PLANNINGANDCONTROLUSING

ORACLE®PRIMAVERA®P6Versions8.2to8.4EPPMWEB

“EnterprisePortfolioProjectManagement”

PlanningandProgressingProjectSchedulesWithandWithout

RolesandResourcesinan

EstablishedDatabase

BY

PAULEASTWOODHARRIS

Page 3: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

©Copyright2014byEastwoodHarrisPtyLtd.Nopartofthispublicationmaybereproducedorusedinanyformorbyanymethodwithoutthewrittenpermissionoftheauthor.

OracleandPrimaveraareregisteredtrademarksofOracleand/oritsaffiliates.

Windows,Microsoft®OfficeProjectStandard2013,Microsoft®OfficeProjectProfessional2013,Microsoft®OfficeProjectStandard2010,Microsoft®OfficeProjectProfessional2010,Microsoft®OfficeProjectStandard2007,Microsoft®OfficeProjectProfessional2007,Microsoft®ProjectStandard2003,Microsoft®ProjectProfessional2003,Microsoft®ProjectStandard2002,Microsoft®ProjectProfessional2002,Microsoft®Project2000,MicrosoftProject®98andExcelareregisteredtrademarksofMicrosoftCorporation.

AstaPowerprojectisaregisteredtrademarkofAstaDevelopmentsplc.

Adobe®andAcrobat®areregisteredtrademarksofAdobeSystemsIncorporated.

Allothercompanyorproductnamesmaybetrademarksoftheirrespectiveowners.

ScreencapturesreprintedwithauthorizationfromOracleCorporation.

ThispublicationwascreatedbyEastwoodHarrisPtyLtdandisnotaproductofOracleCorporation.

DISCLAIMER

Theinformationcontainedinthispublicationistothebestoftheauthor’sknowledgetrueandcorrect.Theauthorhasmadeeveryefforttoensureaccuracyofthispublication,butmaynotbeheldresponsibleforanylossordamagearisingfromanyinformationinthispublication.Furthermore,OracleCorporationreservestherightintheirdocumentationtomakechangestoanyproductstoimprovereliability,function,ordesign.Thus,theapplicationofServicePacksortheuseofupgradedsoftwaremayresultinthesoftwareoperatingdifferentlyfromthedescriptionsinthispublication.

AUTHORANDPUBLISHER

PaulEHarrisEastwoodHarrisPtyLtdPOBox4032DoncasterHeights,3109Victoria,Australia

e-mail: [email protected]: http://www.eh.com.auTel: +61(0)41118770Skype [email protected]

Pleasesendanycommentsonthispublicationtotheauthor.

ISBN978-1-925185-05-8–B5PaperbackISBN978-1-925185-06-5–A4SpiralISBN978-1-925185-07-2–eBook

13December2014

Page 4: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

INTRODUCTIONThispublicationisanupgradeoftheauthor’sunpublishedbookProjectPlanning&ControlUsingPrimaveraP6WebInterface-OneDayTrainingCourseandhasbeenwrittentoenablenewuserstolearntheplanningandschedulingfunctionsofPrimaveraVersions8.2to8.4EPPM(EnterprisePortfolioProjectManagement)WebClient.

ManyuserswillhavepriorexperiencewiththeP6WindowsClient,SureTrak,P3,AstaPowerprojectorMicrosoftProjectandtheauthorexplainswheretherearedifferencesintheproducts’functionality.

Theauthorwouldappreciateanyconstructivecommentsonhowthispublicationmaybeimproved.Feedbackcanbesubmittedtowww.eh.com.au.

SUMMARYThepublicationmaybeusedas:

Atrainingmanualforatrainingcourse,or

Aself-teachbook,or

Areferencemanual.

ThescreenshotsforthispublicationaretakenfromPrimaveraVersions8.2to8.4EPPMWebClient.

Atrainingcoursemayberunusingthispublicationanditincludesexercisesforthestudentstocompleteattheendofeachchapter.Afterthecourse,studentsmayusethispublicationasareferencebook.

Instructors’PowerPointpresentationsareavailablefromEastwoodHarriswebsites.

ThispublicationisidealforpeoplewhowouldliketoquicklygainanunderstandingofhowthesoftwareoperatesandexplainshowthesoftwarediffersfromthePrimaveraP6WindowsClient,P3,SureTrak,AstaPowerprojectandMicrosoftProject,thusmakingitidealforpeoplewhowishtoconvertfromtheseproducts.

CUSTOMIZATIONFORTRAININGCOURSESTrainingorganizationsorcompaniesthatwishtoconducttheirowntrainingmayhavethispublicationtailoredtosuittheirrequirements.Thismaybeachievedremoving,reorderingoraddingcontenttothepublicationandbywritingtheirownexercises.Pleasecontacttheauthortodiscussthisservice.

AUTHOR’SCOMMENTAsaprojectcontrolsconsultantIhaveusedanumberofplanningandschedulingsoftwarepackagesforthemanagementofarangeofprojecttypesandsizes.ThefirstpublicationsIpublishedwereuserguides/trainingmanualsforPrimaveraSureTrak,P3andMicrosoftProjectusers.Thesewerewellreceivedbyprofessionalprojectmanagersandschedulers,soIdecidedtoturnmyattentiontoPrimaveraEnterprise/PrimaveraP6afterarequestfromPrimaveraSystemsInc.towriteabook.Thispublicationfollowsthesameprovenlayoutofmypreviouspublications.Itrustthispublicationwillassistyouinunderstandinghowtouse

Page 5: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

PrimaveraP6onyourprojects.

APPRECIATIONIwouldlikethankMichaelJack,RanSunandJanHanakfortheirassistanceinwritingthisbook.IwouldalsoliketothankJesicaPaulaYaboforherassistanceinupdatingthisbookfromVersion8.2.

Page 6: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 7: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

CURRENTBOOKSPUBLISHEDBYEASTWOODHARRIS99TricksandTrapsforMicrosoftOfficeProject-IncludingMicrosoftProject2000to2007PlanningUsingPrimaveraProjectPlannerP3Version3.1-Revised2006PlanningUsingPrimaveraSureTrakProjectManagerVersion3.0-Revised2006ProjectPlanningandSchedulingUsingPrimaveraContractorVersion6.1-IncludingVersions4.1,5.0and6.1PlanningandSchedulingUsingMicrosoftOfficeProject2007-IncludingMicrosoftProject2000to2003-Revised2009PlanningandControlUsingMicrosoftProjectandPMBOK®GuideFourthEditionPlanningandControlUsingMicrosoftProject2010andPMBOK®GuideFourthEditionProjectPlanning&ControlUsingPrimaveraP6Version7-ForallindustriesincludingVersions4to7Updated2012PlanningandSchedulingUsingMicrosoftProject2010-Updated2013IncludingRevisedWorkshopsProjectPlanningandControlUsingOraclePrimaveraP6-Versions8.1,8.2&8.3ProfessionalClient&OptionalClientPlanificaciónyControldeProyectosUsandoOraclePrimaveraP6-Versiones8.1,8.2y8.3ClienteProfesionalyOpcional项目规划和控制ORACLEPRIMAVERAP6应用-版本8.1-8.4专业&可选客户端PlanningandControlUsingMicrosoftProject2010&PMBOK®GuideFifthEditionPlanningandControlUsingMicrosoftProject2013PlanningandControlUsingMicrosoftProject2013&PMBOK®GuideFifthEditionPlanningandControlUsingOraclePrimaveraP6-Versions8.2&8.3EPPMWeb99TricksandTrapsforMicrosoftProject2013ProjectPlanningandControlUsingOraclePrimaveraP6-Versions8.1to8.4ProfessionalClient&OptionalClientPlanningandControlUsingOraclePrimaveraP6-Versions8.2to8.4EPPMWeb

SUPERSEDEDBOOKSBYTHEAUTHORPlanningandSchedulingUsingMicrosoft®Project2000PlanningandSchedulingUsingMicrosoft®Project2002PlanningandSchedulingUsingMicrosoft®Project2003PlanningandSchedulingUsingMicrosoft®OfficeProject2007PRINCE2TMPlanningandControlUsingMicrosoft®ProjectPlanningandControlUsingMicrosoft®ProjectandPMBOK®GuideThirdEditionProjectPlanningandSchedulingUsingPrimaveraEnterprise®–TeamPlayVersion3.5ProjectPlanningandSchedulingUsingPrimaveraEnterprise®–P3e&P3e/cVersion3.5ProjectPlanningandSchedulingUsingPrimavera®Version4.1forITProjectProjectPlanningandSchedulingUsingPrimavera®Version4.1orE&CPlanningandSchedulingUsingPrimavera®Version5.0–ForITProjectOfficePlanningandSchedulingUsingPrimavera®Version5.0–ForEngineering&ConstructionProjectPlanning&ControlUsingPrimavera®P6–UpdatedforVersion6.2

Page 8: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

PlanningUsingPrimaveraProjectPlannerP3®Version2.0PlanningUsingPrimaveraProjectPlannerP3®Version3.0PlanningUsingPrimaveraProjectPlannerP3®Version3.1ProjectPlanningUsingSureTrak®forWindowsVersion2.0PlanningUsingPrimaveraSureTrak®ProjectManagerVersion3.0PlanningandControlUsingOraclePrimaveraP6-Version8.1ProfessionalClient&OptionalClientPlanning&ControlUsingPrimavera®P6TMForallindustriesincludingVersions4to7PlanningandControlUsingOraclePrimaveraP6-Versions8.2EPPMWebPlanningandControlUsingOraclePrimaveraP6-Versions8.2&8.3EPPMWebPlanningandControlUsingOraclePrimaveraP6-Version8.1&8.2ProfessionalClient&OptionalClientPlanningandControlUsingOraclePrimaveraP6-Version8.1,8.2&8.3ProfessionalClient&OptionalClient

Page 9: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

1INTRODUCTION1.1SoftwareInstallationandConfiguration1.2Purpose1.3RequiredBackgroundKnowledge1.4PurposeofPlanning1.5ProjectPlanningMetrics1.6PlanningCycle1.7LevelsofPlanning1.8MonitoringandControllingaProject

2CREATINGAPROJECTPLAN2.1UnderstandingPlanningandSchedulingSoftware2.2EnterpriseProjectManagement2.3UnderstandingYourProject2.4Level1–PlanningWithoutResources2.4.1CreatingProjects2.4.2DefiningtheCalendars2.4.3DefiningtheProjectBreakdownStructures2.4.4AddingActivities2.4.5AddingtheLogicLinks2.4.6DevelopingaClosedNetwork2.4.7SchedulingtheProject2.4.8CriticalPath2.4.9TotalFloat2.4.10FreeFloat2.4.11RelationshipColors2.4.12ConstraintsTypes2.4.13ProjectConstraints2.4.14ActivityConstraints2.4.15RiskAnalysis2.4.16ContingentTime2.4.17FormattingtheDisplay–ViewsandFilters2.4.18PrintingandReports2.4.19IssuingthePlan

2.5Level2–MonitoringProgressWithoutResources2.5.1SettingtheBaseline2.5.2TrackingProgress2.5.3CorrectiveAction

2.6Level3–SchedulingWithResourcesandRoles2.6.1EstimatingorPlanningforControl2.6.2TheBalanceBetweentheNumberofActivitiesandResources2.6.3CreatingandUsingResources2.6.4CreatingandUsingRoles2.6.5TheRelationshipBetweenResourcesandRoles2.6.6ActivityTypeandDurationType2.6.7Budgets2.6.8ResourceUsageProfilesandTables

Page 10: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

2.6.9ResourceOptimization2.7Level4–MonitoringandControllingaResourcedSchedule2.7.1MonitoringProjectswithResources2.7.2ControllingaProjectwithResources

3STARTINGUPANDNAVIGATION3.1ImplementingWebBasedProjectManagementTools3.2LoggingIn3.3PrimaveraP6Architecture3.3.1Databases3.3.2WebTools3.3.3WindowsClientServerTool3.3.4OtherTools

3.4P6WebFunctionalityAreasandInterface3.4.1DashboardsTab3.4.2PortfoliosTab3.4.3ProjectsTab3.4.4ResourcesTab3.4.5AdministerTab3.4.6AdministerMenu,MyPreferences3.4.7NavigatingAroundP6Web3.4.8BottomPaneTabs3.4.9SavingData

3.5ViewingProjectData–ProjectsTab3.5.1Projects,EPSTab3.5.2ProjectsTabMenuandActivitiesTab3.5.3OpeningaProject3.5.4ViewingtheOBS3.5.5MyPreferences–DateandTimeDisplay

3.6UnderstandingtheProjectsWindow3.6.1ActivitiesWindow3.6.2ActivitiesWindowMenu3.6.3ActivityToolbars3.6.4ViewingtheHierarchyforActivity,Project,andResourceCodes3.6.5Workspace3.6.6TeamUsage3.6.7Issues3.6.8Risks3.6.9Documents

3.7Right-clickingwiththeMouse3.8FullScreenModeIcon3.9MultipleBrowserWindowsandTabs3.10SearchFunction3.11AccessingHelp3.11.1OnlineHelpforP6Professional

3.12FindandReplaceOption3.13ClosingaProject

Page 11: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.14PopupWindows3.15ClosingDown3.16Workshop1–NavigatingAroundtheWindows

4CREATINGANEWPROJECT4.1CreatingaBlankProject4.2CopyanExistingProjectorEPSNode4.3UsingtheProjectTemplatesFunction4.3.1CreatingaNewProjectfromaTemplate4.3.2CreatingaNewTemplate

4.4ImportingaProject4.4.1PrimaveraFileTypes4.4.2NonPrimaveraFileTypes4.4.3XMLImport/ExportEnhancements4.4.4UN/CEFACTXMLDataExport4.4.5GranularDataControlDuringXMLImport

4.5SavingProjectInformationonChangingWindows4.6DeletingaProject4.7SettingUpaNewProject4.7.1Project,EPSGeneralTab4.7.2ProjectPreferencesForm

4.8SavingAdditionalProjectandEPSInformation–Notebooks4.10Workshop2–CreatingYourProject

5DEFININGCALENDARS5.1DatabaseDefaultCalendar5.2AccessingGlobal,ResourceandProjectCalendars5.3TheProjectDefaultProjectCalendar5.3.1UnderstandingtheProjectDefaultProjectCalendar5.3.2AssigningaDefaultProjectCalendar

5.4CreatingaNewGlobalCalendar5.5CreatingaNewProjectCalendar5.6SharedCalendar5.6.1CreatingaNewSharedCalendar5.6.2CreatingNewPersonalCalendar5.6.3PersonalandSharedCalendarsCalculationandDisplay

5.7Administer,MyCalendar5.8Promote,Copy,RenameandDeleteaCalendar5.8.1PromotingaProjectCalendartoGlobal.5.8.2CopyaCalendarfromOneProjecttoAnother5.8.3RenamingaCalendar5.8.4DeletingaCalendar

5.9BaseCalendars5.9.1UnderstandingBaseCalendars5.9.2RemoveaBaseCalendarfromaCalendar

5.10AdjustingCalendarWorkingHours5.10.1EditingCalendarWorkingHours5.10.2EditingSelectedDaysWorkingHours

Page 12: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

5.10.3ViewingtheCalendarWorkingHours5.10.4CalculationofActivityDurationsinDays,WeeksorMonths

5.11CalendarsforCalculatingProject,WBSandOtherSummaryDurations5.12TipsforMixedCalendarSchedules5.13Workshop3–MaintainingtheCalendars

6CREATINGAPRIMAVERAPROJECTWBS6.1ViewingandNavigatingtheWBS6.2CreatingandDeletingaWBSNode6.3WBSNodeSeparator6.4ActivityWindowWorkBreakdownStructureLowerPaneDetails6.5WBSCategories6.6WhyaPrimaveraWBSisImportant6.7Workshop4–CreatingtheWorkBreakdownStructure

7ADDINGACTIVITIESANDORGANIZINGUNDERTHEWBS7.1NewActivityDefaults7.1.1DurationType7.1.2PercentCompleteType7.1.3ActivityTypesandMilestones7.1.4CostAccount7.1.5Calendar7.1.6Price/Unit7.1.7Auto-numberingDefaults

7.2AddingNewActivities7.3DefaultActivityDuration7.4CopyingActivitiesfromotherPrograms7.5CopyingActivitiesinP67.6ElapsedDurations7.7FindingtheBarsintheGanttChart7.8ActivityWindow–BottomPane7.9DiscussionFeature7.10AssigningCalendarstoActivities7.11AssigningActivitiestoaWBSNode7.12ReorderingorSortingActivities7.13Undo7.14SummarizingActivitiesUsingWBS7.15SpellCheck7.16Workshop5–AddingActivities

8FORMATTINGTHEACTIVITYWINDOWANDVIEWS8.1FormattingtheProjectsActivityWindow8.2Views8.2.1UnderstandingViews8.2.2OpeningaView8.2.3CreateaView

8.3ColumnsandActivitySortOrder8.3.1SelectingtheColumnstobeDisplayed8.3.2SettingtheOrderoftheColumnsfromLefttoRightontheScreen

Page 13: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.3.3AdjustingtheWidthofColumns8.3.4FirstColumnDataDisplay8.3.5RenamingColumns8.3.6ActivitySortOrder

8.4Grouping8.5Filters8.5.1UnderstandingFilters8.5.2ApplyingaFilter8.5.3Removingafilter8.5.4CreatingaFilter8.5.5OneParameterFilter8.5.6TwoParameterFilter

8.6ImprovedFiltering8.7ProjectIDFilteringOptionforCreatingPortfolios8.8Bars8.9GanttChart–Timescale8.9.1CustomizeActivityViewform–GanttCharttab8.9.2Right-clickinTimescaleOptions8.9.3ZoomtofitIcon8.9.4DraggingtheTimescale

8.10ActivityNetwork8.11TableView8.12CalendarView8.13Access–SharingViewswithOtherUsers8.14Workshop6–FormattingtheBarChart

9ADDINGRELATIONSHIPS9.1Constraints9.2UnderstandingRelationships9.3UnderstandingLagsandLeads9.4UnderstandingtheLagCalendar9.5FormattingtheRelationships9.6AddingorRemovingRelationships9.6.1GraphicallyAddingandDeletingaRelationship9.6.2Adding,DeletingandEditingRelationshipswiththeActivityDetailsForm9.6.4AddingandDeletingRelationshipsUsingColumns9.6.5ChainLinking

9.7DissolvingActivities9.8CircularRelationships9.9RelationshipsDetailWindowontheActivitiesPage9.10SchedulingtheProject9.11Workshop7–AddingtheRelationships

10ACTIVITYNETWORKVIEW10.1IntroductiontotheActivityNetworkView10.2EarlyDate,LateDateandFloatCalculations10.3Workshop8–SchedulingCalculationsandActivityNetworkView

11CONSTRAINTS

Page 14: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

11.1AssigningConstraints11.1.1NumberofConstraintsperActivity11.1.2SettingaPrimaryConstraintUsingtheActivityDetailsForm11.1.3SettingaSecondaryConstraintUsingtheActivityDetailsForm11.1.4ExpectedFinishConstraint11.1.5SettingConstraintsUsingColumns11.1.6SettingConstraintsbyDragginganActivity

11.2ProjectMustFinishByDate11.3ActivityNotebooks11.3.1CreatingNotebookTopics11.3.2AddingNotes

11.4Workshop9–Constraints12PRINTINGANDREPORTS12.1PrintingtheGanttChart12.2PrintPreview12.3PageSetup12.3.1PageLayoutTab12.3.2HeaderandFooterTabs12.3.3CustomHeaderandCustomFooterTabs12.3.4SheetTab

12.4EnhancedPrintingfromtheEPSandActivitiesWindows12.5Reports12.6OtherPrimaveraReportingOptions12.7Workshop10–Printing

13SCHEDULINGOPTIONSANDSETTINGABASELINE13.1UnderstandingDateFields13.1.1EarlyStartandEarlyFinish13.1.2LateStartandLateFinish13.1.3ActualStartandFinish13.1.4StartandFinish13.1.5PlannedStartandFinish13.1.6PlannedDatesIssues13.1.7RemainingEarlyStartandFinish13.1.8RemainingLateStartandFinish

13.2SchedulingOptions–GeneralTab13.2.1Ignorerelationshipstoandfromotherprojects(&IgnoreExternalDates)13.2.2Makeopen-endedactivitiescritical13.2.3UseExpectedFinishDates13.2.4Scheduleautomaticallywhenachangeaffectsdates–NotintheWebClient13.2.5Levelresourcesduringscheduling13.2.6Recalculateassignmentcostsafterscheduling13.2.7Whenschedulingprogressedactivitiesuse13.2.8Calculatestart-to-startlagfrom13.2.9Definecriticalactivitiesas13.2.10Calculatefloatbasedonfinishdate13.2.11ComputeTotalFloatas

Page 15: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.2.12CalendarforschedulingRelationshipLag13.2.13SchedulingOptions–AdvancedTab

13.3SettingtheBaseline13.3.1CreatingaBaseline13.3.2DeletingaBaseline13.3.3RestoringaBaselinetotheDatabaseasanActiveProject13.3.4UpdateBaselines13.3.5CopyingaProjectwithBaselines13.3.6SettingtheBaselineProjectUnderstandingthe<CurrentProject>Baseline13.3.8DisplayingtheBaselineData

13.4AdditionalBaselineFields13.5Workshop11–WBS,LOEsandSettingtheBaseline

14UPDATINGANUNRESOURCEDSCHEDULE14.1PracticalMethodsofRecordingProgress14.2UnderstandingtheConcepts14.2.1ActivityLifecycle14.2.2AssigninganActualStartDateandTimeofanActivity14.2.3AssigninganActualFinishDateandTimeofanActivity14.2.4CalculationofDurationsofanIn-ProgressActivity14.2.5SummaryBarsProgressCalculation14.2.6UnderstandingtheDataDate

14.3UpdatingtheSchedule14.3.1UpdatingActivitiesUsingtheGeneralTaboftheDetailsForm14.3.2UpdatingActivitiesUsingColumns

14.4ProgressSpotlight14.5SuspendandResume14.6SchedulingtheProject14.7UpdateProject14.8ComparingProgresswithBaseline14.9ProgressLineDisplayontheGanttChart14.10CorrectiveAction14.11CheckListforUpdatingaSchedule14.12Workshop12–ProgressingandBaselineComparison

15ADMINISTERMENU15.1AdministerMenu15.2MyCalendar15.3MyPreferences15.3.1Global,GeneralTab15.3.2Global,General,TimeUnitsFormatTab15.3.3Global,ResourcesTab,ResourceStaffing15.3.4Global,ResourcesTab,ResourceAssignments15.3.5Global,ProjectScoreTab15.3.6Global,PerformanceThresholdTab15.3.7Global,CurrencyTab15.3.8Global,DateFormatTab

Page 16: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.3.9Global,IssuesTab15.3.10ViewTab15.3.11SettingaDefaultStartPage15.3.12PasswordTab

15.4ApplicationSettings15.4.1DataLimits15.4.2EarnedValue15.4.3General15.4.4IDLengths15.4.5Services15.4.6Timesheets15.4.7TimePeriods

15.5EnterpriseData15.5.1UnderstandingUDFsandActivityCodes15.5.2Currencies15.5.3FinancialPeriods15.5.4GlobalCalendars15.5.5Locations15.5.6OverheadCodes15.5.7TimesheetPeriods15.5.8Projects15.5.9Activities15.5.10Resources15.5.11Risks15.5.12Issues15.5.13Documents

15.6GlobalScheduleServices15.7UserAccess15.7.1Users15.7.2OBS15.7.3GlobalSecurityProfiles15.7.4ProjectSecurityProfiles15.7.5CopyUserViewswhenCopyingaUser

15.8UserSessions15.9MiscellaneousDefaults15.9.1DefaultProject

16CREATINGROLESANDRESOURCES16.1UnderstandingResourcesandRoles16.1.1IndividualResources16.1.2GroupResources16.1.3InputandOutputResources16.1.4UnderstandingRoles16.1.5UnderstandingResourceTeamsandRoleTeams

16.2CreatingRoles16.2.1DescriptionTab16.2.2ResourcesTab

Page 17: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

16.2.3PricesTab16.2.4LimitsTab16.2.5RoleTeamsTab

16.3CreatingResourcesandtheResourcesWindow16.3.1ResourcesGeneralTab16.3.2ResourceTeamTab16.3.3ResourcesRolesTab16.3.4ResourcesCodesTab16.3.5ResourcesUnitsandPricesTab16.3.6ResourcesSettingsTab16.3.7NotesTab

16.4Workshop13–AddingResourcestotheDatabase17ASSIGNINGROLES,RESOURCESANDEXPENSES17.1UnderstandingResources17.2UnderstandingResourceCalculationsandTerminology17.3ProjectPreferencesForm,ResourceDefaults17.3.1RateType17.3.2Resourcescanbeassignedtothesameactivitymorethanonce17.3.3UnderstandingResourceOptiontoDriveActivityDatesByDefault17.3.4Price/Unit17.3.5ActivityType17.3.6DurationType

17.4MyPreferencesApplicabletoAssigningResources17.4.1Units/TimeFormat17.4.2ResourceAssignments17.4.3ResourceAssignments

17.5ActivitiesWindowResourceInformation17.5.1DetailsGeneralForm

17.6AssigningandRemovingRoles17.7AssigningandRemovingResources17.7.1AssigningaResourcetoanAssignedRole17.7.2AssigningaResourcetoanActivityWithoutaRole17.7.3RemovingaResourceorRole17.7.4AssigningaResourcetoanActivityMoreThanOnce17.7.5SelectingMultipleItemsinAssignDialogForms

17.8RequestResources17.9ResourceandActivityDurationCalculationandResourceLags17.9.1ActivityDuration17.9.2ResourceLag–WindowsClientOnly

17.10Resource,PlanningWindow17.11Expenses17.12SuggestedSetupforCreatingaResourcedSchedule17.13Workshop14–AssigningResourcesandExpensestoActivities

18RESOURCEOPTIMIZATION18.1ReviewingResourceLoading18.2AssignmentsView

Page 18: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

18.3Resources,Analysis,RoleUsageWindow18.3.1Resources,Analysis,ResourceUsageWindow18.3.2Resources,Analysis,ResourceAnalysisWindow

18.4MethodsofResolvingResourcePeaksandConflicts18.5Workshop15–ResourcesOptimization

19UPDATINGARESOURCEDSCHEDULE19.1UnderstandingPlannedValuesandBaselineProjects19.1.1CostandUnitsPlannedValues19.1.2BaselineProjectandValues

19.2UnderstandingtheCurrentDataDate19.3InformationRequiredtoUpdateaResourcedSchedule19.4ProjectPreferencesDefaultsforUpdatingaResourcedSchedule19.4.1ProjectPreferencesCalculationsTab19.4.2ProjectPreferencesDefaultsTab

19.5ActivitiesWindow–PercentCompleteTypes19.5.1AssigningtheProjectDefaultPercentCompleteType19.5.2PhysicalPercentCompleteType19.5.3DurationPercentCompleteType19.5.4UnitsPercentCompleteType

19.6UsingStepstoCalculateActivityPercentComplete19.7UpdatingtheSchedule19.7.1Preferences,DefaultsandOptionsforUpdatingaProject19.7.2UpdatingDatesandPercentageComplete

19.8UpdatingResources19.8.1AssignmentsTab19.8.2GeneralTab19.8.3ApplyingActuals

19.9UpdatingExpenses19.10UpdatingUsingProgressReporter19.11Workshop16–UpdatingaResourcedSchedule

20OTHERMETHODSOFORGANIZINGPROJECTDATA20.1UnderstandingProjectBreakdownStructures20.2ActivityCodes20.2.1UnderstandingActivityCodes20.2.2ActivityCodeCreation20.2.3DefiningActivityCodeValues,DescriptionsandColors20.2.4AssigningActivityCodeValuestoActivities20.2.5AddActivityCodesWhenAssigningCodes20.2.6Grouping,SortingandFilteringwithActivityCodes20.2.7ImportingActivityCodeswithExcel

20.3UserDefinedFields20.4Workshop17–ActivityCodesandUserDefinedFields(UDF)

21INDEX

Page 19: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

1INTRODUCTION

1.1SoftwareInstallationandConfigurationThisbookdoesnotcoversoftwareinstallation.Webbasedtechnologiesoftenrequirespecialistknowledgetoimplementtoensurethesoftwarefunctionsasdesigned.

Duringthecourseofwritingthisbooktheauthorfoundthattheconfigurationsettingsofthebrowseroccasionallyneededadjustingtoallowpopupstoactivateandsomebrowserupdatestobeinstalled.

1.2PurposeThepurposeofthisbookistoprovideamethodforplanning,schedulingandcontrollingprojectsusingPrimaveraVersions8.2to8.4EPPMWebwithinanestablishedEnterpriseProjectdatabaseorablankdatabaseuptoanintermediatelevel.

TherearedifferencesbetweenhowtheP6V8.3WindowsClientandEPPMWebClientoperateandtheseareidentifiedthroughoutthebook.

TheP6WindowsClienthastwoversions:

•ProfessionalClientwherebythedatabaseMAYNOTbeaccessedbytheWebClientandadministrationfunctionsAREavailableinthistool,and

•OptionalClientwherebythedatabaseMAYbeaccessedbytheWebClientandadministrationfunctionsareNOTavailableinthistool.

InthisbookboththeProfessionalClientandOptionalClientwhicharebothWindowstoolswillbecollectivelyreferredtoastheWindowsClient.Thisbookcoversthefollowingtopics:

•Understandingthestepsrequiredtocreateaprojectplanandmonitoraproject’sprogress

•UnderstandingthePrimaveraP6environment

•Createaprojectandsetupthepreferences

•Definecalendars

•CreatingaWorkBreakdownStructureandaddingactivities

•Formatthedisplay

•Addlogicandconstraints

•UsingFilters,Group,SortandViews(LayoutsintheProfessionalandOptionalClient)

•Printreports

ThebookisnotintendedtocovereveryaspectofPrimaveraP6,butitdoescoverthemainfeaturesrequiredtocreateandupdateaprojectscheduleanunresourcedschedule.Itshouldprovideyouwithasolidgrounding,whichwillenableyoutolearntheotherfeaturesofPrimavera6byexperimentingwiththesoftware,usingthehelpfilesandreviewingotherliterature.

Page 20: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thisbookwaswrittentominimizesuperfluoustext,allowingtheusertolocateandunderstandtheinformationcontainedwithinasquicklyaspossible.Ifatanytimeyouareunabletounderstandatopicinthisbook,itissuggestedthatyouusethePrimaveraHelpmenuorUserManuals,whichareavailableonthesoftwareCDsinpdfformat,ortheOraclewebsitetogainafurtherunderstandingofthesubject.

1.3RequiredBackgroundKnowledgeThisbookdoesnotteachyouhowtousecomputersortomanageprojects.ThebookisintendedtoteachyouhowtousePrimaverainaprojectenvironment.Therefore,tobeabletofollowthisbookyoushouldhavethefollowingbackgroundknowledge:

•Theabilitytouseapersonalcomputerandunderstandthefundamentalsoftheoperatingsystem.

•Experienceusingapplicationsoftware,suchasMicrosoftOffice,whichwouldhavegivenyouexposuretoWindowsmenusystemsandtypicalWindowsfunctionssuchascopyandpaste.

•Asoundunderstandingofhowprojectsaremanaged,suchasthephasesandprocessesthattakeplaceoverthelifetimeofaproject.

1.4PurposeofPlanningTheultimatepurposeofplanningistobuildamodelthatenablesyoutopredictwhichactivitiesandresourcesarecriticaltothetimelycompletionoftheproject.Strategiesmaythenbeimplementedtoensurethattheseactivitiesandresourcesaremanagedproperly,thusensuringthattheprojectwillbedeliveredbothOnTimeandWithinBudget.Planningaimsto:•Identifythetotalscopeoftheprojectandplantodeliverit,

•Evaluatedifferentprojectdeliverymethods,

•IdentifyProducts/Deliverablesrequiredtodeliveraprojectunderalogicalbreakdownoftheproject,

•Identifyandoptimizetheuseofresourcesandevaluateiftargetdatesmaybemet,

•Identifyrisks,plantominimizethemandsetpriorities,

•Provideabaselineplanagainstwhichprogressismeasured,

•Assistinstakeholders’communication,identifyingwhatistobedone,whenandbywhomand

•Assistmanagementtothinkaheadandmakeinformeddecisions.

Planninghelpstoavoidorassistinevaluating:

•Increasedprojectcostsorreductioninscopeand/orquality,

•Additionalchangeoverand/oroperationcosts,

Page 21: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ExtensionsoftimeclaimsagainstyourcustomerorClient,

•LossofyourClient’srevenue,

•Contractualdisputesandassociatedresolutioncosts,

•Thelossofreputationofthoseinvolvedinaproject,and

•Lossofafacilityorassetintheeventofatotalprojectfailure.

1.5ProjectPlanningMetricsThecomponentsthatarenormallymeasuredandcontrolledusingplanningandschedulingsoftware:

•Scope

•Time

•ResourceEffort/Work(thesearecalledUnitsinPrimaveraP6)

•Cost

Achangeinanyoneofthesecomponentsnormallyresultsinachangeinoneormoreoftheothers.

Otherprojectmanagementfunctionsthatarenottraditionallymanagedwithplanningandschedulingsoftwarebutmayhavecomponentsreflectedinthescheduleinclude:

•DocumentManagementandControl,

•QualityManagement,

•ContractManagement,

•IssueManagement,

•RiskManagement,

•IndustrialRelations,and

•Accounting.

ThedevelopmentofEnterpriseProjectManagementsystemshasresultedintheinclusionof

Page 22: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

manyofthesefunctionsinprojectplanningandschedulingsoftware.Primaveraincludesmodulesfor:

•IssueManagement,

•RiskManagement,and

•DocumentManagement.

1.6PlanningCycleTheplanningcycleisanintegralpartofmanagingaproject.AsoftwarepackagesuchasPrimaveramakesthisactivitymucheasier.

Whentheoriginalplanisagreedto,theBaselineorTargetisset.TheBaselineisacopyoftheoriginalplanandisusedtocompareprogressofanupdatedschedule.Earlierversionswerelimited50baselinesbutthisrestrictionhasbeenremovedinlaterversions.

Afterprojectplanninghasendedandprojectexecutionhasbegun,theactualprogressismonitored,recordedandcomparedtotheBaselinedates.TheprogressisthenreportedandevaluatedagainsttheBaseline.

TheplanmaybechangedbyaddingordeletingactivitiesandadjustingRemainingDurations,LogicorResources.Arevisedplanisthenpublishedasprogresscontinues.ArevisedBaselinemaybesetiftheoriginalBaselinebecomesirrelevantduetotheimpactofprojectscopechanges,achangeinmethodologyorexcessivedelays.

Updatingascheduleassistsinthemanagementofaprojectbyrecordinganddisplaying:

•Progressandtheimpactofprojectscopechangesanddelaysastheprojectprogresses,

•Therevisedcompletiondateandfinalforecastofcostsfortheproject,

Page 23: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Historicaldatathatmaybeusedtosupportextensionoftimeclaimsanddisputeresolution,and

•Historicaldatathatmaybeusedinfutureprojectsofasimilarnature.

1.7LevelsofPlanningProjectsareoftenplannedatasummarylevelandthenatalaterdatedetailedoutbeforetheworkcommences.Smallerprojectsmaybescheduledindetailduringprojectplanning,butlargeorcomplexprojectsmayrequireseveraliterationsbeforetheprojectplanisfullydetailedout.

Themainreasonsfornotdetailingoutaprojectearlyarethat:

•Theremaynotbeenoughinformationatthatstageand

•Preparingdetailedscheduleswastestime,astheymaybemaderedundantbyunforeseenchanges.

Thefollowingplanningtechniquesdiscussedinotherwell-knownprojectmanagementbooksmaybeconsidered:

PMBOK®Guide

ThePMBOK®Guide,whichisaprojectmanagementreferencebookpublishedbytheProjectManagementInstitute,discussesthefollowingtechniques:

•TheRollingWave.Thistechniqueinvolvesaddingmoredetailtothescheduleastheworkapproaches.Thisisoftenpossible,asmoreinformationisknownaboutthescopeoftheprojectasworkisexecuted.TheinitialplanningcouldbecompletedatahighlevelintheWorkBreakdownStructure(WBS).Astheworkapproaches,theplanningmaybecompletedataWBSComponentandthentoaWorkPackagelevelplanning.

•TheuseofSub-projects.Theseareusefulinlargerprojectswheremorethanoneentityisworkingontheprojectschedule.Thissituationmayexistwhenportionsofprojectsarecontractedout.Asub-projectmaybedetailedoutwhentheworkisawardedtoacontractor.

•TheuseofPhases.APhaseisdifferentfromaPRINCE2Stage,asPhasesmayoverlapintimeandStagesdonot.Phasesmaybedefined,forexample,asDesign,ProcureandInstall.ThesePhasesmayoverlap,asProcurementmaycommencebeforeDesigniscomplete.ThePhasedevelopmentofascheduleinvolvesthedetailingoutofalltheassociatedWBSelementspriortothecommencementofthatPhase.

•ThePMBOK®GuidedoesnothavestrictdefinitionsforlevelsofplansbutassumesthatthisprocessisundertakenwhendecomposingtheWorkBreakdownStructure(WBS).Therearesomeothermodelsavailablethatmaybeusedasguidelines,suchasthePMI“PracticeStandardforWorkBreakdownStructures.”

PRINCE2PlansPRINCE2isaprojectmanagementmethodologythatwasdevelopedintheUK.Thismethodologydefinesthetypeofplansthataprojectteamshouldconsider.

StagesinPRINCE2aredefinedastime-boundperiodsofaproject,whichdonotoverlapin

Page 24: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

timeandarereferredtoasManagementStages.TheendofaStagemaysignifyamajorevent,suchassigningamajorcontract.ProjectPhasesmayoverlapintime,butStagesdonot.UnderPRINCE2aProjectPlanisdividedintoStagesandaStageplanisdetailedoutpriortoitscommencement.PRINCE2definesthefollowinglevelsofplans:

•ProgrammePlan–whichmayincludeProjectPlansoroneormoreportfoliosofmultipleprojects,

•ProjectPlan–thisismandatoryandisupdatedthroughthedurationofaproject,•StagePlan–thereisaminimumoftwoStagePlans:anInitiationStagePlanandFirst

StagePlan.TherewouldusuallybeoneStagePlanforeachStage,•ExceptionPlan–whichisatthesamelevelanddetailasaStagePlanandreplacesa

StagePlanattherequestofaProjectBoardwhenaStageisforecasttoexceedtolerances(contingenttime),and

•TeamPlan–whichisoptionalandwouldbeusedonlargerprojectswhereTeamsdeliverProductsthatrequiredetailedplanning.Atypicalexampleisacontractor’splan,whichwouldbesubmittedduringthebidprocess.

Jelen’sCostandOptimizationEngineeringThebookoutlinesseverallevelsofplanning,eachofwhichgoesdeeperintheplanningprocess,dependingonthelevelofgranularitytheplannerwantstoachieve:

•Level0:Correspondstotheprojectasawhole,thereforeitwillshowasanindividualbarintheGanttChartwhichextentwillbefromthestarttothefinishdateoftheproject.

•Level1:Thislevelprogrammestheprojectaccordingtoitsmostsignificantparts;hence,itwillshowlikeaBarChartontheGanttChart.Forexample,visualizeascheduleforafoodfactory,whichcouldbebrokendownintoqualitycontrol,processing,packagingandstorage.

•Level2:Thisleveltakesthepreviousoneasafoundationtokeepsplittingdownthepartsoftheproject.Generallytheschedulewillbeshowninabarchartformatanditcouldhavesomeconstraintsagainstit.Followingthepreviousexample,thestorageareainthefoodfactorycouldbefurtherdividedintodriedfoods,freshproduce,cannedproducts,etc.

•Level3:Thebreakdowngoesevenfurtherandatthispointitbecomesveryclearwherethecriticalpathis.Likewise,sincethisdivisionisnottoodetailed,thelevelofcontrolovertheprojectcanbeperformedverywell.

•Levels4–n:Fromthislevel,isuptotheplanner’sdecisiontokeepbreakingdowntheprojectintomoredetailedparts.Thistypeofplanningisusuallyperformedtobuildalook-aheadoftheschedulebetween1and6months.ThemostcommonpracticeistoshowthisschedulesinaBarChartformatorasCPMs.

1.8MonitoringandControllingaProjectAfteraplanhasbeenproduced,itshouldbeexecutedandtheworkauthorizedinaccordancewiththeplan.Ifthereistobeachangeintheplan,thentheplanshouldbeformallychanged.Ifnecessary,theclientshouldbeinformedand,ifrequiredbythecontract,approvalshouldbesought.

Page 25: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Itmaybedifficulttoobtainapprovalforextensionoftimeclaimswhentheplanisnotfollowedthenandfurthermorethiswillmakedisputeresolutionmoredifficult.

Monitoringaprojectrecordsprogresstodate:

•Recordsthestartandfinishdatesofcompletedactivities,

•Confirmsthattherequiredqualityismet,

•Thusconfirmsthedeliverables/productsthathavebeenproduced,

•Confirmsthatthedeliverables/productsareproducedontime,withtheplannedresourcesandtobudget,

•Recordstheprogressofstartedactivities,

•Appliestheproductivitytodateforfuturesimilaractivities,

•Addoramendscheduletoreflectchanges,and

•Historicaldataisrecordedforuseinplanningfutureprojects.

Controlling a project provides the next level of management with information that enablesthemtomanageaprojectandmakeinformeddecisionsonproblems:

•Ensurethattheprojectisbeingexecutedaccordingtotheplan,

•Comparetheproject’sprogresswiththeoriginalplan,

•Reviewstheproductivitytodateandhowthecurrentproductivitywillaffectfutureactivities,

•Forecastproblemsasearlyaspossiblewhichenablescorrectiveactiontobetakenasearlyaspossible,

•Reviewoptionstoimprovetheschedule,and

•Obtaindatarequiredforpreparingextensionoftimeclaimsandfordisputeresolution.

Page 26: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

2CREATINGAPROJECTPLANTheaimofthischapteristogiveanunderstandingofwhataplanisandsomepracticalguidanceonhowaschedulemaybecreatedandupdatedduringthelifeofaproject.

2.1UnderstandingPlanningandSchedulingSoftwarePlanningandschedulingsoftwareenablestheuserto:

•Enterthebreakdownstructureoftheprojectdeliverablesorproductsintothesoftware.ThisisoftencalledaWorkBreakdownStructure(WBS)orProductBreakdownStructure(PBS),

•BreakaprojectdownintotheworkrequiredtocreatethedeliverablesandentertheseintothesoftwareasActivitiesundertheappropriateWBS,

•Assigndurations,constraints,predecessorsandsuccessorsoftheactivitiesandthencalculatethestartandfinishdateofalltheactivities,

•Assignresourcesand/orcosts,whichrepresentpeople,equipmentormaterials,totheactivitiesandcalculatetheprojectresourcerequirementsand/orcashflow,

•Optimizetheprojectplantoensuretheuseofresourcesisoptimized,

•SetBaselineDatesandBudgetstocompareprogressagainst,

•Usetheplantoapprovethecommencementofwork,

•RecordtheactualprogressofactivitiesandcomparetheprogressagainsttheBaselineandamendtheplanwhenrequired,allowingforscopechanges,etc.,

•Recordtheconsumptionofresourcesand/orcostsandre-estimatetheresourcesand/orcostsrequiredtofinishtheproject,and

•Producemanagementreports.

Therearefourmodesorlevelsinwhichplanningandschedulingsoftwaremaybeused.

Planning Tracking

WithoutResources

LEVEL1

PlanningwithoutResources

LEVEL2

TrackingprogresswithoutResources

WithResources

LEVEL3

PlanningwithResources

LEVEL4

TrackingprogresswithResources

Asthelevelincreases,theamountofinformationrequiredtomaintaintheschedulewillincreaseand,moreimportantly,yourskillandknowledgeinusingthesoftwarewillincrease.ThisbookisdesignedtotakeyoufromLevel1toLevel4inasingleprojectenvironment.

2.2EnterpriseProjectManagement

Page 27: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

PrimaveraisanEnterpriseProjectManagementsoftwarepackagethatenablesmanyprojectstobemanagedinonedatabase.TheseprojectsmaybesummarizedunderahierarchicalstructuretitledtheEnterpriseProjectStructure(EPS).ThisfunctionissimilartosummarizingactivitiesofaprojectunderaWorkBreakdownStructure(WBS).

AnEPSisusedforthefollowingpurposes:

•Tomanageuseraccesstoprojectswithinthedatabase.

•Tomanageactivitiesovermultipleprojectsthathaveacommoninterest,suchasacriticalresource.

•Top-downbudgetingofprojectsandresourcesthatmaylaterbecomparedtothebottom-upordetailedprojectestimates.

•Toallowstandardizedreportingofallprojectsinthedatabase.

IndividualprojectsmustbecreatedwithinanEPSdatabase.PrimaverahasnotbeendesignedasasingleprojectplanningandschedulingsoftwarepackageandthereisanadministrativeoverheadinmanagingprojectsinanEPSdatabase.

PrimaverahasafunctiontitledPortfoliosthatenablesalimitednumberofprojectstobeviewedatatime.Forexample,Portfoliowouldenableyoutoviewprojectsinaphysicalarea,orofaspecifictypeorclient.

2.3UnderstandingYourProjectBeforeyoustarttheprocessofcreatingaprojectplan,itisimportanttohaveanunderstandingoftheprojectandhowitwillbeexecuted.Onlarge,complexprojects,thisinformationisusuallyavailablefromthefollowingtypesofdocuments:

•Projectcharterorbusinesscase

•Projectscopeorcontractdocumentation

•Functionalspecification

•Requirementsbaseline

•Plansanddrawings

•Projectexecutionplan

•Contractingandpurchasingplan

•Equipmentlists

•Installationplan

•Testingplan

ManyprojectmanagersconductaStakeholderAnalysisatthestartofaproject.Thisprocesslistsallthepeopleandorganizationswithaninterestintheprojectandtheirinterestsordesiredoutcomes.

•Keysuccessfactorsmaybeidentifiedfromtheinterestsoftheinfluentialstakeholders,and

•Itisimportanttousethestakeholderanalysistoidentifyallthestakeholderactivitiesand

Page 28: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

includethemintheschedule.

Itisimperativetogainagoodunderstandingofhowtheprojectistobeexecutedbeforeenteringanydataintothesoftware.Itisconsideredgoodpracticetoformallyplanaprojectbeforecreatingascheduleinanyplanningandschedulingsoftware.ThesedocumentsarereferredtobymanytermssuchasProjectExecutionPlanorProjectMethodologyStatement.Youshouldalsounderstandwhatlevelofreportingtheprojectteamrequires,asprovidingeithertoolittleortoomuchdetailwilloftenleadtoadiscardedschedule.

Therearethreeprocessesrequiredtocreateormaintainaplanateachofthefourlevels:

•Collectingtherelevantprojectdata,

•Enteringandmanipulatingthedatainsoftware,and

•Distributing,reviewingandrevisingtheplan.

Theabilityoftheschedulertocollectthedataisasimportantastheabilitytoenterandmanipulatetheinformationusingthesoftware.Onlargerprojects,itmaybenecessarytowritepoliciesandprocedurestoensureaccuratecollectionofdatafromthevariouspeople,departments,stakeholders/companies,andsites.

2.4Level1–PlanningWithoutResourcesThisisthesimplestmodeofplanningandwewillgothroughthestepsofcreatingaprojectscheduleinP6.

2.4.1CreatingProjectsTocreateaprojectinaPrimaveradatabase,youwillneedthefollowinginformation:

•AnEPSNode,OBSNodeinthedatabasetoassigntheproject,

•ProjectID(acodeassignedtotheproject)andtheProjectName,

•TheProjectStartDate(andperhapstheFinishDate),and

Itwouldalsobeusefultoknowotherinformationsuchas:

•Clientname,and

•Projectinformationsuchaslocation,projectnumberandstakeholders.

2.4.2DefiningtheCalendarsBeforeyoustartenteringactivitiesintoyourschedule,itisadvisabletosetupthecalendars.Theseareusedtomodeltheworkingtimeforeachactivityintheproject.Forexample,a6-daycalendariscreatedforthoseactivitiesthatwillbeworkedfor6daysaweek.Thecalendarshouldincludeanypublicholidaysandanyotherexceptionstoavailableworkingdays,suchasplanneddaysoff.

Primaverahasthreetypesofcalendars:

•Global–whichmaybeassignedtoactivitiesandresourcesinanyproject,•Project–theseareproject-specificcalendarsassignedtoactivities,and

Page 29: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Resource,(PersonalandShared)–thatareassignedtoresources.ProjectandResourcecalendarsmaybelinkedtoGlobalcalendars,enablinganychangestoholidaysmadetoaGlobalcalendartobeinheritedbytheassociatedProjectandResourcecalendars.

2.4.3DefiningtheProjectBreakdownStructuresAprojectbreakdownstructure(PBS)isawayofcategorizingtheactivitiesofaprojectintonumerouscodesthatrelatetotheproject.Thecodesactastagsorattributesofeachactivity.

Duringoraftertheactivitiesareaddedtotheschedule,theyareassignedtheirPBSssothattheymaybegrouped,summarized,andfilteredinoroutofthedisplay.

PrimaverahastwoprincipalmethodsofassigningaPBStoyourproject:

•TheWorkBreakdownStructure(WBS)function,whichiscomparabletotheP3andSureTrakWBSfunctions.

•TheActivityCodefunctionthatoperatesinawaysimilartoActivityCodesP3andSureTrak,CustomDataFieldsinMicrosoftProjectandCodesinAstaPowerProject.

Beforecreatingaproject,youshoulddesignyourPBSsbyaskingthefollowingquestions:

•Whichphasesareinvolvedintheproject(e.g.,Design,Procure,InstallandTest)?

•Whichdisciplinesareparticipating(e.g.,Civil,MechanicalandElectrical)?

•Whichdepartmentsareinvolvedintheproject(e.g.,Sales,ProcurementandInstallation)?

•Whatworkisexpectedtobecontractedoutandwhichcontractorsaretobeused?

•Howmanysitesorareasarethereintheproject?

UsetheresponsestotheseandothersimilarquestionstocreatethePBSs.

2.4.4AddingActivitiesActivitiesmustbedefinedbeforetheyareenteredintotheschedule.Itisimportantthatyoucarefullyconsiderthefollowingfactors:

•Whatisthescopeoftheactivity?(Whatisincludedandexcluded?)

•Howlongistheactivitygoingtotake?

•Whoisgoingtoperformit?

•Whatarethedeliverablesoroutputforeachactivity?

Theprojectestimateisusuallyagoodplacetostartlookingforabreakdownoftheprojectintoactivities,resources,andcosts.Itmayevenprovideanindicationofhowlongtheworkwilltake.

Activitiesmayhavevariabledurationsdependingonthenumberofresourcesassigned.Youmayfindthatoneactivitythattakes4daysusing4workersmaytake2daysusing8workersor8daysusing2workers.

Usuallyprojectreportsareissuedonaregularbasissuchaseveryweekoreverymonth.Itis

Page 30: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

recommendedthat,ifpossible,anactivityshouldnotspanmorethantworeportingperiods.ThatwaytheactivitiesshouldonlybeIn-Progressforonereport.Ofcourse,itisnotpracticaltodothisonlongdurationactivities,suchasprocurementanddeliveryactivities,thatmayspanmanyreportingperiods.

Goodpracticerecommendsthatyouhaveameasurablefinishpointforeachgroupofactivities.ThesemaybeidentifiedintheschedulebyMilestonesandaredesignatedwithzeroduration.Youmayissuedocumentationtoofficiallyhighlighttheendofoneactivityandthestartofanother,therebyaddingclaritytotheschedule.Examplesoftypicaldocumentsthatmaybeissuedforclarityare:

•Issueofadrawingpackage

•Completionofaspecification

•Placingofanorder

•Receiptofmaterials(deliverylogsorticketsordockets)

•Completedtestingcertificatesforequipmentorsystems

2.4.5AddingtheLogicLinksThelogicisaddedtothescheduletoprovidetheorderinwhichtheactivitiesmustbeundertaken.Thelogicisdesignatedbyindicatingthepredecessorsto,orthesuccessorsfrom,eachactivity.Therearetwomethodsthatsoftwareusestosequenceactivities:

•PrecedenceDiagrammingMethod(PDM),and

•ArrowDiagrammingMethod(ADM).

Mostcurrentprojectplanningandschedulingsoftware,includingPrimavera,usesPDM.YoucancreateaPDMdiagramusingtheNetworkDiagramfunction.

Thereareseveraltypesofdependenciesthatmaybeused:

1.Mandatorydependencies,alsoknownasHardLogicorPrimaryLogic,arerelationshipsbetweenactivitiesthatmaynotbebroken.Forexample,aholehastobedugbeforeitisfilledwithconcrete,oracomputerdeliveredbeforesoftwareisloaded.

2.Discretionarydependencies,alsoknownasSequencingLogicorSoftLogicorSecondaryLogic,arerelationshipsbetweenactivitiesthatmaybechangedwhentheplanischanged.Forexample,iftherearefiveholestobeexcavatedandonlyonemachineavailable,orfivecomputerstobeassembledandonepersonavailabletoworkonthem,thentheorderoftheseactivitiescouldbesetwithsequencinglogicyetchangedatalaterdate.

BothMandatorydependenciesandDiscretionarydependenciesareenteredintoPrimaveraasactivityrelationshipsorlogiclinks.Thesoftwaredoesnotprovideamethodofidentifyingthetypeofrelationshipbecausenotesorcodesmaynotbeattachedtorelationships.

ANotemaybeaddedtoeitherthepredecessororthesuccessoractivitytoexplaintherelationship.

3.Externaldependenciesareusuallyeventsoutsidethecontroloftheprojectteamthat

Page 31: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

impactsontheschedule.Anexamplewouldbetheavailabilityofasitetostartwork.ThisisusuallyrepresentedinPrimaverabyaMilestonethathasaconstraintappliedtoit.Thistopicisdiscussedinmoredetailinthenextsection.

Thesoftwarewillcalculatethestartandfinishdatesforeachactivity.Theenddateoftheprojectiscalculatedfromthestartdateoftheproject,thelogicamongsttheactivities,anyLeads(oftenreferredtoasNegativeLag)orLagsappliedtothelogicanddurationsoftheactivities.Thefollowingpictureshowstheeffectofalagandaleadonthestartofasuccessoractivity:

2.4.6DevelopingaClosedNetworkItisgoodpracticetocreateaClosedNetworkwith.InaClosedNetwork,allactivitieshaveoneormorepredecessorsandoneormoresuccessorsexcept:

•Theprojectstartmilestoneorfirstactivity,whichhasnopredecessors,and

•Thefinishmilestoneorfinishactivity,whichhasnosuccessors.

WhenaclosednetworkisnotestablishedthentheCriticalPath,TotalFloatandFreeFloatwillnotcalculatecorrectly.

Theproject’slogicmustnotloopbackonitself.LoopingoccursifthelogicstatesthatAprecededB,BprecededC,andCprecededA.Thatisnotalogicalprojectsituationandwillcausethesoftwaretogenerateanerrorcommentduringnetworkcalculations.

Thus,whenthelogiciscorrectlyapplied,adelaytoanactivitywilldelayallitssuccessoractivitiesanddelaytheprojectenddatewhenthereisinsufficientspareslippagetimetoaccommodatethedelay.ThissparetimeisnormallycalledFloatbutnotethatMicrosoftProjectusesthetermSlackforFloat.

2.4.7SchedulingtheProjectThesoftwarecalculatestheshortesttimeinwhichtheprojectmaybecompleted,ActivitiesaremovedforwardintimeuntiltheymeetaRelationshiporConstraintoracalendarnonworktime.Un-startedactivitieswithoutlogicorconstraintsarescheduledtostartattheProjectStart

Page 32: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Dateoraspermittedbycalendarnonworktimes.

SchedulingtheprojectwillidentifytheCriticalPath(s)whenthereisaClosedNetwork.TheCriticalPathisthechain(s)ofactivitiesthattakesthelongesttimetoaccomplish;adelaytoanyactivityinthechainwilldelaytheenddateoftheproject.Thecalculatedcompletiondatedependsonthecriticalactivitiesstartingandfinishingontime.Ifanyofthemaredelayed,thewholeprojectwillbedelayed.

2.4.8CriticalPathTheCriticalPathistheshortestdurationthataprojectmaybecompletedinandadelaytoanyactivitywilldelaytheenddateoftheproject,activitiesA1000toA1030andA1060below,alsoshowninredareonthecriticalpath:

2.4.9TotalFloatTotalFloatistheamountoftimeanactivitymaybedelayedwithoutextendingtheprojectenddate.

•AnactivitywithTotalFloatmaydelayanotheractivity,

•MaybedisplayedinacolumnandintheGanttChart,asperthethinblackbarinthepicturebelow,and

•Maybenegative.

2.4.10FreeFloatTheFreeFloatistheamountoftimeanactivitymaybedelayedwithoutdelayinganotheractivity.

•MaybedisplayedinacolumnandintheGanttChart,asperthethinblackbarbelowand

Page 33: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Isneverinthenegative.

TheP6WindowsClientdoesnotdisplayFreeFloatasabar.

2.4.11RelationshipColorsRelationshipcolorsinP6maynotbeformattedaswithmanyothersoftwarepackages:

•SolidBlackareDrivingCritical(theirsuccessorsusuallyhaveNOTotalFloat)orDrivingNon-Critical(theirsuccessorsusuallyhaveTotalFloat).

•DottedBlackareNon-DrivingNon-CriticalandtheirpredecessorshaveFreeFloat.

2.4.12ConstraintsTypesTherearetwotypesofconstraints:

•ProjectConstraintswhichincludestheProjectStartDateandProjectFinishDate,and•ActivityConstraints;thetwomostcommonareStartOnorAfter(EarlyStart)andFinish

OnorBefore(LateFinish).ExternaldependenciesareappliedtoascheduleusingConstraintsandthesemaymodeltheimpactofeventsoutsidethelogicalsequenceofactivities.Aconstraintwouldbeimposedtospecificdatessuchastheavailabilityofafacilitytostartworkortherequiredcompletiondateofaproject.Constraintsshouldbecross-referencedtothesupportingdocumentation,suchasMilestoneDatesfromcontractdocumentation,usingtheNotebooksfunction.

2.4.13ProjectConstraintsAProjectStartDatecalledProjectPlannedStartinP6istheearliestdatethatanyactivitymaybescheduledtostart.AnactivitywillstartontheProjectStartDateunlessoneofthe

Page 34: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

followingstopstheactivitystartingontheProjectStartDate:•ThereisaCalendarNonWorktime,or

•Aconstraint,or

•Arelationship.

AprojectMustFinishDateisoptional,butoncesetthiscontrolsTotalFloat(oftenreferredtoasFloatinP6).

WhenaprojectMustFinishDateconstraintisassignedthenTotalFloatiscalculatedtothisdate.

•ThepictureshowsaprojectwithaProjectFinishdateonFriday26Septemberdeveloping5daysTotalFloat.

P6WebdoesnotdisplaytheTotalFloatonMilestones,unliketheP6WindowsClientwhichwilldisplaythefloatbaronaMilestone,seeimagebelow:

•ThepictureshowsaschedulewithaprojectMustFinishDatedateofFriday12,•Thisisearlierthanthecalculatedfinishdate,thuscalculating5daysNegativeFloat:

TheP6displaysthenegativefloatbarfromtheFinishoftheactivitygoingforwardin

Page 35: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

timeanddoesnotdisplaytheNegativeFloatonMilestones.Othersoftwarepackagesdisplayfloatfromthestartoftheactivitygoingforwardintimewhichmakesthescheduleeasiertoread.

•ThepicturebelowwascreatedusingtheP6WindowsClientandshowsanegativefloatbarisdrawnagainstMilestones:

2.4.14ActivityConstraintsTypicalexamplesofactivityconstraintswouldbe:

•StartonorAfterfortheavailabilityofasitetocommencework,and

•FinishonorBeforeforthedatethatatotalprojectmustbecompletedorhandedover.

