PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Input, Output, Tool (Shortened Name) Input To Tool Of Output From
Acquisition 9.2 Acquire Project Team;
Activity attributes 6.2 Sequence Activities; 6.3 Estimate
Activity Resources; 6.4 Estimate Activity
Durations; 6.5 Develop Schedule;
6.1 Define Activities;
Activity cost estimates 7.2 Determine Budget; 11.2 Identify Risks;
12.1 Plan Procurements;
7.1 Estimate Costs;
Activity duration estimates 6.5 Develop Schedule; 11.2 Identify Risks; 6.4 Estimate Activity Durations;
Activity list 6.2 Sequence Activities; 6.3 Estimate
Activity Resources; 6.4 Estimate Activity
Durations; 6.5 Develop Schedule;
6.1 Define Activities;
Activity resource requirements 6.4 Estimate Activity Durations; 6.5
Develop Schedule; 9.1 Develop Human
Resource Plan; 12.1 Plan Procurements;
6.3 Estimate Activity Resources;
Advertising 12.2 Conduct Procurements;
Alternatives analysis 6.3 Estimate Activity Resources;
Alternatives identification 5.2 Define Scope;
Analogous estimating 6.4 Estimate Activity Durations; 7.1
Estimate Costs;Approved change requests 4.3 Direct and Manage Project Execution;
8.3 Perform Quality Control; 12.3
Administer Procurements;
Approved change requests review 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;Assumptions analysis 11.2 Identify Risks;
Basis of estimates 7.2 Determine Budget; 7.1 Estimate Costs;
Benchmarking 8.1 Plan Quality; 8.2 Perform Quality
Assurance;Bidder conferences 12.2 Conduct Procurements;
Bottom-up estimating 6.3 Estimate Activity Resources; 7.1
Estimate Costs;Budget forecasts 10.5 Report Performance; 7.3 Control Costs;
Business case 4.1 Develop Project Charter;
Cause and effect diagrams 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;Change control meetings 4.5 Perform Integrated Change Control;
Page: 1
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Change log 10.4 Manage Stakeholder Expectations; 4.5 Perform Integrated Change Control
(not in PMBOK)Change request status updates 4.5 Perform Integrated Change Control;
Change requests (see also Approved Change
Requests and Approved Change Requests Review)
4.5 Perform Integrated Change Control; 4.3 Direct and Manage Project Execution;
4.4 Monitor and Control Project Work; 5.4
Verify Scope; 5.5 Control Scope; 6.6
Control Schedule; 7.3 Control Costs; 8.2
Perform Quality Assurance; 8.3 Perform
Quality Control; 9.4 Manage Project Team;
10.4 Manage Stakeholder Expectations;
10.5 Report Performance; 11.6 Monitor &
Control Risks; 12.1 Plan Procurements;
12.2 Conduct Procurements; 12.3
Administer Procurements;
Checklist analysis 11.2 Identify Risks;
Claims administration 12.3 Administer Procurements;
Closed procurements 12.4 Close Procurements;
Co-location 9.3 Develop Project Team;
Communication methods 10.2 Plan Communications; 10.3 Distribute
Information; 10.4 Manage Stakeholder
Expectations; 10.5 Report Performance;
Communication models 10.2 Plan Communications;
Communication requirements analysis 10.2 Plan Communications;
Communication technology 10.2 Plan Communications;
Communications management plan 11.1 Plan Risk Management; 10.2 Plan Communications;
Conflict management 9.4 Manage Project Team;
Contingent response strategies 11.5 Plan Risk Responses;
Contract change control system 12.3 Administer Procurements;
Contract types 12.1 Plan Procurements;
Contracts 4.1 Develop Project Charter; 7.2
Determine Budget; 12.3 Administer
Procurements;Control charts 8.1 Plan Quality; 8.2 Perform Quality
Assurance; 8.3 Perform Quality Control;
Cost aggregation 7.2 Determine Budget;
Page: 2
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Cost management plan 11.1 Plan Risk Management; 11.2 Identify
Risks; 11.4 Perform Quantitative Risk
Analysis;
4.2 Develop Project Management Plan
(not in PMBOK)
Cost of quality 7.1 Estimate Costs; 8.1 Plan Quality; 8.2
Perform Quality Assurance;
Cost performance baseline 8.1 Plan Quality; 12.1 Plan Procurements; 7.2 Determine Budget;
