Consultancy Agreement No. C803Express Rail Link - Detailed Design for Tunnels & Associated Structures (North)
Deliverable No. 3.13A (BD Consultation)Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation BuildingsContract 823B : Shek Kong Stabling Sidings and ERS
Deliverable No. 3.13A (BD Consultation)
Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation Buildings
Contract 823B : Shek Kong Stabling Sidings and ERS
Appendix D
Pile Design Calculations
Consultancy Agreement No. C803Express Rail Link - Detailed Design for Tunnels & Associated Structures (North)
Deliverable No. 3.13A (BD Consultation)Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation BuildingsContract 823B : Shek Kong Stabling Sidings and ERS
Deliverable No. 3.13A (BD Consultation)
Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation Buildings
Contract 823B : Shek Kong Stabling Sidings and ERS
Appendix D1
Design of Pile Structural Capacity and Determination of Minimum Rock Socket Length for Bonding
Consultancy Agreement No. C803Express Rail Link - Detailed Design for Tunnels & Associated Structures (North)
Deliverable No. 3.13A (BD Consultation)Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation BuildingsContract 823B : Shek Kong Stabling Sidings and ERS
Deliverable No. 3.13A (BD Consultation)
Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation Buildings
Contract 823B : Shek Kong Stabling Sidings and ERS
Appendix D2
Determination of Rock Socket Length for Rock Cone Failure
Consultancy Agreement No. C803Express Rail Link - Detailed Design for Tunnels & Associated Structures (North)
Deliverable No. 3.13A (BD Consultation)Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation BuildingsContract 823B : Shek Kong Stabling Sidings and ERS
Deliverable No. 3.13A (BD Consultation)
Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation Buildings
Contract 823B : Shek Kong Stabling Sidings and ERS
Appendix D3
Column and Wall Loading Schedule
Consultancy Agreement No. C803Express Rail Link - Detailed Design for Tunnels & Associated Structures (North)
Deliverable No. 3.13A (BD Consultation)Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation BuildingsContract 823B : Shek Kong Stabling Sidings and ERS
Deliverable No. 3.13A (BD Consultation)
Foundation Design Calculations Part 1 For
Emergency Rescue Siding & Ventilation Buildings
Contract 823B : Shek Kong Stabling Sidings and ERS
Appendix D4
Extract of Base Slab Analysis and Pile Reaction Forces Summary