ratio,

Amendment No. 112

9. Technical Specification 3.2.3, Linear Heat Generation Rate,

Amendment No. 112

10. Technical Specification 3.3.1.1, Reactor Protection System

Instrumentation (SR 3.3.1.1.14), Amendment No. 115

11. Technical Specification 3.3.1.3, OPRM Instrumentation

(SR 3.3.1.3.3), Amendment 138

12. Technical Specification 5.6.5, Core Operating Limits Report,

Amendment No. 136

13. Neutron Monitoring System Design Specification, 22A3739,

Revision 6

14. Calculation FM-075, Support for the Core Operating Limits Report,

Revision 5

15. FTI-B0012, Single Loop Operation

16. Tables D-2 (UO2) and D-4 (U,GdO2) of GE14 Compliance with

Amendment 22 of NEDE-24011-P-A, (GESTAR II), NEDC-32868P,

Revision 6, March 2016, MFN 16-015, March 24, 2016.

17. Tables B-1 (UO2) and B-2 (U,GdO2) of GNF2 Advantage Generic

Compliance with NEDE-24011-P-A, (GESTAR II), NEDC-33270P,

Revision 7, October 2016, MFN 16-073, October 12, 2016.

Page 8: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

7 of 26

18. Condition Report 2015-06018 - Use of GNF Provided Proprietary

Information

19. NEDE-33766P-A, Revision 1 March 2015, GEH Simplified Stability

Solution (GS3)

20. 004N3562-R0, Perry Cycle 17 Power Load Unbalance (PLU) OOS

Analysis

21. Condition Report 2017-08501, Core Operating Limits Report - Single

Loop Power Dependent MCPRp Calculation Is Conservative

Commitments addressed in this document:

None

3.0 T.S. 3.2.1 -AVERAGE PLANAR LINEAR HEAT GENERATION RATE

(APLHR)

All Average Planar Linear Heat Generation Rates (APLHGRs) shall be less

than or equal to the result obtained from multiplying the applicable

MAPLHGR limit by the smaller of either the flow dependent APLHGR factor

(MAPFACt) or the power dependent APLHGR factor (MAPFACp).

MAXIMUM APLHGR LIMIT = MAPLHGR LIMIT * smaller (MAPFACf

or MAPFACp)

MAPLHGR Limits and MAPFACf and MAPFACp are defined in

Obligation 3.

Page 9: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

8 of 26

3.1 MAPLHGR LIMIT

Maximum Average Planar Linear Heat Generation Rates (MAPLHGRs)

Limits for the GE14 and GNF2 fuel types are depicted in the following

figures:

Figure 3.2.1-1 a MAPLHGR Versus Average Planar Exposure

Fuel Type: GE14

Figure 3.2.1-1b MAPLHGR Versus Average Planar Exposure

Fuel Type: GNF2

The MAPLHGR Limits are independent of the selected Flexibility Option

(Equipment In Service, Pressure Regulator Out Of Service, and Power

Load Unbalance Out Of Service).

3.2 FLOW DEPENDENT AND POWER DEPENDENT MAPFAC

The Flow Dependent MAPLHGR Factor (MAPFACf) and the Power

Dependent APLHGR Factor (MAPFACp) are set equal to 1.0.

3.3 FLOW DEPENDENT AND POWER DEPENDENT MAPFAC - SINGLE

LOOP OPERATION

For Single Loop Operation, the Flow Dependent MAPLHGR Factor

(MAPFACf) and Power Dependent APLHGR Factor (MAPFACp) are set

equal to 0.8.

The Single Loop Operation limits take effect when reset for single loop

operation per LCO 3.4.1,"Recirculation Loops Operating". This is

consistent with note "(b)" to Table 3.3.1.1-1 of the Technical Specifications.

