Upload
vuongkhanh
View
231
Download
3
Embed Size (px)
Citation preview
1
PMP® Certification Exam PreparationPMP Certification Exam Preparation PMBOK® 5th Edition ‐ Crash Course
with Bill Doescher, PMP®, MBA, CSMP i i l C lt t d P d t D l t Di tPrincipal Consultant and Product Development Director
Bill Doescher, PMP®
Product Development Director and Principal Consultant, BMC
Bill Doescher is a Principal Consultant and Product Development Director with Business Management Consultants based in Houston, Texas. In his 20‐year career, he has led project teams in new product development, application development, technology introduction, project and portfolio management processes, business process change, and marketing program development.
Mr. Doescher has a strong belief that projects are the instruments of change, and people are the power behind projects. For continued growth and evolution, businesses must be dedicated to improving their ability to translate strategy into projects, to enhancing the environment in which their projects operate, and to maturing the knowledge and skills of their project team members.
Mr. Doescher has held engineering, engineering management, project and program management positions in the geophysical and high tech industries with Geosource, Compaq Computer and Hewlett‐Packard.g , p q p
Mr. Doescher earned a B.S. in Electrical Engineering with Honors at the University of Texas at Austin and an M.B.A. at the University of Houston. He is a member of the Project Management Institute, a PMI®‐certified Project Management Professional (PMP®) and Certified Scrum Master (CSM). He is also a member of the Engineering Management Society of the Institute of Electrical and Electronics Engineers (IEEE).
2
2
Presentation Objectives
• Introduction to PMI, PMP®, and the exam
• Role of, and an introduction to, the PMBOK® Guide, Fifth Edition
• Study recommendations
• Benchmark your current preparation
• Answer any questions you may have
3
Introduction to PMI, the PMP® Certification, and the Exam
4
3
PMI, the PMP®, and the Exam
• PMI was formed in 1969 to promote the profession of project managementprofession of project management
• The PMP® Certification was introduced in 1984– Most globally recognized
• The PMP® is for experienced project team leaders– CAPM®, PgMP®, PMI‐ACP®, PMI‐RMP®, PMI‐SP®, OPM3®
• The PMP® Exam tests for project management knowledge and experience
5
Two Essential Guides ‐ The PMP® Handbook and the PMBOK® Guide, Fifth Edition
View online or download from PMI.org
Purchase paper copy or download from PMI.org (Download is free for PMI members.)
6
4
The PMBOK® Fifth Edition and New Test
The PMBOK® Guide Fourth Edition was introduced in December 2008,
and the new Fifth Edition just released January 2013
Th C ifi i h J l 31 2013 fl i h The Certification test changes on July 31, 2013 to reflect content in the fifth edition PMBOK Guide
The PMP examination consists of 200 individually‐selected, multiple‐choice questions, with a four hour time limit
•• That’s 72 seconds (or 1.2 minutes) per questionThat’s 72 seconds (or 1.2 minutes) per question
The PMP® examination tests for both your project management knowledge and your ability to apply that knowledge in typical project situations.
Visit www.pmi.org, download PMP Certification Handbook
7
PMP Test Domain Content
Project Initiation 13% jProject Planning 24% Project Execution 30%Project Monitoring & Control 25%Project Closing 8%
25 of the 200 questions will not be graded, and are reserved by PMI for evaluation
8
5
Qualification Requirements – PMP® Exam
Graduate
Application Fee:PMI Member = €340, $405 USNon‐Member = € 465, $555 US(Three‐year renewal cycle)
35 contact hours (PDU’s) of PM education
+ =
A minimum of 4500 hours PM experience within the past 8
years
A minimum of 7500 hours PM
Non‐Graduate
Eligibility to take the PMP®
examination
(Three‐year renewal cycle)
A minimum of 7500 hours PM experience within the past 8
years
9
Apply to PMI to take the testSchedule a date with Prometric
http://www pmi org
Application: Project Management Institute (PMI)
ATHENS, GREECE
http://www.pmi.org
Random audit when you submit exam payment
Schedule a test date with Prometric
Control is through audit
http://www.prometric.com/PMI/default.htm
Rescheduling fee = $70 US
Note: You have 90 days to complete application.