ActivityEarlyStartConstraint•AnactivitywillnolongerstartontheDataDatewhenaStartOnorAfterconstraintis

assigned

•ThisismorecommonlyknownasanEarlyStartconstraint.

NOTES:InP6thetimemustalwaysbedisplayedasP6willoftensetconstraintsat00:00hrswhichismidnightandisnotveryoftenanappropriatetimetosetconstraints.

ActivityLateFinishConstraintEarlierthantheScheduledFinish•ThispicturebelowshowsaschedulewithaFinishDateOnorBeforeconstraintassigned

4daysearlierthanthecalculatedfinishdate,

•ThusNegativeFloatiscreated,representingtheamountoftimethatneedstobecaughtup.

•ThisismorecommonlyknownasaLateFinishconstraint:

Page 36: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ActivityLateFinishConstraintLaterthantheScheduledFinish•ThepicturebelowshowsaschedulewithaFinishDateOnorBeforeconstraintassigned

afterthecalculatedfinishdate,

•TheTotalFloatisNOTcalculatedtotheconstraintdatewhentheconstraintdateisLATERthecalculatedEarlyFinish.

•PositiveTotalFloatisNOTcreatedandacriticalpathofzerodaysfloatismaintained:

2.4.15RiskAnalysisPlanningaprojectmayidentifyrisks,soaformalriskanalysisshouldbeconsidered.Ariskanalysismayidentifyriskmitigationactivitiesthatshouldbeaddedtotheschedule.

2.4.16ContingentTimeTheadditionofcontingenttimeshouldbeconsideredwhensubmittingascheduleforapproval.Estimatesusuallyhavecontingencyandifthismoneyistobeexpendedthenanallowancefortimetospendthecontingentfundsneedstobemade.Contingenttimemaybeaddedtoascheduleinanumberofways:

•Insertoneormorecontingenttimeactivitiesintheproject.Thesewouldbeadjustedinlengthastheprojectprogressestomaintaintheplannedenddate.

•Assignworkdaysinthecalendarasnonworkdays.Forexample,abuildingprojectcouldbescheduledona5-dayperweekbasis,knowingthatworkwillbeundertakenontheSaturday.

•Increasetheactivitydurationsbyafactor,thiswillaffecteithertheresourceUnitsperTimeperiodortotalresourceUnitsandshouldnotbeusedonaresourcedschedule.

•Assignpositivelagsbetweenactivities,althoughthisisnotrecommendedbytheauthor.

2.4.17FormattingtheDisplay–ViewsandFiltersTherearetoolstomanipulateanddisplaytheactivitiestosuittheprojectreporting

Page 37: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

requirements.ThesefunctionsarecoveredintheFORMATTINGTHEACTIVITYWINDOWANDVIEWSchapter.

2.4.18PrintingandReportsTherearesoftwarefeaturesthatenableyoutopresenttheinformationinaclearandconcisemannertocommunicatetherequirementstoallprojectmembers.ThesefunctionsarecoveredinthePRINTINGANDREPORTSchapter.

2.4.19IssuingthePlanAllmembersoftheprojectteamshouldreviewtheprojectplaninanattemptto:

•Optimizetheprocessandmethodsemployed,and

•Gainconsensusamongteammembersastotheproject’slogic,durations,andProjectBreakdownStructures.

Teammembersshouldcommunicatefrequentlywitheachotherabouttheirexpectationsoftheprojectwhileprovidingeachwiththeopportunitytocontributetothescheduleandfurtherimprovetheoutcome.

2.5Level2–MonitoringProgressWithoutResources

2.5.1SettingtheBaselineTheoptimizedandagreed-toplanisusedasabaselineformeasuringprogressandmonitoringchange.Thesoftwaremayrecordthebaselinedatesofeachactivityforcomparisonagainstactualprogressduringthelifeoftheproject.

2.5.2TrackingProgressThescheduleshouldbeUpdated(progressed)onaregularbasisandprogressrecordedatthatpoint.ThedateonwhichprogressisreportedisknownbyanumberofdifferenttermssuchasDataDate,UpdateDate,TimeNowandStatusDate.TheCurrentDataDateisthefieldPrimaverausestorecordthisdate.TheDataDateisNOTthedatethatthereportisprintedbutratherthedatethatreflectswhentheupdateinformationwasgathered.

Whateverthefrequencychosenforupdating,youwillhavetocollectthefollowingactivityinformationinordertoupdateaschedule:

•Completedactivities

ActualStartdate

ActualFinishdates

•In-progressactivities

ActualStartdate

PercentageCompleted

DurationorExpectedFinishDateoftheActivity

Page 38: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Un-startedwork

Anyrevisionstoactivitiesthathavenotstarted

Newactivitiesrepresentingscopechanges

Revisionstologicthatrepresentchangestotheplan

Theschedulemaybeupdatedafterthisinformationhasbeencollected.TherecordedprogressiscomparedtotheBaselinedates,eithergraphicallyorbyusingcolumnsofdata,suchastheVarianceBaselineProjectFinishcolumn:

2.5.3CorrectiveActionAtthispoint,itmaybenecessarytofurtheroptimizethescheduletobringtheprojectbackontrackbydiscussingtheschedulewiththeappropriateprojectteammembers.Thepossibleoptionsare:

•Reducethecontingenttimeallowance.

•AssignanegativelagonaFinishtoStartrelationship,whichenablesasuccessortocommencebeforeapredecessoriscompleted.

•Changerelationshipstoallowactivitiestobeexecutedinparallel.

•Reducethedurationsofactivities.Inaresourcedschedule,thiscouldbeachievedbyincreasingthenumberofresourcesassignedtoanactivity.

•Worklongerhoursperdayordaysperweekbyeditingthecalendars,or

•Reducethescopeanddeleteactivities.

2.6Level3–SchedulingWithResourcesandRoles

2.6.1EstimatingorPlanningforControlTherearetwomodesthatthesoftwaremayuseatLevel3.

•Estimating.Inthismode,theobjectiveistocreateaschedulewithcoststhatareusedonlyasanestimate.Theschedulewillneverbeupdated.Activitiesmayhavemanyresourcesassignedtothemtodevelopanaccuratecostestimateandincludemanyitemsthatwouldneverbeupdatedintheprocessofupdatingaschedule.

•PlanningforControl.Inthismode,theintentionistoassignactualunits(hours)andcosts

Page 39: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

toresources,thencalculateunitsandcoststocompletion,andpossiblyconductanEarnedValueanalysis.Inthissituation,itisimportanttoensurethattheminimumnumberofresourcesareassignedtoactivities,andpreferablyonlyoneresourceassignedtoeachactivity.Theprocessofupdatingaschedulebecomesextremelydifficultandtimeconsumingwhenaschedulehasmanyresourcesperactivity.Thescheduleristhenunderthreatofbecomingatimekeeperandmaylosesightofotherimportantfunctions,suchascalculatingtheforecasttocompleteandtheprojectfinishdate.

2.6.2TheBalanceBetweentheNumberofActivitiesandResourcesWhenPlanningforControlonlargeorcomplexschedules,itisimportanttomaintainabalancebetweenthenumberofactivitiesandthenumberofresourcesthatareplannedandtracked.Asarule,themoreactivitiesaschedulehas,thefewerresourcesshouldbecreatedandassignedtoactivities.

Whenaschedulecontainsalargenumberofactivitiesandalargenumberofresourcesassignedtoeachactivity,theresultmaybethatnomembersoftheprojectteamareabletounderstandthescheduleandtheschedulerisunabletomaintainit.

Insteadofassigningindividualresources,suchaspeoplebyname,considerusing“Skills”or“Trades,”andonverylargeprojectsuse“Crews”or“Teams.”

Thistechniqueisnotsoimportantwhenyouuseascheduleforestimatingthedirectcostofaproject(byassigningcoststotheresources)orifyouarenotusingthescheduletotrackaproject’sprogress(suchasaschedulethatisusedtosupportwrittenproposals).

Therefore,itismoreimportanttominimizethenumberofresourcesinlargeschedulesthatwillbeupdatedregularly,becauseupdatingeveryresourceassignedtoeachactivityateachscheduleupdateisverytimeconsuming.

2.6.3CreatingandUsingResourcesFirst,onewouldusuallyestablisharesourcepoolbyenteringalltherequiredprojectresourcesintoahierarchicaltableinthesoftware.Therequiredquantityofeachresourceisassignedtotheactivities.InanEnterpriseenvironmenttheseresourcesmayalreadybedefinedforyou.

SomelargeorganizationsmaycentralizethisfunctionandresourcesmayalreadybecreatedandpossiblylinkedtoaHRManagementsystemwhichcontinuallyupdatesresourcesavailabilityandprices.

Enteringacostrateforeachresourceenablesyoutoconductaresourcecostanalysis,suchascomparingthecostofsupplementingoverloadedresourcesagainstthecostofextendingtheprojectdeadline.

Estimatesandtime-phasedcashflowsmaybeproducedfromthisresource/costdata.

2.6.4CreatingandUsingRolesPrimaverahasanadditionalfunctiontitledRoles,whichisusedforplanningandmanagingresources.

•ARoleisaskillortradeorjobdescriptionandmaybeusedasanalternativetoresources

Page 40: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

duringtheplanningperiodofaproject.

•RolesaredefinedinahierarchicalstructureandholdaProficiencyLevel.

•Rolesmaybeassignedtoactivitiesinawaysimilartohowresourcesareassigned.Rolescanbereplacedlaterbyresourcesafterithasbeendecidedwhoisgoingtobeassignedthework.

•PrimaveraVersion5.0introducedafunctionallowingaRoletobeassignedarate.

2.6.5TheRelationshipBetweenResourcesandRolesPrimaverahastheabilitytodefinerolesandassociatethemwithresources.Aroleisajobtitle,tradeorskillandmayhavemanyresources.Amulti-skilledresourcemayhavemultipleroles.Forexample,arolemaybeaClericalAssistantandtheremaybefiveclericalassistantsinacompanywhowouldbeassignedtheClericalAssistantRole.Ifoneclericalassistantwerealsoadataentryperson,thenthisresourcewouldbeassignedtworoles:ClericalAssistantandDataEntry.

2.6.6ActivityTypeandDurationTypeActivitiesmaybeassignedanActivityTypeandDurationTypewhichaffecthowresourcesarecalculated.Additionalsoftwarefeaturesenabletheusertomoreaccuratelymodelreal-lifesituations.ThesefeaturesarecoveredintheASSIGNINGROLES,RESOURCESANDEXPENSESchapter.

2.6.7BudgetsTheBudgetfunctionenablesTop-DownBudgetingatasummarylevelagainsteachEPSNodeinanaccountingstyle.BudgetsmaybecomparedtothedetailedestimatescalculatedafterresourceshavebeenassignedtoActivities.TheBudgetfunctionisnotcoveredinthisbook.

2.6.8ResourceUsageProfilesandTablesThesefeaturesenablethedisplayandanalysisofprojectresourcerequirementsbothintablesandgraphs.

ThedatamaybeexportedtoExcelorreportsrunforfurtheranalysisandpresentation.

2.6.9ResourceOptimizationTheschedulemaynowhavetoberesourceoptimizedto:

•Reducepeaksandsmooththeresourcerequirements,or

•Reduceresourcedemandtotheavailablenumberofresources,or

•Reducedemandtoanavailablecashflowwhenaprojectisfinancedbyacustomer.

Levelingisdefinedasdelayingactivitiesuntilresourcesbecomeavailable.Thereareseveralmethodsofdelayingactivities,andthuslevelingaschedule,whichareoutlinedintheRESOURCEOPTIMIZATIONchapter.

Page 41: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

2.7Level4–MonitoringandControllingaResourcedSchedule

2.7.1MonitoringProjectswithResourcesWhenyouupdateaprojectwithresources,youwillneedtocollectsomeadditionalinformation:

•Thequantitiesand/orcostsspenttodateperactivityforeachresource,and

•Thequantitiesand/orcostsrequiredperresourcetocompleteeachactivity.

Youmaythenupdatearesourcedschedulewiththisdataorthismaybeimportedfromatimesheetsystem.

Afteraschedulehasbeenupdated,thenareviewofthefutureresourcerequirements,projectenddate,andcashflowsmaybemade.

Updatingaresourcedprojectistimeconsumingandrequiresexperienceandagoodunderstandingofhowthesoftwarecalculatesaschedule.Ideally,thisshouldonlybeattemptedbyexperiencedusersorbyanoviceundertheguidanceofanexperienceduser.

TheOraclePrimaveratimesheetsystemmayalsobeimplementedtoupdateactivities.

2.7.2ControllingaProjectwithResourcesAtthispoint,itispossibletoundertakeagreatdealofanalysisandoftenEarnedValuePerformanceMeasurementtechniquesareused.

Page 42: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3STARTINGUPANDNAVIGATION

3.1ImplementingWebBasedProjectManagementToolsWebbasedtechnologiesoftenrequirespecialistknowledgetoimplementtoensurethesoftwarewillfunctionasdesigned.Thesystemconfigurationofboththehardwareandsoftwarecanalsoimpactthespeedofthesystemwhenimplementedandduetothenumberofdifferentsystemcombinations.

ThebrowserusedforwritingthisbookswasMicrosoftWindowsInternetExplorerVersion8.Duringthecourseofwritingthisbooktheauthorfoundthattheconfigurationsettingsofthebrowseroccasionallyneededadjustingtoallowpopupstoactivateandsomebrowserupdatestobeinstalled.

3.2LoggingInYourSystemsAdministratorwillprovideyouwith:

•AWebAddresstoaccessthePrimaveraWebClientsoftwareLoginscreen,whichmaybedifferenttotheonebelow,

•AUsernameandaPassword,•ADatabaseIDwhentherearemultipledatabasestoselectfrom,•OpentheAdvancedtabtoselectanotherdatabaseortochangetheLanguage,•Clickontothe Loginbutton:

YoumaybetakentothePersonalWorkspacewhichmaylooklikethepicturebelow:

Page 43: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.3PrimaveraP6ArchitecturePrimaveraP6hasthefollowingcorecomponents:

•Databases

•WebClientTools

•WindowsClientTool

•OtherTools

3.3.1DatabasesOneormoredatabasesmaybeinstalledsuchas:

•Production–forkeepingallthecurrentcorporateprojects,•Sandpit–forschedulesthatarenotdesiredinthecorporatedatabasesuchastwoweek

lookaheadschedulesandotherlessimportantinformationsuchas“Whatif”schedules,

•Training–forrunningtrainingcourseswhichisoftenacopyoftheCorporateDatabase,•Import–forimportingexternallysuppliedprojectstoimportandreviewtheseprojectsso

otherdatabasesarenotcorruptedbyunwanteddatathatmaybeimportedwiththeseschedules.

3.3.2WebToolsP6WebClient–isawebbrowsertoolwhichisthetopicofthisbook.•ThistooleliminatestheneedtoloadsoftwareontoaPC.

•P6WebmakesavailablemanyfunctionsoftheWindowsClientServerProjectManagementtool,plussomeadditionalfunctionsnotavailableintheWindowsClientServer.

Page 44: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ItisusedtomanagetheEPPMdatabase,functionssuchasaddingusersanduseraccessetc.

•P6WebisusedtomanagetheEnterpriseenvironment.

P6ProgressReporter–timesheetapplicationaccessedthroughawebbrowser.ThiswasintegratedintoP6TeamMemberinVersion8.4.

P6TeamMember–progressupdateapplicationaccessedthroughawebbrowser.TimesheetswerealsointegratedintothisapplicationinVersion8.4.

PrimaveraPrime–ThisapplicationisaProjectPortfolioManagementapplicationwithanumberofmodulesincludingBudgetPlanning,ProjectInitiationProjectCosting,ProjectSelection,BusinessProcessManagement,StrategicAlignmentandCompliance,PortfolioMonitoringanCollaborationandmaybeintegratedwithP6thoughimportandexport.

•ThePrimeRiskManagement,whichusesaMonteCarloSimulationtocalculateaquantitativeriskanalysis,andthenupdatesP6withtheresults.

•PrimeScopeManagement,allowingP6activitiescostsanddateinformationtobeexchangedwithPrimeWorkPackages.

PrimaveraUnifier–ThisisacostmanagepackagethathassupersededContractManagerandintegrationwithUnifierwasenhancedinVersion8.4.Typicallycost,resourcedatamaybeexchangedbetweenthetwoapplicationsusingimportandexportatasummarylevelusingaCostBreakdownStructurethatisassignedtoactivitiesoratdetaillevel.

3.3.3WindowsClientServerToolThistoolistitledProjectManagement(amongstmanyothernamesassignedinthepast)isatraditionalWindowsClientServertoolusedtomanagetheprojectsandprojecttemplates.ThisisoftenrunthroughCitrixorRemoteDesktopapplicationbymanycompanies.

Page 45: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheWindowsClientisconsideredbytheauthorasasuperiortoolforschedulingandcontrollinglargecomplexprojectsandtheproductivityisintheauthor’sopinionwilldelivermorethantwicetheproductivityoftheWebtool.

TherearemanydifferencesinfunctionalitybetweentheWebClientandWindowsClient.TherearetwoversionsoftheWindowsClient,P6ProfessionalwhichdoesnotoperatewiththeWindowsClientorP6OptionalClientwhichdoesoperatewiththeWindowsClient.ThispublicationtriestoexplainthesedifferencesandWindowsClienttooliscoveredinotherEastwoodHarrispublications.

3.3.4OtherToolsInP6Versions8.2&8.3,theTeamMemberfunctionalitywasextendedtoprovidetheabilitytoupdateprogressviaiPhoneapplicationoremail.

3.4P6WebFunctionalityAreasandInterfaceP6Webhasthefollowingfunctionalityareas:

•Dashboards–thistabdisplaysPortlets(smallwindowsdisplayinginformation)thatmaybecustomizedbytheusertodisplayinformationrelevanttotheportfolios,projectsandresources.

•Portfolios–thistaballowsyoutoreviewinformationongroupsofprojects.Fromthispage,youcanconductaside-by-sidecomparisonoftwoprojectgroups,applywhat-ifanalysisandwaterlineanalysistechniquestoassistwithcritical,executive-leveldecisionmaking.

•Projects–thistabiswhereoneormoreprojectsmaybecreatedoropenedandmanipulated.Thisareawillbecoveredindetailinthisbook.

•Resources–thistabiswhereresourcesarecreated,managedandanalysed.•Administration–thismenuwhereaUsersetstheirsoftwarepreferencesintheareatitled

MyPreferencesandDatabaseAdministratoradministersusersandthedatabase.ThischapterwillexplaintheWebinterface,butultimatelyeachuserwillhavetospendasignificantamountoftimeplayingwiththeinterfacetobecomefamiliarwiththiscomplexpieceofsoftware.

3.4.1DashboardsTabDashboardareusedtoprovideasummarizedviewoftheP6data,configuredtodisplayinformationspecifictotheroleoftheuser.Thedashboarddatacontainsinformationonportfolios,projects,resourcesandactivities.Theinformationcanbedisplayedinatabularorgraphicalformat,withemphasisonsummaryandKPIreporting.

TheDashboardsmodulecancontainanumberofworkspaces,witheachworkspacerepresentedbyatab.Theworkspacedataisdisplayedinanumberofconfigurablesub-windowscalledPortlets.

Accesstothedashboardinformationiscontrolledbymoduleandsecuritysettings,administrationconfiguration,userinterfaceviewsetting,andprojectandactivityassignmentsoftheuser.

Page 46: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Therearethefollowingtypesofdashboards:

•Userdashboardsareprivateworkspacesthatausermaycreateandarenotavailabletootherusers.Theycontaininformationspecifictoauser,suchthelistofactivitiesassignedtotheuser.

•Multi-userdashboardsareaccessibletoaspecificgroupofusers.ThedashboardswouldtypicallybeconfiguredbythesystemadministratorandcanbeviewedbytheassigneduserontheDashboardsHomepage.

•Globaldashboardscontaininformationrelevanttoallusers,andareaccessiblebyalluserswithaccesstotheDashboardsmodule.

ADashboardincludesuserdefinedinformationinsmallwidowscalledPortlets.ThePortletsmaybeformattedandthedataineachPortlethiddenordisplayed:

TheFilterbyfieldonthetoprighthandsidespecifieswhichportfolioprojectdataisviewed.TheDashboardmenushownbelowhasfollowingoptions:•ManageDashboards–whereoneormoreDashboardsarecreatedandformatted.•ApproveTimesheets–whereamanagermayapprovetimesheets.

Afteramenuitemhasbeenselectedthetitleofthecurrentwindowisdisplayed,asshowninthepicturebelowwhereManageDashboardswasselected:

Page 47: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

EachDashboardhasadditionalformattingoptionsthatmaybeaccessedthroughAdminister,MyPreferences,View,Dashboards:

3.4.2PortfoliosTabPortfolioareusedtoprovidemulti-projectreporting,analysisandcomparison.Aportfolioisacollectionofprojectsgroupedbyacommonattribute.Thegroupingtypicallyreflectsanorganizationalbusinessobjective,suchascapitalworksprojectsfornextfinancialyear.

ThePortfoliosmoduleisusedtoanalyzeportfoliodata,conductside-by-sidecomparisonsoftwoprojectgroups,andapplywhat-ifscenariosandwaterlineanalysistechniquestoassistwithexecutive-levelcriticaldecisionmaking.Portfolioviews,suchaspiecharts,bubblechartsandhistogramsassisttheusersintheanalysisandcomparisonofthedataineachportfolio.

ThePortfolioAnalysispageisdividedintotwohalves.Informationrelatedtooneprojectgroupmaybecomparedwithasecondprojectandmaybedisplayedonesideoroneabovetheotherorsidebyside.

Foreachprojectgroup,theusercandisplaythelatestsummarizeddata,orasnapshotofhistoricalprojectdatathathasbeensavedasascenario.Theusercanalsocustomizeaportfolioviewtodeterminethelayoutofprojectdata.

Page 48: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Portfolioscanbealsousedtofilterdashboardreporting.

Dependingonsecurityprivileges,theusercancreatetheirownportfolio,saveportfoliosforotherusersorcreateglobalportfolios.

ThePortfoliotaballowsausertoreview,compareandanalyzeProjectdataassignedtoaPortfolio:

ThePortfoliomenu,activatedbyclickingonthe bythetitle,hasfouroptions:

•OpenPortfolio–allowstheselectionofaPortfolio.•ManagePortfolios–asintheDashboardmenuthisiswhereoneormorePortfoliosare

createdandedited.

•ManagePortfoliosViews–iswhereaviewmaybecreatedthatdisplaysspecificinformationaboutaportfolio,and

•ManageScenarios–aScenarioisarecordofprojectdataataspecificpointintimeandisusedforfuturecomparison.

Thebottompartofthemenushowstheportfoliosrecentlyopened.

3.4.3ProjectsTabThismenuwilldisplayanyopenprojectsandallowsoneormoreprojectstobeopened,created,manipulatedanddeleted.

Page 49: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thiswindowwillbecoveredindetailinthisbook.

3.4.4ResourcesTabThiswindowiswhereresourcesareadded,removedandmanaged:

•Assignmentstabiswhereresourcesareassigned,•PlanningtabiswhereresourcesmaybeassignedtoaWBSNodeforlongtermplanning

andisoutofscopeofthisbook,

•Analysistabiswhereresourceloadingmaybeanalysed,and•Administrationtabiswhereresourcesarecreatedandadministered.

3.4.5AdministerTabAllconfigurationoftheEnterprisedatabaseforthePrimaveraP6EPPMVersions8.2to8.4isperformedusingtheP6WebClientandmaynotbeperformedwiththeOptionalWindows

Page 50: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Client.

Theseconfigurationitemsincludeforexample:

•EPS–EnterpriseProjectStructure,thisisahierarchicalstructureforstoringtheprojects.•OBS–OrganizationBreakdownStructurewhichisusedtoassignaccessrightsforusersto

projectsviatheEPS.

•Users–Creatingusersandaccessrights.ThistabisusedtodefinetheMyPreferences,theseareindividualuserpreferences,andMyCalendarwhichistheuser’sPersonalCalendarwhentheuserhasbeendefinedasaresource.

Thedatabaseconfigurationsettingandsecurityprivilegesareunderthefollowingheadings:

•ApplicationSettings

•EnterpriseData

•GlobalScheduledServices

•UserAccess

•UserInterfaceViews

•UserSessions

UnliketheWindowsClientitispossibletohaveformulaetocalculatevaluesforUserDefinedFieldsfromotherdatabasefieldsintheP6Webtool.

3.4.6AdministerMenu,MyPreferencesTheMyPreferencesmenuisusedbyausertoformatthedisplaytosuittheusersrequirements.Ithasthefollowingtabs:

Administer,MyPreferences,Globaltab–thisiswheretheuserdefineshowthemanyGlobalfunctionsperformandinparticularhowthedate,timeanddurationsaredisplayed:

Page 51: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Administer,MyPreferences,Viewtabiswheretheuserdefineswhichmenuitemsaredisplayed:

Administer,MyPreferences,Passwordtabiswhereausermayresettheirpassword:

Page 52: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.4.7NavigatingAroundP6WebTheP6Webtoolhassomefeaturesthatnewusersshouldbeawareof:

•ClicktheDashboards,Portfolios,ProjectsorResourcestoselectawindow:

•The buttonnexttoeachwindowiconopensadownmenu:

•A willcloseaPortletanda willopenaPortlet.

•A willopencontextsensitivehelp.

•A willrefreshthedatainaPortlet.

•A willmaximizeandminimizeaPortlet.

•A willclosethePortletandremoveitfromtheview.TheCustomize,ViewtabmustbeusedtodisplayahiddenPortlet.

3.4.8BottomPaneTabsSomeoftheWindowshaveabottompanewithtabs,thepicturebelowshowstheActivityWindowstabsatthebottom:•Clickonthetabtoopenthetabcontents:

Page 53: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ThepicturebelowexplainsthefunctionsavailableforformattingthetabsaftertheGeneraltabwasopened:

Thefunctionsinthelowerwindowwilltakesomepracticetomaster.

AfteratabhasbeenmadeFloatingitispossibletomakemultiplewindowsvisibleinthelowerpane.

ToaddaFloatingpanebackintothemainwindowclickonthe RestoreiconintheTopRightHandSideofthefloatingwindowwhenanotherwindowisdisplayed,thisfunctiondoesnotworkwhentherearenononFloatingpanesvisible.

Page 54: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.4.9SavingDataItisveryimportanttounderstandthatdataisnotautomaticallysavedwhenausernavigatesawayfromapageanddatamustbesavedbeforemovingfromonepagetoanother.Thesoftwarewilloftenpromptausertosave,butitisimportantthatyoudosavewhenpromoted:

•Datathathasbeenmodifiedandisyettobesavedwillbeidentifiedbythe ChangedandUnsavedDataicon.

•Fieldsintablecolumnscanbeediteddirectlyonscreen,butthedatamustbesavedprioraftertheupdateiscompletedbyclickingonthe Saveiconortheeditswillbelost.

•Editstodatainformswillnotbesaveunlessthe Saveiconatthebottomoftheformisclicked:

Page 55: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.5ViewingProjectData–ProjectsTabThissectionwillcovertheviewingofprojectdatafoundundertheProjecttab.

3.5.1Projects,EPSTabProjectsmaybesummarizedunderahierarchicalstructuretitledtheEnterpriseProjectStructure(EPS).ThisfunctionissimilartosummarizingactivitiesofaprojectunderaWorkBreakdownStructure(WBS).

TheProjects,EPStaballowsaccesstoareaswhere:•EPSNodesmaybecreatedandedited,•Projectsmaybecreatedandprojectssettingsedited.

3.5.2ProjectsTabMenuandActivitiesTabTheProjectsMenutaballowsaccesstoareaswhere:•ProjectsmaybeopenedusingtheProjects,OpenProjectscommand,•EnterpriseProjectDataisanotheroptiontoview,createandeditEnterprisedata,and•ProjectScheduledServicesareadministeredhere.Theseallowtheschedulingof

functionslikeScheduling,Summarizing,LevelingandApplyingActualsandthedetailsofthisareoutofscopeofthisbook:

Page 56: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.5.3OpeningaProjectTherearetwomethodsofopeningaproject:

•FromtheProjects,OpenProjectsmenu,or•TheProjects,EPSWindow.

ToopenoneormoreprojectsfromtheOpenProjectsmenu:•SelecttheOpenProjectscommandtoopentheProjectsMenu,OpenProjectform,•TheprojectorEPSNodetobeopenedisselectedinthelefthandsideandismovedtothe

righthandsideusingthearrowsofdoubleclickingontheprojecttitleorEPSNode,

•Theprojectslistedintherighthandsidewillbeopenedwhentheformisclosed,

•Closetheformbyselectingthe OKiconandtheprojectdatawillbeavailableforediting:

Page 57: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TheprojectactivitieswillbedisplayedwhenyouareintheActivitiesWindow:

ToopenoneormoreprojectsfromtheProjects,EPSWindow:•SelecttheProjects,EPStoopentheEPSWindow,

Page 58: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•IfyoudonotwantacurrentlyopenprojectopentheselectProjects,EPS,Actions,CloseAll andthiswillcloseallopenprojects,

•Selecttheproject/syouwanttoopen,

•LeftclickandselectOpenProjectorclickontheOpenProject icon,

•MovetotheProjects,ActivitiesWindowtoseeanyActivitiesandedittheschedule:

OpenExclusively willallowotherpeoplewithaccesstoopenyourprojectbuttheywillnotbeabletomakeanychanges.

UnliketheWindowsClientopeninganewprojectwillnotcloseallotheropenprojectsiandwillopenanadditionalproject.IfyouwishtoopenasingleprojectthenyoushouldclickontheCloseAll iconbeforeselectinganewprojecttoopen.

3.5.4ViewingtheOBSTheOBSisusedtoassignuseraccesstoaproject,WBSNodeorEPSNodeandmaybeviewed/assignedinthe:

•Projects,EPS,GeneraltabResponsibleManagerfield,or•BydisplayingtheEPScolumn:

Page 59: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.5.5MyPreferences–DateandTimeDisplayAdminister,MyPreferencesenableseachusertoselecthowsomeinformationisdisplayedorcalculated.ToadjusthowthedateandtimearedisplayedselectAdministerfromthetoprighthandsideofthemenuandselecttheMyPreferences,Globaltab,TimeUnitsFormatarea:

•GototheTimeUnitsFormatarea:

TheDisplayDurationsindetermineshowtheactivitydurationsaredisplayed.PrimaveraessentiallycalculatesinhoursandtheHoursperTimePeriodoptionsconvertthedurationinhourstoDays,Weeks,MonthorYearsforallprojectsthattheuserhasopened.

ItisimportantthattheShowDurationlabelandSub-unitsarecheckedwhendisplayingdurationsinhoursandthenyouwillseeimmediatelywhennonrounddaysfordurationshavebeencreated.

•GototheDateFormatareatoformat:Thedatedisplay,and

Thetimedisplay.

Page 60: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Dateformat.ItisVERYstronglyrecommendedusingMonthnameoninternationalprojectssothereisnoconfusionbetweentheUSmm/dd/yyformatandtheROW(RestofWorld)formatofdd/mm/yy.Timeformat:ItisSTRONGLYrecommendedthatthetimeisALWAYSdisplayedin24hourformatsotheuserknowsthetimeofanyselecteddate.Thisisbecausethesoftwarewilloftenselect00:00,firstsecondofadaywhenassigningdates.Theauthordoesnotdisplayminutestokeepthedatecolumnwidthsslightlynarrower.

3.6UnderstandingtheProjectsWindowTheProjectsWindowhasanumberofwindowsandclickingoneachiconwilltakeyoutoeachwindow:

3.6.1ActivitiesWindowThisiswheretheWBSNodesandactivitiesareaddedandtheschedulecreated:

Page 61: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.6.2ActivitiesWindowMenu•ThereareadditionalmenusavailableintheActivitiesWindow.

•Actionsallowstheusertoperformdatamanipulationactivities,suchasaddordeletingactivities,defineprojectbaselines,calculatetheprojectschedule,printthecurrentvieworimport/exportprojectdata.

•Editallowstheusertocut,copyandpasteactivitiesandtore-organizetheWBShierarchybymovingtheelementsupordownorindentingthem.

Page 62: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Viewallowstheusertomodifytheviewsonthescreen,bychangingthetypeofchartsbeingdisplayed,addingordeletingcolumns,changingthegroupingoftheactivitiesorselectingfilters.

3.6.3ActivityToolbarsRightclickingintheactivitytoolbarallowstheusertocustomizethetoolbarbyaddingor

Page 63: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

deletingshortcuticons.

Someiconsmaybehiddenandthetoolbarsmayneedtobeadjustedbydraggingtorevealthesebuttons.

3.6.4ViewingtheHierarchyforActivity,Project,andResourceCodesP6R8.3showsthefullhierarchyforassignedproject,activityandresourcecodesintheCodesdetailwindowavoidingconfusionwhenduplicatecodesorcodevaluesexist.Bydisplayingthefullhierarchy,itispossibletoseealltheassociatedinformationwithouthavingtoaccessthecodesdictionary.

Furthermore,intheActivitieswindow,anewcolumnhasbeenintroducedintheCodesdetailwindowtabindicatingifanassignedactivitycodeisanEPS,global,orprojectlevelcode.

Tousethisfunction:

•IntheProjectssection,ontheEPSorActivitieswindow,clicktheCodesdetailwindowtabor;

•ClickontheResourcestablocatedonthetopmenutoaccesstheResourcessectionandthenclickontheAdministrationtab.

Page 64: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.6.5WorkspaceThisiswheresummaryinformationfromuserdefinablePortletsmaybeviewed:

3.6.6TeamUsageOnceresourcesareassignedthisallowsthedisplayofresourceshistogramsandusagespreadsheet:

Page 65: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.6.7IssuesThisiswhereissuesaremanagedandisnotcoveredinthisbook.

3.6.8RisksThisiswhererisksaremanagedandisnotcoveredinthisbook.

3.6.9DocumentsThisiswheredocumentsaremanagedandisnotcoveredinthisbook.

3.7Right-clickingwiththeMouseItisimportantthatyoubecomefamiliarwiththeright-clickfunctionofthemouseasthisisoftenaquickerwayofoperatingthesoftwarethanusingthemenus.Theright-clickfunctionwillusuallydisplayamenu,whichisoftendifferentdependingonthedisplayedViewandwindowselected.Itisadvisedthatyouexperimentwitheachviewtobecomefamiliarwiththemenus.

3.8FullScreenModeIconThe FullScreenMode(F11)iconisusedtoexpandtheworkingareahidingallthewebbrowsermenusandallowingmorerealestateonthescreentowork.

3.9MultipleBrowserWindowsandTabsTheP6WebdoesallowmultiplebrowserwindowsandtabsopenwhichwilloftensavetimeinsteadofopeninganewP6Windowinthesamebrowserwindow,especiallyifyousystemhasaslowresponsetime:

Page 66: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Sometimesawindowisnotdisplayedandishidden,theauthorfoundthishappenedwiththeprintpreviewfunction.IfyouthinkthishashappenedpressAltTab.

3.10SearchFunctionYouwilloftenseea Searchiconandclickingonthisiconwillopenacontextsensitivesearch.Forexamplethepicturebelowisasearchforaresourcethatcontainsprojinthenameandhasshortlistedfourresources:

3.11AccessingHelpThePrimaverahelpfilemaybeaccessedby:

Page 67: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ClickingontheHelp icononthetoplefthandsideofthescreenand

•Clickingona icon.PressingtheF1keywillnormallyONLYopenwebbrowserhelpfile.

3.11.1OnlineHelpforP6ProfessionalInR8.3itispossibletoenableonlinehelpinP6ProfessionalconnectingtotheEPPMdatabase.

Tousethisfunction:

•GotoAdminister,ApplicationSettingsandselectGeneral,•EntertheURLforP6ProfessionalonlinehelpfilesandthenclickSave.

TheAlwayslaunchOnlineHelpfortheF1shortcutkeyandcontext-sensitivehelpcheckboxcausesthosefilestoloadwhenuserspresstheF1keyorlaunchcontext-sensitivehelp.

3.12FindandReplaceOptionInP6R8.3userscanfindandreplaceanytextthatisbeingdisplayedinthecolumnsoftheEPS,Activities,andResourcesAssignmentswindows.PreviousversionshadaFindoptionavailableonly.

Toaccessthisfunction:

•GototheEditmenuorclickonthe Find/Replacebuttonslocatedinthetoolbaror;•Right-Clickwiththemousetoopenupthemenu;•Select Findor ReplacebuttontoopentheformtoFindorReplacetext.

Page 68: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.13ClosingaProjectTherearetwomethodsforclosingaproject:

•FromtheProjects,OpenProjectsmenu,leavingoneprojectopentousethisform,•Version8.4nowallowsyoutoreviewcurrentUserswhenselectingaprojecttoopenor

close:

Page 69: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SelectingProjects,EPS,Actions,CloseAll willcloseallprojects:

Page 70: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.14PopupWindowsTherearetwotypesofpopupwindowsyoumaybepresentedwith:

•Awebbrowserwindowwhenthebrowserrequirestheusertoallowpop-upsortoloadfurthersoftwaretooperatesuchaJavascript.Theseshouldnormallybeallowedotherwisethesoftwarewillnotoperate:

•P6popupslikethepicturebelowwhichonceyouunderstandhowthesoftwareoperatesyoushoulddisablebyselectingtheDonotshowagainoption.

Page 71: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.15ClosingDownToclosedown:

•SelectLogoutfromthetoprighthandsideofthescreentoclosedowntheapplication.•Thenclosethewebbrowserifyounolongerrequirethebrowseropen.

3.16Workshop1–NavigatingAroundtheWindows

BackgroundTobecomefamiliarwithPrimaverayouwillopenyourdatabaseandnavigatearoundtheWindows.

Note:Yourwindowmaylookdifferentfromtheoneusedinthispublication.

Page 72: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Assignment1.OpentheP6WebClientfromyourWebBrowserandlogintotheapplication,your

instructororadministratorshouldsupplyyoualoginname,passwordanddatabaseID.

2.Clickonthe Dashboardstab:

ObservewhichprojectsorPortfolioisbeingdisplayedbyviewingtheFilterbyfieldinthetoprighthandside,

ClickonCollapseAllandthenExpandAlltocollapseandthenexpandthePortals.,Usethe Open, Closeand Maximize/MinimizeiconsmanipulatethePortlets,

Donotusethe Closeiconstoopenandcloseeachportal,ClickonCustomize,thisiswhereyoumayselectwhichdatayouwishtodisplayintheportals,

ClickonLayout,thisiswherethesizeandlayoutofPortalsarespecified,ClickonAccessandthisiswhereitisspecifiedwhocanviewthelayout,

Clickonthe totherightof andobservethemenuitems.

3.Clickonthe Portfoliostab:

FirsttimeusersmayhavetoselectatleastonePortfoliofromtheOpenPortfolioscommand,clickonthesmalldownarrowontherightofPortfolios.

Clickonthe totherightof andobservethemenuitems,

ClickonManagePortfolios,andobservethemenuitems.

4.Clickonthe Projectstab,

Thisiswhereyoumayopen,createordeleteprojectsandmanageviews,

Clickonthe totherightof andobservethemenuitems,

ClickontheOpenProjectstoopentheOpenProjectsform,EnsurethatatleastoneprojectisdisplayedintheRightHandSideoftheformandisthereforeopen,

Closetheformbyclickingonthe OKbutton,

Clickonthe buttonandtheprojectactivitiesshouldbedisplayed,

Clickonthe FullScreenMode/NormalModetwicetodisplayandhidethefullscreen.YoumayhavetoedittheViewtoolbartodisplaytheiconorpressF11.

5.Clickon Resourcestab,donotsaveanychanges,thisiswhereresourcesaremanaged:

Page 73: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Clickonthefourtabsandobservethecontentofthewindows,

Clickonthetothe rightof andobservetheEnterpriseResourceDatamenuitem,whereyouareabletoeditGlobalResourcedata.

6.ClickonAdministeratthetoprighthandofthescreenandviewthemenu,7.Right-clickonEnterpriseDatafromtheAdministermenuandopenthiswindowina

newbrowsertab;iswhereGlobaldataismanaged,normallybytheadministrator:

Clickonthemenuitemsonthelefthandsideandobservethecontent.

8.ClickonAdminister,MyPreferences…,Globaltab,thisiswherethedisplayformatofsomedatamaybecustomized,itissuggestedthatyouchangethefollowingoptions,don’tforgettoclickonthe icontoopenuptheoptions:

DateFormat,DateFormat:settothedateformatyourcountrynormallyuses,DateFormat,TimeFormat:setto24hour,DonotShowminutes:

TimeUnitsFormat,DisplayTimeUnitsinHours,sopeoples’workwillbedisplayedinhours,

TimeUnitsFormat,DisplayDurationsinDayssoactivitydurationswillbedisplayedindays,

ShowsubunitsandShowdurationlabelsoyouwillseeifanydurationsarenotwholedays:

Page 74: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheCurrencyshouldbesetbyyouradministratortoyourcountriescurrency.Changingthecurrencyherecouldaffectallthecostsofalltheprojectsyouopenandtheymaycalculateadifferentvaluetothevalueseenbyotherusers.

Clickon Savebeforeleavingthiswindoworyouwillloseyouredits.9.ClickonAdministertab,MyPreferences…,Viewtab,thisiswhereyoumayseewhich

datayouhavebeenallowedtoaccessbytheAdministrator.

Youmayre-orderorhidethetabsfromviewinthisscreen.

Clickon SaveandCloseatthebottomofthescreentoensureyoureditsaresaved.

NOTESFORTRAININGCOURSEINSTRUCTORSAND/ORDATABASEADMINISTRATORS:

Page 75: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

1.Trainingcourseinstructorsand/oradministratorsmayconsiderpurchasingtheinstructor’sPowerPointpresentationfromwww.primavera.com.auorwww.eh.com.auorwww.primaskills.com.au.Theseslideshowsareusuallyavailableintwoformats,fullyeditablePowerPointorreadonlypdfandasampleinpdfformatmaybedownloadedfromthiswebsite.

2.Completedworkshopsmaybedownloadedfromwww.eh.com.au.3.Ifyouareatrainingorganizationandyouwishtotrainmultipleusersinonedatabase

pleasecontacttheauthorforapaperonhowtosetupyourdatabase.

4.Insummary,whenmultipleusersareworkinginasingledatabasetheDatabaseAdministratororCourseInstructorshould:

Createatrainingdatabasewithsampledata,

CreateanEPSNodeforeachstudenttoworkin,

CreateauniqueResourceforeachstudenttouse,

CreateeachstudentaloginwithReadOnlyaccesstothesampledataandreadwritetotheirEPSNode,butunabletoseeotherstudentsEPSNodes,

CreateaTrainerloginwithReadWriteaccesstothewholedatabase,

AssignaprotocolthatthestudentsusetocreateProjectIDsandResourceIDssoeachstudentprojectandtheirresourcesallhaveauniquename.

5.Theauthorwouldwelcomeanyfeedbackonthestructureoftheworkshops.

WhensettingupusersitisimportanttoensurethateachuserhastheappropriateGlobalandProjectprofiles.ForexampleifauserisnotgivenaccesstoanOBSNodethensomeformswillnotdisplaydates.

Page 76: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4CREATINGANEWPROJECTThereareseveralmethodstocreateanewprojectfromtheProjects,EPSwindow:•Addinganewproject,or•Copyinganexistingprojectandeditingit,or•UsingtheProjectTemplatefunction,or•ImportaprojectcreatedfromanotherPrimaveradatabaseorcreatedwithanothersoftware

programsuchasMicrosoftProject,orAstaPowerprojectbutsavedinMicrosoftProjectXMLorPrimaveraXMLformat.

TheP6WebmenuisnotthesameasatraditionalMicrosoftWindowsmenusystemandnewusersandusersconvertingfromtheP6OptionalClientorProfessionalClientwillfinditdifficulttofindfunctionsintheP6Web.

Thetablebelowliststhemainfunctionsthatarerequiredtocreateaprojectandsetupaproject:

Topic MenuCommand

AddinganEPSNodeSelectProjects,EPS,Actions,Add, AddSiblingEPSorAddChildEPS,

EPSNodesmaybereorderedusingthe Bluearrows.CreatingaProject SelectProjects,EPS,Actions,Add,AddProject… icon.

CopyingaProject SelectProjects,EPS,selectyourprojectandusetheEditorLeft-clickCopyandPastecommand.

EditingEPS:

•AnticipatedDates,

•IDandName,

•ResponsibleManager

SelecttheProjects,EPS,selecttheEPSNodeandclickontheGeneraltabinthelowerpaneofthewindow.

EditingProject:

•Dates,

•IDandName,

•Owner,

•Location,

•ResponsibleManager

SelecttheProjects,EPS,selectyourprojectandclickontheGeneraltabinthelowerpaneofthewindow.

SavingadditionalprojectorEPSNodeinformation

SelecttheProjects,EPS,selectyourprojectorEPSNodeandclickontheNotebookstabinthelowerpaneofthewindow.

AssigningtheProjectDefault:

Page 77: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ProjectCalendar

•%CompleteType

•ActivityType

•CostAccount

•Price/Unit

•ActivityIDNumbering

•DefaultResourceRate

TheseareassignedtonewactivitiesfromtheProjects,EPS,selectyourprojectandthenselectActions,SetProjectPreferences icon,clicktheDefaultsoptionintheDefaultsform.

4.1CreatingaBlankProjectYoumaycreateanewprojectatanypointintimebyselectingtheProjects,EPS,Actions,Add,AddProject… iconfromthemenuorclickingontheAddProject… icononthetoolbartoopentheAddProjectform.

Youwillberequiredtoenterthefollowinginformation:

•TheProjectID,aUniquecodewithinonedatabasetorepresenttheproject(amaximumof20characters),andProjectName.

Page 78: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TheDescriptionsectionmaybeusedtorecordprojectinformation.InformationenteredintheDescriptionsectionmaynotbeviewedintheOptionalClient.YoushouldusetheNotebooksfunctionoraCustomUserFieldifthereare

OptionalClientUsersonthesystemthatneedtoseethedata.

•TheEPSNodetheprojectistobeassigned.•TheResponsibleManagerisselectedfromtheOBSstructure.IftheOBShasnotbeen

definedortheresponsibilitynotassignedthenEnterprisemaybeselectedastheResponsibleManager.

•AProjectPlannedStartdate,whichistheearliestdateanyun-startedactivitywillbescheduledtocommenceandanoptionalprojectMustFinishBydate.

BesuretochecktheStartTimeasP6maydefaulttoanunwantedtime.

•AprojectMustFinishBydateisoptional.WhenaprojectMustFinishBydateissettheprojectfloatwillbecalculatedtothisdateandnottothelatestactivityfinish.

•Youmayalsoatthispointintimeelecttouseanyexistingprojectortemplatetocopyfrom,thistopicisdiscussednext.

Itisanormalpracticetocopyandpasteprojectstokeepacopyofaprojectataspecificpointintime,normallyaftereachupdate.WhencopyingprojectsyoushouldconsiderutilizingthePrimaveradefaultsfortherenumberingoftheProjectID.

4.2CopyanExistingProjectorEPSNodeAProjectmaybecopiedwhencreatinganewprojectorintheProjects,EPSWindowby:•HighlightingtheprojectyouwishtocopyandselectEdit,CopyorCtrl+C,•HighlightingtheEPSNodethatyouwishtoassociatethenewprojectwithandselectEdit,

PasteorCtrl+V,•TheCopyProjectOptionsformwillthenbedisplayed,enablingyoutochoosewhich

Projectdataitemsyouwishtocopywiththeproject,

•Openandeditthenewproject.

Page 79: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AnEPSNodemayalsobeselectedandcopiedintheProjectswindow,andpastedtoanotherlocationwhichwillcopytheprojectsandaddanotherEPSNode.

Multipleprojectsmaynotbecopied,exceptbycopyinganEPSNode.

ThecopiedprojectsandcopiedEPSNodeswillbeassignedanewIDwithasequentialnumberaddedtotheOriginalID.

UnliketheWindowsClientthesettingsintheformabovearenotrememberedthenexttimeyoucopyaproject.

4.3UsingtheProjectTemplatesFunction

4.3.1CreatingaNewProjectfromaTemplateP6Version8releasedanewfeaturecalledProjectTemplateswhichhasreplacedtheformerP6MethodologyManagerfeature.TheprojecttemplatescanstoreitemssuchasprojectandWBSinformationaswellasactivityleveldataincludingrelationshipsandcostinformation.Thiscanallowtheorganizationtoenforcecommonschedulingstandardsacrosstheenterprise.

Projectscanbecreatedfromtemplatesandtemplatescanalsobecreatedfromprojectsallowingbestpracticeprojectstobeusedinthefuture.

Page 80: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

YoumaycreateanewprojectfromanexistingtemplatebyfollowingthesamestepsintheCreatingaBlankProjectprocedureaboveuntilyoureachtheCopyformexistingprojectortemplatestep,then:

•Selectthe iconfromtheCopyfromexistingprojectortemplateoption.

•TheSelectProjectorTemplateformwillnowbedisplayed:•Changethefilteratthetopoftheformtodisplaythetemplates:

•Navigatetotherequiredtemplateandselect OK.

4.3.2CreatingaNewTemplate

Page 81: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TocreateanewProjectTemplate:

•SelecttheProjects,EPSWindow,Actions,Add,AddTemplate ,

•UsetheCopyfromexistingprojectortemplateoptiontoselectanexistingtemplateorprojecttocopy,

•ClickontheAdvancedtabtoselectwhichdatatocopy:

4.4ImportingaProjectDifferentVersionsofPrimaverarunondifferentdatabasesincludingOracleandMicrosoftdatabases.Primaverawillonlyoperatewiththedatabaseformatwithwhichithasbeeninstalledandsetup.

Primaverawillnotopenastand-aloneprojectfile,doesnotsupplyareader,andallprojectdatahastobeimportedintoadatabasebeforeitmaybeopened.

Importingaprojectmaybringinlargequantitiesofunwanteddataandmaycalculatedifferentlyfromthedatabaseitoriginatedfrom.

Youmayberequiredtoimportaprojectthathasbeencreatedinanotherprogramsuppliedbysomeonefromwithinoroutsideyourorganization.Primaveraisequippedwithasetoftoolsforimportingprojectsfromothersources.

4.4.1PrimaveraFileTypesThereareafewPrimaveraproprietaryfileformatsthatyouneedtobeawareofwhenusing

Page 82: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

theP6WebClient:

•PrimaveraXML–AformatintroducedwithPrimaveraVersion6.0whichcanbeusedtoexchangedatafromoneprimaveradatabasetoanotherprimaveradatabase.TheXMLfileformatconformstothePrimaverasecuritysettingswithinthetoolallowinggreatercontroloverwhichdataitemscanbeimported.

•ToimportorexportanXMLfile(bothMicrosoftProjectandPrimaveraXMLformat)youneedtogototheProjects,EPSWindowandselecttheActions,Import/ExportmenuhastheXMLImport/Export icon:

•XER–UsedtoexchangeoneormoreprojectsbetweenPrimaveradatabaseswiththeProfessionalorOptionalClientregardlessofthedatabasetypeinwhichitwascreatedandexportsallprojectdata.

•P6WebClientmayNOTimportandexportXERfiles.•EarlierversionsofXERfilesmaybeimportedintolaterversiondatabases.•AP6View(formatting)isnotpartofanXERfile.•OtherProfessionalClientformatslikePLF,ANP,ERP&PCFarenothandledbytheWeb

tool.XERfilesmayonlybeimportedusingtheProfessionalandOptionalClienttoolsandnotwiththeWebClient.

Page 83: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4.4.2NonPrimaveraFileTypesYoumayalsoimportandexportdatatoandfromanExcelfileandaMicrosoftProjectXMLfile.

MSProjectXML–ThisisthesamesoftwarelanguageasthePrimaveraXMLfilebutadifferentformattoaPrimaveraProjectXMLfilewhichcanbeusedtoexportprojectsinaformatthatcanbeimportedintoMSProject.

BoththeProjects,EPSandActivitieswindowsActionToolbarshaveimportandexporticonstorunwizardsthatwillguideyouthroughtheprocessofimportingprojectsintoyourschedule.

ReadtheAdministratorsGuidecarefullybeforeimportingaprojectasthisisaverycomplexoperationandmayimportunwanteddataintoyourdatabase.Itisrecommendedthatyouconsiderestablishingasacrificialdatabaseintowhichyouimportprojectssothatcorporatedatabasesarenotfilledupwithunwanteddata.

4.4.3XMLImport/ExportEnhancementsTheXMLimport/exportfunctionalityhasbeenimprovedinVersion8.3:

•XMLfilesmaybeexchangedwithpreviousversionsofP6;fromR6.2SP4onward,

•AllfeaturessupportedbytheP6ProfessionalXERformatsuchasconstrainingofexternalrelationshipsduringimport,inclusionofPrice/Unitinresourceassignments,importofPastPeriodActuals;aresupportedinXMLformat,

•Itispossibletoimportorexportmultipleprojectssimultaneously;

∘Whenexportingmultipleprojects,theprojectsarecombinedintoasingleXMLfile,

∘ImportingmultipleprojectsrequirestheprojectstobecontainedinasingleXMLfile.

Toaccessthisfeature:

•GototheEPSwindow,Projectssection;

•Clickonthe XMLProjectImport/ExporticontoopentheImport/ExportProjectform.

Page 84: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4.4.4UN/CEFACTXMLDataExportP6Version8.3supportsUNCEFACTXMLformatfromtheProjects,EPSwindow.

Toaccessthis,either:

•GotoActions,Import/ExportandselectXMLProjectImport/Export;•ClickontheExporttabandselectUN/CEFACTXMLfromthedropdownmenuofthe

ExportTypelistor;

•Clickonthe XMLprojectImport/ExportbuttonlocatedonthetoolbarandthenselectExporttab.

ThisformatismandatedbymanyUSGovernmentagenciesanditisdesignedtoexchangescheduleandcostdatainasoftware-neutralformat.ThisfeatureisofparticularimportanceforalltheuserswhoworkwithU.S.DepartmentofDefenseandotherU.S.governmentagencies.

Page 85: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4.4.5GranularDataControlDuringXMLImportP6R8.3hasanewscreenfortheXMLprojectimportfunctionalitywhichprovidestheuserwiththepossibilitytoviewthedatainthefilethatisbeingimportedandmodifyitasrequiredbeforeimportingitintothedatabase.

UnlikepreviousversionsofP6inwhichProjectManagershadtomanuallyscanandmodifydatabeforeimporting,inP6R8.3ispossibletoexcludealltheunwanteddatasuchascodes,UDFsandresourcesbeforeimporting.

4.5SavingProjectInformationonChangingWindowsUnliketheP6WindowsClienttheEPPMWebClientrequirestheusertosaveinformationwhenchangingwindows.

TheuserisoftenpromptedwhenchangingwindowsandthisprocessensuresthatthedataiswrittentotheEPPMdatabase.

•Dependentonwhichscreenyouarecurrentlymodifyingdatawithinyoumaynoticethatasmall iconappearsnexttoactiveelement.

•Examplesofthisdatawouldbeeithera iconintheprojectsscreen,orthe iconoriconintheactivitiesscreen.

•Tosaveprojectandactivityinformationselectthe SaveiconfromthetoolbaroralternativelyselectCtrlS.

•Ifyouattempttoleavetheactivescreenwithoutsavingyouwillbepromptedwithaform

Page 86: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Ifyoudonotclickonthe Yesiconyourpreviousworkwillbelost.•Clickinthe Cancel(Ecs)icontocancelyoursave.

4.6DeletingaProjectTodeleteaproject:

•SelectProjects,EPS,•Selecttheproject,

•SelectActions,Delete orusethedeletekey,

•Then Savetoconfirmdeletion.

4.7SettingUpaNewProjectTheprojectdetailsandpreferenceswillneedtobeaccessedtoreviewormodifysomeofthebasicProjectorEPSinformationenteredwhenaprojectwascreated.

UsersoftheP6theProfessionalorOptionalClientwillbemorefamiliarwiththisinformation.TheEPPMwebusesacombinationofformsandtabstoeditthisdatawhichareverydifferenttotheWindowsClient.

4.7.1Project,EPSGeneralTabFromtheProject,EPSWindow:

•HighlightaprojectorEPSNode,

•Theprojectmustbeopentoeditsomeprojectdata,

•Youmustalsohavetheappropriateaccessrightstoeditdata,

•ClickontheGeneraltab:

Page 87: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheGeneraltabwillnowdisplayfromthebottomofthewindow

•TheProjectIDandProjectNamecanbeeditedfromthiswindow.•TheProjectStatuscanbeeditediftheprojectisopen.•TheResponsibleManagercanbechangedhereallowingaccessrightstotheprojecttobe

edited.

•AnewfeatureforassigningaProjectOwnercannowassignedinthiswindowtoanexistingresourceinthedatabase.

•CheckOutStatusenablestheusertodetermineiftheprojectischeckedinorcheckedout(NewtoVersion4.1).CheckedOutByandDateCheckedOutenablestheusertoestablishiftheprojectiscurrentlycheckedout.

Atthispoint,aprojectwouldhavenormallynotstartedandyouwouldsettheprojectstartdatesometimeinthefutureusingtheProjectPlannedStartfieldintheProject,Details,Generaltab:

•ScheduledDates

TheProjectPlannedStartisthedatebeforewhichnoactivitywillbescheduledto

Page 88: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

start.

TheMustFinishBydateisanoptionaldate.WhenthisdateisentereditisusedtocalculatetheLateFinishofactivities,thusallTotalFloatwillbecalculatedtothisdate.ThistopiciscoveredintheCONSTRAINTSchapter.

TheScheduledFinishdateisacalculateddateandisthedateofthecompletionofthelastactivity.

TheDataDateisusedwhenupdatingaproject.ThistopiciscoveredinUPDATINGANUNRESOURCEDSCHEDULEchapter.UnlikeMicrosoftProject,allincompleteworkisscheduledtotakeplaceafterthisdate.

TheActualStartdateisinheritedfromtheearlieststartedactivity.TheActualFinishdateisinheritedfromthelatestcompletedactivitywhenallactivitiesarecomplete.

•AnticipatedDates

TheAnticipatedStartandAnticipatedFinishdatesmaybeassignedbeforeaWBSstructureandActivitieshavebeencreated.ThestartandfinishdatescolumnsandbarsattheEPSleveladoptthesedateswhentherearenoactivities.AfterActivitieshavebeencreated,theymayremainasahistoricalrecordonlyandarenotdisplayedorinheritedanywhereelse.

AnticipatedDatesmayalsobeassignedtoWBSNodesintheProjects,Activities,Generaltab.

4.7.2ProjectPreferencesFormTheprojectpreferenceformiswhereotherimportantprojectdefaultsaresetandisaccessedbyselectingProject,EPS,Actions,SetProjectPreferences:

Page 89: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4.8SavingAdditionalProjectandEPSInformation–NotebooksOftenadditionalinformationaboutaProjectorEPSNodeisrequiredtobesavedwiththeprojectsuchaslocation,clientandtypeofproject.ThisdatamaybesavedintheProjectDetails,Notebookstab.

ToaddaNotetoaProject:•Clickto opentheNotebooksform.•SelectaSelectNotebookTopicfromthelistbyclickingontheNotebookTopicyouwish

toselectandclickontheAssignicontoaddthetopictotheNotebook:

Page 90: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Closetheformbyclickingonthe Closeicon.YoumaynowaddnotestotheselectedProjectNotebookTopicbydoubleclickinginthenotebooktopicrowellipsis button:

•NotesmaybeaddedtoEPSNodes,ActivitiesandWBSNodesinthesamewayasProjects.

4.10Workshop2–CreatingYourProject

BackgroundYouareanemployeeofWilsonInternationalandareresponsibleforplanningtheBid

Page 91: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

preparationrequiredtoensurethataresponsetoanRFQ(RequestForQuote)fromOzBuildPtyLtdissubmittedontime.Whileshort-listed,youhavebeenadvisedthattheRFQwillbeavailableon02December2013at8:00hrs(8:00am)andyouwillberequiredtosubmit3boundcopiesoftheproposalbefore27January2014at16:00hrs(4:00pm).

