    PIR PANJAL RAILWAY TUNNEL

    A DREAM REALIZED

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    2/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    3/355

    PIR PANJAL RAILWAY TUNNEL

    A DREAM REALIZED

    Concept

    V. K. Gupta

    Project Initiation & Co-ordination

    B. D. Garg

    Working Group

    Achal JainVijyant Bhardwaj

    Kumar Ravi Shankar

    NORTHERN RAILWAY

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    4/355

    Published by

    Northern Railway

    Concept

    V. K. Gupta General Manager, Northern Railway

    Project Initiation & Co-ordination

    B.D. GARG Chief Administrative Officer/USBRL Project, Northern Railway

    Working Group

    Achal Jain Chief Engineer/USBRL Project, Northern Railway

    Vijyant Bhardwaj Ex. DGM/GC-Rites

    Kumar Ravi Shankar DGM/IRCON

    Contributors

    R.S. Poonia Chief Engineer/SECRly

    Dr. F. Prinzl GeoConsult Austria

    P.C.Pardhan Asstt. Engineer/IRCON

    Sharanappa Yalal Project Manager HCC

    Vikas Goyal XEN/ USBRL Project, Northern Railway

    Manuscript Typing

    Santosh Kumar USBRL Project, Northern Railway

    Manjit Singh USBRL Project, Northern Railway

    Printed At

    KOJO Press, New Delhi

    Designed By

    Arpit Printographers

    Copyright@2013

    Northern Railway

    Presented by

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    5/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    6/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    7/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    8/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    9/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    10/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    11/355

    Contents

    Preface xiii

    1. Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project A Historical Perspective 1

    1.1 Background 1

    1.2 Selection of The Alignment of The Railway Line 3

    1.3 Geology and Terrain 5

    1.4 Pir Panjal Railway Tunnel (T-80) 8

    1.5 Construction of the Banihal Road Tunnel in Kashmir 8

    2. Tunnelling Philosophy An Engineering Perspective 16

    2.1 Background 16

    2.2 Evaluation/Description of different Tunnelling methods 16

    2.3 NATM : Detail & Design 33

    2.4 Appointment of the Detailed Design and Construction Supervision Consultant (DDC)

    A New Initiative 50

    2.5 Main Deliverables Required from DDC 50

    2.6 Salient Features of Pir Panjal Tunnel 52

    3. Exploring The Unknown 54

    3.1 Geological And Geotechnical Investigations 543.2 Importance of Investigations Required for The Construction of Tunnel 55

    3.3 Why these Investigations are Necessary? 56

    3.4 Classification of Investigations 56

    3.5 Approach to Carrying out the Investigations 58

    3.6 Investigation During Planning and Design Stage 58

    3.7 Investigation During Construction Stage 61

    3.8 Geological Overview 65

    4. Putting The Dream On Paper (DESIGN) 89

    4.1 Introduction 89

    4.2 Collection of Data/Information 91

    4.3 Site Topography 93

    4.4 Alignment and Layout 94

    4.5 Tunnel Drainage and Waterproofing 104

    4.6 Geotechnical Design 106

    4.7 Geotechnical Instrumentation and Monitoring 111

    4.8 Design of Outer Lining 112

    4.9 Design of Inner Lining 114

    4.10 Tunnel Safety 115

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    12/355

    5. Dream in Motion (Tendering) 116

    5.1 General 116

    5.2 Need for Strategizing the Construction 116

    5.3 Early works 118

    5.4 Main Tunnel Contracts 120

    6. Bringing The Dream To Reality (Construction) 139

    6.1 Construction of Pir Panjal Tunnel 139

    6.2 Construction Materials and Their Quality Aspects 139

    6.3 Detail of Construction Materials 140

    6.4 Waterproofing and Permanent Groundwater Drainage 162

    6.5 Drives (Mining and Lining) 168

    6.6 The Access Tunnel 170

    6.7 Shaft and Cross Passage 171

    6.8 Construction of Cavern at Junction of Access Tunnel and Main Tunnel 175

    6.9 Soft Ground Tunneling at the North and South Ends 176

    6.10 Portal Development 176

    6.11 Construction Methodology of Main Tunnel 179

    6.12 Permanent Lining 190

    6.13 Year wise Progress of Lining Work 195

    6.14 Problems Faced During Construction 196

    6.15 Anticipated Rock Class v/s Actually Encountered 203

    6.16 Second Stage Concreting 204

    6.17 Ballast-less Track (BLT) 205

    7. Breathing Life into The Tunnel (Ventilation) 212

    7.1 Need of Ventilation System 212

    7.2 Design Basics/Fundamentals 215

    7.3 Boundary Conditions for Ventilation Design against Emissions and Fire 216

    7.4 Layout of Ventilation System 223

    7.5 Smoke Behaviour 226

    7.6 Waiting Time 227

    7.7 Specifications of Machinery 228

    7.8 Summary of the Final Longitudinal Ventilation System 229

    8. Livening The Tunnel (Electrical & Mechanical Systems) 231

    8.1 General 231

    8.2 Compliance with the UIC 779-9 R provisions 231

    8.3 A Short Description of the System 233

    8.4 Electrical and Mechanical Installations: 234

    9. Safety (Operational Concepts) 246

    9.1 Safety Concept 246

    9.2 Main Scenarios And Required Measures 246

    10. Through The Eyes of a Camera 256

    Appendix A : Geodetic Survey 301

    Appendix B : The Role of The Roadheader 310

    Appendix C : Instrumentation & Monitoring of Tunnel - Section 314

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    13/355

    Preface

    The engineering work on a large tunnel project is so complex that number of

    engineers and specialists in many areas are required to be involved in design and

    construction. The decisions, of which there may be several, call for a vast amount of

    technical knowhow and sound judgement based on many years of experience.

    The 11 km. long tunnel the Pir Panjal Railway Tunnel represents a culmination of a

    tremendous effort on the part of myriads of engineers who were involved in its

    planning, design and construction engineers from Northern Railway, the Contractor

    IRCON and their various Subcontractors/consultants.

    Northern Railways engineers felt it worthwhile to pen down and put on paper for

    the benefit of posterity the multitude of the involved technical details and the lessons

    that were learnt during design and construction of Pir Panjal Railway Tunnel the

    longest transportation tunnel in india.These notes, stated in the format of a book,give discrete steps to decision making and undoubtedly provide a comprehensive

    coverage of the subject for both the designer and the constructor. At its heart lies

    the Capacity for Development which then is the ability to solve problems, and make

    informed choices, and plan for future.The material in the Book is presented in the

    vein of a comprehensive yet concise compendium. The presentationshave a flow

    that moves from the individual to the organization,with practical skills and

    theory woventogether, offering real-life engineering experience, from problem

    formulation through to implementation.

    This would educate thefuture creatorsin understanding the subject of tunnelling,thus enabling them to employ their grounding in engineering to become workman-

    like partners in future in such type of project.

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    14/355

    FIRSTTR

    AIN

    THROUGH

    TUNNEL

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    15/355

    Chapter

    1Udhampur-Srinagar-Baramulla Rail Link

    (USBRL) Project A Historical Perspective

    1.1 Background

    1.1.1 With a view to provide a reliable alternative transportation system to the Kashmir Valley, the Government

    of India sanctioned the construction of a 326 Km long railway line to the States Summer Capital, Srinagar, taking off

    from its Winter Capital, Jammu.

    1.1.2 Terminating at Baramulla, near Srinagar, the railway line connects Jammu with Udhampur, then Katra,

    Reasi, Banihal, Qazigund and Srinagar en route (Fig 1.1). It is one of the largest and toughest mountain - railway

    project undertaken in the country since independence. The railway line traverses the young Himalayas, which is

    tectonically very active and dotted with many Thrusts and Faults. Work on the Jammu Udhampur section (53 Km)

    was completed and commissioned in April, 2005. Then the section from Baramulla to Qazigund (119 Km) was

    completed and opened to traffic in October, 2009. Work in the remaining stretch from Udhampur to Qazigund,

    totalling 154 Km, is in various stages of construction. The Udhampur-Srinagar-Baramulla rail link (USBRL-273Km)was declared as a Project of National Importance. Some of the important salient features of USBRL Project are as

    follows:

    Item Udhampur Katra Qazigund Total

    Katra Section Qazigund Section Baramulla Section

    Route length 25Km 129Km 119Km 273

    Ruling gradient 1 in 100 1in 80 1in 100

    Sharpest in - plan Curvature 2.75o 4o 2.75o -

    No. of Bridges 38 62 811 911

    Max. height of Bridge 85 m 359 m 22 m -

    Longest individual span length 154m Steel Girder, 467 m Steel Arch, 45 m -

    over river Jhajjar over river ChenabAggregate Bridge Length 1488m 7310m 4210m 13008m

