31
PUERTOLLANO IGCC: Pilot plant for CO 2 capture and H 2 production Francisco García-Peña Engineering – R&D Director ELCOGAS

Pilot plant for CO capture and H2 production · 421 312 259 327 277 263 335 911 1.391 1.595 1.371 1.293 1.129 1.150 1.130 0 500 1.000 1.500 ... ELCOGAS Environmental Permit ELCOGAS

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • PUERTOLLANO IGCC: Pilot plant for CO2 capture and H2 production

    Francisco García-PeñaEngineering – R&D Director

    ELCOGAS

  • 2

    INDEX

    INTRODUCTION

    R&D INVESTMENT PLAN. Lines

    CO2 capture and H2 co-production pilot plant

  • 3

    INTRODUCTION. The Elcogas company

    Spanish company established in April 1992 to undertake the

    planning, construction, management and operation of

    a 335 MWeISO IGCC plant located in Puertollano (Spain)

    Puertollano IGCC Power Plant

    Repsol YPF Refinery

    ENCASUR (open cast coal mine)

    Enel, SpA4,32%

    Siemens Project Ventures GmbH

    2,53%Hidrocantábrico Explotación de Centrales SAU

    4,32%

    Electricité de France

    International, S.A.31,48%

    Endesa Generación, S.A.

    40,99%

    Krupp Koppers GmbH0,04%

    Iberdrola Generación, S.A.

    12,00%

    Hidroeléctrica del Cantábrico, S.A.

    4,32%

  • 4

    Process description

    Air Separation Unit

    N2 O2

    Compressed air

    Waste N2

    Cooling tower

    Hot combustion gasCondenser

    G

    Flue gas to stack

    SteamHeat Recovery

    Steam Generator

    STEAM TURBINE

    135MWISO

    GAS TURBINE

    200 MWISO

    GGasifier

    SlagSulfur (99.8%)

    Sulfur Recovery

    Quench Gas

    O2Air

    Clean Syngas

    Raw Gas

    Coal - N2

    HP Boiler

    MP Boiler Waterwash

    Coal PetCoke

    Limestone

    Coal

    preparation

    Fly ash

    Claus Gas

    HP Steam

    MP Steam

    FiltrationSulfur

    Removal

    Tail Gas

    Waterto treatment

    Puertollano IGCC power plant description

  • 5

    Power output and emissionsGAS

    TURBINE(MW)

    STEAMTURBINE

    (MW)

    GROSSTOTAL(MW)

    NETTOTAL(MW)

    POWEROUTPUT

    182.3 135.4 317.7 282.7

    GROSS NETEFFICIENCY(LHV) 47.12% 42.2%

    EMISSIONS g/kWh mg/Nm3 (6% Oxygen)SO2 0.07 25NOx 0.40 150

    Particulate 0.02 7.5

    COAL PET COKE FUEL MIX(50:50)Moisture (%w) 11.8 7.00 9.40Ash (%w) 41.10 0.26 20.68C (%w) 36.27 82.21 59.21H (%w) 2.48 3.11 2.80N (%w) 0.81 1.90 1.36O (%w) 6.62 0.02 3.32S (%w) 0.93 5.50 3.21LHV (MJ/kg) 13.10 31.99 22.55

    Main Design Data

    Actual average Design Actual average DesignCO (%) 59.26 61.25 CO (%) 59.30 60.51H2 (%) 21.44 22.33 H2 (%) 21.95 22.08CO2 (%) 2.84 3.70 CO2 (%) 2.41 3.87N2 (%) 13.32 10.50 N2 (%) 14.76 12.5Ar (%) 0.90 1.02 Ar (%) 1.18 1.03

    H2S (%) 0.81 1.01 H2S (ppm) 3 6COS (%) 0.19 0.17 COS (ppm) 9 6

    HCN (ppm) 23 38 HCN (ppm) - 3

    Raw Gas Clean GasRaw and clean gas data

    The design fuel is a mixture 50/50 ofcoal/petcoke

    Puertollano IGCC power plant description

  • 6

    Operational data

    IGCC, NGCC and Total yearly production

    9

    1.1621.527 1.435

    744

    836

    622

    321343

    301 452421 312 259 327

    277263

    335

    911

    1.3911.595

    1.371 1.293 1.129 1.150 1.130

    0

    500

    1.000

    1.500

    2.000

    2.500

    1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

    year

    GW

    hIGCC GWh NGCC GWh

    752

    1,171

    1,5331,712

    1,938

    1,6721,744

    1,550 1,4621,389

    1,489

    1,8031,698

    1st 5 years: Learning curve2003: Major overhaul Gas Turbine findings2004 & 2005: Gas turbine main generation transformer isolation fault2006: Gas turbine major overhaul & candle fly ash filters crisis2007 & 2008: ASU WN2 compressor coupling fault and repair MAN TURBO2010: No operation due to non-profitable electricity price (30-40 days).

