Upload
chen-e-lik
View
217
Download
0
Embed Size (px)
Citation preview
8/11/2019 Pile Report
1/14
Grid D.L. L.L. W.L. Mx MyDimension
(B L H)
AsReq Rebar Pile
XDir YDir XDir YDir No. Type
P17
C15:(4,
K)
2425.
8691.4 12.4 0.0 0.0
240024001
0007200 7200 23T20 23T20 5
Square
400400
DESIGN REPORT FOR PILE FOUNDATION P17 C15:(4,K)
Element/Elements Supported = Column C15:(4,K)
FOOTING DESIGN LOADING TABLE
Loading Number Selected for Foundation Design = 3
No. SourceLoad
Case
Load
Comb.
Service LoadLLR. P Ult. F
P (D.L.) P (L.L.) P (W.L.) Mx My
1 G.L. G. LC1 2205.3 628.5 0.0 0.0 0.0 0.0 2833.8 1.44
2 G.L. G. LC1 2205.3 628.5 0.0 0.0 0.0 0.0 2833.8 1.443 N.L. 1 LC2 2205.3 628.5 11.2 0.0 0.0 0.0 2845.1 1.20
4 N.L. 2 LC2 2205.3 628.5 -1.8 0.0 0.0 0.0 2832.0 1.20
5 N.L. 3 LC2 2205.3 628.5 -11.2 0.0 0.0 0.0 2822.6 1.20
6 N.L. 4 LC2 2205.3 628.5 1.8 0.0 0.0 0.0 2835.6 1.20NoteSource - Source of Loading (G.L. for Gravity, W.L. for Wind Load, N.L. for Notional Load, S.L. for Seismic Load)Load Case - Load Case Number of Wind/Notional Load (G. for Gravity)Load Comb. - Load Combination NumberService Load - Foundation Service Load from Column (kN)LLR. - Live Load Reduction from Stump and above (kN)P Ult. - Ultimate Axial Force after multiply by Foundation Load Combination (kN)F - Load Factor use in foundation designMoment value automatically set to 0 when M / P ratio less than 5.0 mmFoundation live load reduction only can be carried out after running 3D Analysis together with Column/Wall live load reduction set to
True
Check the pile load based on the 5 piles provided
P = 3129.57 kN; Mx = 0 kNm; My = 0 kNm
Pile capacity = 70 ton
Pile load due to axial load
= P / n = 3129.57 / 5 = 625.91 kN
= 63.8 ton 70 ton
DESIGN RESULT
Equivalent loadings imposedEquivalent Column Load = 3129.57kN
Equivalent Column moment X = 0.00kNmEquivalent Column moment Y = 0.00kNm
Load Allowance = 10%
Ixx =2.88m^4
Iyy = 2.88m^4
Pile CapPile Cap self-weight Load =138.24kN
Pile Cap self-weight moment X =0.00kNm
8/11/2019 Pile Report
2/14
Pile Cap self-weight moment Y=0.00kNm
Total LoadingsTotal load applied = 3267.81kN
Total moment X applied =0.00kNm
Total moment Y applied =0.00kNm
Pile Group ResultPile Group Centroid : {78000.00,19200.00}mm
Pile
No
Coordinate
X (mm)
Coordinate
Y (mm)
Capacity
(kN)Applied Load Mx(kNm) My(kNm) Pile Type
1 77151 18351 686.70 653.56(pass) -554.57 -554.57 Original
2 77151 20049 686.70 653.56(pass) 554.57 -554.57 Original
3 78000 19200 686.70 653.56(pass) 0.00 0.00 Original
4 78849 18351 686.70 653.56(pass) -554.57 554.57 Original
5 78849 20049 686.70 653.56(pass) 554.57 554.57 Original
Sum 3433.50 3267.81 0.00 0.00
Each pile with their respective load, the pile cap self-weight is taken into account
Sample Calculation for Pile No.1Applied Load = P / n = 3267.81 / 5 = 653.56 kN
Number of Pile
Applied load
with self weight
(kN)
Applied load
without self
weight (kN)
Ultimate
applied load
without self
weight (kN)
1 653.56(pass) 625.91 904.04
2 653.56(pass) 625.91 904.04
3 653.56(pass) 625.91 904.04
4 653.56(pass) 625.91 904.04
5 653.56(pass) 625.91 904.04
Sum 3267.81 3129.57 4520.22
Note: The lump safety factor for load is 1.44
Pile Number TypeDimension
(mm)
1 Rectangular 400X400
2 Rectangular 400X400
3 Rectangular 400X400
4 Rectangular 400X400
5 Rectangular 400X400
Status:
Design Passed