    No. of Tunnels 10 36 - 46

    Aggregate Tunnel Length 10.90 Km 105.00 Km 0 115.90Km

    Aggregate Tunnel length as % of

    section length 43.60 81.40 0 -

    Longest Tunnel length 3.15 Km. 11.27 Km - -

    Max Depth of Cutting 20 m 40 m 12 m -

    Rly. Stations 3 10+1 15 28+1

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    16/355

    2 Pir Panjal Railway Tunnel

    Fig. 1.1: Alignment Plan

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    17/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    18/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    19/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    20/355

    6 Pir Panjal Railway Tunnel

    1.3.4 Other geomorphic processes that are related to the meteorological conditions have also lead to continuous

    modification of the shapes of the Himalayan ranges. Some of these changes in the slopes of mountains and drainage

    basins have occurred within the experience of an average life span of humans. Emergence of the Himalayas is

    considered to have caused the onset of the Indian Summer Monsoon some time in the geological past (about 8

    million years ago, according to one school). The Indian Monsoon has since become more intense and well diversified

    in terms of regional variations in annual rain fall. The Himalayas have also shown themselves as an ideal case forcoupled effects of tectonics and climate. Whereas the tectonics have lead to the rise of the Himalayas, high

    precipitation and high relief have been responsible for faster rates of erosion. Higher rates of erosion, in turn, lead

    to an increase in the rate of uplift of the mountains, and thus the tectonics-climate coupling continues to modify

    the shape of the Himalayan ranges. Understanding these processes of tectonics and erosion has a great bearing on

    designing, executing and maintaining the civil structures, such as rail-roads.

    1.3.5 The rail alignment from Katra to Banihal traverses the most difficult terrains of the Lesser Himalayas

    characterized by steep hills and deep valleys. The Main Boundary Fault (MBF) that marks the boundary between

    the Outer and Lesser Himalayas is located near the Katra end of the alignment. Along the MBF, rocks of Shiwalik

    Group are thrust by the Late Precambrian carbonate sequence named Sirban Limestone. Whereas the Shiwalik

    Group is made up of alternate bands of claystone, siltstone and sandstone, the overlying carbonate sequence

    comprises predominantly of limestone and dolomite with some arenaceous beds in the upper parts of the succession.The limestones and dolomites of the Sirban Limestone are highly jointed and sheared in the vicinity of the MBF.

    1.3.6 The Sirban Limestone is overlain by coaliferous shales and limestones named Subathu Formation of Eocene

    age. These are overlain by the Jungalgali Formation that is made up of limestone, chert, quartzite, shale, sandstone,

    clay bands and bauxite at a few places. Both, the Subathu Formation and the Jungalgali Formation, are exposed

    along the rail alignment in relatively thinner bands of outcrops on the northern bank of the Chenab river. These, in

    turn, are overlain by a thick succession of shale, siltstone and sand stone comprising Murree Formation. While the

    Subathu Formation represents a marine facies, the rocks of younger Murree Formation were deposited in fluvial

    and lacustrine basins.

    1.3.7 The Subathu Formation and Sirban Limestone are again exposed in the upper reaches along the alignment

    where they are separated by the Murree Formation by a series of strike faults. The Murree rocks continue till they

    are separated by yet another important thrust named as Murree Thrust. This structure has lead the Late Proferozoicsequence of phylhtis slates and quartzites, named Ramban Formation, to lie over Late Tertiary sequence (Murree

    Formation).

    1.3.8 The Ramban Formation is truncated in the north by Panjal Thrust that brings a sequence of Late Precambrian

    Salkala Formation of Tethyan Himalayas to lie over the rocks of Ramban Formation. The Salkhala Formation contains

    large bodies of granitic rocks that are foliated and highly jointed. These, in turn, are overlain by rocks of Ramsu

    Formation that are made up of slate phylhtis, quartzite, schist and limestone. The Ramsu Formation is unconformably

    overlain by a sequence of agglomeratic shales, slates and phylhtis with interbeds of fossiliferous limestone. This

    sequence is overlain by a thick sequence of volcanic rocks known as Panjal Volcanics that are exposed in the higher

    reaches of the Pir Panjal Range beyond Banihal.

    The above sequence of Late Precambrian to Tertiary ages have undergone folding and faulting during the Himalayan

    orogeny. Quarternary sediments comprising fluvial, lacustrine, eluvial and glacial sediments occur in small packetsat different places in the Himalayas. These are unconsolidated sediments of variable thicknesses, met with at a few

    places along the alignment (Fig. 1.4).

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    21/355

    Fig. 1.4

    Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project A Historical Perspective 7

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    22/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    23/355

    Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project A Historical Perspective 9

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    24/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    25/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    26/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    27/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    28/355

    14 Pir Panjal Railway Tunnel

    the final tunnel design. In respect of earthquakes no experience at the Banihal area was available, however, on

    various other points in the Kashmir Valley, between 1909 and 1946 observations were made as shown in table I:

    TABLE-I

    Rossi Forel Scale Acceleration in mm s StationsSrinagar Gurez Gulmarg Dras

    I Upto 2.5 6 1

    II 2.5 to 5.0 6 1 1

    III 5 to 10 14 4 1

    IV 10 to 25 54 3 1 2

    V/VI 25 to 50 113 15 46 6

    VII 50 to 100 34 5 18 4

    VIII 100 to 250 3 3 18 4

    IX 250 to 1000 1 1

    X More than 1000

    Noted, intensity

    not known 1 1 2

    Total number of

    earthquakes 1909- 1946 231 29 90 19

    During the construction period of the tunnel a number of earthquakes were noted in Banihal of which only two on

    two subsequent days in spring 1956 must be considered as heavier earthquakes which may have been in the order

    VIII of the Rossi Forel scale. As the above table shows the heaviest earthquakes observed in Kashmir were of the

    grade IX of the scale. Since Kashmir is located in the seismological area of the Himalaya, the government decided on

    an acceleration of 0.1 g for the statical computation of tunnel vault which equivalent to the intensity X of the Rossi

    Forel scale.

    At the time of construction commencement available meteorogical values with respect to temperature, precipitation,

    atmospheric pressure, relative humidity and wind velocities for stations in the Kashmir Valley and in the areas of

    the Chenab and Tavi rivers could not be taken into consideration for the design of the Banihal tunnel since the Pir

    Panjal range follows own weather and natural laws which show very abrupt differencies which in many respects

    deviate from those measured in the Kashmir Valley.

    In order to collect information for the tunnel ventilation and water supply the Central Public Works Department

    installed on the north and south portal of the Banihal tunnel, meteorological stations. With respect to the avalanche

    problem, the Joint Venture could only rely on oral information of the local Public Works Department and their

    observations and experiences in the past.

    1.5.5 Cross-section of the Tunnel

    For both tunnel tubes a contractual clearance area in form of a horseshoe was fixed as shown in picture 4, with a

    semi-circle of 2.72 m radius and a trapezoidal lower part of 5.44 m width at top at 5.03 m at about road level.

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    29/355

    The clearance height in the center is 5.54 m, the maximum width at the spring of calotte 5.44 m. The one-lane road

    pavement has a slope of 1:70 and is normally 3.20 m wide, on by-passes it widens to 5.64 m, the one-sided walkway

    has a railing at 1.25 width, the curbstone on the other side has a width of 0.58 m, both have been executed with arounded-off curb as usually used in this country. The clearance height is for Indian circumstances unusually high

    and even sufficiently high for particular army vehicles. The design of the cross-section particularly took care of the

    possibility, in case of necessity, to allow the installation of a channel for ventilating and fresh air supply. If one

    compares this cross- section e.g. with the Lammerbuckel tunnel of the highway Stuttgart-Ulm, which is also used in

    one-directional traffic only, the cross-section of the Banihal with about 30 m is not even half as big as the highway

    tunnel with approx. 70 m.

    The lining of the tunnel in the earlier projects was to be done in stone-masonry with a thickness of 1" per 1

    clearance width. For the execution, however, instead of stone-masonry concrete and reinforced concrete was chosen

    with a mixing ratio of 1:2:4 and thickness fixed at 12", 15" and 18" respectively, whereby the latter, wherever

    required was to be reinforced and even provided with an invert. The Indian government was not satisfied with the

    empiric formula of thickness as above mentioned, but insisted on a statical computation of the vault in accordance

    with the geological charting and the resulting loadings onto the vaults.

    Therefore, a calculation with a pressure ellipse according to O. Kommerell of h = 100a/p was taken into account

    whereas the deformation of the tunnel top a and the permanent loosening of the rock p in percent were

    estimated according to the local conditions of the rock. For the 21" profile with earthquake reinforcement and

    reinforced concrete invert selected for the area of clay and debris at the tunnel ends, the calculation showed a

    maximum eccentricity of the pressure resultant with the Kommerell load as indicated of only 15 kg/cm, as against

    a permissible value of 52.7 kg/cm according to the Indian standard code IS-456-1953 for a mix of 1:2:4, and even

    the pressure in the concrete/rock interface joint of the invert was within marginal limits.

    Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project A Historical Perspective 15

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    30/355

    Chapter

    2Tunnelling Philosophy

    An Engineering Perspective

    2.1 Background

    Tunnelling is both a Science and An art that over-arches the many disciplines of engineering - civil, structural,

    geological, mechanical, electrical and computer as well as the ecological and environmental constraints. Apart from

    being a highly expensive engineering enterprise, tunnels can present very difficult problems in their construction.

    As more and more tunnels are built, it calls for continued improvement in tunnelling technology. Tunnel as an

    alternative, has to be a cost-effective engineering solution with minimal impact on the ambient environment and

    ecology. Although significant innovations have been made over the years in tunnel construction, the substantial

    growth in passenger traffic and the consequent need for more efficient rapid transit systems in urban areas

    necessitates more and more improvement in tunnel construction practices.

    Here an attempt has been made to examine and evaluate the currently practised construction technologies i.e.

    Tunnel Boring Machine (TBM) method, Conventional Indian Method of Tunnelling and New Austrian TunnellingMethod (NATM) for tunnelling through different medium i.e. through soil and rock.

    2.2 Evaluation/Description of Different Tunnelling Methods

    First a short overview of different construction Technologies is attempted (for better evaluation):

    2.2.1 TBM Technology

    i. Tunnelling by boring, using a Tunnel Boring Machine (TBM) is often adopted for long tunnels. An effective TBM

    method requires the selection of appropriate equipment for different types of rock mass and geological conditions.

    The TBM may be suitable for excavating those tunnels which contain competent rocks that can provide adequate

    geological stability when boring through a long section without structural supports. However, extremely hard rock

    can cause significant wear of the TBM rock cutter and may slow down the progress of the tunnelling to the point

    where TBM becomes inefficient and hence uneconomical and may take longer time than the drill-and-blast tunnelling

    method in such a case. The detail of TBMs commonly use in rock are as under:-

    a. Gripper TBM (Open TBM)- For use in solid rock. The machine is locked at the rock using two or four gripper

    plates. Then, hydraulic cylinders push the cutter head into the tunnel face at high pressure, grinding it with

    cutter rings (Fig. 2.1).

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    31/355

    Fig. 2.1

    b. Single Shield TBM-For use in brittle or soft rock. The tunnel is lined with concrete segments. To tunnel

    forward, the hydraulic thrust cylinders of the Single Shield TBM push against the last installed lining ring

    (Fig. 2.2) .

    Fig. 2.2

    Tunnelling Philosophy An Engineering Perspective 17

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    32/355

    18 Pir Panjal Railway Tunnel

    c. Double Shield TBM-These combine the principles of the Gripper and the Single Shield TBM, enabling fast

    excavation even in varying rock formations (Fig. 2.3) .

    Fig. 2.3

    There are two major shield machines available for tunnelling in soft ground in urban areas i.e the earth pressure

    balanced (EPB) and the slurry type shield machines. Selection of the appropriate shield machine depends on the

    ground conditions, surface conditions, dimensions of the tunnel section, the boring distance, the tunnel alignment

    and the construction period available. Both are closed-face type shield machines, meaning the head part of

    machine is closed and separated from the rear part of machine. The head has a working chamber filled with soi lor slurry between the cutting face and bulkhead to stabilize the cutting face under soil pressure. The EPB type

    shield machine turns the excavated soil into mud pressure and holds it under soil pressure to stabilize the cutting

    face. It has an excavation system to cut the soil, a mixing system to mix the excavated soil into mud pressure, a soil

    discharge system to discharge the soil and a control system to keep the soil pressure uniform. Therefore, EPBM may

    not be applicable for the rocky strata that where it is difficult to turn the excavated soil into slurry. It can be used at

    ground which is predominated by clayey soil. The slurry type shield machine, on the other hand, uses the external

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    33/355

    pressurized slurry to stabilize the cutting face, similar to bored piles or diaphragm walls using Bentonite to hold

    back the trench wall. The slurry is circulated to transport the excavated soil by fluid conveyance. Besides having an

    excavation system, the slurry type shield machine has slurry feed and discharge equipment to circulate and pressurize

    the slurry and a slurry processing equipment on the ground to adjust the slurry properties.

    ii. The sequential steps for construction of tunnel by TBM:

    Schematic construction sequence for working by TBM

    iii) Schematic representation of EPBM ( See Fig.2.4,Fig.2.5)

    Fig. 2.4

    Tunnelling Philosophy An Engineering Perspective 19

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    34/355

    20 Pir Panjal Railway Tunnel

    Fig. 2.5

    iv) Types of cutting face of EPBM ( See Fig. 2.6)

    ??

    Fig. 2.6

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    35/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    36/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    37/355

    x) Types of cutting face of slurry type shield ( See Fig. 2.12)

    Fig. 2.12

    xi) Slurry type TBM : Slurry circulation system ( Representative) (See Fig. 2.13)

    Fig. 2.13

    xii) Slurry type TBM : Slurry circulation system ( Line Diagram) (See Fig. 2.14)

    Fig. 2.14

    Tunnelling Philosophy An Engineering Perspective 23

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    38/355

    24 Pir Panjal Railway Tunnel

    xiii) Slurry type TBM : Slurry Circulation system ( See Fig. 2.15)

    Fig. 2.15

    xiv) Slurry treatment plant. ( See Fig. 2.16)

    Fig. 2.16

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    39/355

    xv) Typical site utilization plan for working with slurry type TBM including working shaft, gantry crane, segment

    stock yard, tanks, etc. ( See Fig. 2.17)

    Fig. 2.17

    xvi) Section view of the site utilization for working with the slurry type TBM (See Fig.2.18)

    Fig. 2.18

    Tunnelling Philosophy An Engineering Perspective 25

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    40/355

    26 Pir Panjal Railway Tunnel

    2.2.2 Shaft Construction

    i) Shaft construction using diaphragm wall method (See Fig. 2.19,Fig.2.20)

    Fig. 2.19

    Fig. 2.20

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    41/355

    ii) Shaft construction using diaphragm wall method - Access stairs, ventilation and passenger hoist are provided (

    See Fig. 2.21)

    Fig. 2.21

    Tunnelling Philosophy An Engineering Perspective 27

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    42/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    43/355

    iii) A receiving shaft to accommodate dismantling ( right) and assembling (left) TBM at the same time (See Fig. 2.24)

    Fig. 2.24

    iv) The shield machine at work ( See Fig. 2.25)

    Fig. 2.25

    Tunnelling Philosophy An Engineering Perspective 29

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    44/355

    30 Pir Panjal Railway Tunnel

    v) The functioning part of TBM ( back up) at the rear (See Fig. 2.26)

    Fig. 2.26

    2.2.4 Conventional Indian Method Of Tunnelling

    In conventional Indian method of tunnelling, the excavation is done by Drill and blast method and thereafter steel

    ribs with backfilling by tunnel muck or lean concrete is used as an almost automatic first step in tunnel support.

    This being a passives support system, a considerable damage is done to the rock mass before the ribs interact with

    it. The combination of the drill-and-blast method of excavation and steel rib support system delays the supporting

    action, allows opening of the existing joints, creates new fractures, permits loosening of the rock mass in the roof,

    mobilizes higher tunnel closures and greater rock loads which require larger excavation and thicker support. All

    these problems result in increased cost and completion period. The steel ribs invite unwanted loosening, and a

    potential weakening-because-of-loosening (Fig.2.27,2.28).The tunnel construction that is based on extensive use

    of steel ribs the conventional Indian Method (Fig. 2.29) is unfortunately slow in most of the rock classes.

    Fig. 2.27 Fig. 2.28

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    45/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    46/355

    32 Pir Panjal Railway Tunnel

    b) Maintain strength of the rock mass and avoid detrimental loosening by careful excavation and by

    immediate application of support and strengthening means.Shotcrete and rock bolts applied close to the

    excavation face help to maintain the integrity of the rock mass.

    c) Rounded tunnel shape:avoid stress concentrations in corners where progressive failure mechanisms

    commence.

    d) Flexible thin lining:The primary support shall be thin-walled in order to minimize bending moments and to

    facilitate the stress rearrangement process without exposing the lining to unfavorable sectional forces.

    Additional support requirement shall not be added by increasing lining thickness but by rock bolting. The

    lining shall be in full contact with the exposed rock. Shotcrete fulfils this requirement.

    e) Statically the tunnel is considered a thick-walled tube consisting of the rock and the lining. The closing of

    the ring is therefore important, i.e. the total periphery including the invert must be shotcreted.

    f) In situ measurements: Observation of tunnel behavior during construction is an integral part of NATM.