NOTE:WhenmultipleusersareworkinginasingledatabasethentheDatabaseAdministratoror

Instructorshould:

•CreateanEPSNodeforeachstudenttocreatetheirprojectsunder.

•AssigneachstudentauniqueProjectIDtousewhencreatingtheirprojects.

Assignment1.CreateanewprojectwiththefollowinginformationbyselectingProjects,EPStoopen

uptheEnterpriseProjectStructurewindow:SelectanappropriateEPSNodeinyourdatabasetocreatetheprojectoryournominatednodewhenworkinginashareddatabase,

Right-clickandselect AddProjectfromthemenuorclickonthe toolbaricon:

2.ThisshouldopentheAddProjectform,enterthefollowinginformationintheform:ProjectID–OZB.

NOTE:ThisProjectIDmaynotbeacceptedifyouareworkinginashareddatabasewhenthereisanotherprojectwiththisProjectID.YoumayneedtouseanotheruniqueProjectIDinthissituation,forexampleOZBplusyourinitials.

ProjectName–BidforFacilityExtensionDescription–Youmaywishtoenterdetailsoftheprojecthere.EPS–Acceptthedefault,whichistheoneyouhighlighted,butmaybechangedhere,ResponsibleManager–AcceptthedefaultPlannedStartDate–02December2013at08:00

Page 92: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

NOTE:Ensurethatthe08:00(8:00AM)isaddedinthisstep.Forgettingtocheckand,ifrequired,settingthetimewhenassigningdatesmayleadtotheschedulenotcalculatingcorrectly.

MustFinishBy–LeaveBlankCopyfromexistingprojectortemplate–leaveblank

Click tocreatetheproject.

3.Theprojectshouldnowbeopen.

4.SelectProject,OpenProjectsandensureonlyyournewprojectisopen.YouareabletocloseallprojectsbeforeyoucreateanewprojectbyselectingProject,EPS,Actions,CloseAll.

5.ChecktheprojecticonundertheProjects,EPS,thisshape indicatestheprojectisopen.

6.Ensuretheprojectisselectedbyclickingonit.

7.PressF11tomovetotheFullScreenMode8.SelecttheGeneraltabfromthebottomofthescreenanddragthehorizontalsplitto

showtheGeneraltabdatafields.

9.Setorcheckthefollowingprojectinformation:

SettheStatustoWhat-if,theprojectneedstobeopentochangethis.Notethechangeintheshapeoftheprojecticonto indicatingitisanunsavedWhatIfproject.

AnticipatedStart–02Dec1308:00AnticipatedFinish–27Jan1416:00ProjectPlannedStart–02Dec1308:00DataDate–02Dec1308:00

10.Savethedatabyclickingonthe Saveiconatthetopofthepage.ClosetheGeneraltab.

11.SelectaGanttChartViewfromthetoolbartoshowtheGanttChart,suchasStandardandifnoGanttChartisdisplayedclickonthe icontodisplaythebars.

12.YoushouldnowseeabarintheBarChartabovespanningthesedatesalthoughtherearenoactivitiesintheschedule.Ifnobarisdisplayedbecauseyouareinthewrongtime

Page 93: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

zonethendouble-clickintheGanttChartarealevelwiththeprojecttobringthebarintoview.

13.SelecttheNotebookstabatthebottomandaddaNotebookTopicusingasuitabletopicsuchasAssumptionsstating,“RFQwillnotbeavailablepriorto02December2013”.

14.Savethedatabyclickingonthe Saveiconatthetopofthepage.

15.Yourprojectshouldlooklikethis:

Page 94: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

5DEFININGCALENDARSThefinishdate(andtime)ofanactivityiscalculatedfromthestartdate(andtime)plusthedurationofthecalendarassociatedwiththeactivity.Therefore,afive-daydurationactivitythatstartsatthestartoftheworkdayonaWednesday,andisassociatedwithafive-dayworkweekcalendar(withSaturdayandSundayasnonworkdays)willfinishattheendoftheworkdayonthefollowingTuesday.

Primaverahasthreecategoriesforcalendars:

•Global –ThesecalendarsareavailabletoallProjectsandResources.

•Project–Thesecalendarsareonlyavailabletotheprojectstheyarecreatedin.Thesemayonlybecreatedforaprojectwhentheprojectisopen.

•Resource–Therearenowtwotypesofresourcecalendars:Personal,newtoPrimaveraVersion8.1,andShared,whichisthesameastheearlierResourcecalendar.

APersonalCalendariscreatedforaspecificindividualresource.ASharedCalendarmaybeassignedtooneormoreResources,whichinturnmaybeassignedtoanactivityinanyproject.

AResourcewillbescheduledaccordingtoaResourceCalendarwhentheActivityTypeissettoResourceDependent;otherwisetheactivityisscheduledaccordingtotheActivitycalendar.

WhenanactivityismadeResourceDependent,unlikeinsomeothersoftware,itstillacknowledgestheActivityCalendarforcalculatingthestartoftheresourcework.YoumaywishtoconsiderplacingResourceDependentactivitiesona24-hour,7-dayperweekcalendarincircumstanceswhenresourcecalendarshavestarttimesthatareearlierinthedaythantheactivitycalendarstarttimes.Thispreventsadelaytostartofresource-drivenactivitiesbyanActivityCalendar.

Youmaycreateanew,oreditanexisting,calendartoreflectyourprojectrequirements,suchasaddingholidaysoradditionalworkdaysoradjustingworktimes.Forexample,someactivitiesmayhavea5-dayperweekcalendarandsomemayhavea7-dayperweekcalendar.

Thischaptercoversthefollowingtopics:

Topic MenuCommandDatabaseDefaultCalendar

SelectAdminister,EnterpriseData,Global,GlobalCalendars…andclickontheDefaultCalendar icon.

AssigningtheDefaultProjectCalendar

Thiscalendarisassignedtonewactivities.FromProjects,EPS,selectyouproject,Actions,SetProjectPreferences

Page 95: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

icon,clicktheDefaultsoptionintheDefaultsform.

Creating,copying,editingordeletingGlobal,ProjectorResourceCalendars

SelectAdminister,EnterpriseData,andselecteitherGlobal,GlobalCalendar,orProjects,ProjectCalendarsorResources,ResourceCalendars,thenselectthe icon,selectacalendartocopyfrom(tocreateanewcalendarbycopyinganexistingcalendar)or todelete.

Renaminganexistingcalendar

SelectAdminister,EnterpriseData,Global,GlobalCalendars,orProjects,ProjectCalendarsorResources,ResourceCalendars,clickthedescriptionandthenmodifyit.

5.1DatabaseDefaultCalendarTheDatabaseDefaultCalendarisselectedintheAdminister,EnterpriseData,Global,GlobalCalendarsandclickingontheDefaultCalendar icon.

TheDatabaseDefaultCalendarisusedtodisplaytheNonworkingtimesinallviews,allprojectsandallusersinadatabase.Thisisaveryseriouslimitationforprojectsthathavemultiplecalendars:

Page 96: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Itisnotpossibleforuserstodisplaydifferentnonworkperiodsfordifferentprojectsorviews,asinmostotherschedulingsoftwarepackages,withoutaffectingallotherprojectsinadatabase.ThismaybecomeanissuewithprojectsthathavedifferentworkperiodsandmaybesolvedbycreatinganotherdatabasewithadifferentDatabaseDefaultCalendar.

5.2AccessingGlobal,ResourceandProjectCalendarsCopying,editinganddeletingcalendars:

•GlobalCalendarsmaybeaccessedfromtheAdminister,EnterpriseData,Global,GlobalCalendars…window,

•ProjectCalendarsmaybeaccessedfromtheAdminister,EnterpriseData,Projects,ProjectCalendars…window,

•ResourceCalendarsmaybeaccessedfromtheAdminister,EnterpriseData,Resources,ResourceCalendars…window,

Thefollowingrulesdictatewhenyouareabletoaccessthecalendars:

•GlobalandResourceCalendarsmaybeaccessedwithorwithoutanyprojectsopen.•AProjectCalendarmayonlybecopied,edited,anddeletedwhentheprojecthasbeen

opened.

•Tolist,create,andeditmorethanoneexistingProjectCalendaratthesametimealltheprojectsinquestionmustbeopen.

5.3TheProjectDefaultProjectCalendar

5.3.1UnderstandingtheProjectDefaultProjectCalendarAprojectisassignedaDefaultProjectCalendarwhichmaybeeitheraGlobalorProjectcalendar:

•AllnewactivitiesareassignedtheprojectDefaultProjectCalendarwhentheyarecreated.ThisisthesamewaythatP3,SureTrakandAstaPowerprojectoperate.ThisisunlikeMicrosoftProjectandchangingtheDefaultProjectCalendarwillNOTaffectthecalendarassignedtoanyactivities.

•TheDefaultProjectCalendarmaybeselectedforcalculatingleadsandlagsintheScheduleProject,Optionsform.

5.3.2AssigningaDefaultProjectCalendarToassignorchangetheDefaultProjectCalendaraprojectmustbeopen:•SelecttheProject,EPSWindowandhighlighttheproject,•SelectActions,SetProjectPreferencestodisplayProjectPreferencesform,

Page 97: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SelecttheDefaultsoptionfromtheleftoftheProjectPreferencesform,•ClickontheCalendaricontoopentheSelectCalendarform:

•Selectthecalendartobeassignedtotheproject.Careshouldbetakenwhenselectingthecorrectcalendarastheglobal,resourceandprojectcalendarsiconswillbothappearidenticaltotheuserwithinthisform.Theauthorsuggeststhatyouuseacalendarnamingconventiontodifferentiatethedifferenttypesofcalendars.

Page 98: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Select OK.•Select SaveandClose.

5.4CreatingaNewGlobalCalendarYoucancreateanewGlobalCalendarbycopyinganexistingGlobalorResourceCalendar.TocreateanewGlobalCalendar:•SelectAdminister,EnterpriseData,Global,GlobalCalendars.•Thenclickonthe icontocreateanewcalendar,

•SelectanexistingGlobalorResourcecalendartocopy,•Assignaname,itisbesttokeeptheseshortastheyaretheneasilydisplayedinacolumn,

•Clickonthe Saveicon.

5.5CreatingaNewProjectCalendarAprojectmustbeactivetocreateaProjectCalendar.YouMAYcreateanewProjectCalendarbycopyinganexistingGlobal,ResourceorProjectCalendar.TocreateanewProjectCalendar:•SelectAdminister,EnterpriseData,Projects,ProjectCalendar,•Selectyourprojectnameintheform,otherwiseyouwillnotbeabletocreateacalendar,

•Thenclickonthe icontocreateanewcalendar,or

•SelectanexistingGlobal,ResourceorProjectcalendartocopyfrom,•Assignaname.Itisbesttokeeptheseshortastheyaretheneasilydisplayedinacolumn,

•Clickonthe Saveicon.Ifyouwishtocopyanotherprojects’calendarthenthatprojectmustbeopen.

Page 99: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

5.6SharedCalendarAResourceoraGlobalcalendarmaybeassignedtooneormoreresources.ThisisdifferentfromthephilosophyofMicrosoftProject,P3andSureTrak,whereeachresourcehasitsowncalendarbasedonaprojectcalendarandmanyresourcesarenotabletoshareonecalendar.

AResourcewillbescheduledaccordingtotheassignedResourceCalendarwhentheActivityTypeissettoResourceDependent;otherwise,theactivityisscheduledaccordingtotheActivityCalendar.

ResourceavailabilityisdisplayedinResourceUsageProfilesandisbasedontheResourceCalendarevenwhenitisassignedtoaTaskDependentactivity.

5.6.1CreatingaNewSharedCalendarTocreateanewSharedCalendar:

•SelectAdminister,EnterpriseData,Resources,ResourceCalendars,•SelectSharedCalendars,•Thenclickonthe icontocreateanewcalendarwhichwilldisplaytheSelectCalendar

ToCopyformor,

•SelectanexistingGlobalorResourcecalendartocopy.YouMAYNOTcopyanexistingProjectcalendar,

•Select OK,•Assignaname,itisbesttokeeptheseshortastheyaretheneasilydisplayedinacolumn,

•Clickonthe Saveicon.

Page 100: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

APersonalCalendarmayalsobemadeintoaSharedCalendarby:•HighlightingthePersonalCalendar,andselectingtheConvertToSharedCalendar

icon,

•Click Yeswhentheformasksforconfirmation,•Clickonthe Saveicon.

5.6.2CreatingNewPersonalCalendarThesemaybecreatedfromtheCalendarformby:•SelectAdminister,EnterpriseData,Resources,ResourceCalendars,•SelectPersonalCalendars,•Thenclickonthe icontocreateanewcalendartodisplaytheSelectResourceform

and

•Expandthehierarchicaltree,selecttheappropriateresourceandclick OK,

Page 101: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Clickonthe Saveicon.

ASharedCalendarmayalsobemadeintoaPersonalCalendarby:

•HighlightingtheSharedCalendar,andselectingtheConvertToPersonalCalendaricon,•Click Yeswhentheformasksforconfirmation,•Clickonthe Saveicon.

5.6.3PersonalandSharedCalendarsCalculationandDisplayThepicturebelowdisplaysthreeactivitieseach5dayslong:

•A1000isTaskDependentandacknowledgesthe5-dayperweekactivitycalendarandignoresallresourcecalendars,

•A1010andA1020bothacknowledgetheirrespectivePersonalorSharedCalendarsforschedulingthework,but

•A1010andA1020bothignoreResourceCalendarsforBarNecking:

•ThepicturebelowisfromtheWindowsClientanddisplayshowthecalendarsoperate.

Page 102: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

BarNeckingisbasedonActivityCalendarnotresourceworkingtimes.

5.7Administer,MyCalendarAusermaybeassignedtotheresourceandthentheymaycreateandthenedittheirownPersonalCalendarhere.Thisoptionworksinthesamewayaseditinganyothercalendar.

AresourcecalendarwillbeusedtocalculateactivitydurationswhenanactivityisassignedanActivityTypeofResourceDependent.

TheAdminister,MyCalendarmenuoptionisnotseenwhenauserisnotassociatedwitharesourceandaPersonalCalendarhasnotbeencreated.

5.8Promote,Copy,RenameandDeleteaCalendar

5.8.1PromotingaProjectCalendartoGlobal.AProjectCalendarmaybepromotedtobecomeaGlobalCalendar:•Opentheprojectthatthecalendarcurrentlyresidesin,

•SelectAdminister,EnterpriseData,Projects,ProjectCalendars,•SelecttherelevantProjectCalendar,

•ThenclickonthePromote iconandclickon Yestoconfirm,•Clickonthe Saveicon.

5.8.2CopyaCalendarfromOneProjecttoAnother

Page 103: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Tocopyacalendarfromoneprojecttoanother:

•Opentheprojectthatthecalendarcurrentlyresidesinandtheprojectthatitistobecopiedtoo,

•SelectAdminister,EnterpriseData,Projects,ProjectCalendars,•Thenclickonthe icontodisplaytheSelectCalendarToCopy,•SelecttheProjectradiobutton,•SelecttheProjectcalendartocopyfrom,

•Click OK,•Assignaname.Itisbesttokeeptheseshortastheyaretheneasilydisplayedinacolumn,

•Clickonthe Saveicon.

5.8.3RenamingaCalendarTorenameacalendar:

•SelectAdminister,EnterpriseData,Global,•Selectthecalendartoberenamed,

•Typetonewnameintothenamefield,

Page 104: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Clickonthe Saveicon.

5.8.4DeletingaCalendarTodeleteacalendar:

•SelectAdminister,EnterpriseData,•Selectthecalendartobedeleted,

•Clickonthe icon,

•WhentheCalendarhasbeenassignedtoactivitiesthenyouwillbepresentedwiththeoptiontoSelectReplacementCalendar:

•WhentheCalendarhasnotbeenassigned:

Page 105: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Clickon Yestoconfirm,•Clickonthe Saveicon.

5.9BaseCalendars

5.9.1UnderstandingBaseCalendarsWhencreatinganewProjectorResourcecalendar,aGlobalCalendarmaybeselectedfromthedropdownboxandthisfunctionwilllinkthecalendarholidaysfromtheselectedGlobalCalendarintothedisplayedcalendar.

IntheWindowsClientthisfunctioniscalledInheritHolidaysandExceptionsfromaGlobalCalendar.

TheGlobalexceptionswillremainlinkedtotheProjectorResourcecalendars(inthesamewayasaGlobalCalendarinSureTrakandP3)andachangetoaGlobalcalendarholidaywillbereflectedinacalendarwithInheritedHolidays.

Itissuggestedthatthisoptionisneverbeused.Eachcalendarshouldbecreatedasastandalonecalendar,withoutinheritingholidaysfromanothercalendar,and

Page 106: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

thereforewillnotchangeifanothercalendarhasholidayschanged.

5.9.2RemoveaBaseCalendarfromaCalendarToremoveaBaseCalendarfromanexistingcalendaryouwillhavetodeletethetextfromthebox.

5.10AdjustingCalendarWorkingHoursItisstronglyrecommendedthattheworkinghoursperdayareallthesamedurationwithineachcalendarandhavethesamestartandfinishtime;otherwise,one-dayactivitiesmayspantwodaysandtwo-dayactivitiesmayspanthreedays,etc.

5.10.1EditingCalendarWorkingHoursPriortoeditingacalendar,particularlyifitisaglobalcalendar,clickthe tabtoopentheUsedByformtodeterminewhichotherProjectsandResourcesalsousethecalendar:

Toeditacalendar:

•SelectAdminister,EnterpriseData,•SelecttheGlobal,ProjectorResourceCalendars,•Selectthecalendaryouwishtoedit,

•Thenclick toopentheStandardWorkWeekformandmodifyanexistingcalendar,

•Selectthedaytobeedited,byclickingonit;ONLYonedayatatimemaybeedited.•SelectingTotalworkhoursallowstheVIEWINGONLYthetotalnumberofhoursperday

butnocontroloverthestartandfinishtimes:

Page 107: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Toeditthestartandfinishtimes:

Grabthetoporbottomofthedaywiththemouseanddrag,or

ToaddorremoveabreaksuchasaalunchbreakclickontheDetailedworkhoursradiobutton.

•SelectingDetailedworkhoursallowstheadditionofmultipleworkperiodsforcreatingmealbreaksetc.byclickingonthe Addicon.

YOUMUSTEDITTHESTARTANDFINISHTIMESNOTTHENUMBEROFHOURS.

Page 108: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AnotherwaytomakeWorkDaysintoNonworkDaysisto,•Highlightthedayyouwanttoedit,

•SelectSetdayastobeNonworkandclick :

Page 109: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TomakeWorkDaysintoNonworkDays,highlighttheday(s)youwanttoeditasdescribedintheparagraphSetdayastobeWorkandclick .

WhenmakingaNonworkDayintoWorkDayensureyoucheckthattheworkinghoursarethesameastherestofthecalendar.

5.10.2EditingSelectedDaysWorkingHoursToedittheworkinghoursofindividualdays:

•SelecttheCalendartaband•ClickonthedaytoopentheEditDayformandeditthehours:

Page 110: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Whenanycalendarischangedoredited,theenddateofallactivitiesassignedwiththecalendarwillberecalculatedbasedonthenewcalendar.Thismaymakeaconsiderabledifferencetoyourprojectscheduledates.

Whencalendarshavedifferentstartandendtimessomeactivitieswillspanonedaymorethanthedurationoftheactivitybecause,forexample,thelasthourofthetaskwillrollintothenextday.

5.10.3ViewingtheCalendarWorkingHoursToviewthecalendarworkinghours:

•SelecttheCalendartaband•ClickonShowExceptionsOnlyandselectShowAllWorkTime:

Page 111: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

5.10.4CalculationofActivityDurationsinDays,WeeksorMonthsP6recordsdurationsinhoursandthedisplayofdurationsindays,weeks,ormonthsofactivitiesisamathematicalcalculationthatmaybemadebyoneoftwomethods:

•IndividuallyforeachCalendar–RECOMMENDEDMETHOD,or•GloballyforAllCalendars–NOTRECOMMENDED(thiswastheonlymethodusedbyP6

Version6.2andearlier).

IntheP6OptionalClienttheoptionfortheGlobalcalculationofthedurationsindays,weeks,andmonthsforallcalendarsissetbytheAdministratorthroughtheWebInterfacebyselectingAdminister, Application Settings, Time Periods and un-checking the Use assignedcalendartospecifythenumberofworkhoursforeachtimeperiodcheckbox:

Itisrecommendedthatthisneverleftunchecked.

IndividuallyforeachCalendar–RECOMMENDEDInthissituationtheUseassignedcalendartospecifythenumberofworkhoursforeachtimeperiodboxischeckedandeachcalendarhasitsownsetofparameterswhicharesetintheHoursperTimePeriodtabwhencreatingoreditingacalendar.Tosettheseparameters:•SelectAdminister,EnterpriseData,GlobalCalendar,ProjectCalendarorResource

Calendar,

Page 112: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Selectthecalendartobeedited,

•Clickonthe EditHoursperPeriodicontoopentheSetTimePeriodsform:

•Thisformallowsthedefinitionofthenumberofhoursperdayforeachcalendar,whichinturnwillenabletheactivitydurationsindaystobecalculatedanddisplayedcorrectlyaslongasthenumberofhoursperdayisthesameforeachworkdayinthecalendar.

Thisisnotanautomatedsystemandyouwillneedtocalculateeachcellmanuallybasedonhowyourcalendarisdefined.FortheHours/Dayparameterstoworkitisadvisablethateachworkingdayinacalendarhasthesamenumberofhoursperday.ThereforeinthesituationwhereaprojectisworkingadifferentnumberofhoursperdayitisrecommendedthatyouuseanaveragehoursperdayandsetboththeWorkHoursperDayintheEditDayformtotheoneaveragenumberofhoursperday.Forexample;ifyouhaveaprojectthatworks10hoursperdayforMondaythroughThursday,8hoursonFridayand6hoursonSaturdaytheneachworkingdayshouldbesetto9hoursperday.

GloballyforAllCalendars–NOTRECOMMENDEDWiththisoptionallcalendarsusethesameparametersandthesearesetbythedatabaseadministrator,intheTimePeriodsformwhichinturnsetsthecalculationforallcalendarsinthedatabasetothesamevalues.

ThisisNOTrecommendedunlessallcalendarsinadatabasehaveexactlythesamenumberofhoursperday,daysperweek,andweeksperyearwhichisveryunusual.

Whenallthecalendarsdonothaveexactlythesamenumberofhoursperday,daysperweek,etc.thenthedurationsindays,weeks,ormonthswillnotcalculatecorrectlyforcalendarsthatdonotcomplywiththesettingintheAdminister,ApplicationSettings,TimePeriodsform.ItisstronglyrecommendedthatthisoptionisNEVERUNCHECKED.

5.11CalendarsforCalculatingProject,WBSandOtherSummaryDurations

Page 113: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

InPrimaveraP6Version7andlaterthesummarydurationsofprojectsinboththeProjectsWindowandActivitiesWindowarecalculatedbasedontheDatabaseDefaultCalendarfromthefirstactivityStarttothelastactivityFinish.

ThesummarydurationofWBSbandsandotherbandscreatedbyGroupingactivitiesbyUserDefinedFieldsorActivityCodesarecalculatedby:

•WhenalltheactivitiesinabandsharethesamecalendarthenthesummarydurationiscalculatedonthecalendaroftheactivitiesinthebandandthecalendarnameisdisplayedintheCalendarcolumn,and

•WhenthecalendarsfortheactivitiesaredifferentthesummarydurationiscalculatedontheProjectDefaultcalendarandthecalendarfieldistheProjectDefaultcalendar,notblankasintheWindowsClient.

ThepicturebelowhastheProjectDefaultcalendarsetasthe10hr/d&5d/wandshowsthatwhenthecalendarsaredifferentthentheProjectDefaultcalendarisusedtocalculatethesummarydurationforWBSNodes,Projectsetc:

5.12TipsforMixedCalendarSchedulesWhenaprojecthasmixedcalendars,sayan8-hourand10-hourperday,thenachangeofcalendarfromapredecessoronan8-hourperdaycalendartoasuccessorona10-hourcalendar,thesuccessoractivitymayhaveonehourofworkonthesamedayasthepredecessorandnowspans2days.ThissituationleadstointerestingFloatcalculationsandconfusiontoschedulers.

ThepictureaboveistakenfromtheWindowsClientastheneckingandtimescaleoptionsoftheWebClientdonotallowthesameclarity.

PrimaveraP6doesnothavea“StartonaNewDay”functionfoundinotherproductssuchasAstaPowerproject,butwhichinitselfbringsonanewsetofcalculationissues.Techniques

Page 114: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

thatmaybeconsideredtoensureone-dayactivitiesspanonedayandtwo-dayactivitiesspantwodays,etc.are:

•Applyanappropriatelagtotherelationship,or

•WhentheStartandFinishTimesarenotanimportantschedulingconsiderationthenassignallthecalendarsthesameStartandFinishtimebutadjustthedurationofthelunchbreaksothedayshavethedesirednumberofhours.Forexample,a10-hourdaycalendarcouldstartat07:00andfinishat17:00withoutanylunchbreakandan8-hourcalendarcouldstartat07:00andfinishat17:00andbeassigneda2-hourlunchbreak.

Thepicturebelowshowshow8-houradayand12-houradaycalendarsinthesameprojectmaybesetuptoensureallactivitiesstartandfinishonthesameday:

Page 115: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

5.13Workshop3–MaintainingtheCalendars

BackgroundThenormalworkingweekatOzBuildPtyLtdisMondaythroughFriday,8hoursperdayexcludingpublicholidays.TheinstallationstaffworksMondaythroughSaturday,8hoursperdayandthecompanyobservesthefollowingholidays:

2012 2013 2014 2015

NewYear’sDay 2January* 1January 1January 1January

Easter 6–9April 29March–1April 18–21April 3–6April

ChristmasDay 25December 25December 25December 25December

BoxingDay 26December 26December 26December 28December*

*Theseholidaysoccuronaweekendandthedateshavebeenmovedtothenextweekday.

NOTE:BoxingDayisaholidaythedayafterChristmascelebratedinmanycountries.AssignmentAlthoughwecoulduseastandardcalendarwewillcreatetwonewcalendarsforthisproject.

1.EnsureyournewOzBuildBidprojectisopen.

2.PressF11ONLYifyouareinFullscreenmode,

Page 116: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.SelectAdminister,EnterpriseData,Projects,ProjectCalendarstoopentheProjectCalendarsform,

4.YoumaywishtocreateanewbrowsertabforthisoperationandpressF11forafullscreen.

5.Selectyourprojectbyclickingontheprojectname,

6.CreateanewProjectCalendarbyclickingonthe iconandcopyinganappropriatecalendar,suchasanexisting5dayperweek,8hoursperdaycalendarandnameitOzBuild5d/w.

7.EnsuretheBaseCalendarissettoBlankbyhighlightinganddeletingthecalendartext,8.EnsuretheStandardWorkWeekhoursarefrom08:00to16:00withoutalunchbreak

fromMondaytoFridayandclosetheform,

9.Clickonthe EditHoursperPeriodiconintheCalendartabtoopentheEditHoursperPeriodformandchecktheHoursperTimePeriodarethesameasinthediagrambelowandthenclosetheform:

10.Addtheholidaysabovein2013and2014only,

11.Checktherearenopre-existingholidaysinthecalendaryouthatneedtobemadeintoworkdays,

12.Yourcalendarshouldlooklikethepicturebelow:

Page 117: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.Clickonthe Saveicon,

14.CreateanewcalendartitledOzBuild6d/wforthe6-dayweekbycopyingtheOzBuild5d/wcalendar,

15.Ensuretheworkhoursarefrom8:00to16:00fromMondaytoSaturdayandclosetheform,

16.EnsuretheBaseCalendarissettoBlank,

17.Clickonthe EditHoursperPeriodicontoopentheSetTimePeriodsformandchecktheHoursperTimePeriodarethesameasinthediagrambelowandthenclosetheform:

Page 118: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

18.Addtheholidaysabovein2013and2014only,

19.Clickonthe Saveicon,

20.PresstheF11key.

Page 119: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

6CREATINGAPRIMAVERAPROJECTWBSThischapteroutlineshowtocreateaWBSstructuretoenableactivitiestobeassignedtoaWBSNodesoaschedulemaybecreated.

TheProjectWBSfunctionisdesignedtorecordahierarchicalWBSthathasbeendevelopedonatraditionalbasisasoutlinedinmanyprojectmanagementdocuments.Awell-structuredWBSshould:

•Includealltheprojectdeliverables,and

•Besetattheappropriatelevelforsummarizingprojectactivitiesandreportingprojectprogress.

TheProjectWBSfunctionisusedtogroupandsummarizeactivitiesunderahierarchicalstructureinthesamewayastheWBSfunctioninP3andSureTrak,WBSinAstaPowerprojectandtheCustomOutlineCodesinMicrosoftProject.ItisalsosimilartoOutlininginallversionsofMicrosoftProject;however,inPrimaveratheActivitiesareassignedtoahierarchicalWBSNodeandarenotdemotedunderaParenttaskaswithOutliningwithMicrosoftProject.TheWBSstructureisusedtoorganizeandsummarizeyourprojectactivities,includingcostsandresourcesduringtheplanning,scheduling,andupdatingofProjects.

Theprojectshouldbegranulated(brokendown)intomanageableareasbyusingaprojectbreakdownstructurebasedonattributesoftheprojectsuchasthePhasesorStages,SystemsandSubsystems,Processes,DisciplinesorTrades,Documents,DesignPackages,deliverablesandAreas,LevelsorLocationsofwork.TheseheadingsarenormallythebasisoftheprojectbreakdownstructureandareusedtocreatethePrimaveraWBSstructure,andtheWBSshouldpresenttheprimaryviewofyourproject.

Definingtheprojectbreakdownstructuremaybeamajortaskforprojectmanagers.

PrimaveraalsohasanActivityCodefunctionsimilartotheActivityCodefunctioninPrimaveraP3andSureTraksoftware,CodesinAstaPowerprojectandtheCustomFieldsinMicrosoftProject.ThisfeatureenablesthegroupingofactivitiesunderheadingsotherthanthePrimaveraWBSStructure.UnlikeinPrimaveraP3andSureTraksoftware,ActivityCodesarenottheprimarymethodoforganizingactivitiesinPrimavera.

IfyouareunabletodefineaWBSthenyouprobablydonothaveaproject.

Topic MenuCommand

CreatingandDeletingaWBSNode

IntheProject,ActivitiesWindow:•EnsureaViewisselecteddisplayingtheWBS,then

•Themenucommands AddChildWBSorAddSiblingWBSwhichisavailableontheRight-clickmenu.

•Clickonthe DeleteicontodeletaWBSNode.

IndentingandOutdentinga IntheActivitiesWindowusethebluetoolbararrows tomovethe

Page 120: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

WBSNode WBSNodesaround.

WBSCategories

TocreateWBSCategoriesselectAdminister,EnterpriseData,Projects,WBSCategoriestab.WBSCategoriesareassignedtoWBSNodesbyinsertingtheWBSCategoriescolumnintheGeneraltaboftheActivitiesWindow,Lowerpane.

AWBSNodeisatermusedbyPrimaverathatisoftencalledaWBSCodeandisasinglepointintheWBSstructurethatactivitiesareassignedto.APrimaveraWBSNodemayrecordmoreinformationthanP3,SureTrak,orMicrosoftProjectincludingthefollowingdata:

•AnticipatedDates,whichareusedtocreateabarintheActivitiesWindowwhentherearenoactivitiesundertheWBSNode,butdonotsummarizeintheProjectsWindow.

•Notes,whicharerecordedunderNotebooks,•FundingandBudgetLog,•WBSMilestones,whichmaybeusedforassigningprogressatWBSNodeLevel.These

arecreatedintheActivitiesWindow,•Documents(WP&DocsintheWindowsClient)thatprovidelinkstodocuments,and

•TherulesforcalculatingEarnedValueforeachWBSNode.

ThestartandfinishdatesofaWBSNodeareadoptedfromtheearlieststartdateandlatestfinishdateofthedetailedactivitiesunderthatWBSNodeandusetheWBSAnticipatedDatestocreateabarwhentherearenoactivitiesassignedtoaWBSNode.

ThedurationofaWBSNodeiscalculatedfromthestartandfinishdates,thedatabaseDefaultCalendarandtheUserOptions.

AWBSNodemaynothavecostsorresourcesassigneddirectlytothenode.AllcostsandquantitiesarecalculatedfromtheactivitiesassociatedwiththeWBSNode.

6.1ViewingandNavigatingtheWBSThereisnoWBSWindowasintheWindowsClientandtoview,edit,orcreateaWBSstructure:

•Theprojectmustbeopen,

•TheActivitiesWindowmustbedisplayedbyselectingProject,Activities,•Ensureyouhaveaviewwitha WBSiconbesideit,suchastheGanttChartbyWBS,

asthisensuresthatyoumayseeandaddaWBSNode.

Page 121: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ThefollowingpictureisoftheOzBuildProjectwith3WBSNodesandbeforeaddinganyactivities:

6.2CreatingandDeletingaWBSNodeTocreateanewWBSNode:

•SelectaWBSCodeortheProjectNameandeither:

Right-clicktodisplaythemenuandusethemenucommands AddChildWBSorAddSiblingWBS,or

Usethemenutoolbar AddChildWBSicon.

•Usethe iconsontheMovetoolbartoputtheWBSNodesattherightlevelortoreorderthem.

ThecommandsAdd,Delete,Copy,CutandPasteallworktocreate,delete,move,andcopyWBSNodes.

•AddwilladdanewWBSNodeunderthelevelcurrentlyhighlighted.

•DeletewilldeletetheWBSNode.WhenaWBSNodehasbeenassignedactivitiesyouwillbegiventheoptiontoeitherdeletetheactivitiesorreassigntheactivitiesbyselectingtheMergeElement(s)optionintheMergeorDeleteWBSElement(s)form.

Page 122: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•CopycopiesaWBSNodeandtheassociatedactivities,

•PastepastestheWBSNodeandtheassociatedactivities,includingallassociateddatasuchresourcesandrelationshipsamongsttheactivities,

•CutpreparestomoveaWBSNodeandtheassociatedactivitiestoanotherlocation.

6.3WBSNodeSeparatorTheDefaultWBSNodeSeparatorisassignedbyselectingAdminister,ApplicationSettings,Generaltab.

EachindividualprojectWBSNodeseparatormaybedefinedfromtheProjectsWindowby:•SelectingtheEPStab,•Selectingyourproject,

•Right-clickandselect SetProjectPreferences…,

Page 123: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SelecttheGeneraltaband•EntertherequiredseparatorintheWBSCodeSeparatorfield:

Analternativeseparatormaybeneededtomeetclientsorcontractrequirementsortoallowimportofdatafromanenterprisesystembymatchingthecodestructure.

6.4ActivityWindowWorkBreakdownStructureLowerPaneDetails

Page 124: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheActivityWindowlowerpanedisplaysdifferenttabswhenaWBSNodeisselectedtowhenanactivityisselected.

•Thetabsmaybehiddenordisplayedbyrightclickingonatabtoopenamenu:

•General–inthistabyoumayassignmanydataitemspertinenttotheWBSNodeincluding:

TheWBSCodehastobeuniqueforeachproject.WBSNameisthedescriptionfortheWBSNode.

TheResponsibleManagerenablesaccesstodatatobecontrolledattheWBSNodelevel.WhenaUserhasaccesstochangedatainoneWBSNodeonlytheyarestillabletoseethewholeprojectbutmayonlychangedataintheonenode.

AnticipatedDates,aswiththeProjectAnticipatedDates,willdisplayabarwhentheWBSNodehasnoactivitiesbutdoesnotsummarizeintheProjectsWindow.

TheProjectStatus–therearefourWBSStatustypes:Planned,Active,Inactive,andWhat-if.ThestatusofaWBSNodecontrolsviewingandaccesstotheNodesandActivitiesassignedtothenodesbyPrimaveraTimesheetusers.

Othercolumnsofdatamaybeaddedbyclickingonthe CustomizeColumnsicontoaddorremovecolumnsfromtheWBSGeneraltab.

•TheNotebooksfunctionisusedinthesamewayastheactivityNotebookandisusedtorecordnotesabouttheWBSNode.

•BudgetLogtabisusedaspartofthetop-downmethodofassigningbudgetsandareindependentofthecostsassignedattheactivitylevel.

•WBSMilestonestabiswhereWBSMilestonesarecreatedattheWBSNodelevelandprovideasummarymethodofassigningaPerformancePercentCompletetoactivitiesassignedtothatnode.Forthisfunctiontooperatetheremustbeatleastoneactivity

Page 125: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

assignedtoaWBSNode.•EarnedValuetabiswheretherulesforcalculatingtheEstimatetoComplete(ETC)and

otherEarnedValueparametersareset.

•DocumentstabenablestheassignmentofdocumentstoaWBSNodeandoperatesinthesamewayastheactivitiesDocumentstab.

•IssuestabiswhereIssuesmaybeassignedtoactivities.

6.5WBSCategoriesWBSNodesmaybeassignedcategories,whichenableWBSNodeswithinanEPStobegroupedandsortedindifferentways.WBSCategoriesaretoWBSNodesasActivityCodesaretoActivities.InearlierP6versionsthesewerereferredtoasProjectPhases.•CreateWBSCategoriesbyselectingAdminister,EnterpriseData,Projects,WBS

Categories:

•WBSCategoriesareassignedtoandremovedfromWBSNodesbyinsertingtheWBSCategoriescolumnintotheGeneraltab.

Page 126: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

OneuseofaWBSCategoryintheWindowsClientcouldbe,forexample,totagtheWBSNodeswiththephasessuchasDesign,ProcureandInstallandthentheActivitiesmaybegroupedbyWBSCategoryandthenWBSorsomeotherActivityCode.

IntheWebitisnotpossibletoGrouporFilteractivitieswiththeWBSCategory.

•ThistopiciscoveredinmoredetailsintheFORMATTINGTHEACTIVITYWINDOWANDVIEWSchapter.

WBSCategoriesmayalsobeusedintheTrackingWindowoftheWindowsClient.

6.6WhyaPrimaveraWBSisImportantPeopleconvertingfromP3andSureTrakwillbeusedtousingActivityCodesandActivityIDCodes.PrimaveradoesnothaveActivityIDcodes.

YoumaybetemptedtoignoretheWBSanduseActivityCodesinstead.ThisparagraphwillexplainthemainpurposesoftheWBSfunction:

•UserAccessmaybeassignedatthislevel,sotwoschedulersmayopenthesameprojectandonemayonlychangeactivitiesinWBSNodesthathavebeenassignedtothatuser.

•EarnedValuecalculationsandProjectPerformancemaybemeasuredatthislevel.•ProgressattheWBSlevelmaybemeasuredwiththeuseofWBSMilestones.•WBSActivitiesareveryusefulassummaryactivities.•AnticipatedDatesmaybeassignedattheWBSleveltoprovideabarwhennoactivities

havebeenaddedtoaWBSNode.

•TheWindowsClientTrackingWindowoperatesdowntoWBSNodelevel.

•ThereareanumberofstandardReportsthatfunctionatWBSNodelevel.

6.7Workshop4–CreatingtheWorkBreakdownStructure

Page 127: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

BackgroundAreviewofthescopeidentifiesthreedeliverables:

•TechnicalSpecification

•DeliveryPlan

•BidDocument

Assignment1.EnsureyourOzBuildprojectisopenandselecttheProjects,ActivitiesWindow,2.IfyoureceiveaP6pop-uptitledGettingStartedwithActivitiesitissuggestedthatyou

readthetextandthenselectDonotshowthisagain,3.Ensureyouhaveaviewwitha WBSiconbesideit,suchastheGanttChartbyWBS,

asthisensuresthatyoumayaddaWBSNode,

4.ClickintheProjecttitleandRight-clicktoopenamenuandaddthethreenewWBSNodes:

5.Yourviewmaybedifferenttothepictureabovedependingonhowyoursystemhasbeensetup,andyoumaynothavetheWBSNameprefixedwithWBS:,thereasonforthisisexplainedintheFORMATTINGTHEACTIVITYWINDOWANDVIEWSchapter.

6.Select Savetosaveyourproject.

Page 128: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

7ADDINGACTIVITIESANDORGANIZINGUNDERTHEWBSActivitiesshouldbewell-defined,measurablepiecesofworkwithameasurableoutcome.Activitydescriptionscontainingonlynounssuchas“BidDocument”haveconfusingmeanings.Doesthismeanread,write,review,submitorallofthese?Adequateactivitydescriptionsalwayshaveaverb-nounstructuretothem.Amoreappropriateactivitydescriptionwouldbe“WriteBidDocument”or“ReviewandSubmitBidDocument.”Thelimitforactivitynamesis120characters,buttrytokeepactivitydescriptionsmeaningfulyetshortandconcisesotheyareeasiertoprint.

WhenactivitiesarecreatedtheyarenormallyaddedunderaWBSNodebutmaybeorganizedunderothercodingstructuressuchasActivityCodesorUserDefinedFields.

Thischapterwillcoverthefollowingtopics:

Topic MenuCommandSettingNewActivityDefaults

SelectProjects,EPS,selectyourproject,SetProjectPreferences…,Defaultstab

AddingNewActivities SelectalineinthescheduleandstriketheIns(InsertKey)orright-clickandselecttheAddmenuitem.

ActivityDetailsform Maybedisplayedinthebottompanebyclickingonatab.

CopyingactivitiesinPrimavera Selecttheactivitiesandcopyandpastetotherequiredlocation.

Assigning%CompleteTypetoActivities

Usethe%CompleteTypedropdownboxintheGeneraltaboftheActivitywindowbottompane.

AssigningActivityTypetoActivities

UsetheActivityTypedropdownboxintheGeneraltaboftheActivitywindowbottompane.

AssigningDurationTypetoActivities

UsetheDurationTypedropdownboxintheGeneraltaboftheActivitywindowbottompane.

AssigningWBSNodestoactivities

CreateanactivityinanexistingWBSband,

DisplaytheWBScolumnandclicktheWBScelltodisplaytheSelectWBSform,or

CutandPasteinadifferentWBSNode.

7.1NewActivityDefaultsAftercreatinganewprojectandbeforeaddingactivitiesitisimportanttosetthedefaultssuchastheActivityIDNumbersandCalendars.Bysettingthemcorrectlybeforeaddingactivitiesyouwillsaveasignificantamountoftimebecauseyouwillnothavetochangeanumberofattributesagainstallactivitiesatalaterdate.ThesedefaultsaresetintheProjectPreferencesformbyselectingProjects,EPS,selectyourproject,SetProjectPreferences…,Defaultstab:

Page 129: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

7.1.1DurationTypeNoneoftheDurationTypeoptionsaffectshowtheschedulecalculatesuntiloneormoreresourcesisassignedtoanActivity.Thefollowingoptionsareavailable:

•FixedUnits•FixedDuration&Units/Time•FixedUnits/Time•FixedDuration&UnitsIfyoudonotplantoaddresourcestoActivities,thenyoudonotneedtoassignaDurationTypeanditmaybeleftasthedefault.ThistopicwillbecoveredindetailintheASSIGNINGROLES,RESOURCESANDEXPENSESchapter.

7.1.2PercentCompleteTypeThePercentCompletetypeshouldbeunderstoodifitisintendedtobeusedtoupdate(statusorprogress)theschedule.ThisoptionmaybesetforeachactivityindividuallyinPrimaveraandthedefaultfornewactivitiesissetinthePercentCompleteTypedropdownbox.PrimaverahasmanyActivityPercentCompletefieldsthatmaybedisplayedincolumnsandwewilldiscussfourofthemnow:

Page 130: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Activity%Complete,whichmaybelinkedtooneonlyofthethreefollowing%Completefieldsandisalwayslinkedtothe%CompletedisplayedontheGanttChartbars:

•Physical%Complete,whichisindependentofactivityresourcesanddurations,•Duration%Complete,whichislinkedtoactivityOriginalandRemainingDurations,and•Units%Complete,whichislinkedtoresourceunits.Therearethreepercentcompleteoptions;eachnewactivityisassignedtheprojectdefaultPercentCompleteTypeandthenthismaybeeditedforeachactivityasrequired.Therefore,forexample,whentheoptionofPhysical%CompleteisselectedforanactivitythentheActivity%CompleteandthePhysical%CompletearelinkedandachangetoonewillchangetheotherandthisvaluewouldbedisplayedontheGanttChart.

DefaultPercentCompleteTypeTheDefaultPercentCompleteTypeforeachnewactivityineachprojectisassignedintheDefaultstaboftheDefaultstaboftheProjects,EPS,SetProjectPreferencesform:

•AnewactivityPercentCompleteTypeissettotheDefaultPercentCompletewhencreatedandmaybechangedatanytime.

PercentCompleteTypes•Physical%Complete–Thisfieldenablestheusertoenterthepercentcompleteofan

activityandthisvalueisindependentoftheactivitydurations.ThisissimilartothewayP3andSureTrakcalculatesthe%CompletewhentheLinkRemainingDurationandPercentCompleteoptionisNOTselected.

•Duration%Complete–ThisfieldiscalculatedfromtheproportionofthePlannedDurationandtheRemainingDurationandtheyarelinked.Achangetoonevaluewillchangetheother.WhentheRemainingDurationissettogreaterthanthePlannedDurationthispercentcompleteisalwayszero.ThisissimilartothewayP3andSureTrakcalculatethe%CompletewhentheLinkRemainingDurationandPercentCompleteoptionisselected

•Units%Complete–Thisiswherethepercentcompleteiscalculatedfromtheresources’ActualandRemainingUnits.AchangetoonevaluewillchangetheotherandwhenmorethanoneresourceisassignedthenalltheActualUnitsforallresourceswillbechangedproportionally.ThiswillbecoveredfurtherintheUPDATINGARESOURCEDSCHEDULE

Page 131: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

chapter.ThisissimilartotheMicrosoftProject%WorkComplete.

TheUnits%CompleteiscalculatedfromthevalueofalltheLaborandNon-Labor,sobecarefulwhenmorethanontypeofresourceisassignedtoanactivity.Forexamplethesoftwarecouldbeaddinglaborhourswithexcavatorhours.

Activity%CompleteTheActivityPercentCompleteTypefieldislinkedtothe%CompleteTypefieldassignedtoanactivityintheActivitiesWindow,Generaltab,Detailsformorthe%CompleteTypecolumn:

•The%CompletedisplayedontheBarintheWebClientistheDuration%Complete:

•IntheWindowsClienttheActivity%Completeisalsolinkedtothe%CompleteBarandthisvalueisrepresentedonthe%Completebar:

ChangingtheActivityPercentCompleteTypeTheActivityPercentCompleteTypemaybechangedintheProjects,ActivitiesWindow:•Inacolumnor

•IntheGeneraltabofthelowerpane:

Page 132: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

7.1.3ActivityTypesandMilestonesAnActivitymaybeassignedoneofthefollowingdefaultActivityTypesusingthedropdownboxintheGeneraltab:

•FinishMilestone

•LevelofEffort

•ResourceDependent

•StartMilestone

Page 133: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TaskDependent

•WBSSummary

ActivityType Description

TaskDependent

TheseActivityTypeshaveadurationandwillonlycalculatethedurationusingtheassignedcalendarevenwhenoneormoreresourcesareassignedtoanactivity.

ResourceDependent

TheseActivityTypeshaveadurationandwillcalculatethedurationonlyusingthecalendarassignedtotheactivitywhenNOresourcesareassignedtotheactivity.

TheseactivitiesacknowledgeResourceCalendarswhenresourcesareassigned.

ThisissimilartoanIndependentActivityTypeinP3andSureTrak.

TheyacknowledgetheActivitycalendartocalculatetheEarlyStartdate.

LevelofEffort–LOE

ThisActivitytypeissimilartoP3andSureTrakHammockactivities.Itspansfromthestartorfinishofoneormorepredecessoractivitiestothestartorfinishofoneormoresuccessoractivitieswhicharelinkedbyrelationships.

NOTE:DonotschedulewithaLOEactivityunlessithasrelationships.IfyoudoscheduleitwillcalculatetoazerodurationandbemarkedasCompleteontheDataDate.YouwillthenhavetomarkitasnotstartedintheActivitiesWindow,GeneraltabandassignadurationsoyoucanseeitontheGanttChart.

StartMilestone

AStartMilestonehasastartdateandnofinishdateintheWindowsClientbutshowsbothaStartandFinishintheWeb.ItisscheduledatthestartofatimeperiodandmaynotbeassignedResources.

FinishMilestone

AFinishMilestonehasafinishdate,nostartdateintheWindowsClientbutshowsbothaStartandFinishintheWeb.ItisscheduledattheendofatimeperiodandmaynotbeassignedResources.

ChangingamilestonefromStarttoFinishwouldnotaffectaschedulewhenalltheactivitiesareononecalendarbutwouldmovethemilestonefromthestartofadaytothefinishofthepreviousday.

WBSSummary

ThisActivitytypecalculatesinthesamewayasP3andSureTrakWBSactivitiesandtheyspanallactivitieswiththesameWBScode,butwithoutrelationshipsthatareusedwithLOEs.

AMilestonehaszerodurationandisusedtomarkthestartorfinishofamajorevent.PrimaveradifferentiatesbetweenStartandFinishMilestonesinthesame

Page 134: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

wayasP3andSureTrak,whereaStartMilestonehasastartdateandnofinishdateandaFinishMilestonehasafinishdateandnostartdate.ThisisunlikeMicrosoftProject,whichonlyhasonetypeofMilestone.LaterversionsofMicrosoftProjectallowmilestoneswithdurations.

TheWindowsandtheWebClientdisplayMilestonedatesdifferentlysobotharedisplayedbelow.

•IntheClienttheStartMilestonedoesnotshowFinishDatesandtheFinishMilestonedoesnotshowStartDatesasP3andSureTrak:

•IntheWebtheStartMilestonesandFinishMilestonesbothshowStartDatesandFinishDatesasmostotherschedulingsoftwarelikeMicrosoftProjectandAstaPowerproject:

7.1.4CostAccount

Page 135: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThisselectsthedefaultCostAccountforallnewResourcesandExpensesandisblankbydefault.

7.1.5CalendarThistopicwascoveredindetailintheDEFININGCALENDARSchapter.Thisdropdownboxisusedtoselectthedefaultcalendarforanactivity.ADefaultProjectCalendarisassignedtoeachprojectfromtheGlobalorProjectcalendarlist.AllnewactivitiesareassignedtheprojectDefaultProjectCalendarwhentheyarecreated;however,individualcalendarsmaybeassignedforeachactivityaftertheyhavebeencreated.

7.1.6Price/UnitLikeMicrosoftProjectanactivitymaybeassignedaUnit(hoursorwork)withoutaresourcebeingassigned.ThisvalueisusedtocalculateacostwhenaUnithasbeenassignedtoanactivitywithoutaresourceassignment.

7.1.7Auto-numberingDefaultsTheAuto-numberingDefaultsdecideshownewactivitiesarenumbered.Thefirstactivityaddedtoanewprojectwillbebasedonthedefaultssetinthisform.

ThereisnofunctionofIncrementActivityIDbasedonselectedactivityasfoundintheWindowsClient.

TherearenoActivityIDCodesallowinglogictobeautomaticallyembeddedintotheActivityIDs,whichareapowerfulfeaturesofbothP3andSureTrak.

7.2AddingNewActivitiesItisoftenquickertocreateascheduleinaspreadsheetandimportthedataintotheschedulingsoftware.PrimaveraoffersaspreadsheetimportfunctionfoundunderCreateImportTemplate,ExporttoExcelandImportfromExcelcommandswhichareveryuserfriendly.

SomedataassociatedwithanimportedactivitymustexistbeforetheactivityisimportedfromExcelotherwiseitwillnotbeimported.ThisincludesitemssuchasRoles,Resources,andActivityCodes.ThesedataitemsmaybeimportedusingthePrimaveraSDK(whichisloadedfromtheinstallationCDandinstructionsareavailableontheAdministrationGuide)andanExcelspreadsheetavailablefromtheOraclesPrimaveraKnowledgebase.

Toaddanactivitytoaproject:

•OpentheActivitiesWindow,

•SelecttheappropriateWBSNodeandtheneither:

PresstheInsertkeyonthekeyboard,or

Page 136: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Clickonthe AddiconontheActionstoolbar.

7.3DefaultActivityDurationThedefaultactivitydurationfornewlycreatedactivitiesisspecifiedintheAdminister,ApplicationGeneraltabActivityDurationcell.

7.4CopyingActivitiesfromotherProgramsActivitydatamaybecopiedfromorupdatedfromotherprograms(suchasExcel)byusingtheExcelImportandExportfunction.

7.5CopyingActivitiesinP6ActivitiesmaybecopiedfromanotherprojectwhenbothprojectsareopenatthesametimeorcopiedfromwithinthesameprojectusingthenormalWindowscommandsCopyandPaste,byusingthemenucommandsRightclick,CopyandRightclick,Paste,orbyusingCtrl+CandCtrl+V.Oneormoreactivitiesmaybeselectedtobecopiedby:

•Ctrl-clicking,or•Holdingtheshiftkeyandclickingonthefirstandlastactivityinarange,or•Draggingarangewiththemouse.Withthisoperationbesuretoselectthewholeactivityor

activities,notjustacell.

ThereisnoCopyActivityOptionsformorRenumberActivityIDbasedonselectedactivitiesformasintheWindowsClientandalldataincludingrelationshipsarecopied.

P6R8.3hasintroducedafeaturethatallowsuserstochoosethedatatobeincludedorexcludedwhencopyingandpastingactivitiesintheActivitiesWindows.Thisfunctionappliestoindividualormultipleactivitieswithinaprojectoracrossmultipleprojects.

Toaccessthisfeature:

•GototheActivitieswindowandcopy/pasteoneormoreactivitiesusingthecommandsCtrl+CandCtrl+Vorbyusingthe Copyand Pastebuttonslocatedinthetoolbar;

•TheCopyActivityOptionsformwillopenupwhenyoupastetheactivities;•Check/Unchecktheboxesfordatathatyouwant/don’twanttoinclude;

•ClickOktoconfirmandclosetheform.

Page 137: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

CopyActivityOptions

P6 R8.3 has introduced a feature that allows users to choose the data to be included orexcludedwhencopyingandpastingactivitiesintheActivitiesWindows.Thisfunctionappliestoindividualormultipleactivitieswithinaprojectoracrossmultipleprojects.

Toaccessthisfeature:

•GototheActivitieswindowandcopy/pasteoneormoreactivitiesusingthecommandsCtrl+CandCtrl+Vorbyusingthe Copyand Pastebuttonslocatedinthetoolbar;

•TheCopyActivityOptionsformwillopenupwhenyoupastetheactivities;•Check/Unchecktheboxesfordatathatyouwant/don’twanttoinclude;

•ClickOktoconfirmandclosetheform.

Page 138: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

7.6ElapsedDurationsAnactivitymayNOTbeassignedanElapseddurationasinMicrosoftProject.Theactivityshouldbescheduledona24-hourperdayand7-dayperweekcalendar.

7.7FindingtheBarsintheGanttChartAttimesyouwillfindtherearenobarsdisplayedintheGanttChartbecausetheTimescalehasscrolledtoofarintothepastorfuture.Double-clickintheGanttChartinlinewithanactivityandtheTimescalewillscrolltodisplaytheactivitybar.

7.8ActivityWindow–BottomPaneTheBottompanehasanumberoftabswhereinformationaboutthehighlightedactivitymaybeviewedandedited.(Thesearenotinanyspecificorderasthetabsmaybereorderedonthescreen.)

Thisformdisplaysthefollowingareasandfunctions:

•DetailsshowingtheActivityID,ActivityDescription,ActivityTypeandLocation.

•DurationsshowingtheactivitydurationsandDurationType.

Page 139: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

General

•StatuswhereActualDates,Activity%CompleteandPercentCompleteTypemaybeupdated.

•ConstraintswherethePrimaryandSecondaryConstraintsmaybeupdatedbutnottheExpectedFinish.

•UnitsandCostsbyselectingfromthedropdownboxtheLaborandNonlaborUnitsorCostsandMaterialCostsmaybedisplayedandupdated.Thisfunctionproportionallyupdatestheresourceswhenassigned.

NOTE:ItispossibletoassignresourceUnitsintheGeneraltabwithoutaresourcebeingassignedtotheactivityandtheratewillbetakenfromtheProjectPropertiesCalculationstab.

Assignments(ResourcesintheWindowsClient)

•ResourcesandRolesmaybeassignedtoselectedactivitiesusingthemenuicons ofAssignResource,AssignRole,RequestResourceandDelete.

•ResourcesandRolesdataassignmentinformationmaybedisplayedbyeditingthecolumns.

Expenses

Expensesmaybeaddedandeditedhere.Theseareintendedforone-offcoststhatdonotrequirearesourcetobecreated.

NOTE:TheseareoftenusedformaterialcostsonconstructionandmaintenanceprojectstopreventclogginguptheResourceWindow.

Notebooks(NotebookintheWindowsClient)

NotesaboutactivitiesmaybemadeherebyaddingaNotebookTopicandthenaddingnotesaboutthetopic.

StepsThisfunctionenablesanactivitytobebrokendownintoincrementstitledStepsthatmaybemarkedascompleteasworkontheActivityprogresses.

Feedback Thisiswherecommentsmadeinthetimesheetmodulemaybeviewed.

Documents(WPs&DocsintheWindowsClient)

ThisiswherefilesthathavebeenlistedintheWorkProductsandDocumentsWindowmaybeassociatedwithactivitiesandthenopenedfromthisform.

CodesThisiswhereActivityCodesmaybeassignedtoactivities.

ThesecodesaresimilartoP3andSureTrakActivityCodesandactivitiesmaybeorganizedunderthesecodes.

Predecessors&Successors(RelationshipsasinWindowsClient)

Thisiswheretheactivity’spredecessorsandsuccessorsareadded,edited,anddeleted.

ThisiscoveredintheADDINGRELATIONSHIPSchapter.

Page 140: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Issues Thisiswhereissuesmaybeaddedorremoved.

Risks Thisiswhererisksmaybeaddedorremoved.

TraceLogic ThisiswheretheTraceLogicfunctionmaybeoperatedandallowstherelationshipstobeviewedinaNetworkDiagramFormat.

Discussion Thisiswhereteammemberscanstartaconversationtoupdateothermembersregardingtheproject,

ThereisnoSummaryformasintheWindowsClienttool.

7.9DiscussionFeatureAnewtabhasbeenaddedtotheActivitiesWindowinP6Version8.3,titledDiscussionwhichenables:

•Userstocreateadiscussionthreadforeachactivity,

•EachentryissavedwiththedateofentryandusernameandtheentirethreadisrecordedallowingandinteractivediscussionbetweenuserswhohaveaccesstoP6,

AnewfieldtitledUnreadCommentshasbeencreatedsousersmayidentifyactivitieswithnewcommentsthattheyhavenotread.ThismaybeaccessedthroughTeamMemberWeb,theTeamMemberforiPhoneapp,andP6.

Toaccessthisfeature:

•SelectanactivityandclicktheDiscussiontablocatedinthedetailwindowontheActivitiespage,

•Addacommentontherightpaneandthenpressthe Postbutton.

ThisfunctionhaslimiteduseintheenvironmentwhereonlytheprojectschedulerhasaccesstoP6.

Page 141: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

7.10AssigningCalendarstoActivitiesActivitiesoftenrequireadifferentcalendarfromthedefaultProjectCalendarthatisassignedintheProjectInformationform.Primaveraenableseachactivitytobeassignedauniquecalendar.AnActivityCalendarmaybeassignedbydisplayingtheCalendarcolumn.TheRightclick,FillDownmaybeusedtoassignanewcalendartomultipleselectedactivities.

Page 142: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Toviewthecalendarassignedtoanactivity,rightclickonanactivitydatacolumnandselectViewCalendar.

