3
1/ 27/15 PERT Estimation Technique w w w. tut ori al spoi nt .com/cgi -bin/pri ntpage.cgi 1/ 3 http://www .tutorialspoint.com/m anagem ent_co ncepts /pert_estimation_technique.htm Copy rig ht © tu torialspoint.co PERT ESTIMATION TECHNIQUE Introduction Before any activ ity begins relat ed to the work of a project, ev ery project requires an advanced, accurate ti estimate. Without an accurate estimate, no project can be completed within the budget and the target completion date. Developing an estimate is a complex task. If the project is large and has many stakeholders, things can be more complex. T herefore, there have been man y init iatives to c ome up with d ifferent techniques for estimati on phase of th project in order to make the estimation more accurate. PERT is one of the successful and proven methods amon g the many other techniques, such as, CPM, Function Point Counting, Top-Down Estimating, WAVE, etc. PERT was i nitially cre ated by the US Nav y in the late 1950s. T he pilot project was for developing Bal listi c Miss iles and there have been thousa nds of c ontractors involv ed.  Af ter PERT methodology was employ ed for this projec t, it actually ended two year s ahead of its initial schedule. Th e PERT Basics  At the co re, PERT is all about man agement probabilities. The refo re, PERT invo lv es in many simple statistical methods as well. Sometimes, people categorize and put PERT and CPM together . Although CPM shares some characteristi cs with PERT, PERT has a di fferent fo cus. Same as most of other estimation techniques, PERT also breaks down the tasks into detailed activities. Then, a Gantt chart will be prepared illustrating the interdependencies among the activities. Then, a networ of ac tiv ities and their interdependencies are drawn in an illustrative manner. In this map, a node represents each event. T he activities are represented as a rrows and th ey are drawn from one e  v ent to another, based on the sequence. Next, the Earli est T ime and the Latest T ime are figured for each activity and iden tify the slack time for each activity.  When it comes to deriv ing th e estimates, the PERT model take s a statistical route to do that. We will cov er more on this in the next two sections.  

PERT Estimation Technique

Embed Size (px)

Citation preview

Page 1: PERT Estimation Technique

12715 PERT Estimation Technique

wwwtutorialspointcomcgi-binprintpagecgi 13

httpwww tut orialspointcomm anagem ent_conceptspert_estima tion_techniquehtm

Copy rig ht copy tu torialspointco

PERT ESTIMATION TECHNIQUE

Introduction

Before any activ ity begins related to the work of a project ev ery project requires an advanced accurate tiestimate Without an accurate estimate no project can be completed within the budget and the targetcompletion date

Developing an estimate is a complex task If the project is large and has many stakeholders things can bemore complex

Therefore there have been many initiatives to come up with different techniques for estimation phase of thproject in order to make the estimation more accurate

PERT is one of the successful and proven methods among themany other techniques such as CPM Function Point Counting Top-Down Estimating WAVE etc

PERT was initially created by the US Navy in the late 1950s T he pilot project was for developing BallisticMissiles and there have been thousands of contractors involv ed

After PERT methodology was employed for this project it actually ended two years ahead of its initialschedule

The PERT Basics

At the core PERT is all about management probabilities Therefore PERT involves in many simplestatistical methods as well

Sometimes people categorize and put PERT and CPM together Although CPM sharessome characteristics with PERT PERT has a different focus

Same as most of other estimation techniques PERT also breaks down the tasks into detailed activities

Then a Gantt chart will be prepared illustrating the interdependencies among the activities Then a networ

of activities and their interdependencies are drawn in an illustrative manner

In this map a node represents each event T he activities are represented as arrows and they are drawn fromone e vent to another based on the sequence

Next the Earliest Time and the Latest Time are figured for each activity and identify the slack timefor each activity

When it comes to deriving the estimates the PERT model takes a statistical route to do that We will covermore on this in the next two sections

P 983154 983151 983143 983154 a 983149 E 983158 a 983148 983157 a 983156 983145 983151 983150 a 983150 983140 R 983141 983158 983145 983141 983159 T 983141 c 983144 983150 983145 983153 983157 983141

C 983154 983145 983156 983145 c a 983148 P a 983156 983144 M 983141 983156 983144 983151 983140

T E T L

12715 PERT Estimation Technique

wwwtutorialspointcomcgi-binprintpagecgi 23

The Three Chances

There are three estimation times involved in PERT Optimistic Time Estimate Most Likely TimeEstimate and Pessimistic Time Estimate