Number of piles required = 5
Footing slab thickness = 1000.00mm
Steel percentage for footing slab X = 100*7226/(2400*1000.0) = 0.30 %
Steel percentage for footing slab Y = 100*7226/(2400*1000.0) = 0.30 %
Pile Cap Cross Section InformationPoint 0:{76800,18000} mm
8/11/2019 Pile Report
3/14
Point 1:{79200,18000} mm
Point 2:{79200,20400} mm
Point 3:{76800,20400} mm
Pile Cap center = {78000.00,19200.00} mm
B = 2400
L = 2400
Thickness =1000mm
Pile Cap Density = 24kN/m^3
Pile Cap weight = 138kN
The depth of the footing slab = 1000mm
The effective depth for reinforcement in x direction = 838mm
The effective depth for reinforcement in y direction = 818mm
Total depth = Effective depth of rebar + rebar radius + distance from rebar to pile + pile penetration
Total depth = 838+10+25+100=9731000mm
The Detailed Calculations for Footing Thickness and Reinforcement Bars
Detailed Moment CalculationThe moment is taken at 1 times of the column face to the column center
The calculation of service state moment about Axis
Load density = service state pile capacity/area
Area mx is the effective area of the pile in consideration of moment X
Area my is the effective area of the pile in consideration of moment Y
Pile
No.
load density
(ld, kN/m)
lever arm
Moment X
(laX, mm)
Area mx (Ax,
m)
Moment about
X(ld*laX*Ax/
10^3, kNm)
lever arm
Moment Y
(laY, mm)
Area my (Ay,
m)
Moment abou
Y(ld*laY*Ay
10^3, kNm)
1 4291.88 -498.5 0.16000 -342.34 0.0 0.000000 0.00
2 4291.88 0.0 0.00000 0.00 0.0 0.000000 0.00
3 4291.88 0.0 0.00000 0.00 0.0 0.000000 0.00
4 4291.87 -498.5 0.16000 -342.34 598.5 0.160000 411.015 4291.88 0.0 0.00000 0.00 598.5 0.160000 411.01
-684.68 822.02
The calculation of ultimate moment (the magnitude)
The absolute ultimate moment X = 1.44*684.68=988.92kNm
The absolute ultimate moment Y = 1.44*822.02=1187.29kNm
Check Thickness Constraint1000mm is a multiple of 50mm
Footing thickness constraint checking pass!!
Check Footing Depth
Footing slab depth minimum thickness1000mm 300mmFooting depth checking pass!!
Moment CheckingClause 3.4.4.4 singly R.C. design(Reinforced Concrete Design, Mosley second edition, pp 62-66)
Mx
8/11/2019 Pile Report
4/14
k'=kk1/fcu
kk1=cb*k1*(1-cb*k2)
cb=limiting effective depth factor = 0.5
Mx and My are ultimate limit state moment
k1 = (0.45-0.15fcu/17.86)fcuk1 = [0.45-0.15*30.00/17.86] 30.00 = 12.12
k2=1-0.45*fcu*(0.5-fcu/3828)/k1
k2=1-0.45*30.00*(0.5-30.00/3828)/12.12 = 0.45
kk1 = cb*k1*(1-cb*k2)
kk1 = 0.50*12.12*(1- 0.50*0.45) = 4.69
k'=kk1/fcu
k' = 4.69/30.00 = 0.156
Steel Area Calculation
k' =M/(fcu*b*d^2)
z = Min (d{0.5+(0.25-k'/(2*0.67/c))}, 0.95*d)Steel area = M/(fy*z/s)
M = Ultimate limit state Bending Moment
d = effective depth
c = partial safety factor for concretes = partial safety factor for steel fy = yield strength for steel
Steel Area in X Directionk = 10^6*1187.29/(30*2400*838) = 0.0235
lever arm = 838*(0.5+(0.25-(0.0235)/2*0.67/1.50))) = 815 mmlever arm = Min (lever arm, 0.95*838) = 796 mm
Steel area x due to moment = 10^6*1187.29/(460/1.15*796) =3730 mmSteel area that are due to minimum requirement = (steel min percentage)*cut sectional area/100 =
0.3*2400*1000/100=7200.00 mm
Steel area provided = 7226 mm
Check for moment in x direction
fcu*b*dk'>=Mx
30.00*2400*838*0.16/10^6 = 7900.69kNm>=1187.29=1187.29kNm
Moment checking pass
Check for steel percentage:
Steel percentage x = 100*7226/(2400*1000.0) = 0.30%
The steel percentage is OK
Check for the sufficiency of steel area provided in x direction
23T20 is used
The total bar area is = 3.142*23*20^2/4 = 7226mm
The steel area provided 7226 mm
7200
8/11/2019 Pile Report
5/14
Bar spacing in x = 100
Bar diameter in x = 20mm
The bar spacing is ok
Check for bar diameter:
Bar diameter in x = 20mm
The bar diameter is ok
Steel Area in Y Directionk = 10^6*988.92/(30*2400*818) = 0.0205
lever arm = 818*(0.5+(0.25-(0.0205)/2*0.67/1.50))) = 798 mmlever arm = Min (lever arm, 0.95*818) = 777 mm
Steel area y due to moment = 10^6*988.92/(460/1.15*777) =3183 mm
Steel area that are due to minimum requirement = (steel min percentage)*cut sectional area/100 =
0.3*2400*1000/100=7200.00 mm
Steel area provided = 7226 mm
Check for moment in y direction
fcu*b*dk'>=My
30.00*2400*818*0.16/10^6 = 7527.94kNm>=988.92=988.92kNm
Moment checking pass
Check for steel percentage:
Steel percentage y = 100*7226/(2400*1000.0) = 0.30%
The steel percentage is OK
Check for the sufficiency of steel area provided in y direction23T20 is used
The total bar area is = 3.142*23*20^2/4 = 7226mm
The steel area provided 7226 mm
7200
8/11/2019 Pile Report
6/14
Y)=100*(7226+7226)/(2010498+1962498)=0.36
Effective steel percentage = Min(Average steel %, 3) = 0.36%
thickness = (838+818)/2=828
Inverted thickness = (max(1,(400/thickness))^(1/4)
Inverted thickness = (max(1, (400/(828)))^1/4 )= 1.00
Shearing capacity, vc = 0.79*0.36^(1/3)*1.00*(30/25.0)^(1/3)/1.25 = 0.48 N/mm^2
Check for the case if the critical section occurs at 0.5d from column face
Enhancement shear multiplier, esm = 1.5
Enhanced shear factor = Max(esm/k, 1)= Max(1.5/0.50,1) = 3.00
Enhanced shear capacity, vc' = vc enchanced shear factor = 0.48 3.00 = 1.44 N/mm
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate Pile
Load Inside the
Critical
Diagonal Zone
(kN)
1 -849 -849 991.8 0.0
2 -849 849 991.8 0.0
3 0 0 991.8 991.8
4 849 -849 991.8 0.0
5 849 849 991.8 0.0
Sum 4959.2 991.8
k = 0.50
The dimension of the effective critical section
B' = B + 2*k*d
B' = 500 + 2*0.50*828 = 1328 mm
L' = L + 2*k*d
L' = 700 + 2*0.50*828 = 1528 mm
Punching shear force = 4959.2-991.8=3967.4kN
punching shear stress = 10^3*3967.37/((2*1328+2*1528)*828)= 0.84
8/11/2019 Pile Report
7/14
Check for the case if the critical section occurs at 1.0d from column face
Enhancement shear multiplier, esm = 1.5
Enhanced shear factor = Max(esm/k, 1)= Max(1.5/1.00,1) = 1.50
Enhanced shear capacity, vc' = vc enchanced shear factor = 0.48 1.50 = 0.72 N/mm
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate Pile
Load Inside the
Critical
Diagonal Zone
(kN)
1 -849 -849 991.8 991.82 -849 849 991.8 991.8
3 0 0 991.8 991.8
4 849 -849 991.8 991.8
5 849 849 991.8 991.8
Sum 4959.2 4959.2
k = 1.00
The dimension of the effective critical section
B' = B + 2*k*d
B' = 500 + 2*1.00*828 = 2155 mm
L' = L + 2*k*d
L' = 700 + 2*1.00*828 = 2355 mm
Punching shear force = 4959.2-4959.2=0.0kN
punching shear stress = 10^3*0.00/((2*2155+2*2355)*828)= 0.00
8/11/2019 Pile Report
8/14
The most critical section is checked at 0.75d
Check for the case if the critical section occurs at 0.75d from column faceEnhancement shear multiplier, esm = 1.5
Enhanced shear factor = Max(esm/k, 1)= Max(1.5/0.75,1) = 2.00
