146
REPORT NO. FRA/ORO-79/09:1 .-._- -- -...... _-_._ .. -, -- I PBBO 13 B31 ---- I 1111111111111111111111111111111 ! - - - - -- --- ---- - -- - POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK . ,-' . •I - NOVEMBER 1979 FINAL REPORT Document is available to public through the National Technical Information Service, __ REPRODUCED BY NATIONAIL TECHNICAL J' INFORMATION SERVICE i u. S. DEPARTMENT OF COMMEIlC£ ; - SPRINGfIELD, VA. U161 - l' '.-- --Prepared for ---- U.S. DEPARTMENT OF TRANSPORTATION FEDERAL RAILROAD ADMJNISTRATION Office of Research and Development Washlnaton, D.C. 20590

POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

REPORT NO. FRA/ORO-79/09:1

~--'- .-._- - - -...... _-_._ .. -._~--~, -,--I PBBO13B31 6~ --~---- ---- -~-.,

I 1111111111111111111111111111111 !- - - - -- --- ---- - -- ----~.)

'~--

POSTMORTEM INVESTIGATION OFTHE KANSAS. TEST TRACK

.,-' .-~.

• I -•

NOVEMBER 1979FINAL REPORT

Document is available to th~ public through theNational Technical Information Service,

J~Rri.D..9t~ld.l. Vlt:9ir~j~__Z~t§J~_.REPRODUCED BY ~

NATIONAIL TECHNICAL J'~ INFORMATION SERVICE i~ u. S. DEPARTMENT OF COMMEIlC£ ;- SPRINGfIELD, VA. U161 - l''.-- --Prepared for ----

U.S. DEPARTMENT OF TRANSPORTATIONFEDERAL RAILROAD ADMJNISTRATIONOffice of Research and Development

Washlnaton, D.C. 20590

Page 2: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

/

Page 3: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

GENERAL DISCLAXMER

This document may be affected by oae or more 01 the loUowUag ltatemeats

e This document has been reproduced from the best copy funaished bythe sponsoring agency. It is being released in the iaterest of makinga\'ailable as much iDformatioD as possible.

e. This document may cODtain data which exceeds the sheetparameters. It was furDished iD this cODditioD by the sponsoringagency and is the best copy available.

• This document may cODtain tODe-oD-toDe or color graphs, chartsand/or pictures which have been reproduced iD black and white.

• This document is paginated as submitted by the origiDal source.

• Portions of this document are not fully legible due to the historicalnature of some of the material. However, it is the best reproductioDavaila ble from the original submission.

Page 4: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK
Page 5: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

1. Report No.

:·I.'~' < ,;: 'j'olFRA/ORD- 79/09. f

2. Government Accellion No.

Tecllnical· Report Documentation Page

3. Recipient'l Cotalog No,

4. Title and,Subtitle

POSTMORTEM INVESTIGATION OF THE KANSAS TEST TRACK,.VOLUME I

5. Report Date

cNoven1ber 19796. Performing Organization Code

~:-'-~~:-:- -:.. --! 8. Performinll Orllani zation Report No.

7. Authorfs) Stafford S. Cooper, Albert J. Bush III,Homer C. Greer III, Mark A. Vispi, Melvin M. Carlson9. Performinll Organi zotion Name and Address 10. Work Unit No. (TRAIS)

Final Report6/1/75-6/1/76

11. Contract or Grant No.

DOT AR-30025

14. Sponsoring Agency C~de .

RRD-32

u. S. Army Engineer Waterways Experiment StationGeotechnical LaboratoryP. O. Box 631, Vicksburg, Miss. 39180

~-::- -:-~-:- ~ .;...---,- ......j 13. Type of Report and Period Covered

12. Sponloring Agency Name and A.ddress

, U. S. Department of TransportationFederal Railroad Administration,Office of Rail Safety ResearchWashington, D. C. 2059015. Supplementary Notos

16. AI:{ltract ~

\ " -\:,,: ,~,

"The Kansas Test ~~rack (KTT) was comprised of nine .differen~tra'Cksystems,, which were built on a: designed embankment. The KTT subgrade experienced prema.ture

failure in service, and KTT operations were terminated in June 1975 after six monthsof operation.

A postmortem investigation of KTT was carried out in 1975 and 1976. VolumesI and'II document the structure, ballast, and embankment studies carried out by theu. S. Army Engineer Waterways Experiment Station in the postmortem investigation.Results presented in Volume I provide needed insight into track system behavior andare particul~rly descriptive of ballast and embankment performance. A rationale ispresented to explain the mechar.ism of failure in the subgrade, and attention isdrawn to' the'structure-ballast-subgrade interactidn processes which govern track·system performance. Inadequate drainage of the top of the KTT embankment led tomoisture content increases in the top of subgrade from 1911 to 1974, when trafficcommenced. The embankment clay was moderately to highly plastic, and moisture­induced loss of strength in the top few inches of subgrade was the principal cause

·of failure. ""; -

I

.'17. Key Word I

BallastEmbankmentsKansas Test TrackRailroad, tracksSoil-track. interaction

SubgradesTrack performance.Tracks

18. O;ltribution Statement

Report is available through the NationalTechnical Information Service, Springfield,Va. 22161

19. Security Clallif,(of this report)

Unclassified

Form DOT F 1700.1 (8-72)

20. Securi!y Cloaii f. (of thi I pag..)

Unclassified

Reproduction of completed page authorized

i

Page 6: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

,.'

Page 7: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

PREFACE

This study was authorized by the Department of Transportation

(DOT) Federal Railroad Administration (FRA) under Interagency Agreement

AR 30025, dated 12 December ,1972, and Amendments 3-8 thereto. The work

was performed by personnel of the U. S. Army Engineer Waterways Experi­

ment Station (WES), P. O. Box 631, Vicksburg, Mississippi 39180.,Dr. R. M. McCafferty of the Office of Rail Safety Research, FRA~

monitored the project.

Mr. A. J. Bush III, Pavement Evaluation Branch, Geotechnical

Laboratory (GL), carried out the field and laboratory trenching study.

~. H. C. Greer, Instrumentation Services Division, was responsible for

the instrumentation investigation, and Mr. M. A. Vispi, Explorations-Branch, GL, accomplished the penetro~eter testing. Mr. M. M. Carlson

was responsible for vibroseismic testing. Mr. S. S. Cooper, Geodynamics

Branch (GDB), Earthquake Engineeri~'aqd Vibrations Division (EE&VD), ',/

directed the investigation and pr~:e.ared this report under the super-'

vision of Mr. R. F. Ballard, Chief, GDB, and Messrs. P. F. Hadala and

F. G. McLean, Chief and former Chief, 'respectively, of EE&VD. The work

was performed under the general supervision of Mr. J. P. Sale, Chief,, ' ""-, '

GL.

COL G. H. Hilt, CE, and COL·,J. L. Cannon, CE, were Directors of

the WESduring this study. Mr. F. R. Brown was Technical Director.

iii !""eceding page blank I

Page 8: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

METRIC CONVERSION FACTORS

ApprOlimltl Convl"ion. to M.trill M...u". ... =--:: ApprOliml" Conver.ion. fro•••tric .....".

=--:: S,..II.1 Whn Y.. lin.. M.IIi,I, II, T. Fl.... S,...II,.... WIll. Y. 11_ . Muhi'" II, T. Fl... S,.hl ~

=-- .. LENGTH

~

LENGTH - nm millimole" 0.04 inche. in

~ em centimeters 0.4 inches in- m moler. 3.3 teel "

in Inchel -2.5 centimeters em - lID m mete..! 1.1 yard. yd

II feet JO c8ntllnerers em -.I - kin kilmnetBn 0.8 miles tn.y<! ,ani. 0.9 meters m ==-==-- _Ifti miles 1.& leilone'er. km ::-

- AMAAREA ~

en - = ar1- ~re .....li_. 0.18 square inches in2

in2

Mluare inches 6.6 square centimeters cm2 :: m2 square met.. 1.2 IqU8f8 yard. .,.r,,2 oq..... ,_ 0.09 oqua.. mole,. m2 _ 1un2 _e kilamsrero 0.4 oq.... mile. mi2

.,dZ oquo.. yont. O.B square me'". rrl- • lIB hectare. 110.000 rrl-) 2.6 .anmi2 square mil.. 2.6 ....re kilarneter. ~ _-

_ens 0.4 hec1llrea h8 _ ..

.. ~ .ASI~wli••t)1-" MASS (w.ilh" - ~

<: g grentlI 0.031 ounce. DZ

... ounce' 28 grem. 9 - ~ IllI kilogrnm. 2.2 pound. IbIb pound. 0.45 k,lOQI'amo kg ~ I ' ...ne. (1000 kg) 1.1 ohort I.......... I.... 0.9 1_ • - ==-- _

12000 Ib) .. c>

VOLUME =-- ~ VOLUMEen

. .. . I - ml milliliters 0.03 fluid ounce_ II oztsp teaspoons 6 ml II Ilitera m 2 -om pi.Tbop labl••_. 15 millilil.... ml - ... I Ii..,. .1 P' n. ...fI oz fluid Ounces 30 millilitBrs rnl W _ , liters 1.06 qua Ic c 0.24 litera I to- I lilers 0.26 9811.CIIl1I ~

pt P=: 0.47 liters I _ m3 cubic meters 35 Qlb~c teet ft J

ql q..ans 0.95 Iilers I _ _ lD mJ cubic meters 1.3 OJbu; yards yd

gal gall.... 3.B liler. I =--tr' cubic leal 0.03 cubic melers m~ .. -... TEMPERATURE (.lIctlyr cubiC yards 0.16 cubiC meters m • •

TEMPERATURE (u.ctl _ • °c C.I.iu. 9/6 1_ Fahranheit OF

--- ,emperabJre add 32) nnp8fature

OF Fahrenheit 5/9 (aft8T Celsius °c _ ~

temperature subtracting temperature ~ _ OF

321 .. ~F 32 98-6 212

_. _ -4~, I' !,~ 'I' ,1 4,°" /8.0" LI,I~O, I ,1,~O'i' ,,2~~"I In '; 2.54 lell:acllyl. For orher e.ilcl conVersluns .11M moce deralled fables. see NBS MI'\.... PubL 2B6. :::I _ - -40 -20 0 20 f40 .60 80 - ~OOUnits of Welghtb and Measures, Price $2.25. SO Cotalog Nu. ClJ.10:2B6. ~ --- £,C 31 C

.. _ u

Page 9: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE OF CONTENTS

INTRODUCTION

BackgroWldPurposeScopePresentation

SITE DESCRIPTION

DEVELOPMENT OF POSTMORTEM TEST PLAN

Structures TestBallast and EmbankmentBuilt-In InstrumentationThe Test Plan and Schedule

FIELD INVESTIGATIONS

Structure Testing (Phase I)Embankment Vibroseismic StudyEmbankment Dutch Cone Penetrometer StudyTest TrenchingEmbankment Instrumentation

LABORATORY INVESTIGATION

Ballast T.estsEmbankment Material Property TestsEmbankment Strength Tests

ANALYSIS OF RESULTS

StructuresBallastEmbankmentInstrumentation

CONCLUSIONS

Mechanism of FailureStructuresBallastEmbankmentInstrumentation

RECOMMENDATIONS

BallastEmbankmentInstrumentation

REFERENCES

v

Page

1

1668

9

12

12222424

28

2931455373

85

858590

93

9395

100119

122

122122123123125

126

126126127

129

Page 10: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

UNCONFINED COMPRESSION TEST RESULTS ON SUBGRADESAMPLES' 92

',RESULTS'OFSTATISTICALF:AND T TESTS ON MEAN CBR'sAT DIFFERENT LOCAT:j:ONq" 105

, ,",', "" CUMU~TlYEi,!DEFORMATI()N' ~~, UPPER· 1. 5 FT OF' KTT" ".• :;EMBANKMENT,:i~hi~oCTOBER:i974 (FROM FRA-ORD-

"><+76'£.25'S.f' ' ',', .' '112

, SUMMARY' OF 'INSTRUMEI.TATION DEFECTS BY TRACKSECTION AND DATA ACQUISITION PERIOD 114

TableNo.

1

'2

3

, 4

5

6

7

8

,9

10

11

,,",',- , ,12

" '

13

FigureNo.

