Post – Rebuild Changes

at the SFGH Campus

Beginning of Part 2 of 2

Page 2: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

2

Campus Changes • Rebuild

• Potrero Ave. streetscape

• Campus changes after the Rebuild

• Move into new hospital

• Outpatient care centralized in existing hospital

• Retrofitting existing buildings

• New UC Research Building

San Francisco General Hospital and Trauma Center

Page 3: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

3

Potrero Ave. Streetscape

Page 4: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

4

New

Hospital

SFGH Campus Map

Proposed

UC

Research

Bldg Existing

Hospital

Bldg

9

Bldg.

40 Bldg

10

Bldg

20

Bldg

30

Bldg

1

Bldg

3

Bldg

80/90

Behavioral

Health

Center

Service

Bldg

Bldg

100

Parking

Garage

Page 5: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

1”

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

14

Page 6: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

15

Page 7: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

16

Page 8: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

17

Page 9: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

1/4”

1/8”

1”

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

18

Page 10: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

1/4”

1/8”

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

19

Page 11: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

1/4”

1/8”

SFGH Campus Changes

Inpatient Services Move to

New Hospital

Retrofit Existing Hospital

Outpatient Services Move to

Existing Hospital

Retrofit Buildings 80/90

Construct New UCSF

Research Building

Building 40 Used for

Construction Offices

UCSF move from Red Brick

Buildings 1, 10/20, 30/40 to

New Research Building

Retrofit Red Brick Buildings

1, 10/20, 30/40

20

Page 12: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

UCSF Interim Seismic Work

Proposals

12

Page 13: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

Background Seismic Information

• City owns space, which UCSF leases or occupies in exchange for services

• UC considers SFGH an adjunct campus, subject to UC seismic policy for owned space – requires that “Poor/Very Poor” buildings be retrofitted to policy-compliant or vacated

• Seismically “Poor/Very Poor” buildings (Levels V and VI per UC Seismic Policy) occupied by UCSF labs/offices/clinics (193K ASF) in Buildings 1, 5, 9, 10, 20, 30, 40, 80/90, 100. All buildings, except Building 5, are historically significant

• UCSF will continue to occupy space in Building 3, rated “Seismically Good” (Level III)

• Consulting seismic experts recommended retrofit or vacating Very Poor buildings by 2019 and interim measures to protect life safety.

13

Page 14: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

SFGH Campus Map and Seismic Ratings

14

Page 15: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

Proposed UCSF Interim Seismic Work

• Temporary measures to protect the safety of workers, patients and visitors in exiting Very Poor buildings (Buildings 10 – 40 & 100) during seismic event

• Canopies over building exits (not attached to buildings)

• Landscaping or low fences at 10’ perimeter of buildings where needed

• Re-anchor some roof tile on Building 30 above exit stairway

• Clear internal exit paths and anchor interior equipment as necessary

• Timeline: As soon as City’s environmental review is completed – work may take place by end of 2013

15

Page 16: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

16

Page 17: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

17

Page 18: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

Proposed UCSF Research Building at SFGH

18

Page 19: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

Proposed UCSF Research Building

• Build New Building on B/C parking lot

– “Wet” research labs and “Dry” research and administrative offices for UCSF employees now in SFGH brick buildings (Poor/Very Poor) + off-campus leases

– Building footprint to be determined.

– Lot contains 158 parking spaces – once building footprint is determined, number of displaced spaces will be determined. We are working on a solution.

• Relocate labs and offices from Buildings 1, 9, 10, 20, 30, 40, 80/90, 100 to new B/C lot bldg.

• Replace displaced parking from B/C lot – location to be determined.

19

Page 20: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

UCSF Research Building Site

20

Page 21: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

21

Parking Options Under

Study

Page 22: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

31

Page 23: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

Next Steps: Proposed Schedule & Review Process

23

Page 24: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

24

UC Actions

Negotiate site control with City 2013

Implement interim measures 2013

Amend LRDP & Complete EIR 2014

Approve budget, funding and design 2014

Build new B/C lot building 2016 – 2018

City Actions

Negotiate site control with UCSF 2013

Update 10-Year Capital Plan and

Institutional Master Plan 2013

SF Health Commission 2014

SF Planning Commission 2014

SF Board of Supervisors 2014

Proposed Schedule & Review Process

Page 25: Post Rebuild Changes at the SFGH Campus · Negotiate site control with City 2013 Implement interim measures 2013 Amend LRDP & Complete EIR 2014 Approve budget, funding and design

UCSF SFGH Community Meeting

February 11, 2013