Phase II GMP March 3, 2009

Plumosa ES Modernization at Seacrest

Project No: 0871-7507

Page 2: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACRESTPROJECT NO: 0871-7507PHASE II GMP CONSTRUCTION3/3/2009

TABLE OF CONTENTS

1. NARRATIVEa. Executive Summaryb. Market Analysisc. Issues Pendingd. Schedule Narrativee. Accounting

2. CONSTRUCTION GMP a. Qualifications & Assumptions

b. Value Engineering Logc. Alternates Log

3. EXHIBITSa. Exhibit B - GMP Summaryb. Exhibit D - Personnel Assigned & Summary of Construction Phase Feec. Exhibit E - CM Staff Per Diemd. Exhibit F - Construction Team Assignede. Exhibit I - Builder's Risk Questionnairef. Beneficial Interest Affidavit

4. DRAWING LIST

5. MWBEa. Exhibit S - Subcontractors Minority Participationb. Exhibit S - List of Major Subcontractorsc. Appendix B - School District MWBE Formd. Appendix D - Statement of Good Faith Efforts, Not Requirede. Appendix E - Good Faith Efforts MWBE Sub Participation, Not Required

6. SCHEDULE

Revision 5

Page 3: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

1. NARRATIVE

Revision 5

Page 4: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL DELRAY BEACH, FLORIDA

PHASE II GMP NARRATIVE

March 3, 2009

Suffolk Construction Company Page 1 of 3 Phase II GMP Construction

EXECUTIVE SUMMARY The Plumosa Elementary School Project is a Construction Management at Risk Project and the design is by Tercilla Courtemanche Architects, Inc. The new GMP documents show 103,605 SF of new construction. The new campus will now have five buildings consisting of new Administration, Reading Room, Media Center, CCTV Studio, Kitchen, Classroom and Art/Music rooms. In addition, the project also includes renovations to the existing Cafeteria, and existing Auditorium; as well as a new chiller building, shared parking facilities with the City of Delray, and a new PE Area. The project is seeking to achieve certification under the LEED for Schools rating system. For the purposes of LEED, the Cafeteria and Auditorium will not count towards the certification process. The Phase II GMP includes the currently designed systems and materials included within the Specifications and Construction Documents working towards LEED certification. The introduction of the LEED standards and goals significantly changed the design from the Design Development drawings. Some of the significant changes were the efficient roofing system; cistern and pumps; mechanical revisions to accommodate a water cooled system including added cooling tower structure which increased concrete, masonry, and finishes; an emphasis on recycled and regional materials which limited the competition for standard products; mold resistant drywall thru out, low VOC materials, sound attenuation materials to meet minimum LEED sound criteria, and certified wood products for items such as wood doors and casework. The combined affect of all of the above added in the range of $5 million dollars to the scope of work. However, due to the economic slow down we are facing throughout the industry, we have obtained outstanding subcontractor coverage in all areas of the project with very competitive pricing both from a materials and labor standpoint. Current market conditions has resulted in overcoming the differences between the Design Development drawings and Construction Documents, and after considering accepted value engineering this GMP is $129,226 under the SDPBC budget. The overall duration of the project to substantial completion is now estimated to be closer to 15 months as compared to the original 13 months shown in the RFP. The primary cause is as outlined in the scope additions detailed above, plus added time needed for the LEED credit for Enhanced Commissioning and air quality testing. This credit extends the overall duration as the air quality must be maintained for test sampling and commissioning activities. During this time, no construction activities can be performed that would entail dust or fumes including any type of added work or punch out work.

Revision 5

Page 5: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL DELRAY BEACH, FLORIDA

PHASE II GMP NARRATIVE

March 3, 2009

Suffolk Construction Company Page 2 of 3 Phase II GMP Construction

DELIVERABLES Multiple phased GMP was required due to additional information received after the dissemination of Construction Document Phase primarily resulting from LEED requirements and the added renovations to the cafeteria and auditorium. MARKET ANALYSIS Strong interest in the project has confirmed the difficult market conditions we are facing with excellent and competitive subcontractor coverage achieved across all areas of the work. ISSUES PENDING Building Department comments issued after receipt of GMP documents are still under review by the team. As indicated above, we have included an allowance in the Phase II GMP to address these potential costs. Additionally, several RFI responses received after receipt of GMP documents are still under review by subcontractors and costs, if any, are also included in this GMP proposal but included as an allowance through RFI#33. SCHEDULE NARRATIVE

The original project time line is as follows:

100% Construction Documents/ GMP:

Notice to Proceed: 4/6/09 TCO of Buildings: 5/28/10 Final Completion of Buildings: 9/10/10

BUDGET/COST STATUS Approved SDPBC Budget $ 23,872,614 Less Preconstruction Phase Fee $ 176,058 Less Phase I Work [Demolition] $ 1,469,765 Less GMP [with accepted V.E.] $ 22,097,565 Total GMP Proposal Differential $129,226 under budget

Revision 5

Page 6: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL DELRAY BEACH, FLORIDA

PHASE II GMP NARRATIVE

March 3, 2009

Suffolk Construction Company Page 3 of 3 Phase II GMP Construction

ACCOUNTING NARRATIVE Five billings for schematic and DD estimates have been issued to the SDPBC for Preconstruction Services, as well as, for demolition work associated with Phase I GMP. Our final preconstruction billing for the Phase II GMP proposal will be submitted in January 2009.

Revision 5

Page 7: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

2. PHASE II GMP

Revision 5

Page 8: Plumosa Phase II GMP Cover

QUALIFICATIONS AND ASSUMPTIONS

PHASE II GMP PLUMOSA ELEMENTARY SCHOOL

MODERNIZATION at SEACREST SDPBC PROJECT NO. 0871-7507

DELRAY BEACH, FLORIDA

March 3, 2009

01000 - GENERAL 1. We have not included impact or utility fees or charges, offsite connections, sewer connection fees,

water tap fees, water meters or water meter fees that may be required by local, state or federal authorities having jurisdiction. Relocation of any existing utilities (if required) not identified in the bid documents is not included.

2. Suffolk has included an allowance of $10,000.00 amount for the recent RFI responses from the

Architect for RFI’s#1 through #33. 3. All allowances are inclusive of purchase, delivery and installation to create a complete system.

We have included the following allowances in our proposal:

Removal of hazardous, contaminated or unsuitable material or buried $ 10,000 objects/debris from site [See Exhibit B Allowance Section]

Irrigation System Cistern, 10,000 gal [See Exhibit B Allowance Section] $ 46,000 Instrument storage cabinets by Wenger [See Exhibit B Allowance Section] $ 12,000 Doors and Hardware: Provide conduit, pulls, power, power transfer, $ 175,000

and electrified hardware with installation for 50 additional door openings to receive Card Readers by the Owner [See Exhibit B Allowance Section]

Wood athletic flooring in Room 1-125 [See Exhibit B Allowance Section] $ 15,000 Epoxy Flooring repair & resurfacing [See Exhibit B Allowance Section] $ 52,400 Playground surfacing & equipment, including reuse of existing salvaged $ 120,000

Equipment [See Exhibit B Allowance Section] Rerouting of water, sanitary and storm water building connection, due $ 7,500

to conflicts between Civil and Plumbing drawings [See Exhibit B Allowance Section]

Fire Protection Work in Building #3 [See Exhibit B Allowance Section] $ 13,000 LEED Measurement and Verification [See Exhibit B Allowance Section] $ 100,000 Stage Lighting in Building #5 [See Exhibit B Allowance Section] $ 146,000 Sound & Video systems in Building #5 [See Exhibit B Allowance Section] $ 167,000 RFI responses 1-33 [See Exhibit B Allowance Section] $ 10,000 Building Department comments, dated 11/20/08

[See Exhibit B Allowance Section] $ 100,000

Total for Allowances (Extraordinary Cost) $ 973,900 4. The following items are excluded from our proposal:

Building and subcontractor permit fees Threshold inspection fees Parking meter, street rental or other fees for use of the site Soccer Goals, Long Jump Pits, Long Jump Take-off Boards, Dugout and Sideline Bleachers,

Skinned Infield, as well as Field Lining and Reference Monuments for soccer and football fields.

Revision 5

Page 9: Plumosa Phase II GMP Cover

Robe Hooks Book Theft Detection System Indoor Basketball Goals and Accessories, Indoor Volleyball Equipment, Gym Floor Cover,

Outdoor Tennis System, Electronic Scoreboard System 5. The bidder amounts shown on the GMP are subject to change based upon receipt of Board

approval of this GMP, and a Notice to Proceed. 02110 – SITE CLEARING 1. A $10,000 allowance has been included for the removal of hazardous, contaminated, or unsuitable

material or buried objects/debris from the site. [See Exhibit B Allowance Section] 02810 – UNDERGROUND IRRIGATION SYSTEM 2. The new irrigation well is included as shown on the drawings at 100 feet deep. If the well is

required to be deeper to provide adequate water to the system, there will be an added cost. 2. A $46,000 allowance has been included for the irrigation system cistern as the full design of the

system has not been finalized. [See Exhibit B Allowance Section] 02950 – TREES, PLANTS, AND GROUND COVER 1. We have deleted UB36 root barrier at the line of cabbage palm as per approved Value

Engineering item #6 under Exterior Construction. 03300 - CONCRETE 1. We have included the site retaining wall to be per layout shown on Sheet G1.1, in lieu of the

layouts shown on the Civil and Architectural plans. 2. We have included the slab at the dumpster enclosure to be reinforced per S4.2 Det.8 in lieu of

G3.1. 3. We have included the concrete approach at the dumpster enclosure to be reinforced per S4.2 Det.8

in lieu of G3.1 4. We have included a thickened slab for all non load bearing CMU walls per S4.1 Det.1. 5. We have included all footings and columns to be sized per the schedules in lieu of sizes shown on

structural drawings. The primary reason to proceed with the sizes per the schedule is that the drawn sizes when scaled, conflict with the schedule.

6. We have included the elevator pit/slab to be constructed as per the structural drawings in lieu of the architectural drawings.

7. We have provided 8” hollow core plank in lieu of 6” for the structural roof of Building #2. 8. Specification Section 03341 Fibrous Reinforcing is not included, as all slab on grade reinforcing

is shown as welded wire fabric on the structural plans which are more specific than the specification and is what the structural plans dictate as reinforcing.

9. We are providing precast concrete joist in accordance with the accepted Value Engineering item #1 under Structure.

04200 - MASONRY 1. We have included 12" CMU at the dumpster enclosures per the structurals drawings in lieu of the

architecturals. 2. We have included the layout for the dumpster enclosures per the architecturals drawings in lieu of

the structurals. 3. We have included the arches at Bldg. 1 to be constructed of stair-stepped CMU and an 8"x16"

concrete rake beam. 4. We have included all CMU wall around mechanical or electrical rooms to be filled with Core-fill

500 Foam or equal in lieu of sand filled. 5. We have included split face block at partition type W13 shown on the elevations in lieu of stucco

on CMU shown on the section drawings.

Revision 5

Page 10: Plumosa Phase II GMP Cover

6. We have included the site retaining wall to 12” CMU with filled cell 16”on center as per accepted Value Engineering item #5 under Exterior Construction. These walls are also included as an 8’ tall average wall height from top of footing to top of wall.

05500 - METAL FABRICATIONS 1. We have included a 4' X 4' Stainless Steel Panel as noted on A1.7 in the cafeteria. There is no

detail provided for this. 2. We have included a single line stainless steel handrail in the cafeteria since the existing rail is

shown as being demolished. We have assumed that the single line shown on the floor plan on A1.7 in the serving area represents a new rail.

3. We have included a new wall mounted handrail at the auditorium seating per the note on the cover of the drawings. We have included new wall mounted handrails at the stair next to the wheelchair lift. All other railing at this building is assumed to be existing.

4. There is no Metal Grating and Floor Plates (spec section 05531) or Expansion Joint Cover Assemblies (spec section 05805) included in this proposal. None were identified on the drawings.

5. The railings shown on the exterior of building #3 on Elevation A3.4 are assumed to be existing to remain.

06410 - CUSTOM CASEWORK 1. Suffolk Construction Co. has included the 6 each instrument storage cabinets by Wenger. This is a

custom built model type 12 with 5 shelves in lieu of 3. We have provided an allowance for this item at $2,000.00 each for a total allowance of, $12,000.00. [See Exhibit B Allowance Section]

2. The folio storage cabinets as detailed and scheduled on A7.10, are not included. There are none identified or shown on the floor plans.

3. Excluded is the casework in building five. There are none identified or shown. 4. Excluded is the library shelving. These are Owner furnished and installed. 07181 WATER REPELLENT PENETRANT 1. Specification Section 07181 Water Repellent Penetrant is not included, as none was indicated on

the building elevations. 07536 - ROOFING 1. Re-roofing of building #3 is included with a complete removal of the existing roofing system and

removal of the existing insulation over the existing tectum deck at the low roof areas. The high roof area is lightweight insulating concrete that will remain. The new system will consist of rigid tapered insulation over a mechanically fasten base sheet to the tectum deck, with an approved roof system being applied over the both the rigid insulation and the existing lightweight concrete.

2. A 3 ply roof system, Soprema or equal, is included as per accepted Value Engineering item #3 under Exterior Construction.

07620 – FLASHING, GUTTERS, DOWNSPOUTS, & OTHER ACCESSORIES 1. All sheet metal flashing, coping caps, scuppers, and downspouts are included as stainless steel as indicated in the specs, in lieu of aluminum as shown on the plans. 08100 - DOORS, FRAMES & HARDWARE 1. We have provided a one year warranty only for the hollow metal doors and frames materials.

The manufacturers will not provide a five year warranty per the specifications 2. Door #4-181-1 will not have product approval as shown because the door swings to the interior

of the building. 3. Hollow Metal Borrowed Lites A1 & D are not included as they are not shown on the drawings.

Revision 5

Page 11: Plumosa Phase II GMP Cover

4. We have provided new cylinder locks for the doors that do not receive new hardware sets at buildings #3 and #5 in order to meet the re-keying requirements as stated in the specifications.

5. We have included an allowance of $175,000 for the 50 additional card readers as stated in specifications. This includes conduit, pulls, power, power transfer, and electrified hardware for a standard hollow metal door and lockset. The card readers and low voltage wiring are considered to be part of the security package that is by owner. [See Exhibit B Allowance Section]

08300 - OVERHEAD DOORS 1. Curtain guides, as specified, are not available on wind rated doors. We have included curtain

guides to meet the hurricane code. 2. We have included an overhead coiling shutter per the specifications and door schedule at the

cafeteria. This door is not shown on the drawings. We have not included connecting this door to any Life Safety Systems.