1

2

3

,LIST OF TABLES

Title

KTT TRACK STRUCTURE DESIGN VARIABLES

PLATE BEARING TEST RESULTS

MAXIMUM VERTICAL DEFORMATIONS UNDER THE TRACKSTRUCTURES (MEASURED AT THE BALLAST-SUBGRADE

, INTERFACE)

TYPICAL RESULTS OF FIELD INSULATION MEASURE­MENTS INSULATION TO GROUND TEST SECTION 2,20 MAY 1976

FINAL EXTENSOMETER READINGS

POSTMORTEM CONDITION OF EXTENSOMETER LVDTASSEMBLY

EXTENSOMETER IN SITU CALIBRATION RESPONSE TOl-IN. DISPLACEMENT, 20 MAY 1976CALIBRATION HISTORY OF MAIN INSTRUMENTATIONARRAY PRESSURE CELLS

LABORATORY CLASSIFICATION TESTS ON SUBGRADESAMPLES

LIST OF FIGURES

Title

LOCATION OF KTT TEST SITE

EXAMPLES OF PUMPING AND SPALLING AT CONTROL POINTSOF THE NONCONVENTIONAL TRACK STRUCTURES

. '

TYPICAL EXAMPLES OF PUMPING IN THE CONVENTIONAL, TRACK STRUCTURES

vi

,Page

3

56

61

75

76

81

83

84

89

2

5

7

Y,

Page 11: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

...

FigureNo.

4

56

7

.8

9

10

11

12

13

1415

16

17

18

19

20

21

22

23

24

Title

SCHEMATIC SHOWING KTT LAYOUT AND LOCATION OF MAIN-INSTRUMENTATION ARRAYS DOT-KANSAS TEST TRACK(PARALLELED AN EXISTING ATSF MAINLINE TRACK 30 FTAWAY)

TYPICAL CROSS SECTION THROUGH KTT EMBANKMENTS

SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 1

SUMMARY OF ATSF MAINTENANCE, TRACK SECTION .2

SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 3

SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 4SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 5

SUMMARY OFATSF MAINTENANCE, TRACK SECTION 7SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 8

SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 9

GRAPHIC SUMMARY OF WES TEST PLAN

CHRONOLOGY OF KTT EVENTS, INCLUDING TIMING OFPOSTMORTEM INVESTIGATIONS

TYPICAL DEFLECTION MEASUREMENT CONFIGURATION FOREACH BEAM IN THE MITRE STATIC AND DYNAMIC TESTS,BEAMS 14-18, TRACK SECTION 4SUMMARY OF INITIAL DYNAMIC STIFFNESS RESULTS FROMPOSTTRAFFIC IMPEDANCE TESTING

TYPICAL VIBROSEISMIC TEST CONFIGURATION

PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 1 (KTT EMBANKMENT)

PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 2 (LOCATION 2A,KTT EMBANKMENT)

PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 2 (LOCATION 2B, KTTEMBANKMENT)

PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 3 (LOCATION3A, KTT EMBANKMENT)

PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 3 (LOCATION 3B,KTT EMBANKMENT)

PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 4 (KTT EMBANKMENT)

vii

10

11

13

141516

17

18

19

20

26

27

30

32

33

34

35

36

37

38

39

Page 12: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FigureNo. Title Page

25 PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 5 (KTTEMBANKMENT) 40

26 PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 7 (KTTEMBANKMENT) 41

27 PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 8,(KTT EMBANKMENT) 42

28 PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTICMODULI VERSUS DEPTH, TRACK SECTION 9(KTT EMBANKMENT) 43

29 PRETRAFFIC AND POSTTRAFFIC SUMMARY PLOTS OFELASTIC MODULI VERSUS DEPTH, TRACK SECTIONS 1THROUGH 9 (KTT EMBANKMENT) 44

30 WES MODIFIED DUTCH CONE PENETROMETER AT TESTLOCATION IN TRACK SECTION 3 46

31 AVERAGE PENETRATION RESISTANCE IN TRACK SECTIONS1, 2, AND 3 47

32 AVERAGE PENETRATION RESISTANCE IN TRACK SECTIONS4, 5, AND 7 48

33 AVERAGE PENETRATION RESISTANCE IN TRACK SECTIONS8 AND 9 49

34 AVERAGE PENETRATION RESISTANCE AT SELECTEDLOCATIONS UNDER THE CONVENTIONAL (TIE) TRACKSTRUCTURES (TRACK SECTIONS 1, 2, 3, 8, AND 9) 50

35 AVERAGE PENErRATION RESISTANCE AT SELECTEDLOCATIONS UNDER THE NONCONVENTIONAL TRACK

·STRUCTURES (TRACK SECTIONS 4, 5, AND 7) 51

36 MEAN AND STANDARD DEVIATION CURVES OF PENETRA-TION RESISTANCE VERSUS DEPTH, BASED ON ALLPENETROMETER DATA (1235 DATA POINTS) 52

37 REMOVAL OF CONVENTIONAL TRACK STRUCTURES FROMTEST LOCATION 2A (TRACK SECTION 2) 54

38 REMOVAL OF NONCONVENTIONAL TRACK STRUCTURES FROMTEST LOCATION (TRACK SECTION 7) 55

39 TYPICAL LOAD-DEFLECTION CURVE FROM 30-IN.-DIAMPLATE BEARING TESTS ON THE BALLAST BENEATH THETRACK STRUCTURES, KANSAS TEST TRACK SECTION 2BCROSSTIE NORTH RAIL 57

viii

Page 13: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FigureNo.

40

41

42

43

44

46

47

48

50

51

52

53

Title

SUBGRADE IRREGULARITIES FOUND AT THE BALLAST­SUBGRADE INTERFACE t TEST PIT 1 (TRACK SECTION. 1)

SURVEY CROSS SECTION AND PROFILES OBTAINED AT THEBALLAST-SUBGRADE INTERFACE t TEST PIT 2A (TRACKSECTION 2)

AVERAGE WATER CONTENT t DRY DENSITY t AND CBR TESTRESULTS. VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 1 (TRACK SECTION 1)

AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TESTRESULTS VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 2A (TRACK SECTION 2)

AVERAGE WATER CONTENT, DRY DENSITY tAND CBR TESTRESULTS VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 2B (TRACK SECTION 2)

AVERAGE WATER CONTENT t DRY DENSITY, AND CBR TESTRESULTS VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 3A (TRACK SECTION 3)

AVERAGE WATER CONTENT t DRY DENSITY t AND CBR TESTRESULTS VERSUS DEPTH IN THE.EMBANKMENT t TESTPIT 3B (TRACK SECTION 3)

AVERAGE WATER CONTENT t DRY DENSITY, AND CBR TESTRESULTS VERSUS DEPTH IN THE,EMBANKMENT t TESTPIT 4 (TRACK SECTION 4)AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TESTRESULTS VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 5 (TRACK SECTION 5)

AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TESTRESULTS VER8~S DEPTH IN THE EMBANKMENT, TESTPIT 7 (TRACK SECTION 7)

AVERAGE WATER CONTENT, DRY DENSITY t AND CBR TESTRESULTS VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 8 (TRACK· SECTION 8)

AVERAGE WATER CONTENT, DRY DENSITY, AND CBR -TESTRESULTS VERSUS DEPTH IN THE EMBANKMENT, TESTPIT 9 (TRACK SECTION 9)

MEAN AND STANDARD DEVIATION CURVES FOR AVERAGEWATER CONTENT, DRY DENSITY, AND CBR DATA FROM ALLTEST PITS VERSUS DEPTH IN THE EMBANKMENT

FIELD CHECK OF MAIN ARRAY INSTRUMENTATIONREADOUTS

ix

58

60

62

63

64

66

67

68

69

70

71

72

74

Page 14: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FigureNo.

54

55"",'

56

- ,

57

58

59

60

61

62

63

64

65

66

67

68

69

Title

TYPICAL EXCAVATION OF MAIN ARRAY INSTRUMENTATION"-, .TESTPIT 7 (TRACK SECTION '7)

VERTTCjj,:EXTENSOME~T~LTOBSERVED IN TEST PIT 9(TRACK-SECTION 9) , ,', - , " , '

.. :", " .'.' ,,;:,>,,~. "·!).:;~:i·-::.. ,.,,~, \: .':",," -.\~ .":'-:. ~ ...;.~-:\ ,,' , .' 't ' .' "

CONDI'I'ION;OF'PCNPRES9TJRE:CCELLS (LOCATION JUST<:BENEATii)THE" BALLAsT,'SUBGRAnE INTERFACE" TRACK

SECTION 3)<,- ," > -'., .

EXAMPLE OF INTERNAL DAMAGE TO MAIN ARRAY VERTICALEXTENSOMETER (TRACK SECTION 2 )

RANGE IN GRADATION OF "TOP" BALLAST SAMPLES'

RANGE IN GRADATION OF "BOTTOM" BALLAST SAMPLES

RAN,GE IN GRADATION OF "SHOULDER" BALLAST SAMPLES

TYPICAL LABORATORY CBR AND COMPACTION TESTRESULTS ( ON SPECIMENS REMOLDED FROM BAG SAMPLE'OBTAINED IN TEST PIT 1, TRACK SECTION 1)

RANKING OF THEKTT TRACK SECTION ACCORDING TOTHEIR INITIAL DYNAMIC STIFFNESS IN PRETRAFFICAND POSTTRAFFIC IMPEDANCE TESTS

RANKING OF THE KTT TRACK SECTIONS ACCORDING TOTHEIR RELATIVE STIFFNESS UNDER TRAFFIC (FROMTRACK GEOMETRY, CAR MEASUREMENTS BY ENSCO,DECEMBER 1974)

ILLUSTRATION OF SUBGRADE MATERIALS PUMPED 11IN. UPWARD INTO THE 15-IN.-THICK BALLAST OFTRACK SECTION 8

ABRASION PRODUCTS, IN THE FORM OF FINE WHITEPOWDER ON THE BALLASI', WHICH TYPICALLY DEFINEDTHE SEATING AREA OF CONCRETE CROSSTIES,AVERAGE CURVES FOR ELASTIC MODULI AND PENETRA­TION RESISTANCE VERSUS DEPTH IN THE EMBANKMENTFROM ALL VIBROSEISMIC AND PENETROMETER DATA,RESPECTIVELY

COMPARISON OF PRETRAFFIC AND POSTTRAFFIC VIBRO­SEISMIC DATA TO DETERMINE TIME AND TRAFFIC­RELATED CHANGES IN STRENGTH AS A FUNCTION OFDEPTH IN THE EMBANKMENT

EMBANKMENT VERTICAL DEFORMATION AS A FUNCTION OFTIME (REPRINTED FROM FRA-ORD-76-258)

AVERAGE CBR AND PLATE BEARING TEST RESULTS BYTRACK SECTION

x

77

79

80,

82

86

87

88

91

96

98

99

101

103

104

107

Page 15: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FigureNo. .Title Page

70 RELATIONSHIP BETWEEN DRY DENSITY, MOISTURE .CON-TENT, AND SHEAR STRENGTH DERIVED FROM CONSTRUC-TION (1971) AND POSTMORTEM (1976) STRENGTH TESTRESULTS 109 .

71 AVERAGE RAINFALL AT THE CASSODAY, KANSAS, GAGELOCATION (3 MILES EAST O~ THE KTT) IN THEPERIOD 1971-1976 ill

72 PONDING OF SURFACE WATER IN THE DRAINAGE DITCHBETWEEN THE KTT AND ATSF MAINLINE TRACK (VIEWLOOKING EASTWARD TOWARD TRACK SECTION 7) 115

73 LATERAL DRAINAGE CULVERT (TRACK SECTION 8,ADJACENT TO GRADE CROSSING) 116

74 DRAINAGE CULVERT UNDER TRACK SECTION 8 117

75 TOP OF SUBGRADE AND DITCH BOTTOM (BETWEEN TRACKS)PROFILES ALONG THE LENGTH OF THE KTT 118

xi

Page 16: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK
Page 17: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

-'i."""

"

POSTMORTEM INVESTIGATION OF THE KANSAS TEST TRACK.

VOLUME I"

INTRODUCTION

Background.

