18th-June-08

PIPELINE REPAIR AT KP 110 – KP 133 KUALA TUNGKAL TO PANARAN TGI OFFSHORE PIPELINE

Page 2: Pipeline Repair Project FEED 2

FEED Handover Meeting Agenda

1. Project Introduction

2. Project Status

3. MTO

4. Procurement & Installation Specifications

5. MR’s

6. TBE/Table of Compliance

7. Procurement Status

8. Discussion and Close out

Page 3: Pipeline Repair Project FEED 2

Project Introduction

KP 133.5

KP 110.5

Page 4: Pipeline Repair Project FEED 2

Project Introduction

Details of Damaged Section (KP110.5 to KP133.5) • Total of 19 buckles along the damaged section

• Maximum deformation of buckle – 7.59% of OD

• Water depth at damaged section – 35m

Page 5: Pipeline Repair Project FEED 2

Design Basis of Replacement Pipeline

DESCRIPTION UNIT PARAMETERS

Approximate Length km Approximately 23.0

Pipeline OD mm 711.2 (28”)

Material - Carbon Steel

Line Pipe Specification - API 5L X65, manufactured to DNV OS-F101

Pipeline Wall Thickness mm 15.9 (.625”)

Service - Dry Sales Gas

Pipeline Corrosion Allowance mm 0.0

Internal Coating - 80 micron DFT Epoxy Coating

External Corrosion Coating - 3 Layer PE

External Corrosion Coating Thickness mm 2.1

Concrete Weight Coating Thickness mm 94

Design Pressure Barg 113.8 (1650 psig)

Operating Temperature °C 40.6

Hydrotest Pressure Barg 136.7 (1983 psig)

Maximum Operating Pressure Barg 103.4 (1500 psig)

Product Density Kg/m3 63.0

Pressure Rating of Pipeline Components - ANSI Class 900

Page 6: Pipeline Repair Project FEED 2

FEED OBJECTIVES

Engineer a feasible repair method that can be executed by available installation contractors in the region

Develop a method based on use of industry proven equipment and procedures

Review the method with potential EPCC contractors to get feedback on their construction risks.

Develop a method which offers no or minimum stoppage of Gas to the consumers

Develop a method which enables restoring the gas flow to the full design pressure as early as possible

Conduct risk work shop and identify risks that should be managed by PMT

Identify long lead items for procurement so that repair work can be executed as early as practically possible

