Planning the work scope

Embed Size (px)

Citation preview

  • 8/12/2019 Planning the work scope

    1/16

    Program

    Programme : BBA

    Semester

    Subject Code: IB 0006

    Subject Name: Project Planning and Scheduling

    Unit Number: 4

    Unit Title : Planning the work scope

  • 8/12/2019 Planning the work scope

    2/16

    Program

    Introduction

    The scope is the most important element to understand about

    any project. All planning and allocation of resources are

    anchored to this understanding. Scope creep is a significant

    risk in software development projects. We discuss why this is

    so, and how to avoid or at least mitigate the risk. New softwareis usually developed as a result of a customer identifying a

    need.

    The Project Management Institute Project Management Body

    of Knowledge (PMBOK) defines product scope as the featuresand functions that are to be included in a product or service.

  • 8/12/2019 Planning the work scope

    3/16

    Program

    Objectives

    To assess scope, schedule and cost estimates in planning

    To understand Work Break Down structure

    To understand authority and responsibility in an organization

    To assess Scope of the Project and its Objectives

    To understand approach and strategies for effective

    implementation of planning

    To assess integration a project requires

  • 8/12/2019 Planning the work scope

    4/16

    Program

    Planning and Control

    All work (including programs, projects, and cost center

    accounts) should be planned and controlled in accordance

    with the following minimum requirements:

    Planning must clearly relate cost and schedule to the scopeof work

    Planning must identify desired performance and technology

    levels.

    Planning must be based on the current best estimates of

    the eventual cost, schedule, and scope of work.

    Scope, schedule, and cost estimates must be defined and

    documented. The basis for planning (estimates) must be

    documented and available for review by a knowledgeable

    group of peers.

  • 8/12/2019 Planning the work scope

    5/16

    Program

    Work Breakdown Structure

    The WBS is a product-oriented hierarchy of the scope of

    work, and is embodied in a numbering structure that provides

    a system for organizing the scope in a logical manner.

    A properly prepared WBS should facilitate the following:

    Ensure better understanding of work

    Planning of all work

    Identifying end products and deliverables

    Defining work in successively greater detailRelating end items to objectives

    Assigning responsibility for all work

    Estimating cost and schedules

    Planning and allocating company resources

  • 8/12/2019 Planning the work scope

    6/16

    Program

    Scope of the Project and its Objectives

    Defining the Project:

    Have you ever had a project that took longer than was

    expected, cost more, or ended up totally different than the

    original plan? You're not alone. Most projects sway from theinitial idea, but they shouldn't and don't have to. By keeping the

    proper scope of your project, you will be able to finish on time,

    on budget, and with fewer headaches.

    Quality is hard to define but some companies use standardswhich set the quality parameters. A danger is where the cost

    and time limits are precise and the project is not. This will allow

    the project scope to grow without control and will place the

    manager under great pressure.

  • 8/12/2019 Planning the work scope

    7/16

    Program

    Internal environment

    The internal environment is essentially all the factors that can

    be controlled by the organization. These factors are usually

    things like technology advancement, e-commerce,

    andbusiness expansion.

    The factors that constitute the internal environment:

    Value System

    Vision, Mission and ObjectivesManagement Structure and Nature

    Internal Power Relationship

    Human Resources

    Company Image and Brand Equity

    http://www.blurtit.com/q848221.htmlhttp://www.blurtit.com/q848221.htmlhttp://www.blurtit.com/q848221.htmlhttp://www.blurtit.com/q848221.htmlhttp://www.blurtit.com/q848221.html
  • 8/12/2019 Planning the work scope

    8/16

    Program

    Planning Basis:

    The planning basis section provides for the documentation of

    key approaches, assumptions, requirements and other factors

    considered during preparation of the PMP.

    The following topics are addressed in this section.

    Project deliverables / end products

    Requirements

    ConstraintsApproaches / strategies

    Key assumptions

    Specifically excluded scope

  • 8/12/2019 Planning the work scope

    9/16

    Program

    Project Specifications

    Project specifications are a part of the statement of work.

    Specifications are used for man-hour, equipment, and material

    estimates. Small changes in a specification can cause large

    cost overruns.

    Milestone Schedules:

    Project milestone schedules contain such information as:

    Project start date

    Project end date

    Other major milestones

    Data items (Deliverables or Reports)

  • 8/12/2019 Planning the work scope

    10/16

    Program

    Schedules

    All work should be scheduled.

    A management summary schedule that encompasses major

    customer and management requirements should be developed.

    The management summary schedule should correspond to theupper levels of the WBS, and should identify major and key

    milestones.

  • 8/12/2019 Planning the work scope

    11/16

    Program

    Metrics for Business Case:

    Opportunity options (sales volume, market share, and follow

    Resource requirements (team knowledge, requirements, and

    skill set).

    Refined project costs

    Refined savings

    Benefits (financial, strategic, payback).

    Risks.

    Exit strategies.

    Overall complexity.

    Technology complexity and constraints

  • 8/12/2019 Planning the work scope

    12/16

    Program

    Project Charter:

    The project charter may be prepared in quite a detailedmanner including the following:

    The scope baseline / scope statement

    Scope and objectives of the projects (SOW)

    Specifications

    Broad WBS

    Timing

    Spending Plan

    The Management Plan

    Resources requirements and man loading

    Resources of key personnel

    Organizational relationship and structure

    Responsibility assignment matrix

    Support required from other organizations

  • 8/12/2019 Planning the work scope

    13/16

    Program

    Managing Project Scope

    Ok, you're about to kick-off a project you're managing. The

    scope and budget are set, the team knows what they're

    delivering, and everyone is ready to begin. You're confident

    that hours have been allocated appropriately, but you alsoknow how easy it is for scope to slip away from you - you need

    to keep a good handle on this project to ensure the team

    doesn't squander their hours and push the project over budget.

    In this article, I'll review some solid tactics you can employ to

    progressively manage your project budget and maintain totalvisibility from beginning to end.

  • 8/12/2019 Planning the work scope

    14/16

    Program

    There are seven essential elements that need to be included in

    the project definition:

    A clear description of the business problem and the solution to

    that problem

    A description of the benefits of completing the project (the

    business case)

    A concise (25-30 word) definition of the project schedule, scope

    and budget)

    A list of the major deliverables (which, when delivered, completely

    satisfy the scope of the project), including what is in scope and

    out of scope for each

    A priority matrix which summarizes the sponsor's priorities for theschedule, scope and budget parameters that define the project

    Target customers for the project deliverables

    Project dependencies (committed dates and commitments to/from

    other projects)

  • 8/12/2019 Planning the work scope

    15/16

    Program

    Create a Work Breakdown Structure (WBS)

    The WBS is the foundation of the project plan. The WBS is a

    hierarchical logical structure that represents all the work

    necessary to produce all the project deliverables. By doing so it

    organizes and defines the total scope of the project. Work that

    is not in the WBS is outside the scope of the project.

    Integrating Scope with Schedules

    Project start and end dates, if known, must be included. Other

    major milestones such as review meetings, prototype available,procurement, testing, and so on, should also to be identified.

    The last topic, data items, is often overlooked.

  • 8/12/2019 Planning the work scope

    16/16

    Program