The 3DMONICORE Computer software will automatically shift between 2

LOOP ON and ONE LOOP ON modes of operation on transfer to Single

Loop Operation. The change in MAPFACf and MAPFACp will occur

automatically. Guidance in FTI-B0012 can be used to verify proper

functioning of the 3DMONICORE System. If the 3DMONICORE System is

not functioning properly, FTI-B0012 will implement administrative limits until

3DMONICORE is properly calculating MAPLHGR Limits.

Page 10: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

9 of 26

Figure 3.2.1 -1a

MAPLHGR Versus Average Planar Exposure

Fuel Type: GE14

16

14

12

U. 10

I

^ 8

o

O 6UJ

PERMISSIBLE

REGION OF

OPERATION

—GE14 ECCS MAPLHGR Liml

N

\r

MAPLHGR = 12.82 for Exposures <= 19.13

MAPLHGR ~ 12.82 + (-0.12526) * (Exposure -19.13)

for 19.13 < Exposures <= 57.61

MAPLHGR = 8.00 + (-0.50934) * (Exposure - 57.61)

for 57.61 < Exposures <= 63.50

10 15 20 25 30 35 40 45 50 55 60 65 70

Average Planar Exposure (GWD/ST)

Page 11: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

10 of 26

Figure 3.2.1-1b

MAPLHGR Versus Average Planar Exposure

Fuel Type: GNF2

16

14

12

£ 10

(DI 8

CO

PERMJSSII

REGION (

OPERATH

s

JLE

)F

OH

\

\\N

—GNF2 ECCS MAPLHGR LJMI7

\\

\\

MAPLHGR = 13.78 for Exposures <= 17.15

MAPLHGR " 13.78 + (-0.15838) * (Exposure -17.15)

for 17.15 < Exposures <= 60.78

MAPLHGR = 6.87 + (-0.50368) * (Exposure - 60.78)

for 60.78 < Exposures <= 63.50

\

5 10 15 20 25 30 35 40 45 50 55 60 65 70

Average Planar Exposure (GWD/ST)

Page 12: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

11 of 26

4.0 T.S. 3.2.2 - MINIMUM CRITICAL POWER RATIO (MCPR)

All Minimum Critical Power Ratios (MCPRs) shall be greater than or equal

to the MCPR Limit. The MCPR Limit is equal to the higher of the Operating

Limit MCPR, the Flow Dependent MCPR (MCPRf), and the Power

Dependent MCPR (MCPRp) plus the MCPR Limit Adder.

MCPR Limit = maximum (Operating Limit MCPR, MCPRf, MCPRp) +

MCPR Limit Adder

Operating Limit MCPR along with MCPRf, MCPRp, and MCPR Limit Adder

are defined in Obligations 3 and Obligation 20.

4.1 OPERATING LIMIT MCPR and MCPR LIMIT ADDER

For Cycle 17, the Operating Limit MCPR is a function of the fuel type and

exposure. Middle of Cycle (MOC) exposure point is defined as End of

Rated (EOR) exposure point minus the Cycle Delta Exposure. For Cycle

17, the EOR exposure is defined in the Cycle 17 Cycle Management

Report. For Cycle 17, the Cycle Delta Exposure is set to 2832 MWd/ST.

Thus, MOC is equal to EOR - 2832 MWd/ST.

The End of Rated (EOR) is defined as the cycle exposure corresponding to

all rods out, 100% power/100% flow, and normal feedwatertemperature.

As such, the EOR is a projection based on various assumptions such as

how the previous cycle operated, current cycle operations, core loading

changes during the refueling outage, inoperable control rods, suppressed

fuel defects, etc. The projected EOR exposure point may have to be

updated during the cycle to ensure the appropriate MCPR limits applied.

The changes in the EOR value are documented in supplements or

revisions to the Cycle Management Report.