08520 - ALUMINUM WINDOWS & GLAZING 1. The aluminum windows are included with a clear anodized finish. 2. We are excluding the wicket screens for the windows as per accepted Value Engineering item #1

under Exterior Construction. 3. We are providing 2 vent windows at Mark type A as per accepted Value Engineering item #2

under Exterior Construction. 09215 – VENEER PLASTER 1. We have included 100% acrylic knockdown finish as per accepted Value Engineering item #1

under Interior Construction & Finishes. 09250 - GYPSUM BOARD SYSTEM 2. We have included mold resistant drywall, which is not specified, but is required to obtain LEED

for Schools Certification. 09300 - CERAMIC & QUARRY TILE 1. Suffolk Construction Co. has excluded all specifications for any quarry tile flooring and base. 09650 - RESILIENT FLOORING 1. Suffolk Construction Co. has excluded any pre molded (inside /outside) corners for the rubber

base materials. 2. A $15,000 allowance has been included for wood athletic flooring in Room 1-125. [See Exhibit B

Allowance Section] 09660 – EPOXY FLOORING 1. Suffolk Construction Co. has included an Allowance of $52,400 for the repair and resurfacing of

the existing epoxy flooring in the kitchen area of Building #3, per the Finish Schedule and Notes. No specifications were included in the current Project Manual for this section of work. [See Exhibit B Allowance Section]

09900 - PAINTING 1. Suffolk Construction Co. has excluded any urethane coating systems as indicated in the specs.

There are none identified or shown on the documents. 2. Suffolk Construction Co. has excluded any intumescent paint. There are none identified or shown

on the documents. There are no areas indicating fireproofing of structural steel members or items.

Revision 5

Page 12: Plumosa Phase II GMP Cover

10000 - SPECIALTIES 1. We have excluded Electric Hand Dryers and Robe Hooks, as none are shown on the drawings. 2. We have assumed that the mark FSD in Specs is mark SD1 soap dispenser in plans. The mark

FSD per page 3 of Section 10800 – Catalong No. Proline DEB SBS Inc. Stainless Steel 1 liter dispenser or as approved by District MP&O Department. Whereas SD1 is a wall mounted liquid soap dispenser per A8.2.

3. We have provided Corner Guards at exposed corners in the corridors only. 4. We have included one Smoke Free Campus sign. 10532 - WALKWAY COVERINGS 1. We exclude all work associated with Solar Panel installation as referred to in the Specs. 2. All aluminum walkway covers are included in a clear anodized finish. See alternates for additional

finish options. 11131 - PROJECTION SCREENS 1. SCCI has included a rear traveler curtain, even though it was not specified or shown on plans. 2. The drawings indicate projection screen VF-2 (8’ x 6’ electronically controlled) in the following

rooms: 1-211, 1-213, 1-216, 1-217, 1-218, 1-221, 1-222, 1-223, 1-225, 1-227. SCCI has included these as VF-1 (80” x 60” manually operated screens). If the Owner requires VF-2 electronically controlled screens as shown on the drawings, the additional cost will be $17,040.

3. SCCI has included one (1) VF-3 projection screen at 12' x 12' per specifications in the cafeteria. If this screen is not required, the deduct amount is $2,130.

11480 – ATHLETIC AND RECREATIONAL EQUIPMENT 1. An allowance of, $120,000, has been included for the playground equipment. [See Exhibit B

Allowance Section] 13120 - PRE-ENGINEERED METAL BUILDING 1. The pre-engineered metal building is to be manufactured by Varco Pruden. The price includes VP

standard rigid frame, three plate tapered rafters and columns, non-expandable end frames, and 8 ½” secondary members. The roof is included as 24 GA zinc coated (Galvalume) steel panels, panel rib corrugated, with 36” coverage, and standard 26GA trim, fasteners, and fasteners.

2. No insulation or liner panels are included on the pre-engineered building. 3. We have included stainless steel gutters and downspouts as indicated on the drawings. 4. Pre-engineered metal building is to be field painted as indicated on the drawings. 5. The pre-engineered building reactions will be provided to the owner’s engineer for final design of

the building foundations. Foundations as shown on the structural plans are currently included. 15420 - PLUMBING 1. Civil utilities C-11.0 and sanitary sewer in drawing P1.02 does not match. We have included an

allowance of $7,500 for re-routing utility lines inclusive of purchase and delivery for a complete system. [See Exhibit B Allowance Section]

2. L.P. Fuel tank & piping to the building #4 is excluded. 3. Can wash is excluded, it is shown as existing. 4. The grease trap at Building #3 is shown as existing, and providing a new grease trap is excluded. 5. We are providing black iron piping as per accepted Value Engineering item #1 under

Mechanical/Fire Protection/Plumbing.

Revision 5

Page 13: Plumosa Phase II GMP Cover

Page 6 of 6

15500 - FIRE PROTECTION 1. Fire protection for building #5 is excluded. That includes the stage, the auditorium and orchestra

pit. 2. We have included an allowance of $13,000.00 for all of the fire protection work within Building

#3. As it relates to design deficiencies in FP1.04, full extent of work in the existing building will be determined after selective demolition is performed and status and routing of pipes as well as hydraulic calculations are run. [See Exhibit B Allowance Section]

3. Assume adequate water pressure is available on site. 4. Fire Pump, jockey pumps are excluded. 5. Heads in finished ceilings will be geometrically aligned, but not necessarily centered in the ceiling

tiles. 15682 - HVAC 1. Temporary cooling is included using the permanent equipment for 90 days. We do not include

cost for rental of portable air conditioning or portable generators with fuel for temporary cooling. 2. We have included all Merv 8 filters as required per LEED. 3. VFD are to be provided by Wisch & Jackson, per plans. 4. The testing, balancing, commissioning, and LEED testing and monitoring of the HVAC systems is

to be provided by Owner. 15900 – ENERGRY MANAGEMENT AND CONTROL SYSTEM 1. An allowance has been added for LEED Measurement and Verification points in the amount of,

$100,000. [See Exhibit B Allowance Section] 16100 – ELECTRICAL 1. We included an allowance for specification section 11066 “Stage Lighting” in Building #5 of

$146,000. [See Exhibit B Allowance Section] 2. We included an allowance for specification section 11067 “Sound & Video systems” in Building

#5 of $167,000[See Exhibit B Allowance Section] 3. We have included projector plates only for the Audio Enhancement system. Conduit and pull

strings are not required for the audio enhancement system as they are free wired with plenum rated cable.

4. The following are excluded from the electrical scope of work: Telephone and data cabling, devices, and terminations by others Television wiring Static uninterruptible power supply system Security devices, wiring and terminations by others Card access devices, wiring, and terminations by others Special testing Independent four corner light fixture support Solar panels as referenced in Spec. Section 10 532 covered walkways Utility consumption and connection fees . Electrical for hand dryers in restrooms. Classroom audio-enhancement system.

Revision 5

Page 14: Plumosa Phase II GMP Cover

Updated: 3/3/09

VALUE COMMENTS Accepted Rejected Pending

STRUCTURE

1. To provide smaller precast concrete joist with wider joist spacing ($183,200) ($183,200)

EXTERIOR CONSTRUCTION

1. To deduct the wicket screens for the windows ($30,992) ($30,992)

2. To provide a 2 vent vs. a 3 vent window at Mark type A windows ($36,875) ($36,875)

3. To provide a 3 ply roof system in lieu of 4 ply ($7,450) ($7,450)

4. Delete UB36 root barrier at the line of cabbage palm as called for on drawing L-3, if this tree line is moved several feet. ($5,600) Confirmation needed by Landscape Architect ($5,600)

5. To change the site retaining walls from poured in place concrete to 12" CMU with filled cells 16" o.c. ($66,000) Pending review of structural detail ($66,000)

INTERIOR CONSTRUCTION & FINISHES

1. To provide a 100% acrylic knockdown finish in lieu of veneer plaster ($15,000)Need RFI to Architect for variance from Bldg. Dept. ($15,000)

MECHANICAL/FIRE PROTECTION/PLUMBING

1. Allow black iron in lieu of stainless steel for Kitchen exhaust ($2,500)Need RFI to Architect/Engineer for variance from Bldg. Dept. ($2,500)

SUBTOTAL ($347,617) ($347,617) $0 $0

General Liability Insurance ($3,336) ($3,336)Payment & Performance Bond ($3,428) ($3,428)Owner Contingency ($8,690) ($8,690)Suffolk Construction (Overhead & Profit) ($21,378) ($21,378)Sales Tax Savings $3,476 $3,476

TOTAL (Savings already incorporated within the GMP amount) ($380,973) ($380,973)

VALUE ENGINEERING TRACKING SCHEDULE

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST

TRADE

SDPBC No. 0871-7507PHASE II GMP CONSTRUCTION

Revision 5

Page 15: Plumosa Phase II GMP Cover

Updated: 3/3/09

APPROXIMATEVALUE

COMMENTS Accepted Rejected Pending

SITE WORK

1. Addendum #1 changes ($12,060)Pending complete submittal of Addendum #1 costs ($12,060)

STRUCTURE

1.

EXTERIOR CONSTRUCTION

1. Allowance - To provide the conduit, pulls, power, power transfer, and electrified hardware with installation for 50 additional door openings to receive Card Readers by the Owner. $175,000 Included in GMP $175,000

2. To provide the Alum. Walkway Covers with a ESP custom color finis $21,500 $21,500

3. To provide the Alum. Walkway Covers with a anodized bronze finish $45,400 $45,400

INTERIOR CONSTRUCTION & FINISHES

1. To provide a 2 coat conc. stain and sealer in lieu of VCT in all Corrid TBD Confirm price TBD

2. To provide a rear traveler curtain as part of the Stage Rigging $6,500 Included in GMP $6,500

3.To provide projection screen VF-2 (8' x6' electrically controled) in the ten (10) classrooms as noted , in lieu of the VF-1 (80"x60" manual operated) that are typical for classrooms and inculed in the base GMP $17,040 $17,040

CONVEYING SYSTEMS

1.

MECHANICAL

1.

ELECTRICAL

1.

SUBTOTAL $253,380 $181,500 $83,940 ($12,060)

General Liability Insurance $2,600 $1,950 $0Payment & Performance Bond $1,900 $1,500 $0Owner Contingency $6,335 $4,538 ($302)Suffolk Construction (Overhead & Profit) $16,646 $11,938 ($779)Sales Tax Savings ($2,534) ($1,815) $121

TOTAL $278,326 $199,610 ($13,020)

ALTERNATES TRACKING SCHEDULE

PHASE II GMP CONSTRUCTION

TRADE

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACRESTSDPBC No. 0871-7507

Revision 5

Page 16: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

3. EXHIBITS

Revision 5

Page 17: Plumosa Phase II GMP Cover

Revision 5

Page 18: Plumosa Phase II GMP Cover

Updated: 3/3/2009

SPECIFICATION VALUE

Removal of hazardous, contaminated or unsuitable material or buried objects/debris from site 02110 10,000.00$ Irrigation System Cistern, 10,000 gallons 02810 46,000.00$ Instrument storage cabinets by Wenger 06410 12,000.00$

08100 175,000.00$ Wood athletic flooring in Room 1-125 09650 15,000.00$ Epoxy Floor repair and resurfacing 09660 52,400.00$ Playground surfacing and equipment, including reuse of existing salvaged equipment 11480 120,000.00$ Rerouting of water, sanitary and storm water building connection, due to conflicts between Civil and Plumbing drawing 15420 7,500.00$ Fire Protection Work in Bui8lding #3 15500 13,000.00$ LEED Measurement and Verfication credit cost 15900 100,000.00$ Stage Lighting in Building #5 16100 146,000.00$ Sound and Video systems in Building #5 16100 167,000.00$ RFI #1 - 33 Responses Various 10,000.00$ Building Department comments dated, 11/20/09 Various 100,000.00$

Total for Allowances (Extraordinary Cost) 973,900.00$

DESCRIPTION

Door and Hardware: Provide conduit, pulls, power, power transfer and electrified hardware with installation for 50 door openings to receive Card Readers by the Owner

EXHIBIT B

PHASE II GMP CONSTRUCTION

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACRESTSDPBC No. 0871-7507

ALLOWANCES

EXHIBIT BALLOWANCE SECTION

Revision 5

Page 19: Plumosa Phase II GMP Cover

EXHIBIT DPERSONNEL ASSIGNED DURING CONSTRUCTION

SUMMARY OF CONSTRUCTION PHASE FEES

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACRESTPROJECT NO: 0871-7507

PHASE II GMP CONSTRUCTION

NAME/ TITLE

DURATION (WEEKS)

PERCENTAGE OF TIME Hours RATE/ WEEK Total for Duration

Jessica Chen 64 100% 40 4839.54 309,731(Senior Project Manager)

Doug Scott 64 100% 40 4202.80 268,979(Lead Superintendent)

Patrick Pollock 64 100% 40 2569.27 164,433(MWBE CM / Asst Super

Roosevelt Kingdom 32 100% 40 2569.27 82,217(MWBE CM / Asst Super

Ben Austin 64 100% 40 2870.86 183,735(Assistant Project Manager)

Shanin Johnson 64 100% 40 2392.12 153,096(LEED Project Engineer)

Carol Jones 64 100% 40 1264.00 80,896(Secretary)

Peter Supple 64 15% 40 6051.20 58,092(Project Executive)

Ray Bernard 64 15% 40 6051.20 58,092(General Superintendent)

John Murphy 64 10% 40 4860.10 31,105(Safety Director)

Steven Muscarella 64 10% 40 3266.40 20,905(Scheduler)

Teresa Suarez 64 49.85% 40 3652.40 116,526(Accounting)

Jon Gantner 64 49.85% 40 3652.40 116,526(MIS)

48,242 1,644,330total per week total

Revision 5

Page 20: Plumosa Phase II GMP Cover

NAME/ TITLE HRS/ DAY RATE/ HR PER DIEM RATE

Ray Bernard 1.2 151.28 181.54$ (General Superintendent)

John Murphy 0.8 121.50 97.20$ (Safety Director)

Steve Muscarella 0.8 81.66 65.33$ (Scheduling Director)

Peter Supple 1.2 151.28 181.54$ (Project Executive)

Teresa Suarez 3.988 91.31 364.14$ (Accounting)

Jon Gantner 3.988 91.31 364.14$ (MIS)

Jessica Chen 8 120.99 967.91$ (Senior Project Manager)

Doug Scott 8 105.07 840.56$ (Lead Superintendent)

Patrick Pollock 8 64.23 513.85$ (MWBE CM/Asst Super)

Roosevelt Kingdom 8 64.23 513.85$ (MWBE CM/Asst Super)

Ben Austin 8 71.77 574.17$ (Assistant Project Manager)

Shanin Johnson 8 59.80 478.42$ (LEED Project Engineer)

Carol Jones 8 31.60 252.80$ (Secretary)

TOTAL STAFF PER DIEM 5,395.46$

EXHIBIT E

PHASE II GMP CONSTRUCTIONPROJECT NO: 0871-7507

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST

CONSTRUCTION MANAGER'S STAFF PER DIEM FOR TIME EXTENSIONS

Revision 5

Page 21: Plumosa Phase II GMP Cover

Owner: School District of Palm Beach County

Owner's Authorized Representative:

Phyllis Karp, SPALloyd Weeks, Project Coordinator

Construction Manager: Suffolk Construction, Inc.