  • 7ELCOGAS power plant emissions in NGCC & IGCC modes (2010)

    Natural gas (NGCC)

    Coal gas (IGCC)

    Natural gas (mg/Nm 3 at 6% O2 dry)

    4,229,2

    291,7250,0

    4,212,5

    169,3

    7,9 0,8050

    100150200250300350

    SO2 Particles NOx

    EEC 88/609ELCOGAS Environmental PermitELCOGAS 2010 average

    Coal gas (mg/Nm3 at 6% O2 dry)

    50

    400

    650

    500

    200

    5

    200

    1,0639,3

    116,3

    0100200300

    400500600700

    SO2 NOx Particles

    EU Directive 88/609/EECEU Directive 2001/80/EEC

    ELCOGAS Environmental PermitELCOGAS 2010 average

    Operational data

  • 8

    Note: Net energy variable costs (average 2010)

    Fuel mode FuelConsume (GJPCS)

    Production (GWh)

    Heat rate (GJPCS/GWh)

    Fuel cost (€/GJPCS)

    Partial cost (€/MWh)

    Total cost (€/MWh)

    GT Natural gas 68.777 3,79 18.150 8,12 147,43 147,43

    NGCC Natural gas 84.005 8,38 10.021 8,12 81,40 81,40

    NGCC + ASU Natural gas 1.725.092 153,19 11.261 8,12 91,48 91,48

    Natural gas 616.828 10.467 8,12 85,03

    Coal 145.769 2.474 3,39 8,37

    Petocke 455.056 7.722 2,34 18,06

    NG auxiliar consumption 265.814 218 8,12 1,77

    Coal 2.914.823 2.390 3,39 8,09

    Petocke 9.104.375 7.465 2,34 17,46

    IGCC 1.219,61 27,32

    NGCC+ASU+Gasifier (by flare)

    58,93 111,46

    Costs

    Operational data

  • 9

    CO2 emission reduction using fossil fuels

    H2 production by gasification of fossil fuels

    DIVERSIFICATION of raw fuels and products

    Other ENVIRONMENTAL improvements

    IGCC processes OPTIMISATION

    DISSEMINATION of results

    BASIS of the PUERTOLLANO IGCC R&D PLAN

    Based on the opportunity that an IGCC plant represents

    Contribution can be relevant in:

    -- climate change mitigation

    -- energy supply reliability

    MAIN LINES OF THE R&D PLAN

    R&D INVESTMENT PLAN. Lines

  • 10

    Battery of co-gasification tests undertaken with olive oil waste (orujillo)

    Test Month/Year

    orujillo dosage ratio in weight%

    orujillo tonnes (t)

    Test duratio

    n (h)2007- 2009 1 -2 % 1.572,84 800,3

    2008 4 % 652,14 154March 2009 6 % 395,86 64,4June 2009 8 % 383,90 46Sept. 2009 10 % 656,68 62

