42
PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA April Winklmann Authority Manager, MTJMA Jared Hutchins Engineering Manager, Black & Veatch

PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

PIONEERING PELLET

SOFTENING TREATMENT

IN PENNSYLVANIA

April Winklmann Authority Manager, MTJMA

Jared Hutchins Engineering Manager, Black & Veatch

Page 2: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Project Background and Drivers

Process Equipment Procurement and Facility

Design

Construction Update

AGENDA

2

Page 3: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

AUTHORITY MANAGER, MTJMA

APRIL WINKLMANN

PROJECT

BACKGROUND AND

DRIVERS

3

Page 4: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Armstrong County, PA

• 5 staff

• Customers: Manor Township,

Manorville Borough, and Ford Cliff

Borough, as well as some areas of

Rayburn, Bethel, Valley, and

Kittanning Townships

• +2 Consecutive Systems

4

Manor Township Joint Municipal Authority (MTJMA)

Page 5: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA
Page 6: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Brine discharge from current ion exchange process to be discontinued

• Lack of redundancy at existing WTP

• No clearwell at existing WTP

• Aging WTP infrastructure

• Limited ability to expand for future demand

• Additional demand by consecutive systems

Black & Veatch 6

Project Drivers

Page 7: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• April Winklmann hired as MTJMA Manager in 2012

• Prior investigation of process for manganese removal

• Recommended the process be investigated for calcium hardness

• Pilot Study in 2012

• Double blind taste test

• RFP for Engineering Services

• Open communications with PADEP

Black & Veatch 7

Pellet Softening Enters the Picture

Page 8: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Technology Evaluation by Black &

Veatch in 2014

• Proven technology capable of

meeting performance requirements

• Pool of qualified vendors

Technology Evaluation

Pellet Softening Technology Recommended for Detailed Design

8

Page 9: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Condition of existing plant

• New consecutive system being built simultaneously

• Timing of changes from old plant to new plant and well pump selections

Black & Veatch 9

Challenges - Timing

Page 10: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Limited space at existing WTP

• Three of four wells at WTP site

• Residential setting

• Soil conditions

• Varied size of pellet softening equipment

Black & Veatch 10

Challenges – Facility Space & Existing Conditions

Page 11: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Anticipated rate increases

• PennVest Loan

• ~$8.5M, Project at over $9M

Challenges – Budget

Black & Veatch 11

Page 12: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Taste is important!

• Resistance to chemical usage

• Clearwell, wet well, pumping modification

• Cost and rates

Black & Veatch 12

Challenges – Board Acceptance

Page 13: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Previously unseen technology for veteran employees

• Young staff, still gaining experience

• Limited training/coursework availability

Black & Veatch 13

Challenges – Staff & Technology

Page 14: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Ability to start and stop operations

• Caustic injection point

• Lime requirement from pilot would have changed outcome

• High freezing points for caustic and sulfuric acid

• Recarbonation vs. sulfuric acid

• Gravity vs. pressure filter

Black & Veatch 14

Challenges – Other

Page 15: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

ENGINEERING MANAGER, BLACK & VEATCH

JARED HUTCHINS

PROCESS

EQUIPMENT

PROCUREMENT &

FACILITY DESIGN

15

Page 16: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

16

Average Day Maximum Day

Current 0.6 MGD 1.3 MGD

Design 0.6 MGD 1.4 MGD

Future 1.4 MGD 2.1 MGD

Black & Veatch

WTP Design Flows and Anticipated Raw Water Quality

Parameter Average Range

pH (standard units) 7.5 7.3 – 7.6

Alkalinity (mg/L as CaCO3) 115 90 - 150

Calcium Hardness (mg/L as CaCO3) 160 110 - 200

Total Hardness (mg/L as CaCO3) 210 130 - 280

Iron (mg/L) 0.25 <0.02 – 1.97

Manganese (mg/L) <0.02 <0.02 – 0.04

Page 17: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• 1.4 MGD initial capacity