THESSALONIKI, GREECE
Candidates have three (3) opportunities to pass the exam in one year. If they do not pass any, they must wait 1 year from the date of the last attempt.
from 30 to 2 days prior to exam date
10
6
Types of questions to expect
You are advised that a major purchased part on your project
Questions requiring experience more than study
You are advised that a major purchased part on your projectwill be delayed. What do you do?
A. Ignore it. It will go awayB. Notify your bossC. Let the customer know about it and talk over optionsD. Meet with the team and identify alternatives
11
Types of questions to expect
A study shows that every time you double the production of
Information that does not matter (distractors)
A study shows that every time you double the production of“widgets”, unit cost goes down by 10%. Based on the study,the company concludes that the production of 4,000 “widgets”will cost $19,000. This illustrates:
A. Learning curve effectsB. Law of diminishing returnsC. The 80/20 ruleD. Bottoms up cost estimatingD. Bottoms up cost estimating
12
7
Types of questions to expect
Questions designed to make you make you think carefully
The theory “optimum quality level is obtained whenThe theory optimum quality level is obtained whenincremental revenue from product improvement equalsincremental cost to secure it” comes from
A. Quality control analysisB. Marginal analysisC. Standard quality analysisD. Conformance analysis
And many more types…13
The PMBOK® Guide, Fifth Edition
14
8
The Role of the PMBOK® Guide
Project managementbody of knowledgeG ll t d
A standard, not a methodology
Common vocabulary
PMBOK® Guide
Interpersonalskills
Applicationarea
knowledge
body of knowledgeGenerally accepted good practice
Common vocabulary
Generalmanagementknowledge
Understandingproject
environment
Not applied uniformly to all projects
Coordinates with the standards on program and portfolio management
15
Relationship between Project, Program, Portfolio Management
Strategic Planning
Management by Projects
Management of Operations
Portfolio Management
ProgramManagement
Role of the PM –to lead the team responsible for delivery of the project objectives.
Project Management
Processes, Tools, Metrics
16
9
Organizational influences on project management
Organizational Communications
Organizational Cultures and
Organizational Structures
StylesStructures
17
Other Organizational Influences
• Organizational Process Assets
– Processes and Procedures
– Corporate Knowledge Base
• Enterprise Environmental Factors
18
10
Project Stakeholders and Governance
Stakeholders are persons or organizations who are actively involved in the project or whose interests may be positively or negatively by the performance or completion of the project.
A stakeholder may also exert influence over the project or its deliverables.
Project governance framework provides the project manager the team with a structure processesmanager the team with a structure, processes, decision‐making models and tools for managing the project, while supporting and controlling the project for successful delivery.
The PMO may play a key role in project governance.
19
The Project Team
Those who will act together in performing the work of the project to achieve its objectives.
Project Manager
SellersUsers /
CustomerProjectStaff
PM Staff BusinessPartners
Team members may be full‐time, part time.PM may have full authority, or relatively no authority over team members.
20
11
The PMI PM Process Groups
Monitoring & Controlling Processes
Closing ProcessesInitiating ProcessesPlanning Processes
Executing Processes
The processes within and between the Process Groups overlap and interact.