-The Department of Transportation (DOT) Federal Railroad Adminis..;.

tration (FRA) is actively engaged-in railway research programs whose

primary objectives are (1) a reduction in frequency of track-caused'

derailments and (2) the development of improved track designs and

maintenance procedures. As a part of this research effort. the 8000-ft­

long Kansas Test Track (KTT) was constructed near Aikman. Kansas, under

joint sponsorship of the FRAl ,2,3 and the Atchison; Topeka ,and Santa Fe

(ATSF) railroad. The KTT was located adjacent to an existing ATSF main­

line track, as shown in figure 1, so that the relatively heavY ATSF

freight traffic could be used as the test loadings for KTT.:,

The KTT was conceived as a means of evaluating the effects of

stiffness variations on track system stability, performance, and main­

tenance requirements under actual traffic conditions. It was built

using nine track support systems, which were designed to provide various

degrees of vertical stiffness. 4 The track systems were foundedoon a

specially designed embankment5 which, to conform with usual railroad

practice, was built of locally available materials. 6 Expectations were

that the embankment and structures would survive for at least the three­

year period required for testing. The desired differences in trac'ksup:­

port system stiffness were achieved by using either conventional (tie)

or nonconventional (beam or slab) construction and by varying other prop­

erties such as tie spacing and ballast thickness. 4 A summary of the

test sections and their d~sign variables is shown in Table 1. Since;

the clay embankment was not intended to be a test variable, it was con-

structed under rigid controls to achieve the maximum practical degree~-bf--~ --:;

subgrade uniformity.6 Instrumentation arrays were built into each

1

Page 18: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

llaIlliU

,...c....

!C> __...~

...... ~. 54

0" .. @VI I"

LOCATION OF KTT TEST SITE

2

I,

j'

Page 19: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 1. KTT TRACK STRUCTURE DESIGN VARIABLES

Section BallastNumber System Type De~ Remarks

1 Concrete ties, 30-in. C-C 10 in.*

2 Concrete ties, 27-in. e-C 10 in.

3 Concrete ties, 24-in. C-C 10 in.

4 Continuous concrete beams 6 in. Cast-in-place structure

w 5 Continuous concrete slab 6 in. Cast-in-place structure

6 Wood ties, 19.5-in. C-C 10 in. 6-in. stabilized ballast layer on subgrade

7 Continuous concrete beams 6 in. Precast beams, installed and field joined

8 Concrete ties, 27-in. C-C 15 in.

9 Wood ties, 19.5-in. C-C 10 in. Control section (standard Santa Fe)

* A table of factors for converting units of measurement is presented on page ii;

Page 20: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

section of the embankment to measure static and dynamic response of the

structures and embankment during the life of the project. Upon comple­

tion of construction work on the KTT embankment in 1971, the U. S. Army

Engineer Waterways Experiment Station (WES) conducted a vibroseismic

study to determine in situ elastic properties at selected locations :,7

By 1972 the track structures had also been installed, and the WES

was asked to determine the dynamic properties of each KTT track system

using mechanical impedance'techniqUes. 8 This investigation was to be a

feasibility study; however, if meaningful results were to be obtained in

the initial study, then periodic (performance) retesting also needed to

be done. Measurements of track system dynamic stiffness were the prime

objective of the study, but other data were also cOllected. 8

On 2 May 1973, slow-order freight traffic from the ATSF mainline

was diverted onto the KTT. After a few hours of operation, the KTT had

to be closed for repairs to the rail fasteners of the nonconventional

track structures. The problem was caused by pullout of the rail fastener

anchor bolts, which were then redesigned by the Portland Cement Associa­

tion (peA). The modified anchor bolts proved to have excellent pullout

resistance; however, replacing all of the defective fastener bolts de­

layed reopening of the KTT until 31 October 1974. After 14 days ,of slow

speed traffic, the KTTwas closed as planned for final repairs and ad­

justments. On ,10 December 1974, the KTT was finally open to unrestricted

mainline ATSF freight traffic. Under the effects of high-volume

traffic, KTT began to show signs of distress after only 2-1/2 months of

operation.

Upper limit (FRA Class 5) profile and gage irregularities, as

measured by a track survey device, occurring in the nonconventional

structures (twin beams in Track Sections 4 and 7) were the first evi­

dence of more serious problems to follow. Cracking of the beams at

vertical construction joints and spalling at'the joint cracks also

occurred. While these conditions were not cause for immediate concern,

the appearance of mud pumping through the ballast certainly was.

Examples of spalling and pumping in the nonconventional structures are

shown in Figure 2. During the spring thaw and rains of 1975, pumping

4

Page 21: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 2. EXAMPLES OF PUMPING AND SPALLING AT CONTROL POINTSOF THE NONCONVENTIONAL TRACK STRUCTURES

5

Page 22: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

in Track Sections 1, 4, 6, an~ 7 after heavy downpours~

These and other

"conditions were in evidence at many locations, being particularly severe

Typical condi-I •• "I.

tions in the conventional track structures are illustrated in Figure 3., • I (",

Two kinks in the KTT track occurred on 6 June 1975; these ~infts were

located in Track' Sections 1 and 2, respectively, and were at~rip~ted to

loss of lateral tie support in the mud-fouled ballast~

operational problems prompted FRA to close the KTT per~aneptly on

11 June 1975.

In subsequent meetings between DOT ~nd WEB r~present~:tive§, the

WEB was as~ed to develop plans for a detailed postmortem irivestigation. ~ ··"f', \,' .- . . . ..

of the KTT embankment }o ~nclude ~pe acquisit~on of str~ct~a+ ~e~pon~e.

data which would be used by other investigators. The po~~mbr~~m test

program proposed by ~9 was adopted by FRA and has since been carrie~

out under authority provided in Interag~ncy Agreeme~t AR 3qO~5, ~~~

Amendments 3-8 thereto. This report plus Referepce 8 comple~e~ all

the work scheduled under agreement.

Purpose

Basic objectives· of the KTT pos~mortem investig~tion carr~e~ out

by the WES were as follows:

1. To determine the mechanism(s) of failure in the emb~~ent.

2. To determine the condition of built-in, instrumentat~o~ and,if possible, the validity of data obtained from ~ame.

3. -To.acquire the static and dynamic load-deflectiop data needed•.:to tune existing analytical models developed by others' and,: toa~quire posttraffic impedance test results for comparison' ,,'

. pUrposes. ' ' , , < '-' ... , '

4. ,ToJec'onimend design improvements for future test faci~ities.

Scope

This report documents the field and laboratory investigati0Il-s ,con~

ducted by'th~WEpduring the FRA KTT postmortem program.. i -

Included are~', .

results of~aterial property tests on the ballast, results of materi~i••. ~l

property Emd, strength tests on the embankment· clays, results of:j.n sftu, '. -, I. " ;. ,~ ,

geophysiciii i'~vestigations of the embankment, and other pertin:~ntdata. . "- :', '. .,

6

,-

Page 23: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 3. TYPICAL EXAMPLES OF prn~ING IN THE CONVENTIONALTRACK STRUCTURES

7

Page 24: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

derived from measurements and insp~ctions of the site, struct~es~ ~4

test trencqes. In addition, results of an investigatton of the p~ilt-~n

~mbankment instrumentation are presented. Results of the v~rious inv~s~

tigatiops are analyze~ and correlated, and a ratiqpale is developed\ , -~~. I t i " ,,- '.

whicq explains the behavior of the KTT embankm~nt. Concl~~ions ~e

drawn regarding the so~ces of KTT subgrade problems anq r~cq~en4~d

preventive and/or remedial treatments are advanced. ~ecornmendations

for future planqing, of s~milar test f~cilities are al~o qffere~.

Presentation

In consideration of the quantities qf data and irform.~tion~en~

erated in this study, results are presented in two yol~es~ Vp+~e I

summarizes the data obtained in the various KTT postmo~te~ inyestig~~

tions and presents analyses, ~onclusions, and recommepdation~ d~riY~d

from same. Volume II describes the test procedur~s and equipment ~se~

in the investigation and also documents the original data. Hopef~l~,

material contained in Volumes I and II will prqvide be~ter insi~~t i~tp

track system behavior under adverse conditions and ~lpo should prom.qte

a better understanding of the structure-ballast~interactiqpprpceppep

which govern performance.

8

. c

Page 25: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

SITE DESCRIPTION

-The KTT paralleled an existing Santa Fe mainline trac~ at, a ,

dist~ce of 30 ft.· MaximUm r'elief in thi~- 'area is ~pproximately 30 ft,

and the terrain is characterized by gently rolling, grassy fields with

occasional limestone outcroppings. Drainage is to the southwest, and

the KTT track runs northeast to southwest with a 0.4 percent slope

towards the latter direction. The average site elevation is approxi-

. mately 1400 ft above mean sea level. Subsurface materials in the site

vicinity typically consist of 1 to 5 ft of residual clay overlying the

parent limestone bedrock.

The KTT embankment consisted of approximately 6ft of residual,

reddish-brown, plastic clay (CH) founded on limestone that had pre­

viously been excavated to design depth. Instrumentation arrays were

installed at preselected locations along the test track. 6 Locations

of the various track support systems and built-in instrumentation arrays

are shown in Figure 4. A typical cross section through the KTT .embank­

ment is shown in Figure 5. Construction details of the embankment and

built-in instrumentation are given in Reference 6.

9

Page 26: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

DOT-KANSAS TEST TRACK(Paralleled an existing ATSF mainline track 30' away)

Track Section #i #2 #3 #4 #5 #6 #7 #8 #9

Length, ft t*-800 ...... ~800 .......... 800~ ... 800i..... 800-+t ..546"..I't-~OO-tf t4-800~800...

+',til'

s:::HI

@);,

COl\.01+,If\'(\J'

:gl+'tils::H,

@)

co I\.0 '+1Lr\ I(\J'Lr\:co:

I ·H .~ -H -I -~ ~H -I -It .. itt t- 1 .\.0 I \.0 \.0 \.0 0 rl ' I.--I I .--I (Y") (Y") co -=t (Y")

+1 + + + + + (Y')+ILr\ (Y") (\J 0 I:-- \.0(Y') -=t , Lr\ \.0 \.0 I:-- 1:--1Lr\ Lr\ I Lr\ Lr\ IJ"\ Lr\ co 'co co , co co co co Lr\ j

: co'@) @)' @)I @)I @) @.) @.)!

~ ~ ~ ~,~ ~ +'s:: s:: s:: I s::' S::II s:: til

'H H H; HI H H s::I H

StationsI-'o

(Y") (Y')i 0 0: 0 0 0 1 0 01 \0 Lr\ IJ"\! 1:--' I:-- 1:--,(Y") Lr\ 0, 0' 0 (\J (\J (\J (\J,\.O (\J (\JI.--II .--I .--I+ + + +, + + + + + + + + + + +,0'\ I:-- 0'\' I:-- Lr\ \.0 -=t (\J (Y") : co' 0 co , .--I ' 0'\ , I:--.--I (\J (\J' (Y') , -=t -=t Lr\ \.0 \.0 I I:-- I:-- I co ' co 0'\ ILr\ Lr\ 'Lr\ Lr\ , Lr\ Lr\ Lr\ IJ"\' Lr\ I ~ Lr\ Lr\' Lr\ I Lr\ Lr\ ,co co co co co , co co co ' co' co co co co: co co I

FIGURE 4. SCHEMATIC SHOWING THE KTT LAYOUT AND LOCATION OF MAIN INSTRUMENTATION ARRAYS

Page 27: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TEST TRACK .. N

1 I

6'

6" GRAVEL SURFACING

DRAINAGEDITCH

16 '

AT&SFRIW20'

ELEVATION OF BASEOF RAIL

ORIGINAL GRADE

11'

" '<-- ---------

_ 30'

ROCK (VARIABLE)

11'

DRAINAGEDITCH

......A........ BIR

MAIN LINE

1410

....IL

Z·0

.....j:::: 1400

I-'«>UJ..JUJ

1390

FIGURE 5. TYPICAL CROSS SECTION THROUGH KTT EMBANKMENT

Page 28: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

DEVELOPMENT OF THE POSTMORTEM TEST PLAN

Planning for the WES participation in the KTT postmortem investiga~

tion began in August 1975, two months after final shutdown of the KTT.

Early ,in the planning phase, input was solicited and received from many

other investigators with an interest in the KTT program. Concurrently,

the WES conducted a review of the KTT embankment construction history.