• Expandable to 2.1 MGD

• New facility located adjacent to

existing WTP

• Raw water feed from four existing

wells

Basis of Design

17

Page 18: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

18 Black & Veatch

Procured Equipment

Process Schematic

WELL

PUMPS REACTOR

FILTER CLEARWELL

BACKWASH

PUMPS

HIGH

SERVICE

PUMPS PELLET

DISCHARGE

SODIUM

HYPOCHLORITE

SPENT FILTER

BACKWASH

SAND &

SODIUM

HYDROXIDE

SULFURIC ACID

Page 19: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• STSFE

• Conical Pellet Softening

Reactors

• Horizontal Enclosed Filters

• Ancillaries, Controls

• Pump Units

Equipment Procurement

19

Startup, Commissioning & Training Support, Performance

Page 20: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

20 Black & Veatch

Site

Location

Page 21: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Black & Veatch 21

Site

Plan

Page 22: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Black & Veatch

Process Layout

22

Page 23: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Black & Veatch

Building Configuration

23

Page 24: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• 0.7 MGD per unit

• 2 units, space for a third

• 8.5 ft diameter

• 24.5 ft in height

Pellet Softening Reactors

Supplied by WesTech

24

OUTLET & OVERFLOW (BACKSIDE)

CATALYST BED

CHEM FEED

SAMPLE PORTS

Page 25: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• 2 filter cells per vessel

• 2 vessels installed initially, space for

future third

• Two vessels rated for 1.4 MGD

with one cell in standby

• Dual medial with anthracite and

sand

Filter Vessels

Supplied by WesTech

25

Page 26: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Seed material for pellet generation

• Fine silica sand

• Initial loading, then periodic

recharge after blowdown

• Sand slurry injection with plant

service water

Sand Feed

Vertical Reciprocating Conveyor promotes sand recharge from top

26

Page 27: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Caustic, Sulfuric Acid by STSFE

Supplier

• Sodium Hypochlorite Feed System

• Provisions for chemical deliveries

• Chemical pipe flushing

• Containment drains

Chemical Feed Systems

27

Page 28: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Slurry discharge to Indoor Pellet

Drainage Area

• Discharge based on operational

experience

• Discharge pellets for reuse in

agricultural applications

Pellet Discharge

28

Page 29: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Backwash Holding Tank

• Gravity setting

• Pumps recycle up to 10% of

process flow to head of WTP

• 31,200 gallon capacity

• 1.65 to 3.34 backwash cycles

Filter Backwash

29

Page 30: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Two independent clearwells and

wet well providing ~300,000 gal

• 12.5% concentration sodium

hypochlorite delivered by PD

peristaltic tube pumps

Disinfection

30

Page 31: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

AUTHORITY MANAGER, MTJMA

APRIL WINKLMANN

CONSTRUCTION

UPDATE

31

Page 32: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• General – Thomas Construction, Inc.

• HVAC – East West Manufacturing

• Plumbing – Enders Plumbing, Inc.

• Electrical – Bronder Technical Solutions

• MTJMA – Owner/Inspector

• Black & Veatch – Construction Administration

Total Construction Contract Award $8.4M Black & Veatch

32

Construction Team

Page 33: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• Notice of Award – 2/18/16

• Construction NTP – 4/11/16

• Substantial Completion – 7/14/2017

• Final Completion – 8/14/2017

Construction Schedule

33

Page 34: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Pellet Softening and

Filtration Process Areas

Page 35: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Backwash Holding Tank

Page 36: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Pellet Softening Reactors

Set

Page 37: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Filter Units and Piping

Page 38: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Backwash Pumps

Page 39: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

PEMB In Progress

Page 40: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

• PEMB Installation – April 2017

• New Well Pumps – May 2017

• New Plant Startup and

Commissioning – Aug/Sept 2017

• New Plant Online – Sept 2017

Upcoming Milestones

40

Page 41: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Learn more at bv.com.

Contact Us

April Winklmann | Authority Manager

2310 Pleasant View Dr., Ford City, PA 16226

P: +1 724-763-2511

E: [email protected]

W: www.mtjma.com

Jared Hutchins | Engineering Manager

4555 Lake Forest Dr., Ste. 310, Cincinnati, OH 45242

P: +1 513-936-5137

E: [email protected]

Page 42: PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

Learn more at bv.com.