The Operating Limit MCPR is additionally defined by the selected Flexibility

Option:

Equipment In Service (EIS)

Pressure Regulator Out Of Service (PROOS)

Power Load Unbalance Out of Service (PLUOOS)

Page 13: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

12 of 26

4.2

4.3

Cycle 17 Operating Limit MCPR is defined as:

Operating Limit

MCPR

BOC to < MOC

>/= MOC to EOC

GE14

EIS/PROOS

1.32

1.35

GEM

PLUOOS

1.40

1.41

GNF2

EIS/PROOS

/PLUOOS

1.34

1.40

For Cycle 17, the MCPR Limit Adder is equal to 0.00.

For Cycle 17, no change to MCPR limits is required for planned reduction

of feedwater temperature to as low as 325.5°F. Final feedwater

temperature may be reduced to 305.5°F after all control rods are withdrawn

at the end of cycle if the OPRMs are OPERABLE.

The 3DMONICORE Computer software will automatically shift the

Operating Limit MCPR based on the MOC exposure point.

FLOW DEPENDENT MCPRf

The Flow Dependent MCPR Limit (MCPRf) is independent of fuel type,

exposure, and the selected Flexibility Option (Equipment In Service,

Pressure Regulator Out Of Service, and Power Load Unbalance Out Of

Service).

The Flow Dependent MCPR Limit is depicted in the following figure:

Figure 3.2.2-1, Flow Dependent MCPR Limit (MCPRf)

Fuel Type: GE14/GNF2

POWER DEPENDENT MCPRd

The Power Dependent MCPR Limit (MCPRp) is independent of the fuel

type and exposure but is dependent on the Flexibility Option selected.

MCPRp figures are provided for Equipment In Service (EIS) and Pressure

Regulator Out Of Service / Power Load Unbalance Out Of Service.

When operating below 38% RTP, MCPRp is independent of fuel type,

exposure, and flexibility option.

Page 14: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

13 of 26

When equal to or above 38% RTP, the power dependent MCPRp is

dependent on the fuel type, exposure, flexibility option, and the variable KP.

MCPRp = KP * Operating Limit MCPR (fuel type, exposure,

flexibility option)

The Power Dependent MCPR Limit is depicted in the following figures:

Figure 3.2.2-2 Power Dependent MCPR Limit (MCPRp)

Equipment in Service

Fuel Type: GE14/GNF2

Figure 3.2.2-3 Power Dependent MCPR Limit (MCPRp)

Pressure Regulator Out of Service

Power Load Unbalance Out Of Service

Fuel Type: GE14/GNF2

The 3DMONICORE Software will not automatically shift to the Pressure

Regulator Out of Service Thermal Limits. The 3DMONICORE databank

will be manually changed using a software change request. Until the

3DMONICORE databank is updated for the Pressure Regulator Out of

Service Thermal Limits, an MFLCPR Administrative Limit will be issued to

Operations. Figure 3.2.2-4 can be used as a guide in establishing the

MFLCPR Administrative Limit. The graph is the ratio of MCPRp -

Equipment In Service to MCPRp - Pressure Regulator Out Of Service.

Figure 3.2.2-4 Maximum Fraction Limiting Critical Power Ratio

Limit (MFLCPR)

Pressure Regulator Out Of Service

The 3DMONICORE Software will not automatically shift to the Power Load

Unbalance Out of Service Thermal Limits. The 3DM0NIC0RE databank

will be manually changed using a software change request. Until the

3DMONICORE databank is updated for the Power Load Unbalance Out of

Service Thermal Limits, Reactor Engineering will review 3DM Periodic

Logs and ratio the calculated MFLCPR's accounting for the change in

Operating Limit MCPR.

Page 15: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

14 of 26

4.4 SINGLE LOOP OPERATION - MCPR LIMITS

The MCPR Safety Limit for Two Loop Operations is 1.10 and the MCPR

Safety Limit for Single Loop Operation is 1.13 <TECHNICAL

SPECIFICATIONS 2.1.1.2>. The Safety Limit Delta CPR is equal to 0.03.