Ray Bernard(General Superintendent)

John Murphy (Safety Director)

Peter Supple(Project Executive)

Jessica Chen(Senior Project Manager)

Ben Austin(Assistant Project Manager)

Shanin Johnson(LEED Project Engineer)

Carol Jones(Secretary)

Doug Scott(Lead Superintendent)

Patrick Pollock(Assistant Superintendent)/MWBE Roosevelt Kingdom(Assistant Superintendent)/MWBE

Architect-Engineer: Tercilla Courtemanche Architects, Inc.Mark Allen Sechrist, Project Manager

PHASE II GMP CONSTRUCTION

EXHIBIT FCONSTRUCTION TEAM ASSIGNED REPRESENTATIVES

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACRESTPROJECT NO: 0871-7507

Revision 5

Page 22: Plumosa Phase II GMP Cover

EXHIBIT I

Builder’s Risk Questionnaire

Owner: School District of Palm Beach County, Florida

Contractor Name & Address: Suffolk Construction , One Harvard Circle, Suite 100, West Palm Beach, FL, 33409

Project Title, Project Number & Description: Plumosa Elementary School Modernization at Seacrest

SDPBC No. 0871-7507

Project Address: 2501 Seacrest Avenue, Delray Beach, FL 33444

Estimated Cost of Construction: New- 16,839,587$ Modernization- $5,257,978

Intended Use of Completed Structure: Elementary School

Number of Stories: 2 Number of Buildings: 5

Total GSF of Construction: 103,605 square feet of New Construction & 32,465 square feet of Renovation

Construction Commencement: 30-Mar-09 Construction Completion: 28-Jun-10

Type of Construction: Walls- Concrete, CMU Roof: Membrane

Footings on Fill, Ground, Piles or Other: Footings on Compressed Soil

Foundation Materials: Concrete

Distance to Nearest Fire Hydrant: 70'

Distance to Fire Department: 3 Miles

Distance to Nearest Structure: 50'

Will Sprinklers Be Installed: Yes

Site Security (Fencing, Lighting, Security Service): Fencing, Security Guard

Material Storage On-Site- No

How Will Material Be Stored: N/A - Off site Value: N/A - Off site

Will Flammables Be Stored On-Site & How: no

List the Major Subcontractors and Estimated Percent of Work:- The HVAC, Electrical & Concrete subcontractors combined, represent

38% of the Work. See attached Exhibit S "List of Major Subcontractors" for listing.

Is Demolition Required (Describe): Minor demolition of interior walls and fixtures at existing Cafeteria and Auditorium

Completed By: Peter A. Supple Date: 3/3/2009

Revision 5

Page 23: Plumosa Phase II GMP Cover

Revision 5

Page 24: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

4. DRAWING LIST

Revision 5

Page 25: Plumosa Phase II GMP Cover

Received Date:Original Set

DRAWING # DRAWING TITLE PREPARED BY DRAWING DATE

Demolition DrawingsTercilla Courtemanche

ArchitectsAD1.01 Overall site Demo Plan 10/15/2008AD1.1 1st Floor Plan - Bldg 5 Existing 10/15/2008AD1.2 Demolition Floor Plan Bldg 3 10/15/2008AD1.3 Demolition Ceiling Plan Bldg 3 11/1/2008AD1.4 Demolition Roof Plan Bldg 3 10/15/2008

Landscape DrawingsNeal Smith &

Associates, Inc.L-1 Existing Tree Disposition Plan 10/15/2008L-2 Existing Tree Disposition Chart 10/15/2008L-3 Site Planting Plan 10/15/2008L-4 North Building Area Planting Plan, Notes and Plant List 10/15/2008L-5 Planting Details 10/15/2008I-1 Irrigation Plan Northwest 10/15/2008I-2 Irrigation Plan Northeast 10/15/2008I-3 Irrigation Plan Southwest 10/15/2008I-4 Irrigation Plan Southwest and Installation Details 10/15/2008I-5 Details 10/15/2008

Civil Drawings EAC Consulting Inc.1 of 2 Boundary and Topographic Survey 6/10/20082 of 2 Boundary and Topographic Survey 6/10/2008C-1.0 General Notes 10/15/2008C-2.0 Utility Demolition Plan 10/15/2008C-3.0 Site and Geometry Plan 10/15/2008C-4.0 Grading Plan 10/15/2008C-5.0 Drainage Plan 10/15/2008C-6.0 Ground Cover Plan 10/15/2008C-7.0 Typical Sections 10/15/2008C-8.0 Paving, Grading and Drainage Details 10/15/2008C-9.0 SWPPP Notes and Details 10/15/2008C-10.0 Signage and Pavement Marking Plan 10/15/2008C-11.0 Water and Sanitary Sewer Plan 10/15/2008C-12.0 Water Profiles 10/15/2008C-13.0 Sanitary Sewer Profiles 10/15/2008C-14.0 Water and Sanitary Sewer Details 10/15/2008

Architectural DrawingsTercilla Courtemanche

ArchitectsCOV.1 Cover Sheet 10/15/2008COV.2 Index of Drawings 10/15/2008G1.1 Overall Site Plan 10/15/2008G1.2 Parking Lot Plan 10/15/2008G1.3 Parking Lot & Bus Loop Plan 10/15/2008G1.4 Drive & Sidewalk Plan 10/15/2008G2.1 Playcourt Plan & Details 1/9/2008G2.2 Covered Walkway Plan 1/9/2008G2.3 Covered Walkway Plan 1/9/2008G2.4 Covered Walkway Plan & Ramp & Guardrails Details 1/9/2008G3.1 Details, Sections & Elevations 10/15/2008G3.2 Fence & Misc Details 10/15/2008G3.3 Walkway Cover Details 10/15/2008G3.4 Details and Site Signage 10/15/2008

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Document List

1 of 12

Revision 5

Page 26: Plumosa Phase II GMP Cover

Received Date:Original Set

DRAWING # DRAWING TITLE PREPARED BY DRAWING DATE

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Document List

LS0.1 Overall Site Plan - Life Safety 10/15/2008LS0.2 1st Floor Life Safety Bldg 1 10/15/2008LS0.3 2nd Floor Life Safety Bldg 1 10/15/2008LS1.1 Partial 1st Floor Life Safety Plan 10/15/2008LS1.2 Bldg 1 Partial First Floor Life Safety Plan 10/15/2008LS1.3 Bldg 1 Partial First Floor Life Safety Plan 10/15/2008LS1.4 Bldg 1 Partial Second Floor Life Safety Plan 10/15/2008LS1.5 Partial 2nd Floor Life Safety Plan 10/15/2008LS1.6 Bldg #2 & #4 Life Safety Plan 10/15/2008LS1.7 Bldg #3 Life Safety Plan 10/15/2008

A0.1 First Floor Plan Bldg 1 10/15/2008A0.2 Second Floor Plan Bldg 1 10/15/2008A1.1 Partial First Floor Plan Bldg 1 10/15/2008A1.2 Partial First Floor Plan Bldg 1 10/15/2008A1.3 Partial First Floor Plan Bldg 1 10/15/2008A1.4 Partial Second Floor Plan Bldg 1 10/15/2008A1.5 Partial Second Floor Plan Bldg 1 10/15/2008A1.6 Floor Plan Bldg 2 & 4 10/15/2008A1.7 Floor Plan Bldg 3 Existing / Addition 10/15/2008A1.8 1st Floor Plan Bldg 5 Existing 11/1/2008A1.9 Wall Types & Details 10/15/2008A1.10 Details 10/15/2008A2.1 Bldg 1 Overall Roof Plan 10/15/2008A2.2 Bldg 1 Partial Roof Plan 10/15/2008A2.3 Bldg 1 Partial Roof Plan & Details 10/15/2008A2.4 Bldg 1 Partial Roof Plan 10/15/2008A2.5 Roof Details 10/15/2008A2.6 Bldg 2 & 4 Roof Plan 10/15/2008A2.7 Roof Plan Bldg 3 10/15/2008A3.1 West and South Elevations 10/15/2008A3.2 East and South Elevations 10/15/2008A3.3 North Elevations 10/15/2008A3.4 Elevations 10/15/2008A3.5 Elevations 10/15/2008A3.6 Elevations 10/15/2008A4.1 Building Sections 10/15/2008A4.2 Building Sections 10/15/2008A4.3 Building Sections 10/15/2008A4.4 Building Sections 10/15/2008A4.5 Building Sections 10/15/2008A4.6 Building Sections 10/15/2008A5.1 Wall Sections 10/15/2008A5.2 Wall Sections 10/15/2008A5.3 Wall Sections 10/15/2008A5.4 Wall Sections 10/15/2008A5.5 Wall Sections 10/15/2008A5.6 Wall Sections 10/15/2008A5.7 Wall Sections 10/15/2008A5.8 Column Details & Wall Sections 10/15/2008A6.1 Details 10/15/2008A6.2 Details 10/15/2008A7.1 Partial First Floor Equipment Plan 10/15/2008A7.2 Partial First Floor Equipment Plan 10/15/2008A7.3 Partial First Floor Equipment Plan 10/15/2008A7.4 Partial Second Floor Equipment Plan 10/15/2008A7.5 Partial Second Floor Equipment Plan 10/15/2008A7.6 Bldg 2 & 4 Plan 10/15/2008A7.7 Bldg 3 Floor Plan 10/15/2008A7.9 Cabinet Details 10/15/2008

2 of 12

Revision 5

Page 27: Plumosa Phase II GMP Cover

Received Date:Original Set

DRAWING # DRAWING TITLE PREPARED BY DRAWING DATE

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Document List

A7.10 Music Storage 10/15/2008A7.11 Misc Cabinet Details 10/15/2008A7.12 Desk Details 10/15/2008A8.1 Mounted Height Chart 1/9/2008A8.2 Enlarged Restroom & Clinic Floor Plans 10/15/2008A9.1 Bldg 1 Partial Reflected Ceiling Plan 1st Plan 10/15/2008A9.2 Bldg 1 Partial Reflected Ceiling Plan 1st Plan 10/15/2008A9.3 Bldg 1 Partial Reflected Ceiling Plan 1st Plan 10/15/2008A9.4 Bldg 1 Partial Reflected Ceiling Plan 2nd Plan 10/15/2008A9.5 Bldg 1 Partial Reflected Ceiling Plan 2nd Plan 10/15/2008A9.6 Bldgs 2 & 4 Reflected Ceiling Plan 10/15/2008A9.7 Bldg 3 Reflected Ceiling Plan 10/15/2008A10.1 Bldg 1 Elevator & Stair Sections & Details 10/15/2008A10.2 Bldg 1 Stair Plans, Sections & Details 10/15/2008A10.3 Bldg 1 Stair Plans, Sections & Details 10/15/2008

Structural Drawings RCT Engineering, Inc.S0.1 Structural Notes & Abbreviations 10/15/2008S0.11 Wind Loads for Components and Cladding 10/15/2008S1.1 Foundation Plan Building 1 10/15/2008S1.2 Foundation Plan Building 1 10/15/2008S1.3 Foundation Plan 10/15/2008S1.4 Column Schedule, Footing Schedule, Details 10/15/2008S1.5 Foundation and Plan - Bldg 2 & 3 Addition 10/15/2008S1.6 Foundation and Plan - Bldg 4 10/15/2008S1.7 Covered Walkway Plan 10/15/2008S1.8 Covered Walkway Plan 10/15/2008S1.9 Covered Walkway Plan 10/15/2008S1.10 Retaining Wall Layout 10/15/2008S2.1 Second Floor Framing Plan - Bldg 1 10/15/2008S2.2 Second Floor Framing Plan - Bldg 1 10/15/2008S2.3 Second Floor Framing Plan - Bldg 1 10/15/2008S3.1 Roof Framing Plan - Bldg 1 10/15/2008S3.2 Roof Framing Plan - Bldg 1 10/15/2008S3.3 Roof Framing Plan - Bldg 1 10/15/2008S3.4 Roof Plan - Bldg 2 & 4 10/15/2008S3.5 Roof Plan - Bldg 3 Addition / Modification 10/15/2008S4.1 Details & Sections 10/15/2008S4.2 Sections 10/15/2008S4.3 Sections 10/15/2008S4.4 Sections 10/15/2008S4.5 Sections 10/15/2008S4.6 Sections 10/15/2008

Fire ProtectionJohnson, Levinson, Ragan, Davila, Inc.

FP0.01 Legend, Schedules and General Notes 10/15/2008FP1.01 First Floor Bldg 1 - Fire Protection Plan 10/15/2008FP1.02 Second Floor Bldg 1 - Fire Protection Plan 10/15/2008FP1.03 Bldg 2 and Bldg 4 Fire Protection Plan 10/15/2008FP1.04 Bldg 3 Fire Protection Plan 10/15/2008FP2.01 Fire Protection Details 10/15/2008FP2.02 Fire Protection Details 10/15/2008

PlumbingJohnson, Levinson, Ragan, Davila, Inc.

P0.01 Legend, Schedules and Notes 10/15/2008P0.02 Details 10/15/2008P1.01 Plumbing Partial Floor Plan - Bldg 1 First Floor - Underground 10/15/2008

3 of 12

Revision 5

Page 28: Plumosa Phase II GMP Cover

Received Date:Original Set

DRAWING # DRAWING TITLE PREPARED BY DRAWING DATE

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Document List

P1.02 Plumbing Partial Floor Plan - Bldg 1 First Floor - Underground 10/15/2008P1.03 Plumbing Partial Floor Plan - Bldg 1 First Floor - Underground 10/15/2008P1.04 Plumbing Partial Floor Plan - Bldg 1 First Floor - Above Ground 10/15/2008P1.05 Plumbing Partial Floor Plan - Bldg 1 First Floor - Above Ground 10/15/2008P1.06 Plumbing Partial Floor Plan - Bldg 1 First Floor - Above Ground 10/15/2008P1.07 Plumbing Partial Floor Plan - Bldg 1 Second Floor 10/15/2008P1.08 Plumbing Partial Floor Plan - Bldg 1 Second Floor 10/15/2008P1.09 Plumbing Partial Floor Plan - Bldg 3 Kitchen 10/15/2008P1.10 Plumbing Partial Floor Plan - Bldg 2, 4 & 5 - Underground 10/15/2008P1.11 Plumbing Partial Floor Plan - Bldg 2, 4 & 5 - Above Ground 10/15/2008P2.01 Enlarged Kitchen Floor Plan - Demolition - Underground 10/15/2008P2.02 Enlarged Kitchen Floor Plan - Demolition - Above Ground 10/15/2008P2.03 Enlarged Kitchen Floor Plan - New Work - Underground 10/15/2008P2.04 Enlarged Kitchen Floor Plan - New Work - Above Ground 10/15/2008P3.01 Riser Diagrams 10/15/2008P3.02 Riser Diagrams 10/15/2008P3.03 Riser Diagrams 10/15/2008

Mechanical DrawingsJohnson, Levinson, Ragan, Davila, Inc.