Cost-benefit analysis 8.1 Plan Quality; 8.2 Perform Quality
Assurance;Critical chain method 6.5 Develop Schedule;
Critical path method 6.5 Develop Schedule;
Data gathering and representation techniques 11.4 Perform Quantitative Risk Analysis;
Decomposition 5.3 Create WBS; 6.1 Define Activities;
Deliverables 4.6 Close Project or Phase; 5.4 Verify
Scope; 8.3 Perform Quality Control;
4.3 Direct and Manage Project Execution;
5.4 Verify Scope; 8.3 Perform Quality
Control;Dependency determination 6.2 Sequence Activities;
Design of experiments 8.1 Plan Quality; 8.2 Perform Quality
Assurance;Diagramming techniques 11.2 Identify Risks;
Documentation reviews 11.2 Identify Risks;
Earned value management 7.3 Control Costs;
Enterprise environmental factors 4.1 Develop Project Charter; 4.2 Develop
Project Management Plan; 4.3 Direct and
Manage Project Execution; 4.4 Monitor
and Control Project Work; 4.5 Perform
Integrated Change Control; 6.1 Define
Activities; 6.3 Estimate Activity Resources;
6.4 Estimate Activity Durations; 6.5
Develop Schedule; 7.1 Estimate Costs; 8.1
Plan Quality; 9.1 Develop Human Resource
Plan; 9.2 Acquire Project Team; 10.1
Identify Stakeholders; 10.2 Plan
Communications; 11.1 Plan Risk
Management; 11.2 Identify Risks; 12.1
Plan Procurements;
9.3 Develop Project Team; 9.4 Manage
Project Team;
Page: 3
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Expert judgment 4.1 Develop Project Charter; 4.2 Develop
Project Management Plan; 4.3 Direct and
Manage Project Execution; 4.4 Monitor
and Control Project Work; 4.5 Perform
Integrated Change Control; 4.6 Close
Project or Phase; 5.2 Define Scope; 6.1
Define Activities; 6.3 Estimate Activity
Resources; 6.4 Estimate Activity Durations;
7.1 Estimate Costs; 7.2 Determine Budget;
10.1 Identify Stakeholders; 11.2 Identify
Risks; 11.3 Perform Qualitative Risk
Analysis; 11.4 Perform Quantitative Risk
Analysis; 11.5 Plan Risk Responses; 12.1
Plan Procurements; 12.2 Conduct
Procurements;
Facilitated workshops 5.1 Collect Requirements; 5.2 Define
Scope;Final product, service, or result transition 4.6 Close Project or Phase;
Flowcharting 8.1 Plan Quality; 8.2 Perform Quality
Assurance; 8.3 Perform Quality Control;
Focus groups 5.1 Collect Requirements;
Forecasting 7.3 Control Costs;
Forecasting methods 10.5 Report Performance;
Funding limit reconciliation 7.2 Determine Budget;
Ground rules 9.3 Develop Project Team;
Group creativity techniques 5.1 Collect Requirements;
Group decision making techniques 5.1 Collect Requirements;
Histogram 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;Historical relationships 7.2 Determine Budget;
Human resource plan 7.1 Estimate Costs; 9.1 Develop Human Resource Plan;
Independent estimates 12.2 Conduct Procurements;
Information distribution tools 10.3 Distribute Information;
Information gathering techniques 11.2 Identify Risks;
Inspection 5.4 Verify Scope; 8.2 Perform Quality
Assurance; 8.3 Perform Quality Control;
Inspections and audits 12.3 Administer Procurements;
Page: 4
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Internet search 12.2 Conduct Procurements;
Interpersonal skills 9.3 Develop Project Team; 9.4 Manage
Project Team; 10.4 Manage Stakeholder
Expectations;Interviews 5.1 Collect Requirements;
Issue log 10.4 Manage Stakeholder Expectations; 9.4 Manage Project Team; 4.3 Direct and Manage Project Execution
(not in PMBOK)Leads and lags 6.2 Sequence Activities; 6.5 Develop
Schedule; 6.6 Control Schedule;
Make-or-buy analysis 12.1 Plan Procurements;
Make-or-buy decisions 12.2 Conduct Procurements; 12.1 Plan Procurements;
Management skills 10.4 Manage Stakeholder Expectations;
Milestone list 6.2 Sequence Activities; 6.1 Define Activities;
Negotiated settlements 12.4 Close Procurements;
Negotiation 9.2 Acquire Project Team;
Networking 9.1 Develop Human Resource Plan;
Observation and conversation 9.4 Manage Project Team;
Observations 5.1 Collect Requirements;
Organization charts and position descriptions 9.1 Develop Human Resource Plan;
Page: 5