    TOTAL 3.661,42 1.126,7

    Diversification of raw fuels and products. Biomass co-gasification

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    14/0

    6/20

    09 7

    :12

    14/0

    6/20

    09 1

    2:00

    14/0

    6/20

    09 1

    6:48

    14/0

    6/20

    09 2

    1:36

    15/0

    6/20

    09 2

    :24

    15/0

    6/20

    09 7

    :12

    15/0

    6/20

    09 1

    2:00

    15/0

    6/20

    09 1

    6:48

    15/0

    6/20

    09 2

    1:36

    16/0

    6/20

    09 2

    :24

    16/0

    6/20

    09 7

    :12

    16/0

    6/20

    09 1

    2:00

    16/0

    6/20

    09 1

    6:48

    16/0

    6/20

    09 2

    1:36

    17/0

    6/20

    09 2

    :24

    17/0

    6/20

    09 7

    :12

    17/0

    6/20

    09 1

    2:00

    17/0

    6/20

    09 1

    6:48

    17/0

    6/20

    09 2

    1:36

    18/0

    6/20

    09 2

    :24

    18/0

    6/20

    09 7

    :12

    18/0

    6/20

    09 1

    2:00

    18/0

    6/20

    09 1

    6:48

    18/0

    6/20

    09 2

    1:36

    19/0

    6/20

    09 2

    :24

    19/0

    6/20

    09 7

    :12

    19/0

    6/20

    09 1

    2:00

    19/0

    6/20

    09 1

    6:48

    19/0

    6/20

    09 2

    1:36

    20/0

    6/20

    09 2

    :24

    20/0

    6/20

    09 7

    :12

    20/0

    6/20

    09 1

    2:00

    20/0

    6/20

    09 1

    6:48

    %

    0

    20.000

    40.000

    60.000

    80.000

    100.000

    120.000

    140.000

    160.000

    180.000

    200.000

    Nm

    3/hCO clean gas (%)

    H2 clean gas (%)

    % Orujillo

    clean gas flow (%)

    gasifer load (%)

    Load during %8 olive oil waste

    co-gasification test

    Biomass selection criteria:

    Size < 25 mmHumidity < 12 %Price < 150 €/tAvailability in large quantities Critical parameter forthe biomass selection

    was the behavior on the ELCOGAS grinding system.

    Olive oil waste storage area

    R&D INVESTMENT PLAN. Lines

  • 11

    Step 1: Syngas production from Gasification

    Fly ash Char Cl-

    CN-

    SH2 COS CO2 N2 …

    Carbon compound + O2 + H2O CO + H2 + Impurities400-1600ºC10-40 bar

    GASIFICATIONCO2 CAPTURE &

    H2PURIFICATION PROCESS

    SECONDARY PRODUCTION H2:

    WATER-GAS REACTION

    PREPARATIONCO2

    H2

    Step 3: “Shifting” or water-gas reaction

    Step 4: H2 and CO2 separation H2 CO2&

    CO + H2O CO2 + H2

    Step 2:Conditioning fly ash removal, particles and sulphur comp.

    CO2 capture using pre-combustion technology involves H2 generation

    CO2 capture and H2 production (pre-combustion)R&D INVESTMENT PLAN. Lines

  • To demonstrate the feasibility of capture of CO2 and production of H2 in an IGCC that usessolid fossil fuels and wastes as main feedstock.

    To obtain economic data enough to scale it to the full Puertollano IGCC capacity insynthetic gas production.

    TARGETS

    Project of pilot plant in an existing IGCC of Puertollano (pre-combustion technology)is part of a Spanish national initiative, “Advanced technologies of CO2 conversion, captureand storage” and it is coordinated with other related projects:

    Project # 2 is to explore oxyfuel combustion to be applied in the construction of a pilotplant (20-30 MW) to be built in El Bierzo, NW of Spain. CIUDEN

    Project # 3 is to study and regulate geological storage in Spain. IGME

    Project # 4 is to study public awareness of CCS technologies. CIEMAT

    PARTICIPANTS & BUDGETELCOGAS – UCLM – Ciemat – INCAR CSIC 14.5 M€ (initially 18.5 M€)

    COORDINATION

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 13

    Puertollano IGCC power plant and pilot plant location

    PRENFLO Gasifier

    Coal preparation

    Sulphur Recovery

    Combined Cycle

    New CO2capture pilot

    plant

    ASU

    Pilot plant general view

    IGCC power plant general view

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 14

    Pilot plant diagram process

    CLEAN GAS2% of total flow (3,600 Nm3/h)

    22,6 bar130ºC

    60,5 %CO22,1% H2

    Tail gas1,3 bar

    MP STEAMSHIFT Reactor CO2 & H2

    separation(Chemical, aMDEA)

    CO + H2O → CO2 + H2PIL

    OT

    PLA

    NT

    40%

    CO2¿H2S?100 t/d

    Raw H2 (80% of purity)

    H2 rich gas 37,5 % CO250,0 % H23,0 % CO

    HYDROGENPURIFICATION

    (PSA)

    COMBINED CYCLE

    COAL + COKE

    GASIFICATIONRaw gas FILTRATION

    SYSTEM

    Clean gas PURIFICATION

    & DESULPHURATION

    183.000 Nm3/h

    Recycle compressor

    Pilot plant size: 1:50 ~ 14 MWtPure H2 (2 t/d)