With this background, final planning was accomplished by FRA and WES

representatives. Representatives of MITRE Corporation, a DOT contractor

organization, were also present, since the FRA wanted them to plan

'special structures tests that would be carried out by the WES during the

postmortem investigation. Major objectives were established by the FRA;

and by late August 1975, the WEB technical approach was developed in de­

tail. By this time ATSF maintenance records for the KTT had been re­

viewed in detail, and a graphical performance summary had been developed

for Track Sections 1 through 5 and 7 through 9, as shown in Figures 6

through 13, respectively. For reasons given later in this report Track

Section 6 was not tested. A WES reconnaissance trip to the KTT to liaise

with ATSF representatives followed in mid-September 1975. In view of the

extensive scope of work and the adverse effect of winter weather on field

operations, WES and FRA representatives la~er agreed that the postmortem

work could best be carried out in two phases. Phase I work, which

would consist,of load-deflection and impedance studies of track struc­

ture response, would be attempted in the period October and November

1975. Phase II work, consisting primarily of embankment investigations,

could only be carried out after the track structures had been removed.

Hence, the Phase II work was tentatively scheduled for April and May

1976, by which time the structures were to have been removed from the

embankment. Other considerations which affected the development of a

detailed test plan are discussed in the following sections.

Structures Test

Structures testing in Phase I of the postmortem investigation

12

Page 29: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

f--'W

"

I·' , ': .. : ....... I II I" . I I I I,, . .. r' . I I I I I I

-+- '!... . .. i' I '!, ,I .' TIIACI. SECTIOli II i -+- .-l_ f-:'i.:1 1 . OOHCIlIlTl TlKS )0. SPAClRG

I

I·· I! ., ""1, -WEST

" ':II : II

,

'- "IS' - , I ! .

-~~I

f-,-f- f t

I !~,6/28{7) :

~61~~f15,..-+-,6/19(7~ I=l6/6175 I I

-.;.....,5/)o?7~Lf-- ~p~t ,ra~·i (io j l ic.t1j)'

~.5/23175 ~Iuu

==t.5/5{7). I. ' I I I. i

5/1(75,_ .-, Spot ,ro1.~ (00 .loca~on).I I ! I

~4/)o(75_ I-c.- Spot r.loe (00 locaUon) I ! I I

---;--.4129175'-- f-""":Spot 'r.le~ (00' l~c"U~), I ,

~4/25(7j I , I , I i J, "1 , I " I ,_;-- 4/14(75,'_ .-_ Spot and lioe (00 locatlon) I ' I i_4/11175 -,' . Dip I I

--+-,4/10(75 ' , II I I Sootb}- lind. of tla. ODd tla CllOta.... c"""rad wltb bUlan=0 4/ 4/ 7)1 I I i r Bouab r1d~ 1 Bail (Ballan .bowlol ......11D0 of d1.10talutlon)___ 3124175[ f--f..( Tie•• leved I 1"1 T 01- All t1e. 10.p"cted .bowad _ .t bott~ ~f 't1;" , I I . i

...l-3/lfJi75' 'Bo;..hrl~' I I 1111' I: I I I I! 1

H-pfli75- .- Ralse oortb. rail - locatlon oot .pacifiad -+-:- ~I -i- I i

Iii I I I~-':t: I I

~W-L.q ..... --'-W. I ~~~ 1- I II- .TIE RD. e--t 311 f-I- 30111 251 201 151 ' 101 51 I ·1 .TUND._

~--l---J-J--l I . I. I I' , I I I. I , U...LuL-I

,! If-STATION _ 8527+53 '- _27' 26 25 ' 24 f3 f2 ·fl 10~ 1519+53 STATIOll_

-·-JJ--!-J-LLI- ::J-J I ' I I I I I I ,'1 ' I ~I- Ie---'--'f- UGEND nELD IIOTKS ('. G. Ilc~ao. recontr1P. 6113175)

e--- SYMBOLI --DESCRlPTIOR 1--e---! A. P\IIOP101 off oortb tie ando oaar .ta. 8527+10. P_log _tar1al ... Ira,..

f-I- - Haavy p\llOPlog (to top of ballaat) al1t1ike • ...,lot. -- . .. -'-'"c'

re- /Wo, Spot rai.a end l10e (1I01og t_ar) : B. PIJIIP1D8 appear. to be quite CDIaaOD throughout thi. aectl_.,.

f---, . 'il Locat1on of lIES teat p1 t---f---t, -r- -e--- : C. MaintenGlce crlrV8 baye d.ropped ballaat between Taila ad OQ aoat.b aide

.-

r H Locatlon of buUt 10 1o.tr..-otati00 (liW.o) I I of trac.k.. Thill ballut .eeu to be Braded in larger IIlz.u tta. cKUUuaI'-- - .... _-" 1----, - 1-~I-f-, • PIOOp1ng l(par~1aly, fOul,ed b~llaatl" ballut.- -,~ - -- f : .;. D. Tlo. end ballJult (cr1b) aubB1ded IllOre tban .boulder on aorth 01_ of tra'cl<. -, .-- -

-H, ,

I, E. ,Araa of .1aolficant P.-p101 end balLoet auba1deau at aoutb ai.da of track

-1'- -- .. 1·- -+.- -. -- .--I oear ata. 8516+15.

'I (3)>i

II

I

.FIGURE 6. SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 1

Page 30: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

_ tw-tJ-+-j++--H+t-·H--P- -~ . --1' , .. :.- -: - .:--+: +~--t+m=f---fffF+-L\_.LI, L_..-'-_ TIIACK SECTION 12

f-~+-~f--i---f--f--f--f--f--HH'--1H'--1H'--1-'--1H-I-I-I-t-l-t-t-+-t-t'-+CONCIlETI! TIES 27' SPACING -1--++++-L-+---c-+-+-+-+-+++++++++-+-+++++++~+-IolEST

I ' I I I I ,I I I II,! +-++-l-+-+++++n+·i-H---I·-:~+-++++-t·H~n+fFFFFTlH--I-~-'--~'+H-f--FFFfFFF!=::r~,L-I.~~~I--'- --I-

ATSPL IlAlNTKliAllCEr "I I I F-+-+-+-'-I-+--+--~f-+-+-+--!--++-I-+--+-+--i--

'-'I-'I-~ LpTTTTt-"'1 J:.LW--l--i--+~, •• I l--r-IT1-T-r-+-~~~-fffR-1fR--+I~W-J-~-+---\-ci-c-l--+--W--1--,~

R=R=i+-rt=P+~; I ! I ! I I I I I I I I I I I I, I i I I I

"I,J ,r--l-,++++++t+-'-+ -t-I--+++~ I I I 1 I I I I I I, I I II

II

I I I I I I, I I I I I": I I I I I I I 1 I I 1 I I I I I I I II I I I +++-+++--1 I II I I I I I I I I !-+-~--J 1·1 I I' I I I, I I II' I I I' I I I I ~r~·~

r-:

,r',kL;

" t

I

I

Til'

~ A. Geoeral .ubaideuce of ballaat.

++++'+:-'++H-+-I'~B. PUIllP101 of Irey. IUt-Uke ..urIal. "" oartb aide of treek at 1.1, I, r 1',1 I I II..veral locations.

"

(11810) I 1 I I 1,1 I I I I I I I I I I I ,I' I ! I ,I I, I I' I I I I I I I I I I 'I 'I i 1.1 I .1' I II I 1"'1 ..III

He.vy PUIIIP101 (to tap of b.ll.at)

Spat' ..he and 110. (...1111 t __r),

Lotatiao of IolES t.at pIt

lAc_tlaa of blUlt 10 luu_UtlO1l

PuapIog (partIal' faulad ballaat)I 'I I

LI·,I--,I~~

J II IIITEI

16/28175 I '\ I I I I I I I \ I I I I ' ''i ;/8175 I I I LL ,II I. TJ r I 1.1 ,.I I I rl i I..&W ~.JI

"', I, ,Spot raiD. tbrouabwt I.c,ti~ ,

;~,~~~~~L u:", mck I I I I I II I ,I ITT;/li75_ -4jSpot rabe (110 Ioc:..ti"" livel1)-Hud .t bottom of cial or allgbtly abava I

,4/30~75, I 11 1 I I I I I I I 1 II!~ ~t 'b';tt;'" 'of' ti... a'r ~u'abtJ.1 ~~I 4/1;/7; ,I I 1,1 1,1 I I I I-U_J II ,I I I I' '" I 'I'. I

'4/14/75 - Spot r.be al1d 110. tr.ck (00 lac.tiao liVeD) TTl I~ 3/24i7; __ "",!-t,a ~att~,af ,t1e."io a..... ~oc~t1:au,. (o~t ~P.Clfledi), 3/4/7;I-SP~t ,raj,ae (00, lac.,tl~ ,giv.o) I I I , 1 , 1 , 1 I ' ,

3/]/7;_ f--c Spat r.be (DO loc.tlau giveo)! I II 1 I I i I I· I 'i I I I 1 I I I 1 I I I I I IUla. I I I I I I', I ,'1 I ~ A

·,1:CI'

i 1,1 1 I I, :-1' "t- 1 , n" I 1 I "'T' , 1 '1" ,T""" . . "1'1' . . 'TT T 1.~TlE NO.' I 1m -I ~11 ~1 I 201 1 1;1 I 101 I '5,1 I I_~rl Jng ~'I_

.,-----rT' 1 I, I I ,I I' 1 I I II liTl"

E,

', ,!sTfTIIONI_81;l~~3( '1 31;: '~4 313:~', : 11 311

. : 3~' u~t+OO'....SUTIOII .:.:

L1tGKIID ' I ,I FlIWl NOTI!S (F. G. lIel..... recaatrip, 6/23/7;)

SYIIBOL DESCTIPTIOII

~.' ..='. \l,H

I--'+:-

,FIGURE 7. SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 2

Page 31: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

'I··'··IIIII I I I

I III IIII

I,l':T:

~+;l..... - ' JT . 11

TB.ACIl SECT~ON 13

,: " . I : :CONCilETE TIES· 24" SPACING .... ,

~,'_l--c ""t -+-++,-t.'--1,-.,1-++4-c+--H---+--c1H-++-+-+-++-1-+,++-4-j: __ WEST

+-~.~+. iii II:: ::r+++-++H+-+++I I I I I I II I IIL:l1111111 1111 H

h9~~ I : I : I i II I II I I I III I I I II L I I I I I I I II I I II II I I I 1.1 I I I II II I I I I 1111111_ 1-1-11 I'll 11,1i., ..

I II.I I" I.·

I I h:I . ~ ,I. :

'.

!::

··:I:i·

arlldad in =tt=t:tj

I" ..""T

n

I

I I I I I I I 5LL.LLL1.~.J.+ 1+ m 110.• ~I.TT:TT r-; I , I I I· I.

+--++-+--+-++-138~85J1+OO'-STATION. _..Ll.....l I I I I II I !I I I ' 1 i+-+.c1---J----j

PULD MOTES (f. G. IIcLaan, racoatrip, 6123/15)

A. Ballast al.lb81denc.e IaOro pTODounced tbaD 1n ••ctioo 12

B. IIapa1r craVD tulvD dlllllPad b.lI.. t iD ceDt.. of track vhicb ia

larger sl ...11 than eU8tlu& ballaat.

I ~. II I_II 111,,1_ I' 1--+ C. PllIIIPiog inevidaDca (both gray ad reddieh brOVll _.erial).I 'I I 'I I I I I I I -I. : I I I I I ,"I I j I.

1 .......... _ , , , , , , , , , , , , , , , I ~..iA~ I'

l~l , lrl

.401 I'llI

I

III I 1'I-rT'Tll'TT

DESClUPTION

LoeatiOll of built in l ....r_t.t1oa (....1.0) I II I I I I I I I II I I I' I ~ •I' I I I I I I I i I I I. I I I. I 1.1 I I J'I I I I I ; I , I r-+-f-

lIa.vy pumpioa ('0 top of b.ll...)

Spot r.1ae aod line (...1.0& ta~er)

LocatiOll of \IES test pl.

\IVV\

LEGEND

SYIIIlOL

-V

~

~LL."tttt I I II I

~ STATION _8545+00 I I I. I I I I I L I

lSmalI.1 .,' rI IIlID I 1___ .".

