29
Ground Improvement Sustainable, economic solutions

PolyCom ground improvement presentation

Embed Size (px)

Citation preview

Page 1: PolyCom ground improvement presentation

Ground Improvement

Sustainable, economic solutions

Page 2: PolyCom ground improvement presentation

A sustainable and economic solution

“PolyCom changes the quality and workability of the soil to increase it’s load bearing capacity and resistance to

displacement and weathering”

Page 3: PolyCom ground improvement presentation

Case Study examples

The following are case studies of sub-grade and pavement stabilisation in variable or hard to manage soils using PolyCom Stabilising Aid

Significant improvements to project outcomes delivered major benefits to the contractor and/or project owner

Contact SEALS for more details

Page 4: PolyCom ground improvement presentation

Utilising available ground - Black soil Stabilised for temporary or low volume roads

ChinchillaSEALS &

Ostwald Construction

Virgin ground -1. Scarify to 150mm on a 9 metre profile 2. This gains sufficient material for 7 metre road and establishes drainage area3. Standard wet mix installing PolyCom4. Mix and compact with pad foot until roller walks out5. Trim and wheel roll

Mow grass and scarify Wet mix profile and compact 5 days later - haulage completed

2 weeks later and constant traffic

1 2 3

4Major project benefits:

✓Economic stabilisation and faster construction

✓Durable and water resistant temporary or low volume road

Page 5: PolyCom ground improvement presentation

Utilising available ground - Black soilStabilised + 75mm gravel wear course

Mt Tyson SEALS & Toowoomba RC

Virgin ground -1. Scarify to 150mm on a 9 metre profile 2. This gains sufficient material for 7 metre road and establishes drainage area3. Wet mix with PolyCom and compact using pad foot rollers 4. Leave pad foot finish to key gravel 5. Place, profile and roll reduced thickness gravel layer

Black soil sub-grade Grader crew stabilise with PolyCom Profiled & Compacted

Reduced gravel thickness 75 mm wear course placed over improved sub-grade

Standard solution for this constructionmeant a gravel cart of more than40 klm and placement of 300mm gravel sheet

Major project benefits:

✓Cost saving of 40% on standard construction option

✓Increased sub-grade strength and water resistance means less gravel (saving resources)

“Stabilisation eliminates the need to ‘remove and replace’ variable, hard to manage soils”

Page 6: PolyCom ground improvement presentation

Utilising available ground - Sandy loamAdding workability to difficult ground

Sandy loamdifficult to manage - normally cut to spoil

Strengthened sandy loam sub-grade is now useful allowing thinner pavement designs

Alpha Coal Project 28 klm Access RoadSEALS & Shadforths Civil

1. Scarify to 150mm, wet mix with PolyCom and compact sub-grade to 8 metre road profile2. Proof roll and place gravel - 150mm

Alternate solution was to remove and replace sub-grade to

300mm

Major project benefits:

✓Improved sub-grade strength & stiffness removed the need for alternate solution ✓Faster, more economical solution

Road train haul road prepped for 150mm gravel sheet

“Improving sub-grade structural strength and stiffness means less chance of road displacement or deformation”

Page 7: PolyCom ground improvement presentation

Utilising available material - Sandy clay loamSub-grade stabilisation - road rebuild

Problem sub-grade is wet and unstable

PolyCom + compaction

Stabilised, trimmed and proof rolled - same day

= Desired result

Boundary St - ToowoombaRoad rebuild

SEALS & Toowoomba RC

1. Scarify area to increase exposed surface area2. Dry spread PolyCom over wet ground3. Mix area to 200mm depth with stabilising machine4. Compact and trim

Major project benefits:

✓More economical and much faster than remove and replace option

✓Improved sub-grade structural strength and stiffness means less chance of road deformation

Reconstruction required remove and replace of in-situ sub-grade material or stabilisation. PolyCom stabilising aid was selected after considering cost, environment and speed of works.

Page 8: PolyCom ground improvement presentation

Utilising available material - Dispersive clayHigh sodic level soil remediated

Highly dispersive soilRemediated by stabilisation with PolyCom

Strengthened,water resistant

Condamine Gas PlantSEALS, Ostwald Bros & Watpac

Construction

Remediate dispersive soil

1. 210,000m² - scarifyarea to 150mm2. Wet mix with PolyCom, compact and trim

Major project benefits:

✓Economic remediation of dispersive soil eliminated the need for capping layer

✓Increasing sub-grade strength allowed engineers to reduce design pavement thickness

“Stabilised sub-grades become part of the overall pavement structure and as such improve the integrity of all layers placed above”

R.O. & Ponds

Gas Plant area

Page 9: PolyCom ground improvement presentation

Utilising available material - In-situ ground Upgrade with PolyCom and competent soil blending

300 Ton all up - 7 m wide bitumenShoulder up-grade using available roadside soil

Blend black soil, sand and gravelStabilise with PolyCom

Strengthened, water proof shoulderSix months and two metres of rain

after the works

Boonal Haul RoadUpgrade

SEALS & Alexanderson Civil

Major project benefits:

✓Safer road for haulers and light vehicles

✓No imported gravel - substantial cost savings

✓27.2 Klm of shoulder stabilisation work was completed with a grader crew only making this work a very economical solution

Page 10: PolyCom ground improvement presentation

Utilising available material - Permian claySub-grade capping

Newcastle Freeway Construction SEALS & Thiess Construction

Final inspectionRip and re-compact to line and level with PolyCom

Major project benefits:✓Stabilising/capping in cut to fill operation reduced traffic and weather damage

✓Significant savings are realised with less re-work

Sub-grade material is reactive Permian clay.Construction method for access roads, construction and plant areas was cut and fill. This meant that areas brought to level exposed vulnerable low strength reactive sub-grade to weather and traffic damage during the construction phase leading to expensive re-work in damaged areas.

Page 11: PolyCom ground improvement presentation

Bohemia Downs Rd 35 klm x 6m

PolyCom wear course up-grade SEALS & Emerald Shire

1. PolyCom stabilisation was completed during a standard rip and re-compact 2. Road was reshaped and drainage was also repaired during this service

Pre work: Natural ground softens during rain event Feb 2010

Stabilisation + 7 months: No ill effects after 2 metres of rain 2010 - 2011

Major project benefits:

✓Improved user safety

✓Increased density delivers decreased permeability

Utilising available material - Natural groundAdding water resistance and strength

Page 12: PolyCom ground improvement presentation

Utilising available material - Natural ground - silt loamIn-situ stabilisation

Auburn Rd: 2 Klm x 6mSEALS & Chinchilla Shire

Low strength natural ground road meant constant and continual maintenance to keep this road at a usable standard

PolyCom stabilisation has strengthened this ground and reduced the frequency of ongoing service to the area

Major project benefits:

✓Improved natural ground strength & weather resistance

✓Significant ongoing maintenance savings - remote area works

Low strength natural ground

Grader mix, shape and compact

Consistent, strengthened and weather resistant

Page 13: PolyCom ground improvement presentation

Utilising available material - Loamy sand Stabilised and durable

Stanthorpe 5klm x 5mSEALS & Stanthorpe Shire

1. Scarify and dry spread PolyCom2. Add water to approx 60% OMC3. Compact and trim

Major project benefits:

✓100mm stabilisation with grader crew

✓Higher densities with less water

12 months after stabilisation80% sand + 5% clay

Tight surface matrix

Page 14: PolyCom ground improvement presentation

Utilising available material - Tertiary clayIn-situ ground can be useful if managed correctly

Mine road wear course improvement utilising in-situ mine spoil - Tertiary Clay

Hard wearing - water resistant - easily managedCat 789 and 793 are using this road

Major project benefits:

✓All weather surface

✓Less future road maintenance and water for dust control

✓Economic stabilisation by on site grader crew

Haul Road ‘A’45,000 m²

SEALS & Jellinbah Mine

PolyCom stabilisation negates the need for gravel

sheeting in some cases

Page 15: PolyCom ground improvement presentation

Utilising available material - Mud stoneCompetent blending and stabilising = results

1. Mud stone haul road2. Mud stone + Basalt + PolyCom

Competent blending3. All weather road

80% less water

4. Seven months on and no maintenance

High volume coal circuit

Haul Road StabilisationSouthern & Northern Haul

Roads & Access Roads180,000 m ²

SEALS & Minerva Mine

Major project benefits:

✓Reduced haul road maintenance

✓Less downtime after rain ✓Improved tyre wear

Page 16: PolyCom ground improvement presentation

Stabilising gravelsRe-sheet improvement

Re-sheet completed in February 2011 with

PolyCom stabilised gravel

PolyCom stabilised re-sheet March 2011 January 2012

Biloela Rd: Re-sheet - 15 Klm x 6m: SEALS and CHRC - Duaringa office

Standard 150mm re-sheet with the gravel being stabilised at site during placement

Ten months after the works and there has been several substantial rain events and seasonal heavy traffic (grain and cattle trucks)

Major project benefits:

✓Increased service life of road

✓Safer, smoother more weather resistant surface

Visual inspection:Minimal lose of material and no corrugations or general road deformation is evident.Minor rutting at 6 Klm - 6.5 Klm, this rutting is due to road shape at this point - area needs re shaping.Shoulder area is eroded at the ten Klm point and needs material adding.