7.11AssigningActivitiestoaWBSNodeActivitiesareassignedtoaWBSNodefromtheActivitiesWindow.Theymaybeassignedusingthefollowingmethods:

•AnewactivitywillinherittheWBSNodeofaselectedexistingactivitywhentheprojectisorganizedbyWBSNodesandanactivityiscreated,

•CuttingandPastingactivitiesfromoneWBStoanother,

•ChangetheactivityWBSby:

InsertingtheWBScolumnbyclickingonthe ColumnsiconandselectingWBSfromtheColumnsformunderGeneral,then

ClickingintheWBScolumnofanactivitywillopentheSelectWBSform:

•The ExpandAllandCollapseAlliconsareusedtoexpandorrolluptheWBSstructure.

7.12ReorderingorSortingActivitiesThesortorderofactivitieswithinabandissetbyanorderfromoneormorecolumnsandyoumaynotdragactivitiesupordownthescheduleinthesamewayasotherproducts.

Therearetwoprincipalmethodsoforderingactivitiesaftertheyhavebeenadded:

•UsingtheSortfunctionintheCustomizeActivityViewform:SelectCustomizeViewoption

Page 143: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ClickontheColumnstabandusetheColumnOptionfunction.

ItisunfortunatethatwithPrimavera,assoonasyouusetheoptionbelowtosortactivitiesthenwithoutanywarningthesortingfieldsenteredintotheSortformaboveareoverwrittenbythecolumnthathasbeenusedtosorttheactivities.

•Highlightingacolumntitleandclickingwiththemouse.Theactivitieswithinabandwillbereorderedwithinthatbandintheorderindicatedwithanarrowintherightsideofthecolumnheader.TheorderwillbeeitherAscendingorDescending:

ThisfunctionchangesallthesettingsmadeintheSortformonapermanentbasis.

TheActivitiesIDsarenotrenumberedwhentheyhavebeenreorderedastheyarewithMicrosoftProject.

SortingonMultipleColumnsInP6R8.3itispossibletosortonmultiplecolumnseitherontheEPS,Activities,andResourcesAssignmentswindows.However,itisstillpossibletosortonanindividualcolumnbyjustclickingonthecolumnheadertothedesiredsortingorder.

Page 144: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheCustomizeColumnsformhastwotabs:

•Columns:AllowsyoutoSelectcolumnstodisplayinthecurrentview;•Sorting:AllowsyoutoSpecifycolumnstosortby,sortingorder(ascendingor

descending),andcolumnsortingpriority

Tousethisfunctionality:

•FromtheViewmenu,selectColumnsor;•Clickthe ColumnsiconlocatedinthetoolbartoopentheCustomizeColumnsform;•ClicktheSortingtabintheCustomizeColumnsform;•Selectthecriteriayouwantthecolumnstobesortedby;

•Addadditionalcriteriabyclicking addbuttonormoveupanddownusingthearrows.ThenclickApplyandOk.

Sortingchoicescanbesavedaspartoftheview.

7.13Undo

Page 145: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThereisnoundoasintheProfessionalorOptionalClient.

Youmayonlyclickinthe Cancle(Ecs)icontocancelyoursave.

7.14SummarizingActivitiesUsingWBSTheWBSbandsmaybesummarizedinthesamewayasinotherprojectplanningandschedulingsoftware.

ThefollowingpictureshowstheactivitiesdisplayedundertheWBSNodes:

•ThefollowingpictureshowstheactivitiessummarizedundertheWBSNodes:

WBSNodesmaybesummarizedorexpandedby:

•Double-clickinganyWBSbanddescription.Thebandwilleitherrollupwhenexpandedorexpandwhenrolledup,or

•Clickingonthe ExpandAllandCollapseAlliconsthatwilleitherdisplayallactivitiesorrolluptheprojecttoonebar,whichisusuallynotveryuseful.

WBSNodesmaybereorderedbyclickingthe MoveiconsontheMovetoolbar

7.15SpellCheckThereisnospellcheckasintheWindowsClient,youcouldexporttoExcelandspellcheckthere.

7.16Workshop5–AddingActivities

Background

Page 146: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Weneedtosetupthedefaultsandaddtheactivitiestotheschedule.

Assignment1.SelectProject,EPS,Right-clickonyourproject,2.SelectSetprojectpreferences…,

3.SelecttheDefaultstabandsetyourdefaultsasperthepicturebelow:

4.Click .

5.SelectProjects,ActivitiestoopentheActivitiesWindow,andaddthefollowingactivitiesundertheappropriateWBS.

6.TheStartandFinishMilestonesmaybeassignedfromtheGeneraltabinthelowerwindow.

7.YoumayneedtoselectadifferentviewtoseetheActivityID,asexplainedinthepreviousworkshop.

8.ClickontheActivityIDcolumnheaderiftheactivitiesbecomeoutoforder.

ActivityID ActivityName PlannedDuration ActivityType

Page 147: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TechnicalSpecification

OZ1000 ApprovaltoBid 0d StartMilestone

OZ1010 DetermineInstallationRequirements 4d TaskDependent

OZ1020 CreateTechnicalSpecification 5d TaskDependent

OZ1030 IdentifySupplierComponents 2d TaskDependent

OZ1040 ValidateTechnicalSpecification 2d TaskDependent

DeliveryPlan

OZ1050 DocumentDeliveryMethodology 4d TaskDependent

OZ1060 ObtainQuotesfromSuppliers 8d TaskDependent

OZ1070 CalculatetheBidEstimate 3d TaskDependent

OZ1080 CreatetheProjectSchedule 3d TaskDependent

OZ1090 ReviewtheDeliveryPlan 1d TaskDependent

BidDocument

OZ1100 CreateDraftofBidDocument 6d TaskDependent

OZ1110 ReviewBidDocument 4d TaskDependent

OZ1120 FinaliseandSubmitBidDocument 2d TaskDependent

OZ1130 BidDocumentSubmitted 0d FinishMilestone

9.RescheduletheprojectbypressingF9andcheckthattheDataDateissetat2December2013at08:00anduncheckDisplayscheduleloguponcompletion.

10.SavetheschedulebyclickingontheScheduleicon.

11.Youranswershouldlooklikethefollowingpicture.

12.Youmayhavedifferentcolumnsdisplayedandtheremaybedifferenttextonthebars,butthelongestbarwillberedwhichisthecriticalpath.

13.EnsurethesortorderisbyActivityIDbyclickingontheActivityIDHeading:

Page 148: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 149: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8FORMATTINGTHEACTIVITYWINDOWANDVIEWS

8.1FormattingtheProjectsActivityWindowThereareanumberoftoolbariconsthatmaybeusedtoformatthescreenandoperatethesoftware.

SomeoftheiconsusedtooperatethesoftwareandformatthetoppaneoftheActivitiesViewarelistedbelow:Icon/s Name Purpose

Save Commitsanychangetodatatothedatabase.

Cancel Reversesanyunsavedchangesnotcommittedtothedatabase.Thiscouldbeconsideredatypeofundo.

Delete Deletesselecteditem.

Schedule Recalculatestheschedule.

Find Findsdataincolumns.Columns OpenstheCustomizeColumnsformtoformatcolumns.

Grouping OpenstheCustomizeGroupingformtoGroupactivitiesunderbands.

Filters Optionstocreate,applyandeditfilters.CustomizeGanttChartOptions

OpenstheCustomizeGanttChartOptionsformwithoptionstoformatbarsandtheGanttChart.

ProgressSpotlight

UsedtomovetheProgressSpotlightlineforwardAndbackwardsonetimescaleperiod.

Show/HideRelationshiplines Thistogglesbetweenshowingandhidingtherelationshiplines.

Show/HideProgresslines Usedtoshoworhidetheprogresslines.

ExpandAllandCollapseAll

UsedtoexpandallWBSNodesandshowallactivitiesandtocollapseallWBSNodesandshowonlyaprojectsummarybar.

ZoomtoFit Zoomsthetimescaletofittheavailablescreenforthetimescale.FullScreenModeandNormalMode

SwitchingtoFullScreenModeandhidesalltheinternetexplorertoolbarsetc.allowingmoreworkingspaceonthescreen.

GanttChart DisplaystheactivityTableandGantChartbars.Table DisplaystheactivityTableONLY.ActivityNetwork DisplaystheActivityNetworkview.

Calendar DisplaystheCalendarview.View Create,editanddeleteViews.

Page 150: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ApplyaView ApplyandexistingViewbuttonsarefoundontheViewMenu.

8.2Views

8.2.1UnderstandingViewsAViewisafunctioninwhichtheformattingofparameterssuchastheColumns,Groupingactivities,FiltersandBarsissavedandreappliedlater.ThisfunctionissimilartoLayoutsinP3,P6WindowsClientandSureTrakorViewsinAstaPowerprojectandMicrosoftProject.•AViewisassignedanameandmaybeedited,savedorreappliedatalaterdate.•ViewshavetheFilterfunctionincorporatedintothefunctionwhichisdifferenttomostother

products.

•AViewmaybecreatedandsavedbyoneuserandmaybemadeavailabletoanumberofotherusers.

ViewsandFilterscreatedintheWindowsClientarenotaccessibleintheWebandmaynotbeimportedintotheWeb.

8.2.2OpeningaViewToopenaview:

•Clickonthe ApplyaViewiconontheProject,ActivityWindow,Viewtoolbar,whichisusuallybydefaultontherighthandside,andthiswillrevealalistofavailableviews,

•Selecttheviewfromthelist,

•Ifyouhavemadeeditstothecurrentviewyouwillbeaskedifyouwishtosavethechangeswhenmovingtoanotherpartofthesoftware.

Viewswitha towblueoverlappingsquaresareorganizedbyWBSandallowadding,deletingandeditingtheWBSstructure.

8.2.3CreateaView

Page 151: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TocreateanewViewyouwillneedtocopyandexistingViewandeditit:

•EnsureyouhaveaprojectopenandareintheProjectsWindowActivitiestab,•Applyanappropriateviewtocopyusingthe ApplyaViewicon,•Clickonthe Viewicontoopenamenu,

•SaveView savesanychangestoaView.NOTE:WhenaViewisnotsavedthenthenexttimeitisappliedalleditsmadetotheViewarenotsaved.

•SaveViewAs iconisusedtosaveandrenameaViewthatmaythenbeedited.

•DeleteView iconpermanentlydeletesthecurrentView.

•E-mailView allowsaviewtobeemailedtoanotherpersonifyourserverhasbeenconfigured,

•Selectthe CustomizeicontoopentheCustomizeActivityViewform,

•ThereforetocreateanewView:

Select SaveViewAsistosaveyournewView,then

Selectthe CustomizeicontoopentheCustomizeActivityViewformtoedityourView:

•TheCustomizeformmayberesizedbydraggingtheedges.•Donotforgettosaveanychangesafteryouhaveappliedanychanges.

Page 152: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.3ColumnsandActivitySortOrderThecolumnstaballowstheselectionandhorizontalorderingofthecolumnsandsortingoftheactivitieswithinbands.

Thecolumnsmaybeeditedusingeither:

•TheColumnsformbyclickingonthe icon,or

•CustomizeViewform.Bothformsoperateinthesameway.

TheActivityNameisusuallydisplayedinthefarleftcolumnandtheActivityIDasthesecondcolumnotherwisethenamesinthebandssuchastheProjectName,WBSnamearetruncatedsotheyareunreadable,asperthepicturebelow:

Page 153: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.3.1SelectingtheColumnstobeDisplayedTheavailablecolumnsaredisplayedintherightwindowandmaybelistedunderCategoriesandeachcategorymaybeopenedbyclickingonthe icons.

ThecolumnstobedisplayedarelistedintherightSelectedColumnswindowandarecopiedfromtheAvailableColumnstoandfromSelectedColumnsusingthe icons.

Version8.4nowallowsyoutoselectthepositionofthenewcolumnbeforeaddingthecolumn.

8.3.2SettingtheOrderoftheColumnsfromLefttoRightontheScreenTheorderofthecolumnsonthescreen,fromlefttoright,isthesameastheorderintheCustomizeActivityViewformSelectedColumnswindowfromtoptobottom.Theorderofthecolumnsmaybealtered:

•HighlightthecolumnintheColumnsformSelectedOptionswindowandusethe andicons,or

•ClosetheformandLeft-clickonthecolumntitleintheProjects,ActivitiesWindowanddragthecolumn.

Page 154: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.3.3AdjustingtheWidthofColumnsYoumayadjustthewidthofthecolumnbydraggingthecolumntitleseparatorintheProjects,ActivitiesWindow:•Movethemousepointertotherighthandsideoftheheadertitleand

•A iconwillthenappearandenablethecolumntobeadjustedbyLeft-clickinganddragging.

8.3.4FirstColumnDataDisplayThefirstcolumnmaydisplaytheActivityIDorActivityNameandthisoptionissetin:

•TheCustomizeViewformColumnstaborthe•Columnsform.

WhentheShowfirstcolumnasissettoActivityIDthentheWBSDescriptionmaybetruncated.

YoumayfinditbettertodisplaytheActivityNameastheShowfirstcolumnasandActivityIDasthefirstSelectedColumn:

8.3.5RenamingColumnsP6R8.3allowsuserstorenamecolumnsontheActivitiespage..

Torenameacolumn:

Page 155: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•IntheActivitiespage,Right-clickonacolumnheaderandselectRenameColumntoopentheRenameColumnform;

•Torenamethecolumn’sDefaultName,typethenewnameintheboxprovidednexttoNewName;

•ClickOktoconfirmchanges.

8.3.6ActivitySortOrder

Theactivitysortorderissetby:

•UsingtheSortbyandSortOrderoptionsintheColumnsform,or

•Clickinginthecolumntitle.ThesortorderisindicatedbyanarrowinthecolumntitleheaderandusersoftheP6WindowsClientwillnoticethatthesearrowsareinthereversedirectionoftheP6WindowsClient.

ClickinginthecolumnheaderwilldestroyanysortordersetupintheColumnstab.SoifyouhaveaveryspecificsortorderdefinedinaViewthenyoushouldsavetheviewassoonaspossibleincaseyouclickintheheaderinerror.

8.4GroupingTheGroupingactivitiesunderthebandsmaybeeditedusingeither:

•TheGroupingformbyclickingonthe Groupingicon,or

Page 156: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•CustomizeViewform.

Bothformsoperateinthesameway.

GroupingenablesactivitiesintheProject,ActivityWindowtobesortedandorganizedunderotherparameterssuchasWBS,TotalFloatand.ThisfunctionissimilartoGroupandSortintheWindowsClient,OrganizeinP3andSureTrakandGroupinginMicrosoftProjectandAstaPowerproject.

TheGroupingformhasseveraloptions:Field,LevelandToLevelWhenahierarchicalcodesuchasaWBSandtheToLevelofAllisselected,thenthesubsequentbandsforLevel2,Level3etc.arecompletedbythesoftwareandtherearenootherbandingoptionsavailableandtheWBSisdisplayedhierarchically:

WhenahierarchicalcodesuchasaWBSisselectedandtheToLevelisassignedavaluethenallthesubsequentbandsareNOTcompletedbythesoftwareandotherbandsmaybe

Page 157: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

selected:

Band,ColorandTextColor•Theseoptionsareusedtoformatthetextofthebands:

SortOrderEachbandmaybesortedusingtheSortOrder,whichoperateson:•TheID/CodewhenHierarchyisselectedand

•Name/DescriptionwhenAscendingorDescendingisselected.

HierarchyshouldnormallybeselectedbuttheName/DescriptionallowsanothersortorderfortheWBS.

BandOptionsTheseoptioncontrolthedisplayofBandtitles,summaryinformationassociatedwithbandsandwhenabandhasnoactivitiesitmaybehidden.

Thepicturebelowshowstheeffectwithalltheoptionsunchecked:

Page 158: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Andchecked:

8.5FiltersThissectioncoverstheabilityofPrimaveratocontrolwhichactivitiesaredisplayed,bothonthescreenandinprintouts,byusingFilters.

8.5.1UnderstandingFiltersPrimaverahasanabilitytodisplayactivitiesthatmeetspecificcriteria.YoumaywanttoseeonlytheincompleteActivities,ortheworkscheduledforthenextcoupleofmonthsorweeks,ortheActivitiesthatarein-progress.

•P6WindowsClientfiltersarenotavailableinP6Web.

•Primaveradefaultstodisplayingallactivities.Thereareanumberofpre-definedfiltersavailablethatyoumayuseoredit.Youmayalsocreateoneormoreofyourown.

Afiltermaybeappliedtodisplay,butNOTtohighlightasinotherproducts,thoseactivitiesthatmeetacriteria.

Therearethefollowingtypesoffilters:

•StandardFilterswhicharesuppliedwiththesystemandmaynotbeeditedordeleted.•Globalwhicharemanagedbytheadministratorandmaybeappliedbyanyusertoany

Page 159: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

project.

•MultipleUseravailabletomorethanoneuser.•Userfilterswhichareeditedasrequired.Therearealargenumberofoptionsavailabletocreateafilterandfromthefollowingexamplesyoushouldbeabletoexperimentandaddyourownfilters.

YoumightconsiderplacingtheprojectnameornumberatthestartofaFilternamesoyoumayidentifywhichFilterbelongstowhichprojects.DatabaseswithalargenumberofGlobalFiltersbecomedifficulttomanage.

Thefollowingtypesoffiltersarenotavailable:

•DropdownorAutofiltersasinExcelandMicrosoftProject.

•InteractivefiltersasavailableinSureTrakandMicrosoftProject.Thisiswhenafilterisappliedandtheuserisofferedchoicesfromdropdownlist.Thelackofthisfunctionmayresultinanexcessivequantityoffiltersbeinggeneratedortheusercontinuallyeditingfrequentlyusedfilters.

•Projectfilters,whichwouldonlybeavailablewhenaprojectisopened.

8.5.2ApplyingaFilterToapplyanexistingsinglefilter:

•Clickonthe Filtericon,or•Select Filters….fromtheViewmenutoopentheCustomizeFiltersform:

Page 160: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Checkthefilteryouwishtoapplyand

Select toapplythefilterandleavetheCustomizeFiltersformopenand

Select toapplythefilterandclosetheCustomizeFiltersform.Toapplymultiplefilters:

•Clickonthe Filtericon,•Select Filters….iconfromtheViewmenutoopentheCustomizeFiltersform,•Checktwoormorefilters,and

•SelectfromShowmatchesforifyouwishtoselect:

allappliedfiltersthatwillnormallyresultinfeweractivities,oranyappliedfiltersthatwillnormallyresultinmoreactivitiesbeingdisplayed.

Page 161: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Then:

Select toapplythefilterandleavetheCustomizeFiltersformopenandSelect toapplythefilterandclosetheCustomizeFiltersform.

8.5.3RemovingafilterToremoveafilter:

•OpentheCustomizeFiltersformanduncheckallthecheckboxes,or•Clickonthe icon,or

•Selectingthe ClearFiltersiconontheFiltersmenu:

8.5.4CreatingaFilterTocreateanewfilter:

Page 162: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Clickonthe Filtericon,andeitherSelect Filters….fromtheViewmenutoopentheCreateFiltersformandclickonthe AddNewFilter….icontoopentheCreateFilterform,or

Clickonthe AddNewFilter….IcontoopentheCreateFilterform:Youarenowreadytoaddthefilternameandcreatethenewfilterandpopulatethefields:

•ClickontheAccesstabtodecidetowhomayaccessandassignthefilter:

8.5.5OneParameterFilterThefollowingexampleisafiltertodisplayactivitieswithTotalFloatthatislessorequalto2days:

Page 163: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.5.6TwoParameterFilterThefollowingexampleisafiltertodisplaycriticalactivitiesthatstartafter1Jan2014:

•ThedropdownboxunderbyMatchhastwooptions:

Matchallofthefollowingrules.Thisisusedwhenanactivitymustmeetalloftheselectedparameters.

Matchanyofthefollowingrules.Thisisusedwhenanactivitymustmeetanyoftheselectedparameters.

IftheSelectFilterCriteriaofMatchallofthefollowingruleswasselectandthenONLYCriticalActivitiesstartingafter1Jan14andallCriticalactivitieswouldbedisplayed.

IftheSelectFilterCriteriaofMatchallofthefollowingruleswasselectedthenallCriticalActivitiesandallactivitiesstartingafter1Jan14wouldbedisplayed.

Page 164: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.6ImprovedFilteringP6R8.3hasintroducednewfieldstofilterdataunderadditionalcriteriaintheEPS,Activities,andResourceAssignmentswindows:

•LastModifiedDate

•LastModifiedBy

•AtCompletionLaborUnits

•AtCompletionNonLaborUnits

•FeedbackfromResource(ActivitiesWindow)

•ReviewFinishDate(ActivitiesWindow)

Tousethesenewfilters:

•GototheActivitiesorEPSwindowintheProjectssection,ortotheAssignmentspageintheResourcessection;

•SelectView,Filter,AddNewFilterorclickonthe Filterbuttonlocatedinthetoolbarandthenclickonthe AddNewFiltertoopentheCreateFilterform;

•Fromthedropdownmenu,definethefilteryouwishtoapplyandthenclickOktoconfirmandclosetheform.

8.7ProjectIDFilteringOptionforCreatingPortfoliosWhencreatingafilteredportfolio,itispossibletousetheProjectIDastheparameterforfilteringinP6R8.3.IfProjectIDisselectedthentheavailableconditionaltermsarethefollowing:

•equals,

•isnotequalto,

Page 165: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•contains,

•doesnotcontain,

•startswith,

•endswith,

Tousethisoption:

•OpenthePortfoliosmenuandselectManagePortfolios,•ClickonCreateProjectPortfolio,•EnteradesirednameandselecttheByFilterfromtheManagethisPortfoliooptions,•SelectProjectIDfromthedropdownmenuontheParameterlist.

8.8BarsTheoptionsforformattingthebarsisself-explanatoryandareeditedfromtheCustomizeActivityViewformbyselecting:

Page 166: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

• Viewicon,

• Customizeicon:

TheOptionsiconallowtheformattingoftextonthebars:TheoptiontoselectaBlanknamebythebardidnotworkontheauthor’ssystemwhenthebookswaswritten.Topreventabarnamebeingdisplayedtheauthorusedablankfieldsononamewasdisplayedbythebar.ThiscouldbeaRoleIDorResourceNameiftheyarenotbeingassigned,StepsorFeedbackiftheyarenotbeingused,

8.9GanttChart–Timescale

8.9.1CustomizeActivityViewform–GanttCharttabTheoptionsforformattingthebarsareself-explanatoryandareeditedfromtheCustomizeActivityViewformbyselecting:• View,

• CustomizeView:

Page 167: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ProgressLineswillbecoveredintheUPDATINGANUNRESOURCEDSCHEDULEchapter.

8.9.2Right-clickinTimescaleOptions•TheTimescalemayalsobeformattedbyrightclickingintheTimescale:

•NonworktimeshadingisshowninthepictureaboveisderivedfromtheDatabaseDefaultCalendarsetintheAdminister,ApplicationSettings,GlobalCalendars.

8.9.3ZoomtofitIcon

Page 168: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThetimescaleshouldbemadetofittheavailableareaonthescreenbyclickingontheZoomtofit toolbaricon.

Thisfunctiondidnotoperateasexpectedintheauthorssystematthetimeofwritingthisbookandresultedinthetimescalebeingsetwiththebarsbeingmadeextremelyshortasperthepicturebelow.Thismaybefixedwithaservicepack.

8.9.4DraggingtheTimescaleThetimescalemaybeadjustedtofitanarea.

ThisfunctiondoesnotworkinthesamewayastheProfessionalandOptionalClient.

Usingthepictureaboveasastartingpoint:

•ThemousewasleftclickedinthemiddleofNovember,

•Letgoofthemousebutton,

•MovethemousetothemiddleofFebruary,

•Thiswilldragtheblackshading,

•Thepicturewilllookasperbelow:

•Left-clickinthemiddleofFebruaryandthetimescalewillexpandtofillfromthemiddleofNovembertothemiddleofFebruary:

Itisnotpossibleforuserstodisplaydifferentnonworkperiodsfordifferentprojectsorviews,asinmostotherschedulingsoftwarepackages,withoutaffectingallotherprojectsinadatabase.ThismaybecomeanissuewithprojectsthathavedifferentworkperiodsandmaybesolvedbycreatinganotherdatabasewithadifferentDatabaseDefaultCalendar.

8.10ActivityNetworkTheActivityNetworkviewisdisplayedby ActivityNetworkicon:

Page 169: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheActivityNetworkisformattedintheCustomizeActivityViewform,ActivityNetworktab:

ThiswillbecoveredinmoredetailintheACTIVITYNETWORKVIEWchapter.

8.11TableViewTheTableViewisdisplayedby TableiconandhidestheGanttChartallowingatabularreporttobeprinted.

Page 170: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.12CalendarViewTheCalendarViewisdisplayedby TableiconanddisplaysaviewthatissimilartoaMicrosoftProjectCalendarView:

DoubleclickingonadayopensuptheDayView.8.13Access–SharingViewswithOtherUsersThistaballowsausertoshareaviewwithallpeopleorspecificusers:

Page 171: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.14Workshop6–FormattingtheBarChart

BackgroundManagementhasreceivedyourdraftreportandrequestssomechangestothepresentation.

Dependingonthesettings,yourGanttChartviewmaydifferfromthatshown,e.g.,theremaybenocriticalbarsforexample.

AssignmentWewillcreateanewviewshowingthedates,durationsandfloatonly:

1.SelecttheProjects,ActivitiestoopentheActivitiesWindow,

2.AssignaviewthathastheactivitiesorganizedbyWBS.

3.CreateanewviewusingtheSaveViewAs icontitledWorkshop6-Dates&Durations.

4.CustomizetheViewasperthepicturesbelow:

Page 172: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 173: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 174: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 175: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 176: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 177: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

5.Adjustthecolumnwidthssotheyarealloptimized,

6.Show,hideandthenshowagainthefullscreenbyclickingonthe iconthreetimes,

7.AssigntheOzBuild6d/wcalendartoactivitiesA1070andA1080,8.PressF9toopentheScheduleProjectformandschedulebyclickingontheSchedule

icon,

9.FormatTimescaletofitbyusingthe toolbaricon,

10.ThenusetheDragtheTimescalefunctiontoresizethetimescale,11.Saveyourview,

12.Yourfullscreenshouldlooklikethisandtheredbaristhecriticalpath:

Page 178: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 179: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

9ADDINGRELATIONSHIPSThenextphaseofascheduleistoaddlogictotheactivities.Therearetwotypesoflogic:

•Relationships(DependenciesorLogicorLinksbetweenactivities),and

•ImposedConstraintstoactivitystartorfinishdates.ThesearecoveredintheCONSTRAINTSchapter.

ThePrimaveraHelpfileandothertextusethetermsRelationshipsandLogicforRelationshipsbutdonotusethetermsDependenciesorLinks.Wewilllookatthefollowingtechniquesinthischapter:

Topic NotesforcreatingaSFRelationship

GraphicallyintheBarChart.

Tocreateadependency:

•Clickonanactivity,

•Dragthe mousepointerfromoneactivitytoanother,and

•Clickagain.

ByopeningtheActivityDetailsform.

PredecessorandSuccessorsmaybeaddedanddeletedfromthePredecessororSuccessortabs.

ByeditingordeletingadependencyusingtheEditRelationshipform.

Right-clickanactivitylinkintheBarChartorNetworkViewandselectEditorDeletefromthemenu.

BydisplayingthePredecessorand/orSuccessorcolumns.

Double-clickinginthePredecessororSuccessorcellswillopentheAssignPredecessorformortheAssignSuccessorform.

ChainLinkingorAutomaticallyLinkingactivitieswithaFinish-to-Startrelationship.

SelecttheusingtheCtrlkey,Right-clickandselectLinkActivities.Theywillbelinkedfromtobottomirrespectiveoftheordertheactivitiesareselected.

RelationshipsTherearetwotypesofdependenciesthatarediscussedinscheduling:

•HardLogic,alsoreferredtoasMandatoryorPrimaryLogic,aredependenciesthatmaynotbeavoided:forexample,afootingexcavationhastobepreparedbeforeconcretemaybepouredintoit.

•SoftLogic,alsoreferredtoasSequencingLogic,DiscretionaryLogic,PreferredLogic,orSecondaryLogic,mayoftenbechangedatalaterdatetoreflectplanningchanges:forexample,determininginwhichorderthefootingholesmaybedug.

Thereisnosimplemethodofdocumentingwhichishardlogicandwhichissoftlogicasnotesoratype(availableinAstaPowerproject)maynotbeattachedtorelationships.Aschedule

Page 180: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

withalargeamountofsoftlogichasthepotentialofbecomingverydifficulttomaintainwhentheplanischanged.Asaprojectprogresses,softlogicconvertstohardlogicduetocommitmentsandcommencingactivities.

MicrosoftProjectallowsonerelationshipbetweentwoactivities,SureTrakandP3tworelationshipsbetweentwoactivitiesandP6fourrelationshipsbetweentwoactivities.

9.1ConstraintsConstraintsareappliedtoActivitieswhenrelationshipsdonotprovidetherequiredresultandareoftenaresultofExternalDependencies.Typicalapplicationsofaconstraintaretoconstrainanactivitytoadatefor:

•Theavailabilityofasitetocommencework,

•Thesupplyofinformationbyaclient,or

•Therequiredfinishdateofaproject.

ConstraintsareoftenenteredagainstMilestoneactivitiestorepresentcontractdatesandmaybedirectlyrelatedtocontractitemsusingNotebookTopicsandarecoveredintheCONSTRAINTSchapter.

9.2UnderstandingRelationshipsTherearefourtypesofdependenciesavailableinPrimaveraP6:

•Finish-to-Start(FS)(alsoknownasconventional)•Start-to-Start(SS)•Start-to-Finish(SF)•Finish-to-Finish(FF)Twoothertermsyoumustunderstandare:

•Predecessor,anactivitythatcontrolsthestartorfinishofanotherimmediatesubsequentactivity.

•Successor,anactivitywherethestartorfinishdependsonthestartorfinishofanotherimmediatelyprecedingactivity.

ThefollowingpicturesshowhowthedependenciesappeargraphicallyintheBarChartandActivityNetwork(alsoknownasPERT,NetworkDiagramandRelationshipDiagramViews):TheFS(orconventional)dependencylookslikethis:

WhiletheSSdependencyislookslikethis:

Page 181: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheSFdependencylookslikethis:

TheFFdependencylookslikethis:

9.3UnderstandingLagsandLeadsALagisadurationthatisappliedtoadependencytomakethesuccessorstartorfinishearlierorlater.

•AsuccessoractivitywillstartlaterwhenapositiveLagisassigned.Therefore,anactivityrequiringa3-daydelaybetweenthefinishofoneactivityandstartofanotherwillrequireapositivelagof3days.

•Conversely,alagmaybenegativewhenanewactivitymaybestartedbeforethepredecessoractivityisfinished.ThisiscalledaLeadorNegativeLag.

LeadsandLagsmaybeappliedtoanyrelationshiptype.AnexampleofaFSwithpositivelag:

AnexampleofaFSwithnegativelag:

HerearesomeimportantpointstounderstandaboutLags:

•ThelagdurationiscalculatedonthelagasinMicrosoftProjectandotherPrimaveraproducts.AlagisnotassignedtooneorbothofthePredecessorandSuccessoractivitiesasinAstaPowerproject,whichismorelogical.

LagsmaybeassignedoneoffourcalendarsfromtheCalendarforSchedulingRelationshiplagdropdownboxintheSelectprojectschedulingoptionsform.Thisformisopenedby:•Clicking Scheduler(F9)icontoopentheScheduleProjectform:

Page 182: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Thenclickingonthe tabtoopentheSelectprojectschedulingoptionsform.

9.4UnderstandingtheLagCalendarThefourLagCalendaroptionsareatthebottomoftheform:

•PredecessorActivityCalendar,

•SuccessorActivityCalendar,

•24-HourCalendar,and

•ProjectDefaultCalendar.LagsarecalculatedbyPrimaveraP3andSureTraksoftwareusingthePredecessorCalendar.MicrosoftProject2003to2010usestheSuccessorCalendarormayhaveanElapsedDurationLag.EarlierversionsofMicrosoftProjectusedtheProjectCalendar.AstaPowerprojectassignsthelagtoeitheroreitherthepredecessororsuccessorthusallowingeitherthePredecessororSuccessorCalendartobeselectedforeachrelationship.YoumustbecarefulwhenusingalagtoallowfordelayssuchascuringconcretewhentheLagCalendarisnotaseven-daycalendar.Becausethistypeofactivitylapsesnonworkdays,theactivitycouldfinishbeforePrimaveracalculatedfinishdate.YoumustbeextremelycarefulwhenopeningmultipleprojectswhentheLagCalendaroptionisdifferentforeachproject.Thisisbecausealltheprojectschedulingoptionsareadoptedfromtheprojectatthetopofthelistofopenedprojectandthereforesomeofyourprojectsmaynotcalculatethesamewayastheydidbeforeopeningtheprojectstogether.ThisisdifferenttothewaytheWindowsClientcalculatesmultipleprojects;theWebdoesnotrecognizetheWindowsClientDefaultProjectfunction,pleaseseeProfessionalandOptionalClientbookformoredetailsonthistopic.

Page 183: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Theexamplebelowshowtheeffectofchangingacalendarfromapredecessortoasuccessorontwoactivities:Thelagbelowis5daysor40hours:SuccessorActivityCalendaristhedefault:

PredecessorActivityCalendaristhedefault:

9.5FormattingtheRelationshipsRelationshiplinesmaynotbeformattedlikeinSureTrak,butunlikeMicrosoftProjecttheydonotadoptthecolorofthepredecessoractivitywhichisoftenmisleading.

•Therelationshipsmaybedisplayedorhiddenbyclickingonthe iconontheActivityWindow,Viewtoolbar.

•Relationshiplinesmaynotbeformatted:

DrivingCriticalandDrivingNonCriticalaresolidblack,andNonDrivingaredottedblack.

9.6AddingorRemovingRelationships

9.6.1GraphicallyAddingandDeletingaRelationshipTographicallyaddarelationship,thisprocessisdifferenttotheWindowsClient:

•Movethemousetotheendofthepredecessoractivitybar,whichwillchangethemousearrowtoa ,DONOTSELECTtheactivity,

•Thenleftclickwiththemouse,

•Movethemousetothestartofthesuccessoractivityandclickthemousebuttonagain:

TocreateotherrelationshipssuchasStarttoStart,dragfromthebeginningofthepredecessortothebeginningofthesuccessorbar.

Toconfirmoreditthelinkafteralinkhasbeenadded,theEditRelationshipformmaybeopenedby:

•Selectarelationshiplinebyclickingattheendsoftherelationshipwilldisplayasquareboxindicatingtherelationshiphasbeenselected,

Page 184: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Right-clicktodisplayamenu,

•SelectEditRelationshiptoopentheEditRelationshipformandedittherelationship,andtheclickonDeleteor

•ClickonDeleteRelationshiptodeletearelationship.

9.6.2Adding,DeletingandEditingRelationshipswiththeActivityDetailsFormTheActivityDetailsforminthelowerpanemaybeusedforaddinganddeletingrelationships.

OpeningtheForm•SelecteitherthePredecessorortheSuccessortab(theyalloperateinasimilarway).The

Predecessortabisdisplayedinthefollowingpicture:

EditingtheFormThePredecessorandSuccessortabsmaybothbeformattedandthecolumnsyourequiremaybedisplayed:

•SelectthePredecessororSuccessortab,and•Select CustomizeColumnsicontoopentheColumnsmenu,

•Thefollowingpicturedisplaysthefieldsthatareavailable:

Page 185: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Thedatafieldsyourequiremaybedisplayedorhidden.

AddingandDeletingaRelationshipToAddapredecessororsuccessor:•Clickonthe AssignicontoopentheSelectPredecessorActivityformtoassigna

predecessor:

•EntertheRelationshipTypefromtheRelationshipTypedropdownlistandthelag,ifrequired,fromtheLagdropdownlist.

•Toenteranotherrelationship,clickthenextactivityline.TheSelectPredecessorActivityorSelectSuccessorActivitySuccessorformwillremainopen.

Page 186: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Deletearelationshipbyselectingarelationshipandclickingonthe Deleteicon.

•ItispossibletofollowthenetworkpathbyjumpingtoanactivityhighlightedinthePredecessororSuccessorformbyclickingonthe Gotoicon.

•Moveupanddownthelistofactivitiesbyclickingonthe iconsinthetopleftsideofthePredecessororSuccessortabs.Thisiconexistsineverylowerpanetab.

EditingaRelationshipVersion8.4allowstheeditingofarelationshipbyenteringadifferentActivityIDinthePredecessororSuccessordetailswindow:

9.6.4AddingandDeletingRelationshipsUsingColumnsToassignrelationshipsusingcolumns:

•DisplaythePredecessorand/orSuccessorcolumns,

•Double-clickinthePredecessororSuccessorcolumnofanactivitytoopentheAssignPredecessororSuccessordetailsforminthelowerwindow,and

•Proceedasabove.

9.6.5ChainLinkingActivitiesmayalsobelinkedbyselectingtwoormoreactivitiesusingtheCrtlkeyandclickingonthe LinkSelectedActivitiesicon:

•ThisoptionwillonlycreateFinish-to-Startrelationships.

•ThisoptiondoesnotenabletheusertoChainUnlink.

•TheactivitiesareNOTlinkedintheorderthattheyareclickedonasintheWindowsClient.

9.7DissolvingActivitiesWhenanactivityisdeletedachainoflogicalactivitiesmaybebroken.

The DissolveiconwilldeleteanactivitybutjointhepredecessorsandsuccessorswitharelationshipwhichisahybridofthetwoexistingrelationshipsandmaynotbeaFinishtoStart.

Page 187: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

9.8CircularRelationshipsACircularRelationshipiscreatedwhenaloopiscreatedinthelogic.WhenyourescheduleyouwillbepresentedwiththeErrorform,whichidentifiesthereisaprobleminthelogic,butnotspecificallyidentifiesaloop.

Ifanerrorisdetectedwhenschedulingaproject,theScheduleProjectLogreportshouldbedisplayedwhichwillidentifyanyproblems:

TodisplaytheScheduleProjectLogreportafterscheduling:•PressF9orclickonthe SchedulericontoopentheScheduleProjectform,

Page 188: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ClickontheDisplayschedulingloguponcompletionicontodisplaythereportaftertheprojecthasbeenscheduled.

Toremoveacircularrelationshipeitherselectthefirstactivityinthelistandremovetheoffendingpredecessor,whichisthelastActivityinthelist,orgotothelastactivityinthelistandremovetheoffendingsuccessor,whichisthefirstactivityinthelist.

9.9RelationshipsDetailWindowontheActivitiesPageP6R8.3hasintroducedanewRelationshipsdetailwindowontheActivitiespagethatallowsuserstocreateandadministertherelationshipbetweenpredecessorsandsuccessorswithinthesamewindow.ThiswindowprovidesthesamecapabilitiesastheseparatewindowsforPredecessorsandSuccessors.

Tousethisfeature:

•OpentheViewmenuontheActivitieswindowandselectCustomizeDetailWindows;•SelecttheRelationshipscheckboxandthenSave.

Page 189: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 190: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

9.10SchedulingtheProjectAfteryouhaveyouractivitiesandthelogicinplace,Primaveracalculatestheactivities’dates/times.Morespecifically,PrimaveraSchedulestheprojecttocalculatetheEarlyDates,LateDates,FreeFloatandtheTotalFloat.ThiswillenableyoutoreviewtheCriticalPathoftheproject.(MicrosoftProjectusesthetermSlackinsteadofthetermFloat.)Toscheduleaproject:

•PressF9orclickonthe SchedulericontoopentheScheduleProjectform,

•ChecktheCurrentDataDate,whichbeforeascheduleisprogressedshouldbethestartdateoftheproject.

•Clickonthe icon.

ThereisnoautomaticcalculationavailablewithP6Web.

9.11Workshop7–AddingtheRelationships

BackgroundYouhavedeterminedthelogicalsequenceofactivities,soyoumaynowcreatetherelationships.

Assignment1.CreateanewViewnamedWorkshop7–AddingRelationshipsbysavingyour

Workshop6–Dates&Durationsview.2.DisplaythePredecessorcolumnfromtheListssectionoftheColumnsform,tothe

rightoftheActivityName.

3.Inputthelogicbelowusingthemethodsdetailedinthischapter.

Page 191: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThepicturebelowisfromtheWindowsClientastheWebwillnotdisplayPredecessorsasActivityIDsonlyasActivityName.

4.PressF9orclickonthe icontoscheduleyourproject.

5.HideanddisplaytheLogicLinksusingthe iconandleavethemdisplayed.

AnswertoWorkshop76.AddthePredecessorcolumnandcheckyourdata:

Page 192: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

7.Nowformatthecolumnsperthefollowingpictureandcheckyourdata:

Page 193: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

10ACTIVITYNETWORKVIEW

10.1IntroductiontotheActivityNetworkViewTheActivityNetwork,alsoknownasthePERT(ProjectReviewandEvaluationTechnique)View,displaysactivitiesasboxesconnectedbytherelationshiplines.Seethefollowingpicture:

Thischapterwillnotcoverthissubjectindetailbutwillintroducethemainfeatures.

ManyfeaturesavailableintheGanttChartViewarealsoavailableintheActivityNetworkView.SomeofthefunctionsoftheActivityNetworkVieware:

Topic MenuCommandViewingaProjectUsingtheActivityNetworkView. Clickonthetoolbar icon.

Toshowdrivingrelationshipsonly. Clickthe icon.

Tomagnifyanarea.Clickthe iconandmovethemouseovertheareatobemagnified.

Toselectanactivitysotheinformationinthebottomwindowisrelevanttotheselectedactivity.

Clickthe icon.

Changethesizeorzoomtofit. Clicktheappropriate icon.

FormattingtheActivityBoxes.

NOTE:FormattingtheActivityNetworkboxesalsoformatstheTraceLogicboxesasintheWindowsClient.

Selectthe CustomizeicontoopentheCustomizeActivityViewform,

SelecttheActivityNetworkformtab.

TomovetheNetworkViewpicturearoundonthe Clickthe iconandthenclickand

Page 194: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

screen. dragthepicture.

ShowProgressonactivityboxes.

Selectthe CustomizeicontoopentheCustomizeActivityViewform,

SelecttheActivityNetworkformtab.

10.2EarlyDate,LateDateandFloatCalculationsTohelpunderstandthecalculationoflateandearlydates,floatandcriticalpath,wewillnowmanuallyworkthroughanexample.Theboxesbelowrepresentactivities.

•Theforwardpasscalculatestheearlydates:EF=ES+DUR–1

Startthecalculationfromthefirstactivityandworkforwardintime.

•Thebackwardpasscalculatesthelatedates:LS=LF–DUR+1

Startthecalculationatthelastactivityandworkbackwardsintime.

Page 195: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TotalFloatisthedifferencebetweeneithertheLateFinishandtheEarlyFinishorthedifferencebetweentheLateStartandtheEarlyStartofanactivity.Thelower2days’activityhasfloatof9–7=2days.Noneoftheotheractivitieshasfloat.

TheCriticalPathisthepathwhereanydelaycausesadelayintheprojectandrunsthroughthetoprowofactivities.FreeFloatisthedifferencebetweenthePredecessorEarlyFinishandtheSuccessorEarlyStart.

AnactivitymaynotbeontheCriticalPathandmayhavemorethanonepredecessor.ADrivingRelationshipisthepredecessorthatdeterminestheActivityEarlyStart.

10.3Workshop8–SchedulingCalculationsandActivityNetworkView

BackgroundWewanttopracticecalculatingearlyandlatedateswithasimplemanualexercise.

Assignment1.ApplytheActivityNetworkViewofyourOzBuildschedulebyclickingonthe icon.

2.ClickoneachnodeoftheWBSandnoticehowonlyactivitiesassignedtoeachnodearedisplayed.

3.ClickonthethreeZoomicons andnoticetheireffectontheschedule.

4.CalculatetheEarlyDates,LateDates,andTotalFloatforthefollowingactivities,assumingaMonday-to-Fridayworkingweekandthefirstactivitystartingon01Feb16.

Page 196: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4.Seeoverthepagefortheanswer:

AnswertoWorkshop8

Page 197: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ForwardPassEF=ES+DUR–1

BackwardPassLS=LF–DUR+1

FloatCalculationTF=LS–ES

TheEarlyBaristheupperbar,theLateBarthelowerbarandtheendoftheTotalFloatbar,whichisthethinbar,endsattheLateFinishdate.

Page 198: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 199: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

11CONSTRAINTSConstraintsareusedtoimposelogiconactivitiesthatmaynotberealisticallyscheduledwithlogiclinks.Thischapterwilldealwiththefollowingconstraintsindetail:

•StartOnorAfter•FinishOnorBeforeThesearetheminimumnumberofconstraintsthatarerequiredtoeffectivelyscheduleaproject.

StartOnorAfter(alsoknownasan“EarlyStart”or“StartNoEarlierThan”constraintasitonlyaffectstheEarlydatescalculation)isusedwhenthestartdateofanactivityisknownanddoesnothaveapredecessor.Primaverawillnotcalculatetheactivityearlystartdatepriortothisdate.

FinishOnorBefore(alsoknownas“LateFinish”or“FinishNoLaterThan”constraintasitonlyaffectstheLatedatescalculation)isusedwhenthelatestfinishdateisstipulated.Primaverawillnotcalculatetheactivity’slatefinishdateafterthisdate.

ThefollowingtablesummarizesthemethodsusedtoassignConstraintstoActivitiesorhowtoaddnotestoactivities:

Topic NotesforCreatingaConstraintSettingaPrimaryandSecondaryconstraintwiththeActivityDetailsform.

OpentheGeneraltabontheActivityDetailsform.

SettingConstraintsusingcolumns.

Thefollowingcolumnsmaybedisplayedandtheconstraintsassignedoredited:

•PrimaryConstraint

•PrimaryConstraintDate

•SecondaryConstraint

•SecondaryConstraintDate

•ExpectedFinishDate

DragginganActivityintheGanttChart.

DragginganActivityintheGanttChartwillopentheConfirmationformwheretheuserisabletoconfirmthesettingofaStartOnorAfterconstraint.

AddingNotes,thesecouldbeaboutconstraintsorotheractivityinformation.

TheActivityDetailsformhasaNotebookstab,whichenablesNotestobeassignedtoNotebookTopics.

Primaverawillpermittwoconstraintstobeassignedtoeachactivity.AstaPowerproject,P3,andSureTrakalsoallowtwoconstraintsbutMicrosoftProjectonlypermitsoneexceptwhenaDeadlineconstraintisapplied.

Page 200: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AfulllistofconstraintsavailableinPrimavera:

<None> Thisisthedefaultforanewactivity.AnactivitybydefaultisscheduledtooccurAsSoonAsPossibleanddoesnothaveaConstraint.

StartOnAlsoknownasMustStartOnandsetsthedatetheactivitywillstart.Therefore,theactivityhasnofloat.TheearlystartandlatestartdatesaresettotheConstraintDate.

StartOnorBefore

AlsoknownasStartNoLaterThanorLateStart,thisconstraintsetsthelatedateafterwhichtheactivitywillnotstart.

StartOnorAfter

AlsoknownasStartNoEarlierThanorEarlyStart,thisconstraintsetstheearlydatebeforewhichtheactivitywillnotstart.

FinishOnAlsoknownasMustFinishOn,thisconstraintsetsadateonwhichtheactivitywillfinishandthereforehasnofloat.TheearlyfinishandthelatefinishdatesaresettobethesameastheConstraintDate.

FinishOnorBefore

AlsoknownasFinishNoLaterThanorLateFinish,thissetsthelatedateafterwhichtheactivitywillnotfinish.

FinishOnorAfter

AlsoknownasFinishNoEarlierThanorEarlyFinish,thissetstheearlydatebeforewhichtheactivitywillnotfinish.

AsLateAsPossible

AlsoknownasZeroFreeFloat.Anactivitywillbescheduledtooccuraslateaspossible.ItconsumesFreeFloatonlyanddoesnothaveanyparticularConstraintDate.TheEarlyandLatedateshavethesamedate.

MandatoryStart

Thisrelationshippreventsfloatbeingcalculatedthroughthisactivityandeffectivelybreaksascheduleintotwoparts.ThisisalsosometimescalledaHardConstraint.

MandatoryFinish

Thisrelationshippreventsfloatbeingcalculatedthroughthisactivityandeffectivelybreaksascheduleintotwoparts.ThisisalsosometimescalledaHardConstraint.

ExpectedFinish

AnExpectedFinishsetstheEarlyFinishtotheExpectedFinishconstraintdateandcalculatestheRemainingDurationfromtheEarlyStartdateforanun-startedactivity,orDataDateiftheactivityisin-progresstotheExpectedFinishdate.

EarlierThanconstraintsoperateontheEarlyDates,andLaterThanconstraintsoperateonLateDates.ThefollowingpicturedemonstrateshowconstraintscalculateTotalFloatofactivities(withoutpredecessorsorsuccessors)againstaprojectof15daysdurationwithaProjectFinishdateset:

Page 201: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AnactivityassignedanAsLateasPossibleconstraintinPrimaveraP6,PrimaveraContractor,PrimaveraP3,andSureTraksoftwarewillscheduletheactivitysoitabsorbsonlyFreeFloatandwillnotdelaythestartofanysuccessoractivities,thisisnormallycalledaZeroFreeFloatconstraint.InMicrosoftProject,anactivityassignedwithanAsLateasPossibleconstraintwillbedelayedtoabsorbtheTotalFloatanddelayallitssuccessoractivitieswhichhavefloat,notjusttheactivitywiththeconstraint.

11.1AssigningConstraintsWhensettingconstraintssometimestheconstrainttimewillnotbesetatthestartorfinishoftheactivitycalendarbutsetat00:00orsomeotherirrelevanttime.ThereforewhensettingconstraintsyoushouldalwaysdisplaythetimebyselectingAdminister,MyPreferences,DateFormatheadingtoensuretheconstrainttimeiscompatiblewiththeactivitycalendar.

11.1.1NumberofConstraintsperActivityEachactivitymaybeassignedtwoconstraintswhicharetitledPrimaryandSecondaryConstraint.AfterthePrimaryhasbeenset,aSecondarymaybesetonlywhenthecombinationislogicalandthereforeareducedlistofconstraintsisavailableafterthePrimaryhasbeenset.

11.1.2SettingaPrimaryConstraintUsingtheActivityDetailsFormToassignaconstraintusingtheActivityDetailsform:•Selecttheactivityrequiringaconstraint,

•OpentheGeneraltabontheActivityDetailsform,

Page 202: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SelectthePrimaryConstrainttypeandDatefromthedownlisttotherightofPrimaryConstraint:

11.1.3SettingaSecondaryConstraintUsingtheActivityDetailsFormASecondaryConstraintmayonlybesetafteraPrimaryConstrainthasbeenset.ToassignaconstraintusingtheActivityDetailsform:•Selecttheactivityrequiringaconstraint,

•OpentheGeneraltabontheActivityDetailsform,•SelecttheSecondaryConstrainttypeandDatefromthedownlisttotherightofthe

SecondaryConstraint:

ThepictureaboveshowsthatafteraPrimaryStartOnorAfterconstraintissetthereareonlytwoSecondaryConstraintsavailable.

AfteraconstraintissettheStartdateorFinishdatewillhaveanasterisk“*”nexttothedatewhendisplayedinActivityViewcolumns.

11.1.4ExpectedFinishConstraintThisconstraintisNOTsetinthedatesStatusareaasintheWindowsClientandacolumnmustbedisplayedtosetanExpectedFinishConstraint.

11.1.5SettingConstraintsUsingColumnsThefollowingconstraintcolumnsmaybedisplayedandtheConstraintseditedorassignedusingthesecolumns:

•PrimaryConstraint

•PrimaryConstraintDate

•SecondaryConstraint

•SecondaryConstraintDate

•ExpectedFinish

Page 203: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

11.1.6SettingConstraintsbyDragginganActivityAnactivitymaybedraggedtosetaconstraint.

WhendraggedyouwillbepresentedwiththeActivityConstraintformtoconfirmyourintension:

11.2ProjectMustFinishByDateAnabsolutefinishdatemaybeimposedontheprojectusingtheEPSWindow,Generaltab:

Page 204: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ImposingaprojectMustFinishBydatemakesPrimaveracalculatethelatedatesfromtheMustFinishBydateratherthanthecalculatedearlyfinishdateofthelastactivity.ThiswillintroducepositivefloattoactivitieswhenthecalculatedEarlyfinishdateispriortotheMustFinishBydate:

Thiswillalsocreatenegativefloatwhentheactivity'scalculatedearlyfinishdateisaftertheMustFinishBydate,butitisnotobviouswherethenegativefloatisbeingdrivenfromastherearenoconstraintsassignedtoactivities:

ToremoveaProjectMustFinishBydate,highlightthedate,presstheDeletekeyandthentheEnterkeyortaboutofthecelltoensurethedateisremoved.ThisfunctionissimilartotheP3andSureTrakfunctionbutverydifferentfromthewayMicrosoftProjectFinishDateoperates.AfteraFinishDateissetinMicrosoftProjectallnewTasksaresetwithanAsLateAsPossibleconstraintandtheStartDateiscalculated.PrimaveradoesnotsetAsLateAsPossibleconstraintsafteraMustFinishBydateissetandtheProjectStartDateisstilleditable.

ItisnotobviouswherethefloatisbeinggeneratedafteraMustFinishBydateisimposedonaproject.ThisisoftenconfusingtopeoplenewtoschedulinganditisrecommendedthatyoudonotuseaMustFinishBydate.Instead,tieallactivitiestoaFinishMilestonewhichhasaLatefinishconstraint.

11.3ActivityNotebooksItisoftenimportanttonotewhyconstraintshavebeenset.Primaverahasfunctionsthatenableyoutonoteinformationassociatedwithanactivity,includingthereasonsassociatedfor

Page 205: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

establishingaconstraint.

TheActivityDetailsformhasaNotebookstab,whichenablesNotestobeassignedtoNotebookTopicsandhassomewordprocessing-typeformattingfunctions.

11.3.1CreatingNotebookTopicsNotebookTopicsarecreatedbyselectingAdminister,EnterpriseData,Projects,NotebookTopicstab.Afteratopichasbeencreatedthistopicmaybemadeavailabletothefollowingdatafieldsbycheckingtheappropriatebox:

•EPS

•Project

•WBS

•Activities

11.3.2AddingNotesToaddanotetoanactivity:

•SelecttheNotebookstabintheActivityDetailsform,•AssignaNotebooktopicusingthe Assign(Insert)icon,and

•ClickontheEditingNotebooksTopic icontoeditthetopic:

Page 206: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

11.4Workshop9–Constraints

BackgroundManagementhasprovidedfurtherinputtoyourscheduleastheclienthassaidthattheyrequirethesubmissiononorbefore27Jan2014.

Assignment1.GototheActivitiesWindowandobservethecalculatedfinishdateandthecriticalpath

oftheprojectbeforeapplyinganyconstraints.

2.DisplaytheFloatBar(TotalFloatBar)bymakingthesecondarybarblackandtypeinaheightof4usingtheCustomizeGanttChartOptionsform.

3.DisplaythecolumnsasthepicturebelowandsaveyourViewasWorkshop9–Constraints.

4.Theclienthassaidthattheyrequirethesubmissionon27Jan2014.ApplyaFinishOnorBeforeconstraintandassignaconstraintdateof27Jan201416:00totheBidDocumentSubmittedactivityfromtheGeneraltab.

NOTE:Theauthorhasinthepastfoundthatconstrainttimeshavenotalwaysmatchedtheactivitycalendarstarttimes(e.g.,08:00)andfinishtimes(e.g.,16:00)andhavebeenset

Page 207: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

to00:00.IfyoufindthefloatsdonotcalculatecorrectlythenopentheMyPreferencesformanddisplaythetime.Reviewifthetimesarecorrectandifnoteditthemtosuityourcalendar.

5.Scheduletheprojectandreformatthetimescale.ThereshouldbenochangeintheTotalFloatasaFinishOnorBeforeconstraintwillnotdevelopPositiveFloat.

6.RemovetheFinishOnorBeforeconstraintfromtheBidDocumentSubmittedactivity.7.NowmovetotheProjects,EPSWindow,Generaltab,selectyourprojectandassigna

projectMustFinishByconstraintof27Jan201416:00.ReturntotheActivitiesWindowandreschedule.Allactivitiesnowhavetheirfloatcalculatedtothisdateandhavepositivefloat.

8.RemoveprojectMustFinishByconstraintof27Jan201416:00(byhighlightingthedateandpressingtheDeletekeyandtaboutofthecelltoensurethedatehasbeendeleted.

9.ScheduletheprojectandtheCriticalPathshouldreturn.

10.ApplyaFinishOnorBeforeconstraintandassignaconstraintdateof27Jan201416:00totheBidDocumentSubmittedactivityandschedule,theCriticalPathwillremain.

Page 208: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

11.DuetotheproximitytoChristmas,managementhasrequestedthatyoudelaytheObtainQuotesfromSuppliersuntilfirstthingintheNewYear(02Jan2014).ConsensusisthatabetterresponseandsharperpriceswillbeobtainedaftertheChristmasrush.

Toachievethis,setaStartOnorAfterconstraintdateof02Jan201408:00ontheObtainQuotesfromSuppliersactivity.

Nowreschedule.

Observetheimpactonthecriticalpathandenddates.

YouwillnoticethattheFinishConstraintontheBidDocumentSubmittedactivityhascreatedsomenegativefloat,whichisdisplayedintheTotalFloatcolumnandtheNegativeFloatbar.

Page 209: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

DisplaytheNotebooktabintheActivitiesWindow.12.AddaNotebookTopicagainsttheObtainQuotesfromSupplieractivityindicatingwhy

thereisaconstrainton02Jan2014.

13.OpentheGroupandSortformbyclickingonthe iconandgroupbyTotalFloatandclosetheform.

Page 210: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

14.Sortonduration(byclickinginthePlannedDurationcolumn)tobringthelongestactivitytothetop.Itisnormallythelongesttaskthatmaybeshortened.Thechangefrom-2dto-3dandbackto-2disduetochangeofcalendarsfrom5-dayto6-dayperweek.NOTE:Notalltheactivitiesaredisplayedinthetwopicturesbelow:

15.Afterreview,itisagreedthat2daysmaybedeductedfromReviewBidDocumentactivity.Changethedurationofthisactivityto2days,

16.Reschedule:

Page 211: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.NowGroupbyWBS,donotShowfieldtitleandsortbyActivityID:

18.Noticethatactivitieswithconstraintshavean“*”bytheirdates.

19.SaveyouView.

Page 212: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

12PRINTINGANDREPORTSThisisthestageatwhichthescheduleisprintedsopeoplemayreviewandcommentonit.Thischapterwillexaminesomeoftheoptionsforprintingyourprojectschedule.

Thereareseveraltoolsavailabletooutputyourscheduletoaprinter:

•ThePrintingfunctionprintsthedatadisplayedinthecurrentView.•TheReportingfunctionprintsreportswhichmaybeaccessedfromtheDashboards.These

areindependentofthecurrentView.Primaverasuppliesanumberofpredefinedreportsthatmaybetailoredtosuityourownrequirements.Reportswillnotbecovereddetailinthispublication.

•TheProjectWebSitePublishertopublishthescheduletoawebsite.ThisfunctionisaccessedfromtheWindowsClientversionandisnotcoveredinthispublication.

ItisrecommendedthatyouconsiderusingaproductsuchasAdobeAcrobattooutputyourscheduleinpdfformat.Youthenwillbeabletoe-mailhighqualityoutputsthatrecipientsmayprintorreviewonscreenwithoutneedingacopyofPrimavera.

12.1PrintingtheGanttChartPrintsettingsareappliedtotheindividualViewsandthesettingsaresavedwiththatView.TherearethreecommandsundertheActionmenuwhichmayalsobedisplayedontheActiontoolbar:

Eachtimeyoureporttotheclientormanagement,itisrecommendedthatyousaveacopyofyourprintoutorreport.Apdfisanexcellentmethodofsavingthisdata.Thisenablesyoutoreproducethesereportsatanytimeinthefutureandkeepanelectroniccopyavailablefordisputeresolutionpurposes.

