Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
PETROPAVLOVSK PLCInvestor PresentationOctober 2017
Simple. Focused. Growth.
Some statements contained in this presentation or in documents referred to in it are or may be forward-looking statements, including
references to guidance. Such statements reflect the Company’s current views with respect to future events and are subject to risks,
assumptions, uncertainties and other factors beyond the Company’s control that could cause actual results to differ from those expressed in
such statements. Although the Company believes that such forward-looking statements, which speak only as of the date of this presentation,
are reasonable, no assurance can be given that they will prove to be correct. Therefore, you should not place undue reliance on these
statements
There can be no assurance that the results and events contemplated by the forward-looking statements contained in this presentation will, in
fact, occur. The Company will not undertake any obligation to release publicly any revisions to these forward-looking statements to reflect
events, circumstances or unanticipated events occurring after the date of this presentation, except as required by law or by any appropriate
regulatory authority. Nothing in this presentation or in documents referred to in it should be considered as a profit forecast.
The past performance of the Company and its securities is not, and should not be relied on as, a guide to the future performance of the
Cautionary and Forward-Looking Statements
Company and its securities
This presentation does not constitute, or form part of or contain any invitation, recommendation or offer to any person to underwrite,
subscribe for, buy, sell, otherwise acquire, exchange or dispose of any shares or securities in the Company or advise persons to do so in any
jurisdiction, including, but not limited to, the Russian Federation, nor shall it, or any part of it, form the basis of or be relied on in any
connection with or act as an inducement to enter into any contract or commitment therefore or engage in any other investment activity. In
particular, this presentation and the information contained herein are not an offer of securities for sale in the United States. This presentation
does not constitute an advertisement of any securities in the Russian Federation
No reliance may be placed for any purpose whatsoever on the information or opinions contained in this presentation or on its completeness
and no liability whatsoever is accepted for any loss howsoever arising from any use of this presentation or its contents or otherwise in
connection therewith.
The development and production plans and estimates set out herein represent the current views of the Company's management. The
Company’s Board reviews the production estimates on an ongoing basis. All planning is subject, inter alia, to available funding and capital
allocation decisions
English law and English courts will have exclusive jurisdiction over any disputes arising from or connected with this presentation
2
>16Mtpa of RIP(3)
processing capacity4 open pit gold
mines, c.6.7Moz of gold produced to
Production >400koz p/a @ c.37% EBITDA
Margin(4)
c.20.2Moz of JORC Resources(2)
including c.8.0Moz of
Petropavlovsk at a GlanceA leading Russian gold miner, operating since 1994
Part of FTSE SmallCap Index,
c.US$350m market cap(5)
gold produced to date(1)
Experienced management team
and skilled workforce
33(1) As at 30 September 2017, including gold produced by the company's alluvial operations and JVs (2) As at 31 Dec 2016, in accordance with the JORC Code. Resources (M,I&I) are inclusive of Reserves (3) Resin in pulp (4) Underlying EBITDA Margin was 37.5% in H1 2017 and 37.0% in 2016 (5) As at 30 September 2017 (source: Bloomberg)
Marginincluding c.8.0Moz of Reserves
High untapped exploration potential
POX Hub staged commissioning scheduled from
Q4 2018
Corporate GovernanceDispersed ownership structure and highly reputable Board of Directors
Board of DirectorsShareholder Structure(1)
Renova Group(2)
22.3%
Sothic Capital10.6%
D.E. & Shaw & Co.
Prudential / M&G
Other42.8%
Vailaski Holdings9.6%
Mr Ian Ashby, Independent Non-Executive Chairman Appointed to the BoD in June 2017 Mr Ashby has 35 years of international experience in the minerals industry. In his most recent
executive role in 2006-2012, he was President of BHP Billiton’s Iron Ore division Mr Ashby holds NED positions on the board of Anglo-American plc, Nevsun Resources and
Alderon Iron Ore Corporation
Mr Sergey Ermolenko, Interim Chief Executive Officer Appointed as Interim Chief Executive Officer and a Director of the Company on 18th July 2017
following the resignation of Dr Pavel Maslovskiy Mr Ermolenko has held top managerial positions with the Group since its inception in 1994. He
was CEO of Petropavlovsk from December 2011 to November 2014
Mr Andrey Maruta, Chief Financial Officer Appointed to the BoD in January 2011 Mr Maruta joined the Group in 2003 as Group Chief Accountant
4
& Co.7.8%
/ M&G6.9%