In PERT these three estimate times are derived for each activity This way a range of time is given for eacactivity with the most probable value TLIKELY

Following are further details on each estimate

1 TOPT

This is the fastest time an activity can be completed For this the assumption is made that all the necessary resources are available and all predecessor activities are completed as planned

2 TLIKELY

Most of the times project managers are asked only to submit one estimate In that case this is the estimatethat goes to the upper management

3 TPESS

This is the maximum time required to complete an activity In this case it is assumed that many things go wrong related to the activity A lot of rework and resource unavailability are assumed when this estimation iderived

The PERT Mathematics

BETA probability distribution is what works behind PERT The expected completion time is calculated a below

E = (TOPT + 4 x TLIEKLY + TPESS) 6

T O P T

T L I K E L Y T P E S S

E

12715 PERT Estimation Technique

wwwtutorialspointcomcgi-binprintpagecgi 33

For every activity in the critical path E and V are calculated

Then the total of all Es are taken This is the overall expected completion time for the project

Now the corresponding V is added to each activity of the critical path This is the variance for theentire project This is done only for the activities in the critical path as only the critical path activitiescan accelerate or delay the project duration

Then standard deviation of the project is calculated T his equals to the square root of the v ariance

Now the normal probability distribution is used for calculating the project completion time with thedesired probability

Conclusion

The best thing about PERT is its ability to integrate the uncertainty in project times estimations into itsmethodology

It also makes use of many assumption that can accelerate or delay the project progress Using PERT projecmanagers can have an idea of the possible time variation for the deliveries and offer delivery dates to theclient in a safer manner

V

Page 2: PERT Estimation Technique

12715 PERT Estimation Technique

wwwtutorialspointcomcgi-binprintpagecgi 23

The Three Chances

There are three estimation times involved in PERT Optimistic Time Estimate Most Likely TimeEstimate and Pessimistic Time Estimate

In PERT these three estimate times are derived for each activity This way a range of time is given for eacactivity with the most probable value TLIKELY

Following are further details on each estimate

1 TOPT

This is the fastest time an activity can be completed For this the assumption is made that all the necessary resources are available and all predecessor activities are completed as planned

2 TLIKELY

Most of the times project managers are asked only to submit one estimate In that case this is the estimatethat goes to the upper management

3 TPESS

This is the maximum time required to complete an activity In this case it is assumed that many things go wrong related to the activity A lot of rework and resource unavailability are assumed when this estimation iderived

The PERT Mathematics

BETA probability distribution is what works behind PERT The expected completion time is calculated a below

E = (TOPT + 4 x TLIEKLY + TPESS) 6

T O P T

T L I K E L Y T P E S S

E

12715 PERT Estimation Technique

wwwtutorialspointcomcgi-binprintpagecgi 33

For every activity in the critical path E and V are calculated

Then the total of all Es are taken This is the overall expected completion time for the project

Now the corresponding V is added to each activity of the critical path This is the variance for theentire project This is done only for the activities in the critical path as only the critical path activitiescan accelerate or delay the project duration

Then standard deviation of the project is calculated T his equals to the square root of the v ariance

Now the normal probability distribution is used for calculating the project completion time with thedesired probability

Conclusion

The best thing about PERT is its ability to integrate the uncertainty in project times estimations into itsmethodology

It also makes use of many assumption that can accelerate or delay the project progress Using PERT projecmanagers can have an idea of the possible time variation for the deliveries and offer delivery dates to theclient in a safer manner

V

Page 3: PERT Estimation Technique

12715 PERT Estimation Technique

wwwtutorialspointcomcgi-binprintpagecgi 33

For every activity in the critical path E and V are calculated

Then the total of all Es are taken This is the overall expected completion time for the project

Now the corresponding V is added to each activity of the critical path This is the variance for theentire project This is done only for the activities in the critical path as only the critical path activitiescan accelerate or delay the project duration

Then standard deviation of the project is calculated T his equals to the square root of the v ariance

Now the normal probability distribution is used for calculating the project completion time with thedesired probability

Conclusion

The best thing about PERT is its ability to integrate the uncertainty in project times estimations into itsmethodology

It also makes use of many assumption that can accelerate or delay the project progress Using PERT projecmanagers can have an idea of the possible time variation for the deliveries and offer delivery dates to theclient in a safer manner

V