M0-01 Legend, Schedules and General Notes 10/15/2008M0-02 Mechanical Schedules 10/15/2008M0-03 Mechanical Schedules 10/15/2008M0-04 Mechanical Schedules 10/15/2008M0-05 Mechanical Schedules 10/15/2008M0-06 Mechanical Schedules 10/15/2008M0.07 Mechanical Site Plan 10/15/2008M1.01 Partial 1st Floor HVAC Plan - Bldg 1 10/15/2008M1.02 Partial 1st Floor HVAC Plan - Bldg 1 10/15/2008M1.03 Partial 1st Floor HVAC Plan - Bldg 1 10/15/2008M1.04 Partial 2nd Floor HVAC Plan - Bldg 1 10/15/2008M1.05 Partial 2nd Floor HVAC Plan - Bldg 1 10/15/2008M1.06 Bldg 4 HVAC Plan Receiving Area 10/15/2008M1.07 Bldg 3 (Kitchen/Dining) HVAC Demolition Plan 10/15/2008M1.08 Bldg 3 (Kitchen/Dining) HVAC New Work Plan 10/15/2008M2.01 Large Scale Mechanical Room Plan - AHU 1-1 10/15/2008M2.02 Large Scale Mechanical Room Plan - AHU 1-2 10/15/2008M2.03 Large Scale Mechanical Room Plan - AHU 1-3, 1-4 10/15/2008M2.04 Large Scale Mechanical Room Plan - AHU 1-5 10/15/2008M2.05 Large Scale Mechanical Room Plan - AHU 4-1 10/15/2008M2.06 Large Scale Mechanical Room Plan - AHU 1-6 10/15/2008M2.07 Large Scale Mechanical Room Plan - AHU 1-7, 1-8 10/15/2008M2.08 Large Scale Mechanical Room Plan - EX - AHU 20-1 10/15/2008M2.09 Chiller Plant Plan (Bldg 4) 10/15/2008M2.10 Chiller Plant and Site Piping Schematic 10/15/2008M2.11 Chiller Plant Section and Piping Elevations 10/15/2008M3.01 Mechanical Details 10/15/2008M3.02 Mechanical Details 10/15/2008M3.03 Mechanical Details 10/15/2008M3.04 Mechanical Details 10/15/2008M3.05 Mechanical Details 10/15/2008M3.06 Mechanical Details 10/15/2008M3.07 Mechanical Details 10/15/2008M3.08 Mechanical Details 10/15/2008M4.01 Mechanical Controls 10/15/2008M4.02 Mechanical Controls 10/15/2008M4.03 Mechanical Controls 10/15/2008M4.04 Mechanical Controls 10/15/2008M4.05 Mechanical Controls 10/15/2008M4.06 Mechanical Controls 10/15/2008M4.07 Mechanical Controls 10/15/2008

4 of 12

Revision 5

Page 29: Plumosa Phase II GMP Cover

Received Date:Original Set

DRAWING # DRAWING TITLE PREPARED BY DRAWING DATE

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Document List

M4.08 Mechanical Controls 10/15/2008M4.09 Mechanical Controls 10/15/2008

Electrical DrawingsJohnson, Levinson, Ragan, Davila, Inc.

E0.01 Electrical Sheet Index 10/15/2008E0.02 Electrical Site Plan 10/15/2008E0.03 Canopy Lighting Plan and Detail 10/15/2008E1.01 Bldg 1 Partial First Floor Lighting Plan 10/15/2008E1.02 Bldg 1 Partial First Floor Power Plan 10/15/2008E1.03 Bldg 1 Partial First Floor Systems Plan 10/15/2008E1.04 Bldg 1 Partial First Floor Lighting Plan, Bldg 2 Lighting Plan 10/15/2008E1.05 Bldg 1 Partial First Floor Power Plan, Bldg 2 Power Plan 10/15/2008E1.06 Bldg 1 Partial First Floor Systems Plan, Bldg 2 Systems 10/15/2008E1.07 Bldg 1 Partial First Floor Lighting Plan 10/15/2008E1.08 Bldg 1 Partial First Floor Power Plan 10/15/2008E1.09 Bldg 1 Partial First Floor Systems Plan 10/15/2008E1.10 Bldg 1 Partial Second Floor Lighting Plan 10/15/2008E1.11 Bldg 1 Partial Second Floor Power Plan 10/15/2008E1.12 Bldg 1 Partial Second Floor Systems Plan 10/15/2008E1.13 Bldg 1 Partial Second Floor Lighting Plan 10/15/2008E1.14 Bldg 1 Partial Second Floor Power Plan 10/15/2008E1.15 Bldg 1 Partial Second Floor Systems Plan 10/15/2008E1.16 Existing Bldg 3 Lighting Plan 10/15/2008E1.17 Existing Bldg 3 Power Plan 10/15/2008E1.18 Existing Bldg 3 Systems Plan 10/15/2008E1.19 Bldg 4 Lighting Plan 10/15/2008E1.20 Bldg 4 Power Plan 10/15/2008E1.21 Bldg 4 Systems Plan 10/15/2008E1.22 Existing Bldg 5 First Floor Plan 10/15/2008E2.01 Enlarged Kitchen Plan 10/15/2008E2.02 Kitchen Equipment Schedule 10/15/2008E2.03 1/4" Scale Plans and Elevations 10/15/2008E2.04 1/4" Scale Plans and Elevations 10/15/2008E2.05 1/4" Scale Plans and Elevations 10/15/2008E2.06 1/4" Scale Plans and Elevations 10/15/2008E3.01 Electrical Power Riser Diagram 10/15/2008E3.02 Systems Riser Diagrams 10/15/2008E3.03 Systems Riser Diagrams 10/15/2008E3.04 Systems Riser Diagrams 10/15/2008E3.05 Systems Riser Diagrams 10/15/2008E4.01 Notes, Legend and Fixture Schedule 10/15/2008E4.02 Miscellaneous Schedules 10/15/2008E4.03 Panelboard Schedules 10/15/2008E4.04 Panelboard Schedules 10/15/2008E4.05 Panelboard Schedules 10/15/2008E4.06 Panelboard Schedules 10/15/2008E4.07 Panelboard Schedules 10/15/2008E5.01 Miscellaneous Details 10/15/2008E5.02 Miscellaneous Details 10/15/2008E5.03 Miscellaneous Details 10/15/2008E5.04 Miscellaneous Details 10/15/2008E5.05 Miscellaneous Details 10/15/2008E5.06 Miscellaneous Details 10/15/2008E5.07 Miscellaneous Details 10/15/2008E5.08 Miscellaneous Details 10/15/2008E5.09 Miscellaneous Details 10/15/2008E5.10 ITV Tower Details 10/15/2008

5 of 12

Revision 5

Page 30: Plumosa Phase II GMP Cover

Received Date:Original Set

DRAWING # DRAWING TITLE PREPARED BY DRAWING DATE

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Document List

Food Service DrawingsTotal Design Consortium

FS-1 Food Service Equipment - Master Utility Schedule Plan 10/15/2008FS-2 Food Service Equipment - Equipment Layout & Schedule 10/15/2008FS-3 Food Service Equipment - Electrical Connection Plan 10/15/2008

FS-3A Food Service Equipment - Electrical Connection Schedule Plan 10/15/2008FS-4 Food Service Equipment - Electrical Connection Plan 10/15/2008

FS-4A Food Service Equipment - Plumbing Connection Schedule Plan 10/15/2008FS-5 Food Service Equipment - Mechanical Connection Schedule Plan 10/15/2008FS-6 Food Service Equipment - Special Condition Plan 10/15/2008FS-7 Food Service Equipment - Details: Elevation / Sections Plan 10/15/2008FS-8 Food Service Equipment - Details: Elevation / Sections Plan 10/15/2008FS-9 Food Service Equipment - Details: Elevation / Sections Plan 10/15/2008

Theater DrawingsTSG Design

Solutions, Inc.T-1 Stage Rigging Detail 10/15/2008T-2 Stage Lighting Detail 10/15/2008T-3 Sound System Detail 10/15/2008T-4 Video System Detail 10/15/2008

END OF SECTION

6 of 12

Revision 5

Page 31: Plumosa Phase II GMP Cover

DOCUMENT TITLE DATE Received

DIVISION 1 GENERAL REQUIREMENTS01010 Summary of Work Contractor Conduit on Campus01027 Procedures for Payment01028 Contract Modification Procedures01039 Project Management and Coordination 01045 Cutting and Patching01060 Regulatory Requirements01120 Alteration Projects Procedures01300 Submittals Procedures01311 Network Analysis Schedules01351 Construction Waste Management01352 Indoor Air Quality (IAQ) Management01353 Noise & Acoustics Management01354 Environmental Management01400 Quality Control01410 Testing Laboratory Service01421 References01500 Temporary Construction Facilities01540 Security Barriers and Enclosures01560 Temporary Controls01600 Material Equipment and Approved Equals01611 Environmental Requirements for Products01650 Starting and Adjusting Systems01700 Contract Closeout01730 Operation and Maintenance Data01740 Warranties01810 Commissioning

DIVISION 2 SITEWORK02060 Building Demolition02070 Selective Demolition02110 Site Clearing02200 Earth Moving02280 Termite Control02400 Asphalt Paving02520 Concrete Paving02540 Athletic Surfacing02580 Pavement Marking02660 Water Distribution System02670 Open End Water Well02685 Gas Piping Storm Drainage Utilities

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Specifications List

Specifications PAGE 7

Revision 5

Page 32: Plumosa Phase II GMP Cover

DOCUMENT TITLE DATE Received

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Specifications List

02700 Storm Drainage Utilities02730 Sanitary Sewerage Utilities02800 Site Improvements02810 Underground Irrigation System02825 Decorative Metal Fencing and Gates02831 Chain Link Fencing and Gates02853 Parking Bumpers02938 Sodding02950 Trees, Plants and Ground Cover

DIVISION 3 CONCRETE03100 Concrete Formwork03200 Concrete Reinforcement03300 Cast-In-Place Concrete03341 Fibrous Reinforcing03346 Concrete Floor Finishing03411 Structural Pre-Cast Concrete03521 Lightweight Insulating Concrete Fill

DIVISION 4 MASONRY04100 Masonry Mortar and Grout04300 Masonry Unit04340 Reinforced Masonry Unit

DIVISION 5 METALS05400 Cold Formed Metal Framing05500 Metal Fabrications05510 Metal Stairs05520 Metal Railings05531 Metal Gratings and Floor Plates05805 Expansion Joint Cover Assemblies

DIVISION 6 WOOD AND PLASTICS06100 Rough Carpentry06200 Finish Carpentry06410 Custom Casework

DIVISION 7 THERMAL MOISTURE PROTECTION07120 Fluid Applied Waterproofing07160 Bituminous Dampproofing07181 Water Repellent Penetrant07191 Vapor Retarders07212 Extruded Polystyrene Board Insulation

Specifications PAGE 8

Revision 5

Page 33: Plumosa Phase II GMP Cover

DOCUMENT TITLE DATE Received

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Specifications List

07213 Batt Insulation07214 Foamed-In-Place Insulation07536 Modified Bitumen Membrane Roofing07620 Flashing Gutters, Downspouts & Other Accessories07724 Roof Hatches07840 Firestop Systems07900 Joint Sealants

DIVISION 8 DOORS AND WINDOWS08050 Door and Window Legend and Schedule

08050-S Door and Window Schedule08110 Metal Doors and Frames08210 Wood Doors08305 Access Doors and Frames08331 Overhead Coiling Doors08333 Coiling Counter Doors08341 Overhead Coiling Grilles08520 Aluminum Windows08710 Door Hardware08800 Glazing

DIVISION 9 FINISHES09050 Finish Schedule Legend

09050-S Finish Schedule09111 Non-Structural Metal Stud Framing09206 Metal Furring and Lathing09210 Gypsum Veneer Plaster 09215 Veneer Plaster09220 Portland Cement Plaster09250 Gypsum Board System09311 Ceramic Tile09330 Quarry Tile09380 Marble Window Stools09511 Acoustical Ceilings09520 Acoustical Wall Panels09650 Resilient Flooring09682 Tile Carpet09900 Painting

DIVISION 10 SPECIALTIES10100 Marker Boards and Tack Boards10171 Toilet Compartments and Cubicles10196 Cuticle Curtains

Specifications PAGE 9

Revision 5

Page 34: Plumosa Phase II GMP Cover

DOCUMENT TITLE DATE Received

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Specifications List

10211 Fixed Louvers10260 Door and Wall Protection10350 Flagpoles10415 Display Cases10420 Plaque10441 Signage10443 Marquee Sign10508 General Corridor Lockers10522 Fire Protection Specialties10532 Walkway Coverings10675 Metal Shelving10800 Toilet Accessories

DIVISION 11 EQUIPMENT11026 Safes11063 Stage Rigging Systems Stage Curtains & Track11066 Stage Lighting Systems11067 Sound and Video System11131 Projection Screens11400 Food Service Equipment11450 Residential Appliances11480 Athletic and Recreational Equipment

DIVISION 12 FURNISHINGS12500 Vertical Louver Blinds12692 Entrance Floor Mats

DIVISION 13 SPECIAL CONSTRUCTION 13120 Fabricated Engineered Structures

DIVISION 14 CONVEYING SYSTEMS14210 Wheelchair Lift14245 Hydraulic Elevators - Passenger

DIVISION 15 MECHANICAL SYSTEMS15000 Basic Mechanical Requirements15073 Minor Plumbing Demolition15073 Minor HVAC Demolition15135 Meters Gages and Thermometers for HVAC Piping15140 Hangers and Supports for Plumbing Piping15140 Hangers and Supports for HVAC Piping15170 Motor Requirements for HVAC15190 Identification for HVAC Piping and Equipment

Specifications PAGE 10

Revision 5

Page 35: Plumosa Phase II GMP Cover

DOCUMENT TITLE DATE Received

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Specifications List

15242 HVAC Vibration Control15260 Plumbing Piping Insulation15260 HVAC Piping Insulation15280 HVAC Equipment Insulation15290 Ductwork Insulation15411 Facility Water Distribution15412 Facility Sanitary Distribution15420 Plumbing Piping 15430 Plumbing Specialties15440 Plumbing Fixtures15450 Plumbing Equipment15500 Fire Suppression15510 Hydronic Piping15515 Hydronic Specialties15535 Refrigeration Piping15540 Hydronic Pumps15671 Air Cooled Refrigerant Condensers15684 Centrifugal Water Chillers15686 Rotary-Screw Water Chillers15712 Cooling Towers15765 Variable Frequency Motor Controls15801 HVAC Water Treatment15817 Electric Resistance Duct Heaters15855 Air Handling Units15870 HVAC Power Ventilators15885 HVAC Air Filters15890 Ductwork 15895 Air Duct Accessories15900 Energy Management and Control Systems15930 Variable Air Volume Units15936 Grilles, Registers, Diffusers15990 Commissioning of HVAC Systems15991 HVAC Testing, Adjusting and Balancing15992 Tests - Plumbing Piping Systems15992 Tests - HVAC Piping Systems

DIVISION 16 ELECTRICAL16010 Electrical Requirements16020 Work Included16050 Electrical Materials and Methods16111 Electrical System Raceway and Boxes16123 Electrical Wire and Cable16141 Wiring Devices

Specifications PAGE 11

Revision 5

Page 36: Plumosa Phase II GMP Cover

DOCUMENT TITLE DATE Received

Plumosa Elementary School Modernization at SeacrestDelray Beach, FL

Phase II GMP Specifications List

16160 Electrical Cabinets and Enclosures16180 Equipment Wiring Systems16190 Hangers and Supports for Electrical Systems16195 Electrical Identification16420 Electrical Utility Service16425 Switchboards16440 Disconnect Switches16450 Grounding and Bonding of Electrical Systems16461 Dry Type Transformers16470 Panelboards16476 Enclosed Switches and Circuit Breakers16477 Fuses (600 Volts and Below)16480 Motor Control16485 Electrical Instrumentation and Control16495 Transfer Switches16510 Interior Lighting16530 Exterior Lighting16535 Emergency Lighting16610 Transient Voltage Suppression16622 Gas Engine Drive Generator Assembly16650 Energy Management and Control System16670 Lightning Protection for Structures16721 Fire Alarm and Smoke Detection Systems16722 Intrusion Detection16723 Video Surveillance System16724 Emergency Radio Communications Systems16725 Access Control16765 Intercom Systems16770 Public Address Systems16781 Master Television Antenna System (MTAS)16902 Electric Controls and Relays16905 Communications System16906 Ceiling Projector System

END OF SECTION

Specifications PAGE 12

Revision 5

Page 37: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

5. MWBE

Revision 5

Page 38: Plumosa Phase II GMP Cover

Revision 5

Page 39: Plumosa Phase II GMP Cover

Revision 5

Page 40: Plumosa Phase II GMP Cover

Revision 5

Page 41: Plumosa Phase II GMP Cover

Revision 5

Page 42: Plumosa Phase II GMP Cover

Revision 5

Page 43: Plumosa Phase II GMP Cover

Corporate Name Principal orDivision of Work and Address Officer's Name License Name & No.