Petropavlovsk PLC is listed on the Main Market of the London stock exchange (since 2009)
The largest shareholder is Renova Group(2)
with a holding of 22.3%
The board composition was substantially renewed in June 2017, when a new Non-Executive Chairman and 3 new NEDs were elected. The new board is committed to delivering strong results in line with the Company’s strategy
(1) Reflects % of interest in voting rights of ordinary shares (2) Renova Group is a stakeholder and strategic investor in a number of world-class companies such as UC Rusal, Sulzer, Schmolz + Bickenbach and others. Renova encompasses direct investment funds and management companies operating in a number of sectors. Renova’s 22.3% holding consists of Renova with 14.76% + Metkombank with 4.42% + Lamesa with 3.17%Note: Figures may not add up due to rounding
Mr Maruta joined the Group in 2003 as Group Chief Accountant Appointed Deputy Finance Director in 2005, Finance Director in 2006 and Chief Financial
Officer in 2012 Mr Maruta is a fellow member of The Association of Chartered Certified Accountants
Mr Bruce M. Buck, Senior Non-Executive Independent Director Appointed to the BoD in June 2017 Mr Buck has been practicing law in Europe since 1983, including at
Skadden, Arps, Slate, Meagher and Flom where his work as a partner, included a broad range of mergers, acquisitions and capital market transactions . Mr Buck has been professionally involved in Central and Eastern Europe, and particularly in Russia, since 1990
Mr Buck is also the Chairman and a Director of Chelsea FC PLC
Mr Garrett Soden, Independent Non-Executive Director Appointed to the BoD in June 2017 Mr Soden has extensive experience as a senior executive and board member of public companies
in the natural resources sector. He has worked with the Lundin Group for the last decade Mr Soden is currently President and CEO of Africa Energy Corp., a Canadian oil and gas
exploration company focused on Africa
Mr Vladislav Egorov, Non-Executive Director Appointed to the BoD in June 2017 Mr Egorov has been practicing law in Russia since 1998 Mr Egorov is currently a Deputy M&A and Project Director at Renova Group, the Company’s
major shareholder
Experienced Management Team and Skilled WorkforceAverage industry experience of senior management of more than 30 years
Many of the Group’s senior management team, including the Interim CEO and the COO, as well as the majority of the middle level management, have been with the Group since inception
The Amur region is home to a large pool of highly qualified individuals with gold mining experience due to the historic presence of the industry
5
Nikolai VlasovGroup Chief Geologist
Vladimir DementievGeneral
Manager, Irgiredmet (Scientific Institute)
Prof. Yakov SchneersonDirector of
GidrometallurgiyaR&D (Scientific Institute)
Valery AlekseevGroup Head
of Construction and Engineering
Dr Alya SamokhvalovaDeputy CEO,
Strategic Development
Andrey MarutaCFO
Dmitry ChekashkinCOO
Sergey ErmolenkoActing CEO
400
500
600
700
12Mtpa
14Mtpa
16Mtpa
18Mtpa
20Mtpa
MAL RIP expanded +
ALB RIP commissioned
POX construction begins
Plantexpansionsdelivered:
PIO, MAL, ALB
Listed on AIM
POK RIP commissioned
Albyn licence +Malomir main
site licenceacquired
Moved to LSE Main Board
PIO RIP plant expanded
PIO RIP expanded
MAL RIP commissioned
RIP + HL Processing
Capex (US$m)
Corporate OverviewTrack Record: Processing Growth…Bulk Tonnage Miner
66
0
100
200
300
400
0Mtpa
2Mtpa
4Mtpa
6Mtpa
8Mtpa
10Mtpa
1999a 2002a 2003a 2004a 2005a 2006a 2007a 2008a 2009a 2010a 2011a 2012a 2013a 2014a 2015a 2016a
First goldfrom PIO
POK RIP expanded
First goldfrom POK
First gold fromMAL
First goldfrom ALB
PIO RIP commissioned
JORC Resources (incl. Reserves)
10.112.3 13.8
2.4
3.8 5.1
5.9
6.6 7.2
11.2
20Moz
25Moz
30Moz
35Moz
Corporate OverviewTrack Record: Resource Growth…Sustaining Long Term Production
77
Depletion + DisposalsRefractory Resources
4.96.8
5.2
13.0 12.8 12.1 12.09.3 9.3 9.3
3.32.1 6.0
10.112.3
11.713.8
14.0 14.4
10.4
1.01.4
1.9
Moz
5Moz
10Moz
15Moz
2007a 2008a 2009a 2010a 2011a 2012a 2013a 2014a 2015a 2016a
Non-Refractory Resources
(1) 2016 data is provisional, calculated as YE 2015 resources adjusted for 2016 depletion and disposals and does not take into account any additions made during the year. 2016 R&R statement figures expected to be published in April 2017
Potential for further resource growth, production
growth + cost reduction
Pioneer under-explored underground potential
Malomir under-explored underground potential
POX expansion upside
416
Group Production (Koz) Upside
Corporate OverviewConsolidated 5 Year Plan
420 to
460
88
POX high-grade upside
Highly prospective greenfield and brownfield
surface exploration potential within c.3,400km2
licence footprint
2016a 2017e 2018e 2019e 2020e 2021e
Note: bar charts not to scale
Group AISC (US$/oz)
807
2016a 2017e 2018e 2019e 2020e 2021e
Ongoing optimisation of the reserves and resources to maximise profitability Further exploration to expand underground reserves Further exploration of the identified refractory targets Potential licence acquisitions adjacent to the existing infrastructure