Itisgoodpracticetokeepacopyoftheprojectaftereachupdate,especiallyiflitigationisapossibility.AprojectmaybecopiedeitherbycreatingaBaseline,byexportingtheprojectasanXMLfileintheclientorbyusingtheprojectcopyfunction,thenmakingtheStatusinactiveintheGeneraltaboftheProjects,EPSWindow.Itisimportanttonotethatalthoughtheprojectmaybemarkedasinactiveitmaystillbeopenedandmodified.

12.2PrintPreview

Page 213: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Clickthe PrintPreviewicontopreviewtheprintout:

TheauthorfoundthatthePrintPreviewformwasopenedasanewwindowinthebrowserbehindtheworkingviewandthereforehidden,youwillneedtochangewindowstoseetheprintpreview.UsetheAlt+Tabkeystochangewindows.

The followingparagraphsdescribe the functionsof the iconsat the topof thePrintPreviewscreenfromlefttoright:

•The iconopensthePrintformwheretheprinter,thepagestobeprinted,papersizeandthenumberofcopiestobeprintedmaybeselected.

•The iconopensthePageSetupformtobecoveredinthenextparagraph.

•The iconsallowscrollingwhenaprintouthasmorethanonepage.

•The and settheprintouttoportraitorlandscape.

•Themagnifyingglass iconszoominandout.YoumayalsoclickinthePreviewscreentozoomin.

Page 214: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•The buttonclosesthepreviewscreen.

12.3PageSetupToopenthePageSetup…form:

•Clickthe PageSetupicononthePrintPreviewtoolbar:

ThePageSetupformcontainsthefollowingtabs:•PageLayout

•Header/Footer

•Sheet

12.3.1PageLayoutTabThePrimaveraoptionsinthePageLayouttabare:•OrientationenablestheselectionofPortraitorLandscapeprinting.•Marginsenablesthemarginsaroundtheedgeoftheprintouttobeadjusted.•Paperallowstheselectionofthepapersize.Itisbesttoallowawidermarginforanedge

thatistobeboundorholepunched.1”(25mm)isusuallysufficient.

ItisoftenbesttoprinttoapdffileinA3formatasitisusuallysimplertofitallthedatatoonepagewhenmanycolumnsarebeingprint.

Metricmeasurementswerenotavailableonanyoftheauthors’printers.

Page 215: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

12.3.2HeaderandFooterTabsHeadersappearatthetopofthescreenaboveallscheduleinformationandfootersarelocatedatthebottom.BoththeHeadersandFootersareformattedinthesameway.Wewilldiscussthesetting-upofFootersinthischapter.

TherearetwooptionstosettheHeadersandFooters:

•Youmayeitherclickonthedropdownboxandselectcontentfromthedropdownbox,or

•Toclickonthe or buttonsandselectthedataandfontsizeusingtheoptionsintheforms.

12.3.3CustomHeaderandCustomFooterTabsTheCustomHeader&CustomFootertabsoperateinthesamewayandclickingonthe

or buttonswillopenuptheappropriateform:

Page 216: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thebuttonsworkasfollows:

• isusedaftertexthasbeenenteredtoformatthetext,asusedintheLeftsection:above,

• aretoenterpagenumberas&[Page]andnumberofpagesas&[Pages].TheCentersection:formattingabovewilldisplayas“Page1of8”.

• willdisplaythedateas&[Date],timeas&[Time]andprojectnameas&[File].

Thesettingsabovewillbedisplayedasperthepicturebelow:

TherearelesspredefinedfieldsthatmaybeshownthatfoundintheWindowsClient.

TheauthorfoundthePrintPreviewwasoftenunclearbuttheprintoutwasclear.

AnyfreefromtexttypedintotheHeaderorFooterformwereavailablewhenreturningtotheformatalaterdate.

12.3.4SheetTabPrintRange•SelectingaSpecificdaterangewillenablepartsofthescheduletobeprintedorallowa

gapatthestartandendofthebarsintheGanttChartsotextattheendofthebarsisnottruncated.

Page 217: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Fitto:specifiesthenumberofpageswidetheprintoutwillfitontoandadjuststhetimescaleasrequired.

Table•Print?tablecolumns(s)selectshowmanyofthedisplayedcolumnsaretobeprinted,•Scaleasrequiredtofitthereportonthepage;increasingthescalewillchangethetextfont

sizeandshrinktheGanttCharthorizontalscale.

•Printtableonallpages.Whenuncheckedallowsjoiningofprintoutsthatarewiderthanonepagetobejoinedupasitwillonlyprintcolumnsonthelefthandsheet.

PageOrder•Pagesarenumberedintheorderselected.

12.4EnhancedPrintingfromtheEPSandActivitiesWindowsUnlikeolderversionsofP6,theVersionR8.3allowstheusertoprintfromeithertheEPSorActivitieswindowandprintonlytheProjectorActivityTableexcludingtheGanttChart,addingflexibilitytoproducetabularreports.Itisalsopossibletospecifyadaterangewhenprinting(orpreviewing)theGanttchart.

OntheActivitiespage,it’sallowedtochoosedatesoruserollingoptionstodefineadaterange.Moreover,thesamefunctionalityhasbeenaddedtothePrintPreviewwhereispossibletoexcludetheGanttChart.InP6R8.3,bothPrintPreviewandPrintincludeonlywhatisdisplayedonthescreen.

Page 218: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AvailableDateOptions:

•EarliestProjectStart

•EarliestProjectBLStart

•LatestProjectFinish

•LatestProjectBLFinish

•EarliestDataDate

•CurrentDate

•CustomDate

Rollingoptions:

•Days

•Weeks

•Months

•Quarters

•Years

Page 219: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Tousethisfunctionality:

•FromtheActionsmenuintheActivitiesorEPSwindowintheProjectssection,selectPageSetupor;

•Clickonthe PrintPreviewbuttononthetoolbarandthenclickonthe PageSetupbuttonintheform;

•UsethePrintRangeoptionslocatedintheSheettab.

Page 220: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

12.5ReportsReportsarerunfromthedashboardandarenotpartofthisbook:

Page 221: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

12.6OtherPrimaveraReportingOptionsThereareseveralotherseveralothertoolsavailablefromOraclethatmaybeusedgeneratePrimaverareports.

TheseincludeVisualizer,P6AnalyticsandBIPublisherwhicharenotcoveredinthisbook.

12.7Workshop10–Printing

BackgroundWewanttoissueareportforcommentbymanagement.

AssignmentOpenyourOzBuildBidprojectfromthepreviousworkshoptocompletethefollowingsteps:1.CreateaWorkshop10–Printingviewasperthepictureoverthepage.GroupbyWBS

anddisplaythefollowingcolumns:

ShowfirstcolumnasActivityName

ActivityID

PlannedDuration

Start

Finish

Page 222: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TotalFloat

2.Adjustyourtimescaletoweekandmonths.

3.Clickthe iconorselectActions,PrintPreviewtopreviewtheprintout:

TheauthorfoundthatthePrintPreviewforwasopenedasanewwindowinthebrowserbehindtheworkingviewandthereforehidden,youwillneedtochangewindowstoseetheprintpreview.UsetheAlt+Tabkeystochangewindows.

4.InthePageLayouttabselectLandscapeandpapersizetobeLetterorA4.

5.IntheHeader/Footertabsetasperthepictures:TheHeaderformisopenedwiththe button.

TheHeadertitleiscreatedusingthe&[File] option,

Theheaderissettoalargerfont,say16Bold,

Page 223: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheFooterformisopenedwiththe button,

ThecentersectioniscreatebytypingPage of ,

Therightsectioniscreatebyclickingofthetwoicons :

Page 224: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

6.IntheSheettabsetdaterangefromweekbeforetheprojectstarttotheweekaftertheprojectfinishtoallowsomespaceattheendsofthebars.

7.Compareyourresultwiththepicturebelow.

Page 225: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AnswerstoWorkshop9

Page 226: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13SCHEDULINGOPTIONSANDSETTINGABASELINETrackingProgressisusedafteryouhavecompletedtheplan,orhavecompletedsufficientiterationstoreachanacceptableplan,andtheprojectmaybeprogressing.Nowtheimportantphaseofregularmonitoringandcontrolbegins.Thisprocessisimportanttohelpidentifyproblemsasearlyaspossible,andthusminimizetheirimpactonthesuccessfulcompletionoftheproject.Themainstepsformonitoringprogressare:

•SavingaBaselineschedule,alsoknownasaTarget.Thisscheduleholdsthedatesagainstwhichprogressiscompared.Thecurrentprojectmaybecopiedandusedasabaselineoranexistingprojectmaybeassignedasabaseline.

•Recordingormarking-upprogressasofaspecificdate,titledtheDataDate.ThisdateisalsoknownastheStatusDate,UpdateDate,CurrentDate,ReportDate,andAs-Of-Date.

•UpdatingorProgressingtheschedule.

•SchedulingtheprojectandatthesametimemovingtheDataDatetothenewDataDateandrecalculatingalltheactivitiesdates.

•ComparingandReportingactualprogressagainstplannedprogressandrevisingtheplanandschedule,ifrequired.

Comparingthestatusofanactivityagainstmorethanonebaselineisuseful;forexample:

•TheoriginalplancouldberepresentedasoneoftheBaselines,toseetheslippageagainsttheoriginalplan.

•LastPeriod,whichcouldbeanotherBaseline,toseethechangessincethelastupdate.

Primaverahasthefollowingfunctions:

•Primaveraallowsanunlimitednumberofbaselineprojectfilestobesavedwithaproject.

•Abaselineprojectmaynotbeopenedandviewed.Itmustberestoredtothedatabasetoopenandeditwhereitwillthereforenolongerbeabaseline.

•ThetwoBaselinesmaybeshownagainstacurrentscheduleatonetimeeitherasbarsontheGanttChartorincolumnsofdata.

•BaselinecomparisonisdisplayedatActivitylevelintheActivitiesWindow,notatresourcelevel.

Onlysomebaselinedatamaybedisplayedincolumns.

TheWindowsClientallowsfourBaselinesbars,theWebClientonlytwo.

Shortcuts:

Topic MenuCommand

TosaveaBaseline,clickonthe DefineBaselineicontoopentheBaselinesform,then

Page 227: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

SavingandDeletingandSettingaBaseline

Clickonthe Addicontocreateacopyofthecurrentproject,or

Clickonthe ConvertaProjecttoaBaselineiconwhichwilltakeanotherprojectandmakeitintoaBaseline.

Clickonthe DeletetodeleteaselectedBaseline.

SettingaBaselineproject ThebaselinesareassignedfromBaselinesform.

13.1UnderstandingDateFieldsPrimaverahasmanymoredatefieldsforthecurrentschedulethanP3,SureTrak,AstaPowerprojectorMicrosoftProject.Thissectionexplainshowthesedatefieldscalculate.

Thereisverylittledocumentationavailableonhowthesedatesarecalculatedandtheauthorhasascertainedtheinformationcontainedinthischapterbytrialusinganunresourcedschedule.

Afteryouunderstandthesedatefields,youshouldlookagainattheBarTimescaleoptionsintheBarsformanditwillbeeasierforyoutounderstandhowthebarformattingworks.

13.1.1EarlyStartandEarlyFinishThesearealwaystheearliestdatesthatun-startedactivitiesortheincompleteportionsofin-progressactivitiesmaystartorfinishbasedoncalendars,relationshipsandconstraints.

•TheEarlyStartofthecompletedactivityA1000issettotheDataDatedateandtimeaftertheactivityhascommenced,nottotheActualStart,asinmostothersoftware,

•TheEarlyFinishofthecompletedactivityA1000issettotheDataDatedateandtimewhentheactivityiscomplete,nottotheActualFinish,asinmostothersoftware,

•TheEarlyStartofanin-progressactivityA1010issettotheActivityRemainingstartaftertheactivityhascommenced,nottotheActualStart,asinmostothersoftware.

NOTE:Lookcarefullyatbarsandthenthedates:•A1000,theEarlyStartandEarlyFinishareequaltotheDataDate,and

•A1010,theEarlyStartissettotheActivityRemainingEarlyStart:

ThustheEarlyStartandEarlyFinishdatesofcompletedactivitiesandEarlyStartofin-progressactivitiesisnotdisplayedinothersoftwareinthiswayandoftenleadstoconfusionwhenusersareconvertingfromothersoftware.

Page 228: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.1.2LateStartandLateFinish•Thesearethelatestdatesthatun-startedactivitiesortheincompleteportionsofIn-progress

activitiesmaystartorfinishbasedoncalendars,relationships,andconstraints.

•TheCompleteactivityhastheLateDatessetthedatethatisequivalenttothelatestpointintimethatthetaskcouldberestarted.

•TheTotalFloatontheCompleteTaskis“Null”butitstillshowsaFloatBar.

TheendoftheTotalFloatbaristhesamedateandtimeastheLateFinishandusedtocalculateTotalFloat.

13.1.3ActualStartandFinishThesedatesaremanuallyapplied,representingwhenanactivitystartedorfinished,andoverrideconstraintsandrelationships.ThesedatesshouldbesetinthepastinrelationtotheDataDate.

ActualdatesshouldneverchangeaftertheyareassignedbutboththeApplyActualswhenactivitiesaresettoAutoComputeActuals,andtheWindowsClientUpdateProgressfunctionsmaychangeActualDates.Thesefunctionsmustbeusedwithextremecaution.

13.1.4StartandFinishTheStartissettotheEarlyStartwhentheactivityhasnotstartedandtheActualStartwhenithasstarted.

TheFinishissettotheEarlyFinishwhentheactivityhasnotstartedorisin-progressandtheActualFinishwhenitiscomplete.•An“A”isplacedafterthedatewhenanActualStartorActualFinishhasbeenset,•An“*”isplacedafterthedatewhenastartconstrainthasbeenappliedtotheactivity,

•ThesedatefieldsallowtheEarlyandActualStartandFinishdatestobedisplayedasexpectedwhentheactivityhasnotstarted,isin-progress,orcomplete:

Page 229: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

UsersconvertingfromP3andSureTrakwillbeusedtodisplayingtheEarlyStartandEarlyFinishdates,buttheEarlyStartandEarlyFinishdatesshouldnotbedisplayedwhenaschedulehasprogress,asthiswillgivemisleadinginformation.TheStartandFinishdatesshouldalwaysbedisplayedundernormalschedulingconditions.

13.1.5PlannedStartandFinishThePlannedFinishiscalculatedfromthePlannedStartplusthePlannedDuration.ThePlannedDurationislabeledOriginalDurationinsomeWindowsClientIndustryVersions.Thesefieldsarealwayslinked,therefore:

•AchangetothePlannedStartwillchangethePlannedFinishviathePlannedDuration,•AchangetothePlannedFinishwillchangepermanentlythePlannedDuration,and•AchangetothePlannedDurationwillchangethePlannedFinish.

WhenanactivityhasNOTstarted:•ThePlanneddatesAREnormallylinkedtotheStartandFinishwhenanactivityhasnot

started.ThePlannedandAtCompletiondurationsareONLYlinkedwhenanactivityhasnotstartedandwhenLinkplannedandatcompletionfornotstartedactivitiesboxintheProjectsPreferences,Calculationstabischecked.

•TheyareNOTlinkedtotheEarlyDates.•APlannedStartmaybemanuallyeditedandastheStartdateislinkeditisalsochanged,

buttheEarlyStartisNOTchanged.ThePlannedStartandStartareresettotheEarlyDateswhenaprojectisscheduled.

•ThePlannedFinishmaybeeditedandislinkedtotheFinishdateandthePlannedDuration.AchangetothePlannedFinishwillchangetheFinishdateandPlannedDuration.ReschedulingwillrecalculatethescheduleusingthenewPlannedDurationandsetthePlannedFinish,Finish,andEarlyFinishtothesamedate.

•ThusachangetothePlannedStartisreversedbyrescheduling,butachangetothe

Page 230: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

PlannedFinishaffectsthePlannedDurationandisnotreversedbyrescheduling.Whenanactivityisin-progress:•ThePlannedStartdateremainsunchangedwhenanActualStartdateissetwhichis

differentfromthePlannedStart.ThereforethePlannedStartremainsthesameastheStartDatebeforetheActualStartwasset.

•ThePlannedFinishiscalculatedfromthePlannedStartDateplusthePlannedDuration.•Afteranactivityhascommenced,theRemainingDurationmaybeeditedindependently

fromthePlannedDuration.ThePlannedFinishmayhaveadifferentdatefromtheFinish,whichisnowsettoequaltheEarlyFinish.

Whenanactivityiscomplete:•ThePlannedDatesareunlinkedfromallotherdatefields.

13.1.6PlannedDatesIssuesThisisoneofthemostimportantparagraphsinthisbookandyoumustbecertainthatyouunderstandthePlanneddatesandhowtoavoidtheissuesassociatedwiththem.

ThePlannedDatesareverycomplextoexplainandunderstand,sopleasereadcarefully.Tosummarizethestatementsabove:

•WhenanactivityhasNotStartedthePlannedDatesmatchtheEarlyStartandEarlyFinish.

•WhenanactivityisCompleteorIn-progressthePlannedDuration,StartandFinishDatesaresettothestatusoftheactivityimmediatelybeforeitwasmarkedasStarted.

Inthesituationwhereascheduleisintheprocessofbeingupdated:

•AssumetheDataDatehasbeenmovedtothenewDataDateandtheprojectscheduled,

•Nowallun-startedactivitieswillhavetheirStartandFinishdatesinthefuture,

•AtthispointeveryactivitythatismarkedIn-progressbyassigninganActualStart(whichshouldbeinthepastinrelationtotheDataDate)willhavePlannedDatesthatNEITHER:MatchthestatusoftheactivitybeforetheactivitywasmarkedasStarted,nor

MatchthestatusoftheactivityaftertheactivitywasmarkedasStartedandpossiblyFinished.

ThusinthissituationandatthispointintimethePlannedDatesarenowholdingirrelevantdatesthatshouldneverbedisplayedorusedforanypurpose.

UnfortunatelythePlannedDatesareusedbydefaultinseveralplacesandDatabaseAdministratorsandUsersmustbeawareofwheretheyareusedandhowtoavoiddisplayingthem.

•ThePlanneddatesaredisplayedastheProjectBaselinebarsandPrimaryUser’sBaselinebarswhennobaselinehasbeenassigned,

Page 231: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

NeverdisplayaBaselineBarorcolumnsunlessabaselineprojecthasbeencreatedandassigned,otherwisetheBaselinebarandcolumnsmayrepresentirrelevantdata.

•ThesePlanneddatesareusedbytheApplyActualsfunction,whenactivitiesaresettoAutoComputeActuals,andtheWindowsClientUpdateProgressfunction.ThusActualStartdatesandEarlyFinishdatesofin-progressactivitieswillbechangedtothePlannedDatevalueswithoutwarning.

EnsureyounevereverusetheApplyActualsfunctiononaschedulethathasbeenprogressed,otherwiseActualStartdatesandEarlyFinishdatesofin-progressactivitieswillbechangedtothePlannedDatesvalueswithoutwarning.

•ThePlannedDatesfromaBaselineschedulewillbedisplayedastheBaselineBarswhentheAdminister,ApplicationSettings,EarnedValuetabissettoPlannedvalueswithplanneddates.ThustheBaselineBarsfromanin-progressschedulewillbeincorrect.

EnsureAdminister,ApplicationSettings,EarnedValuetabhasthisvaluesetasAtCompletionvalueswithcurrentdatesorPlannedValueswithcurrentdates.Whenthescheduleisnotresourceorcost-loadeditdoesnotmatterwhichofthesetwoyouuse.

13.1.7RemainingEarlyStartandFinishThesearetheearliestdatesthattheincompleteportionsofun-startedorin-progressactivitiesmaystartandfinish.

•Theyareblank(null)whenanactivityiscomplete.

•TheymaybeeditedinthesamewayasPlannedDates.

WhenaRemainingEarlyStartiseditedtoadatelaterthanscheduleddate,thereisanoptionforconstrainingtheRemainingEarlyStartwithaStartonorAfterConstraint.Ifthisisnotsetthentheactivitywillmoveforwardtoitsoriginalpositionwhenscheduling.

WhenaRemainingEarlyFinishisedited,theRemainingDurationisalsoeditedandthechangeispermanent.Schedulingdoesnottaketheschedulebacktotheoriginalposition.

Page 232: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.1.8RemainingLateStartandFinishThesearethelatestdatesthattheincompleteportionsofactivitiesmaystartandfinish.

•Theyareblankwhenanactivityiscompleteandmaynotbeedited,

•TheyaresettoequaltheLateDates.

13.2SchedulingOptions–GeneralTabWhenaprojectisrescheduledtherearesomeoptionsavailableintheScheduleProject,Optionsform,GeneraltabwhichisopenedbyselectingScheduler,Options:

Page 233: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Thereisno iconthatwillsettheoptionsbacktotheP6defaultsasintheWindowsClient.

•Thedefaultoptionsareusuallygooddefaultsbutsomeneedtobechangedtosuitspecificsituations.

•Theseoptionsapplytoallactivitiesinthecurrentlyopenedschedule.WhenopeningmultipleprojectsintheWebitcalculatesdifferentlytotheWindowsClient.TheWindowsClienthasaDefaultProjectoptionthatdoesnotexistintheWeb.

•IntheWebtooltheScheduleOptionsoftheprojectlistedatthetopoftheopenedprojectslist(whichwillrearrangewhenyouclosetheformtoanalphabeticallist)isusedtocalculateallprojectsand(unliketheWindowsClient)willnotchangetheScheduleOptionsoftheotheropenedprojects.ThusachangetoyourProjectIDopenedwithotherprojectsmayresultinaprojectcalculatingdifferentlyiftheprojectispusheddownthelistofopenedprojectsand

Page 234: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

whentheprojectatthetopofthelisthasdifferentSchedulingOptions.

•IntheWindowsClienttheScheduleOptionsoftheDefaultProjectareusedtocalculatealltheopenprojectsandtheScheduleOptionsfornon-defaultprojectsarethenchangedpermanentlytothoseoftheDefaultProject,sotheywillnevercalculatethesamewaywhenopenedontheirown.

•ChangingtheScheduleOptionsmaychangethewaytheschedulecalculatesandusersmustbeverycarefulifconsideringchanginganyofthem.Youmaywishtocopytheschedule,baselineit,andthenchangetooptionstoseewhattheeffectisontheschedulecalculation.

SettingaProjectScheduleServicetoschedulemultipleprojectsallowsthenominationofUsethisproject’ssettingsoption.

13.2.1Ignorerelationshipstoandfromotherprojects(&IgnoreExternalDates)Checkthistoignorerelationshipswithotherprojectsthatarecurrentlynotopen.

Theserelationshipsmaybecreatedbetweentwoprojectswhentwoormoreprojectsareopenedtogether.

ThisoptionwillalsoignoreExternalDates,whicharetheExternalEarlyStartandExternalLateFinishdates.ExternalDatesareconstraintscreatedwhenaprojectisexportedfromPrimaveraContractorand/oranotherP6databaseandimportedintoP6.TheyactlikeEarlyStartandLateFinishConstraintsandareusedtorepresenttherelationshipsthatwouldhaveoriginallyprovidedtheEarlyStartandLateFinishdatestotheCriticalPathcalculationsoftheimportedschedule.

Thesedatescanbeveryconfusingifoneisnotawarethattheyhavebeencreatedorhowtheyoperate.Thenegativefloatinthepicturebelowiscreatedbythesedatesafteranactivity’sdurationwasincreasedby34days:

WhenyouimportaprojectfromanotherdatabaseensureyouALWAYScheckforExternalDatesandunderstandhowtheyoperate.IfyouexportandthenimportbackintothesamedatabasethenExternaldatesarenotnormallycreatedbuttherelationshipsarere-establishedwiththeoriginalscheduletheywerelinkedwith.

Ontheotherhand,iftheoriginalscheduleshavebeendeletedthentheseExternalDatesmaybecreated.

Page 235: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.2.2Makeopen-endedactivitiescriticalAnopen-endedactivityisanactivitywithoutasuccessorandwhichhasfloattotheendoftheproject.Checkingtheboxmakestheseactivitiescriticalwithzerototalfloatwhentheydonothaveasuccessor.

•Open-endsNotCritical:

•Open-endsCritical:

Thisalsoallowstheusertodisplaymultiplecriticalpathsinoneprojectwithouttheuseofconstraintsandisusefulshouldyouwishtoseetheindividualcriticalpathsforeachareaofaproject.Inorderforthisfunctiontoworkthelastactivityineachchainoreventsmustnothaveasuccessor:

•Open-endsNotCritical:

•Open-endsCritical:

Page 236: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.2.3UseExpectedFinishDatesTheintentionofthisoptionisforpeopleusingtimesheetstobeabletosetanExpectedFinishconstraintforanactivity.

OnceanExpectedFinishdateissetthenthesoftwarecalculatestheRemainingDurationfrom:

•TheEarlyStartwhenanactivityhasnotstarted,or

•TheDataDatewhenanactivityhasstarted,or

•AResumedateifaSuspendandresumedatehasbeenset.

ThereforeExpectedfinishdatesmaybeassignedfromtheTimesheetsmoduleandthisoptionallowstheprojectmanagertoignorethesedatessubmittedwiththetimesheets.

ThisisalwayscheckedbydefaultandwilldisableorenableExpectedFinishconstraintsassignedintheGeneraltaboftheActivitiesDetailstaborfromacolumn.ThisisusuallynotturnedoffandthepicturesbelowshowtheeffectofthisconstraintbeforeandafterschedulinganactivitywithanExpectedFinishConstraintassigned:

•Beforescheduling:

•Afterscheduling:

13.2.4Scheduleautomaticallywhenachangeaffectsdates–NotintheWebClient

Page 237: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThisissimilartoautomaticrecalculationinotherproductsandthisrecalculatestheschedulewhendatathataffectsthetimingofthescheduleischangedandisnotavailableintheWebClient.

P6isadatabaseproductandScheduleAutomaticallyintheWindowsClientwillresultintheschedulerecalculatingeverytimeyoumakeachange.Thismayslowdownyourworksignificantly;thisoptionisusuallyleftoff.

13.2.5LevelresourcesduringschedulingLevelingascheduledelaysactivitiesuntilresourcesbecomeavailable.Thisisaformofresourceoptimizationandthisoptionlevelstheprojectresourceseachtimeitisscheduled.ResourcelevelingiscoveredintheProfessionalandOptionalClientbook.

ThisisNOTrecommendedasitslowsdowntheschedulecalculationandthescheduleoftenchangeseachtimeitisscheduled.

Itisusuallybettertousesequencingrelationshipstolevelaschedule.

13.2.6RecalculateassignmentcostsafterschedulingResourceUnitRatesmaybesettochangeovertimeintheUnitsandPricestaboftheAdministration,ResourcesWindowlowerpane:

Thisoptionrecalculatesaresourcecostwhenaresourceisscheduledintoadifferentcostratestimebracket.

Page 238: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.2.7Whenschedulingprogressedactivitiesuse“OutofSequenceProgress”occurswhenanactivitystartsbeforeapredecessordefinedbyarelationshiphasfinished.Thereforetherelationshipshavenotbeenacknowledgedandthesuccessoractivityhasstartedoutofsequence.TherearethreeoptionsinP6forcalculatingthefinishdateofasuccessorwhenthesuccessoractivityhasstartedbeforethepredecessoractivityisfinished:

•RetainedLogic

•ProgressOverride

•ActualDates

Theselectedoptionisappliedtoallactivitiesinaschedulewhenitiscalculated.OpentheScheduleOptionsform,GeneraltabbyselectingSchedulerandclickingonthe,Options

iconwheretheoptionsarefoundunderWhenschedulingprogressedactivitiesuse:

Thepicturebelowrepresentsthestatusoftheactivitiesbeforeupdatingtheschedule:

•RetainedLogic.Intheexamplefollowing,therelationshipismaintainedbetweenthepredecessorand

successorfortheunworkedportionoftheactivity(theRemainingDuration)andcontinuedafterthepredecessorhasfinished.Therelationshipformspartofthecriticalpathandthepredecessorhasnofloat.

NOTE:Thisistherecommendedoption:

TheWindowsClientpictureisclearerinshowingtheresult:

•ProgressOverride.

Page 239: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Intheexamplefollowing,theFinish-to-Startrelationshipbetweenthepredecessorandsuccessorisdisregarded,andtheunworkedportionoftheactivity(theRemainingDuration)continuesbeforethepredecessorhasfinished.NOTE:TherelationshipisnotadrivingrelationshipandDOESNOTformpartofthecriticalpathintheexamplebelowandthepredecessorhasfloat:

TheWindowsClientpictureshowsasimilartheresult:

•ActualDates.ThisfunctionoperateswhenthereisanactivitywithActualStartDatesinthefuture,whichisnotlogical.Withthisoptiontheremainingdurationofanin-progressactivityiscalculatedaftertheactivitywithactualstartandfinishinthefuture:

TheWindowsClientpictureisclearerinshowingtheresult:

WhentherearenoActualDatesinthefuturethisoptioncalculatesasRetainedLogic.

ThissituationwithActualsinthefuturemayhappenwhentwoprojectsopentogetherandhavedifferentDataDates.ThissituationisbestavoidedanditisbettertomakealltheDataDatesofallprojectsthesame.

RetainedLogicandProgressOverridearenottermsusedbyMicrosoftProjectbutareusedinP3andSureTrakandoperateinthesamewayinPrimavera.MicrosoftProjectusesthetermSplitinProgress.

RetainedLogicproducesamoreconservativeschedule(alongerduration

Page 240: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

schedule)andismorelikelytoplaceanout-of-progressrelationshiponthecriticalpathandadjustmentsmaybemadeasrequired.

IfyourschedulehasActualdatesinthefutureoftheDataDate(whichmayoccurwhentheupdateinformationiscollectedatdifferenttimesandtheearlierdateisusedastheDataDateormultipleprojectsareopen)thentheuseofActualDateswouldcalculatethemostconservativeschedule.

13.2.8Calculatestart-to-startlagfromThesuccessorofanactivitywithaStart-to-Startandpositivelagwouldstartafterthelaghasexpired.WhenthepredecessorcommencesoutofsequencethelagmaybecalculatedfromthepredecessorcalculatedEarlyStartortheActualStart.

•TheActualStartgivesalessconservativeschedule:

TheWindowsClientpictureisclearerinshowingtheresult:

•TheEarlyStartgivesamoreconservativeschedule:

TheWindowsClientpictureisclearerinshowingtheresult:

13.2.9DefinecriticalactivitiesasCriticalActivitiesDefinitioncriteriaisdefinedintheScheduleProject,Optionsform:

Page 241: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Theseoptionsareusedforanalyzingschedulesthatutilizemultiplecalendarswhichmayresultinactivitiesonthecriticalpathpossessingfloat.

•TotalFloatlessthanorequalto–Activitiesmaybemarkedascriticalandwithachosenfloatvalue.Sometimesasmallpositivevalueisusedtoisolatethenearcriticalactivitiesonschedulesordisplayingthefullcriticalpathonmultiplecalendarschedules.

•LongestPath–Thisoptionisolatesthelongestchainofactivitiesinascheduleandshouldbeusedwhenmultiplecalendarsareinuseandsomeactivities,whichformpartofthecriticalpath,stillhavefloatwhenthesuccessorisassignedacalendarwithfewerordifferentworkingdays.

•IntheexamplebelowtheTotalFloathasbeensettoTotalFloatlessthanorequaltozeroandthecriticalpathhasdisappeared:

•WhentheTotalFloatisthensettolessthanorequalto1dayresultsinthepicturebelow:

•WhentheTotalFloatisthensettoLongestPathresultsinthepicturebelow:

Longestpathisrecommendedforprojectswithmultiplecalendars.

13.2.10CalculatefloatbasedonfinishdateThisisanewfunctiontoVersion6.2.WhenmorethanoneprojectisopenedtheTotalFloat

Page 242: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

maybecalculatedbasedoneachindividualprojectorthelongestproject:

•Eachproject–usedwheneachproject’scriticalpathisrequired:

•Openedprojects–usedwhenalltheP6projectsarerelatedandfloatisrequiredtobebasedonthelongestproject:

Page 243: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.2.11ComputeTotalFloatasTherearethreeoptionsforthecalculationoftheFloatvaluedisplayedintheTotalFloatcolumnofWBSandLOEactivitiesonly:

•StartFloat=LateStart–EarlyStart

•FinishFloat=LateFinish–EarlyFinish

Page 244: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SmallestofStartFloatandFinishFloatItcanbeseenfromthepicturesabovethattheTotalFloatbaronlydisplaystheFinishFloat.

TheSmallestofStartFloatandFinishFloatisthemostconservativebuttheFinishFloatwillalwaysgiveananswerthatisthesameastheTotalFloatbar.

13.2.12CalendarforschedulingRelationshipLagTherearefourcalendaroptionsforthecalculationofthelagforallactivities:

1.PredecessorActivityCalendaristhedefault.Theexamplebelowhasa40-hourlag,or5daysasthelagcalendaris8hourperday:

2.SuccessorActivityCalendar,notethechangeinthesuccessorstartdateasthelagcalendaris24hoursperdaysor1.66day:

3.24-Hour,or4.ProjectDefaultCalendar.

P3andSureTrakusethepredecessorcalendar,MicrosoftProject2000and2002usestheProjectBasecalendar,andMicrosoftProject2003to2010usesthesuccessorcalendar.MicrosoftProjectalsohastheoptionofanElapsedlagduration.AstaPowerprojectdoesnotassignlagstotherelationshipbutarelationshipmaybeassignedalagonthepredecessoractivityandalagonthesuccessoractivity,whichismorelogical.

13.2.13SchedulingOptions–AdvancedTabThistabselectstheoptionsforcalculatingmultiplecriticalpathsandiscoveredindetailintheUtilitieschapteroftheProfessionalandOptionalClientbook.

13.3SettingtheBaselineSettingtheBaselinemakesacompletecopyofaproject,includingrelationships,notebookentriesandcodes.Youarethenabletocomparethecurrentproject’sprogressagainstthebaseline.

TherearetwotypesofBaselinesthatareoftensavedwithschedulingsoftwaresuchasP6–

Page 245: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ManagementandLastPeriodStatus:

ManagementBaselinesTheseareusuallyacopyofanoriginalunprogressedschedulethathasbeencontractuallyagreedtoastheBaselineorTargetscheduleandareusedto:

•EvaluateprogressandreportprogresstoaClientorcustomer,

•ProvideabaseforExtensionofTimeclaimsandothercontractualclaimsthatmaybemadebasedontheseBaselineschedules.

LastPeriodStatusBaselinesThesearecopiesofascheduleatapointintimeandareusedforthemanagementofaproject:

•Usuallytheyareusedtomeasurethelossintimefromonereportingperiodtoanother,

•Theyallowmanagementtoascertainperformanceandmakedecisionsonhowtomanagetheproject,

•TheyaredisplayedinexactlythesamewayasManagementBaselineswiththesoftware,

•TheseBaselinesusually,afterthefirstperiodupdate,haveprogress.

Upto50baselinesperprojectmaybesavedinadatabaseinearlierversionsbutinVersion6.0andlateranunlimitednumbermaybesaved.

Thereisstillarestrictionofcopyingamaximumof50Baselineswhencopyingaproject.

•ThenumberofbaselinesthatmaybesavedissetintheAdminister,ApplicationSettings,DataLimitsformbyselectingAdminister,ApplicationSettings,DataLimitsandsettingthenumberintheMaximumbaselinesperprojectbox.

•ThenumberofbaselinesthatmaybecopiedwhencopyingaprojectissetintheDataLimitsformbyselectingAdminister,ApplicationSettings,DataLimitsandsettingthenumberintheMaximumbaselinescopiedwithprojectbox.

•Twobaselines,oneProjectBaselineandoneUserBaselines,maybedisplayedandcomparedtothecurrentproject.TheWindowsClientmaydisplay4Baselines.

Ifanotheruseropenstheproject,theywillonlyseetheoneProjectBaselineandnottheUser’sBaselinesetbyanotheruser.

•Abaselineprojectmayberestoredbackintoadatabaseasanormalproject.Thenitmaybeeditedandresavedasabaselineproject.

AftertheBaselineisset,itispossibletocomparetheprogresswiththeoriginalplan.Youwillbeabletoseeifyouareaheadorbehindscheduleandbyhowmuch.TheBaselinescheduleshouldbeestablishedbeforeyouupdatethescheduleforthefirsttime.

Page 246: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.3.1CreatingaBaselineTocreateaBaseline,ensuretheprojectisopenandselectProject,ActivitiesWindow,selectActions, DefineBaselinestodisplaytheBaselinesform:

•Tocreateanewbaselineclickthe Addicon,•Clickthe CopyicontocreateacopyoftheselectedbaselineprojectasanewBaseline,

•Clickthe ConvertaprojecttoBaselinewillopentheSelectProjectformwhereanotherprojectmaybeselectedtobeabaseline.ThisprojectwillthenmovefromthecurrentprojectswindowintotheBaselinesformandisnotavailabletobeopenedfromtheProjects,EPSWindow.

•Clickthe Saveicontosaveallchanges,

•Clickthe Cancelicontoignoreallchanges.

Youmayhavetoclosetheformandreopentorefreshthedatainthisform.

13.3.2DeletingaBaselineTodeleteaprojectbaselinefromthedatabase:

•OpentheBaselinesform,•Selectthebaselineprojecttobedeleted,and

•Clickthe DeleteicontodeleteaBaseline.

13.3.3RestoringaBaselinetotheDatabaseasanActiveProjectTorestoreaprojectbacktothedatabasesoitmaybeeditedorusedasacurrentproject:

•OpentheBaselinesform,•EnsurethebaselineisnotassignedasanybaselineintheBaselinesform,•Selectthebaselineprojecttoberestored,and

•ClickontheRestore icon.

Page 247: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.3.4UpdateBaselinesTheWindowsClientUpdateBaselinefunctionwasaddedtotheWebinVersion8.4.ThisallowsthemodificationofanexistingBaselinewithnewofchangeddatafromthecurrentscheduleasanalternativetocreatinganewbaseline.

ToUpdateaBaseline:

•SelecttheEPSorActivitiesPage,ActionsmenuDefineBaselines,•SelectabaselineBaselinesform,and

•ClickontheUpdateBaselineicon.

13.3.5CopyingaProjectwithBaselinesYoumaycopybaselineswhenaprojectiscopiedintheEPSWindowusingCopyandPastebytickingtheappropriateboxes.

Page 248: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.3.6SettingtheBaselineProjectToassignaProjectBaselineorUser’sPrimaryBaseline:•OpentheBaselinesform,•Selectthebaselineprojecttobeassigned,

•SelecttherequiredProjectBaselineorUser’sPrimaryBaselinefromtheappropriatecolumnsdropdownbox,

•BaselineTypesareoptionalandaredefinedintheAdminister,EnterpriseDataform,BaselineTypetab:

•TheProjectBaselineorUser’sPrimaryBaselinemaybeusedforcalculatingEarnedValue.SeeAdminister,ApplicationSettings,EarnedValuetabforotherEarnedValueoptions.ThisBaselineisseenbyanyUserwhoopenstheproject.

SecondaryandTertiaryUserBaselinesintheWindowsClientarenotavailableintheWeb.

Page 249: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheUser’sPrimaryBaselineareonlyseenbytheUserwhohassettheBaseline.Sootheruserswhoopenaprojectandapply,forexample,aProjectViewthatdisplaysaUserBaseline,willhavetoalsomakesurethattheysetthesamebaselineastheoriginaluser.

•EarnedValuecalculationsmaybeperformedusingeitherthePrimaryBaselinevaluesortheUser’sPrimaryBaselinevaluesfromthecurrentproject.SelecttheSettingstabintheProjects,EPSWindow,Actions, SetProjectPreferences:

•TheAdminister,ApplicationSettings,EarnedValuetab,Earnedvaluesectionhasthreeoptions.ThisoptiondecideswhichBaselineschedulevaluesarereadtocalculatetheEarnedValuefieldsandwhichbarsaredisplayedasBaselineBars.TheAtCompletionvalueswithcurrentdatesistheauthor’spreferredoptionwhenresourcesareassigned.

WhenthePlannedvalueswithplanneddatesisselected,whichisoftenthedefaultvaluewhenthesoftwareisloaded,thenthePlannedDatesaredisplayedasabaselinebar.Thisisundesirablewhenaprogressedscheduleisdisplayedasa

Page 250: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Baseline,say,forcomparingthisperiod’sdatevalueswithlastperiod’sdatevalues.ThisisbecausethePlannedDatesoftenholdirrelevantdatawhenaBaselineschedulehasprogress.

13.3.7Understandingthe<CurrentProject>BaselineBecausePlannedDatesaredifficulttounderstandandmayleadtomisinterpretationoftheschedulebaselines,itisimportantthatyouunderstandthefollowingpoints:

•ThePlannedDatesareusedbythe<CurrentProject>BaselineintheDefineBaselineform.

•The<CurrentProject>BaselineisthedefaultbaselineforboththeProjectBaselineandPrimaryUser’sBaseline.

•WhenNObaselinehasbeensetbyauserthenthe<CurrentProject>BaselineandthereforethePlannedDatesaredisplayedastheBaselineBars.

•The<CurrentProject>Baselineisnotatruebaseline,thedatesmaychangeeachtimeascheduleisupdatedandmayholdirrelevantdatainaschedulethathasbeenprogressed.

•ThetermCurrentProjectisnormallyusedtodescribetheactivitiesastheyarecurrentlyscheduled,andtheterm<CurrentProject>BaselineisconfusingasitisnottheCurrentProjectbutthePlannedDates,whichmaybedifferentfromthenormallyacceptedCurrentProject.

Thefollowingpicturehasthreebars:

•TheupperbarrepresentstheStartandFinishdates:

TheStartdateissettotheEarlyStartwhenanactivityhasnotstartedandActualStartwhentheactivityhasstarted.

TheFinishdateissettotheEarlyFinishwhenanactivityhasnotfinishedandActualFinishwhentheactivityiscomplete.

•Themiddlebaristhe<CurrentProject>baseline,thePlannedDates,and•ThelowerbarisaproperProjectBaselinemadebycopyingtheun-progressedproject.Withnoprogressallbarsarethesame,seepicturebelow:

Page 251: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Inthefollowingpicture:

•Activity1hasbeenmarkedcompleteandtheDataDatemoved.•ThePlannedDatesforActivity1equaltheStartandFinishdatebeforetheactivitywas

markedasstarted.

•Theun-startedactivities,Activity2and3,inthe<CurrentProject>baselinewhichrepresentthePlannedDateshavechangedtheirdatestoequaltheStartandFinish,seepicturebelow:

Inthefollowingpicture:

•Activity2hasnowbeenmarkedin-progressandtheDataDateNOTmoved.

•NowActivity2PlannedDates(representedbythe<CurrentProject>baseline)matchthestatusoftheactivitybeforeitwasmarkedStarted,notaBaseline.ThisactivityPlannedDatesnowdisplayirrelevantdata,

•Activity3PlannedDatesrepresentedbythe<CurrentProject>baselinebarshavechangedasecondtimeandmatchthenewStartandFinish:

WhennoBaselineissetbytheuser,theprojectwillDISPLAYthe<CurrentProject>fromthePlannedDates,notthecurrentprojectStartandFinishdates)astheBaselinebarsand,ineffect:

Allun-startedactivitiesareeffectively“re-baselined”ateachscheduleupdate,and

StartedandCompleteactivitiesPlannedDatesmatchtheStartandFinishdatesoftheactivityjustbeforeanactivitywasmarkedasstarted.Therefore,thePlannedDatesoftheseactivitiescouldcontainirrelevantdata.ThishappenswhenaprojecthasbeenrescheduledandtheDataDatemovedforwardandthenactivitiesmarkedasStarted.AtthispointthePlannedDatesnowdonotrepresentaBaseline,thelastperiodstatusorthenextperiodstatusofanactivity.Theycontainirrelevantdatathatshouldneverbedisplayed,asperthepictureabove.

Page 252: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thisisgenerallynotacceptedasagoodpractice.Therearesomesignificantissuesherethatneedtobecarefullymanaged:

•IfnoBaselineissetandaviewthatdisplaysabaselinebarisapplied,thenabaselinebarmaycontainirrelevantdatesfromthePlannedDateswillbedisplayed.Thismaycreateconfusionandthesebarsmaychangeoneachscheduleupdate.

•IfoneusersetsaPrimaryUser’sBaselineandthereforeonlyseenbythatuser,andadifferentuseropensaproject,thenthisseconduserwillseeonlythe<CurrentProject>baselineandnottheotherPrimaryUser’sBaseline.Thiswillresultinoneuserseeingsomethingdifferentfromanotheruserwhentwousersopenaproject.

Youmaywishtorestricttheaccesstoaprojectscheduletopreventthe<CurrentProject>baselinebeingdisplayedinadvertently.

13.3.8DisplayingtheBaselineDataTheBaselineDatesmaybedisplayedby:

•DisplayingtheBaselinecolumns:

BListheProjectBaselineBL1istheUserPrimaryBaseline

•ShowingabaselinebarontheBarChartbyselectingtheappropriatebarsintheCustomizeGanttChartOptionsform,Barstab:

Page 253: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheWindowsClientBL2,theSecondaryUserBaselineandBL3,theTertiaryUserBaselinemaynotbedisplayedintheWebClient.

13.4AdditionalBaselineFields

P6R8.3hasaddedextrabaselinefieldsintheCustomizeColumnsformtobedisplayedontheActivitieswindowafterabaselinehasbeenassignedtoaproject.

Thenewfieldsareavailablefortheprojectbaseline(BL)anduser'sprimarybaseline(BL1):

•ActualExpenseCost

•ActualLaborCost

•ActualMaterialCost

•ActualNonlaborCost

•ActualTotalCost

•ActualStart

Page 254: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ActualFinish

•EarlyStart

•EarlyFinish

•LateStart

•LateFinish

•ActualDuration

•RemainingDuration

•FreeFloat

•TotalFloat

•ActivityStatus

•Activity%Complete

•Cost%Complete

•Duration%Complete

•%CompleteType

•Units%Complete

•ActualLaborUnits

•ActualNonlaborUnits

Toaccessthisfunctionality:

•IntheActivitieswindowontheProjectssection,gotoViewandselectColumnsor;•Clickonthe Columnsbuttonlocatedinthetoolbar.

Page 255: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.5Workshop11–WBS,LOEsandSettingtheBaseline

BackgroundWewillfirstlookathowWBSandLOEactivitiesworkandthensetaBaseline.

Assignment–WBSActivityOpenyourOzBuildBidprojectfileandcompletethefollowingsteps:1.ApplytheWorkshop6Dates&Durationview,checkthecolumnsareasperthepicture

below,

2.DisplaytheFloatBarastheSecondbar,inblackwithaheightof4,3.CreateanewactivityundertheBidDocumentWBSNode,IDOZ1140titledWBS

Activity,4.AssignitanActivityTypeofWBSSummaryusingtheActivitiesWindow,Generaltab.5.SaveandpressF9toScheduletoseehowitcalculates.

Page 256: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

6.MovetheWBSActivitytotheDeliveryPlanWBSNodebycopyingandpastingandscheduletoseehowitoperates.

7.MovetheWBSActivityusingCutandPastetotheTechnicalSpecificationWBSNodeandschedule:

8.GototheScheduler(F9),OptionsformandchangetheComputeTotalFloattoStartFloat:

9.ScheduleandyouwillseethatthefloatvalueisnowthesamevalueastheStartFloat,buttheFloatBarstillshowstheFinishFloatValue:

10.GototheSchedulingOptionsformandchangetheComputeTotalFloattoFinishFloatandschedule.

Assignment–LOEActivity11.ChangetheWBSActivityTypetoaLevelofEffortandrenameittoLOEActivity,12.DonotschedulewithaLOEactivityunlessithasrelationships.Ifyoudoscheduleitwill

calculatetoazerodurationandbemarkedasCompleteontheDataDate.YouwillthenhavetomarkitasnotstartedintheActivitiesWindow,GeneraltabandassignadurationsoyoucanseeitontheGanttChart.

13.MoveOZ1140totheDeliveryPlanWBSNodeandsortonActivityID,

Page 257: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

14.AddOZ1060SSOZ1140predecessorandOZ1140FFOZ1070successorrelationshipsandseehowitcalculates.

EnsureyouopenthePredecessorandSuccessorwindowsandthereareonlyonepredecessorandonesuccessor.

15.AddOZ1050SSOZ1140predecessorandOZ1140FFOZ1110successorrelationshipsandseehowitcalculates.

16.DeletetheLOEactivity.

Assignment–SettingaBaseline17.SelectProject,ActivitiesWindow,selectActions, DefineBaselinestodisplaythe

BaselinesformandclickonAddtosaveacopyofthecurrentprojectasaBaselineandtitleitBidforFacilityExtension–Baseline.

18.AssignanappropriateBaselineType,suchasCustomerSign-Off,(theoptionsmayvarydependingonyourdatabase).

19.MakethisyourProjectBaselineandUser’sPrimaryBaselineandclosetheBaselinesform.BysettingbothBaselines,thisensuresthatanybaselinebarwillshowarealbaselineandnotthePlannedDates.

20.SaveandclosetheBaselinesform.

Page 258: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

21.HidetheFloatBaranddisplaytheProjectBaselinebar,sayinyellowand8high.22.Displaythefollowingcolumns:

Showfirstcolumnas–ActivityName

ActivityID

Activity%Complete

PlannedDuration

RemainingDuration

Start

Finish

TotalFloat

VarianceBL–ProjectFinishDate

23.MakesuretheTimescaleisMonth/Week.24.Showthetimein24-hourformat,butdonotshowtheminutesbyselectingAdminister,

MyPreferences,Datestab.25.SaveyourviewasWorkshop11–BaselineComparison.26.Checkyouranswerbelow:

Page 259: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 260: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

14UPDATINGANUNRESOURCEDSCHEDULENowthattheBaselinehasbeensetwecanstarttrackingprogressandtheimportantphaseofregularmonitoringandcontrolbegins.Thisprocessisimportanttohelpcatchproblemsasearlyaspossible,andthusminimizetheirimpactonthesuccessfulcompletionoftheproject.Themainstepsformonitoringprogressare:

•SavingaBaselineschedule,coveredinthelastchapter,•Recordingormarking-upprogressattheDataDate.•UpdatingorProgressingtheschedule:

CompletedactivitiesareassignedActualStartandActualFinishdates,In-progressactivitiesareassignedActualStartdates,andtheactivity’sRemainingDurationsandPercentCompletesareadjusted,

Adjustmentsaremadetoun-startedworkbasedontheproductivityto-date,and

Projectscopechangesshouldbeaddedasnewactivities.

•SchedulingtheprojectandatthesametimemovingtheDataDatetothenewDataDateandrecalculatingalltheactivitiesdates.

•TheDataDatemayalsobemovedbeforeupdatingtheactivitiesfromtheEPSWindow,DataDatecolumnintheupperpaneortheEPSWindow,Generaltabinthelowerpane.

•ComparingandReportingactualprogressagainstplannedprogressandrevisingtheplanandschedule,ifrequired.

Comparingthestatusofanactivityagainstmorethanonebaselineisuseful;forexample:

•TheoriginalplancouldberepresentedasoneoftheBaselines,toseetheslippageagainsttheoriginalplan.

•LastPeriod,whichcouldbeanotherBaseline,toseethechangessincethelastupdate.

Bythetimeyougettothisphaseyoushouldhaveaschedulethatcomparesyouroriginalplanwiththecurrentplan,showingwheretheprojectisaheadorbehind.Ifyouarebehind,youshouldbeabletousethisscheduletoplanappropriateremedialmeasurestobringtheprojectbackontarget.

Shortlistofcommands:

Topic MenuCommand

ProgressSpotlight ClickontheSpotlight icontomovetheSpotlightforwardorbackwardsoneminortimescaleincrement.

SuspendandResume YoumustdisplaytheappropriatecolumnstoentertheSuspendandResumedates.

SettingtheCurrentDataDateOpentheSchedulerformby:

Page 261: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

andSchedulingtheproject •SelectingScheduler iconor

•PressingtheF9key.

14.1PracticalMethodsofRecordingProgressNormallyaprojectisupdatedonceaweek,bi-weekly,ormonthly.Veryshortprojectscouldbeupdateddailyorevenbytheshiftorhour.Asaguide,aprojectwouldtypicallybeupdatedbetween12and20timesinitslifetime.Ahighriskprojectshouldbeupdatedmoreoftenthanalowriskproject.ProgressisrecordedonorjustaftertheDataDateandtheschedulerupdatesthescheduleuponthereceiptoftheinformation.

Thefollowinginformationistypicallyrecordedforeachactivitywhenupdatingaproject:

•Theactivitystartdateandtimeifrequired,

•Thenumberofdaysorhoursrequiredtocompletetheactivityorthedateandtimetheactivityisexpectedtofinish,

•Thepercentagecomplete,and

•Ifcomplete,theactivityfinishdateandtime.

Aprintoutoftheschedulemaybeusedforrecordingtheprogressofthecurrentscheduleandisoftenproducedpriortoupdatingtheproject.Ideallyprogressshouldberecordedbyaphysicalinspectionoftheworkorbyapersonwhointimatelyknowsthework,althoughthatisnotalwayspossible.Itisgoodpracticetokeepthismarked-uprecordforyourownreference.EnsurethatyounotetheDataDateofthemark-upand,ifrelevant,thetime.

OftenaStatusReportormark-upsheet,suchasthefollowingillustration,whichhasa4-weeklook-aheadfilterapplied,isdistributedtothepeopleresponsibleformarkinguptheprojectprogress.Themarked-upsheetsarereturnedtotheschedulerfordataentryintothesoftwareandthenfiledfordisputeresolution.

Apagebreakcouldbeplacedateachresponsibleperson’sbandintheCustomizeGroupingform,andwhenthescheduleisprintedeachpersoncouldhavetheirownpageofactivitiesthatareeitherin-progressorduetocommence.Thisisparticularlyusefulforlargeprojects.

Otherelectronicmethods,discussednext,maybeemployedtocollectthedata.Irrespectiveofthemethodused,thesamedataneedstobecollected.

Thereareseveralmethodsofcollectingdatafortheprojectstatus:

•Bysendingaprintedsheettoeachresponsiblepersontomarkupbyhandandreturntothescheduler.

Page 262: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ByexportingthedatafromPrimaveraintoanotherdocument,suchasExcel,andE-mailingthedocumenttothemasanattachment.

•Bygivingtheresponsiblepartydirectaccesstotheschedulesoftwaretoupdateit.Thisapproachisnotrecommended,unlesstheprojectisbrokenintosub-projects.Byusingmultipleprojectswithonescheduleraccessingeachproject,orassigningaccessthroughWBSNodes,onlyonepersonupdateseachpartoftheschedule.

•WhenthePrimaveratimesheetshavebeenimplementedthisprocessmaybeusedtoupdatetheactivitiesorotherelectronicmethods.

Someprojectsinvolveanumberofpeople.Insuchcases,itisimportantthatproceduresbewrittentoensurethattheupdateinformationiscollected:

•Inatimelymanner,

•Consistently,

•Completely,and

•Inausableformat.Itisimportantforaschedulertobeawarethatsomepeoplehavegreatdifficultyincomprehendingaschedule.Whenthereareanumberofpeoplewithdifferentskilllevelsinanorganization,itisnecessarytoprovidemorethanonemethodofupdatingthedata.Youevenmayfindthatyouhavetositdownwithsomepeopletoobtainthecorrectdata,yetothersarewillingandcomfortabletoe-mailyoutheinformation.

14.2UnderstandingtheConceptsTherearesometermsandconceptsusedinschedulingandsomethatarespecifictoPrimaverathatmustbeunderstoodbeforeupdatingaprojectschedule.

Usersmustalwaysdisplaythetimewhenupdatingaproject,otherwisethetimeof00:00issometimesselectedbyP6astheStartorFinishtimewhichisusuallynotdesirable.

14.2.1ActivityLifecycleTherearethreestagesofanactivitylifecycle:

•NotStarted–TheEarlyStartandEarlyFinishdatesarecalculatedfromthePredecessors,Constraints,andActivityDuration.

•In-Progress–TheactivityhasanActualStartdatebutisnotcomplete.AssigninganActualStartdateoverridestheStartConstraintsandStartRelationshipswhichareusedtocalculatetheEarlyStart.

TheenddatemaybecalculatedfromtheRemainingDurationoraFinishConstraintoraFinishRelationship.

•Complete–Theactivityisinthepast,theActualStartandActualFinishdateshavebeenenteredintoPrimavera,andtheyoverridealllogicandconstraints.

Page 263: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

14.2.2AssigninganActualStartDateandTimeofanActivityThissectionwillexplainhowPrimaveraassignstheActualStartofaCompleteoranIn-Progressactivity.ThisdateoverridestheEarlyStartdate.•ActualStartdateisassignedintheActualStartfieldbycheckingtheStartedcheckbox,

or

•EnteringadateintheActualStartcolumn.

•TheactivityActualStartdateissettoequaltheStartdatewhenthisboxischecked.•TheActualStartdatecalendarisopenedbyclickingonthe icontotherightofthe

Startedcheckboxandadifferentstartdatemaybeassigned.ThisdateshouldnotbeinthefutureoftheprojectDataDate.Itwouldnotbelogicaltohaveanactivityactualstartsetinthefuture.

•AnActualStartmayalsobeassignedinanActualStartcolumn.

14.2.3AssigninganActualFinishDateandTimeofanActivityThisisassignedinthesamewayasanActualStartandthisshouldbeinthepast.AnActualFinishdateoverridesanEarlyFinishdateandfinishdateconstraintsandfinishrelationshipsareignored.

14.2.4CalculationofDurationsofanIn-ProgressActivityDurationsThePrimaverahasmanydurationsfields,wewilldiscussfourdurationsfieldsbelow:

•AnactivityPlannedDuration(OriginalDurationinsomeWindowsClientIndustryVersions)isthedurationfromtheEarlyStarttotheEarlyFinishcalculatedovertheActivityCalendarandiscalculatedwhenanactivityhasnotyetstarted.WhenanActualStartisentered,thisdurationisnolongerrecalculatedordirectlyusedforscheduling,butmaybeedited.

•TheActualDurationistheactivity’sworkeddurationandiseitherthedurationfrom:TheActualStarttotheDataDateofanIn-progressactivity,or

Page 264: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheActualStarttotheSuspendDateofasuspendedIn-progressactivity,orTheActualStarttotheActualFinishofaCompletedactivity.

•TheRemainingDurationistheunworkeddurationofanIn-progressactivityandisthedurationfromtheDataDateorResumeDatetotheEarlyFinishdateofanactivity.

•TheAtCompletionDuration=ActualDuration+RemainingDuration.Beforeanactivityhasstarted,theActualDurationiszeroandtheRemainingDurationequalsthePlannedDuration.

•ThePlannedDurationislinkedtotheRemainingDurationwhen:Anactivityisun-startedandTheProject,EPS,Actions,SetProjectPreferences…,Calculationstab,Linkplannedandatcompletionfornotstartedactivitiesischecked.Thein-builtproportionallinkbetweenPlannedDuration,ActualDuration,RemainingDuration,and%CompletethatexistsinMicrosoftProjectdoesnotexistinPrimavera.

PercentCompleteAsdiscussedintheADDINGACTIVITIESANDORGANIZINGUNDERTHEWBSchapter,thissectionisrepeatedforcompletenessofthischapter.

ThePercentCompletetypeshouldbeunderstoodifitisintendedtoupdate(statusorprogress)aschedule.InPrimaverathisoptionmaybesetforeachactivityindividuallyandthedefaultfornewactivitiesissetinthePercentCompleteTypedropdownbox.PrimaverahasmanyActivityPercentCompletefieldsthatmaybedisplayedincolumnsandwewilldiscussfourofthemnow:

IntheWebClienttheDuration%Completeisdisplayedasthe%CompleteBar.Activity%Complete,displayedonthe%CompleteBarintheWindowsClientonly,maybelinkedtoonlyoneofthethree%Completefollowingthreefields,Physical%Complete,Duration%Complete,orUnits%Complete.