    99,99% H2 @ 15 bar

    /Acid)(Sweet

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 1515

    Shifting unit

    1

    2

    Shifting Unit (several suppliers):1. Desulphurization reactor2. Shifting reactors3. Heat exchangers: kettles

    and shell&tube

    CO2 Capture Unit

    CO2 Capture Unit (Linde Caloric):1. Syngas absober – 12 m2. CO2 stripper – 16.5 m

    1

    2

    PSA Unit

    2

    PSA Unit (Linde):1. Adsobers – 6.5 m2. Tail gas drum – 12.5 m3. Valve skid

    Electrical and control building

    3

    3

    2

    1

    Electrical/control building:1. Control room2. Electrical room

    1

    Pilot plant diagram process:3D view

  • 16

    Empresarios AgrupadosLinde-CaloricLindeConstrucciones Ocaña-CañasZeus ControlTécnicas ReunidasTécnicas Reunidas y Boreal-VilaJohnson MattheySidsa y CuñadoSAMSON, Tyco Valves and Controls y SAIDIGE PowerABB Process Automation DivisionHGL y MASAMEISA

    Construction permit: December 2008Commissioning: May-October 20101st CO2 t captured: 13 September 2010End of sweet capture tests: February 2011End of programmed tests (within PSE-CO2): June 2011

    Main suppliers

    Mile

    ston

    es

    EngineeringCO2 UnitPSA Unit

    Civil workControl

    ReactorsHeat exchangers

    CatalystsPiping and fitting

    ValvesElectrical components

    On-line analysis systemMechanical erection

    Electrical I&C erection

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 17

    Shifting unit

    Coal gas

    IP saturated steam to feed

    N2 (start-up)

    IP steam

    Desulphuration reactor

    Shifting rectors

    General view of Shifting Unit

    Flow kg/h

    Pbar

    TºC

    CO%

    H2%

    CO2%

    H2O%

    H2S%

    COS%

    Coal gasSweet 3,677 19.8 126 60.45 21.95 2.66 0.29 0.0 0.0

    Sour 3,999 23.6 138 53.72 19.57 2.70 10.40 0,70 0,11

    Shifted gas to separation unit

    Sweet 8,732 17.3 274 1.68 28.37 21.34 43.26 0.0 0.0

    Sour 8,705 21.1 277 1.40 28.39 21.53 42.73 0.74 0.0

    IP saturated steam to feed

    Sweet 5,055 34.0 243 0.0 0.0 0.0 100 0.0 0.0

    Sour 4,706 34.0 243 0.0 0.0 0.0 100 0.0 0.0

    Pilot plant diagram process (I)

    Pre-heater

    SHIFTED GAS TO SEPARATION UNIT

  • 18

    Separation unit

    Flow kg/h Pbar

    TºC

    CO%

    H2%

    CO2%

    H2O%

    H2S%

    COS%

    Shifted gas to absorber

    Sweet 5,318 15.9 45 2.9 49.7 37.3 0.7 0.0 0.0

    Sour 5,318 19.7 45 2.46 49.7 37.69 0.62 0.51 0.0

    Process condensated

    Sweet 3,414 15.9 45 0.0 0.0 0.0 100 0.0 0.0

    Sour 3,387 19.7 45 0.0 0.0 0.0 100 0.0 0.0

    CO2 productSweet 4,185 1.5 40 0 0.18 95.32 4.47 0.0 0.0

    Sour 4,295.5 1.55 40 0.01 0.21 94.02 4.47 1.27 0.0

    H2 to PSASweet 481.7 15.2 40 4.63 79.37 0.5 0.48 0.0 0.0

    Sour 457.3 19.1 40 4.02 80.44 0.5 0.39 0.0001 0.0

    Rich H2 gasSweet 1,190.1 15.6 40 4.63 79.37 0.5 0.48 0.0 0.0

    Sour 1,135.2 19.4 40 4.02 80.44 0.5 0.39 0.0001 0.0

    LP Steam to reboiler

    Sweet 4,763 4.1 144 0.0 0.0 0.0 100 0.0 0.0

    Sour 4,797 4.1 144 0.0 0.0 0.0 100 0.0 0.0

    General view of Separation Unit

    Pilot plant diagram process (II)

    YCO2 product Rich H2 gasLP steam

    Y 40 %60 %

    LP steam to reboiler

    H2 to PSA

    From shifting unit

    Cooling stage

    Absorber

    CO2Stripper

    CO2 separator

    Syngas separator

    Cond. Separator

    Process Cond.