Maintain and expand reserve and resource base
Bulk tonnage open pit producer from non-refractory ore
Production from Non-refractory + refractory oreOpen pit + Underground mining
Petropavlovsk 2016 Petropavlovsk 2019
Corporate StrategyConservative strategy focused on organic growth
99
Unlock existing refractory and underground gold
reserves
Continue optimising costs and strengthening
profitability
Strengthen the balance sheet and liquidity position
Maintain stringent HSE standards
Focus on operation efficiencies and cost optimisation on new projects and continued operations
Hedging of gold price as a complementary measure
Financing of capital expenditures with operating cash flows Leverage below 2.5x Net Debt / EBITDA
Commitment to providing occupational and environmental safety Regular reviews by the HSE committee of the Board Management KPIs include LTIFR and greenhouse gas emissions
Completion of the POX project to treat refractory ore Development of underground operations at Pioneer and Malomir
Assets SnapshotA solid foundation with mining operations in the Russian Far East
St Petersburg RDC Hydrometallurgy
MoscowPetropavlovsk Moscow PHM Engineering
Amur region –production mines
Pioneer
Albyn
Malomir
Pokrovskiy
LondonPetropavlovsk plcCorporate headquarters
Operating mine
Underground development
POX
Analytical labs
R&D
Offices
BlagoveschenskPetropavlovsk Amur RegionRegis ExplorationKapstroi Construction
IrkutskIrgiredmet Institute
IRC Limited (associate company)Amur region – Kuranakh mineJewish autonomous region – K&S mine
1010
Highland Gold 3%
Polymetal 9%
Kinross Gold 8%
Uzhuralzoloto 6%
Petropavlovsk 5%
Nordgold 3%
262.4tonnes
Gold Mine Production in Russia (2016)(1)
Polyus 23%
Other 43%
(1) Source: Russian Union of Gold ProducersNote: Figures may not add up due to rounding10
Operations Overview
1111
Excellent emerging market opportunities
Historic gold province + established mining tradition (>100 yrs)
50% of Russian reserves are in Russia Far East
c.50% of current Russian gold production in Russia Far East
Well educated, skilled workforce
Active State investment in infrastructure
20% corporate tax
Russia Far EastEstablished Gold Belt
1212
Khabarovsk
Yakutia
Pokrovskiy POX Hub
Pioneer(40km from
POX hub)
Malomir(670km from
POX hub)
Albyn
Operations OverviewPetropavlovsk Asset Map
1313
CHINA
Zabaykalsk
EAO
Pokrovskiy POX Hub
Pilot POX Plant
Albyn
Operating Mine
Underground
POX
Analytical Labs
Hydro PlantBlagoveschchensk
Operations OverviewGroup Production Summary FY 2015 – 9m 2017
Mining Units 9m 2017 FY 2016a FY 2015a
Total material moved m3 000 44,780 61,947 74,775
Ore mined t 000 13,960 10,798 13,960
Average grade g/t 0.8 1.1 1.2
Processing Units 9m 2017 FY 2016a FY 2015a
RIP
Total milled t 000 12,410 16,166 15,910
Average grade g/t 0.8 0.91 1.14
Gold content Koz 332 472 581
Recovery rate % 82% 86% 85%
1414
Recovery rate % 82% 86% 85%
Gold recovered Koz 265 407 492
Heap Leach
Ore stacked t 000 1,151 1,141 1,341
Average grade g/t 0.5 0.5 0.6
Gold content Koz 17 18 24
Recovery rate % 39% 51% 52%
Gold recovered Koz 7 9 12
TOTAL gold production Koz 336 416 504
Gold sales Koz n/a 400 482
Costs Units 9m 2017 FY 2016a FY 2015a
TCC US$/oz n/a 660 749
AISC US$/oz n/a 807 874
Pioneer Albyn
180Koz
142Koz (34%)
Operations OverviewFY2016 Production + TCC/oz by Mine
1515
MalomirPokrovskiy
180Koz (43%)
US$581/oz
38Koz (9%)
US$878/oz
(34%)US$631/oz
57Koz (14%)
US$824/oz
FY16 Production 1H16 TCC Pioneer was acquired as a greenfield license in 2001
Licence area of 1,280km2
Produced approx. 2.4Moz Au to date
5.5Moz JORC Resource, 2.6Moz JORC Reserve (c.60% refractory)
Expected >15 year life of mine
6.7Mtpa RIP plant throughput and heap leach
Operations OverviewPioneer – One of Russia’s Largest Gold Operations
16161616
NE Bakhmut 4&5
Vostochnaya
Nikolaevskaya
PerspektivnayaAndreevskaya East
Operations OverviewPioneer Site Plan
17
N
Yuzhnaya
500m
Existing ore body
Depleted / nearly depleted pits; transition to underground
Current + future production pits
Operations OverviewPioneer Production Summary FY 2015 – 9m 2017
Mining Units 9m 2017 FY 2016 FY 2015
Total material moved m3 000 11,638 17,360 23,980
Ore mined t 000 7,096 3,266 6,016
Average grade g/t 0.75 0.95 1.28
Processing Units 9m 2017 FY 2016 FY 2015
RIP
Total milled t 000 5,091 6,700 6,582
Average grade g/t 0.72 0.75 1.25
Gold content Koz 118 160 265
1818
Gold content Koz 118 160 265
Recovery rate % 76% 86% 85%
Gold recovered Koz 90 137 225
Heap Leach
Ore stacked t 000 708 701 800
Average grade g/t 0.49 0.53 0.56
Gold content Koz 11 12 15
Recovery rate % 44% 44% 46%
Gold recovered Koz 5 5 7
TOTAL gold production Koz 132 142 231
Costs Units 9m 2017 FY 2016 FY 2015
TCC US$/oz n/a 631 625
AISC US$/oz n/a 789 752
Pioneer Production (Koz)
142
Pioneer is one of the Group’s most highly prospective
assets, providing enormous near term optionality from:
Underground non-refractory exploration potential
Regional exploration potential from the Pioneer
flanks
Upside
Operations OverviewPioneer 5 Year Plan
19
789
2016a 2017e 2018e 2019e 2020e 2021e
2016a 2017e 2018e 2019e 2020e 2021e