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Organizational process assets 4.1 Develop Project Charter; 4.2 Develop
Project Management Plan; 4.3 Direct and
Manage Project Execution; 4.4 Monitor
and Control Project Work; 4.5 Perform
Integrated Change Control; 4.6 Close
Project or Phase; 5.2 Define Scope; 5.3
Create WBS; 5.5 Control Scope; 6.1 Define
Activities; 6.2 Sequence Activities; 6.3
Estimate Activity Resources; 6.4 Estimate
Activity Durations; 6.5 Develop Schedule;
6.6 Control Schedule; 7.1 Estimate Costs;
7.2 Determine Budget; 7.3 Control Costs;
8.1 Plan Quality; 8.3 Perform Quality
Control; 9.1 Develop Human Resource
Plan; 9.2 Acquire Project Team; 9.4
Manage Project Team; 10.1 Identify
Stakeholders; 10.2 Plan Communications;
10.3 Distribute Information; 10.4 Manage
Stakeholder Expectations; 10.5 Report
Performance; 11.1 Plan Risk Management;
11.2 Identify Risks; 11.3 Perform
Qualitative Risk Analysis; 11.4 Perform
Quantitative Risk Analysis; 12.1 Plan
Procurements; 12.2 Conduct
Procurements;
4.6 Close Project or Phase; 5.5 Control
Scope; 6.6 Control Schedule; 7.3 Control
Costs; 8.2 Perform Quality Assurance; 8.3
Perform Quality Control; 9.4 Manage
Project Team; 10.3 Distribute Information;
10.4 Manage Stakeholder Expectations;
10.5 Report Performance; 11.6 Monitor &
Control Risks; 12.3 Administer
Procurements; 12.4 Close Procurements;
Organizational theory 9.1 Develop Human Resource Plan;
Outputs of planning processes 4.2 Develop Project Management Plan;
Parametric estimating 6.4 Estimate Activity Durations; 7.1
Estimate Costs;Pareto chart 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;Payment systems 12.3 Administer Procurements;
Performance reporting 12.3 Administer Procurements;
Page: 6
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Performance reports 4.4 Monitor and Control Project Work; 9.4
Manage Project Team; 10.3 Distribute
Information; 11.6 Monitor & Control Risks;
12.3 Administer Procurements;
10.5 Report Performance;
Performance reviews 6.6 Control Schedule; 7.3 Control Costs;
Plan Quality and Perform Quality Control tools and
techniques
8.2 Perform Quality Assurance;
Planning meetings and analysis 11.1 Plan Risk Management;
Pre-assignment 9.2 Acquire Project Team;
Precedence diagramming method (PDM) 6.2 Sequence Activities;
Probability and impact matrix 11.3 Perform Qualitative Risk Analysis;
Process analysis 8.2 Perform Quality Assurance;
Process improvement plan 8.1 Plan Quality;
Procurement audits 12.4 Close Procurements;
Procurement contract award 12.2 Conduct Procurements;
Procurement documentation 12.4 Close Procurements; 12.3 Administer Procurements;
Procurement documents 10.1 Identify Stakeholders; 12.2 Conduct
Procurements; 12.3 Administer
Procurements;
12.1 Plan Procurements;
Procurement management plan 12.1 Plan Procurements;
Procurement negotiations 12.2 Conduct Procurements;
Procurement performance reviews 12.3 Administer Procurements;
Procurement statements of work 12.1 Plan Procurements;
Product analysis 5.2 Define Scope;
Project charter 4.2 Develop Project Management Plan; 5.1
Collect Requirements; 5.2 Define Scope;
10.1 Identify Stakeholders;
4.1 Develop Project Charter;
Page: 7
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Project documents 11.2 Identify Risks; 12.2 Conduct
Procurements;
4.3 Direct and Manage Project Execution;
4.4 Monitor and Control Project Work; 4.5
Perform Integrated Change Control; 5.2
Define Scope; 5.3 Create WBS; 5.4 Verify
Scope; 5.5 Control Scope; 6.2 Sequence
Activities; 6.3 Estimate Activity Resources;
6.4 Estimate Activity Durations; 6.5
Develop Schedule; 6.6 Control Schedule;
7.1 Estimate Costs; 7.2 Determine Budget;
7.3 Control Costs; 8.1 Plan Quality; 8.2
Perform Quality Assurance; 8.3 Perform
Quality Control; 10.2 Plan
Communications; 10.4 Manage
Stakeholder Expectations; 11.5 Plan Risk
Responses; 11.6 Monitor & Control Risks;
12.2 Conduct Procurements;
Project funding requirements 7.3 Control Costs; 7.2 Determine Budget;