TherearethreePercentCompleteoptions;eachnewactivityisassignedtheprojectdefaultPercentCompleteTypeandthenthismaybeeditedforeachactivityasrequired.ThereforeiftheoptionofPhysical%CompleteisselectedforanactivitythentheActivity%CompleteandthePhysical%Completearelinkedandachangetoonewillchangetheother.

Default%CompleteTheDefaultPercentCompleteTypeforeachnewactivityineachprojectistheProjectPreferences,Defaultstab:

Page 265: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•EachnewactivityPercentCompleteTypeissettotheDefaultPercentCompleteandmaybechangedatanytime.

PercentCompleteTypes•Duration%Complete–ThisfieldiscalculatedfromtheproportionofthePlanned

DurationandtheRemainingDurationandtheyarelinkedandachangetoonevaluewillchangetheother.WhentheRemainingDurationissettogreaterthatthePlannedDurationthispercentcompleteisalwayszero.ThisissimilartothewayP3andSureTrakcalculatesthe%CompletewhentheLinkRemainingDurationandPercentCompleteoptionisselected

•Physical%Complete–Thisfieldenablestheusertoenterthepercentcompleteofanactivityandthisvalueisindependentoftheactivitydurations.ThisissimilartothewayP3andSureTrakcalculatesthe%CompletewhentheLinkRemainingDurationandPercentCompleteoptionisNOTselected.

•Units%Complete–ThisiswherethepercentcompleteiscalculatedfromtheresourcesActualandRemainingUnits.AchangetoonevaluewillchangetheotherandwhenmorethanoneresourceisassignedthenalltheActualUnitsforallresourceswillbechangedproportionally.ThiswillbecoveredfurtherinTheUPDATINGARESOURCEDSCHEDULEchapter.ThisissimilartotheMicrosoftProject%WorkComplete.

TheUnits%CompleteiscalculatedfromthevalueofalltheLabor,Non-LaborResources,sobecarefulwhenmorethanontypeofresourceisassignedtoanactivity.Forexamplethesoftwarecouldbeaddingconcretevolumeswithlaborhoursandexcavatorhours.

Activity%CompleteTheActivity%CompletefieldislinkedtothePercentCompleteTypefieldassignedtoanactivityintheActivitiesWindow,Detailsform,Generaltaborthe%CompleteTypecolumn:

Page 266: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TheActivity%CompleteisNOTlinkedtothe%CompleteBarandtheDuration%Completeisdisplayedonthe%CompleteBar,inthesamewayasMicrosoftProject’sdefault%Completebar.

IntheWindowsClienttheActivity%CompleteisdisplayedontheBar:

14.2.5SummaryBarsProgressCalculationSummarybarssuchasWBSNodebarsmaynotbeupdated,astheyarevirtualactivitieswiththeirdatacreatedfromsummarizingtheactivitiesintheWBSband.

14.2.6UnderstandingtheDataDateTheDataDateisalsoknownastheCurrentDataDateintheWindowsClient,UpdateDate,StatusDate,ProgressDate,AsAtDate,TimeNow,ReportDateandtheProjectDataDate.PrimaverahasoneDataDate,titledCurrentDataDate,whichoperatesinasimilarwaytotheDataDateinP3andSureTrak.ThePrimaveraDataDateisdisplayedasaverticallineontheschedule;thisDataDateverticallinemayNOTbeformatted,onlyhiddenordisplayed.UnlikeAstaPowerproject,whichallowsalltheReportDatestobesetupatthestartofaproject,P6onlyhasoneDataDatethatismovedoneachupdate.

InP6thefunctionoftheDataDateisto:•Separatethecompletedpartsofactivitiesfromincompletepartsofactivities.

•Calculateorrecordallcostsandhoursto-datebeforetheCurrentDataDate,andto

Page 267: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

forecastcostsandhourstogoaftertheCurrentDataDate.

•CalculatetheFinishDateofanin-progressactivityfromtheCurrentDataDateplustheRemainingDurationovertheActivityCalendar,whentheSuspendandResumefunctionhasnotbeenused.

14.3UpdatingtheScheduleThenextstageistoupdatetheschedulebyenteringthemark-upinformationagainsteachactivity.

Whendealingwithlargeschedulesitisnormaltodevelopalook-aheadschedulebycreatingafiltertodisplayincompleteandun-startedactivitiescommencinginthenearfutureonly.

Theschedulemaybeupdatedusingthefollowingmethods:

•UsingthefieldsintheStatusareareaofGeneraltabintheDetailsform,or•Displayingtheappropriatetrackingcolumnsby:

Creatingyourownview,or

Insertingtherequiredcolumnsinanexistingview.

14.3.1UpdatingActivitiesUsingtheGeneralTaboftheDetailsFormEnsureyouareshowingthetimeandthenopentheGeneraltab:

UpdatingaCompleteactivity:•ChecktheStartedboxandentertheactualStartDateandTimeifdifferentfromthe

displayeddate.

•ChecktheFinishedboxandentertheactualFinishDateandTimeifdifferentfromthedisplayeddate.

UpdatinganIn-progressactivity:•ChecktheStartedboxandentertheactualStartDateandTimeifdifferentfromthe

displayeddate.

•WhentheDurationTypeisDurationthe%DurationCompleteandRemainingDurationare

Page 268: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

linkedtoeither:

TheRemainingDurationiseditedandthe%Completeiscalculated,orThe%CompleteisenteredandthesoftwarecalculatestheRemainingDuration,orARemainingDurationgreaterthanthePlannedDurationmaybeenteredandthe%Durationwillremainatzero,untiltheRemainingDurationislessthanthePlannedDuration.

IrrespectiveofthemethodusedtocalculatetheRemainingDuration,afterthescheduleisrecalculatedtheenddateoftheactivityiscalculatedfromtheCurrentDataDateplustheRemainingDurationovertheActivityCalendar.

Becarefulthatthe%DurationCompletedoesnotchangetheRemainingDurationtoanon-rounddayandthatactivitythenfinisheshalfwaythroughaday.Thisresultsinallsuccessoractivitiesstartingandfinishinthemiddleoftheday.

UpdatinganUn-startedactivity:•ThePlannedDuration,RelationshipsandConstraintsofanun-startedactivityshouldbe

reviewed.

14.3.2UpdatingActivitiesUsingColumnsAnefficientmethodofupdatingactivitiesisbydisplayingthedataincolumnsby:

•Insertingtherequiredcolumnsinanexistingview,orbetter:

•CreatingaViewwiththerequiredcolumnsandupdatingthescheduleusingthesecolumns.

14.4ProgressSpotlightThefunctiontitledProgressSpotlighthighlightstheactivitiesthatshouldhavebeenworkedonintheperiodhighlighted.ClickontheSpotlight icontomovetheSpotlightforwardorbackwardsoneminortimescaleincrement.

14.5SuspendandResumeYoumustdisplaytheappropriatecolumnstoentertheSuspendandResumedates.ThisfunctionworksinasimilarwaytotheP3andSureTrakfunctionandenablesonlyonebreakinanactivity.

ThefollowingexampleshowsanactivitywithaSuspenddateandResumedate:•ThisfeatureworkswhenanactivityhascommencedandnormallytheSuspenddateisin

thepastandtheResumedateinthefuture.

Page 269: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TheactivitymusthaveanActualStartdatebeforeyoucanrecordaSuspenddate.

•OnlyResourceDependentandTaskDependentactivitiesmaybesuspendedandresumed.

•Thesuspendedperiodisnotcalculatedaspartoftheactivitydurationandresourcesarenotnormallyscheduledinthisperiod.

UnliketheProfessionalandOptionalClientyoumaynotupdatethesedatesinanylowerwindowtab,youmustdisplaythecolumns.

TheSuspendandResumetimemaybesetattheincorrecttimeoftheday.TheauthorhasfoundthattheSuspendisusuallysetatthestartofthedayandResumeusuallyattheendoftheday;thereforethedefaultsforbothareillogical.ThereforeyouSHOULDALWAYSdisplaythetimewhensettingSuspendandResumedatestoensurethattheyarecorrect.

14.6SchedulingtheProjectAtanytime,butusuallyaftersomeoralltheactivitieshavebeenupdated,theprojectisscheduled:

•OpentheScheduleProjectform:SelectScheduler(F9) iconor

PresstheF9key,or

Page 270: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•DataDate

AllprojectusetheirowndatadatewillnotchangeanyDataDates,

ApplyselecteddatadatetoopenprojectswillchangetheDataDateofalopenprojects,andselecttherequirednewDataDatefromtheDataDatebox,

•Clickthe Schedulebutton.•Thesoftwarewillrecalculatealltheearlyfinishdatesfromtheremainingdurationsandthe

newCurrentDataDate,takingintoaccounttherelationshipsandtheScheduleOptions.

14.7UpdateProjectThereisnoUpdateProjectfunctionasfoundintheWindowsClient.

14.8ComparingProgresswithBaselineTherewillnormallybechangestothescheduledatesandmoreoftenthannottherearedelays.ThefullextentofthechangeisnotapparentwithouthavingaBaselinebartocomparewiththeupdatedschedule.

TodisplayoneormoreoftheBaselineBarsintheBarChartyoumustopentheBarsformintheCustomizeGanttChartformandmodifyasrequired.

IfyouwanttoseetheStartandFinishDatevariances,theyareavailablebydisplayingtheVariance–BLStartDate,Variance–BLFinishDate,Variance–BL1StartDate,andVariance–BL1FinishDatecolumns.

Asdiscussedearlierinthischapter,whenaProjectBaselineoraPrimaryUser’sBaselinebarisdisplayedwithoutabaselinebeingsetandthe<CurrentProject>(whichisbasedonthePlannedDates)willbedisplayed.The<CurrentProject>/PlannedDatesofanin-progressprojectsarenotBaselinesandmayholdirrelevantdata.

14.9ProgressLineDisplayontheGanttChartAprogresslinedisplayshowfaraheadorbehindactivitiesareinrelationtotheBaseline.

Page 271: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

EithertheProjectBaselineorthePrimaryUser’sBaselinemaybeusedandtherearefouroptions:

•DifferencebetweentheBaselineStartDateandActivityStartDate,•DifferencebetweentheBaselineFinishDateandActivityFinishDate,•ConnectingtheprogresspointsbasedontheActivity%Complete,•ConnectingtheprogresspointsbasedontheActivityRemainingDuration.

ThepicturebelowisusingtheoptionsinthepictureabovebutalltheactivitiesaresetasaPhysical%CompletebuttheWebtoolonlydisplaystheProgressonthebarsandActivity%CompleteonthebarsasintheWindowsClient.

Page 272: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

14.10CorrectiveActionDateslippageoccurswhenanactivityisrescheduledtofinishlaterthanoriginallyplanned.Therearetwocoursesofactionavailable:

•Thefirstistoaccepttheslippage.Thisisrarelyacceptable,butitistheeasiestanswer.

•Thesecondistoexaminethescheduleandevaluatehowyoucouldimprovetheenddate.

Solutionstoreturntheprojecttoitsoriginalcompletiondatemustbeauthorizedbythepersonresponsiblefortheproject.

Suggestedsolutionstobringtheprojectbackontrackinclude:

•Reducingthedurationsofactivitieson,ornear,thecriticalpath.Whenactivitieshaveappliedresources,thismayincludeincreasingthenumberofresourcesworkingontheactivities.Changinglongeractivitiesisoftenmoreachievablethanchangingthelengthofshortdurationactivities.

•Providingmoreworktimeandchangingcalendars,sayfromafive-daytoasix-daycalendar,sothatactivitiesarebeingworkedonformoredaysperweek.

•Reducingtheprojectscopeanddeletingactivities.

•Changingactivityrelationshipssoactivitiestakeplaceconcurrently.ThismaybeachievedbyintroducingnegativelagstoFinish-to-Startrelationships,whichmaintainsaClosedNetwork.Anegativelagwillallowthesuccessoractivitytostartbeforethepredecessoriscomplete,whichisoftenwhathappensinreality.

•ReplacingFinish-to-StartrelationshipswithStart-to-Startrelationships.Activitiesarenowprogressinginparallelandthereforeatthesametime.Thishasthepotentialofcreatinganopennetworkasthepredecessoractivitymaynolongerhaveafinishsuccessorandanextensioninthedurationofthisactivitymaynotaffectthecriticalpath.TomaintainthecriticalpaththenthisoptionshouldbeavoidedoraFinish-to-Finishsuccessoraddedtocompleteaclosednetwork.

•Changingtheplanandthereforechangingthelogictoreducetheoveralllengthofthecriticalpath.

14.11CheckListforUpdatingaScheduleBeforeupdatingascheduleyoushouldcheckthefollowingitems:

•EnsureyouareshowingthetimefromtheAdminister,MyPreferences,DateFormatsectionandcheckthatallStartandFinishdatesandtimesarelogical.Youcanseethatthesetimesmakesensewhenyouareupdatingaproject.

•Checkthe%CompleteTypeforalltheactivities;theauthorrecommendsthatthisbesettoPhysical.

•ChecktheScheduler,Options.Thedefaultsareusuallygood,butifyouhavemultiplecalendarsyoushouldconsiderusingtheLongestPathoption.

•CheckthattheAdminister,ApplicationSettings,EarnedValuetabisNOTsettoPlannedvalueswithplanneddates,soyouwillnotreadthePlannedDatesfromaBaselineSchedule.

Page 273: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•AftercreatingaBaseline,ensurethatyouhavenotlefta<CurrentProject>astheProjectBaselineorPrimaryUser’sBaseline.

•EnsureallActualDatesareinthepastastheyareassigned.•TakeacompletecopyofyourscheduleincludingallBaselineprojectsafterupdateforclaim

analysisatalaterdate.

14.12Workshop12–ProgressingandBaselineComparison

BackgroundAttheendofthefirstweekyouhavetoupdatethescheduleandreportprogressandslippage.

Assignment1.Wearenowgoingtoupdatethescheduleattheendofthefirstweek.

2.EnsureyourOzBuildprojectisopenandyouhavetheWorkshop11BaselineComparisonviewapplied.

3.UpdatetheprojectactivitiesintheActivities,bottompaneGeneraltabwiththefollowing:NOTE:Greyhighlightedcellsmaynotbeedited.

4.F9toopentheScheduleProjectform:SelectApplyselecteddatadatetoallprojects,ChangetheCurrentDataDateto9-Dec-1308:00,thatwillbeMondaymorning,

OpentheSchedulerOptionsformbyclickingonthe OptionsiconandensureRetainedLogicisselected,andthenclosetheSchedulerOptionsform,

Clickonthe Schedulebuttontorescheduleandchecktheanswer

Page 274: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 275: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

NOTE:ThelowerbaristheBaselineanddelaystoactivitiescreatedbythelateschedulingoftheCreateTechnicalSpecificationactivityisclearinthepictureabove.

5.OpentheGeneraltaboftheCreateTechnicalSpecificationactivityandchangethe%CompleteTypetoDuration,

6.SaveandscheduleandtheActivity%Completewillchangeto0%.Alinkisnowestablishedbetweenthe%CompleteandRemainingDurationandthereforethe%CompleteandRemainingDurationmaynotbeenteredindependentlyfromtheActivity%Complete.TheActivity%CompletevalueiszerobecausetheRemainingDurationisgreaterthanthePlannedDuration.

7.IfyouturnonShowneckingforthefirstbarintheCustomizeActivityViewformBarstabyouwillseetheneckingofthebarsoverthenon-workperiods.

8.Enter20%CompleteagainsttheCreateTechnicalSpecificationactivityintheGeneraltabandschedule.TheRemainingDurationwillreduceto4daysandyouwillnoticethelinkbetweentheActivity%CompleteandRemainingDuration.

9.Nowchangethe%CompletefortheCreateTechnicalSpecificationactivityto50%andSave.

10.Reschedule.

11.EnsureyouareshowingtheDurationSub-unitofHoursbyopeningtheAdminister,MyPreferences…TimeUnittabandcheckthesettingareasperbelow:

Page 276: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

12.ThishasresultedintheRemainingDurationnolongerbeingexpressedinwholedaysandactivitieswhicharetwodayslong,forexampleActivityOZ1030,nowspanningthreedaysbecausetheystartandfinishatmidday.

Page 277: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

13.ThesituationofhavingdurationsthatarenotrounddaysisoftennotdesirableandmaybepreventedbyusingPhysical%CompleteandenteringtheRemainingDurationinwholedays.

Page 278: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15ADMINISTERMENU

15.1AdministerMenuTheAdminmenuisavailableintheP6ProfessionalClient.WhentheWebisinstalledandtheP6OptionalClientisusedtheAdminmenuisnolongeravailableandalladministrationfunctionsmustbeaccessedthroughtheWebmodulewhenusingtheOptionalClient.

P6ProfessionalTheAdmincommandopenstheAdminform.DependingonhowPrimaverahasbeeninstalledandyouraccessrightsset,youmayormaynothaveaccesstosomeorallofthesemenus.

P6WebThewebAdministermenuiswheretheOptionalAdmincommandsarelocatedandtheseareallverysimilartotheProfessionalClient.

TheWebcommandswillnotbecoveredindetailinthisbookbuttheyoperateinexactlythesamewayastheWindowsProfessionalClient.

ThischapterwilllookatthefollowingtopicsundertheAdministermenu:

•MyCalendar

Page 279: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•MyPreferences,calledUserPreferencesintheProfessionalandOptionalClients•AdministerSettings

•EnterpriseData

•GlobalScheduleServices

•UserAccess

•UserInterfaceViews

•UserSessions

15.2MyCalendarWhenauserisalsocreatedasaresourceinadatabaseandhasaPersonalCalendarcreatedthentheusermayedittheirowncalendarinthisareatoreflecttheirpersonalavailabilityandmayaddtheirholidaysetc.intheircalendar.

Thisoptionworksinthesamewayaseditinganyothercalendar.

AresourcecalendarwillONLYbeusedtocalculateactivitydurationswhenanactivityisassignedanActivityTypeofResourceDependent.

15.3MyPreferencesSelectAdminister,MyPreferencestoopentheMyPreferencesform.Thisformisusedtosetupanumberofuserdefinedparameters,whichwilldeterminehowdataisdisplayed:

TheMyPreferencesformhasthreetabs:•Global–wheretheMyPreferencesoptionsthatcontrolhowdataiscalculatedareedited,•View–wheretheuserformatsmanyoftheirViews,allowingtheusertohideordisplay

dataand

•Password–wheretheuserchangestheirpassword.

15.3.1Global,GeneralTab

Page 280: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

MaximumnumberorrowsdisplayedineachsectionandMaximumnumberofrowsdisplayedintreesandpicklistsrestricttheamountofdataavailableinlists.Anexampleofthistypeofrestrictionisdisplayedinthepicture.

Itisrecommendedthathighvaluesaresetheresoasnottohidedata.

Sende-mailtoresourcesuponaddingorremovingassignmentsandPromptbeforesendingemailareself-explanatory.CalculateperformanceandearnedvalueinformationbyCostsorLaborUnitsaffectsEVcalculationsandthisisaninterestingfeatureasthisallowsdifferentuserstoreportdifferentdataforthesameprojects.

15.3.2Global,General,TimeUnitsFormatTabTheDisplayTimeUnitsinsectionofthetabisusedtodefinetheUnitofTimeformatthatresourceinformationandresourceassignmentsaredisplayedwith,e.g.daysorhours.

TheDisplayDurationsFormatinsectionofthetabisusedtodefinetheUnitofTimeformatthatactivitydurationsaredisplayedwith,e.g.,daysorhours.

Page 281: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thepicturetotherightshowstheauthor’srecommendedsettings.ItisbesttoshowboththeDurationsubunitsandlabelthenyouwillseeifyouhavedurationsthatarenotrounddays.

TheUnits/TimeFormatsectionoftheformenablestheMicrosoftProject-typeformattingoptionsofResource/TimeFormattoshowResourceutilizationasapercentage(50%)orasunitsperduration(4h/d).Thereforethereareseveraloptionshere;forexample,threepeopleassignedtoanactivitymaybedisplayedinmanyformatsincludingthefollowingwhichallcalculatethesamevalueofthreeresources:

•300%

•24h/d

•3d/d

•3h/h

15.3.3Global,ResourcesTab,ResourceStaffingAutomaticallysummarizeprojectafterassigningresourcesensuresthatsummarydatadisplayedinotherviewshasbeenrecalculatedbythesystem.

Page 282: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

DisplayResourceAssignmentsUncheckingthesedoesnothidethesedataitemsintheProject,Activitiesbottomwindowbutwillhidethisdatainsomeotherviews.

DisplayNotebookUncheckingthesedoesnothidethesedataitemsintheProject,Activitiesbottomwindowbutwillhidethisdatainsomeotherviews.

DisplayStepsUncheckingthesedoesnothidethesedataitemsintheProject,Activitiesbottomwindowbutwillhidethisdatainsomeotherviews.

15.3.4Global,ResourcesTab,ResourceAssignmentsWhenaddingorremovingmultipleresourceassignmentsonactivitiessectionhastwooptions:

PreservetheUnits,Duration,andUnits/Timeforexistingassignments.Withthisoption,asResourcesareaddedordeletedthetotalnumberofhoursassignedtoanActivityincreasesordecreases.Thehoursassignedforeachresourcearecalculatedindependently.

RecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationType.Thetotalnumberofhoursassignedtoanactivitywillstayconstantas

Page 283: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

secondandsubsequentresourcesareaddedorremovedfromanActivity,exceptwhentheActivityTypeisFixedDurationandUnits/Time.RecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationTypeissimilartomakinganactivityEffortDriveninMicrosoftProject.ThereisnosimilarfunctioninP3andSureTrak.

WiththeRecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationTypeoptionasyouassignorremoveresourcestoorfromanactivitythetotalnumberofhoursofworkstayconstantandtheworkisdividedamongstalltheresources.Thus,assigningresourceswillreducetheworkforeachresourceandeithertheactivitydurationwillreduceortheUnitsperTimePeriodforeachresourceassignmentwillreduce.ThiscalculationisdependentontheDurationType.TheauthorprefersasadefaultPreservetheUnits,Duration,andUnits/Timeforexistingassignments.Inthissituationeachresourceworkisindependentonotherresourcesassignedtoanactivity.

Whenassigningaresourcetoanexistingactivityassignment:Theoptionsallowausertodecide what Units/Time are assigned to a resource when a resource is assigned to anexistingassignment.

When a resource and role share an activity assignment: The options allow a user todecidewhatPrice/Unitisassignedtoaresourcewhenaresourceisassignedtoanexistingassignment.

Displaytherole limitbasedon:Primavera introducedRoleLimits inVersion6.0and thisenablesoptionsfordisplayingtheRoleLimitsinResourceProfiles.Arolemayhavebeendefineda limitofsix resourcesbutonlyhave fourPrimaryResourcesassigned.Thisoptionallowsyoutodecideifyouwishtodisplayalimitoffourbasedontheresourcesavailableorsixbasedonthelimitassignedtotherole.

NumberofavailableitemstosearchforRoles,Resources,andResourceCodesThissetsthelinesavailableintheOpenarequestforaresourceform,inthepicturetheoptionissetto2:

Page 284: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.3.5Global,ProjectScoreTabTheseoptionsareusedforProjectandPortfolioreportingandareoutofscopeofthisbook.

15.3.6Global,PerformanceThresholdTabThissectionisusedtocustomizethedashboards:

Page 285: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.3.7Global,CurrencyTabTheCurrencyOptionstabselectsthecurrencysymbolusedtodisplaycosts.

TheCurrenciesform,availablefromtheAdminister,EnterpriseData,Globalsectionmenuitem,isusedtodefinetheBaseCurrency.AllcostsarestoredintheBaseCurrencyandallotherCurrenciesarecalculatedvaluesusingtheBaseCurrencyvalueandconversionrate.

Itispossibletohavetwocurrencieswiththesamesymbolandifauserselectsadifferentcurrencythenallcostsdisplayedbytheuserwillbeconvertedtoadifferentvalue.Thisoptionmustbecarefullymonitoredandifyoudonotneedmultiplecurrenciesthenitissuggestedthatyoushoulddeleteallbutonecurrency,toavoidany

Page 286: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

possibleproblems.Ifyouareusingmultiplecurrenciesthenmakesurethatallhaveadifferentsignsothereisnoconfusion.

15.3.8Global,DateFormatTabTheDateFormattabisself-explanatoryandisusedtoformatthedisplayofdatesandtime.NOTE:Itisnotpossibletohidetheyearandtherealwayshastobeadateseparator,thusleadingtowiderdatecolumnsthanotherwisecouldbeachieved.ItisalsonotpossibletodisplaythedaysincharacterssuchasMonorMondaywiththedate.

Thepicturetotherightshowstheauthor’srecommendedsettings.PeopleintheUSmaywishtousetheirlocalDateFormat.

TheauthorrecommendsthattheTimeshouldalwaysbedisplayedsoausermayseewhattimePrimaverahasselectedwhenassigningActualdates,Constraintdates,SuspendandResumedates.OftenPrimaveraselects00:00,whichismidnightonthemorningoftheselecteddate.TheauthorrecommendsthattheMonthnameshouldalwaysbedisplayedtoavoidconfusionbetweentheUSdateformatofmm/dd/yyandtheROW(RestofWorld)dateformatofdd/mm/yy.

15.3.9Global,IssuesTabThisiswhereauserspecifieswhichIssuestheyareinformedabout.

Page 287: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.3.10ViewTabTheViewtabisusedtodisplayorhideP6windows:

15.3.11SettingaDefaultStartPageInP6R8.3itispossibletospecifythedefaultstartpagethatauserwillbepresentedwithuponlogginginby:

•Settingthedefaultstartpage;

Page 288: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ThenselectingaP6sectionintheStartPagelistand;

•Ensuringthatthestartpageisthetop-mostpageselectedfordisplay.

Toaccessthisfeatureeither:

•GotoAdminister,MyPreferencesandselectViewtab;or•GotoAdministerandselectUserInterfaceViewsand•ClickontheContenttaboftheGeneralsection.

15.3.12PasswordTabTheUserPasswordtabisusedtochangetheuserpassword.

Page 289: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.4ApplicationSettingsThisiswheresomedatabaseparametersarecreatedandedited:

15.4.1DataLimitsTheDataLimitstabspecifies:•Themaximumnumberoflevelsallowedinallhierarchicalcodestructures,

•ThemaximumnumberofActivityCodesperproject,

•ThemaximumnumberofBaselinesperproject,

•PrimaveraVersion6.0addedtheMaximumbaselinescopiedwithproject,whichislimitedto50.

15.4.2EarnedValueSeetheEarnedValuechapterintheProfessionalandOptionalClientbookformoreinformation.

ThistabsetstheWBSdefaultsforcalculatingEarnedValueandmaybechangedindividuallyforeachWBSandapplytoallactivitieswithineachWBSNode.

Page 290: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TheTechniqueforcomputingperformancepercentcompleteselectstheformulaforcalculatingtheEarnedValue.

•TheTechniqueforcomputingEstimatetoComplete(ETC)selectstheformulaforcalculatingtheETC.TheETCisacalculatedfieldandisindependentoftheAtCompletionFieldsbutmaycontainthesamevalue.

EarnedvaluecalculationsselectssomeoptionsforcalculatingtheEarnedValueanddisplayingtheBaselineBar.ThePrimaveradefaultisusuallysettoPlannedValueswithPlannedDates.ThissettingshouldNEVERbeusedandpleasereadthewarningbelow.

ItisveryimportantthatusersreadthesectionsonPlannedDatesasleavingthesettingatPlannedValueswithPlannedDateswillresultintheriskthatallin-progressBaselinesmaydisplayirrelevantdatesasBaselinedates.

15.4.3General•CodeSeparatorsetsthedefaultseparatorfornewprojectWBSCodesandothercodes

suchasCostAccounts.TheCodeSeparatormayalsobesetforeachindividualprojectintheProjectWindow,Settingtab.

•StartingDayoftheWeeksetstheFirstdayofweekthatisshownonthetimescaleandtheleftcolumnofcalendars.

•ActivityDurationsetsthedefaultActivitydurationfornewactivities.•PasswordPolicy,introducedinVersion6.2,allowstherequirementforapasswordofa

minimumof8charactersincludingaletterandnumber.ThedefaultisusuallySundayandshouldbechangedtoaMonday,whichresultsinthecalendardayinthetimescalerepresentingaworkingday,whichisoftenalotmoreusefulthanthedateofanon-workdaydisplayed.

InP6R8.3thePasswordSecurityPolicyisenabledbydefault.

ToEnable/Disablethis:

•GotoAdminister,ApplicationSettingsandselectGeneral,•Enable/DisablethecheckboxtitledPasswordPolicy.

•IndustrySelectionallowstheselectionofanindustrytypewhichonlyaffectshowsomedatalabelsaredisplayedintheWindowsClient,seetheWindowClientbookformoredetails.

15.4.4IDLengthsTheIDLengthstabspecifiesthemaximumnumberofcharactersintheCodeIDfields,nottheCodeDescription.

15.4.5ServicesServicesallowpublicationandsummarizationtohappenautomatically.

Page 291: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.4.6TimesheetsThisiswheresomeofthetimesheetrulesaresetbytheadministrator.

15.4.7TimePeriods

CheckingUseassignedcalendartospecifythenumberofworkhoursforeachtimeperiod(titledAllowuserstospecifythenumberofworkhoursforeachtimeperiodintheWindowsClient)enablesuserstoedittheHoursperTimePeriodineachcalendar.WhenthisisnotcheckedthentheHoursperTimePeriodvaluesinthisformareusedtoconvertfromonetimeperiodUnittoanotherforallcalendars,forexamplefromdaystohours.Therefore,a40hoursactivitywouldbealwayscalculatedas5dayswiththesettingdisplayedinthepictureaboveirrespectiveoftheactivitycalendarHours/Day.

Itisimportantthattheseconversionsareunderstood.PleaserefertotheDEFININGCALENDARSchapterformoredetails.ItisveryimportantwhenmultiplecalendarswithdifferenthoursperdayarebeingusedthatthischeckboxischeckedandtheusercorrectlysetstheHoursperTimePeriodineachcalendar.

TimePeriodAbbreviationsareusedtoindicatethedurationabbreviationseverywhereinthesoftwareforallusers.

15.5EnterpriseDataThisiswhereGlobalCodes,Calendarsandotherdatabasefieldsarecreatedandedited:

Page 292: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thissectionofthesoftwareisnormallymanagedbythedatabaseadministerandtheintentionofthisbookistointroduceuserstothesefunctionssowhentheyareunabletouseafunctionthentheyareabletoasktheadministratorforaccesstospecificfunctions.

15.5.1UnderstandingUDFsandActivityCodesAUDFisaUserDefinedField.ThesemaybecreatedinadatabaseforanydatatablesuchasActivities,ResourcesandExpensesandthenvaluesassignedforeachactivity.TheyareusedtoholdadditionaldatathatmaynotbeheldbythestandardPrimaverafields.ThesearesimilartoMicrosoftProjectCustomFields.AUDFmaybecreatedforoneofthefollowingDataTypes:

•Text

•StartDate

•FinishDate

•Cost

•Number

•Integer

•Indicator,4graphicaliconsonly

ToassignaUDFtheappropriatecolumnisDisplayed.ThereforeanActivityDeadlineUDFisassignedfromtheProjects,ActivitiesviewbydisplayingtheDeadlineUDFcolumn,seetheexamplebelow:

Page 293: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AUDFmaybeassignedanyvalidvalueanditissimpletoentertwosimilarvalues,suchas“Bookshop”and“Bookshop”intoacolumnasUDFvaluesarenotdrawnfromalookuptable.Whenthishappensthesedonotfilterandsortproperly,whichisadisadvantageofUDFs.

AnActivityCodeorResourceCodeiscreatedinatableandhaveaValueandDescription.Thevalueisassignedtoanactivityandthedescriptionislookedupfromthetable.

AnactivityCodemustexistinthetablebeforeitisassignedbutmaybecreatedwhenassigningacode:

TheactivitycodemaybeusedtoGrouporFilteractivitiesandallowsahigherlevelofdisciplineandcontrolthanUDFs.

15.5.2Currencies

Page 294: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheCurrenciesformopenedfromtheAdminister,EnterpriseData,Globalsectionmenuitemisusedtodefinesystemcurrencies.Currencyfieldsare:

•CurrencyID•CurrencyName•CurrencySymbol•ExchangeRateTomaketheBasecurrencyintoyourcountry’scurrencyyouwillneedtoedittheCurrencyIDandCurrencySymbolasthefirstcurrencyispermanentlychecked.

Itispossibletohavetwocurrencieswiththesamesymbolandifauserselectsadifferentcurrencythenallcostsdisplayedbytheuserwillbeconvertedtoadifferentvalue.Thisoptionmustbecarefullymonitoredandifyoudonotneedmultiplecurrenciesthenitissuggestedthatyoushoulddeleteallbutonecurrency,toavoidanypossibleproblems.Ifyouareusingmultiplecurrenciesthenmakesurethatallhaveadifferentsignsothereisnoconfusion.

15.5.3FinancialPeriods

ThisiswheretheFinancialPeriodsassociatedwithStoringPeriodPerformancearecreated.

FordetailsonthisfunctionseethesectiononStorePeriodPerformanceintheEarnedValuechapterintheProfessionalClientbook.

Page 295: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

FinancialPeriodshavetobeusedwhenitisimportanttohavedatathatreflectshowmuchworkwascompletedorcostsspentineachperiodandnotjustaveragedovertheperiodstodate.PerioddataisoftenusedtocreateS-Curves.

15.5.4GlobalCalendarsThesewerecoveredintheDEFININGCALENDARSchapter.

15.5.5Locations

Thisiswherethelocationtableisedited.

15.5.6OverheadCodes

ThisiswheretheOverheadCodesthatmaybeusedwithtimesheets.

15.5.7TimesheetPeriods

Page 296: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThisiswhereTimesheetPeriodsarecreated,

15.5.8ProjectsThisiswherethefollowingtablesaremanaged:

•BaselineTypes UsedtoidentifyBaselines.

•FundingSources Usedtoidentifyprojectfundingsources

•NotebookTopics TopicunderwhichNotebookTopicsarecreated.

•ProjectCalendars CoveredintheDEFININGCALENDARSchapter.

•ProjectUDFs UserDefinedFieldsmayholdspecificdataaboutaproject.

•WBSCategories UsedtoGroupandSortWBSNodes

•WBSUDFs UserDefinedFieldsmayholdspecificdataaboutaWBSNode.

15.5.9Activities

Page 297: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thisiswherethefollowingtablesaremanaged:

•ActivityCodes–EPS

ActivitiesCodescreatedhereareonlyavailabletoprojectsunderthespecifiedEPSNode.ThisfunctionallowsActivityCodesthatareonlysuitableforcertainprojecttypestoonlybeavailabletothoseprojects.ForexampleRailProjectsmayallbekeptunderaRailwayEPSNodeandallrailwayEPSActivityCodessuchasBallast,OverheadWiresandSwitchesetc.wouldbemadeasEPSCodes.

•ActivityCodes–Global

ActivitiesCodescreatedhereareavailabletoallprojects.

•ActivityCodes–Project

ActivitiesCodescreatedhereareONLYavailabletotheprojecttheyarecreatedfor.

•ActivityUDFs ToassignaUDFtheappropriateActivityColumnisDisplayed.

ActivitiesmaybeFilteredorGroupedbyaUDF.

DatamaybeimportedfromExcelintoaUDF.

•CostAccounts

CostaccountsarenormallycreatedandassignedtoResourceand/orExpenseassignmentssocostsofaspecifictypemaybeaddeduptocreateAccountingBudget.

ThisareaiswhereCostsAccountsaremanaged.

Page 298: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

NormallyadefaultCostsaccountisassignedtoaResourceandthenwhenaresourceisassignedtoanactivitytheResourceAssignmentadoptsthedefaultCostsAccountassignedtotheResource.InPrimaverathedefaultCostsAccountisassignedtotheProjectandallResourceAssignmentsadoptsthedefaultCostAccountwhichmakestheCostsAccountfieldinP6lessusefulaseveryRecourseassignmentwillhavetobeeditedifthedefaultisnotvalid.

•ExpenseCategories

ExpenseCategoriesaremanagedhere.ThesecategoriesmaybeassignedtoExpensesandallowExpensetobesummedupbyaCategory.ThisfunctionmaybeusedtosetafinancialbudgetsbyexportingthetotalcostperExpenseCategorytoafinancialmanagementsoftwarepackage.

•StepTemplates

AnactivitymaybebrokenintoStepsallowingprogresstobemeasuredagainstanactivityinameasurableway.Stepsforadocumentcouldbeforexample:

•Start–10%

•FirstDraft–40%

•InternalReview–30%

•Complete–20%

AStepTemplateallowsforStepstobeassignedtoactivitiesquicklyandaremanagedhere.

•StepUDFs AStepUDFmaybecreatedforStepsandvalues,textordatesmaybeassignedtotheStepUDF.

15.5.10Resources

Page 299: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AssignmentUDFsTheseareUDFsthatmaybeassignedtoaResourceAssignment.IfyouwishtomakeanoteofwhythisresourcehasbeenassignedtoanactivityandyoumaychoosetouseanAssignmentUDF.

RateTypesPrimaverahasfiveresourceratestypesandtheResourceRateTypesformenablesyoutorenamethetitlesoftherates.Youmayhave,forexample,ratesfor:

•Standardrate

•Internalconsulting,

•Externalconsulting,

ResourceCalendarsThesewerecoveredintheDEFININGCALENDARSChapter.

ResourceCodesResourcesmaybeassignedResourceCodesandmaybeusedtorecordinformationaboutaresourcethatmaybetakenfromapicklistsuchastheoffice,employmenttype(fullorparttime),gender(MaleorFemale)etc.

ResourceCurvesResourceCurvesenableanon-linearassignmentofresourcestoschedulesinthesamewayasP3andMicrosoftProject.Theseareoftenusedonlongactivitieswherethereisnotarequirementforalinearassignmentofresources.

ResourcecurvesareassignedintheCurvecolumnintheAssignmentstaboftheActivitieslowerpane.

ResourceUDFs

Page 300: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ResourcesmaybeassignedResourceUDFstorecordpersonaldetailsthatarenotsuitedtousingResourceCodessuchasaddress,nextofkinnameetc.

UnitsofMeasure

Thesearecreatedhereandareusedinconjunctionwithmaterialresources,butnorExpenses.

15.5.11Risks

ThefollowingRiskcodesaresetuphere:

Page 301: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•RiskCategories•RiskScoringMatrices•RiskThresholds•RiskUDFs

15.5.12Issues

ThefollowingIssuescodesaresetuphere:

•IssuesCodes•IssuesUDFs

15.5.13Documents

Page 302: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ThefollowingDocumentscodesaresetuphere:

•DocumentCategories•DocumentStatuses•DocumentUDFs

15.6GlobalScheduleServicesAGlobalScheduleServicemaybescheduledtoberunbytheadministratorhere.

Page 303: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Version8.4nowallowsthestatusofservicestobereviewedintheEPS,EnterpriseProjectStructure,Actionsmenu,ViewServiceStatus….

15.7UserAccessThisiswhereusersarecreatedandassignedaccesstothesoftwareandprojects:

15.7.1UsersTheUsersformisusedtoaddanddeletesystemusers.Theinformationmayberecorded

Page 304: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

suchasthePersonalName(theperson’sname),LoginName,telephonenumber,emailaddressandtheUsersAssociatedResource.

•ProjectAccesstab-thisiswheretheUserisassignedtooneormoreOBSNodesandmayonlyaccessProjectsassociatedwiththoseOBSNodes.ThelevelofuseraccesstoprojectscontrolledbythedesignatedSecurityProfile.

•ModuleAccesstab-thisiswhereapersonisassignedalicense.Alicenseneedstobeassignedbeforethepersonmayoperatethesystem.

•UsersareassignedaResponsibleMangerwhoapprovestimesheets.•Version8.4allowstheoptionofassigningmultipleResponsibleManagerstoaResource.

ThisallowsaresourcetohaveadifferentResponsibleManagefordifferentprojects.

15.7.2OBSTheOBS–OrganizationalBreakdownStructureisanEnterprisehierarchicalstructurethatisintendedtorepresentthecompany’sOBS.

TheOBSfunctionisthesecuritygatewayanddoesnothavetomirroryourcompany’sOBS.AnystructurethatenablesyoutoassignuseraccesstoprojectsisusuallysatisfactoryandsomecompaniesjustduplicatetheirEPSastheOBSand

Page 305: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

useaprojectcodefortheOBS.

•AusermaybeassignedtoprojectsornodesintheEPSortoaWBSNode.

•AuserassignedanEPSisnormallyresponsibleforallprojectsassociatedwithallelementsoftheEPS.

•TheOBSmayalsobeusedtoassignaccessbyindividualpeopletoprojectsandWBSNodes.

•AresourceassignedtoanOBSNodeisassignedtheDefaultProjectSecurityProfile.InVersion8.4theSecurityProfileofmultipleResourcesassignedtoaOBSNodemaybechangedatthesametimebyselectingmultipleResourcesandthenassigningthenewSecurityProfile.

15.7.3GlobalSecurityProfilesGlobalProfilemaybeestablishedinthisform.GlobalProfilesarecreatedand/oreditedtoenableaccesstospecificEnterprisefunctionsandareassignedtousers.

15.7.4ProjectSecurityProfilesProjectProfilesarecreatedand/oreditedtoenableaccesstospecificProjectfunctions.AProjectProfileisassignedtoauserwhentheyareassignedtooneormoreOrganizationBreakdownStructureNodes.AdifferentProjectProfilemaybeassignedtoeachuserforeachOBSNode,allowingaUserdifferentaccessrightstodifferentprojects.ProjectsandEPSNodesmayonlybeassignedtooneOBSNode.

ItiscriticalthattheSecurityProfilesbecarefullyevaluatedandeachpersonassignedanappropriatelevel.

NooneexcepttheAdministrator/sshouldbeabletodeletecriticaldatasuchasprojectandEPSNodes.

UserInterfaceViews

AUserInterfaceViewdictateswhatscreensausermayaccessaftertheyhaveloggedintoP6.Thisareaallowsanadministratortodesigntheseviews.

Page 306: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

DoubleclickingonanexistingUserInterfaceViewwillopenuptheView,Detailsformwheretheviewisdesigned.

TheUserInterfaceViewisassignedtotheUserintheAdminister,UserAccess,Usersform:

15.7.5CopyUserViewswhenCopyingaUserInP6R8.3whenacurrentuseriscopied,theuser-levelviewsandmulti-userviewsarecopiedtoo.

Toaccesstheviews:

•GotoAdminister,UserAccessandthenselectUserstocopyanuserandcreateanew

Page 307: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

one;

•Todisplaytheviewsthatwerecopiedalongwiththeuser,gototheViewlistontheEPS,ActivitiesorResourceAssignmentswindow.

15.8UserSessions

Thisallowstheidentificationofalluserswhoareusingthesystem.

Page 308: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

15.9MiscellaneousDefaults

15.9.1DefaultProjectThereisnoDefaultProjectasintheWindowsClientandyoushouldreadthesectionintheSchedulingOptions–GeneralTabtounderstandthewaymultipleopenedprojectscalculateintheWeb.

Page 309: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

16CREATINGROLESANDRESOURCESTraditionally,planningandschedulingsoftwaredefinesaResourceassomethingorsomeonethatisrequiredtocompletetheactivityandsometimeshaslimitedavailability.Thisincludespeopleorgroupsofpeople,materials,equipmentandmoney.

PrimaveraisabletoassignUnitRates,aCalendar,oneormoreRoles,aUserandsomepersonalinformationtoaResource.PrimaverahasafunctiontitledRoles.ARoleisnormallyusedattheplanningstageofaprojectandrepresentsaskillorposition.Later,andbeforetheactivitybegins,aRolewouldbefilledbyassigningaspecificindividualwhowouldbedefinedasaResource.RolesmaybeassignedtobothResourcesandActivities.AsearchbyRolemaybeconductedonalltheResourceswhenitisrequiredtoreplaceanActivity-AssignedRolewithanindividualfromtheResourcepool.PrimaveraallowsratestobeassignedtoRoles.

TherearelargenumbersofresourcefunctionsavailableinPrimavera.Withoutgettingintotoomuchdetail,thispublicationwilloutlinetheimportantresource-relatedfunctionsthatwillenableyoutocreateandassignRolesandResourcestoyourschedules.

ThischapterwillconcentrateonResourcesandRoles.ThefollowingstepsshouldbefollowedtocreateanduseresourcesinaPrimaveraschedule:

•CreatetheResourcesintheResourceManagement,Resourcestab,•CreatetheRoles,ifrequired,intheResourceManagement,Rolestab,•AssignResourcestoRoles,

•ManipulatetheResourceCalendarsifresourceshavespecialtimingrequirements.

ThefollowingcommandsareusedwhenmanagingRoles,ResourcesandTeams.

Topic MenuCommandCreatingResources OpentheResources,Administration,Resourcestab.

CreatingRoles OpentheResources,Administration,Rolestab.

CreatingResourceTeams

OpentheResources,Administration,ResourceTeamstab.

CreatingRolesTeams

OpentheResources,Administration,RoleTeamstab.

EditingResourceCalendars

SelectAdminister,EnterpriseData,Resources,ResourceCalendarstoopentheOpentheResources,Administration,Resourcestab.Calendarform.

Page 310: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ResourceGlobalDatamaybeeditedusingthe:

•Administer,EnterpriseDataor•ByselectingtheResources,EnterpriseResourceDatamenu:

16.1UnderstandingResourcesandRolesTherearetypicallytwomethodsofusingtheResourcefunctionforresourceplanning:

•IndividualResources,and

•GroupResources

16.1.1IndividualResourcesTheseresourcesareindividualpeoplewhoareoftenresponsibleforcompletingtheactivityortasksassociatedwithactivitiestowhichtheyhavebeenassigned.TheyareidentifiedbytheirnameinP6andcouldalsobeauser.

Thisistypicallyworkundertakeninanofficeenvironment,suchasanITdevelopmentproject,wheretimesheetsareoftencompletedbythepeopleundertakingtheworkandthetimesheetsystemisdirectlylinkedtotheschedulingsystem.

Inthissituation,theupdatingofActivitiesthatarein-progressiscompletedbythepersonassignedasaResourcetoanActivity,oftenviathetimesheetsystem,andtheschedulerhasareviewfunctionintheprojectupdating.

16.1.2GroupResourcesTheseresourcesrepresentgroupsofpeople,suchastradesordisciplinesonaconstructionsite.Verylargeprojectsgangsorcrews,whichwouldbemadeupofequipmentandanumberofdifferenttrades,couldalsobeconsidered.Thepersonresponsiblefortheworkisnotaresourceassignedtoanactivityandindividualpeopledoingtheworkwillnotbeassigningtheirtimesheetsdirectlytoactivitiesintheschedule.

Also,inthisenvironmenttheschedulernormallyupdatestheactivitiesandtheresources.Inthissituationitisrecommendedthataminimumnumberofresourcesbeassignedtoactivities.Thisisbecauseeveryresourceaddedtotheschedulewillneedtobeupdatedandasmoreresourcesareadded,thescheduler’sworkloadwillincrease.

Resourceminimizationsimplifiesascheduleandmakesiteasiertomanagelargeschedules.Thisisachievedbynotclutteringtheschedulewithresourcesthatareinplentifulsupplyorareoflittleimportance,andbygroupingtradesordisciplinesintocrewsandgangsonlargeprojects.

Page 311: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

WhenGroupResourcesareusedtheRolefunctiontendstobecomeredundantbutcouldbeusedtoplanthecontractortypeortheactualcontractortobeusedontheproject.

16.1.3InputandOutputResourcesWhenyoucreateyourresources,youmayalsoconsiderthemwithinthecontextofthefollowingheadings:

•InputResources–Theseresourcesarerequiredtocompletetheworkandrepresenttheprojectcosts:

Individualpeoplebyname.

Groupsofpeoplebytrade,discipline,orskill.

Individualequipmentormachinerybyname.

Groupsofequipmentormachinerybytype.

GroupsofresourcessuchasCrews,Gangs,orTeamsmadeupofequipmentandmachinery.

Materials.

Money.

•OutputResources–Thesecouldbetheprojectdeliverablesoroutcomesandcouldhaveadirectrelationshiptotheprojectincome:

Specificationscompleted.

Brickslaid.

Tons/Tonnesofmaterialloadedwithanexcavator.

Linesofcodewritten.

Testscompleted.

Thistypeofresourceisoftenusedintheminingenvironmentwheretheoutputintons/tonnesorvolumeisscheduledand/orleveled.

TheanalysisofanddifferencebetweentheInputandtheOutputresources’valueandtimingmaybeusedtorepresenttheCashFlow,CashPositionandProjectProfit(orloss).

ThetypeofcontractthattheworkisbeingconductedunderwouldoftendetermineiftheclientismoreinterestedintheInputorOutputResources.

16.1.4UnderstandingRolesAnevaluationatprojectorenterpriselevelinordertounderstandthelongtermdemandforresourcesmaybemadebyacombinationofRolesforlongtermplanningandResourcesforshorttermplanning.

RolesareassignedtoactivitiesforlongtermplanningandResourcesrepresentindividualpeopleareassignedtorolesforshorttermplanningandwouldrepresentactivityassignment.

•Thelight(green)areatotherightofthehistogrambelowshowstheunsatisfieddemandof

Page 312: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

therolestitledUnstaffedUnits,•Thesatisfieddemandfromtheassignedresourcesinthedarkarea(blue)aretotheleftand

aretitledStaffedRemainingUnits.•Thedark(red)areaabovethehorizontal(red)lineshowsOverloadedUnitswherethere

arenotsufficientrolesorresourcesavailabletocompletealltheplannedwork.

Ifyouareaconstructioncontractorandnotassigningworktoindividualpeoplethenyoumayconsiderusingresourcesonlyastheyhavemorefunctionsthanroles.

16.1.5UnderstandingResourceTeamsandRoleTeamsATeamisagroupingofResourcesorRolesthatmaybeusedforreportingandresourceloadinganalysis.

TeamsmaynotbeusedforassigningresourcesandtherearetwotypesofTeams:

•GlobalTeams–availabletoallusers.•UserTeams–availabletoonlytheuserwhocreatedtheteam.TeamsarecreatedintheResources,Administration,ResourceTeamstabandRoleTeamstab.Theseareverysimpletocreateandwillnotbecoveredindetail.

16.2CreatingRolesToview,create,edit,ordeleteaRole,opentheResources,Administration,Rolestab:

Page 313: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheRoleWindowhasatopandbottompane:•Thebottompaneisopenedbyclickingonatabatthebottomand

•Closedbyclickingonthe MinimizeDetailsbutton:

RolesmayhaveahierarchicalstructureinasimilarwaytoaWBSorEPSandare:

•Createdusingthe Addor AddSiblingicons,

•Deletedusingthe Deleteicon,

•Movedaroundinthehierarchicalstructureusingthe Moveicons

Page 314: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AsummaryRolemaybeusedaseither:

•PlaceholdertogroupRolesofasimilartype,suchasalldesignersmaybeplacedunderaDesignRole,buttheDesignRolemayneverbeassignedagainstanactivity,or

•Arolethatmaybeassignedtoactivities.

TheotherToolbariconshavesimilarfunctionstootherToolbarsandwillnotbecoveredhere.

EachRolewhenitiscreatedisassigneda:

•RoleID,auniquecodeusedtoassigntheRoletoanActivity,and•RoleName,thenameoftheSkillorTrade.

16.2.1DescriptionTabAroledescriptionmaybeenteredhereasinthepictureabove.

16.2.2ResourcesTab

IntheResourcestab:•EachRolemaybeassignedtooneormoreResources.

•TheResourceisassignedbydefaultaProficiencyof“3–Skilled”whichmaythenbechangedtoanyoftheoptionsshowninthelist.

•TheResourcemaybeassignedaPrimaryRolewhichwouldrepresentthetaskorjobtheywouldnormallybeassigned.

ThePrimaryRolealsolinkstoRoleavailabilitywhentheoptionintheAdminister,MyPreferences,Global,General,TimeUnitsFormatTab,DisplaytheRoleLimitbasedonissettoCalculateprimaryresources’limit.

16.2.3PricesTabUpto5rates(thesamenumberofratesasresources)maybeassignedtoroleswhichmaybeusedforestimatingandcashflowforecastingofprojectsbeforetheactualresourcecompletingtheworkisassignedtotheactivity.Differentratesmayberequiredfordifferent

Page 315: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

clientssuchasinternalprojectratesandratesfordifferenttypesofexternalclients.

•ClickonthePricestabtoedittheRolePrice/Unit.•TheRoleRateTypedescriptionisadoptedfromtheResourceRateTypesetinthe

Administer,EnterpriseData,Resources,RateTypestab.•Differentratesmayberequiredfordifferentclientssuchasinternalprojectratesandrates

fordifferenttypesofexternalclients.

•ThedefaultrateforaprojectisselectedwhenaprojectiscreatedandmaybechangedintheProjectsWindow,EPStab,SelectProjectPreferences,Defaultstab,NewAssignments,RateTypedropdownbox.

Fiveresourceandroleratesmaynotbesufficientwhenacompanyhasanumberofclients.Therearesomeoptionswhichincludecreatinganewsetofresourcesfor

Page 316: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

eachproject,oranewdatabaseforeachproject,ornotselectingtheoptionoflinkingcostsandunits.

Roleratesmaynotbevariedovertimeorleveled.

16.2.4LimitsTab

Thistablesetthelimitsforthenumberofrolesthatareavailableforassignment.

ThiswillnotstopyoufromassigningRolesbutwillindicateoverloadinhistogramsandtables.

TheAdminister,MyPreferences,Global,Resources,ResourceAssignments,DisplaytherolelimitbasedonsectionspecifiesforeachuserifthislimitisusedorifthenumberofResourcesassignedtoaRoleisusedtocalculatetheRoleLimit.

Thusdifferentusersmaydisplaydifferentvaluesinreportswhentheyselectdifferentoptionsintheformabove.

16.2.5RoleTeamsTabThisiswhereaRolemaybeassignedtoateamforreportingpurposes:

16.3CreatingResourcesandtheResourcesWindowOpentheResources,Administration,Resourcestabtoview,create,edit,ordeleteresources:

Page 317: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ResourceswouldnormallyhaveahierarchicalstructureinasimilarwaytoaWBSorEPSandare:

•Createdusingthe Addor AddSiblingicons,

•Deletedusingthe Deleteicon,

•Movedaroundinthehierarchicalstructureusingthe Moveicons

TheResourceWindowhasatopandbottompane:•Thebottompaneisopenedbyclickingonatabatthebottomand

•Closedbyclickingonthe MinimizeDetailsbutton:AsummaryResourcemaybeusedaseither:

Page 318: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•PlaceholderorheadingwhichisusedtogroupResourcesofasimilartype,suchasdesignersandthesemaybeplacedundera“Design”resource,buttheDesignresourceneverassignedtoanactivity,or

•AResourcethatmaybeassignedtoactivitiesandtheResourcescreatedundertheparentresource,theparentresourcethencouldrepresenttheirsupervisor.

16.3.1ResourcesGeneralTab

Thefieldsinthistabaremostlyself-explanatory:

•TheResourceIDhastobeuniquewithinadatabaseand•AResourceNameismandatory.

ResourceTypesTherearethreetypesofResources:

•Labor,intendedforpeople,•Nonlabor,intendedforequipmentusedtoperformprojectwork,•Material,intendedformaterials/supplies.

MaterialResourcesMaybeleveledandhavethefollowingdifferencesfromotherresources:

•TheymaybeassignedaUnitsofMeasure,whichiscreatedinAdminister,EnterpriseData,Global,Resources,UnitsofMeasuretab.

LaborandNonlaborresourcesaremeasuredinunitsoftimesuchashoursordaysanddependoneachuser’sindividualUserPreference,thereforebecarefulasdifferentusersmaydisplaydifferentresultsforthesamedata.

Page 319: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•TheymaynotbeassignedaRole.

•TheymaynotlogOvertime.Materialresourcesdonotdisplayunits(quantities)inanActivitiesWindowcolumn,aswithmanyotherproductslikeP3,SureTrak,andAstaPowerproject.Thesevaluesmaybedisplayedinotherviewsandinreports.

•TheEmployeeID,E-MailAddress,TitleandOfficePhoneareoptional,and

•WhentheActiveboxisunchecked,theResourceisinactiveandindicatesthattheresourceisnotavailable.WhenassigningResourcestoActivitiesthereisafiltertodisplayonlyactiveResources.Aresourcewouldbemadeinactivewhenhe/shehaslefttheprojectteambutisassignedtoactivitieswithactuals.

16.3.2ResourceTeamTabThisiswhereresourcesareassignedtoteamsandtheTeamfunctionisusedforreporting:

16.3.3ResourcesRolesTabThisiswhereaResourceisassignedtooneormoreRolesandtheRolesfunctionisusedforreporting:

Page 320: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•AResourcemaybeassignedmorethanoneRole,andtheirProficiencyfortheRole,issetinthistab.

•WhenmultipleRolesareassigned,oneisassignedasthePrimaryRole.

16.3.4ResourcesCodesTab

ResourceCodesareassignedtoResourcesandtheseallowadditionalfacilitiestogroup,sortandreportresourcesandtorecordinformationsuchaspersonaldetailsorofficelocation.

•ResourceCodesmaybedefinedintheResourceCodeDefinitionform,whichisopenedbyselectingAdminister,EnterpriseData,Resources,ResourceCodessection.

•TheyareassignedfromtheSelectResourceCodeformbyclickingonthe AssignResourceCodeicon.

•ResourceCodesmaythenbeselectedinaViewtosortandgroupResources.

16.3.5ResourcesUnitsandPricesTab

Page 321: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

EffectiveDateandRatesEachResourcemayhaveuptofiverates(Price/Unit)andtheseratesmaybevariedovertime.

•TheEffectiveDaterepresentsachangeinRateoravailabilityatthatpointintime.•ThecolumntitlesofPrice/Unit1toPrice/Unit5mayhavetheirdescriptionseditedinthe

Administer,EnterpriseData,Resources,ResourceRateTypessection.ThesetitlesaresharedwithRoles.

•Whenarateisaddedtheeffectivedateisthedatefromwhichtherateisapplied.

ShiftsResourceShiftsareusedinconjunctionwithlevelingandshouldnotbeassignedunlesstheyarebeingused.ResourceShiftsarecoveredintheLevelingchapteroftheProfessionalandOptionalClientbook.

16.3.6ResourcesSettingsTab

CalendarTheResourceisassignedaGlobalorResourceCalendarinthisform.•ASharedCalendarmaybecreatedandassignedtomorethanoneResource.Thistopicis

coveredinmoredetailinthenextsectionofthischapter.

•APersonalCalendarforaresourceasoutlinedintheDEFININGCALENDARSchapter.TheResourcecalendarisusedtodisplaytheresourcelimitsirrespectiveofthecalendarassignedtoanactivity.

DefaultUnits/Time

Page 322: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheDefaultUnits/Timeisthevaluethataresourceadoptswhenitisfirstassignedtoanactivity.InasimilarwaytoMicrosoftProject,theUnitsperTimePeriodmaybedisplayedasaPercentageorinUnits/Time.•SelectAdminister,MyPreferences,TimeUnits,Unit/Timesectiontabandselectthe

preferreddisplayfromtheUnits/TimeFormatsection:

Forexampleyoumayhaveafleetof12trucksandyouusuallyassignfourtruckstoeachloader.InthissituationyouwouldassigntheDefaultUnits/Timeas400%,or4d/d,32h/dor4h/hifthetrucksareworking8hoursperday.

OvertimeALaborResourcemaybeallowedtorecordOvertimeinthePrimaveratimesheetsystemwhentheOvertimeboxischeckedandthecostsderivedfromtheUnitRatesaremultipliedbytheOvertimeFactor.