(1) AISC/oz data is based on internal midrange company estimates. Bar charts not to scale
- Non-refractory
- Refractory
Long term optionality includes:
Bringing forward the Pioneer flotation plant
(6.0Mtpa) development, currently scheduled for
2021
Untapped greenfield exploration potential within
1,280km2 licence
Pioneer AISC (US$/oz)
Brownfield exploration at deeper extensions of the
Andreevskaya, NE Bakhmut and Nikolaevskaya zones
Greenfield: assessment of previously delineated 8km
long gold - arsenic anomaly south of Pioneer;
exploration west from Pioneer, Alexandra and
Zheltunak
2017 est. exploration CAPEX US$8m
Alexandra
N
10km
Pioneer licence
Operations OverviewPioneer Exploration
2020
2017 est. exploration CAPEX US$8m
Pioneer
ZheltunakPokrovskiy
Pokrovskiy licence
Key
Open pit
Processing plant
Areas of proposed green field exploration
Licence outline
2016 geochemical anomalies
Alluvial deposits
FY16 Production 1H16 TCC Albyn was acquired in 2005 as a greenfield license
Licence area of 1,053km2
Produced approx. 0.9Moz Au to date
4.8Moz JORC Resource, c.2.1Moz JORC Reserve(1) (100% non-refractory)
Expected >15 year life of mine
4.7Mtpa RIP plant throughput
Operations OverviewAlbyn – the Company’s Largest Producing Mine
2121 (1) Unaudited internal estimate as at 31 Dec 2016, resources include reserves2121
N
Albyn
Unglichikan
Operations OverviewAlbyn Site Plan
2222
1000m
Elginskoye
Existing ore body
Depleted / nearly depleted pits; transition to underground
Current + future production pitsKey:
Operations OverviewAlbyn Production Summary FY 2015 – 9m 2017
Mining Units 9m 2017 FY 2016 FY 2015
Total material moved m3 000 22,719 31,763 36,722
Ore mined t 000 3,677 4,970 4,906
Average grade g/t 1.13 1.25 1.15
Processing Units 9m 2017 FY 2016 FY 2015
RIP
Total milled t 000 3,464 4,675 4,600
2323
Total milled t 000 3,464 4,675 4,600
Average grade g/t 1.15 1.28 0.89
Gold content Koz 128 193 169
Recovery rate % 93% 94% 93%
Gold recovered Koz 119 180 158
TOTAL gold production Koz 138 180 158
Costs Units 9m 2017 FY 2016 FY 2015
TCC US$/oz n/a 581 747
AISC US$/oz n/a 719 910
180
Albyn Production (Koz) Upside
Albyn is a largely under-explored 1,053km2 licence
area with strong potential to discover high grade
non-refractory resources
Recent work at Elginskoye has confirmed a material
increase in reserves further supporting the long-term
sustainability of Albyn mine
Operations OverviewAlbyn 5 Year Plan
2424
2016a 2017e 2018e 2019e 2020e 2021e
(1) AISC/oz data is based on internal midrange company estimates. Bar charts not to scale
Albyn AISC (US$/oz)
719
2016a 2017e 2018e 2019e 2020e 2021e
Within the Albyn licence area there are lots of alluvial
deposits, historical underground gold mines and large
geochemical anomalies
Yasnoye(1): 2016 confirmed a 3km mineralised
extension. Five trenches were developed to explore
this structure beyond the historically mined area
Initial assay results from one trench: 12.2m @
Yasnoye
Albyn
UnglichikanN
Operations OverviewAlbyn Exploration
2525
Initial assay results from one trench: 12.2m @
4.72g/t, 6.0m @ 3.09g/t and 6.0m @ 2.37g/t
2017 est. exploration capex budget US$7m
Elginskoye
Afanasevskoye
10km
Key
Active
Areas of proposed green field exploration/surveying
Licence outline
Geochemical anomalies
Proposed
Open Pits:
Stand by
Principal exploration targets
Alluvial deposits
Ulgen
(1) All thicknesses are apparent
Leninskoye
Malomir was acquired as a greenfield asset in 2003
Licence area of 820km2
Produced c.0.6Moz Au to date
7.1Moz JORC Resource, 3.0Moz JORC Reserve (>85% refractory)
Expected >15 year life of mine
3.0Mtpa RIP plant throughput
Operations OverviewMalomir – the Largest Asset by R&R
2626
N500 m
Ozhidaemoye Magnetitovoye
Operations OverviewMalomir Site Plan
27
Quartzitovoye
Existing ore body
Depleted / nearly depleted pits; transition to underground
Current + future production pitsKey:
Operations OverviewMalomir Production Summary FY 2015 – 9m 2017
Mining Units 9m 2017 FY 2016a FY 2015a
Total material moved m3 000 7,451 8,115 8,904
Ore mined t 000 2,191 1,535 2,105
Average grade g/t 0.83 1.11 1.01
Processing Units 9m 2017 FY 2016a FY 2015a
RIP
Total milled t 000 2,503 3,000 2,937
2828
Total milled t 000 2,503 3,000 2,937
Average grade g/t 0.82 0.86 0.93
Gold content Koz 66 83 88
Recovery rate % 61% 69% 67%
Gold recovered Koz 40 57 59
TOTAL gold production Koz 44 57 59
Costs Units 9m 2017 FY 2016 FY 2015a
TCC US$/oz n/a 824 1,092
AISC US$/oz n/a 1,004 1,180
57
Malomir Production (Koz) Upside
Malomir is the largest asset by R&R
The POX Hub will unlock the significant value of its
refractory reserves and potential for additional
discoveries (possible flagship mine)
Expected to be a flagship asset
Refractory production plan budgets for high grade
Operations OverviewMalomir 5 Year Plan
2929
1,004
2016a 2017e 2018e 2019e 2020e 2021e
2016a 2017e 2018e 2019e 2020e 2021e
(1) AISC/oz data is based on internal midrange company estimates. Bar charts not to scale
Malomir AISC (US$/oz)
Refractory production plan budgets for high grade
ore (1.44g/t) to be processed during initial years to