21
PMI Project Management Process FrameworkProcess Groups
Knowledge AreasExecuting Closing
Monitoring &Controlling
Management
5. Project ScopeManagement
4. Project Integration 4.1 Dev. Project Charter 4.2 Develop Project 4.3 Direct & Manage 4.4 Monitor & Control Project Work 4.6 Close Project or PhaseManagement Plan Project Work 4.5 Perf. Integrated Change Control
5.1 Plan Scope Mgmt. 5.5 Validate Scope5.2 Collect Requirements 5.6 Control Scope5.3 Define Scope
PlanningInitiating
6. Project TimeManagement
7. Project CostManagement
8. Project QualityManagement
9. Project HumanResource Management
10. Project CommunicationsManagement
p5.4 Create WBS
6.1 Plan Schedule Mgmt. 6.7 Control Schedule6.2 Define Activities6.3 Sequence Activities6.4 Est. Activity Resources6.5 Est. Activity Durations6.6 Dev. Schedule
7.1 Plan Cost Mgmt. 7.3 Control Costs7.2 Estimate Costs7.3 Determine Budget
8.1 Plan Quality 8.2 Perform Quality 8.3 Control QualityManagement Assurance
9.1 Plan Human Resource 9.2 Acquire Project TeamManagement 9.3 Develop Project Team
9.4 Manage Project Team
10.1 Plan Communications 10.2 Manage 10.3 ControlManagement Communications Communicationsg
11. Project RiskManagement
12. Project ProcurementManagement
13. Project StakeholderManagement
11.1 Plan Risk Management 11.6 Control Risks11.2 Identify Risks11.3 Perform Qual. Risk Analysis11.4 Perform Quant. Risk Analysis11.5 Plan Risk Responses
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 12.4 Close Procurements
13.1 Identify Stakeholders 13.2 Plan Stakeholder 13.3 Manage Stakeholder 13.4 Control StakeholderManagement Engagement Engagement
From PMBOK® Guide, Fifth Edition, page 61.
22
12
The Project Life Cycle(vs. Product Life Cycle and Process Groups)
Starting a Project
Organizing and
Preparing
Executing the Work Closing a Project
l p g
Cos
t and
Sta
ffin
g L
evel
Time
Project Charter
Project Management Plan
Accepted Deliverables
Archived Project
Documents
23
Project Life Cycles
• Life Cycle Phases
– Single Phase vs. Multi‐phase
– Sequential or Overlapping phases
• Life Cycle Approaches
– Predictive
– Iterative and Incremental– Iterative and Incremental
– Adaptive
24
13
Practice Exam Questions
2 Project sponsors have the GREATEST influence on the scope2. Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:
A. Concept phaseB. Development phaseC. Execution phaseD. Close‐down phase
25
Practice Exam Questions
1 All of the following are the responsibility of a project1. All of the following are the responsibility of a project manager except?
A. Maintain the confidentiality of customer confidential information
B. Determine the legality of company proceduresC. Ensure that a legal conflict of interest does not
compromise the legitimate interest of the customerD. Provide accurate and truthful representations of costD. Provide accurate and truthful representations of cost
estimates
26
14
PMI Project Management Process FrameworkProcess Groups
Knowledge AreasExecuting Closing
Monitoring &Controlling
Management
5. Project ScopeManagement
4. Project Integration 4.1 Dev. Project Charter 4.2 Develop Project 4.3 Direct & Manage 4.4 Monitor & Control Project Work 4.6 Close Project or PhaseManagement Plan Project Work 4.5 Perf. Integrated Change Control
5.1 Plan Scope Mgmt. 5.5 Validate Scope5.2 Collect Requirements 5.6 Control Scope5.3 Define Scope
PlanningInitiating
6. Project TimeManagement
7. Project CostManagement
8. Project QualityManagement
9. Project HumanResource Management
10. Project CommunicationsManagement
p5.4 Create WBS
6.1 Plan Schedule Mgmt. 6.7 Control Schedule6.2 Define Activities6.3 Sequence Activities6.4 Est. Activity Resources6.5 Est. Activity Durations6.6 Dev. Schedule
7.1 Plan Cost Mgmt. 7.3 Control Costs7.2 Estimate Costs7.3 Determine Budget
8.1 Plan Quality 8.2 Perform Quality 8.3 Control QualityManagement Assurance
9.1 Plan Human Resource 9.2 Acquire Project TeamManagement 9.3 Develop Project Team
9.4 Manage Project Team
10.1 Plan Communications 10.2 Manage 10.3 ControlManagement Communications Communicationsg
11. Project RiskManagement
12. Project ProcurementManagement
13. Project StakeholderManagement
11.1 Plan Risk Management 11.6 Control Risks11.2 Identify Risks11.3 Perform Qual. Risk Analysis11.4 Perform Quant. Risk Analysis11.5 Plan Risk Responses
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 12.4 Close Procurements
13.1 Identify Stakeholders 13.2 Plan Stakeholder 13.3 Manage Stakeholder 13.4 Control StakeholderManagement Engagement Engagement
From PMBOK® Guide, Fifth Edition, page 61.
