2011 Schedule Carry out trail construction, fencing, and planting. 2012 – Park Opening Open park in late spring. Winter 2009-10 PORT UNION WATERFRONT PARK Community Newsletter Port Union Phase 2 Construction Progress Progress to October 2009 Construction progress to date: Headlands 5, 6, 7, and 8 complete Rubble filling complete to Headland 9 e total amount of material delivered to the site so far: 7,500 truck loads of rubble and fill material 3,500 tonnes of cobble stone 10,000 tonnes of rip rap stone 17,000 tonnes of armourstone 2010 Schedule Continue rubble filling Construct Adams Creek wetland and channel Complete cobble beach filling Start site preparation for final landscaping Port Union Phase 2 of construction s Construction Schedule 2009 2010 2011 Headland & Beach Construction Headland Armouring Cobble Beach Filling Adams Creek Wetland Trails and Landscaping

PORT UNION WATERFRONT PARKtrca.on.ca/dotAsset/69566.pdf · 2009-12-22 · Waterfront Trail. With the help of 173 volunteers, we achieved this goal – successfully planting 600 trees

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PORT UNION WATERFRONT PARKtrca.on.ca/dotAsset/69566.pdf · 2009-12-22 · Waterfront Trail. With the help of 173 volunteers, we achieved this goal – successfully planting 600 trees

2011 Schedule• Carryouttrailconstruction,fencing,andplanting.

2012 – Park Opening• Openparkinlatespring.

Winter 2009-10

PORT UNION WATERFRONT PARKCommunity Newsletter

Port Union Phase 2 Construction Progress

Progress to October 2009Construction progress to date:• Headlands5,6,7,and8complete • RubblefillingcompletetoHeadland9

The total amount of material delivered to the site so far:• 7,500truckloadsofrubbleandfillmaterial• 3,500tonnesofcobblestone• 10,000tonnesofriprapstone• 17,000tonnesofarmourstone

2010 Schedule• Continuerubblefilling• ConstructAdamsCreekwetlandandchannel• Completecobblebeachfilling• Startsitepreparationforfinallandscaping

PortUnionPhase2ofconstructions

Construction Schedule 2009 2010 2011

Headland&BeachConstruction

HeadlandArmouring

CobbleBeachFilling

AdamsCreekWetland

TrailsandLandscaping

Page 2: PORT UNION WATERFRONT PARKtrca.on.ca/dotAsset/69566.pdf · 2009-12-22 · Waterfront Trail. With the help of 173 volunteers, we achieved this goal – successfully planting 600 trees

The“midway”wasexpandedthisyear:theScramblercomplementedtheFerrisWheelandtherewastwicethefunfortheyoungerkids.NewexhibitsincludedtheEastEndersCarClubwhobroughtacollectionofclassiccarstoPortUnionRoad.

PopularfeaturesincludedtheEnbridgeBBQcrewservingdelicioushotdogsandsoftdrinksatfamilypricesandtheTorontoServicesfireboatdelightingandamazingyoungandoldalike.OtherreturningfavouritesincludedHawkshadow,specialmusicalguestsanddisplaysfromlocalbusinessesandcommunityorganizations.

Thisyearwehadevenmorereasontocelebrate.CouncillorMoeserofficiallyannouncedthestartofconstructionforthenewGOTransitParkinglotontheeastsideoftheCommonalongtheDuthieSt.roadallowance.TherewasasodturningeventwithspecialguestsMayorDavidMillerandotherlocaldignitaries.

Staytunedfordetailsofthe2010PortUnionWaterfrontFestival,scheduledforJune12.

Port Union Waterfront Festival June 13, 2009 Whenacommunityhasabeautifulwaterfront,wefeeltheneedtoinviteourneighborsovertocelebrate.SuchisthecasewiththePortUnionVillageandthePortUnionWaterfrontPark.Thepathways,f lowingwaterfeature,playground,beautifullandscapingandWaterfrontTrailareannuallycelebratedatthePortUnionWaterfrontFestival.ThisyearitwasheldonSaturday,June13andhadanattendanceofapproximately6000people.

SodTurningwithspecialguestss

ViewofPortUnionWaterfrontFestival,2009s

Port Union Waterfront Community Newsletter — Winter 2009-10

Page 3: PORT UNION WATERFRONT PARKtrca.on.ca/dotAsset/69566.pdf · 2009-12-22 · Waterfront Trail. With the help of 173 volunteers, we achieved this goal – successfully planting 600 trees

Thank you for your Support!HaveyoueverplantedatreeinthePortUnionWaterfrontPark?Participatedinanaturehikeorbuiltabirdbox?Ifso,thenthankyouforbeingapartofthePortUnionStewardshipInitiative.

OverthetwoyearspanofthePortUnionStewardshipInitiative(January2008toDecember31,2009),wehavebeenveryluckytohavehadsuchanactivecommunitytoworkwith.TherehasbeenongoingsupportfromtheCentennialCommunityRecreationAssociation,theCityofTorontostaffatthePortUnionRecreationCentre,theWestRougeCommunityAssociationandmanyothercommunitygroups.