, L 6i28/7~1 1r.1D1r. , ., ,:.~~ '" ' i

f->-.617/15 I." ,.. I " ::.'f.-L b/&175 " " .,.,I- 5ho/7~ S_ll~ , ,'" SUD

f.-f- 5/9/15._. Spot rabed, 00 locatIo';' ~J.v"'" 'kiD1r. If--_

5/ 8175 .. . i', I .i

1-- 51517~_I--Spot ra1aa Veat aod: I I I I i'. , , .. , , ...

f--- 512175 __ f-SPoi t jr.loe (DO Ioc.ti~ ,gIIVeD,) I I : ,I

I-f.- 4/1J175 . I ... 'Dipe io tr.ck I I .

I I I I J I I I I I I I I 11 l~ I:.:i I "' ... "

/-'Vl

I·I:LL,· ,.

..1:·ri I I

FIGURE 8; SUMMARy OF ATSF MAINTENANCE, TRACK SECTION 3

Page 32: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

e--I--~+-+--t-~'H++++ -H 1,,11,·-h +-,,1· :·1 :1 ~+_\L+_;I : i- 1-' I . !' I : 1··:·1 !.. r-' - +~--L

...: ...2-,-- r-I +·1· .-~ .----'-----,- .' . TMCK SECTIOH ~4 ' i: I. -,'1: .: -,-- ---'--.---- - ..: . ;. • , COl'lTINUOUS CONCIlETE BEMSrt ' ' T ' ; , .,! f-,- "'r- -r- _..L ,.. -- -, - -_.. - ------. .. _lIEST r . , .\ : " , .- ~. --',---.- - -r-

Tf i -+~' -:- ' ". I

L ··1-- L .. j __~L~. . L .·-it --j- "-i'- iJ ..... I" : I .. , .. i ' c- --1-h- .f--L. "-'--~ ~I ,.' i I ., i ' ': ' __ ' . " '"

.C I-·-c--r-~~,-'---ri-H- -~-...;_.. -t -'-"1'-~' r' ,- .·f ',. i I .,+J '-C .. --:- r !.+--..----~-~~. -.~ iT-+-

II -

"

iII

-+-L'++++-I++.-q--t.+-+-JI I I I I I+-~ -~-J. ,~·H-++++ I I I, I I I I I '-+-+-f(-.in) ~ ·-I---J-·- I

I I III 1111 I: ~¥~i

DESCillPTlOll

Heavy pODj>in& (to top of balla...)

Spot raise aDd lin. (udnS tlllllper)

LDc.at1OD. of ViS test pit

LoC.atlcm of built 1n lDstr\Jlllll!l,Dtatioa.

Nortb rall

Soutb rail

SYHIlOL

N\MI\

V

HN

.s

.~~~E!WfCE~-+~+++,-J-diH, .. t=-~+-!- - ." ---- .. c+_~ i--·t--Fr=FFttlTtTF-~--f"" -~

, - I : r - I '\ r ~ -I ~+ l '++1'-1'1' ''IIr:'¥F' '" I 'IrFbT I ' '-"-'1' I'T • r '-1' I l' r fT--.-r.-rT r ' I , rr:l-I--~--+ ·-I-I~-I--- --c+ ... '. -·i-·-'----1-e· -c- -+-r-+ ~- - ·+-~-·_...LTf--I---r- --,-. ~ - ---t---I-+- -+-~

~~IWI 1I0.~!W I 70. 60· : 501 i '40' 30 i I 20 ' 101 I I BUM NO.i ~ I I : I . . I I i.1 i I -pJL __ I- _+- _, ·Lf--L '! i ~ f i ' I Ii. I, I ~

.

STAT10IL8~.54+20 I I I 53 ' I 152 . I~+ T r 50· 49 I, '. 48 ' ) 41 ,. 8546+20. STATION_. -J-.l....l+--J--: ' 1 I I I ,I ~~ . I " I .~_l I . 1 I I ~ _~I--+--+-+- I 1 I I liT'·

IEGEliD " ,'1 T I FIELD lIl1TES (~-. G. HcLellD. recODtr1P. 6/23/7 5) I I I Ii_I, I . ..L ' I I ! I I I

I !-T- - _. -I '-r 1-- - I A. Balb.. g..... rally aubaided n.ar beaaa. '( I .

+__ T '-t--- .. __ ...I .. : ,B. Balla.. a..nding a"ay frOlll beall "" nortb ddtl. ::-+---t, 'I 'i'lit c. Evid....c. of PlIIII'ing tbroughout aeoti"". notably at joinu. c-t- ~--j-- I i I I· I

--~-~l'- ...L.1 I-~U- i D. Structural diotreoa (spalled joints. cracUnB at joints). -J- : I I I I I! ! I I I I I I I I I I I I I I I I I i I- I I I r 1- I ,- I I I i

b/;~;~~.=r-~! N:+'~f-~+j' .. jT~1'- ,- -,' r-';' ~~+. .' ,I iT I I' I ! i~_,6/16/75 1-. '- ..-l \ ,: ' ,I ·-t rr "', ., -' .: t--. I6/5/75 i-- . "--+-+-- . , . I. I.. L--t-'-: " ' , S i: ' -i' ..... ,~.

6/41

,_ __, I ' ,,1I"S r-' -- . I...... I, '."'10.' 'I T': .. 75. ........., i ••-.' ~;'l': r, ..:-.~.. - ~. '-_. - '""" . i' ~ I ~ ; I. ; :_ . ; _. .:"". '._ . , . ;H I! II!;.I, I , 1e+-H

1 5/2~/15 ._' '4. i. _~- , • ' I ,l I-j ---I- --.'

~ 5/22/75 ' t-i-, I f--. .. l' ' I '~_:4/U/75 ,---;.: I _: -: :~: I .•J!" , I' j----c -r ' iT' --T ~- -r \ . f : If I 1,4/11/75 I ' IT· .......... __ __ i. ' ,'N, I ': I I, T TT

___ 4110/15 I I ! I :' ," ~ -r-+~ f' ,-0- r Ii T 'J 1~ 14/4/75 i '1'I(-+-;........L .. -W f---l~U- i ' , , ' I -

3/31/75 ! ' I " T '" 1 ! I I" " : 1"'-, IT '3/26/15 " , .*....·r i"! _L -+ ' : ITT

:._3120/75 ....A~- ~ ,r...,-, Til it- , . .• I i3/11/15 -!'!"!' ~ i' T' I· i . r- T I I. I ,: "T''''i''._'''~ ",' I -Ie r~ -eTC +-,. -!~+.~ +,~. t

I, ,,:s +! I 1 I L...LI:.t-- I i.1 -I I' , , ,T'- TCJL I T -l---l' , ' '+1' [~ I : i -,-+-r--- l- --+ _1 ' .iAOi ITlJ ; \ I l I I" . ---t--IH

I--'0\

FIGURE 9. SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 4

Page 33: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

I-'--J

FIGURE lO. SUMMARY OF ATSF MAINTENANCE, TRACK SECTION .~

•• il,.il:'l'EI'''

.,::§,t'tta., •. I.'

m"~" ,. --:."~-.:._~~_~: ..e-----_~.Reproduce& from .' ,hestavailable COpy.

r_-=---'-"" ••••• - - ~ .

Page 34: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

. 1 TTl' . ;. . ., . . ~nT' TTTTTl I rJ t .; TIIAQt SECTIO~ 17

I, I I 1 JJ.. J 1 CX1lITlIlUOUS COIICIII!TIl BIWIS '-+--+++rll ! I,:" I _WEST

P=

T:TTT I

F' 'II Ii

i,

rI"

~'-,

t;1III ' ' '.. :.• ATSf t,.!,!.11.1·1!·1ttuttjtttDjttt-H-++t+-H-t-++ft-H4+++-H---+++t=t=1=t=++r+=~=+4+:r=t=d~l=ttjjj"IlAl~. I I I Ii I I ·1 '1>111 J

f-'CP

'i·' 1:1:1111'11 .TTT13 ' ' I I , Ii III.. ,,6/28{75.. . r .. .. i KIA,' • J .' I: l' "T 1 If' I : I I I II

.5/11{J.l "jq :: .; III!.. (TiihtllD 8&8a roda). . I .. • I I •I .1 1.15/20175 I~I'-t.. ::l1li ~"'" ~(JlihF89a) I~

.5/19(75 ", .. ',' •. ,,, ~;r

.~:::~~~ .. ~.;;,~-' •• ,1- ; •. ••..~ I~l . '.Ia.. III . I ... , : ...• . .:. , ~,-:~5/UI75 ..., --, • '1! . I lJ fSharp d1p' !I J

.;,5/9175 .c, J .... "'::' . '.::' I., .... ,botb r&1lA···' .. 1.: I '1 ]:.: .5/8{7~ "'" c (alulr' diP)if'T -" (ubar' dip»' I I'],. ..• 1 L l-

e~ \i~!lir"~,;;j;;: ~ ',;,~" "::,~,:::, ,,';' ,.. i,~~~ c. • cc • "OS', ',-, :~l·.. 1. y:.

"1· I·

.a"1....

:n::-r:"

Fl'

.;. ::.:..: -==.LocaUoa of bullt in 1Datr_Dtat1oa

Soutb rail

Loeat1OD of IllS ta"t pitvH

E'., ,,~fPY1fffifitT:t1~'21'CT" 'f''; ~." .... 'r:!;:~':::H':: ::::': '::>:<~'~":';:':.--:c~·:.rdih:H'·~~ LlGEIIll,••. .iJc1dHiI'Jllll'II.;I .. III l'I:l'hj"l~!f.J'II:tllllg;:~ SYllBOL IlBSCiIPTIQli ":. i,'. • i' rULIl HOTES (r. G. ""Lem. recoau1P. 6/23/75)

I:~ . r.-ping (partiaUy foulad ballAn).I" .". •.•• .:" .': :~.:: i'; ',: • Ii A. BaUut aubuided at 8571+<15.~~ - lIeavy PUlllPiDS (to top of ballaat) .••--,pl"": . .. c'.. , . c. h-' '. ., B. Subsrado p_1DI at au. 8571+25.~~ --c.;;, .

' . I'VV'\ JadriDl ad t_inl ,. ..... .,' .• -- L" , __ ". C. Spallad joint with p_iDI iDtO joiDt at 8512+55.::-- '::.: :.' • «'" __ r . 1'1:;' '1:_ 'J.:

Ii IOl'th rail :~; !;i; ~~ ;':- -;", ;;r.. _:' ;'i: ~.:::;.~:..:.! :!~:.;! ~ D. P\DP1D.1 ad aub81deDce at 8.57>+61. ~1::;t;l;-:.::

,~ ... R~ :-"& ~lS:~:~~ '. ,,':~' ;'~ ,'! I·L~~~r~;~~ .. ~Q:':'~·I~~t~~'1~~~t~:,~,~=,,,,~,altn ru....

FIGURE, 11. ' SUMMARY OF ATSF MAINTENANCE. TRACK SECTION 7

Page 35: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

I-'\0

"'-': !'" ,'0' ,~, "0' ,. "if "" liflj'O'l:" ,," Fm~~I"o'L:l'" "" :,;i .. ," ,," . ,~.,: '.1 ~L'~L· .T' ·cT:T"bJii.±." i:; ,:,:r::H~;:J~'tCT", ':::['T80·'£" :~. :.. '~ ~~ ::: . '. ,<e' :.:: ,,':' ., ~ ~'~ .". :~i iii' .~ "ii ::" ,." "i '!;i~ ::ii,',LI::f:"i': :.: ":'flo". ':Il~:U!mi·iiL'; ::,'t4q::;II:",j::::h~iHJ )1, . ;IJI I . "~{::.lrl:m:i',~:"r.:l'''lct$f':~~''-(:':'!': "~C€E' : .. ,.~ . iii, ,$~'i' ..',. ~..';, ."'i ::;, :..:: :" 7'iFI'c ' if > iii, ,iii ;,,:iP.I

~ r:':~~":'~~~~fDlS:T~OB; :;:1;:' ii': i='! ,n, :;~~:,' "'~"" ,;~;,! L~ ,(~:$~~~ti~ '~~~::~~~.~;'G':'=~~' re~":tri;.' ~~~lis)::1'l"k ,'" ,"::: :;:

mi " ' _ a••..,. p_iDa (to top of bellaet) ::: l' , ;:1, ;, .. "iIi: 11 B. Sent. Fe - <lUi iDto • ubsre4. IIDd fooad it Ura.