27
Knowledge Area Mind Maps
28
15
Initiating Process Group
Initiating
4.1 Develop Project Charter13.1 Identify Stakeholders
29
4.1 Develop Project Charter
30
16
4.1 Develop Project Charter
ExamTip
31
13.1 Identify Stakeholders
It is critical for project success to identify the stakeholders early in the project, and to analyze their levels of interest, expectations, importance and influence
Stakeholders should be classified according to their interest, involvement and influence in the project
32
17
Planning Process Group Planning
4.1 Develop Project Management Plan5.1 Plan Scope Management5.2 Collect Requirements
5.3 Define Scope5 4 Create WBS5.4 Create WBS
6.1 Plan Schedule Management6.2 Define Activities
6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Durations
6.6 Develop Schedule7.1 Plan Cost Management
7.2 Estimate Costs7.3 Determine Budget
8.1 Plan Quality Management9 1 Plan Human Resource Management9.1 Plan Human Resource Management10.1 Plan Communications Management
11.1 Plan Risk Management11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses12.1 Plan Procurement Management13.1 Plan Stakeholder Management
33
4.2 Develop Project Management Plan
Scope Management Planp gRequirements Management Plan
Schedule Management PlanCost Management Plan
Quality Management PlanProcess Improvement Plan
Human Resource Management PlanCommunications Management Plan
Ri k M t PlRisk Management PlanProcurement Management PlanStakeholder Management Plan
Scope BaselineSchedule Baseline
Cost Baseline34
18
Scope Management: Planning
5.1 Plan Scope Management• Scope management plan
5.2 Collect Requirements• Requirements documentation• Traceability matrix• Scope management plan
• Requirements management plan
5.3 Define Scope• Project Scope Statement
Traceability matrix
MAILworksWBS
PlanningServer
Preparation DocumentsMigrate PROFS
Customers
Migrate Other E-
Mail Users
Develop Migration
Plan
Class for
Configure MAILworks
Server
Configure
Training Ref.
Material
Review of
Migrate PCSA Cust.
Migrate Off-site PROFS
Migrate Remaining
PROFS
Migrate Novell Cust.
Admin.
Notify Cust for Training
5.4 Create WBS• Scope Baseline
(project scope statement, WBS, WBS dictionary)
Class for Local Cust.
Class for Off-site Cust.
ID HORO E-Mail Cust.
Schedule Cust for Training
Configure Dialup Access
Ref. Material
Produce Final Docs.
Admin. MailworksAccounts
Notify Cust for Training
Change Cust to
Mailworks
Train Cust.
Admin. MailworksAccounts
Notify Cust for Training
Change Cust to
Mailworks
Train Cust.
Admin. MailworksAccounts
Notify Cust for Training
Change Cust to
Mailworks
Train Cust.
Admin. MailworksAccounts
Notify Cust for Training
Change Cust to
Mailworks
Train Cust.
MailworksAccounts
Change Cust to
Mailworks
Train Cust.