Enhanced shear capacity, vc' = vc enchanced shear factor = 0.48 2.00 = 0.96 N/mm
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate Pile
Load Inside the
Critical
Diagonal Zone
(kN)1 -849 -849 991.8 0.0
2 -849 849 991.8 0.0
3 0 0 991.8 991.8
4 849 -849 991.8 0.0
5 849 849 991.8 0.0
Sum 4959.2 991.8
k = 0.75
The dimension of the effective critical section
B' = B + 2*k*d
B' = 500 + 2*0.75*828 = 1742 mm
L' = L + 2*k*d
L' = 700 + 2*0.75*828 = 1942 mm
Punching shear force = 4959.2-991.8=3967.4kN
punching shear stress = 10^3*3967.37/((2*1742+2*1942)*828)= 0.65
8/11/2019 Pile Report
9/14
Check for Ultimate Shear
shear stress = Ultimate axial load/(ColPerimeter*d)
8/11/2019 Pile Report
10/14
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate pile
load at one side
of the slab (kN)
1 -849 -849 991.8 0.0
2 -849 849 991.8 0.0
3 0 0 991.8 0.04 849 -849 991.8 0.0
5 849 849 991.8 0.0
Sum 4959.2 0.0
Enhanced shear factor = Max(1.5/k,1) = Max(1.5/1.00,1)=1.50
Enhanced shear capacity, vc' = 0.48 1.50 = 0.72 N/mm
Flexural shear stress = 0.00 1000 / (2400 838) = 0.00 N/mm vc = 0.72 N/mm F lexure Shear Checking Pass!
The f lexur al shear is checked at section, av =1.00d at right porti on of the cap
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate pile
load at one side
of the slab (kN)
1 -849 -849 991.8 0.0
2 -849 849 991.8 0.0
3 0 0 991.8 0.04 849 -849 991.8 0.0
5 849 849 991.8 0.0
Sum 4959.2 0.0
Enhanced shear factor = Max(1.5/k,1) = Max(1.5/1.00,1)=1.50
Enhanced shear capacity, vc' = 0.48 1.50 = 0.72 N/mm
Flexural shear stress = 0.00 1000 / (2400 838) = 0.00 N/mm vc = 0.72 N/mm F lexure Shear Checking Pass!
8/11/2019 Pile Report
11/14
The f lexur al shear i s checked at section, av =1.00d at upper por tion of the cap
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate pile
load at one side
of the slab (kN)
1 -849 -849 991.8 0.0
2 -849 849 991.8 0.0
3 0 0 991.8 0.0
4 849 -849 991.8 0.0
5 849 849 991.8 0.0Sum 4959.2 0.0
Enhanced shear factor = Max(1.5/k,1) = Max(1.5/1.00,1)=1.50
Enhanced shear capacity, vc' = 0.48 1.50 = 0.72 N/mm
Flexural shear stress = 0.00 1000 / (2400 818) = 0.00 N/mm vc = 0.72 N/mm F lexure Shear Checking Pass!
8/11/2019 Pile Report
12/14
The f lexur al shear i s checked at section, av =1.00d at lower porti on of the cap
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate pile
load at one side
of the slab (kN)
1 -849 -849 991.8 0.0
2 -849 849 991.8 0.0
3 0 0 991.8 0.0
4 849 -849 991.8 0.0
5 849 849 991.8 0.0
Sum 4959.2 0.0
Enhanced shear factor = Max(1.5/k,1) = Max(1.5/1.00,1)=1.50
Enhanced shear capacity, vc' = 0.48 1.50 = 0.72 N/mm
Flexural shear stress = 0.00 1000 / (2400 818) = 0.00 N/mm vc = 0.72 N/mmF lexure Shear Checking Pass!
8/11/2019 Pile Report
13/14
The most critical section of the face shear is at 0.70d
The flexural shear is checked at section, av =0.70d at left portion of the cap
Pile NumberCoordinate X
(mm)
Coordinate Y
(mm)
Ultimate Design
Load (kN)
Ultimate pile
load at one side
of the slab (kN)
1 -849 -849 991.8 991.8
2 -849 849 991.8 991.8
3 0 0 991.8 0.0
4 849 -849 991.8 0.0
5 849 849 991.8 0.0Sum 4959.2 1983.7
Enhanced shear factor = Max(1.5/k,1) = Max(1.5/0.70,1)=2.14
Enhanced shear capacity, vc' = 0.48 2.14 = 1.02 N/mm
Flexural shear stress = 1983.68 1000 / (2400 838) = 0.99 N/mm vc = 1.02 N/mm F lexure Shear Checking Pass!
8/11/2019 Pile Report
14/14