Mechanical Quantum Specialty Contractors Patrick Gordon CMC12495503825 Investment Lane, Suite 5West Palm Beach, FL 33404(561) 868-1008

Electrical Stryker Electrical Steven E. Dixon EC-00008194241 SW High Meadows AvenuePalm City, FL 34990(772) 219-3389

Plumbing Coastal Mechanical Services Alfred Osterhout CMC 035444394 East Drive holder: Howard HauserMelbourne, FL 32904(321) 725-3061

HVAC Quantum Specialty Contractors Patrick Gordon CMC12495503825 Investment Lane, Suite 5West Palm Beach, FL 33404(561) 868-1008

Coastal Mechanical Services Alfred Osterhout CMC 035444394 East Drive holder: Howard HauserMelbourne, FL 32904(321) 725-3061

Roofing A-1 Duran Roofing Eugenio Hernandez CGC0518898095 NW 64th Street1st flr - roofingMiami, FL 33166(305) 500-9373

Concrete & Southwest Construction Julie Sabiston CBC1255584

Masonry 212 Wallace AvenueLehigh Acres, FL 33971(239) 768-9963

Structural / Structural Prestressed Industries Emilio R Vega CGC058209

Precast Concrete 11405 NW 138th StreetMiami, FL 33178(305) 556-6699

Sitework Messier Land Developing, Inc. Edward Schwab CGC0217736903 Vista Parkway North, Suite #1West Palm Beach, FL 33411(561) 616-9819

PHASE II GMP CONSTRUCTION

EXHIBIT SLIST OF MAJOR SUBCONTRACTORS

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACRESTPROJECT NO.: 0871-7507

Exhibit S

Revision 5

Page 44: Plumosa Phase II GMP Cover

Revision 5

Page 45: Plumosa Phase II GMP Cover

Revision 5

Page 46: Plumosa Phase II GMP Cover

THE SCHOOL DISTRICT OF PALM BEACH COUNTYCONSTRUCTION.PURCHASING DEPARTMENT3326 FOREST HILL BOULEVARD, C.216

WEST PALM BEACH. FLORIDA 33406.5813(561) 434-8508

LETTER OF TNTENT - M|NOR|TY/WOMEN BUSTNESS ENTERPRTSE (M/WBE) SUBCONTRACTOR PARTICIPATION

PROJECT NAME: Plumosa Elementary School Modernization at SeacrestPROJECT NO: 0871-7507

NAME OF BIDDER: Southwest Construction Services of SW FL.. Inc.

The undersigned intends to perform work with the above project as (check one):

I Individual tI Partnership E Corporation E[hoint Venture(NOTE: lf a joint venture, attach letterhead or other documentation proving relationship.)

The undersigned intends to perform work with the above project as (check one):

El SuUcontractor tI Manufacturer E Supplier

The undercigned is:

E Certified with the School District of Palm Beach Gounty M/WBE CoordinatorO Certified with the State of Florida, Department of General Services

The undercigned is (check only one in each applicable column):

coLUitN I

_ Black American_ Hispanic American_ Asian American_ Native American

x White American

COLUMN 2

_ Physically Disabled

COLUMN 3

x Female_ Male

Name of M/WBE Subcontracting

tame arQ

Signature:

PARTICIPATION:The undersigned intends to perform the following work in connection with the above project:

ITEM NO: CONTRACT (TRADE) ITEMS AMOUNT

1M/WBE Subcontractor- Cast in Place Concrete Work $1.954.000.00

or print):

Date: )-aq-ot

Revision 5

austib
Typewritten Text
Southwest Construction Services of SW FL, Inc.
austib
Typewritten Text
Page 47: Plumosa Phase II GMP Cover

Southwest Construction Services of SW FL, Inc.

Julie Sabiston, President

Revision 5

Page 48: Plumosa Phase II GMP Cover

Revision 5

Page 49: Plumosa Phase II GMP Cover

Revision 5

austib
Typewritten Text
austib
Typewritten Text
austib
Typewritten Text
Star Quality, Inc.
austib
Typewritten Text
Maximo Sanchez, President
Page 50: Plumosa Phase II GMP Cover

“An Equal Opportunity Employer” M/WBE Certification does not qualify your firm for SBE Set-A-Side Projects.

The School District of Palm Beach County, FL 3300 Forest Hill Blvd., Suite A-106 West Palm Beach, FL 33406-5813 Office of Diversity in Business Practices

Arthur C. Johnson Ph.D., Superintendent Heidi Galloway, Business Analyst

Telephone: (561) 434-7422 Fax: (561) 432-6384

Bid Information: www.bidsync.com E-Mail: [email protected]

M/WBE (Minority/Woman) Business Enterprise

The School District of Palm Beach County has certified STAR QUALITY INC., as a Minority/Woman

Business Enterprise (M/WBE) under the Procurement Category. Your certification is valid for three years, from January 27, 2009 – January 27, 2012.

Certification is not a guarantee that your firm will receive work. If you do not have a vendor number, you will be issued with one after receiving a contract or project. You must notify this office if the status of your firm changes. Failure to report changes that affect the ownership and control of your firm may result in decertification. It is the vendor’s responsibility to maintain the certification. If the certification expires, a contract may be terminated and awarded to another vendor. Your certification is not a blanket conveyance. You have requested certification, demonstrated managerial control or ability, or hold license in a specific trade, commodity or discipline. This certification letter identifies the areas in which your firm has been certified: Casework & Cabinet Manufacturing Services. While you may bid on any service or commodity that you feel qualified for, this certification and any benefits to be derived (preferences or other considerations) shall only be attributable to the trade, service or commodity indicated on the certification letter. Please examine this certificate letter and advise us of any concerns. Any change to your certification requires you to submit proof of expertise, licensure and a business history (at minimum) to justify the additional certification. You are also required to submit a copy of your certification letter with each bid, or proposal that you submit to the School District. This congratulations certification letter lists those areas for which your firm has been certified. The benefits afforded a certified M/WBE will apply only to those areas listed on the certificate. For this reason, we suggest that you keep us advised of all changes relevant to your certification. Again, you must submit a copy of your certification letter with each bid or proposal you submit to the School District or to any prime contractor that you participate with as a subcontractor on a SDPBC project. Sincerely,

[x|w| ZtÄÄÉãtç Heidi Galloway `Business Analyst’ Office of Diversity in Business Practices- School District of Palm Beach County

Revision 5

Page 51: Plumosa Phase II GMP Cover

Revision 5

Page 52: Plumosa Phase II GMP Cover

Revision 5

Page 53: Plumosa Phase II GMP Cover

Revision 5

Page 54: Plumosa Phase II GMP Cover

Revision 5

Page 55: Plumosa Phase II GMP Cover

CMS Speciality Services doing business as Quantum Speciality Contractors

Patrick Gordon, President

Revision 5

Page 56: Plumosa Phase II GMP Cover

Revision 5

Page 57: Plumosa Phase II GMP Cover

Revision 5

Page 58: Plumosa Phase II GMP Cover

Revision 5

Page 59: Plumosa Phase II GMP Cover

Revision 5

Page 60: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

APPENDIX D

Statement of Good Faith Efforts

NOT REQUIRED, WE MET THE GOAL

Revision 5

Page 61: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

APPENDIX E

Good Faith Effort MWBE Subcontractor Participation

NOT REQUIRED, WE MET THE GOAL

Revision 5

Page 62: Plumosa Phase II GMP Cover

PLUMOSA ELEMENTARY SCHOOL MODERNIZATION AT SEACREST DELRAY BEACH, FLORIDA

SDPBC No. 0871-7507

PHASE II GMP CONSTRUCTION March 3, 2009

6. SCHEDULE

Revision 5

Page 63: Plumosa Phase II GMP Cover

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

Milestones

1070 0 LETTER OF INTENT - START BID &AWARD

01DEC08* 5

1160 12 BONDS & INSURANCE 19MAR09 03APR09 0

1000 0 START CONSTRUCTION - NOTICE TOPROCEED

06APR09* 0

1060 0 BUILDING PERMIT REQUIRED 06APR09 0

1140 254* CONSTRUCTION DURATION - SITE 06APR09 05APR10 0

1020 418* CONSTRUCTION DURATION (NTP TOTCO) CALENDAR DAY

06APR09 28MAY10 0

1130 99* CONSTRUCTION DURATION - BLDG 5 21APR09 08SEP09 176

1100 104* CONSTRUCTION DURATION - BLDG 3CAFETERIA

21APR09 15SEP09 171

1050 224* CONSTRUCTION DURATION - BLDG 1 08JUN09 22APR10 18

1120 159* CONSTRUCTION DURATION - BLDG 4 02JUL09 16FEB10 65

1080 129* CONSTRUCTION DURATION - BLDG 2 07JUL09 08JAN10 92

1110 153* CONSTRUCTION DURATION - BLDG 3ADDITION

23JUL09 01MAR10 56

1090 45* CONSTRUCTION DURATION - BLDG 2METAL BDLG

08OCT09 14DEC09 110

1150 39* CONSTRUCTION DURATION - FINALINSPECTIONS

06APR10 28MAY10 0

1030 0 OBTAIN TCO - SUBSTANTIALCOMPLETION

28MAY10 0

1170 15 LEED TESTING 31MAY10 18JUN10 0

1040 60 OBTAIN FULL CO 21JUN10 10SEP10 0

1010 0 OBTAIN CO - FINAL COMPLETION 10SEP10 0

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

LETTER OF INTENT - START BID & AWARD

BONDS & INSURANCE

START CONSTRUCTION - NOTICE TO PROCEED

BUILDING PERMIT REQUIRED

CONSTRUCTION DURATION - SITE

CONSTRUCTION DURATION (NTP TO TCO) CALENDAR DAY

CONSTRUCTION DURATION - BLDG 5

CONSTRUCTION DURATION - BLDG 3 CAFETERIA

CONSTRUCTION DURATION - BLDG 1

CONSTRUCTION DURATION - BLDG 4

CONSTRUCTION DURATION - BLDG 2

CONSTRUCTION DURATION - BLDG 3 ADDITION

CONSTRUCTION DURATION - BLDG 2 METAL BDLG

CONSTRUCTION DURATION - FINAL INSPECTIONS

OBTAIN TCO - SUBSTANTIAL COMPLETION

LEED TESTING

OBTAIN FULL CO

OBTAIN CO - FINAL COMPLETION

© Primavera Systems, Inc.

Start Date 03NOV08

Finish Date 10SEP10

Data Date 03NOV08

Run Date 24FEB09 15:15

Early Bar

Progress Bar

Critical Activity

PGA2

SUFFOLK CONSTRUCTION COMPANY INC

PLUMOSA GMP

SCHEDULE DEVELOPMENT

Sheet 1 of 21

Revision 5

Revision 5

Page 64: Plumosa Phase II GMP Cover

Sheet 2 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

Construction

.

Sitework

C1020 5 ESTABLISH SURVEY CONTROLS/ SITELAYOUT

06APR09 10APR09 0

C1000 10 MOBILIZE TO SITE 06APR09 20APR09 0

C1040 15 GRADE SITE - CUT (NORTH) 14APR09 04MAY09 0

C1760 15 GRADE SITE - FILL (SOUTH) 21APR09 11MAY09 51

C1770 10 DRAINAGE - NORTH 05MAY09 18MAY09 0

C1050 10 TEMPORARY ROADS (NORTH & EAST) 12MAY09 26MAY09 51

C1780 5 DRAINAGE - WEST 19MAY09 26MAY09 0

C2980 10 RETAINING WALLS 19MAY09 02JUN09 43

C1060 5 DRAINAGE - SOUTHEAST 27MAY09 02JUN09 51

C1800 8 DEEP UTILITIES - NORTH 27MAY09 05JUN09 0

C1810 8 DEEP UTILITIES - WEST 08JUN09 17JUN09 40

C1820 10 DEEP UTILITIES - SOUTH 18JUN09 01JUL09 40

C1120 8 SUB-GRADE ROAD & PARKING -NORTHEAST

02JUL09 13JUL09 49

C1130 3 CURBING - NORTHEAST 14JUL09 16JUL09 53

C1840 9 SUB-GRADE ROAD & PARKING - WEST &BUS LOOP

14JUL09 24JUL09 49

C1140 2 ASPHALT - 1ST LIFT- NORTHEAST 17JUL09 20JUL09 53

C1860 5 CURBING - WEST & BUS LOOP 27JUL09 31JUL09 59

C1850 10 SUB-GRADE ROAD & PARKING - NORTH 27JUL09 07AUG09 49

C1880 3 ASPHALT -1ST LIFT - WEST 03AUG09 05AUG09 59

C1870 5 CURBING - NORTH 10AUG09 14AUG09 49

C1890 3 ASPHALT -1ST LIFT - NORTH 17AUG09 19AUG09 49

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

ESTABLISH SURVEY CONTROLS/ SITE LAYOUT

MOBILIZE TO SITE

GRADE SITE - CUT (NORTH)

GRADE SITE - FILL (SOUTH)

DRAINAGE - NORTH

TEMPORARY ROADS (NORTH & EAST)