    With the monitoring and interpretation of deformations, it is possible to optimize the working procedures

    and the support requirements.

    2.2.6 Why the TBM Method was not adopted for construction of Pir panjal Tunnel

    Because of Likelihood of encountering-Mixed Geology (non-uniform medium)

    Heavily Faulted and/or Wide Fault Zones

    High Squeezing Effected Anticipated in the middle portion, with High Overburden almost 1100 to 1200 m.

    Heavy Water Flows in the Lime Stone Zones with High overburden

    Ground Movement that could easily trap the TBM.

    The TBM technology is suitable for excavating through nearly uniform medium with no serious obstacles.

    The TBM method with shield is also used for tunnels in pervious ground below water level.

    2.2.7 Why Conventional Indian method of tunnelling was not adopted in

    construction of Pir panjal Tunnel

    This method of construction is not flexible enough to accommodate required changes to suit ground

    conditions/encountered geology like :

    o Vary the support system as per requirement

    o Splitting of the excavation face to tackle varied geological conditions

    o To carry out Ground treatment

    o Tackle heavy ingress of water

    2.2.8 Why NATM was adopted for construction of Pir panjal Tunnel

    NATM provides for more cost effective, flexible and safe tunnelling methodology without the long mobilization

    process endemic with TBM procurement. NATM is well suited for tunnelling in ground with varying geology. As

    such, the New Austrian Tunnelling Method (NATM), was the appropriate alternative.

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    47/355

    2.3 NATM : Detail & Design

    2.3.1 Development of Natm

    i) The name NATM (New Austrian Tunnelling Method) was introduced by Prof.Rabcewicz in 1962 to

    differentiate this new method from the then old Austrian Tunnelling Method which was one of several

    tunnelling methods that were developed during the first half of the 20thcentury. Typical for these old

    European methods were small headings with temporary timber support, which were systematically widened

    to the full cross section. During the installation of the final lining, usually made of bricks and stone masonry,

    the timber strutting was removed but timber lagging often was left in place. Another characteristic was the

    use of heavy side walls and foundation beams but no invert (no ring closure), Figure 2.30

    Fig. 2.30 : Karawanken Railway Tunnel, Cracking due to missing ring closure

    ii) Rabcewicz initiated a new and entirely different tunnel construction procedure and disregarded completely

    the generally used state-of-the-art techniques. He also introduced newly developed construction

    technologies into tunnelling.

    iii) Rabcewicz had collected a profound tunnelling experience between the two world wars when he was

    working on hydropower and railway projects in Persia and Turkey. He summarized his knowledge and

    understanding of tunnelling in a systematic way in his book Rock Mass Pressure and Tunnelling which

    was published in 1944. The books title is characteristic for some of the important topics which he described.

    iv) He differentiated very clearly between the pressure fromrock mass loosening, real rock (squeezing) pressure

    and swelling pressure. He recognized that the development of the loosening pressure is related to the

    Tunnelling Philosophy An Engineering Perspective 33

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    48/355

    34 Pir Panjal Railway Tunnel

    shortcomings of the construction procedure and the temporary support with timber struts and lagging,

    which could not prevent material loss, loosening and excessive movements even at low pressure. He stated

    time factorand rock mass structureas important parameters for control of loosening and the necessity to

    maintain a three dimensional stress distribution throughout the procedure of excavation and support

    installation. On the other side he explained that real rock mass pressure can be observed when the

    stressesat the side walls exceed therock mass strength. If this happens the stresses will be redistributed,away from the opening, deeper into the rock mass where confined stress conditionsexist and the so called

    protective shell is developed. Rabcewiecz also distinguished the different behavior of the various rock

    types under high pressure with spalling appearances in hard rock and large plastic deformation in soft

    rock. He stated that in the latter case even strongest support can not withstand the pressure if installed too

    early. In this respect he criticized the practice of lining design of that time, as being only suitable to support

    the loosening pressure. He introduced and insisted in the importance of monitoringas a compulsory

    requirement for his new tunnelling method.

    v) Other tunnel engineers to be mentioned for their contributions during the very early stage of the

    development of the NATM are Dr.Lauffer who introduced the rock mass classification system in 1962,

    Prof.Pacherwho described the rock mass behavior in the Fenner-Pacher characteristic curve and Prof.Mller

    who was a leading member of the Salzburg Circle a group of tunnel engineers who met regularly inSalzburg for exchange of experiences and new ideas.

    vi) Important break through eventswere the successful application of the NATM in the Massenberg Tunnel in

    Austria and in the Schweikheim Tunnelin Germany in 1964 which were both tunnels with shallow cover. At

    the Massenberg Tunnel, Figure 2.31, the design and construction method was changed after great difficulties

    were encountered during construction.

    Fig. 2.31: Original and New Design (after stand still) of the Massenberg Tunnel

    vii) With the Tauerntunnel, which started in 1970, the method was applied for the first time in a tunnel with

    high overburden and real rock mass pressure. It was also used in the talus section at the portal zones where

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    49/355

    soft ground with large boulders had to be tunnelled. The 6.5 km long main tunnel section with more than

    1000 m overburden consisted of various rock types including long sections of highly stressed Phyllites. For

    the stabilization of the heavy rock mass pressure with large deformations, longitudinal slots in the shotcrete

    were used for the first time. In combination with long rock bolts this section was also successfully completed

    and the tunnel was a technical and economical success.

    2.3.2 Basic Principles of NATM

    i) It is important to understand that NATM is a construction procedure and the excavation and support have

    to be seen always in cross sectional and longitudinal direction. It has been always avoided to limit the

    application of NATM by the definition of particular and distinct guide lines. The application depends widely

    on the particular conditions of each tunnel project and a generalization and simple copying may lead to an

    inadequate design in other conditions. For better understanding some of the basic principles of the method

    are summarized below:.

    a) The major load bearing member is the rock mass.

    b) The primary support shall help to:

    maintain the integrity and strength of the rock mass around the opening, shall be slim but shall have a good contact with the rock mass and shall cover the whole area of the

    rock face (shotcrete),

    shall strengthen the rock mass (bolts, grout)

    shall provide immediate protection to workers (steel ribs, wiremesh) and

    shall be installed as quickly as possible

    c) Effective ring closure shall be achieved fast. This is provided by the rock or by the installation of an invert,

    if the rock strength is too low.

    d) Two dimensional stress conditions shall be avoided.

    e) The excavation area shall be as large as possible and if possible full face excavation shall be used. Small

    partial excavations shall be avoided.

    f) Tunnel cross section should have a smooth and rounded shape.

    g) The Rock mass and support interaction (system behavior) must be continuously controlled by monitoring.

    h) The inner lining should increase the factor of safety of the permanent support and shall be installed only

    after complete balance of the stresses when deformations have stopped.

    ii) Rock Mass Classification of Lauffer (1962)

    a) In 1962 a rock mass classification system was introduced by Dr.Lauffer.

    b) The Lauffer diagram (Fig. 2.32) shows the relation between the unsupported effective span (m) and

    the standing time (h) in relation to seven Rock Mass Classes which he separated in accordance with the

    rock mass behavior. As such, classes A to G represent rock mass behavior types. He also indicated the

    characteristic range of application. He proposed that the rock mass classification shall accompany the

    project from the design to the final documentation. This system has been used with some modifications

    until recently and still provides the basis for the Rock Mass Behavior types which are described later.

    Tunnelling Philosophy An Engineering Perspective 35

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    50/355

    36 Pir Panjal Railway Tunnel

    Fig. 2.32: Rock Mass Classification system of Lauffer

    X-axis: Stand Time (h), Y-axis: Effective

    Span (m), Rock mass classes A to G

    Shaded area presents characteristic range of application

    iii) Characteristic Curve of Pacher (1963)

    The characteristic curve, Fig. 2.33 generally called the Fenner Pacher curve, shows the relation between

    deformation (X-axis) and load/support development (Y-axis - up) and deformation and time of support

    development (Y-axis - down). It represents the interaction of the rock mass and the support system with

    time. In non stable rock mass the decrease of the radial stresses with deformation will have a low point

    after which the loosening pressure and the required support increase. The point of pressure balance of the

    rock mass and the support should be always on the downward curve of the radial stress.

    Fig. 2.33: Fenner Pacher Curve

    X-axis: Deformation, Y-axis: up: Load/Support

    Development down: Time

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    51/355

    2.3.3. Geotechnical Tunnel design

    i) Basic Procedure of the Geotechnical Design

    The present status of tunnel design in accordance to NATM has been described in

    The Austrian Draft of CONVENTIONAL TUNNELLING

    these are guidelines published by the Austrian Society of Geomechanics. The guidelines were recently republished

    still as a draft as Guideline for Geotechnical Design of Underground Structures with Conventional Excavation.