Work Packages35
Time Management: Planning
6.2 Define
6.3 Sequence Activities
Activities6.1 Plan Schedule Management
6.4 Estimate Activity
Resources
Activities
3
4
8
6
54
2
4 1 6
1
7
5
63
6.5 Estimate Activity Duration
6.6 Develop Schedule
36
19
Cost Management: Planning
7.1 Plan Cost Management• Cost management plan
7.3 Determine Budget• Cost baseline• Project funding requirements
7.2 Estimate Costs• Activity cost estimates• Basis of estimates
37
8.1 Plan Quality Management
Quality metrics
Quality Management Plan• Quality requirements• Quality assurance• Quality control
Process Improvement Plan
Quality checklists
• Project and product processes
38
20
9.1 Plan Human Resource Management
Human Resource Management Plan
• Roles and responsibilities
– Role, authority, responsibility, competency
• Project organization charts
• Staffing management plan
– Staff acquisition, resource calendars, release plan, training needs, recognition and rewards, compliance and safety
39
10.1 Plan Communications
Tools & TechniquesC i ti i t l i• Communication requirements analysis
• Communication technology• Email, video, websites, phone, texts, posters, …
• Communication models• Encode, Transmit, Decode, Acknowledge, Feedback
• Communication methods• Push, pull, interactive
• Meetings
Communications management plan
40
21
Risk Management: Planning
11.1 Plan Risk Management• Risk management plan
11.2 Identify Risks• Risk register
11.3 Qualitative
11.4 Quantitative Risk Analysis
Risk Analysis
11.5 Plan Risk Responses
41
12.1 Plan Procurement Management
M k B
Outputs:
Make‐or‐Buy Decisions
Procurement Statements of Work
Change Requests
42
22
13.2 Plan Stakeholder Management
Tools & TechniquesE t j d t• Expert judgment
• Meetings• Analytical techniques
Stakeholder management plan
43
Practice Exam Questions
3 The decomposition process is a technique used to construct3. The decomposition process is a technique used to construct a:
A. Precedence networkB. Critical Path Method DiagramC. Variance analysisD. Work breakdown structure
44
23
Practice Exam Questions
2. If the numbers in the PDM network below represent days to complete each task what is the overall duration of thecomplete each task, what is the overall duration of the project?
A. 20 DaysB. 23 DaysC. 18 DaysD. 21 Days
45
Practice Exam Questions
1 The project manager is preparing the budget for the project1. The project manager is preparing the budget for the project. There are a number of inputs to project budgeting that she will use. One of the things the project manager will not use is:
A. Cost baselineB. Cost estimatesC. Project scheduleD. Work breakdown structureD. Work breakdown structure
46
24
Executing Process Group
Executing
4.3 Direct and Manage Project Work8.2 Perform Quality Assurance
9.2 Acquire Project Team9.3 Develop Project Team9.4 Manage Project Team
10.2 Manage Communications12.2 Conduct Procurements12.2 Conduct Procurements13.3 Manage Stakeholder
Engagement
47
4.3 Direct and Manage Project Work
Outputs:
Work performance dataA l /fi i h
Deliverables• Actual start/finish• Actual cost• KPI’s, technical
performance measures
Change requests• Corrective action• Preventive action• Defect repair• Document
updates
48
25
8.2 Perform Quality Assurance
QualityQuality AssuranceAssurance (QA)(QA):: the process of auditing quality requirements, and the results
from quality control (QC) measurements, to ensure quality standards and operationaldefinitions are useddefinitions are used.
Quality assurance involves Quality Audits, and is part of the Execution Process Group.
QualityQuality ControlControl (QC)(QC):: the process of monitoring and recording results (both product
and project management) of executing quality activities to assess performance and torecommend necessary changes. Involves identifying ways to remove the causes ofquality defects.
Quality control involves inspection and requires an understanding of sampling strategies,tolerances, and the causes of variation in a process. It is part of the Monitoring andControlling Process Group.