Project management estimating software 7.1 Estimate Costs;
Project management information system 4.3 Direct and Manage Project Execution;
Project management plan 4.3 Direct and Manage Project Execution;
4.4 Monitor and Control Project Work; 4.5
Perform Integrated Change Control; 4.6
Close Project or Phase; 5.4 Verify Scope;
5.5 Control Scope; 6.6 Control Schedule;
7.3 Control Costs; 8.2 Perform Quality
Assurance; 8.3 Perform Quality Control;
9.2 Acquire Project Team; 9.3 Develop
Project Team; 9.4 Manage Project Team;
10.3 Distribute Information; 10.4 Manage
Stakeholder Expectations; 10.5 Report
Performance; 11.6 Monitor & Control
Risks; 12.2 Conduct Procurements; 12.3
Administer Procurements; 12.4 Close
Procurements;
4.2 Develop Project Management Plan; 4.3
Direct and Manage Project Execution; 4.4
Monitor and Control Project Work; 4.5
Perform Integrated Change Control; 5.5
Control Scope; 6.6 Control Schedule; 7.3
Control Costs; 8.2 Perform Quality
Assurance; 8.3 Perform Quality Control;
9.2 Acquire Project Team; 9.4 Manage
Project Team; 10.4 Manage Stakeholder
Expectations; 11.5 Plan Risk Responses;
11.6 Monitor & Control Risks; 12.2
Conduct Procurements; 12.3 Administer
Procurements;
Page: 8
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Project management software 6.3 Estimate Activity Resources; 6.6
Control Schedule; 7.3 Control Costs;Project performance appraisals 9.4 Manage Project Team;
Project schedule 6.6 Control Schedule; 7.1 Estimate Costs;
7.2 Determine Budget; 12.1 Plan
Procurements;
6.5 Develop Schedule;
Project schedule network diagrams 6.5 Develop Schedule; 6.2 Sequence Activities;
Project scope statement 5.3 Create WBS; 6.2 Sequence Activities;
6.4 Estimate Activity Durations; 6.5
Develop Schedule; 11.1 Plan Risk
Management; 11.3 Perform Qualitative
Risk Analysis;
5.2 Define Scope;
Project staff assignments 9.3 Develop Project Team; 9.4 Manage
Project Team;
9.2 Acquire Project Team;
Project statement of work 4.1 Develop Project Charter;
Proposal evaluation techniques 12.2 Conduct Procurements;
Proprietary quality management methodologies 8.1 Plan Quality; 8.2 Perform Quality
Assurance;Prototypes 5.1 Collect Requirements;
Published estimating data 6.3 Estimate Activity Resources;
Qualified seller list 12.2 Conduct Procurements;
Quality audits 8.2 Perform Quality Assurance;
Quality checklists 8.3 Perform Quality Control; 8.1 Plan Quality;
Quality control measurements 8.2 Perform Quality Assurance; 8.3 Perform Quality Control;
Quality management plan 11.2 Identify Risks; 8.1 Plan Quality;
Quality metrics 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;
8.1 Plan Quality;
Quality planning tools 8.1 Plan Quality; 8.2 Perform Quality
Assurance;Quantitative risk analysis and modeling techniques 11.4 Perform Quantitative Risk Analysis;
Questionnaires and surveys 5.1 Collect Requirements;
Recognition and rewards 9.3 Develop Project Team;
Records management system 12.3 Administer Procurements; 12.4 Close
Procurements;Reporting systems 10.5 Report Performance;
Requirements documentation 5.2 Define Scope; 5.3 Create WBS; 5.4
Verify Scope; 5.5 Control Scope; 12.1 Plan
Procurements;
5.1 Collect Requirements;
Requirements management plan 5.1 Collect Requirements;
Requirements traceability matrix 5.4 Verify Scope; 5.5 Control Scope; 5.1 Collect Requirements;
Page: 9
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Reserve analysis 6.4 Estimate Activity Durations; 7.1
Estimate Costs; 7.2 Determine Budget;
11.6 Monitor & Control Risks;
Resource breakdown structure 6.3 Estimate Activity Resources;
Resource calendars 6.3 Estimate Activity Resources; 6.4
Estimate Activity Durations; 6.5 Develop
Schedule; 7.2 Determine Budget; 9.3
Develop Project Team;
9.2 Acquire Project Team; 12.2 Conduct
Procurements;
Resource leveling 6.5 Develop Schedule; 6.6 Control
Schedule;Risk audits 11.6 Monitor & Control Risks;
Risk categorization 11.3 Perform Qualitative Risk Analysis;
Risk data quality assessment 11.3 Perform Qualitative Risk Analysis;
