PIPING & FITTINGS: Y/N
All welding is complete
Piping schedule, material and size is correct
Piping is in proper location
Piping has required clearances
Fittings have correct ratings and are proper material
Installation is straight and plumb or sloped per drawing
Reducer orientation is correct
Cold spring is per drawing
VALVES:
Check all valve tags for compliance with piping and material specifications
Assure control, globe, angle and check valves have correct flow direction
Valves should be in open position
Direction of handles should be per ISO
All vents and drains are installed including those required for testing
SUPPORTS, GUIDES & ANCHORS:
Properly installed per details
All temporary erection supports have been removed
Spring hangers chocked against movement
Small bore supports installed per specification, in sufficient quantities and on location
INSTRUMENTATION:
Connections for instruments installed and isolated as required
Orifice flange tap valves at correct angles, seal welded and jack screws in place
Orifice flanges have correct meter runs, smooth bores; orifice plates removed
All thermowells installed
All reinforcing pads have weep holes
BOLTS:
Proper material and grade of bolt and nut installed
Proper diameter and length installed
Valves should be in open position
Thread compound applied per Project requirements
GASKETS:
Proper type and material installed per piping material specifications
Sized to match flange rating and fills bolt circle
PIPING SPECIALTY ITEMS:
Verify direction of flow for filters, strainers, traps and expansion joints
Expansion joints have stops installed
All blinds are sized correctly and installed as required by the drawing
MECHANICAL EQUIPMENT:
All equipment not included in test has been isolated / removed
J&L Rep.
Test Package# F-004
1 OF 1