    These guidelines have been developed by a working group of engineers from clients, contractors and consultants in

    Austria using the experience gained in many projects constructed in accordance with NATM over several decades.

    In Austria the guidelines serve as a supplement to the Standard OENORM B-2203-1, Regulation of the Construction

    Contract for Mined Tunnelling.

    The following sections, limited to the Design Phase, are partly an extract of the Austrian Draft, and provides a

    better understanding of the design process. The Geotechnical and Tender Design as used for the Pir Panjal Railway

    Tunnel follows widely the Austrian Draft.

    ii) Purpose Scope of Work

    The intended purpose of the Austrian Draft is to summarize the state of the art for conventional tunnelling inAustria. The design, contractual applications and construction management are described in detail.

    Fundamental requirements for conventional tunnelling projects in Austria are:

    Evaluation and classification of the ground conditions with respect to particular project requirements

    Design subdivided in phases, staged with the project (and construction) development, which provides the

    framework for a range of potential applications

    Construction methods suitable for standard plant, equipment and materials

    Back-checking of the predictions by geotechnical monitoring and adjustment to the conditions encountered

    Flexible contractual models for fair remuneration

    iii) Geological Geotechnical Evaluation

    a) The main task of the geotechnical design is the economic optimization of the construction considering the

    rock mass conditions as well as safety, stability, and environmental requirements.

    b) The variability of the geological architecture including the local rock mass structure, rock mass and soil

    parameters, stress and ground water conditions requires that a consistent and specific procedure be used

    during the design process. The key influences governing the geotechnical design are the ground conditions

    and behavior.

    c) Existing schematic rating systems and their recommendations for excavation and support have been

    developed from experience under specific conditions. A generalization for other rock mass and boundary

    conditions frequently leads to inadequate design. Consequently a technically sound and economical design

    and construction can be achieved only by applying a project specific and rock-mass-specific procedure.

    d) In spite of all uncertainties in the description of the rock mass conditions, underground engineering needsa strategy, allowing a consistent and coherent design procedure that is traceable throughout the entire

    project. The procedure outlined in this guideline consists of several phases.

    e) There are two basic phases:

    Tunnelling Philosophy An Engineering Perspective 37

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    52/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    53/355

    A. Phase-1-Design

    Basic Procedure

    The geotechnical design, as part of the tunnel design, serves as a basis for approval procedures, the tender documents

    (determination of excavation classes and their distribution), and the determination of the excavation and support

    methods used on site .

    The flow chart (Fig.. 2.3) shows the basic procedure, consisting of 5 general steps, to develop the geotechnical

    design, beginning with the determination of the rock mass types and ending with the definition of excavation classes.

    The five steps, which have to be followed, include:

    Step 1 Determination of Rock Mass Types

    The first step starts with a description of the basic geologic architecture and proceeds by defining geotechnically

    relevant key parameters for each ground type. The key parameters, values and distributions are determined from

    available information and/or estimated with engineering and geological judgment; values are constantly updated

    as pertinent information is obtained. Rock Mass Types (RMT) are then defined according to their key parameters.

    The number of Rock Mass Types elaborated depends on the project specific geological conditions and on the stage

    of the design process.

    Step 2 Determination of Rock Mass Behavior Types (BT)

    The second step involves evaluating the potential rock mass behaviors considering each rock mass type and local

    influencing factors, including the relative orientation of relevant discontinuities to the excavation, ground water

    conditions, stress situation, etc. This process results in the definition of project specificBehavior Types.

    The rock mass behavior has to be evaluated for the full cross sectionalarea without considering any modifications

    including the excavationmethod or sequence and supportor other auxiliary measures.

    The rock mass behavior types form the basisfor determining the excavation and supportmethods as well as assist

    in evaluating monitoring data during the excavation.

    Step 3 Determination of the excavation and support

    Based on the defined project specific behavior types, different excavation and support measures are evaluated and

    acceptable methods determined.

    The System Behavior is a result of the interactionbetween the rock mass behaviorand the selected excavation

    and supportschemes. The evaluated System Behavior has to be compared with the defined requirements. If the

    system behavior does not comply with the requirements, the excavation and/or support scheme has to be modified

    until compliance is obtained.

    Once the acceptable excavation and support methods have been determined, both risk and economic analyses

    should be performed to allow appropriate assessments during the tender process.

    Tunnelling Philosophy An Engineering Perspective 39

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    54/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    55/355

    This is the final step in the geotechnical design process. All possible geological conditionsshould be addressed with

    a defined rangeof excavation and supportmethods as well as the probability or likely hood of occurrence.

    Step 5 Determination of excavation classes

    In the final step of the design process the geotechnical design must be transformed into a costand time estimate

    for the tender process. Excavation Classes are defined based on the evaluation of the excavation and support

    measures. The excavation classes form a basis for compensation clauses in the tender documents. In Austria the

    evaluation of excavation classes is based on the regulations in ONORM B2203-1. At other places the local or agreed

    regulations should be used.

    The distributionof the expected behavior types and the excavation classes along the alignment of the underground

    structure provides the basisfor establishing the bid priceduring tender and the bill of quantitiesduring project

    execution.

    iv) Detailed Assessment

    a) Determination of Rock Mass Types

    A Rock Mass Type is defined as a geotechnically relevant rock mass volume, including discontinuities and

    tectonic structures, which is similar with respect to following properties

    - in rock: rock type, mineral composition, strength (intact rock rock mass), rock- and rock mass conditions,

    types of discontinuities, discontinuity properties, hydraulic properties

    - in soil: grain size distribution, density, mineral composition, parameters of the soil components, matrix

    parameters, water content and hydraulic properties

    See Table 2.1 for key Parameters in Basic Rock Types.

    Different Rock Mass Types have different characteristic parameters that influence their mechanical behavior.

    To determine different rock mass types relevant key parameters have to be evaluated and defined. Rock

    masses with similar combinations of relevant parameters are distinguished as one Rock Mass Type.

    The definitions of the Rock Mass Types have to be based on the current knowledge in each project stage,

    considering their importance for the successful completion of the project. The numberof defined Rock

    Mass Typesisproject specificand depends on the design phase as well as on the complexity of the geologicalconditions in the project area. In general, in early design phases, a rough discrimination will be sufficient,

    with increased information in subsequent design phases the distinction between the single Rock Mass Types

    will be, and has to be more precise.

    The final task in this step is to assignthe Rock Mass Typesalong the alignment.

    Method

    - Selected key parameters describe the geotechnically relevant properties of the rock mass. Table 2.1 is

    intended to provide assistance for the selection of the relevant parameters for different rock types.

    Depending on project specific boundary conditions, weighting of the parameters may be required. In

    any case it has to be checked if the selected parameters are sufficient to adequately describe the rock

    mass properties.

    - The determination of the various parameters shall be based on local standards and regulations. The

    reasons for the use of other standards or procedures have to be clearly explained.

    - Identical lithological types with significantly different discontinuity and/or intact rock properties have to

    be specified as different Rock Mass Types if this difference results in a different behavior type when

    considering the variation in influencing parameters.

    Tunnelling Philosophy An Engineering Perspective 41

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    56/355

    42 Pir Panjal Railway Tunnel

    Table 2.1: Example of selected key parameters for different general rock types

    - Different key parameters may be required depending on the type and use of the underground structure.

    The number of parameters used for the definition of the Rock Mass Types and their mode of classification

    can change as the project progresses.

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    57/355

    - Collection of the relevant geotechnical parameters and influencing factors is done preferably during the

    preliminary design. Investigations during the tender design should concentrate on reducing the uncertainty

    or risk in geotechnically critical areas.

    - Simple rating methods can be used in early project phases (feasibility study, preliminary design). Frequently

    in these phases parameters from literature or previous experience have to be used due to lack of data

    from the project area.

    - Empirical and numerical methods, as well as in situ tests may be used in later project phases (project

    approval, tender design) for the determination of the properties of a representative rock mass volume.

    - Rock mass strength, deformation characteristics, hydraulic properties, as well as specific properties (for

    example pronounced anisotropy, low friction of discontinuities, time dependent behavior, intercalation

    of other rock types, etc.) have to be evaluated and shown in the documents.

    b) Determination of Rock Mass Behavior Types

    The rock mass behavior is determined for each rock mass type by evaluating the effect of the influencing

    factors on the response of the rock mass with the full excavation geometry. First the orientation of relevant

    discontinuity sets relative to the axis of the underground structure must be determined; the appropriatestress conditions defined, as well as the local ground water conditions for single homogeneous sections

    along the alignment. After assigning all relevant properties and influencing factors to each section, the rock

    mass behavior (reaction to the excavation) can be evaluated for each section of the underground structure.

