Post – Rebuild Changes
at the SFGH Campus
Beginning of Part 2 of 2
2
Campus Changes • Rebuild
• Potrero Ave. streetscape
• Campus changes after the Rebuild
• Move into new hospital
• Outpatient care centralized in existing hospital
• Retrofitting existing buildings
• New UC Research Building
San Francisco General Hospital and Trauma Center
3
Potrero Ave. Streetscape
4
New
Hospital
SFGH Campus Map
Proposed
UC
Research
Bldg Existing
Hospital
Bldg
9
Bldg.
40 Bldg
10
Bldg
20
Bldg
30
Bldg
1
Bldg
3
Bldg
80/90
Behavioral
Health
Center
Service
Bldg
Bldg
100
Parking
Garage
1”
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
14
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
15
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
16
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
17
1/4”
1/8”
1”
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
18
1/4”
1/8”
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
19
1/4”
1/8”
SFGH Campus Changes
Inpatient Services Move to
New Hospital
Retrofit Existing Hospital
Outpatient Services Move to
Existing Hospital
Retrofit Buildings 80/90
Construct New UCSF
Research Building
Building 40 Used for
Construction Offices
UCSF move from Red Brick
Buildings 1, 10/20, 30/40 to
New Research Building
Retrofit Red Brick Buildings
1, 10/20, 30/40
20
UCSF Interim Seismic Work
Proposals
12
Background Seismic Information
• City owns space, which UCSF leases or occupies in exchange for services
• UC considers SFGH an adjunct campus, subject to UC seismic policy for owned space – requires that “Poor/Very Poor” buildings be retrofitted to policy-compliant or vacated
• Seismically “Poor/Very Poor” buildings (Levels V and VI per UC Seismic Policy) occupied by UCSF labs/offices/clinics (193K ASF) in Buildings 1, 5, 9, 10, 20, 30, 40, 80/90, 100. All buildings, except Building 5, are historically significant
• UCSF will continue to occupy space in Building 3, rated “Seismically Good” (Level III)
• Consulting seismic experts recommended retrofit or vacating Very Poor buildings by 2019 and interim measures to protect life safety.
13
SFGH Campus Map and Seismic Ratings
14
Proposed UCSF Interim Seismic Work
• Temporary measures to protect the safety of workers, patients and visitors in exiting Very Poor buildings (Buildings 10 – 40 & 100) during seismic event
• Canopies over building exits (not attached to buildings)
• Landscaping or low fences at 10’ perimeter of buildings where needed
• Re-anchor some roof tile on Building 30 above exit stairway
• Clear internal exit paths and anchor interior equipment as necessary
• Timeline: As soon as City’s environmental review is completed – work may take place by end of 2013
15
16
17
Proposed UCSF Research Building at SFGH
18
Proposed UCSF Research Building
• Build New Building on B/C parking lot
– “Wet” research labs and “Dry” research and administrative offices for UCSF employees now in SFGH brick buildings (Poor/Very Poor) + off-campus leases
– Building footprint to be determined.
– Lot contains 158 parking spaces – once building footprint is determined, number of displaced spaces will be determined. We are working on a solution.
• Relocate labs and offices from Buildings 1, 9, 10, 20, 30, 40, 80/90, 100 to new B/C lot bldg.
• Replace displaced parking from B/C lot – location to be determined.
19
UCSF Research Building Site
20
21
Parking Options Under
Study
31
Next Steps: Proposed Schedule & Review Process
23
24
UC Actions
Negotiate site control with City 2013
Implement interim measures 2013
Amend LRDP & Complete EIR 2014
Approve budget, funding and design 2014
Build new B/C lot building 2016 – 2018
City Actions
Negotiate site control with UCSF 2013
Update 10-Year Capital Plan and
Institutional Master Plan 2013
SF Health Commission 2014
SF Planning Commission 2014
SF Board of Supervisors 2014
Proposed Schedule & Review Process
UCSF SFGH Community Meeting
February 11, 2013
END of Presentation