bring cash flows forward
This will be reflected in the last few years of life of
mine, where we schedule to process 0.76g/t average
grade ore
N JORC resource 210Koz @ 8.2g/t
Indicated + 100koz @ 5.3 g/t Inferred(1)
Resource drilling to date only up to 200m below pit shell
Mineralised zones remain open in multiple directions
New drill intercepts marked not included in JORC
Operations OverviewMalomir Underground: Quartzitovoye
3030
included in JORC
Appointed NAO Bashkirskoe SPY underground contractors
Development commenced Q1 17 -decline and ventilation portals complete
2017 est. underground exploration CAPEX estimate US$4m
(1) Group internal estimate as of Q3 2016, in accordance with JORC Code (2012)
Currently mining a small fraction of the orebody from outcropping at surface
Quartzitovoye open pit has produced c.0.35Moz from high grade (>5.1g/t)
No indication ore zone is pinching out
Possibility of a ‘swell’ in the orebody as it intersects the diagonal thrust zone
Quarzitovoye Long Section in combination with Malomir Cross Section
Operations OverviewMalomir Upside
Ver
tica
l str
uct
ure
ho
stin
g Q
uar
tzit
ovo
yeh
igh
gra
de
zon
e
Exploration potential on down
dip extension
3131
Quartzitovoye Malomir
N
Key
Active open pit
Process plant
Exploration targets Tumannoe
Stand by open pit
Operations OverviewMalomir Licence Area
Quartzitovoye
10km
Malomir
MagnetitovoyeOsenie
Razlomnoye
Zapadnoe
Begen
Uspenskoe
Areas of proposed green fieldexploration
3232
FY16 Production 1H16 TCC
Operations OverviewPokrovskiy
3333
Pokrovskiy was the Group’s first asset, acquired in 1994
License area of 95km2
Produced approx. 2Moz Au to date
As Pokrovskiy nears the end of its mine life, the excellent infrastructure, including 1.8Mtpa RIP plant, is being augmented into the POX Hub
3333
West Zheltunak
East Zheltunak
Pokrovskiy Site Plan
Operations OverviewPokrovskiy Asset Overview
3434
Existing ore body
Depleted / nearly depleted pits; transition to underground
Current + future production pitsKey:
Pokrovskiy FY2016: Mining Unit RIP HL
Total material moved m3 000 4,709 n/a
Ore mined t 000 1,027 n/a
Pokrovskiy FY2016:Processing
Total milled t 000 1,791 440
Average grade g/t 0.7 0.5
Recovery rate % 90.1 64.8
Gold recovered Koz 34 4
Total gold recovered Koz 38
Pressure Oxidation Plant (POX Hub) Refractory Growth Story
3535
Asset Location LaunchDaily
Production(Tonnes)
Grade(g/t Au conc)
#Auto/ claves
S (%) S/Au
ORE
Goldstrike USA 1990 16,000 n/a 6 3 0.3
LihirPapua New Guinea
1997 9,800 5 6 7 1.4
Twin Creeks USA 1997 7,200 n/a 2 4 1.3
Pressure oxidation is an established
technology for treating refractory
ore, employed for decades:
- 1952, first POX plant for base
metals commissioned
- 1985, first POX plant to treat
POX Hub OverviewGlobal Market, Proven Technology
3636
Pueblo ViejoDominican Republic
2012 24,000 3 4 7 2.3
Çöpler Turkey 2018e 5,000 2 - 5 1 (7) 4.2 1 - 2
CONCENTRATE
PorgeraPapua New Guinea
1991 2,100 100 4 9 0.1
MacraesNew Zealand
1999 560 45 1 10 0.2
Kittila Finland 2008 500 30 1 18 0.6
Donlin USA n/c 8,000 13 2 7 0.5
Quimsacocha Ecuador n/c 510 29 1 30 1.0
Amursk Russia 2012 770 45 1 7 0.1
PokrovskiyPOX Hub
Russia 2018e 1,800 25 4 24 0.9
gold refractory ore
commissioned in
McLaughlin, USA
Existing POX operations in
Russia, North America, New
Zealand, Papua New Guinea and
Finland, with many under
construction, including our POX Hub
at Pokrovskiy, Amur Region
(1) n/a = data not available n/c = not commissioned yet
Mayskoye
KyuchusNezhdaninskoye
Russia• Extensive and well understood refractory gold R&R base
• c.80% of R&R are refractory or partly refractory
• Experience in treating refractory ore across multiple metals
• Highly skilled labour and technology
• The POX Hub give Petropavlovsk a competitive advantage and offers new growth opportunities
POX Hub OverviewSignificant Refractory Gold Territory
3737
Pokrovskiy POX Hub
Olimpiada
Veduga
Albazino
Taseevskoye
Itakinskoye Kluchevskoye
Malomir
Bogolubovskoye
PioneerKey: Principal refractory / partly refractory deposits
Petropavlovsk
Other assets
Nasedkino
Khabarovsk
Yakutia
Pokrovskiy POX Hub
Pioneer(40km from
POX hub)
Malomir(670km from
POX hub)
Albyn
Excellent location Well established infrastructure 10km from Trans-Siberian Railway Access to ample hydropower Milling facilities and skilled workforce Viable hub for processing third party ore
POX Hub OverviewStrategically Positioned
3838
CHINA
Zabaykalsk
EAO
Pokrovskiy POX Hub
Pilot POX Plant
Albyn
Operating Mine
Underground
POX
Analytical Labs
Hydro Plant
Lime Deposit
Blagoveschchensk
JORC Refractory Mineral Resources(1)JORC Refractory Ore Reserves(1)
3.2Moz @0.96g/t3.2Moz
@0.96g/t
POX Hub OverviewPOX Unlocks c.50% of our Existing Reserve Base
3939 (1) As at 31 Dec 2015; in accordance with JORC 2012; WAI April 2016;
@0.96g/[email protected]/t
ProbableProven
Total Proven + Probable Refractory Reserves = 4.0Moz @ 1.0g/t
InferredIndicatedMeasured
Total Measured, Indicated + Inferred Refractory Resources = 9.3Moz @ 0.8g/t
>15yrs of sustainable refractory production
150 –170ktpa
FRO
M 2
01
8
FRO
M 2
02
3