DRAINAGE - WEST

RETAINING WALLS

DRAINAGE - SOUTHEAST

DEEP UTILITIES - NORTH

DEEP UTILITIES - WEST

DEEP UTILITIES - SOUTH

SUB-GRADE ROAD & PARKING - NORTHEAST

CURBING - NORTHEAST

SUB-GRADE ROAD & PARKING - WEST & BUS LOOP

ASPHALT - 1ST LIFT- NORTHEAST

CURBING - WEST & BUS LOOP

SUB-GRADE ROAD & PARKING - NORTH

ASPHALT -1ST LIFT - WEST

CURBING - NORTH

ASPHALT -1ST LIFT - NORTH

Sheet 2 of 21

Revision 5

Revision 5

Page 65: Plumosa Phase II GMP Cover

Sheet 3 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C3020 0 START FINAL PHASE OF SITEWORK 30OCT09* 0

C1900 10 PLAY COURTS 30OCT09 13NOV09 0

C1830 10 SIDEWALKS 16NOV09 30NOV09 0

C1910 15 WALKWAY COVER - EAST 01DEC09 21DEC09 0

C1920 20 WALKWAY COVER- WEST 22DEC09 19JAN10 0

C3010 9 ASPHALT - TOP COAT & STRIPING 20JAN10 01FEB10 0

C1940 10 FENCING 02FEB10 15FEB10 0

C1150 10 IRRIGATION - SOUTH 16FEB10 01MAR10 0

C1930 10 IRRIGATION - NORTH 02MAR10 15MAR10 0

C1160 10 LANDSCAPING -SOUTH 02MAR10 15MAR10 10

C1950 10 LANDSCAPING - NORTH 16MAR10 29MAR10 0

C1170 5 DEMOBILIZE 30MAR10 05APR10 0

BLDG 1 - NEW ELEMENTARY SCHOOL

Structure

SECTION 1 - NE

C1600 10 GRADE PAD 08JUN09 19JUN09 0

C1610 3 DEEP UTILITIES 22JUN09 24JUN09 0

C1620 5 FOOTINGS 25JUN09 01JUL09 0

C1630 3 STEM WALLS 02JUL09 06JUL09 0

C1640 10 U/G M/E/P R/I 07JUL09 20JUL09 0

C1650 3 SOG 21JUL09 23JUL09 0

C1660 7 CMU TO JOIST BRG ELEV 24JUL09 03AUG09 0

C1670 3 SET PSI JOIST 04AUG09 06AUG09 5

C1680 5 FORM DECK - FL-02 07AUG09 13AUG09 5

C1690 5 MEP R/I DECK FL-02 14AUG09 20AUG09 5

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

START FINAL PHASE OF SITEWORK

PLAY COURTS

SIDEWALKS

WALKWAY COVER - EAST

WALKWAY COVER- WEST

ASPHALT - TOP COAT & STRIPING

FENCING

IRRIGATION - SOUTH

IRRIGATION - NORTH

LANDSCAPING -SOUTH

LANDSCAPING - NORTH

DEMOBILIZE

GRADE PAD

DEEP UTILITIES

FOOTINGS

STEM WALLS

U/G M/E/P R/I

SOG

CMU TO JOIST BRG ELEV

SET PSI JOIST

FORM DECK - FL-02

MEP R/I DECK FL-02

Sheet 3 of 21

Revision 5

Revision 5

Page 66: Plumosa Phase II GMP Cover

Sheet 4 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C1700 3 POUR ELEVATED SLAB 21AUG09 25AUG09 5

C1710 8 CMU TO ROOF PSI JOIST BRG ELEV 26AUG09 04SEP09 5

C1790 3 SET PSI JOIST 08SEP09 10SEP09 14

C1720 5 FORM & REINFORCE ROOF DECK 11SEP09 17SEP09 14

C1730 3 POUR ROOF DECK 18SEP09 22SEP09 14

C2260 3 THOROSEAL FL-01 18SEP09 22SEP09 54

C1740 3 CMU PARAPET 23SEP09 25SEP09 14

C2270 3 THOROSEAL FL-02 28SEP09 30SEP09 57

C1750 5 PARAPET CAP BEAM 28SEP09 02OCT09 14

SECTION 2 - CENTER

C1970 5 DEEP UTILITIES 25JUN09 01JUL09 2

C1980 5 FOOTINGS 02JUL09 08JUL09 2

C1990 3 STEM WALLS 09JUL09 13JUL09 2

C2120 3 ELEVATOR PIT 09JUL09 13JUL09 11

C2130 1 WATERPROOF ELEVATOR PIT 14JUL09 14JUL09 11

C2000 10 U/G M/E/P R/I 14JUL09 27JUL09 2

C2010 3 SOG 28JUL09 30JUL09 2

C2020 8 CMU TO JOIST BRG ELEV 04AUG09 13AUG09 0

C2030 3 SET PSI JOIST 14AUG09 18AUG09 0

C2040 5 FORM DECK - FL-02 19AUG09 25AUG09 0

C2050 10 MEP R/I DECK FL-02 26AUG09 09SEP09 0

C2060 3 POUR ELEVATED SLAB 10SEP09 14SEP09 0

C2070 10 CMU TO ROOF PSI JOIST BRG ELEV 15SEP09 28SEP09 0

C2990 3 SET PSI JOIST 29SEP09 01OCT09 0

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

POUR ELEVATED SLAB

CMU TO ROOF PSI JOIST BRG ELEV

SET PSI JOIST

FORM & REINFORCE ROOF DECK

POUR ROOF DECK

THOROSEAL FL-01

CMU PARAPET

THOROSEAL FL-02

PARAPET CAP BEAM

DEEP UTILITIES

FOOTINGS

STEM WALLS

ELEVATOR PIT

WATERPROOF ELEVATOR PIT

U/G M/E/P R/I

SOG

CMU TO JOIST BRG ELEV

SET PSI JOIST

FORM DECK - FL-02

MEP R/I DECK FL-02

POUR ELEVATED SLAB

CMU TO ROOF PSI JOIST BRG ELEV

SET PSI JOIST

Sheet 4 of 21

Revision 5

Revision 5

Page 67: Plumosa Phase II GMP Cover

Sheet 5 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C2080 8 FORM & REINFORCE ROOF DECK 02OCT09 14OCT09 0

C2090 3 POUR ROOF DECK 15OCT09 19OCT09 0

C3190 3 THOROSEAL FL-01 15OCT09 19OCT09 50

C2100 3 CMU PARAPET 20OCT09 22OCT09 0

C3200 3 THOROSEAL FL-02 23OCT09 27OCT09 44

C2110 5 PARAPET CAP BEAM 23OCT09 29OCT09 0

SECTION 3- SW

C2150 3 DEEP UTILITIES 02JUL09 06JUL09 37

C2160 5 FOOTINGS 07JUL09 13JUL09 37

C2170 3 STEM WALLS 14JUL09 16JUL09 37

C2180 7 U/G M/E/P R/I 17JUL09 27JUL09 37

C2190 3 SOG 28JUL09 30JUL09 37

C2200 8 CMU TO JOIST BRG ELEV 14AUG09 25AUG09 27

C2210 3 SET PSI JOIST 26AUG09 28AUG09 27

C2220 5 FORM DECK - FL-02 31AUG09 04SEP09 27

C2230 5 MEP R/I DECK FL-02 08SEP09 14SEP09 27

C2240 3 POUR ELEVATED SLAB 15SEP09 17SEP09 27

C2280 3 CMU PARAPET 18SEP09 22SEP09 27

C3170 3 THOROSEAL FL-01 23SEP09 25SEP09 55

C2290 5 PARAPET CAP BEAM 23SEP09 29SEP09 27

Facade

SECTION 1 - NE

C3140 5 INSTALL WINDOWS - SECTION 1 FL-01 23SEP09 29SEP09 54

C3180 5 INSTALL WINDOWS - SECTION 1 FL-02 06OCT09 13OCT09 54

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

FORM & REINFORCE ROOF DECK

POUR ROOF DECK

THOROSEAL FL-01

CMU PARAPET

THOROSEAL FL-02

PARAPET CAP BEAM

DEEP UTILITIES

FOOTINGS

STEM WALLS

U/G M/E/P R/I

SOG

CMU TO JOIST BRG ELEV

SET PSI JOIST

FORM DECK - FL-02

MEP R/I DECK FL-02

POUR ELEVATED SLAB

CMU PARAPET

THOROSEAL FL-01

PARAPET CAP BEAM

INSTALL WINDOWS - SECTION 1 FL-01

INSTALL WINDOWS - SECTION 1 FL-02

Sheet 5 of 21

Revision 5

Revision 5

Page 68: Plumosa Phase II GMP Cover

Sheet 6 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

SECTION 2 - CENTER

C3150 5 INSTALL WINDOWS - SECTION 2 FL-01 20OCT09 26OCT09 50

C3210 5 INSTALL WINDOWS - SECTION 2 FL-02 28OCT09 03NOV09 44

SECTION 3- SW

C3160 5 INSTALL WINDOWS - SECTION 3 29SEP09 05OCT09 54

Roof

SECTION 2 - CENTER

C3000 3 STUCCO PARAPET 30OCT09 03NOV09 19

C3080 2 PAINT PARAPET 04NOV09 05NOV09 19

C3090 3 MECHANICAL CURBS 04NOV09 06NOV09 33

C3100 15 ROOFING SYSTEM 06NOV09 30NOV09 19

C3070 7 STUCCO PARAPET 30OCT09 09NOV09 43

C3110 2 PAINT PARAPET 10NOV09 12NOV09 43

C3120 3 MECHANICAL CURBS 10NOV09 13NOV09 49

C3130 7 ROOFING SYSTEM 24NOV09 03DEC09 36

Equipment

C2700 60 INSTALL ELEVATOR 01DEC09 23FEB10 19

Interior Work

SECTION 1 - NE

1ST FLOOR

C2300 15 WALL FRAMING 05OCT09 26OCT09 14

C2310 15 DUCTWORK 13OCT09 02NOV09 24

C2320 15 FIRE SPRINKLER 20OCT09 09NOV09 24

C2330 15 ELECTRICAL R/I 03NOV09 24NOV09 24

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

INSTALL WINDOWS - SECTION 2 FL-01

INSTALL WINDOWS - SECTION 2 FL-02

INSTALL WINDOWS - SECTION 3

STUCCO PARAPET

PAINT PARAPET

MECHANICAL CURBS

ROOFING SYSTEM

STUCCO PARAPET

PAINT PARAPET

MECHANICAL CURBS

ROOFING SYSTEM

INSTALL ELEVATOR

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

Sheet 6 of 21

Revision 5

Revision 5

Page 69: Plumosa Phase II GMP Cover

Sheet 7 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C2340 10 PLUMBING R/I 10NOV09 24NOV09 24

C2350 1 FRAMING INSPECTION 25NOV09 25NOV09 24

C2360 5 INSTALL STAIRS 27NOV09 03DEC09 24

C2370 5 WALL INSULATION 04DEC09 10DEC09 24

C2380 2 SCCI WALL CLOSURE CHECK LIST 11DEC09 14DEC09 24

C2390 10 HANG DRYWALL 15DEC09 29DEC09 24

C2400 10 TAPE & FINISH DRYWALL 30DEC09 12JAN10 24

C2410 5 PRIME PAINT 13JAN10 19JAN10 24

C2420 8 MECH ABOVE CEILING R/I 20JAN10 29JAN10 24

C2430 8 ELECTRICAL ABOVE CEILING R/I 20JAN10 29JAN10 24

C2440 8 PLUMBING ABOVE CEILING R/I 20JAN10 29JAN10 24

C2450 8 SET CERAMIC TILE 20JAN10 29JAN10 32

C2460 3 AC START UP 01FEB10 03FEB10 32

C2470 8 ACOUSTICAL CEILING GRID 01FEB10 10FEB10 24

C2510 10 LAY-IN LIGHT FIXTURES & ELEC TRIM 03FEB10 16FEB10 24

C2500 10 HVAC GRILLES & TRIM 03FEB10 16FEB10 29

C2480 8 FIRST COAT PAINT 04FEB10 15FEB10 32

C2490 8 DOORS & HARDWARE 04FEB10 15FEB10 35

C2520 8 INSTALL CASEWORK 05FEB10 16FEB10 25

C2530 10 PLUMBING FIXTURES 09FEB10 22FEB10 25

C2540 1 ABOVE CEILING INSPECTION 17FEB10 17FEB10 31

C2560 5 FIRE ALARM TEST 17FEB10 23FEB10 24

C2550 4 DROP ACOUSTICAL CEILING TILE 18FEB10 23FEB10 31

C2570 10 CARPET/ FLOOR 22FEB10 05MAR10 31

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

PLUMBING R/I

FRAMING INSPECTION

INSTALL STAIRS

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

MECH ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

LAY-IN LIGHT FIXTURES & ELEC TRIM

HVAC GRILLES & TRIM

FIRST COAT PAINT

DOORS & HARDWARE

INSTALL CASEWORK

PLUMBING FIXTURES

ABOVE CEILING INSPECTION

FIRE ALARM TEST

DROP ACOUSTICAL CEILING TILE

CARPET/ FLOOR

Sheet 7 of 21

Revision 5

Revision 5

Page 70: Plumosa Phase II GMP Cover

Sheet 8 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C2580 5 SPECIALTIES 23FEB10 01MAR10 35

C2590 5 MEPF & LIFE SAFETY INSPECTIONS 24FEB10 02MAR10 24

C2600 5 SCCI WORKLIST 08MAR10 12MAR10 31

C2620 5 OWNER A/E COURTESY WALK 15MAR10 19MAR10 34

C2610 5 FINAL PAINT 15MAR10 19MAR10 37

C2630 5 FINAL CLEAN 22MAR10 26MAR10 37

2ND FLOOR

C2640 15 WALL FRAMING 27OCT09 17NOV09 14

C2650 15 DUCTWORK 03NOV09 24NOV09 14

C2660 15 FIRE SPRINKLER 10NOV09 02DEC09 14

C2670 15 ELECTRICAL R/I 25NOV09 16DEC09 14

C2680 10 PLUMBING R/I 03DEC09 16DEC09 14

C2690 1 FRAMING INSPECTION 17DEC09 17DEC09 14

C2710 5 WALL INSULATION 18DEC09 24DEC09 14

C2720 2 SCCI WALL CLOSURE CHECK LIST 28DEC09 29DEC09 14

C2730 10 HANG DRYWALL 30DEC09 12JAN10 14

C2740 10 TAPE & FINISH DRYWALL 13JAN10 26JAN10 14

C2750 5 PRIME PAINT 27JAN10 02FEB10 14

C2760 8 MECH ABOVE CEILING R/I 03FEB10 12FEB10 14

C2770 8 ELECTRICAL ABOVE CEILING R/I 03FEB10 12FEB10 14

C2780 8 PLUMBING ABOVE CEILING R/I 03FEB10 12FEB10 14

C2790 8 SET CERAMIC TILE 03FEB10 12FEB10 22

C2800 3 AC START UP 15FEB10 17FEB10 24

C2810 8 ACOUSTICAL CEILING GRID 15FEB10 24FEB10 14

C2850 10 LAY-IN LIGHT FIXTURES & ELEC TRIM 17FEB10 02MAR10 14

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

SPECIALTIES

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

OWNER A/E COURTESY WALK

FINAL PAINT

FINAL CLEAN

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

PLUMBING R/I

FRAMING INSPECTION

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

MECH ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

LAY-IN LIGHT FIXTURES & ELEC TRIM

Sheet 8 of 21

Revision 5

Revision 5

Page 71: Plumosa Phase II GMP Cover

Sheet 9 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C2840 10 HVAC GRILLES & TRIM 17FEB10 02MAR10 19