ResourceandActivityAutoComputeActualsWhenthisoptionischecked,PrimaveracalculatestheActualUnitsbysubtractingtheRemainingUnitsfromthePlannedUnitswhentheApplyActualsfunctionisselected.Thisshouldbeswitchedoffifyouareusingtimesheets.

TheoptionmayONLYbeswitchedonoroffagainstaresourceintheResourcesSettingstabandifchangedintheResourcesSettingstabitwillaffectallresourceassignmentsforallprojectsforthisresource.

TheActivityAutoComputeActualsfieldmaybedisplayedasacolumnintheActivitiesWindow.Whenthisoptionischecked,allResourcesassignedtotheactivityAutoComputeActualsirrespectiveofhowtheyarecheckedintheResourcesWindow:

Page 323: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

CurrencyAnalternateCurrencymaybeassociatedwitharesource.ThiswillnotaffecthowtheResourceUnitRatescostsareenteredbutprovidesafurthertaggingmechanismforsortingandreporting.Thecostsarestoredinthedefaultcurrencybutaredisplayedusingtheconversionrateinthecurrencyselectedfortheresource.

CalculateCostsfromUnitsWiththisoptionchecked,thecostsforaresourcearecalculatedfromtheResourceUnit/Timewhenaresourceisassignedtoanactivity.Whenunchecked,thecostsremainatzerowhenaresourceisassignedtoanactivity.ThiswascalledCostUnitsLinkedinearlierversionsofP6.

Whenaresourcehasbeenassignedtoanactivity,thereisaResourceAssignmentfieldavailableintheAssignmentstaboftheActivitiesWindowtitledCalculateCostsfromUnits.ThisischeckedtomatchtheCalculateCostsfromUnitsfieldintheResourcesWindow.TheActivitiesWindowfieldtitledCalculateCostsfromUnitsisnotlinkedtotheCalculateCostsfromUnitsfieldintheResourcesWindowandonlyadoptsthesettingwhenaresourceisassignedtoanActivity.

16.3.7NotesTabNotesmaybeaddedherebuttherearenoNotebookstopicsavailabletoResources.

16.4Workshop13–AddingResourcestotheDatabase

Page 324: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

BackgroundThisworkshopwillonlyuseResourcesandthesemustnowbeaddedtothedatabase.

Wehaveupdatedourcurrentproject,butweneedaprojectthathasnotbeenupdatedforthenexttaskofassigningresources.Therefore,wewillhavetorestoretheBaselineschedulesavedpriortoupdatingthecurrentscheduletoprovideanunprogressedscheduleforthisexercise.

NOTE:Ifyouareworkinginadatabasewithotherpeoplecompletingthisworkshoptheneachperson’sResourceIDwillhavetobeunique,saybyaddingyourinitialsattheendofeachResourceID.Atrainingcourseleaderordatabaseadministratorshouldadvisehere.

Assignment1.SelectProject,Activities,Actions,DefineBaselines…andremoveallprojectBaselines

bysettingtheBaselinestothe<CurrentProject>.2.NOTE:BaselineBarswillnowdisplaythePlannedDatesandtheseshouldnotbe

displayed.

3.Clickonyouprojectandrestoretheprojectusingthe RestoreaBaselineicon.4.GototheProjects,EPSwheretherestoredbaselinefilewillbevisible.5.RenametherestoredBaselineprojectBidforFacilityExtension–ResourcedSchedule

andchangetheProjectIDtoOZB-R.NOTE:UserssharingadatabasewillneedtouseuniqueProjectIDs.

6.SaveyourchangesandopenONLYtherestoredBidforFacilityExtension–ResourcedScheduleproject.

7.OpentheMyPreferencesform,settheResourcesandTimeUnitstabasperthefollowing.Continued…

Page 325: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.NowopentheResource,Administration,Resourcestab.9.FormatthecolumnsintheResourcesWindowasinthefollowingpicture.10.Addtheresourcesinthepicturebelowusingthe Addresourceor Addchild

icons:NOTES:Ifyouareworkinginadatabasewithotherpeoplewhencompletingthisworkshopthenyour

administratorshouldhavecreatedaResourceNodeforyoutocreateyourresourcesunder.

Eachperson’sResourceIDwillhavetobeunique,saybyaddingyourinitialsattheendofeachResourceID.

TheUnitsofMeasuremaynotbeavailableinyourdatabase,so:EitheradditinAdminister,EnterpriseData,Global,Resources,UnitsofMeasuretab,or

Ifyouhaveaccess,ordonotassignaUnitofMeasure.

11.Youmayneedtousethearrowsonthe Moveiconstomovetheresourcestothecorrectindentlocation.

12.EnsurethattheresourceEffectiveDateintheUnits&Pricestabissetto2December2013orearlierotherwisetheResourcewillbedelayedbeyondthisdatewhenlevelingtheresources.

13.UsetheResourcedefaultPrice/UnitintheUnits&Pricestabasperthetablebelow,whichisnormallyPrice/Unit1orStandardRate:

NOTES:YouwillneedtosavetheresourcesbeforeyoumayaddtheUnitRates.Youshould

Page 326: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

useyourdatabasecurrency.

ProjectManager 120.00/h

SystemsEngineer 90.00/h

ProjectSupport 80.00/h

PurchasingOfficer 70.00/h

ClericalSupport 50.00/h

ReportBinding 100.00/Each

14.SettheDefaultUnits/Timeto8hoursperdayforalltheresources.15.SetthecalendarforallresourcestobeaGlobal5-DayWorkweek,with8hoursperday,

yourcalendarmaybecalledaStandard5Day/Weekorsimilar.

16.CheckCalculateCostsfromunitsandAutoComputeActualsforeachresource.

Page 327: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17ASSIGNINGROLES,RESOURCESANDEXPENSES

17.1UnderstandingResourcesDuringtheplanningstage,RolesmaybeassignedtoActivitiestogainanunderstandingofthelong-termresourcedemandandtheyarelaterreplacedbyaResourcewhenitisknownwhowillbeundertakingthework.IfyouarenotusingnamedresourcesthenyoushouldconsidernotusingRoles,asResourceshavemorefunctionalitythanRoles.AResourcemaybeassigned:

•DirectlytoanActivity,or

•ToaRolewhichhasbeenassignedtoanActivity.

Therearethreetypesofresources,Labor,NonlaborandMaterial,asdiscussedinthepreviouschapter.ALaborResourcehasadditionalfunctionalityincludingOvertime,ResourceCalendars,ShiftsanduserdefinedAutocostrules.TheLaborandNonlaborresourcesaresimilartotheMicrosoftProjectWorkResources.AMaterialresourceissimilartoMicrosoftProjectMaterialResources,butmaynothavetheunitsdisplayedinActivitiesWindowcolumns.

PrimaveraalsohasafunctiontitledExpenses,wherecostsmaybeassignedtoactivitieswithoutresourcesandmaybeassignedaquantityandthedefaultquantityisone.ThisfunctionissimilartotheCostResourcefunctioninMicrosoftProject.Astheprojectprogresses,ActualandToCompleteUnitsandCostsmaybeassignedtoExpensesinthesamewayasresources.ExpenseunitsmaynothavetheunitsdisplayedinActivitiesWindowcolumns,maynotbeassignedResourceCurves,butmayhavecostsassignedbeforetheactivityhasstarted,mayhaveRemainingCostswhentheactivityiscomplete,andmaybeassignedtoMilestones.

Thefollowingarethemorecommonlyusedfunctions:

Topic MenuCommands

•SetUnits/TimeFormatandResourceAssignments

SelectAdminister,MyPreferencestoopentheMyPreferencesformandselecttheTimeUnitsFormattabandResourcestab.

•SetDefaultDurationTypeandDefaultActivityType

SetthesedefaultsintheProjectPreferencesformbyselectingProjects,EPS,selectyourproject,SetProjectPreferences…,Defaultstab.

•AssignaRoletoanActivity

SelecttheAssignmentstabintheProjects,Activitydetailsformandclickonthe AssignRoleicononthetoolbartoopentheSelectRolesform.

•Toassigna

Page 328: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ResourcetoaRolethathasbeenassignedtoanactivity

SelecttheRoletobeassignedaResourcefromtheAssignmentstabandclicktheResourceNamefieldtheSelectResourceformandViewbyAssignedResource.

•ToassignaResourcetoanactivitywithoutaRole

SelecttheActivitytobeassignedtheResourceandclicktheiconontheAssigntoolbartoopentheSelectResourceform.

•ToassignRequestResourcesforanactivitywithaRoleassignment

SelecttheRoletobeassignedaRequestedResourcefromtheAssignmentstabandclickthe RequestResourcesicontheSelectResourceformandopentheOpenarequestforaresourceform.

17.2UnderstandingResourceCalculationsandTerminologyAResourcehasthreeprincipalcomponentsafterithasbeenassignedtoanActivity:

•Quantity,intermsofWorkinhoursordaysorMaterialquantitiesrequiredtocompletetheactivity,whicharereferredtoasUnitsbyPrimavera,

•TheResourceUnitRateistermedPrice/UnitinPrimavera,and•Cost,whichiscalculatedfromtheResourceUnitRatexUnits.

EachResourceandExpensehasthesamefourfieldsforCostsandUnits,whichare:•Planned,

•Remaining,

•Actualand

•AtCompletion.

TherelationshipamongthesefieldschangesdependingonwhethertheactivityisNotStarted,In-ProgressorComplete.

•WhenanactivityisNotStartedandthe%Completeiszerothen:

PlannedisnormallylinkedtoRemainingandAtCompletionandthereforeachangetoonewillchangetheothertwoandtheywillalwaysbeequal,and

Actualwillbezero.•WhentheactivityismarkedStartedandwouldnormallybeIn-Progressandthe%

Completeisbetween0.1%and99.9%then:

PlannedbecomesunlinkedfromRemainingandAtCompletion,thusallowingprogressandtheAtCompletionvaluetobecomparedtothePlannedvalue(ofthecurrentproject),oraBaselinePlannedvalueoraBaselineAtCompletionvalue,and

Page 329: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AtCompletion=Actual+RemainingandhavealinktotheUnit%Complete,whereachangeinvaluetoonewillresultinachangetotheothervalues.

•WhentheactivityisCompleteandtheUnits%Completeis100%then:

Remainingissettozero,andAtCompletion=Actual.

ThePlannedvaluesforCostsandUnitsarelinkedtotheAtCompletionvaluesuntil:

•AnActivityhasbeenmarkedasStartedorhasa%Complete,or

•TheLinkplannedandatcompletionfornotstartedactivitiesintheProjectWindowCalculationstabisunchecked,seethefollowingpicture:

InP3onewouldoftenunlinkBudget(Planned)andAtCompletionwhenaprojecthasbeenapprovedandare-estimateisrequiredwhilemaintainingtheBudget.

ThisfunctioninP6alsounlinksthePlannedDurationfromtheAtCompletionDurationforun-startedactivitieswhichaddsanothercomplicationthatshouldbeavoided.

ThecomparisonofthecurrentAtCompletionCostsisnormallymadewiththeBaselineprojectAtCompletionvalues.ThereforetheBudgetvalueinthecurrentscheduleiseffectivelyaredundantvalueandprobablyshouldnotbedisplayed.

SomepeopleconsiderthePlannedValueintheCurrentScheduletorepresenttheEstimatedValueofwork,orpossiblythevalueofunapprovedscopechangesandwhenaBaselineissetthePlannedValueorAtCompletionValueintheBaselineschedule.

17.3ProjectPreferencesForm,ResourceDefaultsPreferencesanddefaults(whichmaybechangedforeachresourceassignment)thataffecthowallresourcesinaprojectarecalculatedaresetintheProjectPreferencesformandpertaintoallactivitiesandresources.

TheDefaultstabintheProjectsPreferenceshassomeoptionsthatmustbeunderstood.

Page 330: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.3.1RateTypeTherearefiveResourceRatesavailableinPrimavera.Oneratemaybesetasaprojectdefault.Afterassignmenttoanactivity,theResourceRatemaybechangedusingtheRateTypefieldintheAssignmentstaboftheActivitiesWindow.

17.3.2ResourcescanbeassignedtothesameactivitymorethanonceCheckingtheResourcescanbeassignedtothesameactivitymorethanonceboxenablesaresourcetobeassignedtoanactivitymorethanonce.Thisisusefulifitisrequiredtoassignaresourceatthebeginningofanactivityandlaterattheendofanactivitywithalag.

Forexample,onemaywanttoassignacraneonthefirstdayoftheactivitytoassistinerectingandonthelastdaytoassistindismantling.Thischeckboxneedstobecheckedforaresourcetobeassignedtwicetoanactivity.

TheWebClientdoesnotallowtheassignmentofaresourcelag,butresourcesmaybesetuphereforuseintheWindowsClient.

17.3.3UnderstandingResourceOptiontoDriveActivityDatesByDefaultAresourcehasthefollowingfields:

Page 331: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•PlannedDuration.Thedurationthataresourceisworking,•Start.Thedatetheresourcestartswork,and•Finish.ThisdateiscalculatedbytheadditionoftheActivityStartDate+thePlanned

Duration.

WhentheDriveActivityDatesoptionisswitchedoffitispossibleforaresourcetocalculateoutsidetheactivityduration.Inthefollowingexampletheactivitiesare5dayslongandtheresourcesassignedtoeachactivityareworkingfor10days.Thishasresultedintheresourcebeingoverloaded.TheResourcesacknowledgetheactivityStartdatebutnottheFinishDate.

TheWindowsClientscreenshotsareclearer:

NowtheDriveActivityDatesoptionhasbeencheckedagainsteachactivity,theactivitiesarenow10dayslong,andtheresourceisnotoverloaded.

Page 332: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheClientscreenshotsareclearer:

ItisrecommendedthattheDriveactivitydatesbydefaultboxisalwayschecked,thusResourceswillbeassignedasDriveActivityDatesandthisensuresthatallworkiscontainedwithinthedurationofanactivity.TheActivityStartiscontrolledbytheActivityCalendar,thereforewhenanactivityisResourceDrivenitisimportanttosetanActivityCalendarthatwillallowtheresourcetostartworkwhenitisrequiredtostart.Thusifthereisamorningshiftstartingat4:00am,theActivityCalendarshouldstartat4:00amorearlier.InscheduleswithcomplexresourcecalendarsyoumaywishtoconsiderplacingalltheResourceDrivenactivitiesona24x7calendarandthenallresourceworkwillbecontrolledbytheresourcecalendars.

17.3.4Price/UnitThisrateisalsousedtocalculatetheresourcecostswhenanactivityisnotassignedrolesorresourcesbutisassignedaquantityintheActivitieslowerpane,Generaltab.•LaborUnitsenteredinthePlannedLaborUnits:

Page 333: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•LaborCostcalculatedinthePlannedLaborCost:

TheotherfunctionsinthistabaffecttheupdatingofresourcedactivitiesandarecoveredintheUPDATINGARESOURCEDSCHEDULEchapter.

ThisisknowninWindowsClientasthePrice/UnitforactivitieswithoutresourceorrolePrice/Units.

17.3.5ActivityTypeTherearefiveActivityTypesthatmaybesetasadefaultintheDefaultstabintheProjectsPreferenceschangedintheGeneraltabintheActivitiesWindow:

ActivityType Notes

TaskDependent

ActivitiesassignedasTaskDependentacknowledgetheirActivityCalendarwhenschedulingandtheFinishDateiscalculatedfromtheActivityCalendar.Resourcesignoretheirowncalendarsforcalculationpurposes

ThisActivityTypeisusedtoindicatethecommencementofaPhase,Stage,or

Page 334: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

StartMilestone

amajoreventinaproject.

•IthasonlyaStartDateandnoDuration,

•TheFinishDateissettobethesameastheStartDateandnotblankasintheP6WindowsClient.

•ItmayonlyhaveStartConstraintsassigned.•Itmaynothavetime-dependentresourcesassignedbutmayhave:

AnOwnerassignedfromthelistofuserstoindicatewhoisresponsiblefortheactivity.“Owner,”thenewactivityfieldinPrimaveraVersion6.0,enablesauserwhoisNOTaresourcetobeassignedresponsibilityforanactivity.

APrimaryResourceassignedfromtheActivitiesWindow,GeneraltabwhomayupdatetheMilestone,butnoeffortisassignedorrecorded.

FinishMilestone

ThisActivityTypeisusedtoindicatethecompletionofaPhase,Stage,oramajoreventinaproject.

•IthasonlyaFinishDateandnoDuration.

•TheStartDateissettobethesameastheFinishDateandnotblankasintheP6WindowsClient.

•ItmayonlyhaveFinishConstraintsassigned.•Itmaynothavetime-dependentresourcesassignedbutmayhave:

AnOwnerassignedfromthelistofuserstoindicatewhoisresponsiblefortheactivity.“Owner,”thenewactivityfieldinPrimaveraVersion6.0,enablesauserwhoisNOTaresourcetobeassignedresponsibilityforanactivity.

APrimaryResourceassignedfromtheActivitiesWindow,GeneraltabwhomayupdatetheMilestone,butnoeffortmaybeassignedorrecorded.

ResourceDependent

ActivitiesassignedasResourceDependentacknowledgetheirResourceCalendarwhenbeingscheduled.ThisissimilartoanIndependentActivityTypeinP3andSureTrakandtheresourcesworkindependentlyanddonothavetobeavailableatthesametime.

TheActivityFinishDateiscalculatedbasedonthelongestResourceDurationwhentheresourceoptionofDriveActivityDatesischeckedagainsttheresourceassignment.

Theactivitystartdatecalculatedontheactivitycalendar,nottheresourcecalendar,maydelaythestartofanactivitywhentheresourcecalendarhaslongerworkinghoursthantheactivitycalendar.

ThisActivityTypespansotherActivities.ThereforetheStartDate,FinishDate,

Page 335: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

LevelofEffort(LOE)

andDurationsmaychangeasthestartorfinishdateofactivitiesthatitisdependentuponchangeduringschedulingorupdating.

LOEActivityTypeissimilartoaHammockinP3andSureTrak,butmorerelationshipsmaycontroltheStartandFinishDates.ThereisnoequivalentinMicrosoftProject.ALevelofEffortactivitydoesnothavetheAstaPowerprojectHammockoptiontodisplaytheactivitiesitspansbelowtheLOEactivity.

Thistypeofactivitydoesnotcreateacriticalpathirrespectiveofthefloatcalculationsthataredisplayed.

TheStartDatemaybecontrolledbythefollowingrelationships:

•Finish-to-Startpredecessors

•Start-to-Startpredecessors

TheFinishDatemaybecontrolledbythefollowingrelationships:

•Finish-to-Finishpredecessors

•Start-to-Finishpredecessors

ResourcesassignedtoaLevelofEffortactivityarenotconsideredincalculationswhenascheduleisLeveled.LevelofEffortactivitiesmaynotbeassignedaConstraint.ThepicturebelowshowsthreedifferentwaysaLOEactivitymaycalculateandthetwoTaskDependentactivitiesareheldinplacebyconstraints

NOTE:DonotschedulewithaLOEactivityunlessithasrelationships.IfyoudoscheduleitwillcalculatetoazerodurationandbemarkedasCompleteontheDataDate.YouwillthenhavetomarkitasnotstartedintheActivitiesWindow,GeneraltabandassignadurationsoyoucanseeitontheGanttChart.

ThenewPrimaveraVersion5.0WBSSummaryActivityisanactivitythatspansthedurationofallactivitieswhichareassignedexactlythesameWBSCodeand,unlikeaLevelofEffortActivity,donothaveanypredecessorsorsuccessors.

Page 336: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

WBSSummaryActivity

ThereforeaWBSactivitywillchangedurationwheneithertheearlieststartorlatestfinishofactivitiesthatitspansischanged.Thismayhappenastheprojectprogressesandactivitiesdonotmeettheiroriginalscheduleddates,orthedurationofanactivityischanged,orlogicischanged,orthescheduleisleveled.

ThisfunctioncalculatestheWBSActivityDurationinthesamewayasWBSactivitiesinP3orSureTrak,orTopicactivitiesinSureTrak.ItissimilartothewaySummaryactivitydurationsarecalculatedinMicrosoftProject,excepttheactivitiesdonotneedtobedemotedbelowthedetailedactivitiesasinMicrosoftProject.

WBSactivitiesmaybeusedfor:

•ReportingatsummarylevelbyfilteringonWBSactivities,

•EnteringestimatedcostsatsummarylevelforproducingcashflowtableswhilethedetailedactivitiesareusedforcalculatingtheoveralldurationfortheWBSandday-to-daymanagementoftheproject,and

•Recordingcostsandhoursatsummarylevelwhenisitnotdesirableorpracticaltorecordatactivitylevel,especiallywhenthedetailedactivitiesareliabletochange.

ItdoesnotmatterhowactivitiesareGroupedastheyalwaysspanactivitieswiththesameWBSCode.

Page 337: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.3.6DurationTypeTheDurationTypebecomeseffectiveafteraresourcehasbeenassignedtoanactivity.TheDurationTypeforallnewactivitiesissetinintheProjectPreferencesformbyselectingProjects,EPS,selectyourproject,SetProjectPreferences…,Defaultstab:

TheDurationTypeforeachnewactivitymaybechangedintheActivitiesWindow,GeneraltaborbydisplayingtheDurationTypecolumn:

Page 338: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

TheDurationTypedetermineswhichofthefollowingvariableschangewhenoneoftheothersischangedintheequation:

•ResourceUnits=ResourceUnitsperTimePeriodxDuration

Forexample,a40-houractivitywith2peopleworking8hoursperdaywilltake20hoursor2.5days:

•40hoursofwork=2peopleperhourx20hours

Whenanactivityisin-progressthisequationismodifiedto:

•RemainingResourceUnits=ResourceUnitsperTimeperiodxRemainingDuration

PrimaverahasfouroptionsforDurationType,MicrosoftProjecthasthreeoptions,andP3andSureTrakhavetwooptions(whicharealoteasiertounderstand).

ThePrimaveraterminologythatdescribesthewaythesoftwaretreatstherelationshipbetweenDurations,ResourceUnitsandResourceUnits/TimePeriodisdifferentfromMicrosoftProject,P3,andSureTrak.Primaverahasmoreoptionsthanalltheotherproductsandthisgivestheproductmoreflexibility.Thefollowingtableshouldclarifytheseoptions:

PurposeoftheDurationTypes

DurationType Purpose

Option1ThisoptionisusedwhentheDurationofanactivityshouldnotchangewhenResourcesareaddedorremovedorUnits/Timechanged.

Forexample,whenthetimetocompleteanactivityisfixed,theresourcesmaybemanipulateduntilasatisfactoryresourceloadingisestablishedwithouttheactivitydurationchanging.

Page 339: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•FixedDuration&Units

Option2AchangetotheDurationwillchangetheUnits/Time;however,theUnitswillremainconstant.

Ifonepersonisassignedtoanactivityfor8hoursperdayandtheactivityisdoubledinduration,therewillbenowbeonepersonworkingontheactivityfor4hoursperdayandtheactivitywillrequirethesamenumberofhourstocomplete.

IMPORTANTPOINT:TheEstimateatCompletionWILLNOTchangewhentheactivitydurationischangedandthenumberofresourcesWILLchange.

•FixedDuration&Units/Time

ThisDurationTypedisablestheMyPreferences,CalculationstaboptionRecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationType.Option1ThisoptionisusedwhentheDurationofanactivityshouldnotchangewhenResourcesareaddedorremovedorUnits/Timechanged.

Forexample,whenthetimetocompleteanactivityisfixed,theresourcesmaybemanipulateduntilasatisfactoryresourceloadingisestablishedwithouttheactivitydurationchanging.

Option2AchangeintheDurationwillchangetheUnits;however,theUnits/Timewillremainconstant.

Forexample,whentherearetwopeopleassignedtoanactivityandtheactivityisincreasedinduration,therewillstillbetwopeopleworkingbutforalongerperiodoftime.

IMPORTANTPOINT:TheEstimateatCompletionWILLchangewhentheactivitydurationischangedandthenumberofresourcesWILLNOTchange.

•FixedUnits

Thisoptionisusedwhentheamountofworkrequiredtofinishanactivityisconstant.

Forexample,ifthereare8,000brickstobelaidandabricklayerisabletolay100bricksperhour,thereare80hoursofworkforonebricklayer,40hoursfor2bricklayersand20hoursfor4bricklayers.ChangingtheDurationortheUnits/Timewillnotchangethenumberofhoursrequiredtocompletetheactivity.

•FixedUnits/Time

Thisoptionisusedwhenthesamenumberofpeoplearerequiredtocompleteanactivityirrespectiveoftheactivityduration.

Forexample,ifamachinerequirestwopeopletooperateitandthereforea

Page 340: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ResourceisassignedtotheActivityat200%,changingeithertheUnitsortheDurationwillnotchangetheUnits/Timeandtherewillalwaysbetwopeopleoperatingthemachine.

ThedurationofbothFixedUnitsandFixedUnits/TimeactivitieswillchangeiftheresourceUnits/TimePeriodorRemainingUnitsarechanged.Itistheauthor’spreferencetouse:

•FixedDuration&Unitswhentheestimateatcompletionmustnotchange,and•FixedDuration&Units/Timewhenthecrewsizemustremainconstant.

Thefollowingtabledisplayswhathappenstotherelationshipineachofthefouroptionswhenonevariableischangedand

•TheMyPreferences,CalculationstaboptionPreservetheUnits,Duration,andUnits/Timeforexistingassignmentsisselected:

DurationType

LaborUnitsChangeinGeneralTab

ActivityDurationChange

ResourceUnitsChange

Units/TimePeriodChange

AddorRemoveResources

FixedUnits/Time

DurationChange

UnitsChange

DurationChange

DurationChange

ActivityUnitsChange,ResourceUnitsConstant,DurationConstant

FixedDuration&Units/Time

Units/TimeChange

UnitsChange

Units/TimeChange

UnitsChange

ActivityUnitsChange,ResourceUnitsConstant,DurationConstant

FixedUnits

DurationChange

Units/TimeChange

DurationChange

DurationChange

ActivityUnitsChange,ResourceUnitsConstant,DurationConstant

FixedDuration&Units

Units/TimeChange

Units/TimeChange

Units/TimeChange

UnitsChange

ActivityUnitsChange,ResourceUnitsConstant,DurationConstant

Thefollowingtabledisplayswhathappenstotherelationshipineachofthefouroptionswhenonevariableischangedand

•TheMyPreferences,CalculationstaboptionRecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationTypeisselected:

LaborUnits Activity Resource Units/Time

Page 341: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

DurationType

ChangeinGeneralTab

DurationChange

UnitsChange

PeriodChange

AddorRemoveResources

FixedUnits/Time

DurationChange

UnitsChange

DurationChange

DurationChange

ActivityUnitsConstant,ResourceUnitsChange,DurationChange

FixedDuration&Units/Time

Units/TimeChange

UnitsChange

Units/TimeChange

UnitsChange

ActivityUnitsChange,ResourceUnitsConstant,DurationConstant

FixedUnits

DurationChange

Units/TimeChange

DurationChange

DurationChange

ActivityUnitsConstant,ResourceUnitsChange,DurationChange

FixedDuration&Units

Units/TimeChange

Units/TimeChange

Units/TimeChange

UnitsChange

ActivityUnitsConstant,ResourceUnitsChange,DurationConstant

•Bolddescriptionsintherightcolumninthetableindicatethedifferencesfromtheuppertable.

•TheMyPreferences,CalculationstaboptionPreservetheUnits,Duration,andUnits/TimeforexistingassignmentswillnotfreezetheActivityUnitswhentheDurationTypeofFixedUnitsisselected.

17.4MyPreferencesApplicabletoAssigningResourcesSelectAdminister,MyPreferencestoopentheMyPreferencesform:

17.4.1Units/TimeFormatTheUnits/TimeFormatenablesMicrosoftProject-styleformattingofResource/TimeFormatshowingResourceutilizationasapercentageorasunitsperduration.

Page 342: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.4.2ResourceAssignmentsThistabhastwoResourceAssignmentoptions:

•PreservetheUnits,Duration,andUnits/Timeforexistingassignments.Withthisoption,asResourcesareaddedordeletedthetotalnumberofhoursassignedtoanactivityincreasesordecreases.EachResource’shoursarecalculatedindependently.

•RecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationType.Thetotalnumberofhoursassignedtoanactivitywillstayconstantassecondandsubsequentresourcesareaddedorremovedfromanactivity.

NOTE:ThisfunctiondoesnotworkwhentheActivityTypeisFixedDurationandUnits/Time.

TheRecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationTypefunctionissimilartotheMicrosoftProjectEffortDrivenfunction.PreservetheUnits,Duration,andUnits/TimeforexistingassignmentsfunctionissimilartotheMicrosoftProjectNonEffortDrivenfunction.ThereisnosimilarfunctioninP3andSureTrak.

Page 343: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ItisrecommendedthatPreservetheUnits,Duration,andUnits/Timeforexistingassignmentsbeusedasadefaultaseachindividualresourceassignmentdoesnotchangeasresourcesareaddedorremovedfromanactivity.

17.4.3ResourceAssignmentsTheResourceAssignmentsoptionisself-explanatoryandshouldbeconsideredcarefullywhenresourcesandroleshavedifferentrates.IfitisnotunderstoodandsetincorrectlytheresourcemayendupwiththeincorrectunitratewhenassignedtoaRoleorexistingResource.

Whentwousershavedifferentsettingsthismayresultinaschedulehavingtwodifferentratesforthesameresource.

17.5ActivitiesWindowResourceInformation

17.5.1DetailsGeneralFormThisformhasasectiontitledLaborUnitsattherightsideasseeninthefollowingpicture.Thedropdownmenuenablesyoutoselectwhichdataistobedisplayedinthissectionoftheform.

Page 344: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Thereisalinkbetweentheentriesinthisformandthevaluesthatareassignedtoresources:

•ThevaluesinthisformarethesumofthevaluesassignedtoResourcesandRoles.

•Whenthesevaluesareedited,theywillchangethevaluesassignedtoResourcesandRoles.

ItispossibletoenteraLaborUnitvalueintheActivities,Generaltabandnotassignaresource.WhenaresourceisassignedtheresourcewilladoptthisvaluefromtheGeneraltab.ThisrateissetintheDefaultstabintheProjectsPreferencesform.

17.6AssigningandRemovingRolesToassignaRoletoanactivity:

•SelecttheoneormoreactivitytobeassignedtheRole,either

Clickonthe AssignRolesiconontheToolbar,orWhenonlyoneactivityhasbeenselectedclickonthe AssignRolesiconintheAssignmentstab,

•TheSelectRolesformwillopen:

Page 345: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•UsetheViewRolesBy:menutoselecthowtheRolesareorganized,•Clickonthe AssignicontoassigntheRolestotheactivities.

Atthispoint,theRoleshoursandcostsmaybeeditedasrequired.ToremoveaRole:

•SelecttheRole,and

•Clickonthe icon.

17.7AssigningandRemovingResourcesResourcesmaybeassigneddirectlyto:

•AnactivitythathasanAssignedRole,or

•AnActivitywithoutaRole.

17.7.1AssigningaResourcetoanAssignedRole

Page 346: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ToassignaResourcetoaRoleassignedtoanactivity:

•SelecttheactivitytobeassignedaResource,

•SelecttheRoletobeassignedaResourcefromtheAssignmentstab,•ClickintheResourceNamefieldintheAssignmentstab,•Thiswillcreatea OpenDropDownBoxiconintheResourcesfield,clickonthe

icontoopentheSelectResourceform,•UsetheViewResourcesby:dropdownboxandselectingAssignedRolewilldisplayonly

theresourcesthatareassignedtherole,

•SelecttherequiredresourceandclickOK:

Version8.4hasadditionalsearchingfunctionswhenassigningresourcesasperthepicturebelow:

Page 347: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.7.2AssigningaResourcetoanActivityWithoutaRoleToassignaResourcetoanactivity:

•SelecttheactivitytobeassignedtheResource,

•Clickonthe AssignResourceicontoopentheSelectResourceform,•UsetheViewResourcesby:dropdownboxtoselectwhichresourceyouwishtoassign,•Clickonthe Assignicontoassigntheresource.

Page 348: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.7.3RemovingaResourceorRoleBeforeyouremoveaResourceorRolefromanactivitythathasmorethanoneresourceassignedtoit,youmustbeawareofyourResourceAssignmentpreferences.ThesepreferencesdetermineifthetotalnumberofUnitsassignedtotheactivity(orwork)willbereducedorremainconstantasresourcesaredeleted.

Toremovearesource,selectoneormoreResourcesinthebottompaneResourcetabandeither:

•StriketheDelkey,or•Clickonthe DeleteiconontheAssignmenttoolbaratthebottomofthescreen,notthe

atthetopofthescreenwhichwilldeleteanactivity,

•YouwillbepresentedtheconfirmationboxbelowaseachresourceisremovedandclickYes:

Whenthelastresource(s)is(are)removedtherewillbethesamemessage:

•Ifyouselect Yesthentheresourcewillbedeleted,•ButtheresourceUnitsvaluesintheActivitiesWindow,Generaltabwillbeleftatthe

samevalueasbeforeyoudeletedthelastresource.

•YouwillnotreceivetheoptionfoundintheWindowsClienttoResetlaborunitstozeroandyouwillhaveunitsActivitiesWindow,GeneraltabandcostsagainsttheactivitywillbecalculatedfromthevalueenteredinthePrice/Unitfield.

•YouwillnowhavetodeletetheunitsfromtheActivities,Generaltabanddeletetheunitsifyouarenotgoingtoassignmoreresourcestothisactivity.

Page 349: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AtthispointyouwillhaveUnitsandpossiblyCostsassignedtoanactivitythatmaybeseenintheActivitiesWindow,Generaltabwithoutanyassignedresources,whichmaynotbedesirable.WhenyouassignaresourcetoanactivityinthisconditiontheresourcewilladopttheUnitsvaluefromtheActivitiesWindow,Generaltab,ignoringtheDefaultUnits/TimePeriodsetintheResourceWindow,butnormallycalculatetheresourcevaluefromtheresourceRate.

17.7.4AssigningaResourcetoanActivityMoreThanOnceTheoptionintheDefaultstabintheProjectsPreferencesundertheNewAssignmentsheadingenablesaresourcetobeassignedmorethanoncetoanactivity.

AresourcecouldbeassignedtoworkatthestartofanactivityandtheninconjunctionwithResourceLagworkagainattheendofanactivity.

Forexampleyoumayneedacraneonthefirstdayofanactivitytoliftupsomeformworkandonthelastdaytoremovetheformwork.

ThismaybeachievedintheWindowsClientbuttheWebdoesnothavetheoptiontoassignalagtoaresourceassignmentsothistypeofresourcemodelingmaynotbeachievedintheWeb

17.7.5SelectingMultipleItemsinAssignDialogForms

P6R8.3providestheabilitytoassignmultipleresources,roles,predecessorsandsuccessorsatthesametime.

Todothis:

•GototheActivitieswindowintheProjectssection,•OpenanAssignformbyclickingononeoftheiconslocatedonthetoolbarofthe

appropriatetabie..AssignmentstabintheActivityDetailswindowwillhave whilePredecessors/Successorswillhave ;

•SelectseveralitemsbypressingCtrl+ClickorShift+Clicktoselectarange;•Clickonthe buttontoassignallofthemtoanactivitysimultaneously.

ThisfeaturewillnotworkfromtheResourceAssignmentswindowortheResourcePlanningwindow.

Page 350: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.8RequestResourcesARequestResourceisarequestforaresourceandinsummarycalledDemandResourcesintheProfessionalversion:

•AresourceorRoleisrequestedbythe RequestResourcesfunctionintheActivitieswindow,Assignmenttab.

•ThisResourceRequestmaybeviewedbythemanagerinaDashboard:

Page 351: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Themanagerthenassignsaresourcefromthedashboard.

17.9ResourceandActivityDurationCalculationandResourceLags

17.9.1ActivityDurationAnactivityPlannedDuration(oractivityRemainingDurationofanIn-Progressactivity)isadoptedfromthelongestResourceDuration(orResourceRemainingDurationofanIn-Progressactivity)whenmorethanoneresourcehasbeenassignedtoanactivity.

InasituationwheremorethanoneResourcehasbeenassignedtoanactivitywithdifferentUnitsand/orUnits/Time,theResourcesmayhavedifferentdurations.

InthefollowingexampletheActivityDurationis10days,whichiscalculatedfromProjectSupportresourcePlannedDurationof10days:

ThisiscalculatedinasimilarwaytoP3andSureTrakwhenallResourcesaresettoDriving.

Page 352: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.9.2ResourceLag–WindowsClientOnlyIntheWindowsClientaResourcemaybeassignedaLag,thedurationfromthestartoftheactivitytothepointatwhichtheResourcecommenceswork.

InthefollowingexampletheActivityDurationis20days,whichiscalculatedfromtheProjectSupportresourceOriginal(Planned)Lagof10daysplustheresourceOriginal(Planned)Durationof10days:

IntheWebitisnotpossibletoaccesstheResourceLagfield,butifwhenlagisassignedtoaresourceintheWindowsClientthentheincreaseddurationwillbeseenintheWebbuttheuserwillhavenoideafromwheretheincreaseddurationhasbeenderived.

Thepicturebelowdisplaysaresourcewitha10daydurationandtheactivitywitha20dayduration.

17.10Resource,PlanningWindowTheResource,PlanningwindowisoutofthescopeofthisbookbutitallowshighlevelresourceplanningbyallowingresourcesorrolestobeassignedatWBSNodelevel:

Page 353: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

17.11ExpensesExpensesareintendedtobeusedforoneoffnon-resourcetypecostsandcouldinclude:

•Purchaseofofficeequipmenttosetupaprojectoffice,

•Travelcosts,

•Paymentforaconsultant’sreport,

•Insurancecosts,and

•Trainingcourses.

ExpensesmaybecreatedusingtheExpensestabofanactivity.

AnExpenseItemhasthefollowingfields:

•CostsandUnitsaremainlyself-explanatory.Thefollowinginformationisentered:PlannedUnits,ActualUnits,RemainingUnitsandAtCompletionUnits–thequantityoftheExpenseitem.WhenanExpenseiscreateditissetadefaultvalueof1.Ifsettozerothenthecostsaresettozeroandcostsmaynownotbeentered.Price/Unit–thecostperExpenseitem,

ThePlannedCosts,ActualCosts,RemainingCostandAtCompletionfieldsarecalculatedfromtheUnitsandPrice/Unit.

CheckAutoComputeActualstoallowthesoftwaretocalculatetheActualandRemainingCostsandUnits(quantities)basedontheRemainingDuration,whenApplyActualsisused,

AccrualType–thisenablesyoutoselectifthecostsareaccruedorcashflowedatthebeginning,end,oruniformlyoverthedurationoftheactivity.

Page 354: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•FieldsCreatedinAdminister,EnterpriseDataExpenseCategory–SelecttheExpenseCategory.CostAccount–SelectaCostAccountshouldyouwishtoseeorreportthecostsagainstaCostAccount.

•Otherfields

Vendor–Afreeformfieldtoenterthevendororsuppliername.DocumentNumber–AfreeformfieldtoenterthedocumentnumberthatcouldrepresentthePurchaseOrder,Contract,orInvoiceNumber.

UnitsofMeasure–thisisafreefromfieldwhereyoucantypeinformation.ItdoesnotreadfromtheMaterialResourceUnitsofMeasurelist.Description,PlannedUnitsandPlannedCostsintheWebaretheBudgetedUnitsandBudgetedCostsintheWindowsClientforsomeIndustryversions.

17.12SuggestedSetupforCreatingaResourcedScheduleTheorderthattopicsareintroducedinthischapterisalsoasatisfactoryorderofactionsthatshouldbeconsideredwhenpreparingtoassignresourcestoactivities.

Thesimplestcalculationoptionsshouldbeusedasadefault,andmorecomplexoptionsconsideredonlywhenthereisaspecificschedulingrequirement.

Thetablefollowinglistsprocessesandsuggestedoptionsthatcouldbeconsideredwhencreatingaresourcedschedule.Itisimportanttosetalltheparametersbeforetheactivitiesareaddedotherwisealotoftimeiswastedchangingparametersonanumberofactivities.Thesearenotintendedtosuiteveryprojectbutareastartingpointforlessexperiencedusers.

Step SuggestedSettings

•SettheUnits/TimeformatbyselectingAdminister,MyPreferencestoopentheMyPreferencesformandselecttheTimeUnitsFormatsection.

Thereisachoiceofpercentage(50%)orunits/duration(4h/d).Thisshouldbesetonpersonalpreference.Theauthorprefers(4h/d)asthisreducestyping.

•SettheResourceAssignmentsoptionbyselectingAdminister,MyPreferencestoopentheMyPreferencesformandselecttheResources

ItissuggestedthatthePreservetheUnits,Duration,andUnits/Timeforexistingassignmentsisselected.WiththisoptionasResourcesareaddedordeletedthetotalnumberofhoursassignedtoanActivityincreasesordecreases.EachResource’shoursarecalculatedindependently.

TheoptionsunderAssignmentStaffingneedtobecarefullyconsideredandunderstoodsothatwhenResourcesareassignedtoRolesandresource

Page 355: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

section. assignmentsarechangedthattheuserunderstandswhichUnitRateandwhichUnitCostwillremainagainsttheactivity.

•IntheProjects,EPS,SetProjectPreferences…,DefaultstabsetthedefaultActivityType.

ItissuggestedthatTaskDependentisused,aswiththisoptionResourcecalendarsarenotusedmakingtheschedulesimpler.

ResourceDependentshouldbeusedwhenPersonalCalendarsareinuse.

•IntheProjects,EPS,SetProjectPreferences…,DefaultstabsetthedefaultDurationType.

ItissuggestedthatFixedDuration&Unitsisused.WiththisoptiontheActivityDurationdoesnotchangewhenresourceassignmentsarealtered,andwhenanActivityDurationischangedtheUnitsdonotchange,soyourestimateofhoursandcostswillnotchange.

•IntheProjects,EPS,SetProjectPreferences…,DefaultstabsetthedefaultPercentCompleteType.

TheauthorpreferstousePhysicalasthisenablestheActivityPercentCompletetobeindependentoftheActivityDurations.

•IntheProjects,EPS,SetProjectPreferences…,Defaults:

UnlessmultipleRatesarebeingusedthenPrice/UnitorStandardshouldbeselected.

CheckDriveactivitydatesbydefault.

17.13Workshop14–AssigningResourcesandExpensestoActivities

BackgroundTheResourcesmustnowbeassignedtotheirspecificactivities.

AssignmentOpentheOzBuildwithResourcesprojectandcompletethefollowingsteps.

1.EnsureyouhaveonlytheBidforFacilityExtension–ResourcedScheduleopen.2.ApplytheWorkshop6-Dates&DurationsViewandsaveasWorkshop16–

AssigningResourcesView.3.SetyourMyPreferencesasbelow,useyouowncountriescurrencyifyouwish:

Page 356: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

4.IntheActivitiesWindowselecttheCreateTechnicalSpecificationactivity,5.DisplaytheExpensestabinthebottomwindow.6.AssignanExpensetotheCreateTechnicalSpecificationactivityperthepicture

below:

7.FormattheAssignmentstabwiththecolumnsshowninthefollowingpicture:

Continued…

8.SaveyourViewasWorkshop14–AssigningResources.9.AddtheResourceNamescolumntotheGanttChartperthepicturebelow.10.AssignthefollowingResourcestotheActivitiesusingtheAssignmentstab

AssignResourceicon:

Page 357: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

11.Enter3asthePlannedUnitsandAtCompletionUnitsfortheReportBindingassignment.

12.Addthecolumnsasperbelowandyouranswershouldlooklikethis:

13.ChangetheMyPreferences,TimeUnits,UnitsFormat,UnitsperTimetoDaysandviewthedifference:

Page 358: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

14.YouwillnoticethatthereisnocolumntodisplaytheMaterialsquantityatcompletion.

Inamulti-userenvironmentitisimportantthatallusershavethesameMyPreferencesotherwiseeachpersonmaydisplaydifferentQuantitiesatcompletion.

15.ChangetheMyPreferences,TimeUnits,UnitsFormat,UnitsofTimetoHours.16.SaveyourViewasWorkshop14–AssigningResources.

Page 359: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

18RESOURCEOPTIMIZATIONTheschedulemaynowhavetoberesourceoptimizedto:

•Reducepeaksandsmooththeresourcerequirements,thusreducingthemobilizationanddemobilizationcosts,ortoreducethedemandforsitefacilities,or

•Reduceresourcedemandtotheavailablenumberofresources,or

•Reducedemandtoanavailablecashflowwhenaprojectisfinancedonincome.

18.1ReviewingResourceLoadingThereareanumberoffacilitiesforreviewingresourceloadingwhichconsistofeitherdisplayingaVieworrunningareport.TheTimescaleintervalaffectsthedisplays.Viewswillnotbecoveredindetail,astheyareself-explanatory.

ItisimportantthatthedatatobereviewedisSummarizedbeforeanyresourceanalysisisundertakenbysettingaProjects,ProjectScheduledServiceorbyselectingProjects,EPS, SummarizeProjects.

18.2AssignmentsViewThisviewallowsthedisplayofResourceAssignments,

•ThiswindowisdisplayedbyselectingtheResources,Assignmentstab.•ThepicturebelowshowstheOzBuildWorkshopresourcesonly.Thiswindowhasthree

panesasindicatedbythearrows:

ThelefthandpanethatjustdisplaystheActivityName.Thecenterpanehascolumnsofdataand

TherighthandpanemaydisplayTimePhasedDataoraGanttChartorbehiddenandthereforecapableofdisplayingalargertable:

Page 360: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ResourcesAssignmentsViewsViewsmaybecreatedinthesamewaysasActivityViewsusingtheViewicondisplayedbelow:

LeftHandPane•ThisonlydisplaystheActivityName.

•The GroupandSortandtheFiltericonswillallowausertoformattherowsofdatabygrouping,sortingandfilteringtheactivitiesfromthedatabase.

CenterPane•Datacolumnstobedisplayedmaybeselectedusingthe Columnsicon.

RightHandPaneTimePhasedDataTodisplaytimephaseddataincolumns:

•Clickonthe UsageSpreadsheeticon,•Clickonthe UsageOptionsicon(whichisthesameastheUsageSpreadsheeticon)to

opentheCustomizeUsageOptionsform,andselectwhichrowofdataistobedisplayedinthetable.

Page 361: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

RightHandPaneGanttChartTodisplayaGanttChart:

•Clickonthe GanttCharticon,asperthepicturebelow,and•Thebarsareformattedwiththe GanttChartOptions iconinthesamewayasthe

GanttChartintheProjects,Activitiesview.

RightHandPaneHiddenTohidetherighthandpaneanddisplayalargercentertable:

•Clickonthe Tableicon:

FiltersFiltersshouldbeusedtoreducetheamountofdatathatisdisplayedonthescreenandassignmentfiltersarecreatedinasimilarwaytothewayfilteringactivitieswasoutlinedintheFORMATTINGTHEACTIVITYWINDOWANDVIEWSchapter.ThepicturebelowisfilteringontheOzBuildProjectIDOZB-R:

Page 362: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

GroupingGroupingshouldbeusedtodisplaytheresourceassignmentdatainthewayyouwouldlikeitformatted.GroupingassignmentdataiscreatedinasimilarwaytothewaygroupingactivitieswasoutlinedintheFORMATTINGTHEACTIVITYWINDOWANDVIEWSchapter.ThepicturebelowisfilteringontheOzBuildProjectIDOZB-R:

18.3Resources,Analysis,RoleUsageWindowThiswindowallowsdisplayby:

•RoleHierarchyorRoleTeam,

•SpreadSheetorHistogram:

Page 363: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Customizeallowssomeformattingoptions:

Page 364: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

18.3.1Resources,Analysis,ResourceUsageWindowThiswindowallowsdisplayby:

•ResourceHierarchy,ResourceTeam,ResourceCodes,ResourceCodes(enablingviewingbyanofficeorlocation)orPrimaryRole,

•SpreadSheetorHistogram:

IntheSpreadsheetDisplayyoumaydoubleclickonaprojecttoseetheactivitiestheresourceisassigned:

Page 365: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AfterclickingonArcadia–AutomatedSystemsprojecttitleinthepictureabove:

18.3.2Resources,Analysis,ResourceAnalysisWindowThiswindowallowsHistogramdisplayby:

•ResourceHierarchy,ResourceTeam,ResourceCodes,ResourceCodes(enablingviewingbyanofficeorlocation)orPrimaryRole,

•ThereareoptionsofHistogram,StackedHistogram,AreaChartorPieChart,

•ThepicturebelowdisplaystheStackedHistogram:

Page 366: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ThepicturebelowdisplaystheAreaChart:

•ThepicturebelowdisplaysthePieChart:

Page 367: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Tobeabletoviewdatainchartsyouwillhavetoperformsomeformattingbyfilteringoutthedatayouwishtoview,changingthetimescaleandsettingthedisplayunits.

TheCustomizebuttonwillopenuptheSelecttheinformationtodisplayinthechartform:

Page 368: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

18.4MethodsofResolvingResourcePeaksandConflictsMethodsofresolvingresourceoverloadproblemsare:

•RevisingtheProjectPlan.Reviseaprojectplantomitigateresourceconflicts,suchaschangingtheorderofwork,contractingworkout,orusingoff-sitepre-fabrication,etc.

•DurationChange.Increasetheactivitydurationtodecreasetheresourcerequirements,soa5-dayactivitywith10peoplecouldbeextendedtoa10-dayactivitywith5people.

•ResourceSubstitution.Substituteoneresourcewithanotheravailableresource.•IncreaseWorkingTime.Thismayreleasetheresourceforotheractivitiesearlierandis

createdbyworkingmoredaysperweekorhoursperday.

•Splitanactivityaroundpeaksindemand.Somesoftwareenablesthesplittingofactivities,whichinturnenablesworktobesplitaroundpeaksinresourcedemand.ThesplitfunctionisnotavailableinPrimavera,however,anactivitymaybesplitintwoindividualactivitiestoallowtheworktoceaseintimesofpeakdemand.Ifoneneedstorelatebacktoabaselinethentwonewactivitiesmaybecreatedtorepresentthesplitandtheoriginalactivitymadeintoahammocktospanthetwonewactivities,butremembertodisplaythe

Page 369: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

LOEBaselineBar.

•Levelingtheschedule.Thistechniquedelaysactivitiesuntilresource(s)areavailable.•ResourceCurvesmayassistinsomeinstances.

18.5Workshop15–ResourcesOptimization

Assignment1.BeforeanyUsageorAnalysisdatawillbedisplayedaprojectmustbeSummarized.Go

toProject,EPS,selecttheOZB-R–BidforFacilityExtension–ResourcedScheduleproject,rightclickandselectSummarizeProjects,

2.DisplaytheAssignmentsWindowbyselectingtheResources,Assignmentstab.3.CreateanAssignmentsviewtitledOzBuildAssignmentsthatissimilartothepicture

below:

CreateafilterthatselectonlyyourBidforFacilityExtension–ResourcedScheduleproject:

CreateagroupingbyProjectandthenResource:

Page 370: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

DisplaytheGanttChart:

4.DisplayaResourceUsageHistogramfortheOzBuildResourcesintheResources,Analysis,ResourceAnalysiswindow:SelecttheOzBuildresourcesProjectManager:

ClickontheCustomizebuttontoopenuptheSelecttheinformationtodisplayinthechartformandsettheoptionasperbelow:

Page 371: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Createafilterasperbelow:

Page 372: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

GroupbyProjectandyourpictureshouldbeasperbelow:

NowtrytheAreaChartandotheroptionssuchasselectingotherresources.

Page 373: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

19UPDATINGARESOURCEDSCHEDULEItisoftenconsideredbestpracticetoupdateaprojectbetween10and20timesinitslifecycle.Somecompaniesupdateschedulestocorrespondwithaccountingperiods,whicharenormallyeverymonth.Thisfrequencyisoftentoolongforprojectsthatarelessthanayearinduration,astoomuchchangemayhappeninonemonth.Therefore,morefrequentupdatingmayidentifyproblemsearlier.

Updatingaprojectwithresourcesemploysanumberofpreferencesandoptions,whichareveryinteractiveandwillrequireasignificantamountofpracticebyausertounderstandandmasterthem.

Afterreadingthischapterandbeforeworkingonaliveproject,inexperiencedusersshouldgainconfidencewiththesoftwareby:

•CreatinganewprojectandsettingtheDefaults,Preferences,andOptionstoreflectthemethodinwhichyouwishtoenterinformationandhowyouwantPrimaveratocalculatetheprojectdata.

•Creatingtwoorthreeactivitiesandthenassigningtwoorthreeresourcestoeachactivity.

•UpdatingtheActivitiesandResourcesasifyouwereupdatingascheduleandobservetheresults.

•Alteringthepreferencesanddefaultsifyouarenotreceivingtheresultyourequire.Re-updateandnotethepreferencesanddefaultsforfuturereference.

Someofthesesettingsmayhavebeensetbyyourorganizationandyoumaynotbeassignedaccessrightstochangethesettings.Youshouldstillgothroughtheupdatingprocessinatestprojectwithdummydatasimilartoyourrealprojectdataandbepreparedtochangethosesettingstowhichyoudohaveaccess,asrequired.

Updatingaprojectwithresourcestakesplaceintwodistinctsteps:

•Thedates,durationsandrelationshipsareupdatedusingthemethodsoutlinedintheUPDATINGANUNRESOURCEDSCHEDULEchapter,and

•TheResource,ExpensesUnits(hoursandquantities)andCosts,boththeActualtoDateandToComplete,arethenupdated.ThesevaluesmaybeautomaticallyupdatedbyPrimaverafromthe%CompleteorimportedfromaccountingandtimesheetsystemsorupdatedbythePrimaveraTimesheetsystem.

Adecisionneedstobemadeaboutwhatdataistobeenteredorimportedintothescheduleandwhatdataistobecalculatedbythesoftwareandthesoftwareoptionssetappropriately.

Thischaptercoversthefollowingtopics:

•UnderstandingPlannedvaluesandBaselineProjects•UnderstandingtheCurrentDataDatewithrespecttoresources•Informationrequiredtoupdatearesourcedschedule

•ProjectPreferencesandActivitiesDefaults

•UpdatingResourcesandExpenses

Page 374: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Reviewingtheupdatedschedule.

19.1UnderstandingPlannedValuesandBaselineProjects

19.1.1CostandUnitsPlannedValuesThePlannedValuesinPrimaveraareassignedtobothUnitsandCostsforeachResourceandExpenseatthetimetheResourceorExpenseisassignedtoanActivity.

PlannedValuesresideinthecurrentprojectandinallBaselineProjects.

ThePlannedvaluesnormally,bydefault,arelinkedtotheAtCompletionvalueswhenanactivityhasnotcommencedbutaftertheactivityisin-progressbybeingmarkedasStartedthesevaluesbecomeunlinked.

Shouldyouwishtore-estimatethecostofaprojectandcompareittoapreviousvaluewhenactivitieshavenotstartedyoucouldeither:

1.CreateaBaselineProjectbeforere-estimatingtheprojectandcompareyourrevisedcoststotheBaseline,or

2.UnchecktheProjects,EPS,SetProjectPreferences…,CalculationstabandunchecktheLinkplannedandatcompletionfornotstartedactivitieswhichwillunlink:

PlannedCostsfromAtCompletionCostsPlannedUnitsfromAtCompletionUnitsPlannedDurationsfromAtCompletionDurations

ThisoptiontounlinkOriginalandAtCompletionDurationsmaynotbedesirable,butthisoptiondoesnotinvolvesettingabaseline.Thisthereforeaddsfurthercomplicationsanditisrecommendedthatitisnotused.

19.1.2BaselineProjectandValuesABaselineprojectisacompletecopyofaprojectincludingtherelationships,resourceassignmentsandexpenses.

ThecreationandassignmentofaBaselineProjectwascoveredintheUPDATINGANUNRESOURCEDSCHEDULEchapter.•BaselineDatesarealsoknownasTargetDatesandarenormallyconsideredtobethe

approvedProjectEarlyStartandEarlyFinishdatesofanunprogressedproject,whicharerecordedbysavingaBaselineproject.

•BaselineDurationistheoriginalplanneddurationofanactivity,calculatedfromtheEarlyStarttotheEarlyFinishofanActivity.ThisisnottheP6PlannedDurationValue.

•BaselineCostsarealsoknownasBudgetsandrepresenttheoriginalprojectcostestimate.ThesearethefiguresagainstwhichtheActualCostsandCostatCompletion(orEstimateatCompletion)maybecompared.

•BaselineUnitsarealsoknownasBudgetedQuantityandrepresentstheoriginalestimateoftheprojectquantities.Thesearethequantitiesagainstwhichtheconsumptionof

Page 375: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

resourcesmaybecompared.

TheBaselinevaluesarevaluesagainstwhichprojectprogressismeasured.Allthesevaluesmaybereadbyandcomparedwiththecurrentprojectvaluesandshowvariancesfromtheoriginalplan.

ABaselinewouldnormallybecreatedpriortoupdatingaprojectforthefirsttime.

ThePrimaveraVariancecolumnsuseBaselinedatafromBaselineProjectstocalculatevariances.

19.2UnderstandingtheCurrentDataDateTheDataDateisastandardschedulingterm.ItisalsoknownastheReviewDate,StatusDate,ReportDate,AsofDate,TimeNow,andUpdateDate.•TheDataDateisthedatethatdividesthepastfromthefutureintheschedule.Itisnot

normallyinthefuturebutisoftenintherecentpastduetothetimeitmaytaketocollecttheinformationrequiredtoupdatetheschedule.

•ActualCostsandQuantities/HoursorActualWorkoccurbeforetheDataDate.•CostsandQuantities/HourstoCompleteorWorktoCompletearescheduledafterthe

DataDate.

•ActualDurationiscalculatedfromtheActualStarttotheCurrentDataDateorSuspendDate.

•RemainingDurationisthedurationrequiredtocompleteanactivity.ItiscalculatedforwardfromtheCurrentDataDate.TheEarlyFinishdateofanin-progressactivityiscalculatedfromtheCurrentDataDateusingthe:

ActivityCalendarwhentheActivityTypeisTaskDependentorisResourceDependentbutnoResourceshavebeenassigned,or

ResourceCalendarwhentheActivityTypeisResourceDependentandusesthelongestResourceDuration.

PrimaverahasoneDataDate,theCurrentDataDate,whichoperatesinthesamewayastheP3andSureTrakDataDate.MicrosoftProjecthasfourdatesassociatedwithupdatingaschedule.TheMicrosoftProjectStatusDateissimilarinfunctiontothePrimaveraCurrentDataDate.P6doesnothaveafeaturelikeAstaPowerprojectwherealltheReportDatesmaybeestablishedinthesoftwareatthestartoftheproject.

19.3InformationRequiredtoUpdateaResourcedScheduleAprojectscheduleisusuallyupdatedattheendofaperiod,suchaseachday,week,ormonth.Onepurposeofupdatingascheduleistoestablishdifferencesbetweentheplan,whichisusuallysavedasaBaseline,andthecurrentschedule.

Thefollowinginformationisrequiredtoupdatearesourcedschedule:

Activitiescompletedintheupdateperiod:

Page 376: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ActualStartdateoftheactivity,•ActualFinishdateoftheactivity,•ActualCostsandQuantities(Units)consumedorspentonLaborResources,Material

ResourcesandExpense.Thesemaybecalculatedbythesoftwareorcollectedandenteredintothesoftware.

Activitiescommencedintheupdateperiod:•ActualStartdateoftheactivity,•RemainingDurationorExpectedFinishdate,•ActualCostsand/orActualQuantities.Onlywhenthesearetobeenteredintothe

software,

•QuantitiestoCompleteandCoststoComplete.Onlywhenthesearetobeenteredintothesoftware,

•%Complete.ActivitiesNotCommenced:•ChangesinLogic,Constraints,orDuration,or

•ChangesinestimatedCosts,HoursorQuantitiesand•Addorremoveactivitiestorepresentscopechanges.

Theschedulemaybeupdatedafterthisinformationiscollected.