",' N\I\ Spot rei.. IIDAI Uu (uaiDg tuper) c"~' :~' .. iii-:, ·.;cc " ~ ~ ~.,: ',': :':: C. Illdic.ti... of ..... b.llast plllu:hiDg iDto .ubgrede .t _c.. 8S8l)+i)O (ven,. . .·:,,'i,;~ "i V Locatioo of lIBS teet Pit':" ~'; ',c):: IIDAI of .."tloo). ',',::

H Locat1. of bailt 10 1DatrUMDutioa ! j;:~ :1:: ~!:T .;': i~: ;ji: ;::: 1::_ .~I :;;" ;:;: :~:i i~: j' ,!.. Som fiDe vb1te particl•• OD tie. (aea-r t1e _d8)~ .. ... :_: .. ~ ~ .. , :~.

~~~:~~Il '~U:~7~iL~t~;~f;.I·t~:j~~~;~;:;'~':' ;; .;i .....::11:" ~' 0;:; ..~ ',~ ::'~< ::1: .•~.' "#~;+; ,2.•." "::1 ......' :.~~~f:;~O~i·3··;·i.j:,~i:,.L, j::lJ'1!'ttI'S1'444.:,:+:I:';!'illiii;Wini i!W::lrl[' ':.,::. ii'iii:J :~, '< ",.J:.:, ~,'t;jiliilil6~,~ci'~':, ::ill ':'~ir,l' ':.,'1]' .,i ,i· ",:, ~, ;:c.", .., "c '~El~+'~:':~,'I" ,.:,: ::l~±,

FIGURE 12; SUMMARY OFATSF MAINTENANCE, TRACK SECTION 8

Page 36: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

! '

:!':

,.:tho:

::::L:[:il

'fii:'

~

,

.i:d'"

m

·Y:IL

1

'1,+4::., .. ,.. h'_

_:::;I~t.:=f;~£::

·1··,

..•"",,:1"',.

I

I'

'1·-"

:~r;:K~

[:,.

'I"

:i:

"[;1'1: ....';

I"

,"',..I

i'TF

...,:::II!:l'

'1

I 1>1'1·

rlpc 1I• .c, ,co. c~",' ,

1

I

I' '

:1,'-·

:~h~:_II·

I

~

I

.h i

,I:L

',!,'"

"",.'11

1-+1-:.'. ','rt+, 1<,f:TT

·1: I

"

'­'1

·''::I.L

"

,"

,ll",

"·,t:I:::

·,JJLLI

"TI:'~:

"':'1

"rn-'

,I

. I: 11:':":; I:; i~ I. ;; -•. -

'-'~,4-l'io'

,'il~

,Ii:',!:"

--=JI~jiJ

=-- ~ -

,lkUA::l:l :ITr

'.Ii:·

-VIST

;.~;I:j :_ I :l.

p

,,44i'#i4

:+':1-'

,_,. ..1 ,VI}:J

1

:m~:

~J""

<I:br

hJ TIACI: SICT1011 '9

'lVOOD nBS, 19" SPAClIll;, CllIITIOL SICTI(lll--J-:~l-+-++-+++-+44:'+-44:44j~F~P~¥¥¥¥~f*~~

~

:'1>:r,:--:o+.

4

, 'LL~_

"J'R:E;."".

'-",::U~, '

C:I:;:li: l:

11;':':.

;j::t.:..:..:..t::;±;::.J .. :j_I;-1::..

'itlFitilil\H:E4: H.kl:{&fc:1'thl",!gl;'!:I~c:I"i,., .. ,u ..

"~"'ih~:if.d:;&~Ll.r'i:f·,-rh:;,!;~[::Lbtd':H!i!:l!:::J'c,IU'"

~~~~t];~-.. --

::-:-'"

e~

~lItqailljj~, .

~..l::p.-;:

,on

.~

'§E;,

'-~~~".

·.:illffiItt~

:;~

DlSCIIll'TIOR

Ilea.., p.-p1ll, (co cop of ballu C)

Spot rala. ad l1De (...111, c_r)

LouU.... of' VIS ceet pte

~;:~(::r::~~~~~~':::E'(:"'):,:':i. ,j:,,"'~~,~>::::;::;'}ji 1 l]llllJUjlljl}i~n,}Jj~i7iI';J@[""ftW>:·:t ":,~~: :'~ ~i; ;;1: ;,:!, , •.,T :'! ' c;: ".. ,"c :T': •• fl

~=:a-il:~'

'"Jt=J:~

--IVVV\

'V

H

STIIIOL

~",

E2:-i.=..

~",,"

)/1/1) , , __ ',' ' -- ". ,', ,,' .- '1'" ~ ",.•~' ~ ""Eli? i;;; :..,"" co., --, '""j,e: (IIonb ~alI.!",!) 11 1 '1111 '1'11 I,',1§i§3' 1 Inlllla1ae( loe cl) ., .... _,.,. --.'. .., ..., , .. ' u' .." ...'. -1-' , " J!'

4 3 POc r 110 • "011. ," 11'!iI" .",.,';' ,li, ,,- "', 'J' ,,:.r,., "',": 'i "',T:, ,if 'I' ' ' "f

=:. ~:.~~~ ~,....,,~:: 0 ~ ••• ~';~~~~::;;3~,~'i~·:!,":~i:~:i(:'~·,L~~:~;:~:'.[......n",,:·~·~··~~.~~\'.~'~:

1::::-

f\)o

FIGURE 13. SUMMARY OF ATSF MAINTENANCE, TRACK SECTION 9

Page 37: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

would take place in three steps, as foll.ows:"

1. Installation of vertical deflection sensors by the WES inTrack Section 4 followed by dYnami~ testing under captivetrain loadings, per MITRE specifications.

2. Static load-deflection tests for MITRE at the same location.

3. Posttraffic impedance tests of selected track sections for'comparison with earlier (pretraffic) WES impedance results.

Items 1 and 2 above were to provide data needed to refine a finite

element analytical track model developed by the MITRE Corporation.

Item 3, posttraffic impedance testing, was to provide a basis for assess­

ing traffic-induced changes in track system stiffness through compari­

sons with pretraffic results. In accordance with FRA wishes, post­

traffic impedance tests were performed only in Track Sections 1, 2, 3,

4, 5, 8, and 9. The inferior ~erformance of Track Section 6. was attrib-. , ,uted to the ballast stabilization (elastomeric polymer) treatment used.

The FRA did not desire further study of this stabilization technique.

Accordingly, Track Section 6 was not tested. Track Sections 4 and 7were physically alike and had shown similar responses in pretraffic

tests, so retesting of Track Section 4 was deemed to be sufficient for

postmortem purposes.

The FRA also desired that posttraffic impedance tests,be carried

out under conditions similar to those existing at the time of track

failure, i.e. subgrade pumping at the test 10cations. 8 In the interval

(April-October 1975) between track closure and posttraffic impedance

testing, the subgrade was expected to dry to some degree under the

effects of the summer and fall weather. Consequently, pumping condi­

tions had to be re-created by some expedient m~ans. The method adopted

included multiple applications of weather to the preselected test loca­

tions and repeated passes of a captive train to stimulate pumpjng of

the subgrade. The captive train, consisting of an engine, two hopper

cars, and a caboose, was provided by ATSF. This train was also used

for the MITRE dynamic structural response tests conducted in Track,

Section 4.

21

Page 38: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

.Ballast and Embankment

The embankment and ballast studies were to be conducted during

Phase II of the field work, which was tentatively scheduled for April­

May 1976. The principal factors which influenced this timing have

already been discussed; however, it was also reasoned that testing the

embankment materials during the spring of 1976 (when surface water con­

ditions should be similar to those ~xisting at the time of track closure

i~ April 1975) would constitute an added advantage. Implicit to this

reasoning was the assumption that softening of the embankment surface,

if any, was at least partly related to the presence and cumulative

absorption of surface water. One such instance of surface softening

from water absorption had occurred during construction of the embank­

ment. 6 For this reason, an effort was made to protect the top surface

of the completed embankment by adding a 6-in.-thick, 3 percent lime­

stabilized surface soil layer and a thin (sprayed) asphaltic membrane. 6

These measures were taken in 1971 during final construction of the

embankment.

Verbal reports and field observations had indicated that KTT sub~

grade problems were confined to the upper region of the embankment,

hence. this was a logical focal point for the planned embankment soils

investigation. The WES and FRA agreed that the investigation should

address the following major areas of. concern:

1. Existing structure-ballast-subgrade conditions at locationsof interest, with particular emphasis in the region of theballast-subgrade interface.

2. Variations in embankment material properties and strength asa function of location and depth in the ·embankment.

3. Uniformity of embankment properties throughout its length.

4. Differential settlements and related phenomena resultingfrom differences in track structure geometry and loadintensity.

5. Other pertinent matters, including primarily the site drain­age conditions.

Items 1, 2, and 4 above could best be dealt with by staged trenching to

a depth of 3 ft into the embankment, but time and money constraints

22

Page 39: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

would necessarily limit the physical size and number of test trenches.

Other more cost-effective methods would be needed to provide an index

of embankment uniformity (in terms of strength versus depth) in areas

outside the test pits. The Dutch cone penetrometer and in situ vibro­

seismic methods 'were well suited to the purpose and were selected to

satisfy item 3 above. Vibroseismic results would also be compared with

earlier (pretraffic) results to determine traffic-related changes in

embankment elastic moduli. Item 5 above would be accomplished using

photographs and phYl?ical (i. e. survey) measurements as needed.

As finalized, the ballast investigation was to consist of material

property,t~stsoribag's8JD.ple~ obtained beneath the structures and at the, , '

ballast sho"uld~r in each test location. Gradation curves derived from., '. .'

·<.!hn':.ges.i",',ef"'-,_.r<do".'m:~J~~'W:91.1ld.;:'it:~a'§\hoP~d~:i.ndicate the severity of subgrade pump-...' v:a,riat±oh~s,:{h"the8.mountof fines present. Classification

tests on the fines pa~sing a'No. 200 sieve would identify the ,source of,

the pumped materials. Gradation comparisons between shoulder and under­

structure ballast samples, would also serve as indexes of any ballast

deterioration under traffic loadings; Since part of the original struc­

tures design criteria were based on results ~f 30-in.-diam plate bear;..

ing tests on'- the embankment, plate bearing tests were also to be run as

part of the ballast-embankment investigation., . .

Each embankment trench or test pit would typically consist of a

3-to 4-ft-wide'staged excavation that would span the structure and one:

shoulder of the embankment.' In an effort to identify zones of·either

II good ll 'or "poor" performance ~ 'locations of the various t.estpits would

be determined from Santa Fe track maintenance records (summarized in

Figures'6-13). Zones that pumped and/or required relatively frequent

maintenance were termed to have poor perfqrmance, the opposite was

termed to be good performance. First, ballast samples would be taken;

then the ballast would be carefully removed by hand to expose the

ballast subgrade interface (the 0 level of the test pit). Depth incre­

ments for data acquisition in the test pits would be at 0, 6, 12, 24,

and 36 in. below the ballast-subgrade interface. California bearing

ratio (CBR) and conventional field density and moisture content tests

23

~,

Page 40: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

f'

would be performed at each stage of the'excavation. Two undisturbed 'box

samples would also be obtained from each pit for later laboratory test-,

ing. Locations for data acquisition in the pits were chosen to typ~fy

conditions at, for example, heavily stressed (beneath rail seat of ,ti~),

moderately stressed (center of tie), and relatively unstressed (center

, of crib) areas of the subgrade. Conditions in each test pit would be

also documented with color photographs.

Built-In Instrumentation

The embankment was built by Shannon and Wilson6 (S&W), who also

installed the built-in embankment instrumentation. ' The PCA installed

top of subgrade pressure cells, instrumented the track structures, and

was responsible for all phases of data acquisition during testing,(including the S&W instrumentation).

There had been three major data acquisition periods in the brief

life of KTT; but part of these.data, notably moisture measurements and

some of the final readings of the vertical extensometers, were thought

to be Unreliable. 9 The FHA desired an evaluation of the embankment

instrumentation to include its design, function, calibration, and condi­

tion. This work was to be carried out in Phase II of the field investi­

gations. The WES would base its instrumentation evaluation on sample

calibration readings from selected arrays, excavation of selected

instruments, and a series of recalibrations performed on the excavated

instruments. Pressure cells, vertical extensometers, and moisture and

temperature cells from the main instrumentation arrays6 WOul~ be studied'

in this way. In addition, most of the Carlson pressure cells, .installed

by PCA just beneath the ballast-subgrade interface, would be exposed for

visual inspection. Finally, both data acquisition procedures and signal

conditioning e~uipment would be reviewed. Results would be used to

assess the validity of data obtained.