C2820 8 FIRST COAT PAINT 18FEB10 01MAR10 24

C2830 8 DOORS & HARDWARE 18FEB10 01MAR10 27

C2860 8 INSTALL CASEWORK 19FEB10 02MAR10 15

C2870 10 PLUMBING FIXTURES 23FEB10 08MAR10 15

C2880 1 ABOVE CEILING INSPECTION 03MAR10 03MAR10 23

C2900 5 FIRE ALARM TEST 03MAR10 09MAR10 14

C2890 4 DROP ACOUSTICAL CEILING TILE 04MAR10 09MAR10 23

C2910 8 CARPET/ FLOOR 08MAR10 17MAR10 23

C2920 5 SPECIALTIES 09MAR10 15MAR10 25

C2930 5 MEPF & LIFE SAFETY INSPECTIONS 10MAR10 16MAR10 14

C2940 5 SCCI WORKLIST 18MAR10 24MAR10 23

C2960 5 OWNER A/E COURTESY WALK 25MAR10 31MAR10 26

C2950 5 FINAL PAINT 25MAR10 31MAR10 29

C2970 5 FINAL CLEAN 01APR10 07APR10 29

SECTION 2 - CENTER

1ST FLOOR

C3350 15 WALL FRAMING 30OCT09 20NOV09 0

C3360 15 DUCTWORK 06NOV09 30NOV09 1

C3370 15 FIRE SPRINKLER 16NOV09 07DEC09 1

C3380 15 ELECTRICAL R/I 01DEC09 21DEC09 1

C3390 10 PLUMBING R/I 08DEC09 21DEC09 1

C3400 1 FRAMING INSPECTION 22DEC09 22DEC09 1

C3410 10 INSTALL STAIRS 23DEC09 06JAN10 1

C3420 5 WALL INSULATION 07JAN10 13JAN10 1

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

HVAC GRILLES & TRIM

FIRST COAT PAINT

DOORS & HARDWARE

INSTALL CASEWORK

PLUMBING FIXTURES

ABOVE CEILING INSPECTION

FIRE ALARM TEST

DROP ACOUSTICAL CEILING TILE

CARPET/ FLOOR

SPECIALTIES

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

OWNER A/E COURTESY WALK

FINAL PAINT

FINAL CLEAN

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

PLUMBING R/I

FRAMING INSPECTION

INSTALL STAIRS

WALL INSULATION

Sheet 9 of 21

Revision 5

Revision 5

Page 72: Plumosa Phase II GMP Cover

Sheet 10 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C3430 2 SCCI WALL CLOSURE CHECK LIST 14JAN10 15JAN10 1

C3440 10 HANG DRYWALL 18JAN10 29JAN10 1

C3450 10 TAPE & FINISH DRYWALL 01FEB10 12FEB10 1

C3460 5 PRIME PAINT 15FEB10 19FEB10 1

C3470 8 MECH ABOVE CEILING R/I 22FEB10 03MAR10 1

C3480 8 ELECTRICAL ABOVE CEILING R/I 22FEB10 03MAR10 1

C3490 8 PLUMBING ABOVE CEILING R/I 22FEB10 03MAR10 1

C3500 8 SET CERAMIC TILE 22FEB10 03MAR10 9

C3510 3 AC START UP 04MAR10 08MAR10 11

C3520 8 ACOUSTICAL CEILING GRID 04MAR10 15MAR10 1

C3560 10 LAY-IN LIGHT FIXTURES & ELEC TRIM 08MAR10 19MAR10 1

C3550 10 HVAC GRILLES & TRIM 08MAR10 19MAR10 6

C3530 8 FIRST COAT PAINT 09MAR10 18MAR10 11

C3540 10 DOORS & HARDWARE 09MAR10 22MAR10 12

C3570 8 INSTALL CASEWORK 10MAR10 19MAR10 2

C3580 10 PLUMBING FIXTURES 12MAR10 25MAR10 2

C3590 1 ABOVE CEILING INSPECTION 22MAR10 22MAR10 10

C3610 5 FIRE ALARM TEST 22MAR10 26MAR10 1

C3600 4 DROP ACOUSTICAL CEILING TILE 23MAR10 26MAR10 10

C3620 8 CARPET/ FLOOR 25MAR10 05APR10 10

C3630 5 SPECIALTIES 26MAR10 01APR10 12

C3640 5 MEPF & LIFE SAFETY INSPECTIONS 29MAR10 02APR10 1

C3650 5 SCCI WORKLIST 06APR10 12APR10 10

C3670 5 OWNER A/E COURTESY WALK 13APR10 19APR10 13

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

MECH ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

LAY-IN LIGHT FIXTURES & ELEC TRIM

HVAC GRILLES & TRIM

FIRST COAT PAINT

DOORS & HARDWARE

INSTALL CASEWORK

PLUMBING FIXTURES

ABOVE CEILING INSPECTION

FIRE ALARM TEST

DROP ACOUSTICAL CEILING TILE

CARPET/ FLOOR

SPECIALTIES

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

OWNER A/E COURTESY WALK

Sheet 10 of 21

Revision 5

Revision 5

Page 73: Plumosa Phase II GMP Cover

Sheet 11 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C3660 5 FINAL PAINT 13APR10 19APR10 16

C3680 5 FINAL CLEAN 20APR10 26APR10 16

2ND FLOOR

C3690 15 WALL FRAMING 19NOV09 10DEC09 0

C3700 15 DUCTWORK 27NOV09 17DEC09 1

C3710 15 FIRE SPRINKLER 02DEC09 22DEC09 0

C3720 15 ELECTRICAL R/I 15DEC09 05JAN10 1

C3730 10 PLUMBING R/I 23DEC09 06JAN10 0

C3740 1 FRAMING INSPECTION 07JAN10 07JAN10 0

C3760 5 WALL INSULATION 08JAN10 14JAN10 0

C3770 2 SCCI WALL CLOSURE CHECK LIST 15JAN10 18JAN10 0

C3780 10 HANG DRYWALL 19JAN10 01FEB10 0

C3790 10 TAPE & FINISH DRYWALL 02FEB10 15FEB10 0

C3800 5 PRIME PAINT 16FEB10 22FEB10 0

C3810 8 MECH ABOVE CEILING R/I 23FEB10 04MAR10 0

C3820 8 ELECTRICAL ABOVE CEILING R/I 23FEB10 04MAR10 0

C3830 8 PLUMBING ABOVE CEILING R/I 23FEB10 04MAR10 0

C3840 8 SET CERAMIC TILE 23FEB10 04MAR10 8

C3850 3 AC START UP 05MAR10 09MAR10 8

C3860 8 ACOUSTICAL CEILING GRID 05MAR10 16MAR10 0

C3900 10 LAY-IN LIGHT FIXTURES & ELEC TRIM 09MAR10 22MAR10 0

C3890 10 HVAC GRILLES & TRIM 09MAR10 22MAR10 5

C3870 8 FIRST COAT PAINT 10MAR10 19MAR10 8

C3880 10 DOORS & HARDWARE 10MAR10 23MAR10 9

C3910 8 INSTALL CASEWORK 11MAR10 22MAR10 1

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

FINAL PAINT

FINAL CLEAN

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

PLUMBING R/I

FRAMING INSPECTION

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

MECH ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

LAY-IN LIGHT FIXTURES & ELEC TRIM

HVAC GRILLES & TRIM

FIRST COAT PAINT

DOORS & HARDWARE

INSTALL CASEWORK

Sheet 11 of 21

Revision 5

Revision 5

Page 74: Plumosa Phase II GMP Cover

Sheet 12 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C3920 10 PLUMBING FIXTURES 15MAR10 26MAR10 1

C3930 1 ABOVE CEILING INSPECTION 23MAR10 23MAR10 7

C3950 5 FIRE ALARM TEST 23MAR10 29MAR10 0

C3940 4 DROP ACOUSTICAL CEILING TILE 24MAR10 29MAR10 7

C3960 10 CARPET/ FLOOR 26MAR10 08APR10 7

C3970 5 SPECIALTIES 29MAR10 02APR10 11

C3980 5 MEPF & LIFE SAFETY INSPECTIONS 30MAR10 05APR10 0

C3990 5 SCCI WORKLIST 09APR10 15APR10 7

C4000 5 FINAL PAINT 09APR10 15APR10 18

C4010 5 OWNER A/E COURTESY WALK 16APR10 22APR10 10

C4020 5 FINAL CLEAN 16APR10 22APR10 18

SECTION 3- SW

1ST FLOOR

C4030 15 WALL FRAMING 30SEP09 21OCT09 27

C4040 15 DUCTWORK 07OCT09 28OCT09 27

C4050 15 FIRE SPRINKLER 15OCT09 04NOV09 27

C4060 15 ELECTRICAL R/I 29OCT09 19NOV09 27

C4070 10 PLUMBING R/I 05NOV09 19NOV09 27

C4080 1 FRAMING INSPECTION 20NOV09 20NOV09 27

C4090 5 INSTALL STAIRS 23NOV09 30NOV09 27

C4100 5 WALL INSULATION 01DEC09 07DEC09 27

C4110 2 SCCI WALL CLOSURE CHECK LIST 08DEC09 09DEC09 27

C4120 10 HANG DRYWALL 10DEC09 23DEC09 27

C4130 10 TAPE & FINISH DRYWALL 24DEC09 07JAN10 27

C4140 5 PRIME PAINT 08JAN10 14JAN10 27

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

PLUMBING FIXTURES

ABOVE CEILING INSPECTION

FIRE ALARM TEST

DROP ACOUSTICAL CEILING TILE

CARPET/ FLOOR

SPECIALTIES

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

FINAL PAINT

OWNER A/E COURTESY WALK

FINAL CLEAN

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

PLUMBING R/I

FRAMING INSPECTION

INSTALL STAIRS

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

Sheet 12 of 21

Revision 5

Revision 5

Page 75: Plumosa Phase II GMP Cover

Sheet 13 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C4150 8 MECH ABOVE CEILING R/I 15JAN10 26JAN10 27

C4160 8 ELECTRICAL ABOVE CEILING R/I 15JAN10 26JAN10 27

C4170 8 PLUMBING ABOVE CEILING R/I 15JAN10 26JAN10 27

C4180 8 SET CERAMIC TILE 15JAN10 26JAN10 35

C4190 3 AC START UP 27JAN10 29JAN10 35

C4200 8 ACOUSTICAL CEILING GRID 27JAN10 05FEB10 27

C4210 8 FIRST COAT PAINT 01FEB10 10FEB10 35

C4220 8 DOORS & HARDWARE 01FEB10 10FEB10 38

C4240 8 LAY-IN LIGHT FIXTURES & ELEC TRIM 02FEB10 11FEB10 27

C4250 8 INSTALL CASEWORK 02FEB10 11FEB10 28

C4230 8 HVAC GRILLES & TRIM 02FEB10 11FEB10 32

C4260 8 PLUMBING FIXTURES 08FEB10 17FEB10 28

C4270 1 ABOVE CEILING INSPECTION 12FEB10 12FEB10 34

C4290 5 FIRE ALARM TEST 12FEB10 18FEB10 27

C4280 4 DROP ACOUSTICAL CEILING TILE 15FEB10 18FEB10 34

C4300 10 CARPET/ FLOOR 17FEB10 02MAR10 34

C4310 5 SPECIALTIES 18FEB10 24FEB10 38

C4320 5 MEPF & LIFE SAFETY INSPECTIONS 19FEB10 25FEB10 27

C4330 5 SCCI WORKLIST 03MAR10 09MAR10 34

C4350 5 OWNER A/E COURTESY WALK 10MAR10 16MAR10 37

C4340 5 FINAL PAINT 10MAR10 16MAR10 40

C4360 5 FINAL CLEAN 17MAR10 23MAR10 40

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

MECH ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

FIRST COAT PAINT

DOORS & HARDWARE

LAY-IN LIGHT FIXTURES & ELEC TRIM

INSTALL CASEWORK

HVAC GRILLES & TRIM

PLUMBING FIXTURES

ABOVE CEILING INSPECTION

FIRE ALARM TEST

DROP ACOUSTICAL CEILING TILE

CARPET/ FLOOR

SPECIALTIES

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

OWNER A/E COURTESY WALK

FINAL PAINT

FINAL CLEAN

Sheet 13 of 21

Revision 5

Revision 5

Page 76: Plumosa Phase II GMP Cover

Sheet 14 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

BLDG 2 - NEW PHYSICAL ED

Structure

C1510 5 PREP PAD 07JUL09 13JUL09 74

C1520 10 DEEP UTILITIES 14JUL09 27JUL09 74

C1530 10 FORM MONO SLAB 28JUL09 10AUG09 74

C1540 10 U/G M/E/P R/I 11AUG09 24AUG09 74

C1550 3 SOG 25AUG09 27AUG09 74

C1560 5 CMU TO TIE BEAM ELEV 28AUG09 03SEP09 74

C1570 10 SET H.C. PLANK 04SEP09 18SEP09 74

C1580 5 FORM PARAPET BEAM 21SEP09 25SEP09 74

C1590 3 TOPPING SLAB 28SEP09 30SEP09 74

Roof

C3240 5 INSTALL ROOFING SYSTEM 01OCT09 07OCT09 74

Interior Work

C4710 5 WALL FRAMING 08OCT09 15OCT09 74

C4720 5 DUCTWORK 16OCT09 22OCT09 74

C4730 5 FIRE SPRINKLER 16OCT09 22OCT09 74

C4740 5 ELECTRICAL R/I 23OCT09 29OCT09 74

C4750 5 PLUMBING R/I 23OCT09 29OCT09 74

C4760 1 FRAMING INSPECTION 30OCT09 30OCT09 74

C4780 2 WALL INSULATION 02NOV09 03NOV09 74

C4790 1 SCCI WALL CLOSURE CHECK LIST 04NOV09 04NOV09 74

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

PREP PAD

DEEP UTILITIES

FORM MONO SLAB

U/G M/E/P R/I

SOG

CMU TO TIE BEAM ELEV

SET H.C. PLANK

FORM PARAPET BEAM

TOPPING SLAB

INSTALL ROOFING SYSTEM

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

PLUMBING R/I

FRAMING INSPECTION

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

Sheet 14 of 21

Revision 5

Revision 5

Page 77: Plumosa Phase II GMP Cover

Sheet 15 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C4800 5 HANG DRYWALL 05NOV09 12NOV09 74