As identified in the Cycle 17 Supplemental Reload Licensing Report -

Section 11 Non-Pressurization Events Table, the minimum OL-MCPR for

Rated Equivalent Single Loop Operating Pump Seizure Event is 1.38 for

the GNF2 Fuel Type. This results in a delta CPR of 0.04 over the GNF2

Two Loop Operating Limit and is greater than the Safety Limit Delta CPR of

0.03.

To simply the Cycle 17 3DMONICORE Databank Installation, MCPR Limit

Adder (Single Loop Operation) is set equal to 0.04 for all fuel types and all

exposures to bound both the Safety Limit Delta CPR and the results the

single loop pump seizure analysis.

Planned reduction of rated feedwater temperature from nominal rated

feedwater temperature is not permitted during plant operation with the

reactor recirculation system in Single Loop Operation.

The Single Loop Operation limits take effect when reset for single loop

operation per LCO 3.4.1/'Recirculation Loops Operating". This is

consistent with note "(b)" to Table 3.3.1.1-1 of the Technical Specifications.

The 3DMONICORE Computer software will automatically shift between 2

LOOP ON and ONE LOOP ON modes of operation on transfer to Single

Loop Operation. The change in the MCPR Limit Adder will occur

automatically. The guidance in FTI-B0012 can be used to verify proper

functioning of the 3DMONICORE System. If the 3DMONICORE System is

not functioning properly, FTI-B0012 will implement administrative limits until

3DMONICORE is properly calculating MCPR values.

Page 16: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

15 of 26

Figure 3.2.2-1

Flow Dependent MCPR Limit (MCPRf)

Fuel Type: GE14/GNF2

1.8

1.7

1<5Q.

OQ.OO

I"dtQ.

O

1.4

1.3

\2

_V

MCPRf = MAX [1.30,

1.65 0.00714 {F 30.0)]

PERMISSIBLE

REGION OFOPERATION

MCPRf clamped at 1.30

20 40 60 80

CORE FLOW (% RATED)

100 120

Page 17: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

16 of 26

Figure 3.2.2-2

Power Dependent MCPR Limit (MCPRP)

Equipment In Service

Fuel Type: GE14/GNF2

2.4

2j00

2.2

2.1

2.0

1.9

1.8

PERMISSIBLE

REGION OF

OPERATION

MCPRp = 2.61 - 0.02817 (P - 23.8)

For 23.8% <= P < 38%; Core Flow > 50%

MCPRp = 2.41 - 0.02042 (P- 23.8)

For 23.8% <= P < 38%; Core Flow <= 50%

£40

&a.

o

S

220

1.6

1.5

1.4

Q.

1.3

1.2

1.1

1.0

Core Flow<= 105%Kp = 1.576-0.00975 <P-38) 38%<=P<=50%

Kp = 1.190-0.00320 <P-50) 50%<P<=60%

Kp = 1.158-0.00328 <P-60) 60%<P<=66.7%

Kp = 1.115 - 0.00251 (P -66.7) 66.7% < P <= 85%

Kp = 1.069-0.00460 <P 85) 85%<P<=100%

iMCPRp = Kp * OL-MCPR

OL - MCPR GE14 GNF2BOCto<MOC 1.32 1.34

>/=MOCtoEOC 1.35 1.40

0.9

2.00

120

0.00 20.00 40.00 60.00 80.00

CORE THERMAL POWER {% RATED)

100.00

Page 18: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

17 of 26

Figure 3.2.2-3

Power Dependent MCPR Limit (MCPRP)

Pressure Regulator Out Of Service

Power Load Unbalance Out Of Service

Fuel Type: GE14/GNF2

2.4

2.3

2.2

2.1

2.0

PERMISSIBLE

REGION OF

OPERATION

MCPRp - 2.61 - 0.02817 (P - 23.8)

For 23.8% <= P < 38%; Core Flow > 50%

MCPRp = 2.41 - 0.02042 (P- 23.8)

