7 1 2 3 4 5 6 8 9 11 12 13 10 Survey and Staking Months ahead of construction, field crews conduct civil, cultural and environmental surveys along the proposed pipeline route, or right-of-way. A final route is then selected and marked with stakes. 1 Right-of-Way Grading In cultivated areas, the topsoil along the right-of-way is stripped by bulldozer and stored in piles for careful replacement later. 3 Stringing Pipe Crews re-stake the final route of the pipeline and lay out or "string" sections of the pipe in a single line within the right-of-way. 4 Bending Pipe Crews bend the pipe to follow the contours of the land and weld the pipe sections together. 5 Lowering Pipe into Trench The pipe is surveyed and laid within prepared trench bottom. 10 Final Coating and Inspection The pipe coating is inspected one more time. 9 Backfill and Rough Grade The trench is then backfilled with subsoil (and separated topsoil). 11 Testing Final Tie-In Before operation, water is used to test the pressure of the line and ensure the structural integrity of the pipe and welds. 12 Final Clean-Up and Restoration Final grading is performed and topsoil is spread over work area. Right-of-way is restored to pre-construction contours and reseeded with native species. 13 Front-End Clearing Crews prepare for construction by removing trees and grading the soil within the right-of-way and temporary workspace areas. 2 Trenching Backhoes or wheel ditchers are used to dig a trench. 7 Soil Separation In agricultural areas, careful attention is paid to properly separating and storing the topsoil and subsoil so they do not mix. 8 Line-Up, Initial Weld These pipes are already coated to prevent corrosion. The integrity of the weld is inspected, and the weld joint is coated. 6 Note: These illustrations are conceptual and general in nature; specific sites, processes and equipment vary. TYPICAL PIPELINE CONSTRUCTION SEQUENCE energytransfer.com Updated 1-23-18 ETP Pipeline Facts on @ ETPfacts on Energy Transfer on

Pipeline Construction Sequence 1-23-18 [8.5x11] · Months ahead of construction, field crews conduct civil, cultural and environmental surveys along the proposed pipeline route, or

  • Upload
    others

  • View
    13

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Pipeline Construction Sequence 1-23-18 [8.5x11] · Months ahead of construction, field crews conduct civil, cultural and environmental surveys along the proposed pipeline route, or

7

12

3

4

5

6

8

9

11

12

13

10

Survey and StakingMonths ahead of construction, field crews conduct civil, cultural and environmental surveys along the proposed pipeline route, or right-of-way. A final route is then selected and marked with stakes.

1

Right-of-Way GradingIn cultivated areas, the topsoil along the right-of-way is stripped by bulldozer and stored in piles for careful replacement later.

3

Stringing Pipe Crews re-stake the final route of the pipeline and lay out or "string" sections of the pipe in a single line within the right-of-way.

4

Bending PipeCrews bend the pipe to follow the contours of the land and weld the pipe sections together.

5

Lowering Pipe into TrenchThe pipe is surveyed and laid within prepared trench bottom.10

Final Coating and InspectionThe pipe coating is inspected one more time.9

Backfill and Rough GradeThe trench is then backfilled with subsoil (and separated topsoil).11

Testing Final Tie-InBefore operation, water is used to test the pressure of the line and ensure the structural integrity of the pipe and welds.

12

Final Clean-Up and RestorationFinal grading is performed and topsoil is spread over work area. Right-of-way is restored to pre-construction contours and reseeded with native species.

13

Front-End ClearingCrews prepare for construction by removing trees and grading the soil within the right-of-way and temporary workspace areas.

2

TrenchingBackhoes or wheel ditchers are used to dig a trench.

7

Soil SeparationIn agricultural areas, careful attention is paid to properly separating and storing the topsoil and subsoil so they do not mix.

8

Line-Up, Initial WeldThese pipes are already coated to prevent corrosion. The integrity of the weld is inspected, and the weld joint is coated.

6

Note: These illustrations are conceptual and general in nature; specific sites, processes and equipment vary.

TYPICAL PIPELINE CONSTRUCTION SEQUENCE