Flotation Plant Flotation Plant
300 –330ktpa
Malomir concentrate 86% recovery 5.5% concentrate
yield 24 g/t Au
Pioneer concentrate 82% recovery 2.9% concentrate
yield 24 g/t Au
MALOMIR PIONEER
POX Hub OverviewFlowsheet
TOTAL recovery =
c.80%
4040
170ktpa concentrate
330ktpa concentrate
POX HUB
Concentrate Re-grinding
90% -0.044мм
1
Autoclave Oxidation
4x 15mx4m autoclave
225°C @ 35 bar20 - 30 minutes
2
RIP Circuit
Purogold Resin
3
Doré to Refinery
RecoveriesMalomir = 93%Pioneer = 98 %
4
Malomir Flowsheet Pioneer Flowsheet
Floatation concentrate Floatation concentrate
Ore processed 5.4Mtpa (Stage 1: 3.6Mtpa) Ore processed 6.0Mtpa
Ore grade 1.04 g/t Ore grade 0.91 g/t
Flotation recovery 86% Flotation recovery 82%
Concentrate yield 5.5% mass Concentrate yield 2.9% mass
Concentrate grade 24 g/t Au Concentrate grade 24 g/t Au
Pressure oxidation 300 - 330ktpa Pressure oxidation 150 - 170ktpa
POX Hub OverviewOperating Parameters
41
Malomir flotation commissioning from 4Q17; Pioneer flotation commissioning from 2023
Pressure oxidation 300 - 330ktpa Pressure oxidation 150 - 170ktpa
Sulphur 24.90% Sulphur 21%
Gold recovery 93% Gold recovery 98%
TOTAL avg gold recovery 79% TOTAL avg gold recovery 80%
Est. operating costs US$615-$675/oz Est. operating costs US$785-$865/oz
Mining $2.5/m3 rock Mining $2.6/m3 rock
Transport $26/t concentrate Transport $1.7/t concentrate
Flotation $4.6/t treated ore Flotation $4.6/t treated ore
POX $78.2/t concentrate POX $78.1/t concentrate
Blagoveschensk Pilot Plant
- Only autoclave test plant in Russia
- Models complex physicochemical processes to identify the optimal solution for autoclave concentrate recovery
- Testing permutations of the operating parameters (temp, pressure, flow rate, qty of reagents)
- Running simulation of ramp-up scenarios
- Automation and controls exactly as will be implemented at the Pokrovskiy plant
Derisks the commercial scale implementation, allowing for
POX Hub OverviewPilot Plant – Reducing Execution Risk and Optimising Output
4242
Ongoing optimisations of POX technology: oxidation kinetics, concentrate blends, impact of chloride ions
Derisks the commercial scale implementation, allowing for effective, efficient ramp-up.
In 2013 - 2015 pilot plant tests confirmed the feasibility of POX for Malomir and Pioneer concentrates
- Recovery achieved of 92 to 95% for Malomir and 98% for Pioneer
- Research + pilot plant tests allowed significantly improved oxidation time
- This opened up a potential to increase capacity by 30% (compared to original design)
POX Hub OverviewMalomir Flotation Plant – STAGE 1 (3.6Mtpa) 90% Complete
• Malomir was acquired in 2003 as a greenfield license, now the Group’s largest asset by R&R.
• License area of 964km2
• Produced c.0.6Moz Au to date
• 6.8Moz JORC resource, 2.7Moz JORC reserve (>90% refractory)
• Completing POX will unlock an implied LOM of
• 3.0Mtpa RIP plant throughput 4343
Stage 1: 3.6Mtpa – commissioning 4Q17 Stage 2: 3.6Mtpa expansion - commissioning in 2019 TOTAL capacity 5.4Mtpa across three lines Stage 1 & 2 CAPEX est. US$32m
43
Filtration unitOxygen stationAutoclave unit
Container
POX Hub OverviewPOX Hub Construction 65% Complete
44
Container unit, equipment
storage
POX Hub staged commissioning scheduled from 4Q18, with ramp up throughout 2019 Most design, earth works and civil works complete. All critical items on site, including 80% of project
equipment. All key contracts signed, including installation and commissioning work with Outotec The autoclaves (x 4) are installed / lined Total pre-production CAPEX est. US$120m (2017 est. US$65m CAPEX)
Autoclave Building
4545
Autoclave building Autoclaves installed on foundations
Autoclave agitators Flash tanks
INSERT IMAGE
x
Filtration Building
INSERT IMAGE
46
Press filter
Fine filter Reagent preparation / dispenser
Agitator for neutralisation vessel
Malomir Flotation Plant
4747
Internal view of flotation plant
Flotation tail thickeners Flotation machines
Aerial view of flotation plant
Oxygen Plant
4848
Oxygen plant building
Internal view of the oxygen plant Internal view of the oxygen plant
Oxygen plant building
Expansion. The POX Hub is engineered to allow for an additional two autoclaves to be installed, increasing capacity by 30% to 650Ktpa
Potential to take third party concentrates for toll treatment
Different concentrates can be processed in parallel without compromising recovery
Project Economics (2018-2032)(1) Optionality
POX Hub capacity 500Ktpa
Project NPV (10%) US$603m
Project IRR 65%
Project payback 3.25 yrs
Revenue 2018 – 2032 US$3,965m
Avg Gold Production (koz pa) 220Koz
POX Hub OverviewProject Economics
49
8%
36% 39% 41%
100% 92%
64% 61% 59%
0%
20%
40%
60%
80%
100%
2017e 2018e 2019e 2020e 2021e(1) Assuming LT avg gold price US$1,200/oz and FX of USD:RUB of 60
20
17
Malomir Flotation Plant Due Date
Stage 1 construction complete Q4
Stage 1 commissioning Q4
POX Hub Construction
Delivery of equipment + materials (80% on site) Q3
Supporting infrastructure work Q4
Piping + welding Ongoing
Malomir Flotation Plant
POX Hub OverviewPath to Production
5050
20
18