For 23.8% <= P < 38%; Core Flow <= 50%

Core Flow <= 105%

Kp=1.576 0.00831 {P 38) 38* <= P <= BO.0%

Kp = 1.100-Oj00500(P-80) 80%< P<= 100%

MCPRp = Kp * OL-MCPR

OL-MCPR GEM GE14 GNF2

(PROOS) (PLUOOS)

BOCto<MOC 1.32 1.40 1.34

>/=MOCtoEOC 1.35 1.41 1.401.0

0.9

0.00 20.00 40.00 60.00 80.00

CORE THERMAL POWER (% RATED)

100.00

Page 19: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

18 of 26

Figure 3.2.2-4

Maximum Fraction Limiting Critical Power Ratio Limit (MFLCPR)

Pressure Regulator Out Of Service

Fuel Type GE14/GNF2

in

oo

Ql

OLL

1.000

0.975

0.950

0.925

0.900

Q_

O

LL 0.875

0.850

0.825

0.800

(23.8, 1.000) _|(38, 1.000) L (100, 1.000)

20253035404550556065 70 75 80859095 100

CORE THERMAL POWER {% RATED)

Page 20: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

19 of 26

5.0 T.S. 3.2.3 - LINEAR HEAT GENERATION RATE (LHGR)

All Linear Heat Generation Rates (LHGRs) shall be less than or equal to

the result obtained from multiplying the applicable LHGR limit by the

smaller of either the flow dependent LHGR factor (LHGRFACf) or the

power dependent LHGR factor (LHGRFACp).

MAXIMUM LHGR LIMIT = LHGR LIMIT * smaller (LHGRFACf or

LHGRFACp)

LHGR Limits and LHGRFACf and LHGRFACp are defined in Obligations 3,

4, 16, 17, and 20.

5.1 LHGR LIMIT

Linear Heat Generation Rates (LHGRs) Limits for the GE14 Uranium only

fuel pins and Gadolinia bearing fuel pins are listed in:

Tables D-2 (UO2) and D-4 (U,GdO2) of "GE14 Compliance with

Amendment 22 of NEDE-24011-P-A, (GESTAR II), NEDC-32868P",

Revision 6, March 2016.

Linear Heat Generation Rates (LHGRs) Limits for the GNF2 Uranium only

fuel pins and Gadolinia bearing fuel pins are listed in:

Tables B-1 (UO2) and B-2 (U,GdO2) of "GNF2 Advantage Generic

Compliance with NEDE-24011-P-A, (GESTAR II), NEDC-33270P",

Revision 7, October 2016.

For both GE14 and GNF2 Gadolinia bearing fuel pins, the maximum

Gadolinia content of a fuel pin is 7 wt-% Gd2O3.

The LHGR Limits are independent of the selected Flexibility Option

(Equipment In Service, Pressure Regulator Out Of Service, and Power

Load Unbalance Out Of Service).

Page 21: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

20 of 26

5.2 FLOW DEPENDENT LHGRFACf

The Flow Dependent LHGR Factor (LHGRFACf) is independent of fuel

type, exposure, and the selected Flexibility Option (Equipment In Service,

Pressure Regulator Out Of Service, and Power Load Unbalance Out Of

Service).

The Flow Dependent LHGRFACf is depicted in the following figure:

Figure 3.2.3-1 Flow Dependent LHGR Factor (LHGRFACf)

Fuel Type: GE14/GNF2

5.3 POWER DEPENDENT LHGRFACo

The Power Dependent LHGR Factor (LHGRFACp) is independent of fuel

type and exposure but dependent on the selected Flexibility Option

(Equipment In Service, Pressure Regulator Out Of Service, and Power

Load Unbalance Out Of Service).

An LHGRFACp curve is provided for Equipment In Service / Pressure

Regulator Out of Service and an LHGRFACp curve is provided for Power

Load Unbalance Out Of Service.