OtherConsiderationsPrimaveranormallybydefaultcalculates:

•TheUnitstoCompleteandinturntheActualUnitsbytherelationshipbetweentheRemainingDurationandResourceUnits.

•TheCoststoCompleteandtheActualCostsbytherelationshipbetweentheResourceUnitRateandResourceUnits.

WhentheserelationshipsareturnedoffthentheUnitsandCostsmaybeenteredmanually.

Amarked-upcopyoftheschedulerecordingtheprogressofthecurrentscheduleisoftenproducedpriortoupdatingthedatawithPrimavera.Ideally,themark-upshouldbepreparedbyaphysicalinspectionoftheworkorbyapersonwhointimatelyknowsthework,althoughthatisnotalwayspossible.Itisgoodpracticetokeepthismarked-uprecordforyourownreference.Ensurethatyounotethedateofthemark-up(i.e.,thedatadate)and,ifrelevant,thetime.

OftenaStatusReportormark-upsheetisdistributedtothepeopleresponsibleformarkinguptheproject’sprogress.Apagebreakcouldbeplacedateachresponsibleperson’sband,andwhenthescheduleisprinted,eachpersonwouldhaveapersonallistingofactivitiesthatareeitherin-progressorduetocommence.Thisisparticularlyusefulforlargeprojects.Themarked-upsheetsarethenreturnedtotheschedulerfordataentryintothesoftwaresystem.

Otherelectronicmethods,suchasthePrimaveraTimesheetsystemorane-mailbasedsystemwithspreadsheetorpdfattachments,maybeemployedtocollectthedata.

Page 377: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Irrespectiveofthemethodused,thesamedataneedstobecollected.

Itisrecommendedthatonlyonepersonupdateeachschedule.Thereisahighprobabilityforerrorswhenmorethanonepersonupdatesaschedule.

19.4ProjectPreferencesDefaultsforUpdatingaResourcedScheduleTheProjectPreferencessettingsaffectallactivitiesinaprojectthatisbeingupdated.Whenmorethanoneprojectisopen,theSchedulingOptionsoftheprojectatthetopofthelistofopenedprojectsareusedtocalculateallopenprojectswhentheyarescheduledorleveled.(ThereisnoDefaultProjectfunctionfoundintheWindowsClientintheWeb).

TheCalculationsandDefaultstabintheProjectsPreferencestabssetssomeimportantresourcedefaults:

19.4.1ProjectPreferencesCalculationsTab

•ThetwooptionsResetplanneddurationsandunitstoremaining(authorspreferred)andResetremainingdurationandunitstoplanneddeterminehowthePlannedDurationandUnitsareresetwhenprogressisremovedfromactivities.

•CalculateActivity%fromactivitysteps.ThePrimaveraStepfunctionenablesactivitiestobebrokendownintoelementscalledSteps.Eachelementearnsadesignated%CompletewhentheStepismarkedascomplete.Physical%CompleteTypemustbeselectedtouseSteps.

•UncheckingLinkplannedandatcompletionfornotstartedactivitiesenablestheusertore-estimatethecostorquantitiesofun-startedactivitieswhilepreservingtheoriginalPlannedValueofanactivity.ThisalsounlinksthePlannedDurationfromtheAt

Page 378: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

CompletionDurationforun-startedactivitiesanditsuseisnotrecommended.•WhenupdatingActualUnitsorCosts.Therearetwooptions,whicharethesameasthe

P3AutocostRuleNumber3:

AddActualtoRemaining.WhenActualCostsareentered,theAtCompletionincreasesbytheamountoftheActualCosts.

SubtractActualfromAtCompletion.WhenActualCostsareentered,theAtCompletedoesnotchangeandtheToCompleteisreducedbythevalueoftheActual.Thisistheauthor’spreferredoption,astheAtCompletiondoesnotchangeuntiltheAtCompletionisexceededbytheActual.

•RecalculateActualUnitsandCostwhenduration%completechanges.ThisoptionlinkstheDuration%CompletetothePlannedandToComplete,thusanincreaseinDuration%CompletewillincreasetheActualanddecreasetheToCompletevalueskeepingtheAtCompletionconstant.ThisisusedwhenyouwantthesoftwaretoestimateActualcostsandunits.

•Linkactualtodateandactualthisperiodunitsandcost.ThisisthesameastheP3AutocostRuleNumber6.Withthisoptionchecked,whenyouenteranActualthisperiod,theActualtodatewillbecalculatedbyincreasingtheoriginalvaluebythevalueoftheActualthisperiod.Alternatively,youmayentertheActualtodateandPrimaverawillcalculatetheActualthisperiod.Whenunchecked,thetwofieldsareunlinkedandyoumayenteranyfigureineachfield.Thisoptionisgrayedoutiftheprojectisnotopenandisusedtofixerrorsindataentry.ThisallowsthefixingupofdataerrorswhentheStorePeriodPerformancefunctionisbeingused.

19.4.2ProjectPreferencesDefaultsTab

Page 379: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•DurationType.ThiswillaffecthowaresourceremainingunitscalculatewhenaremainingdurationischangedandhasbeencoveredindetailintheASSIGNINGROLES,RESOURCESANDEXPENSESchapter.

•Price/Units.ThisisthesameasthePrice/UnitforactivitieswithoutresourceorrolePrice/UnitsintheWindowsClient.WhenanactivityisassignedaquantityintheActivities,Generaltabbutnoresourceisassigned,thenthisrateisusedtocalculatethecostagainstLaborandNonlaborunits.

19.5ActivitiesWindow–PercentCompleteTypesTherearethree%Completetypeswhichmaybeassignedtoeachactivity.ThedefaultisadoptedfromtheselectionintheDefaultstabintheProjectsPreferencesform:•Physical•Duration•Units

19.5.1AssigningtheProjectDefaultPercentCompleteTypeTheDefaultPercentCompleteTypeforeachnewactivityineachprojectisassignedintheProjectPreferences,Defaultstab:

Page 380: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•EachnewactivityPercentCompleteTypeissettotheDefaultPercentCompleteandmaybechangedatanytimeintheintheActivitieswindow,Generaltab:

EachPercentCompleteTypehasitsowndatacolumnandisalwayscalculated.ThereisalsoanActivity%CompletecolumnwhichislinkedtoanddisplaysthevaluefromthePercentCompleteTypecolumnthathasbeenassignedtotheactivity.Seethefollowingpicture:

IntheWindowsClienttheActivity%CompleteisdisplayedontheBarbutintheWebonlytheDuration%Completeisalwaysdisplayedonthebar.

Page 381: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

19.5.2PhysicalPercentCompleteTypeAnactivityassignedPhysicalPercentCompleteTypemayhavethe%PhysicalCompleteenteredinthePhysical%CompleteortheActivity%Complete.ThisfieldhasnoimpactonschedulecalculationsandisnotlinkedtoeithertheResourceUnitsortheActualandRemainingDurationsoftheActivity.

Physical%CompletemustbeusedwhenStepsarebeingusedtorecordprogress.ThePhysicalPercentCompletetypeisoftenusedwhentheprogressofanActivityisbeingmeasuredoutsidePrimavera.Forexample,anactivityrepresentingtheinstallationcablethatismeasuredbylengthofcableinstalledwouldhavethepercentcompletecalculatedby:

•%Complete=Qty.ofCableInstalled/TotalQty.ofCabletobeInstalled

Forexample,theactivitymayonlyhavetheinstallationlaborassignedtoit,andthereforetheinstallationlaborparametermaynotbeusedforthemeasurementoftheActivity%Complete.Inaddition,becausethepercentcompleteoftheactivityisbasedonthelengthofcableinstalled,theActivity%Complete(theprogressofthework)maybecomparedtotheresourceUnits%Complete(theamountoflaborused)whichiscalculatedfromtheformula:•Units%Complete=ActualUnits/AtCompletionUnits

Thisexampleisdemonstratedinthefollowingpicture:

•ThePhysical%Completeissetat50%.

•TheUnit%Completeof20%iscalculatedfromtheAtCompletionUnitsof12.00hrsandAtCompletionUnitsof60.00hrsandnotthePlannedUnitsof48.00hrs.

Afterasecondresourceisadded,theActivityUnits%Completeof40%iscalculatedfromtheadditionofthetworesourceActualUnitsandAtCompletionUnits:

•ActivityUnit%Complete=ActualLaborUnits/AtCompletionLaborUnits

•Therefore,40%=(12+36)/(60+60)

Page 382: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

19.5.3DurationPercentCompleteTypeWithDurationPercentCompletethereisalinkestablishedbetween:

•Duration%Complete•PlannedDuration•RemainingDurationADuration%CompletemayonlybeenteredafteranActualStartDatehasbeenassignedandshouldbeinthepastwithrespecttotheCurrentDataDate.

Achangeinoneparameterwillchangeoneother:

•AchangeintheDuration%CompletewillchangetheRemainingDuration,and•AchangeinthePlannedDurationorRemainingDurationwillchangetheDuration%

Complete:

TheActualDurationisalwayscalculatedfromthedurationofActualStarttotheCurrentDataDate,orSuspendDatewhenset.TheActivityUnitsPercentCompleteisstillcalculatedfromtheResourceUnits.

19.5.4UnitsPercentCompleteType

Page 383: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

WhenUnitsPercentCompletetypeisselected:•ThisoptioncreatesalinkbetweentheActivity%CompleteandtheactivityUnits%

Complete,and•TheUnits%CompleteiscalculatedfromtherelationshipbetweentheActualUnitsand

AtCompletionUnits.

19.6UsingStepstoCalculateActivityPercentCompleteAnactivitypercentcompletemaybedefinedbyusingsteps.AStepisameasurableoridentifiableactivityrequiredtocompleteanactivity.Insummary,tousesteps:

•ASteptemplatemaybecreatedbyselectingAdminister,EnterpriseData,Activities,StepTemplatestoopentheActivityStepTemplatesform.

•AddasmanyStepsasrequiredandassigntheirweightwhichwillbeusedtoapportionthepercentcompleteofanactivity.

•TheCalculationsandDefaultstabintheProjectsPreferencestabshasacheckboxtitledCalculateActivitypercent%fromactivitystepswhichmustbecheckedtoallowStepstobeused:

•YoumaydisplaytheActivitypercentcompletebasedonstepscheckboxintheProjects,EPSWindow,anddisplaytheCalculateActivitypercent%fromactivitystepsdatacolumn:

Page 384: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SelectthePhysicalinthe%CompleteTypeforeachactivitythatistobemeasuredbystepsintheGeneraltabofActivitiesWindow,

•SelecttheStepstabintheActivitiesWindow,•Formatthecolumnsyouwishtodisplay,

•AddthenumberofstepsyourequireorimportfromaStepTemplate,•Editthedescriptionsasrequired,

•EdittheStepWeightsotheStepWeightPercentreflectsthedesiredvalueoftheStep,•ChecktheCompletedcheckboxaseachstepiscompletedandthiswillupdatethepercent

complete.

•TheRemainingDurationmaybeupdatedfromtheStep%CompleteviathePhysical%CompleteusingaGlobalChange.

19.7UpdatingtheScheduleThistakesplaceintwosteps:

•FirstlytheDatesandDurationsareupdatesinthesamewayasanun-resourcesschedule,then

•TheResourcesandExpensesUnitsandCostsareupdated.Itmustbedecidedhowthisoperationiscompletedastherearemanyoptions.

19.7.1Preferences,DefaultsandOptionsforUpdatingaProjectSomePrimaveraoptionsaregood,buttherearesomethatshouldbechanged.Theoptionsto

Page 385: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

beconsideredandcheckedbeforeupdatingascheduleare:

Function Discussion

•%CompleteType

Itistheauthor’spreferencetousePhysical%CompletewhentheresourcesareInputresources,i.e.,thosedoingthework.Thisallowsthe%ofdeliverablescompletetobemeasuredindependentlyoftheresource(s)doingthework,thusallowingacomparisonofthedeliverablescompletedagainsttheresourcesconsumed.

•ActivityType

ActivitieswithknowndurationsshouldbesetasTaskDependentandwillusetheActivitycalendar(nottheResourceCalendar)forcalculatingthefinishdateoftheactivity.

ResourceDependentactivitiesshouldonlybeusedifthereareresourceavailabilityissueswhichmayonlyberesolvedbytheuseofResourceCalendars.

LevelofEffortandWBSactivitiesareusefulbutshouldbeavoidedbythenoviceuserastheseaddanadditionallevelofcomplexitythatisnotrequired.

Milestonesmaynotbeassignedresources.

•Linkactualtodateandactualthisperiodunitsandcost

TheLinkactualtodateandactualthisperiodunitsandcostoptionfoundintheCalculationstaboftheSetProjectPreferencesformshouldbecheckedifitisintendedtoStorePeriodPerformance.

•DurationType

Itistheauthor’spreferencetouseFixedDurationandUnitsbecausetheestimatetocompleteisnotalteredbychangingtheActivityDurationorUnits/Time.

ThisdurationtypealsosetstheResourceAssignmentsoptionintheMyPreferences,Global,ResourcesectiontoRecalculatetheUnits,Duration,andUnits/TimeforexistingassignmentsbasedontheactivityDurationType.

•Timesheets

Timesheetsmaybeusedtoupdateactualsfornone,some,orallresources.Organizationsusingtimesheetsshouldhaveproceduresmanagingtheiruse.Timesheetsareoutofthescopeofthispublicationbutiftheyarebeingusedtheactualvaluesshouldbecarefullycheckedbeforebeingappliedtoensuretheyarelogical.

ResourceCostsmaybecalculatedfromtheResourceUnitRatesforeachindividualresourceassignment.

EachresourceassignmenthasafieldtitledCalculatecostsfromunits.

Page 386: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ResourcesCostCalculation

Whenthisischeckedtheresourcecostsarecalculatedfromtheresourceunits.

TheCalculatecostsfromunitscheckboxintheResourceWindow,DetailstabsetsthedefaultvalueforCalculatecostsfromunitsfornewresourceassignments.

Thetwofieldsarenotlinkedandtheresourceassignmentsettingmaybechangedatanytime.

•AutoComputeActuals

Thisfieldislinkedtoallresourcesassignments.WhenthisoptionischeckedforaresourcePrimaveracalculatestheRemainingUnitsbasedontheRemainingDurationandtheActualUnitsbysubtractingtheRemainingUnitsfromBudgetedUnitswhenusingtheApplyActualsfunction.

AnuncheckedresourceassignmentoptionmaybeoverriddenbyapplyingtheActivityAutoComputeActualsoption

•CalculateCostsfromUnits

ThereisafieldavailablewhenaresourceisassignedtoanactivitytitledCalculatecostsfromunits.WiththisoptioncheckedthecostsforaresourcearecalculatedfromtheResourceUnit/TimewhenaresourceisaddedtoanactivityandwhenevertheResourceUnitsarechanged.

•ScheduleOptions

OneofthemoreimportantoptionstoreviewistheWhenschedulingprogressedactivitiesuseoptions,astheseaffecthowout-of-progresssequenceishandled.Theseoptionsshouldbereviewedtoensurethatwhenthescheduleisrecalculatedyouwillunderstandwhatishappening.

TheauthorprefersRetainedLogicasthisgivesamoreconservativescheduleandthoserelationshipsthatneededitingmaybeeditedtoreflectretainedlogicasrequired.

•Steps

ShoulditbedecidedtouseStepstoupdateascheduletheSetProjectsWindowPreferences,CalculationstabshouldhavetheActivitypercentcompletebasedonactivitystepsoptioncheckedand

TheActivitymustbeassignedPhysical%CompleteTypeintheGeneraltaboftheActivitiesWindowforeachactivity.

•Earnedvaluecalculation

TheAdminister,ApplicationSettings,EarnedValuetab,MUSTNOTBESETTO“Plannedvalueswithplanneddates”whenaBaselinehasprogress,otherwisethePlannedDateswillbedisplayedintheBaselineandthesemaycontainirrelevantdatawhentheschedulehasprogress.

19.7.2UpdatingDatesandPercentageCompleteThescheduleshouldbefirstupdatedasoutlinedintheUPDATINGANUNRESOURCEDSCHEDULEchapter.Insummary,thisiscompletedbyentering:•TheActualStartandActualFinishdatesofCompleteactivities.•TheActualStart,%Completeand/orRemainingDurationofIn-Progressactivities.

Page 387: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•AdjustLogic,ConstraintsandDurationsofUn-startedactivities.Beforeupdatingthe%Complete,the%CompleteTypeshouldbecheckedtoensurethattheActualandRemainingDurations,Costs,andUnitscalculateasrequired.Thisideallyshouldbedonebysettingtheprojectdefaultsatthetimetheprojectiscreatedandadjustingthesettingsasactivitiesareaddedandresourcesassigned.

19.8UpdatingResourcesTherearemanypermutationsavailableforcalculatingresourcedata.DuetothenumberofoptionsavailableinPrimavera,itisnotfeasibletodocumentallthecombinationsavailableforresourcecalculation.

Resourceunitsandcostsmaybeupdatedusingoneofthefollowingmethods:

•EnteringthedatausingtheAssignmentstabintheActivitiesWindow,or•EnteringthedatausingtherightsectionoftheGeneraltabintheActivitiesWindow,or•EnteringProgressAutomaticallyfromthetimesheets,aprocesstitledApplyingActuals,or•ImportingfromExcel.ActualdatesandRemainingDurationsmaybeimportedbutSuspend

andResumemaynot.

19.8.1AssignmentsTabTheAssignmentstabmaybeusedtoupdatetheresourceUnits(andCostsiftheUnitsandCostshavebeenunlinkedwiththeCalculatecostsfromunitsfield).AnupdatingViewcouldbecreatedandthecolumnsintheAssignmentstabformattedtoyourupdatingmethod;seethefollowingpicture:

19.8.2GeneralTabTherightwindowmaybeusedforupdatingtheresources.

Page 388: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Whenthereisoneresourcetherewillbeadirectlinkbetweenthisformandthevaluesassignedtotheresource.

•Whenthereismorethanoneresourcetherewillbeaproportionalchangetoalltheresourcevalueswhenachangeismadeinthisform.

19.8.3ApplyingActualsThisfunctionsmaybeusedintwoverydifferentways:

•Updatesactivitieswithresources,whenassignedwithAutoComputeActuals,asiftheywentaccordingtothePlannedDates(thismaychangeActualDatesandcurrentscheduledates)andonlyupdatesactivitiesintheperiodfromtheoldtotheNewDataDate,or

•AppliesApprovedactualsenteredinthePrimaveraTimesheetsystem.

ToApplyActuals:

•ClickontheProjects,Activities ApplyActualsicontoopentheApplyActualsform,

•EntertheNewDataDateandclick icon.

•Ifmorethanoneprojectisopenadifferentdatadatemaybeselectedforeachproject.

•TheActivityrequirestheAutoComputeActualsfieldcheckedforthisfunctiontoapplytoanActivityandalltheResourcesassignedtoanactivity.

•WhentheAutoComputeActualsfieldisnotcheckedonlytheresourcesthathavetheResourceAutoComputeActualsfieldcheckedintheResourceWindowwillbeupdated.Ifoneresourceischeckedandonenot,thenthecheckedresourcewillbeupdatedandtheuncheckedresourceworkwillbedelayeduntilaftertheCurrentDataDate.

TherearesomeimportantissueswithusingApplyActualsthatmustbeunderstood:

Page 389: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•ThisfunctionusesthePlannedDates,notthecurrentscheduledates,toprogressaschedulesoActualStartDatesandtheEarlyFinishdatesmaybechangedbythisfunction.Thiscalculationprocessmakesthisfunctionoflittleusetomostschedulers.

•TheApplyActualsfunctiondoesnotworkinthesamewayastheP3/SureTrakfunction“UpdateProgress”ortheMicrosoftProjectfunction“UpdateProject”whichbothupdateallactivitiesandresourceassignmentsasiftheprojectprogressedexactlyaccordingtocurrentschedule.TheydonotchangeanyexistingActualDatesinthewaythePrimaveraUpdateProgressandApplyActualfunctionschangedatestothePlannedDateswhichmayholdirrelevantdata.

•WhentheActivityAutoComputeActualsISNOTcheckedonlyactivitieswithresourcesthatareassignedAutoComputeActualswillhavetheirdatesupdatedtotheirPlannedDatesandresourceassignmentsrecalculated.UnresourcedactivitiesarescheduledaftertheDataDate.

•WhentheActivityAutoComputeActualsIScheckedthentheseactivitieswillhavetheirdatesupdatedtotheirPlannedDatesandresourceassignmentsrecalculated.

•IntheWindowsClient,aGlobalChangemayberunfirsttosetthePlanneddatestotheStartandFinishdatesbeforeApplingActualsorUpdatingProgress,butthisresultsinachangetotheOriginalDurationandthereforethe%DurationwillcalculateincorrectlyandthereisariskthattheuserwillforgettoruntheGlobalChange.

19.9UpdatingExpensesExpensesareupdatedinasimilarwaytoresourcesintheActivitiesWindow,Expensetab.Expenseswillnotbecoveredindetail,butherearesomenotesaboutExpensesthatyoumayfinduseful:

•Expensesdonotautomaticallyupdatefromany%Completeandhavetobemanuallyupdated.

TheExpenseAutoComputeActualsonlyworkswiththeApplyActualsfunction.

•Expensesmayhaveacostassignedbeforetheiractivityismarkedstartedorcomplete;resourcesmaynot.Thisisusefultorepresentcontractor’smobilizationcosts.ThesearescheduledontheDataDate.

•ExpensesmayhaveacosttocompletebeforetheiractivityisNOTmarkedstarted;resourcesmaynot.Thisisusefultorepresentcontractorbackchargesorretention.ThesearescheduledonthePlannedDates:

Page 390: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•Expensesmustbeassignedaquantityandunitrate.Thequantityisbydefaultavalueofone.

•Expensequantitiesmaynotbedisplayedinthe:

ActivitiesWindowcolumns,orResourceUsageViews.

•ExpenseQuantitiesmaybedisplayedin:Reports,orActivityDetails,Expensestab.ThusitissimpletogetExpenseDataintothesystembutdifficulttogetExpenseQuantitydataoutofthesystem.

19.10UpdatingUsingProgressReporterProgressReporteristhePrimaveratimesheetapplication.WhenusingProgressReporter:

•InP6aresourceisdefinedasusingatimesheet,associatedwithaUserIDandgivenProgressReportermoduleaccess.

•Timesheetperiodshavetobesetupinthedatabase.

•CreatingaresourceassignmentagainstanactiveprojectwillcreateanentryinUserIDtimesheetassociatedwiththeresource.

•ThatactivitywillappearintheusertimesheetwhentheyopenthePrimaveraTimesheet.

•ThentheuserthroughtheProgressReporterrecordsthehoursworkedontheactivity.

•Dependingonthesystemconfigurationthetimesheetwillgothroughanapprovalprocess.

•ThehoursfromtheapprovedtimesheetswillbeconsolidatedandpostedwhenApplyActualsprocessisrunfromP6.

•Seethepicturebelowforanexampleofatimesheetbeingupdated:

Page 391: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

WhenApplyActualsisrunthenthesubmittedandapprovedtimesheethourswillbeconsolidatedandpostedtotheresourcesassignment.

19.11Workshop16–UpdatingaResourcedSchedule

BackgroundWenowneedtoupdatetheactivitiesandresourcesasof09Dec13.

Assignment1.CreateandassignabaselineanddisplaytheBaselinebarbyselectingDefineBaseline

andcreateaBaselinebysavingacopyoftheexistingproject:

2.SelectthisasbothyourProjectBaselineandPrimaryUser’sBaseline,thusensuringthebaselinebarwilleitherbeblankordisplaytheBaselineandnotthePlannedDates.

Page 392: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

3.GototheProjects,EPS,selectyourprojectandselectSetprojectpreferences…,Calculationstabandensureyoursettingsareperthefollowingpictureasthiswillmakeitsimplertoupdateyourschedule.TheseareNOTthestandardsettings:

4.ApplyyourWorkshop11–BaselineComparisonViewandtheBaselinebarshouldbedisplayed.

5.SavetheViewasWorkshop16–UpdatingResourcesandformatthecolumnsasinthefollowingpicturesanddisplaytheProjectBaselinebar.

6.GotoProjects,ActivitieswindowandassigntheProjectManagertotheCreateTechnicalSpecificationtaskasthisresourcewasmissedoutattheestimatingstageandwillgiveanimmediatedifferencebetweentheCurrentScheduleandtheBaselineUnitsandCosts.

7.UpdatethisschedulebyenteringthefollowingdataintheActivitiesWindow,Generaltaborthecolumns:

Page 393: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.ScheduleandmovetheDataDateto09Dec1308:00.

9.OZ1010iscompletesotherearenoRemainingCostsorRemainingUnitsandtheActualshavebeensettoequalthePlanned,butmaybemanuallyadjusted.SelectOZ1010andopentheAssignmentstabandformatthecolumnsasperbelow:

10.OZ1020isinprogressandtheRemainingUnitsandCostshavebeencalculatedfromtheRemainingDurationandtheRemainingUnits/Time,butmaybemanuallyadjusted.

11.Displaycolumnsinthepictureaboveandcheckyouranswer:

12.SelectOZ1020,opentheExpensestabfortheSpecialistConsultantassignment.Expensesdonotautoupdate.AdjustcolumnsasrequireandupdatetheActualCoststo

Page 394: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

$2,000.00andtheremainingto$4,500.00.

13.NowcreateaWorkshop16–PercentagesViewanddisplaythePercentCompletecolumnsperthefollowingpicture.EnsureGroupTotalsaredisplayed:

14.Enter80%againsttheActivity%CompleteofCreateTechnicalSpecification,ScheduleorSaveandseethePhysical%Completechangeto80%astheactivity%CompleteTypeisPhysical:

15.SelecttheCreateTechnicalSpecificationactivity,opentheGeneraltab,andchange:TheActualLaborUnitsfrom48hto24hintheUnitsandCostsboxontherightside,and

TheRemainingLaborUnitsto56.

SelectSaveandnoticetheUnits%Completechangeto30%asfewerhourshavebeenused,buttheRemaininghasincreasedto56hours:

Page 395: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

16.NowlookattheAssignmentstab,adjustcolumnsasrequiredandbothresourcesnowshow12hActualand28hremainingeach.TheRemainingUnits/Timeisnow14hours/daybecausetheActivityTypeisFixedDurationandUnits:

17.NowchangetheRemainingUnitsofCreateTechnicalSpecificationintheGeneraltabto24,ScheduleorSave.NotethechangeintheUnitsandCostsagainsttheresources.

18.CreateanewViewtitledWorkshop16–BaselineComparisonandeditthecolumnssoyouareabletoseetheAtCompletionVariancesagainstactivityOZ1020,theTechnicalSpecificationWBSNode,andtheProject:

Page 396: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 397: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

20OTHERMETHODSOFORGANIZINGPROJECTDATATheWorkBreakdownStructure–WBSfunctionwasdiscussedearlierasamethodoforganizingprojectsandactivitiesunderhierarchicalstructures.TherearealternativefeaturesavailableinPrimaveraforgrouping,sortingandfilteringactivities,resources,andprojectinformation:

•ActivityCodes

•UserDefinedFields(UDF)

•WBSCategories–notcoveredinthisbook

•ResourceCodes–notcoveredinthisbook

•CostAccounts–notcoveredinthisbookTherearenoActivityIDCodesinPrimaveralikethefunctionfoundinP3andSureTrak.InPrimaveraP6eachactivitymusthaveauniqueActivityIDbutnologicalcodemaybeassociatedwiththeActivityID.Someusersdouble-codeactivitiessosomeActivityIDcharactersarethesameasanActivityCode.

20.1UnderstandingProjectBreakdownStructuresAProjectBreakdownStructurerepresentsahierarchicalbreakdownofaprojectintologicalfunctionalelements.Someorganizationshavehighlyorganizedanddisciplinedstructureswith“rules”forcreatingandcodingtheelementsofthestructure.SomeclientsalsoimposeaWBScodeonacontractorforreportingand/orclaimingpayments.Thefollowingareexamplesofsuchstructures:

•WBS WorkBreakdownStructurebreaksdowntheprojectintotheelementsofworkrequiredtodeliveraproject.

•COACodeofAccounts,alsoknownasCostBreakdownStructure.Oftenthiscontainscoststhatarenotincludedinaschedule,suchasinsurancesandoverheads.TheWBSwouldinthissituationrepresentpartoftheCOA.

•OBSOrganizationBreakdownStructureshowsthehierarchicalmanagementstructureofaproject.Primaverahasapredefinedfieldforthisbreakdownstructure.

•CBS ContractBreakdownStructureshowsthebreakdownofcontractsintoelements.

•SBS SystemBreakdownStructure,aSystemEngineeringmethodofbreakingdownacomplexsystemintoelements.

•PBSProductBreakdownStructure,aPRINCE2termusedforthebreakdownofprojectdeliverablesundertwoheadingsofProjectManagementandSpecialistsproducts.

20.2ActivityCodes

Page 398: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ActivityCodesmaybeusedtoGroup,Sort,andFilteractivitiesfromoneormoreopenprojects.

•ActivityCodes,suchasPhases,Trades,orDisciplines,areoftendefinedintheActivityCodesDefinitionform.

•ActivityCodeValuesaredefinedintheAdminister,EnterpriseData,Activities,ActivityCodestabs,suchas:

PhasesofDesign,Procure,InstallandTest,

TradesofBrickwork,PlumbingandElectrical,and

DisciplinesofConcrete,Mechanical,Pipework.

•ActivityCodesareassignedfromtheActivitiesWindowusingtheCodestabinthelowerpaneordisplayingtheappropriateActivityCodecolumn.

20.2.1UnderstandingActivityCodesTherearethreetypesofActivityCodes:

•GlobalActivityCodesthatmaybecreatedatanytimeandappliedtoanyproject.•EPSwhicharecreatedforprojectsassociatedwithoneEPSNodeandmayonlybe

assignedtoprojectactivitiesthatareassociatedwiththatEPSNode.ThusyoumaywishtocreateRailwayEPSActivityCodesforprojectsintheRailwayEPSandSoftwareDevelopmentEPSActivityCodesforprojectsintheSoftwareDevelopmentEPS.

•ProjectActivityCodesthatmayonlybecreatedwhenaprojectisopenedandappliedonlytotheprojecttheywerecreatedfor.ThesemaybemadeGlobalbyclickingthe iconintheActivityCodes–Projectform.

Activity Codes may be added, deleted, or modified in the Activity Codes tabs in theAdminister,EnterpriseData,Activities,ActivityCodestabs,•SelecteitherGlobal,EPSorProjecttabdependingonwhetherthecodesareforaspecific

projectoravailabletoallprojects,

•ThefirstindentistheActivityCodeandmayhaveoneormoreActivityCodeValuesandassociatedActivityCodeDescriptionandoneONLYmaybeassignedtoanactivity,unlikeAstaPowerprojectthatmayhavemultiplecodesvaluesfromonecodesassignedtoanactivity.

•ThelengthoftheCodeisdefinedwhenthecodeiscreated;seethenextsection.

Page 399: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

20.2.2ActivityCodeCreationThisprocesscreatesafieldinthedatabasewheretheActivityCodesmaybeadded.

•OpenanActivityCodestabandselect:Global,orEPS,orProject.

EachformisslightlydifferentandActivityCodesmaybecreated,deleted,ormadeintoGlobalandreorderedintheseforms.

•ClicktheAddCode icontoaddanewCode.

•TheMaximumLengthisthemaximumnumberofcharactersacodemaybeassignedwhenitiscreatedintheActivityCodes.

•TheSecureCodeallowsaccesstobecontrolledthroughtheUsersSecurityProfile.•TheActivityCodes–Projectformhasthefollowingicons:

MovetoGlobal iconmakesaProjectActivityCodeaGlobalActivityCode,andMovetoEPS iconmakesaProjectActivityCodeanEPSActivityCode.

•ThepicturebelowshowsthecreationofaProjectActivityCodetitledBranch/Department.

Page 400: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

20.2.3DefiningActivityCodeValues,DescriptionsandColorsToDefineanActivityCodeValue:

•SelecttheappropriateActivityCode,

•Clickonthe AddActivityCodeValueicon(whichlooksthesameastheAddActivityCodeicon),

•EntertheNamewhichisnormallycalledacodeandthedescription,•The ArrowiconsmaybeusedtoreorderCodes,and

•SelectcolorsforcoloringGanttChartBars:

20.2.4AssigningActivityCodeValuestoActivitiesActivityCodesmaybeassignedtoanactivityfromtheProjects,Activitieswindow:•SelecttheCodestabinthelowerpanebyclickingthe Assigncodeicontoopenthe

SelectCodeValueformandassignanActivityCode,or•Displaytheappropriateactivitycodecolumn.

Page 401: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

20.2.5AddActivityCodesWhenAssigningCodesActivityCodesmaybeaddedontheflybyclickingonthe AddCodeValueiconontheSelectActivityCodesformthatallowsActivityCodestobecreatedastheyareassigned:

20.2.6Grouping,SortingandFilteringwithActivityCodesWhenmorethanoneprojectisopenanActivityCodemaybeusedtogroupactivitiesfromalltheopenprojectsunderonecodestructure.

Page 402: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ActivityCodesareGroupedandFilteredinthesamewayasWBScodes,TheexamplebelowisusingtheOzBuildProjectGroupedbyBranch/Department:

20.2.7ImportingActivityCodeswithExcelIfanActivityCodeistobeimportedwithactivitiesusingthePrimaveraExcelImportfunction,itmustexistinthedatabasebeforeitisimported;otherwise,thecodewillnotbeimported.

ActivityCodesmaybeimportedbyloadingtheSoftwareDevelopmentKit(SDK)andusinganExcelspreadsheetavailablefromtheOraclePrimaveraKnowledgebase.InstructionsforloadingtheSDKareavailablefromtheAdministrationGuide.

TherearealsoanarticleontheauthorswebsiteabouttheSDK.

20.3UserDefinedFieldsUserDefinedFieldsaresimilartoCustomDataItemsinP3,orCustomFieldsinMicrosoftProject,orUserfieldsinAstaPowerprojectandprovidetheabilitytoassignadditionalinformationtodatabaserecords.TheymaybeusedforrecordinginformationaboutthedatafieldasanalternativetoActivityCodesandotherpredefinedPrimaverafields.ThetypeofdatathatmaybeassignedtoUserDefinedFieldswouldbeequipmentnumber,ordernumber,variationorscopenumber;road,railwayorpipelinechanges;addressandadditionalcostsdata.

Activitydatamaybefiltered,grouped,andsortedusingtheseUserDefinedFieldsinasimilarwaytoActivityCodes.

Datamaybeimportedintothefieldsand,unlikeActivityCodes,thedataitemdoesnothaveto

Page 403: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

existinthedatabasebeforeimporting.

Thereareanumberofpredefinedfieldsthatmayberenamedandnewonesmaybecreated.UserDefinedFieldsmaybedefinedfor:

•Activities

•ActivityResourceAssignments

•ActivitySteps

•Issues

•ProjectExpenses

•Projects

•Resources

•Risks

•WBS

•WorkProductsandDocuments

ThefieldsareassignedaDataTypefromthefollowinglist:•Text–maximumof255characters

•StartDateandFinishDate–whichmaybeusedtocreatebars

•Cost

•Indicator–selectfrom

•Integer

•Number

Aftersomedatahasbeenenteredagainstafieldinanyproject,theDataTypemaynotbechanged.

OneadvantageofUserDefinedFieldsoverNotebooksisthattheymaybealsodisplayedincolumnsandbecutandpastedintootherprogramslikeExcel.AlsoUserDefinedFielddatamayeasilybeimportedfromExcelandwillnotchangeyourprojectdata.YoumayconsiderimportingdataintoUserDefinedFieldsandthenGlobalChangetheinformationintotheappropriatelocationasasecondstep.

•ThusResourcedataneedstobeimportedintoResourceUserDefinedFields,and

•ActivitydataneedstobeimportedintoActivityUserDefinedFields.YoumustbecarefulthatyoudonotmakeaUserDefinedFieldwiththesamenameasaP6field,otherwiseyouwillnotknowwhichiswhichwhencreatingfilters.YoumayconsideraddingafullstopattheendofeachUserDefinedFieldnamesoitisclearwhichisaUserDefinedfieldandwhichisaP6field.

TocreateormodifyUDFs:

Page 404: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

•SelectAdminister,EnterpriseDataandlocatetherequiredUDFfield,suchasActivityUDFsorExpenseUDFs.

•SelecttheSubjectAreainthedropdownboxinthetopright-handsideoftheform.•Usethe Addand Deleteiconstocreateanddeletefields.•SelecttheDataTypefromthedropdownlist.

ThelistofUserDefinedfieldswillre-sortassoonasanewfieldisaddedorthetitleeditedandyoumayhavetoscrollupordowntofinditinthelist.

•TodisplayoreditdatainaUserDefinedFieldthecolumnshouldbedisplayedintheappropriatewindow.

•Forexample,ifanActivityUserDefinedFieldhasbeencreatedthentheActivitiesWindowshouldbeselectedandthefieldwillbedisplayedunderaUserDefinedcolumn.

•TheexamplebelowhasaSafetyandaNotesUDFdisplayedandpopulated:

20.4Workshop17–ActivityCodesandUserDefinedFields(UDF)

Page 405: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

BackgroundThisworkshopwilllookatcreatinganActivityCodeandsomeUDFs.

Wewillcreateanactivitycodetorepresentthedepartments’responsibilitiesfortheProject.

IfyouareusingashareddatabaseyouradministratorwillcreatetheActivityCodesandyouwillstartthisassignmentatpara4.

Assignment–ActivityCodes1.SelectintheAdminister,EnterpriseData,Activities,ActivityCodes–Projecttab,2.AddaBranch/DepartmentcodeasperthepicturebelowwiththreeDepartments,3.EnsureyouassignadifferentcolortoeachCode.

4.CreateaviewWorkshop17–ActivityCodesandaddtheBranch/Departmentcolumn.

5.AssigntheBranch/DepartmentusingtheCodestabandcolumnasperthepicturebelow:

Page 406: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

6.GrouptheActivityCode:Branch/Department,sortbyActivityID.TheMilestonesarenowatthetopofthescreen.

7.OpentheCustomizeGanttChartOptionsform,BarstabandcolorthebarsbyBranch/Department:

Page 407: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

8.YourpictureshouldlooklikethiswithadifferentcolorbarforeachDepartment:

Page 408: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

9.NowgroupWBS,sortbyActivityId.10.SavetheView.

Assignment–UDFs11.Ifyouareworkinginashareddatabasethenyoushouldbeabletodisplaysome

existingUDFfieldsandpopulatethem,yourinstructorshouldadvisehere.

12.IfyouareworkinginastandalonedatabasethencreatetwoactivityUDFsbyselectingAdminister,EnterpriseData,Activities,ActivityUDFs:SafetyasanIndicator,andNotesasText.

13.DisplayWorkshop6-Dates&DurationsviewandsaveasWorkshop17–UDFs,14.DisplaytheUDFsascolumnsandassignsomedataasshownintheexamplebelow:

Page 409: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM
Page 410: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

21INDEXAccrualType,282ActiveProject,87Activity

Add,93AssigningCalendars,104AutoComputeActuals,257Calendar,69,303Codes,83,322Codes–EPS,236Codes–Global,236Codes–Project,236CodesDefinitionform,322Codesform,322,323CodesMaximumNumber,229Constraintform,156Copy,100Detailsform,93,135,140,153,155,158Dissolving,142Duration,280Hierarchy,40ID,102Information,101In-Progress,207,208Lifecycle,207Networkform,149Notebooks,158PercentComplete,96,210Recording,105Sorting,105Summarizing,88Type,21,65,69,97Type-ResourceDependent,69UDFs,236Window,307

ActualCostsandQuantities,303Dates(similartoRetainedLogic),186Duration,208,303Finish,60,205,210

Page 411: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Start,60,205,207,208,210ActualStartandFinish,177Actualthisperiod,306Actualtodate,306Actualsform,314Add

NewActivities,93,99NewActivityDefaults,94NotebookTopics,158Notes,158Relationships,135SiblingWBS,85WBS,85

AddChildWBS,85AddProjectform,52,54AdditionalProjectInformation,61ADM,12Adminform,221Administer

Defaultstartpage,227Administration,30Administrationtab,29AdvancedScheduleOptionsform,137Allappliedfilters,121Allofthefollowing,123Allowuserstospecifythenumberofworkhoursforeachtimeperiod,231Analysistab,29ANP,55AnticipatedDates,84

Project,60WBS,87

AnticipatedFinish,60AnticipatedStart,60Anyappliedfilters,121Anyofthefollowing,123ApplicationSettings,30ApplyaView,112,113ApplyActuals,314ApproveTimesheets,26ArrowDiagramming,12

Page 412: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

AsOfDate.SeeCurrentDataDate.Assign

ActivityCodesform,324CalendarstoActivities,104Constraints,155MultipleItems,279Resourceform,277Resources,283Rolesform,275Successorform,135

Assignmentstab,29AtCompletionDuration,208AutoComputeActuals,257,314AutomaticCalculation,145Automaticallysummarizeprojectafterassigningresources,223Auto-numberingDefaults,93,99BandsWBS,107Barcolors,323Bartab,197Barsform,176,213BaseCalendar,74Baseline,4,19,175,205

Additionalfields,198Bars,213ComparingtoProgress,213Costs,302Dates,302Define,175Delete,192Duration,302MaximumNumber,191,229Restoring,192Saving,192Setting,194Type,194Types,235Update,193Work,302

Baselinesform,175,192BottomPane,101

Page 413: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

BrowserWindows,42Budget

Log,87Quantity,302

BudgetLog,84CalculateActivitypercent%fromactivitysteps,305,310Calculatecostsfromunits,257,312Calculateperformanceandearnedvalueinformationby,222Calculatestart-to-startlagfrom,187Calculation

Automatic,145form,224,272Manual,145

Calendar,256Activity,69,303Assigning,104Copy,72Create,68,69DatabaseDefault,66,127DefaultActivity,67,98Delete,73ForSchedulingRelationshipLag,190form,70Global,66,72,98Lag,138Personal,65Project,66,67,68,98Renaming,73Resource,65,69,303ResourceDependent,65Shared,65,69View,129

CalendarUsedByform,75Cancel(Ecs),58Cancle(Ecs),106CBS(ContractBreakdownStructure),321ChainLinking,142Changetheuserpassword,227,228CheckOut,59CircularRelationships,142

Page 414: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ClosedNetwork,13ClosingDown,45COA,321CodeActivity,83CodeofAccounts,321CodeSeparator,230Codes

Activity,322Codestab,322CollapseAll,104,107Columnwidth,115Columns

Sortmultiple,106Columnsform,104,114Commandtoolbar,107ComparingProgressWithBaseline,213ComputeTotalFloatas,189Constraint,136,153

AsLateAsPossible,154ExpectedFinish,154FinishConstraint,153FinishOn,154FinishOnorAfter,154FinishOnorBefore,154MandatoryFinish,154MandatoryStart,154MustFinishBydate,157None,154Primary,153PrimaryStart,155Secondary,153,155StartNoEarlierThan,153StartOn,154StartOnorAfter,154StartOnorBefore,154Types,15

ContingentTime,18ContractBreakdownStructure,321Copy

Calendar,72

Page 415: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Activity,100ActivityOptionsform,100Calendar,72fromexistingprojectortemplate,53,54,64Options,101ProjectOptionsform,53

CostAccount,98,236,282CostandUnitsPlannedValues,302CostBreakdownStructure,321CostUnitsLinked,257Create

ActivityCodes,322,323Filterform,122Roles,248,249

CreatingaBlankProject,53CriticalPath,14,145,150Currenciesform,233Currency,257CurrencyID,233CurrencyName,233CurrencyOptionsform,226CurrencySymbol,233CurrentDataDate,175,210,213,301,303CustomizeActivityViewform,105,113,125,149CustomizeColumns,87,140CustomizeColumnsform,111CustomizeFiltersform,120Customizeform,113CustomizeGanttChartOptionsform,111,159CustomizeGroupingform,111CustomizeViewform,114,115Dashboardmenu,26Dashboards,26DashboardsFunctionalityArea,25DataDate,19,60,205,303DataDateformatting,175,205DataLimitsform,191DataType,327Database

MicrosoftSQLServer,54

Page 416: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Oracle,54DatabaseDefaultCalendar,66,79,127Databases,24DateCheckedOut,59DateFormat,37DayView,129Default

ActivityCalendar,67,98ActivityDuration,99,230Auto-numbering,99NewActivities,94Price/UnitforactivitieswithoutresourceorrolePrice/Units,266,306Project,67,244Units/Time,256

Defaults,51Defaultsform,65DefineBaseline,175Definecriticalactivitiesas,187Delete

Baseline,192Calendar,73WBS,85

Dependencies,135Detailsform,95DetailsGeneralform,274Discretionarydependencies,13DisplayDurationsin,37Displayschedulingloguponcompletion,143DissolvingActivities,142DocumentCategories,239DocumentStatuses,239DocumentUDFs,239Documents,41,84,87Driveactivitydatesbydefault,265DrivingRelationships,150Duration

Actual,208,303AtCompletion,208Elapsed,101,137Format,223

Page 417: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

In-ProgressActivity,208Original,208PercentCompleteType,309Planned,208Remaining,208Type,94,270,271

EarlyFinish,150EarlyStart,150EarnedValue,87,194Earnedvaluecalculation,312Edit

Relationshipform,135WorkingDays,75WorkingHours,75

EditDayform,77,79EditHoursperPeriod,82EditRelationshipform,139EditingNotebooksTopic,158ElapsedDuration,101,137E-MailAddress,254EmployeeID,254Enterprise

ProjectManagement,9ProjectStructure(EPS),9,34

EnterpriseData,30EnterpriseDataform,194EnterpriseProjectStructure,30EPS-EnterpriseProjectStructure,9,30,34ERP,55EstimatetoComplete,87ETC(EstimateToComplete),87ExceptionPlan,6ExchangeRate,233ExpandAll,104,107ExpectedFinishConstraint,154,156ExpenseCategories,236ExpensesWindow,282Export,55ExternalDates,181Externaldependencies,13

Page 418: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ExternalEarlyStart,181ExternalLateFinish,181F9,137Feedback,102FileANP,55FileTypes,55

ERP,55MSProjectXML,56PCF,55PLF,55XER,55xml,55

FillDown,104FilterParameter,122Filters,119

ProjectIDfiltering,124Filtersform,120FinancialPeriods,233Find,43FindingtheBarsintheGanttChart,101FinishConstraint,153FinishMilestone,97,267FinishNoLaterThanConstraint,153FinishVariance,213Finish-to-FinishRelationship,136Finish-to-StartRelationship,136FirstColumn,115Firstdayofweek,230Fitto,167FixedDuration&Units,271FixedDuration&Units/Time,271FixedUnits,271FixedUnits/Time,271Float,14

FreeFloat,15,145TotalFloat,14,145

ForeignLanguage,23Form

ActivityCodes,322,323ActivityCodesDefinition,322

Page 419: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ActivityConstraint,156ActivityDetails,93,135,140,153,155,158ActivityNetwork,149Actuals,314AddProject,52,54Admin,221AdvancedScheduleOptions,137,184AssignActivityCodes,324AssignResource,277AssignSuccessor,135Bars,176,213Baselines,175,192Calculations,224,272Calendar,70CalendarUsedBy,75Column,104,113Columns,114CopyActivityOptions,100CopyProjectOptions,53CreateFilter,122Currencies,233CurrencyOptions,226CustomizeActivityView,105,113,125,149CustomizeColumns,111CustomizeFilters,120CustomizeGanttChartOptions,111,159CustomizeGrouping,111CustomizeView,114,115DataLimits,191Defaults,65Details,95,211DetailsGeneral,274EditDay,79EditDay,77EditRelationship,135,139EnterpriseData,194Filters,120Grouping,117MergeorDeleteWBSElement(s),85MyPreferences,222,273,283

Page 420: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Notebooks,61Openarequestforaresource,225PageSetup,164Predecessor,140Print,164ProjectInformation,104ProjectPreferences,60,67,94,261,270RenumberActivityIDbasedonselectedactivities,100ResourceRateTypes,237Schedule,205ScheduleOptions,184ScheduleProject,137,145,213ScheduleProjectOptions,67,180SecurityProfiles,242SelectCalendar,67SelectCalendarToCopy,69,72SelectCode,324SelectProject,192SelectProjectorTemplate,53Selectprojectschedulingoptions,137SelectResource,70SelectWBS,93SetTimePeriods,78Sort,105StandardWorkWeek,75TimePeriods,79UserPassword,227,228Users,240

FormatColumnWidth,115Durations,223Units,223

FreeFloat,15,145FullScreenMode,41,111Funding,84FundingSources,235Generaltab,211,313Global

Calendar,66,72,98,256Dashboards,26

Page 421: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Profile,241ResourceTeam,248RoleTeam,248ScheduledServices,30

GroupResources,246Grouping,83Groupingform,117HardLogic,13,135HeaderandFooter,165Help,42

Online,43Histogram:,292HoursperPeriod,78HoursperTimePeriod,37,231IDLengths,230Ignorerelationshipstoandfromotherprojects,181Import

XMLdatacontrol,57ImportingaProject,54ImportingActivityCodeswithExcel,325InactiveProject,87IndividualResources,246Industry,177,208,282InheritHolidaysandExceptionsfromaGlobalCalendar,74In-ProgressActivities,12,207InputResources,246Issues,41,87,102IssuesCodes,239IssuesUDFs,239Jelen'sCostandOptimizationEngineering,6Jumpingtoanactivity,141Lag,13,137

Resource,264LagforCalendar,138Landscape,165Language,23LateFinish,150LateStart,150Lead,13,137LevelofEffort,97,268

Page 422: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

LevelofPlans,6Licensing,240Limits,251LinkActivities,135,142Linkactualtodateandactualthisperiodunitsandcost,306,311Linkplannedandatcompletionfornotstartedactivities,178,208,262,302,305Links,135LOE,97LoggingIn,23Logic,135

Hard,135Links,12Looping,14Preferred,135Primary,135Secondary,135Sequencing,135Soft,135

Login,23,240Logout,45LongestPath,187LoopingLogic,14Makeopen-endedactivitiescritical,182ManageDashboards,26ManagePortfolios,28ManagePortfoliosViews,28ManageScenarios,28Mandatorydependencies,13ManualCalculation,145Margins,165Mark-upSheet,206,304MaterialResources,253Maximumnumberofrowsdisplayedintreesandpicklists,222Maximumnumberorrowsdisplayedineachsection,222MergeorDeleteWBSElement(s)form,85MergeWBS,85MethodologyManager,53MicrosoftSQLServerDatabase,54Milestones,12,97

Finish,97

Page 423: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Start,97MoveToolbar,85MSProjectXML,56MultipleBrowserWindows,42MustFinishBy,52MustFinishBydate,52,60,157MustFinishDate,16MyCalendar,221MyPreferences,30,37MyPreferencesform,222,273,283NegativeLag,13,137NewActivityDefaults,94NodeSeparator,85Notebook,84,87

Activity,158AddNotes,158form,61TopicEditing,158Topics,158,235

Notestab,257OBS,30OfficePhone,254Openarequestforaresourceform,225OpenExclusively,36OpenPortfolio,28OpenProject,35OracleDatabase,54OrganizationBreakdownStructure,30,242,321Orientation,165OriginalDuration,208Outlining,321OutputResources,247OverheadCodes,234Overtime,256Page

Layout,165Numbering-Printing,167Order,167Setup,165Setupform,164

Page 424: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

ParameterFilter,122Password,23,222PasswordPolicy,230

Enable/Disable,230Passwordtab,227,228PBS-ProjectBreakdownStructure,11PCF,55PDM,12PercentComplete,94,208

Activity%Complete,96,210Default%Complete,95,209Duration%Complete,95,209Physical%Complete,95,209Type,94Units%Complete,95,209Updating,313

PercentCompleteTypeDuration,309Physical,308Units,309

PersonalCalendar,65,70PERT,135,136Phases,5PhysicalPercentCompleteType,308PieChart,294PlannedDates,195PlannedDuartion,177,208PlannedDuration,Resource,264PlannedFinish,177PlannedProject,87PlannedStart,52,60,177PlanningCycle,4Planningtab,29PLF,55PMBOK®Guide,5Portfolios,27Portlets,25,26Portrait,165PrecedenceDiagrammingMethod,12Predecessor,136

Page 425: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Predecessorform,140PreferredLogic,135PreservetheUnits,Duration,andUnits/Timeforexistingassignments,224Price/Unit,98,266Price/UnitforactivitieswithoutresourceorrolePrice/Units,264,266PrimaryLogic,135PrimaryRole,249PrimaryStart,155PrimaveraPrime,24PrimaveraUnifier,24Prime,24PRINCE2,5,6,321PrintPreview,165PrintRange,167Printtableonallpages,167Printing,163

Enhancement,167form,164HeaderandFooter,165Options,167PageNumbering,167PageSetup,163,164,165Preview,164PrintPreview,163Zoom,164

Proficiency,21,249,254Profile

Global,241Project,242

ProgramPlan,6Progress

CalculationSummary,210Overide,185Override,184Recording,206Spotlight,212Tracking,19

ProgressReporter,24,316ProgressSpotlight,111Project

Page 426: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Access,240Baseline,194BreakdownStructure,11,83,321Calendar,66,67,68,98,235FinishDate,60Hierarchy,40ID,52,59Information,104Must,16,52,157MustFinishBydate,157MustFinishByDate,52Name,52Owner,59Phase,88Planned,16Preferences,60,67Preferencesform,94,261,270Profile,242Savinginformation,57settingup,59Status,59,87Toolbar,84UDSs,235WBS,83Web,163

ProjectIDFiltering,124

ProjectsFunctionalityArea,25ProjectsWindow,38Promote,72Promptbeforesendingemail,222RateType,263Recalculateassignmentcostsafterscheduling,184RecalculatetheUnits,Duration,andUnits/Timeforexistingassignmentsbasedontheactivity

DurationType,224RecordingActivities,105Relationship

administer,144Detailwindow,144

Relationships,136

Page 427: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Add,135ChainLinking,142Colors,15Driving,150LinkActivities,142Predecessor,136Successor,136

RemainingDuration,208RemainingEarlyStartandFinish,179RenameCalendar,73RenumberActivityIDbasedonselectedactivitiesform,100Replace,43ReportScheduleProjectLog,143Reporting,163Reports,169RequestResource,280RequestResources,261,280Resetplanneddurationsandunitstoremaining,305Resetremainingdurationandunitstoplanned,305Resource

Assigning,277,283Assignments,274AssignmentsWindow,175Calendar,65,69,256,303Codes,237,255Cost,262DependentActivityType,97,267DependentCalendar,65Group,246Individual,246Input,246Labor,261Lag,264,281Nonlabor,261Output,247PlannedDuration,264Proficiency,254Quantity,262RateType,263RateTypesform,237

Page 428: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Removing,277Shifts,255tab,263,267,278Teams,248Types,253UDFs,238Updating,313

Resource/TimeFormat,223Resources

tab,313Resourcescanbeassignedtothesameactivitymorethanonce,264ResourcesFunctionalityArea,25ResourcesWindow,245ResponsibleManager,36,52,59,87ResponsibleManger,241RestoringaBaseline,192Resume,205,212RetainedLogic,184,185Right-clickingwiththeMouse,41RiskAnalysis,18RiskCatogories,238RiskScoringMatricies,238RiskThresholds,238RiskUDFs,238Risks,41,102,238RoleHierarchy,292RoleTeam,292RoleTeams,248Roles,21RollingWave,5Saving

AdditionalProjectInformation,61Baseline,192

Scale,167Scheduleautomaticallywhenachangeaffectsdates,183ScheduleOptionsform,184ScheduleProjectform,137,145,213ScheduleProjectLog,143ScheduleProjectOptionsform,67,180ScheduleUpdating,211

Page 429: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Scheduler,143Schedulerform,205SchedulingtheProject,145SDK,325Search,42SecondaryConstraint,155SecondaryLogic,135SecurityProfilesform,242SelectCalendarform,67SelectCalendarToCopyform,69,72SelectCodeform,324SelectProjectform,192SelectProjectorTemplateform,53Selectprojectschedulingoptionsform.,137SelectReplacementCalendar,73SelectResourceform,70Selecttheinformationtodisplayinthechart,295,298SelectWBSform,93Sende-mailtoresourcesuponaddingorremovingassignments,222SequencingLogic,13,135Services,230Setdayas,76SetProjectPreferences,86SetTimePeriodsform,78SettingBaseline,194SetupFilterstab,228SharedCalendar,65,69,256SharingViews,129Shifts,255ShowDurationlabel,37Showfirstcolumnas,115Slack,14SoftLogic,135SoftwareDevelopersKit,325Sortform,105Sortfunction,105Sorting

MultipleColumns,106SortingActivities,105Specificdaterange,167

Page 430: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

SpellCheck,107SpreadSheet,292StaffedRemainingUnits,247StagePlan,6StakeholderAnalysis,10StandardWorkWeekform,75Start

Milestone,97,267NoEarlierThanConstraint,153Variance,213

StartandFinishDates,177StartMilestone,97StartingDayoftheWeek,230Start-to-FinishRelationship,136Start-to-StartRelationship,136Status,175,205StatusDate,60,175,301StatusingReport,206,304StepTemplates,236StepUDFs,236Steps,102,305,308,310StorePeriodPerformance,233,306Sub-projects.,5Sub-units,37Successor,136Successorform,140SummaryActivities,107SummaryProgressCalculation,210SuspendandResume,212SystemBreakdownStructure,321Tab

Administration,29Analysis,29Assignments,29Codes,322General,313Notes,257Password,227,228Planning,29Resources,263,267,278,313

Page 431: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

SetupFilters,228Target,4,175TaskDependent,97,267TeamMember,24TeamPlan,6TechniqueforcomputingEstimatetoComplete(ETC),229Techniqueforcomputingperformancepercentcomplete,229Templates,53TimePeriods,230TimePeriodsform,79Timesheets,183,230Title,254Toolbar

Command,107Move,85Project,84

Toolbars,39Top-DownBudgeting,21TotalFloat,14,145,150TotalFloatlessthanorequalto,187Totalworkhours,75TraceLogic,103TrackingProgress,19,175,205TrackingWindow,88,89Type

Activity,21,69,97Duration,94PercentComplete,94,208

UDF,231UNCEFACT

XML,57Unifier,24UnitsFormat,223UnitsofMeasure,238,253UnitsPercentCompleteType,309Units/TimeFormat,223UnstaffedRemainingUnits,247Update,175,205

Activity,211Baselines,193

Page 432: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

Schedules,211UpdateProject,213UpdatingaCompleteactivity,211UpdatingaResourcedSchedule,303Updatinganactivitythathasnotstarted,212UpdatinganIn-progressactivity,211UpdatingExpenses,315UpdatingtheSchedule,311Useassignedcalendartospecifythenumberofworkhoursforeachtimeperiod,78,231UseExpectedFinishDates,183Usethisproject’ssettings,181UserAccess,30Userdashboards,26UserDefinedField,30,231,326UserInterfaceViews,30,242UserPasswordform,227,228UserPreferences,221UserResourceTeam,248UserRoleTeam,248UserSessions,30,244Username,23Usersform,240View

Calendar,129Day,129Sharing,129

Views,112WBS,5

Activity,269Add,85Bands,107Categories,88,235CodeSeparator,86Copy,85Delete,85Merge,85Milestones,87Name,87Node,87NodeSeparator,85

Page 433: Planning and Control Using Oracle Primavera P6 Version 8.2 to 8.4 EPPM

OrganizingActivities,83Project,83Reordering,107Summary,97UDFs,235Window,84WorkBreakdownStructure,11

WebSitePublisher,163What-ifProject,87Whenschedulingprogressedactivitiesuse,184Window

Resources,245Tracking,88WBS,84

WorkAfterDate,301WorkBreakdownStructure,5,11WorkPackage,5WorkProductsandDocumentsWindow,102WorkingHours,75WP&Docs,84XER,55XML,56

Granulardatacontrol,57Import/Export,56UN/CEFACT,57

xmlFileType,55ZoomPrinting,164Zoomtofit,127