    Shiftedgas

  • 19

    PSA unit

    General view of PSA unit

    Flow Nm3/h

    Pbar

    TºC

    CO%

    H2%

    CO2%

    H2S%

    COS%

    H2 from separation unit

    Sweet 1,431 15.2 40 4.63 79.37 0.5 0.0 0.0

    Sour 1,412 19.1 40 4.02 80.44 0.5 0.0001 0.0

    H2 productSweet 795 14.7 43 0.0004 99.99 0.0001 0.0 0.0

    Sour 795.1 18.6 43 0.0004 99.99 0.0001 0.0 0.0

    Tail gasSweet 636 1.3 35.9 10.42 53.58 1.13 0.0 0.0

    Sour 616.9 1.3 35.7 9.2 55.23 1.14 0.0002 0.0

    Rich H2 gas (40 % flow)

    Tail gas

    H2 product

    Adsorbers

    H2 fromseparation unit

    Tail gas drum

    Pilot plant diagram process (III)

  • 20

    Comparative : sweet vs sour (design data)

    Sweet Sour

    Global(shifting+amines)

    C.G.E s+a 88,5 % 88,2 %

    Thermal efficiency s+a 60,2 % 62,5 %

    CO2 recovery 91,7 % 93,6 %

  • 21

    Block diagram. Control flexibility

    CO2Syngas FC PC

    FC

    Shifting CO2

    PSA

    H2

    FlareTail gas

    Flare

    Pure H2

    FlarePC

    PC

    Flare

    PC

    Flare

    PC

    N2FCPC

  • 22

    Some Test results

    41

    41,5

    42

    42,5

    43

    43,5

    44

    1,1 1,2 1,3 1,4 1,5 1,6

    vapor/gas rate

    CO

    2 co

    mpo

    sitio

    n(%

    )

    9595,295,495,695,89696,296,496,696,89797,2

    Tot

    al C

    O c

    onve

    rsio

    n (%

    )

    CO2 composition

    Total COconversion (%)

    0123456789

    10

    75 80 85 90 95 100 105 110

    T desorción (ºC)

    % F

    uga

    CO

    2

    0,0

    0,2

    0,4

    0,6

    0,8

    1,0

    % F

    uga

    H2

    Fuga CO2 Fuga H2CO2 leak H2 leak

    % C

    O2

    leak

    % H

    2le

    ak

    Desortion T (ºC)

    Shifting:

    Coversion rate has to be reconsidered!

    CO2-H2 separation:

    Desortion temperature can be optimised

  • 23

    Test results

    UNIT START

  • 24

    SHIFTING UNIT CONVERSION / TEMPERATURE (SWEET)

    0,0

    5,0

    10,0

    15,0

    20,0

    300 350 400 450 500 550 600

    Temperature(ºC)

    CO (%

    )

    Johnson Matthey Selection High temperature Fresh Potential (Johnson Matthey) Potential (High temperature)

    20/01/11 17:24-28:35

    JM simulation (01/10/10)

    Real values(SWEET3 test)

    JM - Fresh catalyst

    FIRST REACTOR

    SECOND REACTOR

    STEAM GENERATOR

    Conversion very close to theoric, although higher reactor outlet temperature.

    The high conversion obtained in the first step (near 95%) will make considering a shifting process only with one step.

    PSE-CO2 project : CO2 Capture Pilot Plant

    The inlet second reactor temperature is higher than expected

  • 25

    Expected vs. obtained compositions of main streams (SWEET)

    i) All compositions are in % vol. (dry basis)ii) Analysis carried out by ELCOGAS Laboratory

    Comparison of sweet & sour catalysts: sweet tests up to Feb 2011, sour tests up to June 2011

    Optimization of steam/gas ratio at shifting unit

    Optimization of energy balance

    Real costs of CO2 capture and H2 production.