The Power Dependent LHGRFACp are depicted in the following figures:

Figure 3.2.3-2 Power Dependent LHGR Factor (LHGRFACp)

Equipment In Service

Pressure Regulator Out Of Service

Fuel Type: GE14/GNF2

Figure 3.2.3-3 Power Dependent LHGR Factor (LHGRFACp)

Power Load Unbalance Out Of Service

Fuel Type: GE14/GNF2

The 3DMONICORE Software will not automatically shift to the Power Load

Unbalance Out of Service Thermal Limits. The 3DMONICORE databank

will be manually changed using a software change request. Until the

3DMONICORE databank is updated for the Power Load Unbalance Out of

Service Thermal Limits, Reactor Engineering will review 3DM Periodic

Logs and ratio the calculated MFLPD's accounting for the change in

LHGRFACp.

Page 22: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

21 of 26

5.4 SINGLE LOOP OPERATION - LHGR LIMITS

For Single Loop Operation, LHGRFACf and LHGRFACp shall not exceed

0.8.

The Single Loop Operation limits take effect when reset for single loop

operation per LCO 3.4.1,"Recirculation Loops Operating". This is

consistent with note "(b)" to Table 3.3.1.1-1 of the Technical Specifications.

The 3DMONICORE Computer software will automatically shift between 2

LOOP ON and ONE LOOP ON modes of operation on transfer to Single

Loop Operation. The change in LHGRFACf and LHGRFACp will occur

automatically. Guidance in FTI-B0012 can be used to verily proper

functioning of the 3DMONICORE System. If the 3DMONICORE System is

not functioning properly, FTI-B0012 will implement administrative limits until

3DMONICORE is properly calculating LHGR Limits.

Page 23: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

22 of 26

Figure 3.2.3-1

Flow DependentLHGR Factor (LHGRFACf)

Fuel Type: GE14/GNF2

1.1

1.0

0.9

i0.8

0.7

0.6

0.5

— -—

y

i

i

Clamped at 0.80 IDuring SLO |

LHGRFAQ

= 0.544 - 0.00310 (F 30) => 30% and < 40% flow

= 0.575 + 0.02020 (F - 40) => 40% and < 50% flow

= 0.777 * 0.00850 (F 50) => 50% and < 60% flow

= 0.862 + 0.00680 (F - 60) => 60% and < 80% flow

= 0.998 * 0.00667 (F - 80) => 80% and < 80.3% flow

= 1.0 => 80.3% and <= 107% flow

20 40 60 80

CORE FLOW (% RATED)

100 120

Page 24: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

23 of 26

Figure 3.2.3-2

Power Dependent LHGR Factor (LHGRFACP)

Equipment In Service

Pressure Regulator Out Of Service

Fuel Type: GE14 / GNF2

0.604 + 0.00507 (P- 23.8) =>23.8% and <38% power

0.676 + 0.00408 (P - 38) =>38% and <S0% power

0.725 + 0.00550 (P- 50) =>50% and <100% power

38%<= P<=100%; Core Flow<=105%

23.8%<=P<38%; Core Flow <=50%

Clamped at

0.80 During SLO

LHGRFACp= 0.57 +0.00211 (P-23.8)

23.8%<=P<38%; Core Flow >50%

0.5

20 40 60 80

CORE THERMAL POWER {% RATED)

Page 25: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

24 of 26

Figure 3.2.3-3

Power Dependent LHGR Factor (LHGRFACP)

Power Load Unbalance Out Of Service

Fuel Type: GE14/GNF2

i.i

1.0. -

0.9 -

a

LL. 0.8 i -

I

0.5

LHGRFACp

0.604 + 0.00507 (P- 23.8) =>23.8% and <3S% power

: 0.676 + 0.00408 (P - 38) =>38% and <50% power

: 0.72S + 0.00130 [P - 50) =>50% and <80% power

: 0.764 + 0.01180 (P- 80) =>80% and <=100% power

38%<= P<=100%; Core Flow <=105%

23.8%<=P<38%; Core Flow <=50%

0.7 . —-

7Clamped at

0.80 During SLO

0.57 +0.00211 (P-23.8)