    The expected rock mass behavior is then categorized into the general types listed in Table 2.2, and the

    distribution along the alignment determined.

    The Rock Mass Behavior Types form the basis for the design of the excavation sequence and appropriate

    support.

    Method

    - An unsupported and indefinitely long cavity has to be assumed When considering long underground

    structures (tunnels). Sequential excavation steps are not considered in this phase. All construction

    measures (excavation and support, as well as auxiliary measures) shall be derived from the determinedrock mass behavior determined in a consistent manner.

    - For underground structures with a limited length (portals, caverns, lay-bys, etc.) the evaluation should

    consider the entire length and geometry.

    - The following influencing factors are usually considered for the evaluation of the Rock Mass Behavior:

    a) Rock Mass Type (RMT)

    b) Virgin stress conditions

    c) Shape, size, and location of the underground structure

    d) Excavation method

    e) Relative orientation of the underground structure and discontinuities as a basis for kinematical

    analyses, and the influence of the rock mass structure on the stress redistribution

    f) Ground water, seepage force, hydraulic head

    For the determination of the rock mass behavior the following evaluations are recommended:

    g) Kinematics: Kinematical analyses for the determination of discontinuity controlled overbreak and

    sliding of wedges

    Tunnelling Philosophy An Engineering Perspective 43

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    58/355

    44 Pir Panjal Railway Tunnel

    Methods: Key Block Theory , analyses using stereographic projection

    h) Rock mass utilization: evaluation of the ratio between the strength of the rock mass and the spatial

    and transient stress situation in the vicinity of the underground opening.

    Methods: analytical and numerical methods

    i) Time dependent effects: evaluation of creeping, swellingj) Failure mechanisms: possible failure mechanisms of the rock mass have to be analyzed and described

    at least qualitatively (for example: spalling, shearing along discontinuities as result of stress release,

    shear failure, etc.)

    Methods: model tests, analytical analyses, numerical analyses, which allow the modeling of discrete

    failure planes, case histories, which are backed up by measurement results.

    - Analytical and/or numerical methods are to be used, which provide appropriate modeling methods for

    the characteristics of the rock mass types under evaluation under the given boundary conditions.

    - The Rock Mass Behavior Types resulting from the analyses have to be assigned to one of the general

    categories listed in Table 2.2. In case more than one Behavior Type is identified in one of the general

    categories, sub types have to be assigned (for example 2/1, 2/2 for a rock mass with a different potential

    for overbreak with different combinations of joint sets or orientations)

    Behavior Type (BT) Description of potential failure modes/mechanisms during excavation of the

    unsupported rock mass

    1 Stable Stable rock mass with the potential of small local gravity induced falling or sliding

    of blocks

    2 Stable with the potential of Deep reaching. discontinuity controlled, gravity induced falling and sliding of

    discontinuity controlled blocks, occasional local shear failure

    block fall

    3 Shallow shear failure Shallow stress induced shear failures in combination with discontinuity and gravity

    controlled failure of the rock mass.

    4 Deep seated shear failure Deep seated stress induced shear failures and large deformation

    5 Rock burst Sudden and violent failure of the rock mass, caused by highly stressed brittle

    rocks and the rapid release of accumulated strain energy

    6 Buckling failure Buckling of rocks with a narrowly spaced discontinuity set, frequently associated

    with shear failure

    7 Shear failure under low Potential for excessive overbreak and progressive shear failure with the

    confining pressure development chimney type failure, caused mainly by a deficiency of side pressure

    8 Ravelling ground Flow of cohesionless dry or moist, intensely fractured rocks or soil

    9 Flowing ground Flow of intensely fractured rocks or soi l with high water content

    10 Swelling Time dependent volume increase of the rock mass caused by physical-chemicalreaction of rock and water in combination with stress relief, leading to inward

    movement of the tunnel perimeter

    11 Heterogeneous rock mass Rapid variations of stresses and deformations, caused by block-in-matrix rock

    with frequently changing situation of a tectonic mlange (brittle fault zone)

    deformation characteristics

    Table 1.2: General categories of Rock Mass Behavior Types

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    59/355

    c) Records

    Each Rock Mass Behavior Type has to be described sufficiently. The following list represents the minimum

    requirements:

    - Sketch of the expected rock mass structure

    - Rock Mass Type(s)

    - Orientation of relevant discontinuities relative to the underground structure

    - Rock mass strength/utilization

    - Ground water, both quantities and influence on rock mass behavior

    - Rock mass behavior (behavior during excavation, face stability, type of failure mechanism, long term

    behavior) with sketches of expected failure mechanisms

    - Displacements, estimate of magnitude, orientation, and development over time

    In case more than one Behavior Type is determined in one general category, the delimiting criteria for the

    sub types can be:

    - Rock Mass Type- Rock mass structure

    - Ground water

    - Kinematics, failure mode

    - Magnitude and time dependent development of displacements

    d) Determination of excavation and support

    After the Rock Mass Types and the Behavior Types have been determined, appropriate construction methods

    (excavation sequence, separation of faces, support methods, and auxiliary measures if required) are

    determined. The following step evaluates the System Behavior (representing the interaction between the

    rock mass behavior and construction measures), which is then compared to the design requirements. Influencing factors for the System Behavior are:

    - Rock Mass Behavior Type

    - Shape and size of underground opening, considering intermediate construction steps

    - Spatial and timely construction sequence

    - Time dependent properties of the rock mass and support elements, if relevant

    - Support elements, their place and time of installation

    Method

    - The analysis methods depend on the boundary conditions of the underground structure investigated.

    Basically the following methods for analysis of the System Behavior are applicable:

    a) Analytical methods

    b) Numerical methods

    c) Comparative studies, based on experience from previous similar projects

    - The variability of the influencing factors, as well as the influence of the construction on the environment

    has to be considered.

    Tunnelling Philosophy An Engineering Perspective 45

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    60/355

    46 Pir Panjal Railway Tunnel

    - Analysis and Proofs: The system behavior shall be confirmed by analyses and compared with the design

    requirements. The analysis of the system behavior shall decide:

    a) The stability of all construction stages.

    b) The compliance with environmental requirements (surface settlements, vibrations ground water

    disturbance, etc.)

    c) that displacements are within defined limits (critical strain, serviceability, compatibility)

    e) Determination of excavation classes

    After the final determination of all construction related measures related to the rock mass behavior,

    excavation classes must be determined. In Austria this is according to ONORM B2203-1. The excavation

    classes by definition are required to specify the underground work, enable a cost estimate, and provide the

    basis for compensation. The two parameters, the round length and a support rating (normalized support

    quantity value) define the excavation classes.

    An excavation class may be assigned to more than one Behavior Type, as the same measures can be

    appropriate for different rock mass behavior types. On the other hand it may be required to design more

    than one excavation class for one Behavior Type, in case the variation of properties requires a wider rangeof support measures. Preferably in such cases separate Behavior Types should be defined, with clear limiting

    criteria (for example range of displacements, volume of expected overbreak, etc.). However, if one Behavior

    type requires different excavation classes depending on local influencing factors then the criteria should be

    reevaluated and new behavior type determined with clear limiting criteria (for example the expected range

    of displacements, volume or location of expected overbreak, etc.

    To establish the bill of quantities a prediction of the distribution of excavation classes is required. This

    distribution has to be established for the most probable distribution of Behavior Types, and should also

    show the likely variations of excavation classes resulting from the distribution (variation, spread) of

    influencing factors. When establishing the distribution of excavation classes along the alignment the

    heterogeneity of the rock mass has to be considered. In very heterogeneous ground, frequently changing

    the excavation and support methods in many cases will be technically and economically unfeasible.

    f) Geotechnical Report

    The results of the geotechnical design have to be summarized in a Geotechnical Report. In this report, the

    single steps outlined in this guideline have to be shown in a way to allow a review of the decisions taken.

    The individual reports submitted by the various expert teams involved in the project form the basis for the

    Geotechnical Report. Experts, geotechnical engineers and the tunnel designer should prepare the report in

    a joint effort.

    Contents of the Geotechnical Report

    - A summary of the results of geological and geotechnical investigations, and the interpretation of the

    results.

    - A description of the Rock Mass Types and the associated key parameters

    - A description of the Rock Mass Behavior Types, the relevant influencing factors, the analyses performed,

    and the geotechnical model on which the BT is based

    - A report on the determination of excavation and support, relevant scenarios considered, analyses applied,

    and results

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    61/355

    - The baseline construction plan

    - Detailed specifications to the Baseline construction plan (system behavior, measures to be determined

    on site, warning criteria and limits, etc.)

    - Report on the determination of excavation classes, their distribution along the alignment

    Contents of the Baseline Construction PlanThe baseline construction plan summarizes the geotechnical design and should contain following information:

    - Geological model with distribution of Rock Mass Types and Behavior Types in a longitudinal section

    - Sections, where specific requirements for construction have to be observed

    - Fixed excavation and support types (round length, excavation sequence, overexcavation, invert distance,

    support quality and quantity, ground improvements, etc.)