C4810 6 TAPE & FINISH DRYWALL 13NOV09 20NOV09 74

C4820 2 PRIME PAINT 23NOV09 24NOV09 74

C4830 2 MECH ABOVE CEILING R/I 25NOV09 27NOV09 74

C4850 2 PLUMBING ABOVE CEILING R/I 25NOV09 27NOV09 74

C4840 3 ELECTRICAL ABOVE CEILING R/I 25NOV09 30NOV09 74

C4860 5 SET CERAMIC TILE 25NOV09 02DEC09 75

C4870 3 AC START UP 30NOV09 02DEC09 88

C4880 4 ACOUSTICAL CEILING GRID 30NOV09 03DEC09 74

C4890 3 FIRST COAT PAINT 03DEC09 07DEC09 88

C4900 3 DOORS & HARDWARE 03DEC09 07DEC09 91

C4940 3 PLUMBING FIXTURES 04DEC09 08DEC09 78

C4920 2 LAY-IN LIGHT FIXTURES & ELEC TRIM 08DEC09 09DEC09 74

C4910 2 HVAC GRILLES & TRIM 08DEC09 09DEC09 77

C4990 5 SPECIALTIES 09DEC09 15DEC09 88

C4950 1 ABOVE CEILING INSPECTION 10DEC09 10DEC09 86

C4970 3 FIRE ALARM TEST 10DEC09 14DEC09 74

C4960 2 DROP ACOUSTICAL CEILING TILE 11DEC09 14DEC09 86

C4980 3 CARPET/ FLOOR 15DEC09 17DEC09 86

C5000 5 MEPF & LIFE SAFETY INSPECTIONS 15DEC09 21DEC09 74

C5010 5 SCCI WORKLIST 22DEC09 29DEC09 84

C5030 5 OWNER A/E COURTESY WALK 30DEC09 05JAN10 87

C5020 5 FINAL PAINT 30DEC09 05JAN10 92

C5040 3 FINAL CLEAN 06JAN10 08JAN10 92

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

MECH ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

FIRST COAT PAINT

DOORS & HARDWARE

PLUMBING FIXTURES

LAY-IN LIGHT FIXTURES & ELEC TRIM

HVAC GRILLES & TRIM

SPECIALTIES

ABOVE CEILING INSPECTION

FIRE ALARM TEST

DROP ACOUSTICAL CEILING TILE

CARPET/ FLOOR

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

OWNER A/E COURTESY WALK

FINAL PAINT

FINAL CLEAN

Sheet 15 of 21

Revision 5

Revision 5

Page 78: Plumosa Phase II GMP Cover

Sheet 16 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

BLDG 2 - METAL BUILDING

Structure

C5050 10 ERECT STRUCTURE 08OCT09 22OCT09 110

C5060 5 INSTALL ROOFING SYSTEM 23OCT09 29OCT09 110

Interior Work

C5070 10 FRAME CEILINGS 30OCT09 13NOV09 110

C5080 10 DRYWALL / STUCCO CEILINGS 16NOV09 30NOV09 110

C5090 10 PAINT 01DEC09 14DEC09 110

BLDG 3 - EXIST. CAFETERIA REMODEL

C1180 15 SELECTIVE DEMO 21APR09 11MAY09 171

C1190 8 INSTALL NEW ROOFING SYSTEM 12MAY09 21MAY09 171

C1200 15 M/E/P ABOVE CEILING ROUGH 22MAY09 12JUN09 171

C1960 66 BUILDING 3 INTERIORS 15JUN09 15SEP09 171

BLDG 3 - ADDITION

Structure

C1280 5 PREP PAD 23JUL09 29JUL09 40

C1290 10 DEEP UTILITIES 30JUL09 12AUG09 40

C1300 5 FOOTINGS 13AUG09 19AUG09 40

C1310 3 STEM WALL 20AUG09 24AUG09 40

C1320 10 U/G M/E/P R/I 25AUG09 08SEP09 40

C1330 3 SOG 09SEP09 11SEP09 40

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

ERECT STRUCTURE

INSTALL ROOFING SYSTEM

FRAME CEILINGS

DRYWALL / STUCCO CEILINGS

PAINT

SELECTIVE DEMO

INSTALL NEW ROOFING SYSTEM

M/E/P ABOVE CEILING ROUGH

BUILDING 3 INTERIORS

PREP PAD

DEEP UTILITIES

FOOTINGS

STEM WALL

U/G M/E/P R/I

SOG

Sheet 16 of 21

Revision 5

Revision 5

Page 79: Plumosa Phase II GMP Cover

Sheet 17 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C1340 5 CMU TO JOIST BRG ELEV 14SEP09 18SEP09 40

C1350 3 SET PSI JOIST 21SEP09 23SEP09 40

C2250 3 F/R/ POUR SLAB 24SEP09 28SEP09 40

C1360 3 CMU TO PARAPET BEAM ELEV 29SEP09 01OCT09 40

C1370 5 F/R/ POUR PARAPET CAP BEAM 02OCT09 08OCT09 40

Facade

C3220 7 STUCCO 19OCT09 27OCT09 40

Roof

C3230 2 STUCCO PARAPET 09OCT09 13OCT09 40

C1380 3 INSTALL ROOFING SYSTEM 14OCT09 16OCT09 40

Interior Work

C5480 7 WALL FRAMING 28OCT09 05NOV09 40

C5500 5 FIRE SPRINKLER 06NOV09 13NOV09 47

C5490 15 DUCTWORK 06NOV09 30NOV09 40

C5520 10 PLUMBING R/I 25NOV09 09DEC09 40

C5510 7 ELECTRICAL R/I 01DEC09 09DEC09 40

C5530 1 FRAMING INSPECTION 10DEC09 10DEC09 40

C5550 3 WALL INSULATION 11DEC09 15DEC09 40

C5560 2 SCCI WALL CLOSURE CHECK LIST 16DEC09 17DEC09 40

C5570 5 HANG DRYWALL 18DEC09 24DEC09 40

C5580 7 TAPE & FINISH DRYWALL 28DEC09 05JAN10 40

C5590 3 PRIME PAINT 06JAN10 08JAN10 40

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

CMU TO JOIST BRG ELEV

SET PSI JOIST

F/R/ POUR SLAB

CMU TO PARAPET BEAM ELEV

F/R/ POUR PARAPET CAP BEAM

STUCCO

STUCCO PARAPET

INSTALL ROOFING SYSTEM

WALL FRAMING

FIRE SPRINKLER

DUCTWORK

PLUMBING R/I

ELECTRICAL R/I

FRAMING INSPECTION

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

Sheet 17 of 21

Revision 5

Revision 5

Page 80: Plumosa Phase II GMP Cover

Sheet 18 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C5600 3 MECH ABOVE CEILING R/I 11JAN10 13JAN10 42

C5610 3 ELECTRICAL ABOVE CEILING R/I 11JAN10 13JAN10 42

C5620 3 PLUMBING ABOVE CEILING R/I 11JAN10 13JAN10 42

C5630 8 SET CERAMIC TILE 11JAN10 20JAN10 40

C5640 3 AC START UP 14JAN10 18JAN10 59

C5650 3 ACOUSTICAL CEILING GRID 18JAN10 20JAN10 40

C5660 3 FIRST COAT PAINT 19JAN10 21JAN10 59

C5670 3 DOORS & HARDWARE 19JAN10 21JAN10 62

C5690 5 LAY-IN LIGHT FIXTURES & ELEC TRIM 20JAN10 26JAN10 42

C5680 5 HVAC GRILLES & TRIM 20JAN10 26JAN10 44

C5700 3 INSTALL TOPS 22JAN10 26JAN10 40

C5720 1 ABOVE CEILING INSPECTION 27JAN10 27JAN10 56

C5730 2 FIRE ALARM TEST 27JAN10 28JAN10 42

C5710 4 PLUMBING FIXTURES 27JAN10 01FEB10 40

C5740 2 DROP ACOUSTICAL CEILING TILE 28JAN10 29JAN10 56

C5770 5 MEPF & LIFE SAFETY INSPECTIONS 02FEB10 08FEB10 40

C5760 5 SPECIALTIES 02FEB10 08FEB10 50

C5780 5 SCCI WORKLIST 09FEB10 15FEB10 50

C5800 5 OWNER A/E COURTESY WALK 16FEB10 22FEB10 53

C5790 5 FINAL PAINT 16FEB10 22FEB10 56

C5810 5 FINAL CLEAN 23FEB10 01MAR10 56

BLDG 4 - NEW CEP

Structure

C1390 5 PREP PAD 02JUL09 08JUL09 40

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

MECH ABOVE CEILING R/I

ELECTRICAL ABOVE CEILING R/I

PLUMBING ABOVE CEILING R/I

SET CERAMIC TILE

AC START UP

ACOUSTICAL CEILING GRID

FIRST COAT PAINT

DOORS & HARDWARE

LAY-IN LIGHT FIXTURES & ELEC TRIM

HVAC GRILLES & TRIM

INSTALL TOPS

ABOVE CEILING INSPECTION

FIRE ALARM TEST

PLUMBING FIXTURES

DROP ACOUSTICAL CEILING TILE

MEPF & LIFE SAFETY INSPECTIONS

SPECIALTIES

SCCI WORKLIST

OWNER A/E COURTESY WALK

FINAL PAINT

FINAL CLEAN

PREP PAD

Sheet 18 of 21

Revision 5

Revision 5

Page 81: Plumosa Phase II GMP Cover

Sheet 19 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C1400 10 DEEP UTILITIES 09JUL09 22JUL09 40

C1410 5 FOOTINGS 23JUL09 29JUL09 47

C1420 3 STEM WALL 30JUL09 03AUG09 47

C1430 10 U/G M/E/P R/I 04AUG09 17AUG09 47

C1440 3 SOG 18AUG09 20AUG09 47

C1500 3 HOUSEKEEPING PADS 21AUG09 25AUG09 47

C1450 5 CMU TO JOIST BRG 26AUG09 01SEP09 47

C1460 3 SET PRECAST PLANK 02SEP09 04SEP09 47

C1470 3 CMU PARAPET 08SEP09 10SEP09 47

C1480 3 F/R/ POUR PARAPET CAP BEAM 11SEP09 15SEP09 47

C1490 5 TOPPING SLAB 16SEP09 22SEP09 47

Facade

C5860 15 STUCCO 23SEP09 14OCT09 47

Roof

C5850 7 ROOFING SYSTEM 23SEP09 01OCT09 47

Equipment

C5820 40 SET & WIRE SWTICHGEAR 02OCT09 01DEC09 48

C5830 15 START-UP PERMANENT POWER 02DEC09 22DEC09 48

C5440 10 SET CHILLERS 24DEC09 07JAN10 47

C5450 3 SET GENERATOR 08JAN10 12JAN10 50

C5840 10 COMMISSION CHILLERS 08JAN10 21JAN10 47

C5460 3 START-UP GENERATOR 13JAN10 15JAN10 50

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

DEEP UTILITIES

FOOTINGS

STEM WALL

U/G M/E/P R/I

SOG

HOUSEKEEPING PADS

CMU TO JOIST BRG

SET PRECAST PLANK

CMU PARAPET

F/R/ POUR PARAPET CAP BEAM

TOPPING SLAB

STUCCO

ROOFING SYSTEM

SET & WIRE SWTICHGEAR

START-UP PERMANENT POWER

SET CHILLERS

SET GENERATOR

COMMISSION CHILLERS

START-UP GENERATOR

Sheet 19 of 21

Revision 5

Revision 5

Page 82: Plumosa Phase II GMP Cover

Sheet 20 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C5470 1 TEST GENERATOR 18JAN10 18JAN10 50

Interior Work

C5100 10 WALL FRAMING 07OCT09 21OCT09 47

C5110 10 DUCTWORK 15OCT09 28OCT09 47

C5120 10 FIRE SPRINKLER 15OCT09 28OCT09 47

C5130 10 ELECTRICAL R/I 29OCT09 12NOV09 47

C5140 10 PLUMBING R/I 29OCT09 12NOV09 47

C5150 1 FRAMING INSPECTION 13NOV09 13NOV09 47

C5170 5 WALL INSULATION 16NOV09 20NOV09 47

C5180 1 SCCI WALL CLOSURE CHECK LIST 23NOV09 23NOV09 47

C5190 10 HANG DRYWALL 24NOV09 08DEC09 47

C5200 6 TAPE & FINISH DRYWALL 09DEC09 16DEC09 47

C5210 5 PRIME PAINT 17DEC09 23DEC09 47

C5390 5 MEPF & LIFE SAFETY INSPECTIONS 22JAN10 28JAN10 47

C5400 5 SCCI WORKLIST 29JAN10 04FEB10 57

C5420 5 OWNER A/E COURTESY WALK 05FEB10 11FEB10 60

C5410 5 FINAL PAINT 05FEB10 11FEB10 65

C5430 3 FINAL CLEAN 12FEB10 16FEB10 65

BLDG 5 - AUDITORIUM REMODEL

C1210 15 SELECTIVE DEMO 21APR09 11MAY09 176

C1220 5 FILL ORCHESTRA PIT 12MAY09 18MAY09 176

C1230 2 POUR CUP SLAB AT ORCHESTRA PIT 19MAY09 20MAY09 176

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

TEST GENERATOR

WALL FRAMING

DUCTWORK

FIRE SPRINKLER

ELECTRICAL R/I

PLUMBING R/I

FRAMING INSPECTION

WALL INSULATION

SCCI WALL CLOSURE CHECK LIST

HANG DRYWALL

TAPE & FINISH DRYWALL

PRIME PAINT

MEPF & LIFE SAFETY INSPECTIONS

SCCI WORKLIST

OWNER A/E COURTESY WALK

FINAL PAINT

FINAL CLEAN

SELECTIVE DEMO

FILL ORCHESTRA PIT

POUR CUP SLAB AT ORCHESTRA PIT

Sheet 20 of 21

Revision 5

Revision 5

Page 83: Plumosa Phase II GMP Cover

Sheet 21 of 21

Activity

ID

Orig

Dur

Activity

Description

Early

Start

Early

Finish

Total

Float

C1240 3 EXCAVATE FOR NEW FOOTINGS 21MAY09 26MAY09 176

C1250 3 REINFORCE & POUR NEW FOOTINGS 27MAY09 29MAY09 176

C1260 2 MASONRY TO ELEVATOR 01JUN09 02JUN09 176

C1270 2 POUR BACK SLAB 03JUN09 04JUN09 176

C2140 67 BUILDING 5 INTERIORS 05JUN09 08SEP09 176

Closeout

C5870 0 ARCHITECT SUBSTANTIAL COMPLETIONLETTER

05APR10 0

C3030 15 FINAL INSPECTIONS 06APR10 26APR10 0

C3040 8 SCCI WORKLIST 27APR10 06MAY10 0

C3050 8 MP & O-A/E PUNCHLIST 07MAY10 18MAY10 0

C3060 8 FINAL CLEAN 19MAY10 28MAY10 0

2008 2009 2010 2011S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M AMAY

EXCAVATE FOR NEW FOOTINGS

REINFORCE & POUR NEW FOOTINGS

MASONRY TO ELEVATOR

POUR BACK SLAB

BUILDING 5 INTERIORS

ARCHITECT SUBSTANTIAL COMPLETION LETTER

FINAL INSPECTIONS

SCCI WORKLIST

MP & O-A/E PUNCHLIST

FINAL CLEAN

Sheet 21 of 21

Revision 5

Revision 5