Malomir Flotation Plant
Concentrate production (stockpiling + trucking) H1
POX Hub Construction
Piping + welding complete Q2
Autoclaves complete Q3
Pokrovskiy RIP refurbishment + integration Q3
POX Hub Commissioning
Oxygen plant complete Q2
Plant infrastructure (incl. steam plant, electrical, automation) Q2
Autoclaves: staged commissioning Q4
FIRST PRODUCTION Year End
Financial Overview
5151
624.5504.1
416.3298.1 336.4
2014 2015 2016 9M 2016 9M 2017 2017E
Gold Production
Koz
420 - 460
Gold Production and RevenuesGrowth resumed in 2017
(1)(1)
+13%
Up to 10.5%
Disposal of alluvial operations and focus on profitable ounces
Focus on profitable ounces and the impact
of extreme weather conditions on the mining schedule
2014 2015 2016 9M 2016 9M 2017 2017E
5252
Revenue
(1) From the beginning of 2017, the Company moved to using gold poured as the definition for production. Comparable 9M 2016 gold production numbers are adjusted accordinglyNote: Figures may not add up due to rounding
(1)(1)
821.7567.6 488.5
233.4 290.8
865.0
599.9 540.7
254.0 304.0
1,331
1,1781,222 1,194
1,255
2014 2015 2016 H1 2016 H1 2017
Gold sales Other revenues Average realised gold sales price (US$/oz)
US$m
+20%
Operating Cash Expenses(1) Structure
Materials33%
Staff costsFuel14%
Other 9%
Electricity10%
Other external services
11%
401.0 329.2 266.0123.4 150.6
505.7360.7
263.7129.7 156.4
860749
660 663 675
2014 2015 2016 H1 2016 H1 2017
Operating cash expenses Other cash costs
Total Cash Costs
US$m
Operating Costs and EBITDAIncreasing profitability on the back of lower production costs
US$ 150.6m
+2%
(1)
(2)
53
Staff costs23%
14%Operating cash expenses Other cash costsTCC (US$/oz)
EBITDA and EBITDA Margin
251.8172.8 200.1
88.0 114.1
29.1% 28.8%
37.0%34.6%
37.5%
2014 2015 2016 H1 2016 H1 2017Underlying EBITDA Underlying EBITDA margin
(1) Operating cash expenses are defined as operating cash costs less refinery and transportation, other taxes, mining tax and deferred stripping. Presented before movement in stockpiles, work in progress and bullion in process attributable to gold production (2) Other cash costs were negative in 2016 due to movement in stockpiles, work in progress and bullion in process attributable to gold production (3) is defined as profit/(loss) for the period from continuing operations before investment income, interest expense, other finance gains, other finance losses, foreign exchange gains and losses, taxation, depreciation, impairments, reversals of impairment write-downs to adjust the carrying value of net assets of disposal groups held for sale to fair value less costs to sell and the Group’s share of interest expense, investment income, other finance gains, other finance losses, foreign exchange gains and losses, taxation, depreciation and impairments recognised by an associate Note: Figures may not add up due to rounding
US$m
+30%
(1)
(3)
Capital Expenditures
10096.8
168.8
111.0
US$m
Cash FlowsInvestments are funded via internally generated cash flows
5454
24.3(2)
12.7 10.9 14.1
100
34.1
18.9 16.6 10.9
38.4
1.01.9
16.8
96.8
32.629.4
41.837.0
74.6
2014 2015 2016 H1 2017 FY2017E
Sustaining capex Exploration Development Net cash from operating activities
Construction of POX Hub
resumed
(1) (1)
(1) From continuing operations (2) Including c.US$23.2m for hard rock mines and c.US$1m for alluvial operationsNote: Figures may not add up due to rounding
Construction of POX Hub suspended
(1)
(2)
Net Debt and Leverage
977.8638.3 611.2 602.8
929.7610.0 598.6 570.1
3.7x 3.5x
3.0x2.5x(1)
Leverage and Debt StructureContinued focus on deleveraging
US$m -1.2x
5555
Debt Structure (30 June 2017)
YE2014 YE2015 YE2016 30 June 2017
Total debt Net debt Net debt / Underlying EBITDA
Convertible bond- Carrying value per IFRS: US$89.9m- Principal amount: US$100.0m- Maturity: March 2020- Exchange price: £0.0826 (actual price
£0.0800 as at 30 Sept 2017)
Bank loans- Carrying value per IFRS: US$512.9m- Principal amount: US$518.2m- Maturity: final maturity in September
2022 (with amortisation) - Lenders: Sberbank and VTB
Bank loansUS$512.9m
Conv. bond US$89.9m US$
602.8m
(1) Underlying EBITDA for the year ended 30 June 2017, which is used for calculation of the ratio, is US$226.2m
Key Strengths
Exploitable and long life mineral resource base with expansion potential
Strong track record of mine development, expansion and asset optimisation
New growth opportunities – POX hub and underground mining
1
2
3New growth opportunities – POX hub and underground mining
Highly efficient mining and processing operations
Experienced management team and skilled workforce
Strategic location and access to developed infrastructure
4
5
6
56
Appendix
5757
Total Group Reserves and Resources
Total Ore Reserves for Open Pit and Underground Extraction(1)
Category Tonnage (kt) Grade (g/t Au) Gold (Moz)
Total Reserves
Proven 32,032 0.82 0.84
Probable 229,667 0.96 7.11
Proven+Probable 261,699 0.95 7.95
Non-Refractory Reserves
Proven 22,177 0.69 0.49
Probable 95,632 1.10 3.39
Proven+Probable 117,809 1.03 3.88
Refractory Reserves
Proven 9,854 1.11 0.35
Probable 134,036 0.86 3.72