Page 7: Pipeline Repair Project FEED 2

Schematic Diagram

Page 8: Pipeline Repair Project FEED 2

MTO for Zero Downtime Method

Hot Tap Tees

Size Material Quantities

28 x 6” ASTM A 694 F65 2

28 x 16” ASTM A 694 F65 2

28 x 28” ASTM A 694 F65 4

28” 5D Hot Induction Bends

28”, 90ºBends API 5L X65 4+1spare 2 for Test bend and WPQT

Mechanical Connectors

28” ASTM A 694 F65 2

Flanges

6” Pressurizing line ASTM A 694 F65 4+1 Swivel type

16” Branch Line ASTM A 694 F65 2+1 WN Flange

4+1 Swivel flange

8+1 Blind flange

Misalignment flange

28” Pipeline ASTM A 694 F65 4+1 WN Flange

6+1 Swivel flange

10+1 Blind flange

2+1 Misalignment flange

28” Pig Launcher/Receiver ASTM A 694 F65 2 Swivel flange

Page 9: Pipeline Repair Project FEED 2

MTO for Zero Downtime Method

Testable Gaskets

Size Material Quantities

28” SS 316 Octagonal 4+1 Kamos Gasket

16” SS 316 Octagonal 4+1 Kamos Gasket

Test Kit SS316 2 Kamos

Weldolets

28 x 4 “ ASTM A 694 F65 / WPHY65 2+1 80XS

28 x 2” ASTM A 694 F65 / WPHY65 2+1 80XS

16 x 4” ASTM A 694 F65 / WPHY65 2+1 80XS

16 x 6” ASTM A 694 F65 / WPHY65 2+1 80XS

Barred Tee

28” x 16” ASTM A 694 F65 / WPHY65 2 Reducing Tee

Elbow

16” ASTM A 694 F65 / WPHY65 4 90º

Subsea Ball Valves

2" Body: A350-LF-2 / A352 LCC

Ball & Seat: A182-F55 with WC coating

Seat Spring: Inconel X750

2 Full Bore, RTJ x Welded End

4" 4 Full Bore, RTJ x Welded End

6” 2 Full Bore, RTJ x Welded End

Page 10: Pipeline Repair Project FEED 2

MTO for Zero Downtime Method

Expanding Gate Valves

Size Material Quantities

16” Body: A350-LF-2 / A352 LCC

Gate & Seat: A182-F55 with WC coating

Seat Spring: Inconel X750

2 Reduced Bore, Welded end.

Through conduit Double Block and Bleed

28” 2 Full Bore, Piggable and welded end

Through conduit Double Block and Bleed

Subsea Globe Valve

6” Body: A350-LF-2 / A352 LCC

Trim : A182-F55 with WC coating

Stem packing : Flexible Graphite

2 RTJ X RTJ

Welded bonnet

Page 11: Pipeline Repair Project FEED 2

Material Specifications

S/N Activities Status Further Actions

1. Line Pipe TGI Specification Done -

2. Flanges, Bolts, Nuts, Gaskets and Fittings

29780-00-SU-SPC-001

Done -

3. Subsea DBB Expandable Gate Valves / Gate Valves

29780-00-SU-SPC-003

Done -

4. 5D Induction Bends 29780-00-SU-SPC-004

Done

5. Subsea Mechanical Connectors & Hot Tap Assembly

29780-00-SU-SPC-005

Done EPC Contractor to attend all FAT testing for both mechanical connectors and hot tap assembliesEPC Contractor to perform mock testing at the works followed by full mock up before the actual installation works

6. Field Welding and NDT 29780-00-SU-SPC-002

Done EPC Contractor to prepare welding and NDT procedures

7. Installation 29780-00-SU-SPC-007

Done EPC Contractor to develop installation procedures.

8. Survey and Monitoring 29780-00-SU-SPC-008

Done -

9. Hydrotest, Gauging and Pigging

29780-00-SU-SPC-009

Done EPC to develop site procedures. Final HAZOP and HAZID need to be performed.

10. Construction Materials ---- Not Done All non-long lead and construction materials to be procured by EPC Contractor

Page 12: Pipeline Repair Project FEED 2

Material Requisitions

S/N Activities Status Further Actions

1. Line Pipe TGI Done -

2. Flanges, Bolts, Nuts, Gaskets and Fittings

29780-00-SU-RFQ-0003 Done -

3. Subsea DBB Expandable Gate Valves / Ball Valves

29780-00-SU-RFQ-0002 Done -

4. 5D Induction Bends 29780-00-SU-RFQ-0001 Done -

5. Subsea Mechanical Connectors & Hot Tap Assembly

29780-00-SU-RFQ-0004 Done -

Page 13: Pipeline Repair Project FEED 2

TBE/Table of Complinace

S/N Activities Status Further Actions

1. Line Pipe TGI -- -

2. 5D Induction Bends TGI -- -

3. Flanges, Bolts, Nuts, Gaskets and Fittings

TGI Done -

4. Subsea DBB Expandable Gate Valves / Ball Valves

TGI Done -

5. Subsea Mechanical Connectors & Hot Tap Assembly

TGI Done -

Page 14: Pipeline Repair Project FEED 2

Project Status – Procurement

Steel Plate and Line Pipe Manufacturing Inspection

• AnYang Steel Plate Mill audit – Done

• Line Pipe Manufacture Kick-off meeting and Mill audit – ????

All non-long lead items & consumables to be supplied by EPC Contractor and subjected to PMT’s approval – status ????

Specifications and MRs for Long Lead Items Preparation – Done

• Long lead items are identified in the MTO Report

Page 15: Pipeline Repair Project FEED 2

Project Status – Procurement

Procurement Assistance

S/N Activities Status Further Actions

Float MR TBE

1. Flanges, Bolts, Nuts, Gaskets and Fittings

Done Done -

2. Subsea Double Expandable Gate Valves / Gate Valves

Done Done -

3. 5D Induction Bends - - Specifications and MRs issued to TGI. TGI to send out for quotations – Status unknown ???

4. Subsea Mechanical Connectors & Hot Tap Assembly

Done Done PMT to ensure EPC Contractor attend all FAT testing and perform mock testing before actual repair works

Page 16: Pipeline Repair Project FEED 2

Project Status – Procurement

Procurement Assistance

S/N Activities Selected Vendor Further Actions

1. Line Pipe PT Bakrie 28” Line Production status to be updated by TGI.

Status of 16” pipe to be informed by TGI ????

2. 5D Induction Bends - - Specifications and MRs issued to TGI. Awaiting TGI to send out for quotations. TGI to update the status ????

3. Coating & Anodes BrederoShaw -Batam TGI to update the status ?????

4. Flanges, Bolts, Nuts, Gaskets and Fittings

Oceanering TGI to update the staus

5. Subsea Double Expandable Gate Valves / Globe/Ball Valves

BEL Valves -

6. Subsea Mechanical Connectors & Hot Tap Assembly

OCEANERING PMT to ensure EPC Contractor attend all FAT testing and perform mock testing before actual repair works

Page 17: Pipeline Repair Project FEED 2

Project Status – Procurement

Balance Procurement Items

S/N Activities

1. Line Pipe Small bore pipes like 6”,4”, 2” etc to be procured by EPC contractor

2. Small Bore valves ¾” 2 “

3. Flanges, Bolts, Nuts, Gaskets and Fittings

Small bore and miscellaneous items to be procured by EPC contractor

5. Barred Tee To be confirmed by TGI ?????

6. Structurals for Skid assembly

To be Procured by EPC contractor

Page 18: Pipeline Repair Project FEED 2

Discussion and Close Out