    - List of measures to be determined on site (support ahead of the face, face support, ground improvement,

    drainage, etc.)

    - Description of System Behavior (behavior during excavation, deformation characteristics, utilization of

    supports, etc.)

    - Warning criteria and levels, as well as remedial measures according to the safety management plan

    2.3.4 NATM Process on site

    The simplified steps of an underground transition created with NATM are shown below.

    Step #1

    Cutting a length of tunnel,with a roadheader/

    Excavator/Drill &Blast

    Tunnelling Philosophy An Engineering Perspective 47

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    62/355

    48 Pir Panjal Railway Tunnel

    Step#2

    Applying layer of shotcrete on reinforcementmesh and thereafter Rockblt

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    63/355

    Step#3

    Primary lining applied to whole cavity, which

    remains under observation.

    Step#4

    Final lining applied.

    Step#5

    Completed Tunnel

    Tunnelling Philosophy An Engineering Perspective 49

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    64/355

    50 Pir Panjal Railway Tunnel

    2.4 Appointment of the Detailed Design and Construction Supervision Consultant (DDC)

    A New Initiative:

    2.4.1 The detailed design and construction of the new Rail line project in Pir Panjal range of the Himalayas (a

    relatively young Geological Formation) was a big challenge for Engineers. It is well known that Himalayan

    geology is complex full of frequently changing formation and surprises. Folds, thrust zones and Faults arecommon. The strata comprises Fluvioglacial deposits, Limestone , Quartzite , Slate and Tuff , Volcanic traps

    and bands of Shale, Sandstone and Limestone. The geology along the chosen alignment comprises rocks

    with unconfined compressive strength ranging between 60MPa to 140 MPa, and at places laden with

    considerable amount of trapped water.

    2.4.2 All Underground works are prone to unforeseen problems. Geological and Geotechnical investigations can

    only provide some clues to these problem but their gravity can best understood only when encountered. In

    Pir-Panjal tunnel the defined alignment shows it commencing in soft ground with low overburden at each

    end. This low cover was due to the nallahs flowing over the tunnel alignment. Both nallahs are perennial in

    nature and are situated at tunnel meters 220 and 442 at its North and South ends respectively. The tunnel

    alignment passes under populated villages, NH-1A, and an Aquifer with considerable charge of water. These

    make the construction more difficult.2.4.3 It is also to be noted that the region falls in seismic Zone-V of the country ,which experiences severe tectonic

    movement and seismicity.

    2.4.4 Besides the unpredictable geology, the terrain, the mode of communication and the climatic conditions

    impose further challenges in the construction of the countrys longest railway/transportation tunnel. It was

    almost a dream to construct this Tunnel which would be open a marvel of civil engineering. National Highway

    NH 1A is the only link between Jammu and Srinagar, the winter and summer capitals of the state of Jammu

    & Kashmir. Landslides close this Highway frequently during the snows and also the rainy season. This cuts off

    road communication the only available economical mode of communication between the two capitals.

    2.4.5 The clear objective of the Indian Railways is to establish a dependable all weather rail transportation in the

    state of Jammu and Kashmir and connect it with the rail network in the rest of the country.

    2.4.6 The in house knowledge and expertise available in this field within the Railways was very limited and

    inadequate to meet the requirements of design of the tunnel of this magnitude. The tunnel had to be designed

    and constructed catering for ventilation and disaster safety aspects. Considering these factors, it was desirable

    to engage the services of a consultant who would design the tunnel system as a whole, together with the

    construction methodology, also rendering the technical know-how during the process of construction through

    the variable strata conditions.

    2.4.7 Keeping the above requirements in view, the notice for expression of interest for design of this tunnel was

    issued, inviting applications from different firms agencies, who were interested in associating themselves

    with the design and construction supervision of this tunnel.

    2.4.8 In response of NIT for this work, 25 firms/consultants showed interest, evaluation and selection of Consultant

    for this complex and highly specialized assignment was done on QCBS method (quality and cost based system).

    In the evaluation, 80% weight age was given to the technical competence of the consultant.

    2.5 Main Deliverables Required from DDC

    2.5.1 The detailed design and construction supervision consultant (DDC) required to prepare detailed engineering

    documentation required for actual implementation of work In summary, the DDC had to :

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    65/355

    (i) Develop design criteria: The consultant shall prepare comprehensive design criteria that achieve the

    objectives of the Project which had to deal with the vagaries of the varying geology coupled with soft

    ground and high overburden and trapped water formations.

    . The design criteria was to be prepared and presented in such a way that these could be readily applied by

    the DDC and any other design consultant (such as the one that was to be engaged under a design and

    construct contract). The design criteria has to include all requisite and incumbent assumptions regardingloads imposed, deformations expected and to be accounted for in the design in a way that the proposed

    method could deal with the varying geology and other existing conditions.

    (ii) Prepare schematic designs for all elements of the Project, Notwithstanding any earlier feasibility studies,

    the DDC was required to develop the relevant outline designs for a number of different options for the

    main Tunnel, the Access drive inside the tunnel, the Shaft, the approach roads and, if appropriate, the

    slope protection works to enable options to be objectively compared against each other. Each option had

    to developed in sufficient detail to demonstrate that the project objectives and design criteria had been

    complied with and to enable estimate the preliminary construction costs to enable prepare the construction

    program. The DDC had then to formulate an objective method for comparing the options in order to select

    the design of the preferred scheme.

    (iii) Formulate the construction methodology, construction sequences and the construction program.

    (iv) Design the Tunnel ventilation system during construction and during subsequent service

    (v) Design the Drainage system as appropriate during and after construction

    (vi) Define the scope and requirement of safety and disaster management

    (vii) Detailed planning;-The DDC was required to prepare a program for all aspects of the project implementation,

    including for the activities within the DDCs scope of services and those that were to be undertaken by

    others concerned. This was to be referred to as the project program. This program had to reflect the agreed

    procurement strategy and Scheme Designs for all elements of the Project. It had to be achievable and

    accompanied by a commentary which had to identify options and alternative scenarios where ever

    appropriate.

    (viii) Define requirements for any further investigations or tests, Additional studies prior to and during the detaileddesign phase (expected to be needed) to provide important information that would reduce any uncertainty

    that would be associated with the technical, and commercial aspects of the Project. The DDC had to identify

    the extent of the above studies and any other studies considered appropriate which would lead to the

    overall objective of reducing all risks to acceptable levels. As part of this undertaking the DDC had to define

    in detail where and if appropriate how the additional studies would be executed and what the objectives of

    the studies would be.

    (ix) Prepare tender documents for all elements of the Project. The DDC was required to prepare comprehensive

    detailed technical specifications, setting out the objectives of the requisite studies, the required deliverables

    and the information that would be provided by the DDC to form part of the studies. These technical

    specifications, where appropriate, had to set out the minimum requirements for tests e.g. scale, duration,

    sample type, etc.(x) Assist with the prequalification and appointment of contractors who would be responsible for the

    construction of this long Tunnel forming part of the Construction of Udhampur Srinagar Baramulla

    Broad Gauge Rail Link

    Tunnelling Philosophy An Engineering Perspective 51

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    66/355

    52 Pir Panjal Railway Tunnel

    2.6 Salient Features of Pir Panjal Tunnel

    GENERAL FEATURES

    CLIENT NORTHEN RAILWAY

    PRIME CONTRACTOR IRCON INTERNATIONAL LIMITEDSUB CONTRACTORS M/S HCC LTD, FOR PACKAGE V-A & V-B &BUMI DEVELOPERS

    FOR SOFT GROUND TUNNELLING

    CONSULTANT M/S GEO CONSULT RITES JV

    TOTAL LENGTH OF TUNNEL 10.960 Km

    TOTAL LENGTH OF TUNNEL INCLUDING CUT

    AND COVER PART 11.215 Km

    WORK AT SOUTH PORTAL COMMENCED ON 10Aug 2005

    WORK AT NORTH PORTAL COMMENCED ON 30 July 2005

    WIDTH OF TUNNEL AT 2.167 M above rail level 8.394 m

    FINISHED WIDTH At rail level 7.331 m

    FINISHED HIGHT Above rail Level 6.629 m

    FINISHED CROSS SECTIONAL AREA OF TUNNEL 48 m2

    FINISHED PERIMETER OF TUNNEL 26 m

    EXCAVATED CROSS SECTIONAL AREA OF TUNNEL 59 m2TO 80 m2

    DIFFRENCE BETWEEN C/L OF TUNNEL AND

    C/L OF TRACK 1.196m

    TYPE OF CONSTRUCTION SINGLE LINE TRACK WITH 3 M WIDE RESCUE ROAD ON ONE SIDE

    METHOD OF CONSTRUCTION NEW AUSTRIAN TUNNELLING METHOD (NATM)FINAL INNER LINING CONCRETE M30

    OUTER LINING SHOTCRETE M25

    2.TECHINAL PARAMETERS

    FORMATION LEVEL AT SOUTH END 1713.15 m

    FORMATION LEVEL AT NORTH END 1756.22 m

    TUNNEL HIGH POINT (altitude) 1771.479 m at CH 159+124

    DESIGN SPEED 100 KmPh

    TUNNEL CURVATURE (in plan) STRAIGHT (INFINITY)