Proven+Probable 143,890 0.88 4.07
5858
(1) Notes:- In accordance with JORC Code as at 31 Dec 2016, Resources (M,I&I) are inclusive of Reserves- Figures may not add up due to rounding- Figures include the non-core Tokur project, which contains a total of c.1.4Moz of non-refractory Resources of which c.0.2Moz are Reserves
Total Mineral Resource for Potential Open Pit and Underground Extraction(1)
Category Tonnage (kt) Grade (g/t Au) Gold (Moz)
Total Resources
Measured 51,859 0.94 1.57Indicated 418,167 0.89 11.96Measured + Indicated 470,026 0.90 13.53Inferred 257,409 0.80 6.63
Non-Refractory Resources
Measured 33,654 0.91 0.99Indicated 207,117 0.96 6.36Measured + Indicated 240,771 0.95 7.35Inferred 115,328 0.96 3.55
Refractory Resources
Measured 18,205 0.99 0.58Indicated 211,050 0.82 5.60Measured + Indicated 229,255 0.84 6.18Inferred 142,081 0.67 3.08
9M 2017 Group Production Summary
Units Pioneer Albyn Malomir Pokrovskiy
Total material moved m3 000 11,638 22,719 7,451 2,972
Ore mined t 000 7,096 3,677 2,191 996
Average grade g/t 0.75 1.13 0.83 0.51
Gold content Koz 171.1 133.5 58.3 16.3
Resin in pulp (RIP) plant
Total milled t 000 5,091 3,464 2,503 1,352
Average grade g/t 0.72 1.15 0.82 0.46
5959
Average grade g/t 0.72 1.15 0.82 0.46
Gold content Koz 118.4 127.6 65.8 19.8
Recovery rate % 76.1 93.1 61.3 81.9
Gold recovered Koz 90.1 118.8 40.3 16.2
Heap leach operations
Total stacked t 000 708 443
Average grade g/t 0.49 0.39
Gold content Koz 11.1 5.6
Recovery rate % 43.8 35.6
Gold recovered Koz 4.8 2.0
Gold production – Dore(1) Koz 131.8 138.0 43.8 22.8
(1) From the beginning of 2017, the Company moved to using gold poured as the definition for production
HSE and Social Responsibility
Safety
GHG Emissions
One of the key indicators the Group uses to identify safety trends is Lost Time Injury Frequency Rate (LTIFR)(1); an integral part of complex management systems
The measure ensures compliance with Russian legislation and provides the Group with a basis for ongoing improvement
The Group is aiming for a low LTIFR and zero fatalities by seeking to implement new, or improve on existing, OH&S systems
Monitoring greenhouse gas (GHG) emissions enables the Group
2.50 2.63 2.64
2014 2015 2016LTIFR
Emissions 2016 2015 2016 vs.
(1)
60(1) LTIFR is the number of accidents (incl. fatalities) taking place on Group premises (excludes IRC, which has a separate HSE management system) measured against the number of man hours worked during that period (per million man hours worked)
Monitoring greenhouse gas (GHG) emissions enables the Group to look for opportunities to minimize its carbon footprint
Emissions come from the following sources: diesel; kerosene; benzene; coal
The Group continues to monitor GHG emissions and reviews all relevant data in order to identify opportunities for improvement
Emissions 2016 2015 2016 vs. 2015
Operation of facilities (tonnes of CO2e) 182,408 260,195 -30%
Own use(tonnes of CO2e) 222,847 276,144 -19%
Total emissions per oz. of gold produced
0.97 1.07 -9%
Social Responsibility
Petropavlovsk takes a responsible approach to operations in areas inhabited by the Evenki people (an indigenous community) of the Amur region, actively seeking their support for operations, continually assessing potential risks and contributing to community development
The Company recognises the socioeconomic influence it has as a major employer and taxpayer in the Amur region. The Group provides equal opportunities and pays in all aspects of employment, regardless of gender or background, as required by both Russian and UK legislation
A producer and developer of industrial
commodities, principally iron ore. Based in the
Russian Far East, IRC benefits from low production
costs and proximity to the Chinese border
Listed on the Hong Kong Stock Exchange (1029 HK)
since 2010
Petropavlovsk is a 31.1% shareholder:
‒ IRC is accounted as an associate under the equity
accounting method
‒ Worth US$70m as at 30 September 2017(1)
ICBC project finance facility to fund construction
of K&S mine, 100% guaranteed by POG
IRC at a Glance POG Equity Interest and Contingent Liability
IRC LimitedPetropavlovsk has a 31.1% equity interest
IRC’s key mining assets are K&S, Kuranakh and
Garinskoye:
‒ K&S: A producing iron ore mine which is located in
the Jewish Autonomous Region (EAO) of the
Russian Far East. The plant is currently operating at
a steady capacity of around 80%
‒ Kuranakh: the BoD has authorised a strategic
assessment of the option to restart the operation
‒ Garinskoye: the project is at an advanced stage of
exploration
‒ The only debt within IRC
‒ c.US$234m outstanding principal, as at
30 September 2017
‒ 2017 repayment holiday
‒ Guarantee fee of 1.75% p/a on outstanding facility
amount payable to Petropavlovsk by IRC
As part of the balance sheet optimization, the Group
is constantly assessing the best way to realise the
value of its interest in IRC
61 (1) IRC market capitalisation as at close 30 September 2017 (US$225m, source: Bloomberg) x Petropavlovsk’s equity interest (31.1%) = US$70m
Investor Relationse: [email protected]: +44 (0) 207 201 8900