Page 17: PolyCom ground improvement presentation

Stabilising gravelsRehabilitate in-situ gravel

End of life road rehabilitated2 Klm x 6m in-situ stabilised

to 100mm in Aug 2006

Road condition- July 2009: good shape has been retained

little material losstight surface matrix

Beerburum Rd: Stabilisation - 2 Klm x 6m: SEALS and Forestry Queensland

Standard 100mm stabilisation of existing gravel using grader crew.Road carries local traffic and heavy seasonal logging traffic.Three years after the works and only three minor maintenance trimsthis road is in excellent condition as evidenced

Major project benefits:

✓Rehabilitation has delivered substantial cost savings - alternate was re-sheet

✓Durable surface with reduced maintenance

Page 18: PolyCom ground improvement presentation

Stabilising gravelsImproving crushed rock hard stand

BMA - Crinum Mine3 hectare lay down areaSEALS & Garwoods Earth Moving

Class three road base wear course stabilised with PolyCom to provide weather immunity, improve strength & flexibility

Stabilised to 100mm with PolyComusing standard grader crew

Very tight surface

Major project benefits:

✓Cost effective improvement

✓Durable surface with less dust

✓Reduced ongoing maintenance

Page 19: PolyCom ground improvement presentation

Stabilising gravelsRehabilitate in-situ pavement

End of life road rehabilitated with PolyCom

1 Klm x 6m in-situ pavement stabilised with PolyCom to 200mm in May 2007

Visual inspection Feb 2011Seal in in good condition with no signs

of embedment or bleedingNo other signs of wear are evident

Cooyar Rd: Pavement rehabilitation - 1 Klm x 6m x .2m:

SEALS, Main Roads Qld & Kingaroy Shire

Works were completed using a stabilisation machine and standard grader crew. Old pavement was recycled (including bitumen) and PolyCom was used to stabilise.

Major project benefits:

✓Rehabilitation has delivered substantial cost savings - alternate solution was rebuild

✓Considerable savings in time for pavement stabilisation and preparation for seal plus construction water

Page 20: PolyCom ground improvement presentation

Stabilising gravelsRehabilitate in-situ pavement

‘End of life’ road due for rebuildalternate option:

In-situ pavement stabilisation using PolyCom Works completed

Mar 2007

May 2011No visual signs of wear

this road is in top condition

Proston Rd: Pavement rehabilitation - 1.5 Klm x 6m x .15m:

SEALS, Main Roads Qld & Wondai Shire

Stabilisation works were completed using a standard grader crew. Old bitumen was removed, pavement was recycled to 150mm depthand prepped for a seal.

Major project benefits:

✓The use of PolyCom and a grader crew only for the stabilisation works realises significant cost savings for this project

✓Stabilising thin layers (as little as 100mm) is possible without fatigue or stress problems normally encountered with conventional stabilisation of thin layers

Page 21: PolyCom ground improvement presentation

Simple insuranceAdding weather immunity to soils and gravel

Water crossed this road for a six hour period Road shoulders and table drains have washed away

PolyCom stabilised pavement is still in place

Gingi grain storage access - Emerald, Qld - SEALS & CHRC

Page 22: PolyCom ground improvement presentation

Installation methodsStabilising machine

Cunningham Hwy, Warwick, Qld

SEALS, Main Roads Qld & CMC Construction

Installation with stabilising machine No bulk bags or spreader trucks

Strengthened flexible

&water resistant

Stabiliser Installation:

✓No cure time constraints

✓No block or shrinkage cracking

Page 23: PolyCom ground improvement presentation

Installation methodsGrader crew

Standard grader crew wet mixGrader, water cart & rollers

Standard compaction techniquesLoaded scraper works well

Jellinbah CoalHaul road ‘A’ - 45,000 m²

SEALS & Jellinbah works crew

Grader Installation:

✓Conventional, standard work method

✓No extra plant or man power

Page 24: PolyCom ground improvement presentation

Installation methodsDry spread

1. Grading and spreading 2. Council maintenance utility

3. SEALS Group support utility 4. Contractor power rake

1. Australian Rail And track - Site access road

2. Bendigo Council, VictoriaWear course upgrade

3. Main Roads, QueenslandHighway truck parking bays

4. Calder Highway, VictoriaHighway patching crew

Page 25: PolyCom ground improvement presentation

Engineering benefits

Reliable, cost effective treatment for sub-grades, gravels and crushed rock

Adding workability to variable ground allows more certainty and consistency to design and construction

Long term improved performance of roads

Page 26: PolyCom ground improvement presentation

Works crew benefits

Consistent work methods

Added workability means easier use of variable or hard to manage soils and gravels

Minimum machinery and plant requirement

Page 27: PolyCom ground improvement presentation

Cost benefits

Guaranteed cost savings through thinner pavement requirements, less cartage and less onsite plant

Faster construction and less labour to achieve the same results

Increased pavement life with reduced ongoing maintenance

Contractor quoting advantage

Page 28: PolyCom ground improvement presentation

Environmental benefits

Saving of resources (gravel and water)

Stabilised roads produce less dust and sediment

Less CO2 production during construction and maintenance

Zero environmental or OH&S concerns

Page 29: PolyCom ground improvement presentation

SEALS Group - Specialist sub-contractor

SEALS Group 143-157 Harrison RdCedar Vale, Qld, 4285

AustraliaP. 61 7 5543 1053 - Ops Manager 0414 185 493

[email protected] www.sealsgroup.com

“It’s all about improving and preserving the dry strength of the available material”