23.8%<=P<38%; Core Flow >50%

20 40 60

CORE THERMAL POWER {% RATED)

80 100

Page 26: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

25 of 26

6.0 T.S. 3.3.1.1 - REACTOR PROTECTION SYSTEM INSTRUMENTATION

The simulated thermal power time constant shall be 6 +/-0.6 seconds

(Obligation 13).

7.0 T.S. 3.3.1.3 - OSCILLATION POWER RANGE MONITOR (OPRM)

INSTRUMENTATION

OPRM setpoints for operable OPRMs:

1. Confirmation Count Setpoint (NP = N2): 16

2. Amplitude Setpoint (Sp): 1.15

(Obligation 3)

8.0 SCOPE OF REVISION

Rev. 27 Middle of Cycle 17 Update - clarify Single Loop Limits and to provide

Thermal Limits for when the Power Load Unbalance is Out Of Service:

1 Obligations List, updated revision level of Calculation FM-75 from 4 to

5 and added Obligation 20 (GEH PLUOOS Analysis) and Obligation

21 (Condition Report 2017-08501 - Core Operating Limits Report -

Single Loop Power Dependent MCPRp Calculation Is Conservative).

2 CR 2017-08501:

a. Sections 3, 4, and 5, reorganized and added subsections to

better identify the associated limit and its multipliers. Added an

equation to each section to show the relationship between the

limit and its multipliers.

b. Sections 4, clarified on how MCPR Limits for Single Loop

Operation are calculated.

c. Section 4, added the term "MCPR Limit Adder". This matches

GNF Methods and 3DMONICORE software. The MCPR Limit

Adder is set equal to 0.00. For Single Loop Operation, MCPR

Limit Adder is set to 0.04. The values do not change - the

variable now has a label. Additional discussion was provided

in Section 4.4 to clarify how the 0.04 value was selected.

d. Deleted Single Loop Figures 3.2.2-2, 3.2.2-4, and 3.2.2-6 as

the figures provided no new information.

Page 27: Perry Nuclear Power Plant, Unit 1 - Mid-Cycle Revision to ... · Plant Data Book Effective Date: 1-16-18 Preparer: PatCurran / 12-1-17 Date Approver: Paul Bordlev / 12-7-17 ... Neutron

PERRY NUCLEAR POWER PLANT

Title:

Core Operating Limits Report for the Perry Nuclear

Power Plant Unit 1 Cycle 17 (Reload 16)

Procedure Number:

PDB-F0001Use Category:

In-Field Reference

Revision:

27

Page:

26 of 26

e. Renumbered and updated figure titles as appropriate - Rev

bars not included.

f. Figures 3.2.2-1 and 3.2.2-2, removed from "Two Loop

Operation" from the title - Rev bars not included.

3 Sections 3, 4, and 5, updated sections to incorporate Thermal Limits

associated with the Power Load Unbalance Out Of Service

(PLUOOS) Analysis.

a. Section 3, identified that MPHLGR Limits are independent of

PLUOOS.

b. Section 4, updated the Operating Limit MCPR for GE14 with

PLUOOS.

c. Section 4, identified that PROOS Limits are to be used with

PLUOOS.

d. Figure 3.2.2-3, added "PLUOOS" to the title and updated the

OL-MCPR for GEM (PLUOOS).

e. Section 5, added discussion that LHGRFACp is dependent on

the flexibility option selected - LHGRFACp (EIS/PROOS) and

LHGRFACp (PLUOOS).

f. Figure 3.2.3-2, added "EIS and PROOS" to the title.

g. Added Figure 3.2.3-3 LHGRFACp (GE14 / GNF2 PLUOOS).