The Test Plan and Schedule

The KTT postmortem investigation by the WES was structured to

24

Page 41: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

include the preceding studies. Figure 14 is a graphic ~ummary of the

test plan that also shows the locations selected for~esting. Figure 15

presents a chronological history of the KTT, including the timing of the

postmortem investigations.

25

Page 42: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

" ...•

8662+20

P8562+00

I

p8560+00

I

p p

8558+00 8558+30

TRACK SECTION 5-CONTINUOUS,CONC. SLAB

V.M.T8558+20

P P P P P8571+00 8573+00 8574+50 8576+10 8578+00·

I _ I I , I

8554+20-1 .

I TRACK SECTION 8-CONCRETE TIES-21" C-C I8581+11...J I L8589+17

V.M.T8581+10

P P P P8591+01 8593+00 8594+83 8596+31

I I I I

8545+00

P8554+00

I

L- 8527+53

p8527+00

I

C-t

P8544+00,

I .

p

8525+00

V,M,T8542+49

P8551+60

I

V.M.T8524+75

.p8523+00

V.M.Te540+l7 ,.r

P8550+0C)'

TRACK SECTION 3-CONCRETE TIES-24" C-C

P8521+01

P8538+00

I

p p8546+45 8548+00

I I

p p p P8529+00 8531+00 8533+00 8534+96

I I I I

J TRACK SECTION 2-CONCREI'E'tIES-21" C-C I8529+00-1 , I L. 8531+00

V.M.T V.M.T-8531+60 8535+16

p p

8540+00 8542+30I

,8531+00-1I\)0\

TRACK SECTION 4-eONTINUOUS CONC. BEAMS

8546+20 -I L-8554+20V,T

8551+50M

8553+85

LEGENDSYMBOL

PVMT

-

DESCRIPrIONLOCATION OF DUTCH CONE PENETROMETER TESTLOCATION OF VIBROSEISMIC TEST

. LoCATION OF MECHANICAL IMPEDANCE TESTLOCATION OF TEST TRENCH IN EMBANKMENTLOCATION OF MAIN (BUILT-IN) INSTRUMENTATION ARRAY

FIGURE 14. GRAPHIC SUMMARY OF THE WES TEST PLAN

Page 43: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

1911

1912

1=, Embankment

Pretrafflc

construction

vibroseismic testing of the KTT embankment

I\)-'.:l,

1913

1914

1915'

1976

1977

k APproximate period required to install track structures

Pretraffic impedance testing

Ir-First traffic~shutdown to repair pulled out anchor bolts in nonconventionaltrack structures (track sections 4, 5, and 1)

Approximate period required to replace all anchor bolts in nonconventionalstructures

~KTT traffic period (corrtinuous from Dece~ber 10, 1974 ~ April 1975)

~Final shutdown of KTT

~Phase I KTT postmortem field investigation (structures and impedance testing)

----.r-Phase II KTT postmortem (ballast and embankment studies).·

.-; ,

"

FIGURE 15. CHRONOLOGY OF KTTEVENTS ,INCLPDING' TIMING OF, POSTMORTEM" INVESTIGATIONS.,

. ~ .

Page 44: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIELD INVESTIGATIONS

The KTT postmortem field investigation began with static and

dynamic testing of the KTT track support systems (Phase I). This work

was performed in the period September-October 1975 by a WES field party

(a project engineer and two technicians). The MITRE representatives

were present during part of this time to observe the static and dynamic

tests conducted for their purposes. Upon comp~etion of the Phase I

work, the field .party returned to the WES to document these results and

to prepare for the Phase II field effort.

In February 1976 all parties scheduled to participate in Phase II

work, consisting of studies of the ballast and embankment, had been con­

tacted to coordinate WES planning. These participants included ATSF,

MITRE, peA, and S&W representatives. Phase II work was scheduled to

commence on· ~l April 1976, and final planning by the WES and the ATSF

took place during a 24 March inspection trip to the KTT site. Findings

during the inspection trip were as follows:j ,

1. Th~ test locations previously selected and marked by the WESwere in excellent condition and showed no signs of disturbance.

2. The KTT concrete ties and rails had been removed as requiredfor Phase II testing, but their removal had so disturbed theballast between test locations that WES vehicles could nottravel over it.

3. The ATSF did not feel that. the nonconventional track struc­tures coUld be removed prior to arrival of the WESfield party,because contract negotiations for the work were then inprogress.

The ATSF agreed to arrange for a motor grader to level the ballast;

however, it was apparent that removal of the nonconventional track

structures would have to be arranged to suit circumstances. In view

of other WES commitments, which precluded reschedul~ng KTT field work,

. the only alternative was to remove the structures in stages as WES field

work progressed. The ATSF also agreed to secure the necessary heavy

equipment and to provide other assistance as needed so the Phase II

investigation could proceed as scheduled. Although plans had been made

for long-term protection of the foundation materials beneath the

28

Page 45: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

structures, removal of the structures just prior to testing minimized.

this requirement. Hence, only a weighted tarpaulin was needed to pro­

tect the test area from environmental changes in moisture content while

testing was in progress. The nonconventional structures were continuous

reinforced concrete, and jackhamme~s and ~tting torches were used to

sever them for removal. Each severed beam or slab section was verti­

cally lifted with a 60-ton crane to minimize disturbance of the ballast

and foundation materials. Testing was begun immediately thereafter.

The Phase II field work was performed in April and May 1976 by a

WES field party (three engineers and nine technicians). The PCA, MITRE,

and S&W representatives observed the work in progress during the week of

17 through 24 May. An ATSF representative was present at all times when

work was under way at the site.

Structure Testing (Phase I)

Structure testing began 16 October 1975 with the instrumentation

of north rail Beams 14, 15, 16, 17, and 18 in Track Section 4. Vertical

ext~nso~eters were installed at the midpoint and at one end of each beam

to measure absolute deflections of the beams with respect to the lime­

stone bedrock. In the dynamic tests, absolute and relative motions were

measured using film potentiometers. The dynamic and static test con­

figurations specified by MITRE are shown in Figure 16; detailed descrip­

tions of the installation and dataac~uis~tion procedures are given in. ~ '~ ..; "

Appendix A, Volume II, of·thisreport. Data were acquired for 17 passes

of the captive train at speeds ranging from 2 to 55 mph. For the dyna­

mic test series, 13 data channels were recorded, including absolute and

relative motion of the beams, rail accelerations, bending strain in the

beams, and ,peak particle velocity measurements of the rail and beam

motions. A second series of structural tests, consisting of three

static load-deflection tests on Beams. 14 through 18 in Track Section 4

was then conducted. Dial indicator measurements of relative and abso-

lute deflections of these beams, as well as strain gage measurements of

29

Page 46: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

North Beams

Reference rods Deflection gages

/

I P u,- z--p - P 61""'" __ '" • "pv'" «ole!' Ballast

6' Approx. Protective sleeve

/Residual clay

LtJo

Legend

~. Relative deflection measured between beams

~ Absolute deflection referenced to limestone bedrock

Note: Dial gages were used to make static test measurements. Inthe dynamic tests,deflection measurements were made usingfilm potentiometers and analog signal conditioning and tapesystems.

Limestone

FIGURE 16. TYPICAL DEFLECTION MEASUREMENT CONFIGURATION FOR EACH BEAM IN THEMITRE STATIC AND DYNAMIC TESTS, BEAMS 14-18, TRACK SECTION 4·

Page 47: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

bending strains induced in Beam 16, ~ere recorded for each load incre­

ment and decrement.

The above. static and dynamic data were transmitted to MITRE in

February 1976 and have since been used to refine an existing analytical

model of nonconventional track structure response. 10

The final postmortem structures testing consisted of WES post­

traffic mechanical impedance tests on the track support systems in Track

Sections 1, 2, 3, 4, 5, 8, and 9~ As planned and prior to testing, an

effort was made to re-createsubgrade pumping conditions at each test

location by the application of water and repeated passes of a captive

train. Despite up to 600 train passes and the surface application of

over 16,000 gal of water to some test locations, surface indications of

pumping were achieved only in Track Sections 1, 2, and 3, although some

traces of the onset of pumping were oDserved in Track Section 5.Detailed descriptions of the pretraffic and posttraffic·impedance

investigations performed by the WES are available in a separate repor~~but will not be repeated here in the interest of brevity. However, a

ranking of KTT track systems according to their initial dynamic stiff­

ness, as determined under posttraffic (postmortem) test conditions, is

significant to the postmortem investigation and is shown in Figure 17.

Comparisons based on these and other pertinent data will be treated in

the analysis section of this report.

Ewbankment Vibroseismic Study

The postmortem vibroseismic study was performed as part of the

Phase II field work conducted in April and May 1976. Vibroseismic test­

ing was performed at each test pit location (Figure 18), according to

procedures that are documented in the literature7 and described in

detail in Appendix B, Volume II, of this report. Volume II also con­

tains all of the original data acquired in the study. Postmortem vibro­

seismic results from each track section tested are summarized in Fig-)

ures 19 through 28. Each figure contains a plot of Young's (E) and

shear (G) moduli versus depth in the embankment. A summary plot of all

vibroseismic data is shown in Figure 29. The E and G moduli curves in

31

Page 48: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

•.-.' ,

• 3A

.*•

.3D

.2B1

1• 2A

~

"".......,Q

106M.~

lDlDII~ .**fHfH

""~lD

()or4

~

~'d'1"'1+J IpSor4C

H

1 2 3 456Track Section

7 8 9

. "" - --" ---- -----_._-------- _.,~ -- .-

-Not considered to be representative of performance undertra.ffic; see text.

FIGURE 17. SUMMARY OF INITIAL DYNAMIC STIFFNESS RESULTS FROM POST­TRAFFIC IMPEDANCE TESTING

32

Page 49: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 18. -TYPICAL VIBROSEISMIC TEST CONFIGURATION

33

Page 50: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

32 40

MobULI, io3 PSI

O 8 16 24O~----""""--~--T-----~---'-----'T""""----"'"

o

\'oI1III

J

---- _....

• • SHEAR; G PRETRAFFIC0- --0 . SHEAR, G POSTTRAFFI.C• • . COMPRESSION, E PRETFI.l\FFiC ..0- -0 . COMPRESSION, E PosnRAFFIC

5

3

2

4

:I:I­0:.Wa

6

7L.-------.L.-----""----__-L. ...... .....

FIGURE 19. PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 1 (KTT EMBANKMENT)

34

Page 51: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

------

MODULI, 103 'PSI

0 8 16 24 . 32 40.0

• • H R, PRETRAFFIC

~~. SHEAR, G POSTIRAFFIC

• • COMPRESSION, E PRETRAFFIC

~-o COMPRESSION, E POSTIRAFFIC

~ \0

~ \\ ,~

\f2 '\ 0

\,\I \

3 I ,I- el 0 I~

:I:, ,

I-D.

~ ?I&.l0

4 ,'I, I

L I'5 l j

6

7'------........-----------~------L..------J

FIGURE 20. PRETRAFFIC ANDPOSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 2 (LOCATION2A, KTT EMBANKMENT)

35

Page 52: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

6

------ ------

MO,DULI, 103 PSI

0 8 16 24 32 400

• • . SHEAR, G PRETRAFFIC----

I>-~ ; SHEAR, G POSTIRAFFIC• '.1 COMPRESSION"E PRETRAFFIC0-~! COMPRESSION,E POSTIRAFFIC

~~ \\ \\ \

2 \ \c\

0

\c , 0 \I \

3 I... c I 0~'

I-,::I: Il-

IIl.loJ

ICl

b4 /0,I I1 I

5 I, I~ cl

7~----""""----""""'-----""""----"""""---_-.J

FIGURE 21. PRETRAFFIC AND ,POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SEC'TION 2 (LOCATION2B, KTT EMBANKMENT)

36

'".'or .