49
Quality Tools, Tools, Tools…
Seven Basic Quality Tools
• Cause & Effect Diagrams
Other Quality Tools
• Affinity Diagrams• Cause & Effect Diagrams
• Flowcharts
• Checksheets
• Pareto Diagrams
• Histograms
• Affinity Diagrams
• Process Decision Program Charts
• Interrelationship Diagraphs
• Tree Diagrams
P i iti ti M t i• Control Charts
• Scatter Diagrams
• Prioritization Matrices
• Activity Network Diagrams
• Matrix Diagrams
26
Human Resource Management: Executing
9.2 Acquire Project Team Adjourning
9.3 Develop Project Team
Forming
Storming
Norming
Performing
9.4 Manage Project Team• Observation and conversation• Project performance appraisals• Conflict management• Interpersonal skills
51
10.2 Manage Communications
Manage CommunicationsManage Communicationsinvolves the activities required for information to be createdfor information to be created, distributed, received, acknowledged, and understood. Outputs may include:Stakeholder notificationsStakeholder notificationsPerformance Performance reportsreportsProject presentationsProject presentationsProject recordsProject recordsFeedback from stakeholdersFeedback from stakeholdersLessons learned documentationLessons learned documentation
52
27
12.2 Conduct Procurements
Outputs:
• Selected sellers
• Agreements (contracts)
• Resource calendars
• Change requests
• Project plan or document updates
53
13.3 Manage Stakeholder Engagement
Tools & TechniquesC i ti th d• Communication methods
• Interpersonal skills• Management skills
• Issue log• Change requests• Updates to plan,
documents or OPAs
54
28
Practice Exam Questions
2 Which of the following is not a form of power derived from2. Which of the following is not a form of power derived from the project manager’s position:
A. FormalB. RewardC. PenaltyD. Expert
55
Practice Exam Questions
1. The project team is arguing about the prospective sellers who have submitted proposals. One team member argues for a certain seller while another team member wants the project to be awarded to a different seller. The project manager should remind the team to focus on what item in order to make a selection?
A. Procurement documentsB. Procurement auditsC E l ti it iC. Evaluation criteriaD. Procurement management plan
56
29
Monitoring & Controlling Process Group
Monitoring & Controlling
4.4 Monitor & Control Project Work4.5 Perform Integrated Change Control
5.5 Validate Scope5.6 Control Scope
6.7 Control Schedule7.4 Control Costs8.3 Control Quality
10.3 Control Communications11.6 Control Risks
12.3 Control Procurements13.4 Control Stakeholder Engagement
57
Integration Management: Mon. & Control
• 4.4 Monitor and Control Project Work
– Accept and analyze information from the control processes
– Develop work performance reports, change requests, updates to project plan and documents
• 4.5 Perform Integrated Change Control
– Review all change requests
– Approve/reject, maintain change log, update project plans and documents
58
30
5.5 Validate Scope
Validate Validate ScopeScopeis the process of formalizing acceptanceformalizing acceptance of the completed project deliverables.
Scope validation is different from quality control in that validate validate scope is primarily scope is primarily concerned with the concerned with the acceptance of the acceptance of the deliverablesdeliverables
59
5.6 Control Scope
60
31
6.7 Control Schedule & 7.4 Control Costs
PV = Planned Value (was BCWS) (1)
EV = Earned Value (was BCWP) (2)
AC = Actual Cost (was ACWP) (3)
(1) requires a performance baseline(2) requires a way to measure value of work
completed (earned value)(3) requires a way to collect actual costs at work
package levelpackage level
Cost, Hours, or Work Products
EV
PVPlanned Value
ACActual Cost
SVScheduleVariance
CVCost
Variance
TotalVariance
t Actual
t When Planned
Time
Work Performed(Earned Value)
Variances, Performance Indices & Forecasts
61
8.3 Control Quality
Know the difference between:
• Prevention and Inspection
• Attribute sampling and variables sampling
• Tolerances and control limits
QC Outputs
• Quality control measurements
• Validated changes
• Verified (correct) deliverables
• Work performance information
• Change requests, document updates62
32
The Other M&C Processes
• 10.3 Control Communications
• 11.6 Control Risks
– Implementing plans, reassessing risks, evaluating effectiveness of risk process
• 12.3 Control Procurements
– Performance reviews reporting– Performance reviews, reporting
– Claims administration
• 13.4 Control Stakeholder Engagement
63
Practice Exam Questions
3 Your most recent project status report contains the following3. Your most recent project status report contains the following information:
EV (BCWP) = 3,000, AC (ACWP) = 3,500, and PV (BCWS) = 4,000.