ThePortUnionStewardshipInitiativehasmeaningfullyengaged1,527volunteersinenvironmentalactivities.OneofourmajorgoalswastoplantasmanytreesaswouldfitalongthePortUnionWaterfrontTrail.Withthehelpof173volunteers,weachievedthisgoal–successfullyplanting600trees.ThevolunteerswhohelpedwiththisprojectincludedtheFirstHighlandCreekGirlGuidesandmanyotherswhoparticipatedinEarthDayin2008and2009.

Inadditiontoplantingtreeswehave:

• Plantedover200wildflowersinconstructedbedsatSirOliver MowatCollegiateInstituteandSt.Brendan’sCatholicSchool.

• Constructedandinstalled55birdboxeswithinAdam’sPark withtheFirstHighlandCreekGirlGuidesandSecond HighlandCreekBeavers.

• HostedtwoTDGreatCanadianShorelineCleanupswhere volunteerspicked-upatotalof18bagsofgarbagefromthe PortUnionWaterfrontshoreline.

• ParticipatedinthePortUnionWaterfrontFestivaleachsummer.

• ParticipatedinWinterfestatthePortUnionRecreationCentre.

Thankyouforthesupportandencouragement.Weappreciateallofyourhelp!

ThePortUnionStewardshipInitiativeisfundedbyEcoActionandtheCityofTorontowithin-kindsupportfromthelocalcommunity.

TofindoutmorecallMaryWilliamsat416-661-6600ext.5753oremailmawilliams@trca.on.ca.

PortUnionTreePlanting,Fall2009s

Port Union Waterfront Community Newsletter — Winter 2009-10

Page 4: PORT UNION WATERFRONT PARKtrca.on.ca/dotAsset/69566.pdf · 2009-12-22 · Waterfront Trail. With the help of 173 volunteers, we achieved this goal – successfully planting 600 trees

Port Union Waterfront Community Newsletter — Winter 2009-10

For information regarding the Port Union Waterfront Improvement Project, visit: www.trca.on.ca/water_protection/strategies/lakeontario. If you have specific questions regarding the project or if you would like to be added to the project mailing list, please contact:

Catherine DeAbreuWaterfront Administrative ClerkTelephone: 416-661-6600, ext. 5305Email: [email protected]

TD Great Canadian Shoreline CleanupOnSaturday,September19,2009,acleanupeventwasheldatthePortUnionWaterfrontPark.ThiseventwaspartoftheTDGreatCanadianShorelineCleanup,anational,week-longeventthatwasinitiatedbytheVancouverAquariumin1994.Sincethenthiseventhasgrowntobecomethesecondlargestcleanupintheworld.

AtthePortUnioneventwehadfifteenenthusiasticvolunteerswhocameouttocleanuptheshoreline.WeconcentratedontacklingthebeachareaontheeastsideoftheHighlandCreekbridgeandthenworkedourwaybackalongtheshorelinetowardsthelookoutpoint.Wecollectedfourbagsofgarbageandtwobagsofrecycling.Afterwards,wehadapicniclunchtogethertoenjoytheviewofthenewlycleanedbeach.ThankstothePortUnionStewardshipInitiativeforsupplyingthedeliciousfood.We’realreadylookingforwardtonextyear’seventandhopetherewillbeevenlessgarbageonthebeachforustopickup.

FormoreinformationontheTDGreatCanadianShorelineCleanup,pleasevisit:http://www.vanaqua.org/cleanup/home.php

Port Union 25th Anniversary Hike and PlantingOnthecrispSaturdaymorningofSeptember26,2009,agroupofpassionatevolunteersmetatthePortUnionWaterfrontParktodiscoverthewildlifethatlivesalongthetrail.Theinterpretivehikeexploredthebirds,butterflies,andmammalsthatliveintheareaandthenaturalhabitatfoundwithinthepark.

Afterthehike,allthirty-sevenvolunteersspentthedayplanting100nativetrees.ThisplantingwasthefinalstepintherehabilitationandnaturalizationofthePortUnionWaterfrontPark.Todate,therehavebeen600treesplantedalongthewaterfronttrailatthissite,contributingtothehabitatestablishmentinthisman-madepark.

Wehadagreatturnoutofparticipantsandasuccessfulcommunityhikeandplanting.ThankyoutotheCityofToronto,theCentennialCommunityRecreationAssociationandeveryonewhotookpartinthisfantasticday!

The Western GatewayThisprojectwillconnecttheeasternedgeofthePortUnionWaterfrontParktotheCityofPickering,creatingaseamlesswaterfronttrailbetweentheCityofTorontoandtheCityofPickering.ImprovementsontheeastshoreoftheRougeRiverwillincludenewstepsonthenorthsideoftherailwayandthereplacementoftheraisedpedestrianboardwalkonthesouthsideoftherailway.TheWesternGatewayprojectisfundedunderthePortUnionWaterfrontParkprojectinacostsharingagreementwiththeCityofPickering.

Installationoftheraisedpedestrianboardwalk-November2009sGreatCanadianShorelineCleanUp,Fall2009s