Risk management plan 11.2 Identify Risks; 11.3 Perform
Qualitative Risk Analysis; 11.4 Perform
Quantitative Risk Analysis; 11.5 Plan Risk
Responses;
11.1 Plan Risk Management;
Risk probability and impact assessment 11.3 Perform Qualitative Risk Analysis;
Risk reassessment 11.6 Monitor & Control Risks;
Risk register 7.1 Estimate Costs; 8.1 Plan Quality; 11.3
Perform Qualitative Risk Analysis; 11.4
Perform Quantitative Risk Analysis; 11.5
Plan Risk Responses; 11.6 Monitor &
Control Risks; 12.1 Plan Procurements;
11.2 Identify Risks; 11.3 Perform
Qualitative Risk Analysis; 11.4 Perform
Quantitative Risk Analysis; 11.5 Plan Risk
Responses; 11.6 Monitor & Control Risks;
Risk urgency assessment 11.3 Perform Qualitative Risk Analysis;
Risk-related contract decisions 12.1 Plan Procurements; 11.5 Plan Risk Responses;
Rolling wave planning 6.1 Define Activities;
Run chart 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;Scatter diagram 8.2 Perform Quality Assurance; 8.3
Perform Quality Control;Schedule baseline 8.1 Plan Quality; 6.5 Develop Schedule;
Schedule compression 6.5 Develop Schedule; 6.6 Control
Schedule;Schedule data 6.5 Develop Schedule;
Page: 10
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Schedule management plan 11.1 Plan Risk Management; 11.2 Identify
Risks; 11.4 Perform Quantitative Risk
Analysis;
4.2 Develop Project Management Plan
(not explicitly identifed as an output of this
process in the PMBOK)
Schedule network analysis 6.5 Develop Schedule;
Schedule network templates 6.2 Sequence Activities;
Scheduling tool 6.5 Develop Schedule; 6.6 Control
Schedule;Scope baseline 6.1 Define Activities; 7.1 Estimate Costs;
7.2 Determine Budget; 8.1 Plan Quality;
11.2 Identify Risks; 12.1 Plan
Procurements;
5.3 Create WBS;
Selected sellers 12.2 Conduct Procurements;
Seller proposals 12.2 Conduct Procurements;
Source selection criteria 12.2 Conduct Procurements; 12.1 Plan Procurements;
Stakeholder analysis 10.1 Identify Stakeholders;
Stakeholder management strategy 10.2 Plan Communications; 10.4 Manage
Stakeholder Expectations;
10.1 Identify Stakeholders;
Stakeholder register 5.1 Collect Requirements; 8.1 Plan Quality;
10.2 Plan Communications; 10.4 Manage
Stakeholder Expectations; 11.2 Identify
Risks;
10.1 Identify Stakeholders;
Statistical sampling 8.1 Plan Quality; 8.2 Perform Quality
Assurance; 8.3 Perform Quality Control;
Status meetings 11.6 Monitor & Control Risks;
Strategies for negative risks or threats 11.5 Plan Risk Responses;
Strategies for positive risks or opportunities 11.5 Plan Risk Responses;
SWOT analysis 11.2 Identify Risks;
Team performance assessments 9.4 Manage Project Team; 9.3 Develop Project Team;
Team-building activities 9.3 Develop Project Team;
Teaming agreements 12.1 Plan Procurements; 12.2 Conduct
Procurements;Technical performance measurement 11.6 Monitor & Control Risks;
Templates 6.1 Define Activities;
Three-point estimates 6.4 Estimate Activity Durations; 7.1
Estimate Costs;To-complete performance index (TCPI) 7.3 Control Costs;
Training 9.3 Develop Project Team;
Variance analysis 5.5 Control Scope; 6.6 Control Schedule;
7.3 Control Costs; 10.5 Report
Performance;
Page: 11
From http://www.PMRoadTrip.com
PMBOK, 4th Edition
Index of Inputs, Tools Techniques, and Outputs
Variance and trend analysis 11.6 Monitor & Control Risks;
Vendor bid analysis 7.1 Estimate Costs;
Virtual teams 9.2 Acquire Project Team;
WBS 5.3 Create WBS;
WBS dictionary 5.3 Create WBS;
What-if scenario analysis 6.5 Develop Schedule; 6.6 Control
Schedule;Work performance information 4.5 Perform Integrated Change Control;
5.5 Control Scope; 6.6 Control Schedule;
7.3 Control Costs; 8.2 Perform Quality
Assurance; 10.5 Report Performance; 11.6
Monitor & Control Risks; 12.3 Administer
Procurements;
4.3 Direct and Manage Project Execution;
Work performance measurements 8.3 Perform Quality Control; 10.5 Report
Performance;
5.5 Control Scope; 6.6 Control Schedule;
7.3 Control Costs;