    CO2 capture & H2 co-production pilot plant. Tests

    Shifted gas CO2 H2 rich gas Pure H2

    Design Lab Analysis Design Lab Analysis DesignLab

    AnalysisE

    Design Lab Analysis

    H2 50.05 51.88 0.19 0.314 - 1.31 79.75 82.3 – 83.14 99.99 99.959- 99.995CO 2.92 1.85 0 0.053 - 0.07 4.65 2.86 - 3.78 4 ppm N/ACO

    237.56 37.36 99.78 98.2 - 99.622 0.5 0.02 - 0.82 1 ppm N/A

    N2 8.76 8.30 0.01 0.05 - 0.28 13.97 12.2 - 13.6 15 ppm 4 - 17 ppm

    Ar 0.71 0.60 0.02 0.01 - 0.09 1.13 0.89 - 0.97 80 ppm 3 - 14 ppm

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 26

    The main learning in project phase:● The finance delay: MICINN (Spanish Science & Research Minister) and JCCM(Regional Government). Delay in main equipment supply: more than 12-14 months. Detailed engineering: conditioned by suppliers. PP construction step: delay due to safety permits since it is installed in an operatingplant. Delay of commissioning: low availability of experimented personnel.

    The main learning in commissioning & operation phases:● Investment costs: € 13 million● Unexpected reactivity: 95% CO conversion in first step of shifting unit

    Estimated: 85% consider a shifting process with only one step.● CO2 and H2 design specifications: easily achieved● CO2 capture rate: 91.7%● Auxiliary consumption: lower than estimated in design● Integration of O&M in the existing IGCC: very easy

    CO2 > 99 %H2 pure > 99.995 %

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 27

    CO2 Capture Costs Comparison

    1) Scaled up 100% Puertollano IGCC synthetic gas from the 14MWt pilot plant.2) Existing plant capture cost = f (investment costs and operational costs).

    3) First ELCOGAS estimations show values of 25-30 €/ t CO24) Comparing to other studies

    tonnesCO CapturedOPEXCAPEXCO€/t cost, capture CO2

    22

    Fuente: DOE/NETL CCS RD&D ROADMAP December 2010

    30 forELCOGAS

    retrofit

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 28

    1015202530354045505560

    27 28 29 30 31 32 33 34 35 36 37

    IGCC plant efficiency w ith CO2 capture, %

    CO

    2 co

    st, €

    /t C

    O2

    3.000 h

    3.500 h

    4.000 h

    4.500 h

    5.000 h

    5.500 h

    6.000 h

    6.500 h

    7.000 h

    7.500 h

    CO2 Capture Costs (SWEET). As IGCC retrofit

    PSE-CO2 project : CO2 Capture Pilot Plant

    100 %Treated gas

    33 %Net efficiency of power plant with CO2 capture

    40 €/MWhElectricity price

    0.92 Average load factor

    6,500 hOperating hours (IGCC mode)

    0.75Scale factor

    0.5 %Bank fee

    3.0 %Bank interest

    25 Expected life

    Data Variables

    100 %Treated gas

    33 %Net efficiency of power plant with CO2 capture

    40 €/MWhElectricity price

    0.92 Average load factor

    6,500 hOperating hours (IGCC mode)

    0.75Scale factor

    0.5 %Bank fee

    3.0 %Bank interest

    25 Expected life

    Data Variables

  • 29

    Minimum H2 prices depending on electricity price

    0

    1

    2

    3

    4

    5

    6

    0 50 100 150€/MWh

    €/Kg

    60.000 Kg/y 720h

    120.000 Kg/y 1440 h

    180.000 Kg/y 2160 h

    420.000 Kg/y 5040 h

    90.000 Kg/y 1080 h

    Better to sell H2

    Better to sell electricity

    Minimum H2 price per fix cost of production (external personal and spares) depending on anual production hours.

    Minimum pure H2 price depending on the electricity price

    PSE-CO2 project : CO2 Capture Pilot Plant

  • 30

    Pilot plant for CO2 capture and production of H2 and electricity with IGCC technology

    Other activities: To be done after PSE as R&D platform: Water shift reaction catalyst optimization. Tests of

    different catalyst

    New processes to separate CO2-H2 CO2 different treatment processes

    Improvement of integration efficiency between CO2separation processes and IGCC plant

    ELCOGAS offers both the Puertollano IGCC and the Pilot Plant for CO2 capture and H2 production as

    technical platforms to develop of process, equipments, components, or even pre-engineering of new plants

    with CCS and Zero emissions

    Pilot Plant beyond PSE project

  • Francisco García-PeñaEngineering – R&D Director

    ELCOGAS [email protected]

    Thank you for your attention