The schedule variance is:
A. + 1,000B. + 500B. + 500C. ‐ 500D. ‐ 1, 000
64
33
Practice Exam Questions
2 While completing a project a project manager realizes he needs to2. While completing a project, a project manager realizes he needs to decrease project costs. After researching his options, he comes up with the following choices. Which choice would decrease project costs?
A. Change to component A from component B. Component A costs more to purchase but has a lower lifecycle cost than B
B. Change task A to be completed by resource B instead of resource C. Resource B is a more experienced worker
C. Move tasks B and H to occur concurrently, and take the risk of a 30%C. Move tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources later
D. Delete an acceptance test from the project plan
65
Practice Exam Questions1. You are halfway through a major new cell phone rollout. There are 200
locations in the U.S. with another 100 in Singapore. A software seller has just released a major software upgrade for some of the phones being produced The upgrade would provide the customer with functionalityproduced. The upgrade would provide the customer with functionality they requested that was not available at the time the project began. What is the best course of action under these circumstances?
A. Continue as planned, your customer has not requested a changeB. Inform the customer of the upgrade and the impacts to the project’s
timeline and functionalityC. Implement the change and adjust the schedule as necessary because
this supports the customer’s original requestD. Implement the change for the remaining supply and continue with
the schedule
66
34
Closing Process Group
67
4.6 Close Project or Phase
Outputs:
Final product, service or result transition
Organizational process assets updates• Project files• Project or phase closure
documents• Historical information,
lessons learned
68
35
12.4 Close Procurements
Tools & TechniquesP t dit• Procurement audits
• Procurement negotiations• Records management system
Outputs• Closed procurements• Organizational process
assets updates
69
PMI Code of Ethics and Professional Conduct
“As practitioners of project management, we are committed to doing what is right and honorable ”committed to doing what is right and honorable.”
• Aspirational and Mandatory Conduct
• Values
– Responsibility
R t– Respect
– Fairness
– Honesty
70
36
Practice Exam Questions
1 A KEY activity in closing out a project is to1. A KEY activity in closing out a project is to:
A. Disseminate status reports and risk assessmentsB. Disseminate information to formalize project completionC. Monitor the specific project results to determine if they
comply with relevant quality standardsD. Transfer all the project records to the project owners
71
Preparing for the Exam
72
37
Reasons people fail the exam
They do not read all the questions correctly
h d d ll h h i i hThey do not read all the choices in each question
They are too nervous
They have not studied enough or use source books other than the PMBOK®
They believe they can rely purely on experience
They have not taken a PMP® pre course
73
Personalized Study Guide
Take the Practice/Diagnostic test; identify strong/weak areas
Take a PMP Exam Prep Class, find out what you do/don’t know
Read the PMBOK® Guide and Glossary carefully
Review the PMBOK® data flow diagrams; process interactions
Read the PMI Code of Ethics & Professional Conduct
Do plenty of practice questions, look up unknown concepts
Use the internet; “PMP + any topic”; look for 5th Ed. updates
P i “ l i i ” h PMBOK Practice “explaining” the PMBOK processes
Practice “filling in” the PMI PM Process table
Get in a study group
74
38
Any Questions?
If you have questions later:
doescher@bmcdoescher@bmc‐‐online.comonline.com
Bill Doescher, P.M.P®
Practice Test / DiagnosticPractice Test / Diagnostic30 Questions, 36 minutes
75