    RULING GRADIENT 1 IN 100

    GEOLOGICAL FEATURE / ROCK TYPE FAULTED MOUNTAIN RANGE WITH SILTY CLAY SOIL, SHALE, LIMESTONE,

    QUARTZITE, AGGLOMERATIC SHALE, ANDESITE/BASALT

    RAIL GAUGE 1676 mm

    TRACK 60KG HH ,RHEDA 2000 BLT WITH VOSSLOH 300-1U FASTENING SYSTEM

    VENTILATION BY JET FANS

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    67/355

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    68/355

    54 Pir Panjal Railway Tunnel

    Chapter 3

    Exploring The Unknown

    3.1 Geological And Geotechnical Investigations

    3.1.1 These investigations are the key to tunneling with comprehensiveness that urges well for reliability and

    simplicity that permit convenient repetition of procedures and support-systems during construction.

    Knowledge of ground conditions plays a key role in choosing the optimized construction technique which

    ultimately leads to successful completion of the Project. It is important to realize that the ability to influence

    the project outcome (in terms of cost and schedule) is easier only through proper site investigations.

    3.1.2 However, it is worth mentioning here that no matter how much of the ground we test in the preliminary site

    investigation, how many bore hole cores we test in the laboratory, even then we can test only a small portion

    of the total strata affected by the construction of the Tunnel.

    3.1.3 Preliminary site investigations only help in making merely an informed decision but investigations conducted

    during construction and the continuous measurements made during construction are essential to compare

    the actual with the data anticipated from the preliminary site investigations. It is important to realize thatthe preliminary site investigations only help in closing-in on the ground model that develops and evolves as

    the project progresses.

    3.1.4 Site investigation is defined as the overall investigation of sites associated with tunnel construction including

    the overhead and subsurface strata investigation. The aim of site investigation is to produce a full three

    dimensional model of the site including the overhead and the subsurface strata. This can assist in guessing

    the associated risk involved in the tunneling work. The risk can then be assessed and its mitigation attempted

    using the appropriate construction technique.

    3.1.5 The cost involved in carrying out appropriate site investigation can range between 1% to 3% of total the cost

    of the Tunnel Project. It is important to use this money wisely to enable encounter the risks likely to be faced

    during the actual construction.

    3.1.6 In the subsurface works pre- and post-construction investigations play important roles in planning, designing,

    and in the actual construction work. Tunnel construction is governed by the ground through which it is to

    penetrate and hence overhead and subsurface site investigations are vital to obtain the requisite ground

    characteristics the geotechnical and hydrological parameters. Hidden Geology and Hydrology not only

    influence the cost of the project but also the completion time, the potential in service behavior of the

    structure and in deciding the long term maintenance strategies and procedures. The Geology of the area can

    affect the alignment of the railway line in hilly terrain. Hence a serious combined effort is necessary from all

    parties that are involved in planning, designing and construction.

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    69/355

    Exploring The Unknown 55

    3.1.7 Geology of the strata to be tunneled through plays significant role in the planning and construction of the

    tunnel. Subsurface work can pose formidable, if not impossible challenges to the geotechnical design and

    construction teams.

    3.1.8 In this chapter an attempt is made to explain the importance of geological and geotechnical investigations

    that were required in planning, designing and constructing the Pir-Panjal Railway Tunnel. It emphasizes on

    overall approach and the flexible rules set out for investigation in the complex geological conditions. Great

    care had to be taken in the geological and geotechnical investigations called for in the construction of this

    10.960 Km long Pir-Panjal tunnel. The Tunnel construction schedule necessitated construction of an Access

    Tunnel and Shaft for creating additional faces (fronts) for taking up the Tunnel excavation. This tunnel is for

    a single track Broad Gauge Railway line with approximately 3m wide side service road in the west side of the

    tunnel. It is a straight tunnel aligned nearly in N-S direction. It has a maximum overburden of 1.2 Km and

    minimum overburden as low as 10m.

    3.2 Importance of Investigations Required for The Construction of Tunnel

    3.2.1 Geology of the area affects almost every major decision that must be taken in the planning, design, andconstruction of a tunnel. Geology dictates the cost of the project and behavior of the structure. Indeed

    geology and hydrology of the area in the tunnel construction dominantly effects nearly all aspects of planning,

    design, construction and even the subsequent maintenance work.

    3.2.2 In view of rather complex geology and surface conditions in the Pir-Panjal range, our approach had to be

    very flexible and yet elaborate. This definitely helped in deciding the support systems in a way that lead to

    limited over-breaks in the excavation, less risk of collapse and ultimately prevented any major incidents. This

    helped in optimizing construction time and cost. Geological and geotechnical investigations in complex

    geological ambience can be divided in three phases, namely:- 1) investigations required during fixing of

    alignment, 2) investigations required before detailed design and tendering and 3) investigations required

    during construction.

    3.2.3 Himalayas present a rather young folded mountain range whose geology is complex and rapidly changing.Detailed geological and geotechnical investigations of the project area were carried out and a surface map of

    the project area 500m either side of the alignment was developed together with tectonic and drainage map.

    On the basis of these maps limited seismic surveys were conducted in the soft ground near the portals to

    know more about the effects of the low overburden strata there.

    3.2.4 Due to steep slopes, accessibility along the tunnel alignment was severely limited to allow extensive

    geotechnical investigations along the alignment. Geo-technical explorations were carried out by drilling 76mm

    dia cores and testing them. More deep bore geotechnical investigations were done in an attempt to understand

    the medium to be tunneled through, to establish various bedding planes and to verify the geological profile

    based on the captured surface geological data. M/s RITES and M/s Mineral Exploration Corporation Limited

    (MECL) were engaged for drilling bore holes varying in depth from 30m to 640m. Majority of these extended

    below the formation level of the tunnel. Deep bore holes were drilled by wire line method hence weresusceptible to deviate from direction and some times the results could well be misleading. Despite these

    limitations, a fairly good knowledge of the rocks that were likely to be encountered, was obtained from

    initial investigation. A total of 14 bore holes were drilled in all.

    3.2.5 A significant variation was expected between the predicted geology and the actual geology owing to presence

    of weathering in the rock under low rock cover and presence of deep seated faults and folds. Probe holes

    were drilled during the progress of the Tunnel work in entire length. These proves very useful in obtaining

    the required Geological and Geotechnical inputs. Based on the results of these probe holes and the geology

    actually encountered, geological predictions were made for the approaching face. This helped in deciding

  • 7/23/2019 Pir Panjal Railway Tunnel - A dream realized

    70/355

    56 Pir Panjal Railway Tunnel

    the support system in advance. In addition to probe holes, Seismic prediction method at the face was also

    used to know the geology ahead, but this method was not found very useful on account of rapidly changing

    geology.

    3.3 Why these Investigations are Necessary?

    These are necessary in order to:

    3.3.1 Establish at least the general nature, the pattern and some properties and behavior of the rock/soil mass,

    3.3.2 Assess the the most probable conditions and the most unfavourable conceivable deviations from these

    conditions which play a major role in the assessment of geology.

    3.3.3 Establish a design based on a workable hypothesis regarding the behavior anticipated under the most probable

    of conditions.

    3.3.4 Estimate the quantities likely to be executed on the basis of the working hypothesis as construction proceeds.

    3.3.5 Estimate the quantities under the most unfavourable conditions.

    3.3.6 Selection in advance of any action on or modification of the design for every foreseeable (significant) deviation

    of the observable findings vis--vis those predicted on the basis of the working hypothesis.

    3.3.7 Modify design to suit actual site conditions.

    3.4 Classification of Investigations

    3.4.1 The required investigations can be classified as follows:

    i) Preliminary investigations,

    ii) Design investigations and

    iii) Control investigations.

    i) Preliminary Investigations

    Investigations needed to access general suitability of the site and compare different alignments with due consideration

    of third party.

    ii) Design Investigations

    Investigations needed to provide information required for design of tunnel including its construction methodology.

    iii) Control Investigations

    Investigations required during construction or execution of the project for checking and alerting against the ground

    characteristics and ground water condition.

    3.4.2 A typical site investigation comprises following four key el