Page 53: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

" "

40

,MO~ULl, 103 PSI

0.8 ' 16 , 2 4 ',~ 32 .;'6 ,..'--.:......;-'---"r------,--'--..,....-,...------r-~'"""-----"-r__----_,

' ... :

,.'" ~ , "'c • ':;:sHE~R;g'PFtETRAFFIC --- .",. ~~LsHEAR;GeosTTRAFFIC

" , , ',', '."" ' "~ l·qf.'M~F!~SSI0N,E PR.E,TRAFFIC,. .~~,Lc9,Mp,~ESSION;:EPOSTTRAFFIC

.'

", .0 '.,.0,\ "'.

S,\0,\: \ 0.

\\\ °01'r.,

':~

\"

\\\.\\\\\~"b

,,,"'~

, \ '

\\\\~

c

6

5

3I­10. "

:I:1-,CL'Iol0'

'4J., - .

71...-------,........-----,----I.-----, ..... .....L. --J

. . ,

FIgURE 22. ,PRETRAFFIC·ANDPOSTTRAFFIC PLOTSOFELASTIC MODULIVERSUS :DEPTH, TRACK SECTION 3 '(LOCATION 3A, KTTEMBANKMENT)

37

"

Page 54: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

7'------:---....L...---_....L..----......L------l------.J

FIGURE 23. PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 3 (LOCATION 3B, KTT EMBANKMENT) .

. 38

Page 55: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

4032

MODULI, .103 PSI

16 248. 0o ;.......---.....,..,..........-----"T"'""-----.,.------r--------,.

2

3

" o/Y-OgJ,\C\\\\~0\

• • rsHEAR, GPRETRAFFIC~ --0 • SHEAR, GPOSTTRAFFIC"• • COMpRESSION, E PRETRAFFIC .

I "". " "0--0, COMPRESSION, E POSTTRAfFIC.

4

5

6

. 7 '-- -.... ..L.- --.A.,........ ...J.... ---'

FIGURE 24. PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 4 (KTT EMBANKMENT)

39

Page 56: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

MODULI, 103 PSI

0 8 16 24 32 ' 400

---.---_. - ...~-• •. 'SHEAR. G PRETRAFFIC

! 10----0 SHEAR, G POSTIRAFFIC

• • -COMPRESSION, E PRETRAFFIC~-o . COMPRESSION, E POSTIRAFFIC

~- ~, \ • •~ • •

2 \~ \ 0

~' ?, '\3

, \I- ,

~II.

1:r \I-~

\ \wQ

4 \ \, \\ \\ \

5 \ \\ \\ \b \

06

7L- .L..- .L..- ...L-... ...L-... --.I

FIGURE 25. PRETRAFFIC AND ,POSTTRAFFIC .PLOTS OF ELASTIC MODULIVERSUS DEPTH, ~RACK SECTION 5 (KTT EMBANKMENT)

40

Page 57: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

~ • J

MODULI, 103 PSI

0 " 8 II 2~ . 32 400

• • SHEAR, G PRETRAFFIC0--~ i SHEAR; G POSTTRAFFIC

• . • ,. COMPRESSION, E PRETRAFFIC •. C\. ". ~ --0 COMPRESSION, ~ POSTTRAFFIC

~.

\~ " 0b.. 0

~ 0\C\\"

~ 0\2 \ \ •, \

\ \, \3 D I 0 \l-

II. ,\

1: I \I-0. 0 I 0I&J \Q

~ ,\

I \I \

5I \I \ \I \~ !

6

7'------........----------........----...1...-------1

FIGURE 26. PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH. TRACK SECTION 7 (KTT EMBANKMENT)

41

Page 58: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

MODULi, 10 3 PSI

o 8 16 24 32 40Or---------r-----"T"'""----~------:-~------....;.,

.-----'-------'----- - ---------_• • SHEAR, G PRETRAFFIC~~ iSHEAR, G POSTTRAFFIC• • :COMPRESSION, E PRETRAFFIC9- -0 :.COMPREsSION, E POSTTRAFFIC

3I-Lo.

J:I-0. 0W0

4 C 0

• •• •

5

6

c o

7L...-----......L. ~_~___J. ....L. ___'

FIGURE 27. PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 8 (KTT EMBANKMENT)

42

Page 59: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

~OOULI , 103 PSI

0 e II 204 32 400

~

'"\0 ",,0\0 ",0

~ 0\

\ \\

2 0 • \

\6

• • SHEAR, G PRETRAFFIC[}- --0 SHEAR, G POSTTRAFFIC• • \COMPRESSION, E PRETRAFFIC<>-- --0 I COMPRESSION, E POSTTRAFFIC

7'------....L.-- .L- -.1. ....L.. ~

FIGURE 28. PRETRAFFIC AND POSTTRAFFIC PLOTS OF ELASTIC MODULIVERSUS DEPTH, TRACK SECTION 9 (KTT EMBANKMENT)

43

Page 60: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

. ,r

3224

MODULI, 103 PSI

16810O.:------.,.-----"""T""-----...----.....,

o SHEAR, Go COMPRESSION, EX COINCIDENT POINTS

cBOem ~

0

20

Q

I- ):f CDu.=i 3 l:( ~ CDI-a.. 0 0 0 0

'W 0 0O.

0 0 00 0 0

0 0CD

4 00

0 0 0

5

o

o1.6 L- ..LL- ..J...._-L..__.....L. .....

I" II :IJI~I': : 'I). I '1\1':'I'I~/WII' I C fiND l)():~II"l'l\J\li'l" LC mJMJv!J\RY PLOTS OF1':I,/\;:'I'IC MllJlllJ.1 VI,:m~II~~ llI':T"l'Il,'l'HI\CK ~1I':C~'ION8 1 'rHROUGJI 9(K'I".I' J':MBANKMI';N'l') .

44

Page 61: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Figure 29 represent average values for the entire embankment. All of~~...~~~J~.\~~~:.'\~;'~'it'~:::~. : ; ~

the above,vibroseismic data were obtained at relatively low stress

levels in comparison with rail traffic induced soil stresses, and the

E and G moduli derived are considered to represent upper bound values

of embankment strength.

Embankment Dutch Cone Penetrometer Study

Dutch cone penetrometer tests (CPT) were performed using a port­

able penetrometer. Penetrometer testing was originally envisioned as

an expedient means for assessing embankment uniformity throughout its

length, and penetrometer tests were conducted at four to five locations

in'each section, as shown in Figure 14. The portable Dutch cone pene-

. trometer used by the WES was adapted to a forklift (Figure 30) so the

apparatus could be easily transported to each test location. TWo lead

blocks~ weighing 2000 Ib each, were used to react against the vertical

uplift force generat,ed by the penetrometer. Two to three penetrations

of the'subgrade were made at each test location. These penetration posi­

tions were patterned to typify soil'conditions at various polntsof.' ~ • '" " e

interest. beneath the structures. Readings of penetration resistanc'e

began attheba'ilast-subgrade inte'rface and were. obtained every 6 in. in

depth to a total, depth of '6 ft in the embankment. Figures 31 through 33

present aVeraged CPT results for each section tested., 1n numerical order.

Figure j4pr'e's~nt~, the' averaged CPT resUlts for each pehetration posi­

tion in'theco~veJ:1tio'nal structUre (Track Sections 1,2, 3, 8, a.il.d 9)

test pattern.' Figure 35 presents averaged CPT results for thepenetra­

tion positions 'used in thenoncohventional structure (Track Sections ~4,

5, and 7) test pattern. F'igure 36 shows the mean ahd standard deviation

curves for 'all of the penetrometer data. In each figure', cone pbint

penetration resistance in tons per square foot (ts-f) versus depth in the,

embankment is plotted. The equipment and procedures used and the data

acquired in the cone penetrometer study are documented in Appendix C,

Volume II, of this report. Further details regarding cone penetration. 11

equipment and procedures are available from the literature.

Page 62: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 30. WES MODIFIED DUTCH CONE PENETROMETER AT TEST LOCATIONIN TRACK SECTION 3

46

Page 63: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Embankment. ,

DUtch cone penetration resistance, tsf

.~...r:::~Q)

A

1

2

3

4

5

6

o 10

Sec 3

40 50 60

Sec 1

Sec 2

7..----.,..--__--.........--.......-----,..-- -- --_-__&.

FIGURE 31. AVERAGE PENETRATION RESISTANCE IN TRACK SECTIONS1, 2, AND 3

47

Page 64: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Erpbankment

Dutch cone penetration resistance, tsf.

1

5

6

o 60 70 o '90

FIGURE 32. AVERAGE PENETRATION RESISTANCE IN TRACK SECTIONS4, 5, AND 7

48

Page 65: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

...Dutch cone penetration resistance, tsf

o 10 20 30 . 40 50 60 70 80 90

Sec 8Sec 9

2

1

5

6

· 3~ .

...r::+JPolIV~.

4/-.

7 ......---,,-----?--

FIGURE 33. AVERAGE P.ENErRATION, RESISTANCE IN TRACK SECTIONS 8AND 9

Page 66: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

·~

1

2

3

4

5

6

o

Dutch cone penetration resistance, taf

10

Legend

• Under rail seat of tieo Crib area (under rail) .li. Under center of tie (track l't. )

40

7 ......---,---.----r---"-'T--.....,...---r---"""""T"---r----+

FIGURE 34. AVERAGE PENETRATION RESISTANCE AT SELECTED LOCA­TIONS UNDER THE CONVENTIONAL (TIE) TRACK STRUCTURES (TRACKSECTIONS 1, 2, 3, 8, AND 9)

50

Page 67: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Dutch cone penetration resistance, tsf

o 10 20 30 40·

1

2

4

.5

6

7

• Under jointo Center of beam or slab

FIGURE 35. AVERAGE PENETRATION RESISTANCE AT SELECTED LOCA­TIONS UNDER THE NONCONVENTIONAL TRACK STRUCTURES (TRACK SEC­

. TIONS 4, 5, and 7)

51

Page 68: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Dutch cone penetration resistance, tsf

3% limeStabilized layer

• i~_ •

- ',~', .. ,'\'

. '" .~, "

. ~ "

90~.o7060

Residual clay

o

2

3

5

4

6

1

~ - , . .

FIGURE 36. MEAN AND STANDARD DEVIATION CURVES OF PENETRATIONRESISTANCE VERSUS DEPTH, BASED ON ALL PENETROMETER DATA (1235DATA POINTS) .

52

Page 69: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Test Trenching

Ten test pits were excavated through the ballast and 3 ft into

the KTT embankment. Details of equipment and procedures ~sed in the

trenching operations, as well as all the original data, are presented

in Appendix D, Volume II, of this report. Locations of the pit, center

lines are given in Figure 14. Each track section, except Section 6,

had one test pit; Track Sections 2 and 3 had two pits each, primarily

to assess pretest performance judgments. Track Section 6 was not tested

for reasons given earlier in this report~

At each pit location the track structure was first remqved by

lifting vertically with either a backhoe (Figure 37) or a crane (Fig­

ure38) to minimize disturbance of the bal~ast beneatl).. Next, 30-in~­

diam plate ,bearing tests were run at the structure-balla~t interf~ce, as

described in ASTM Method DI196~64.12Resultsof these tests are sum­

marized in Table 2. A typical load deflection curve for the plate

bearing test is sho~ in Figure 39. It c~'be seen from Figure 39 that

a large part of the total· deflection 'was not'recoverable.

Bag samples were next obtained from the ballast just beneath the, .

structur~..·(.o.;. to 6-in.depth) and from just above the bal;J.ast-subgrade

interface· (6;;; to. 15.-.:in. depth). Only. one saniple could be obtained

beneatlr!-he nonconv'enti~na:i structures, becaus,e the ballast was no more

than 2~3 in.' thick in Track Sections '4,5, and 7. A sample of the

shoulderballa.stwas also. obtained for purposes of comparison. Results

. of material piopert;tests On the ballast samples are discuss~d in the" ..

next section.'

After the ballast samples were. obtained, a backhoe was used to"remove, tl).e excess ballast to wlthin4 to 6 in .. of the su,bgrade:... The

remaining .ballast .in the test pit area was removed by hand to preserve" ,'''.,

the ballast:-subgrade' interface. Cross' sections 'and profiles of the\ ' ' I, ~

exposed ballast-subgrade interface were taken as well as photographs.

f\n example of the latter, Fif,ure40, shows the subgrade surface in Test

Pit 1. 'L'llis photograph reveals the area beneath th~ north rail; the

pronounced depressions in the subgrade were located beneath the north

53

Page 70: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 37. REMOVAL OF CONVENTIONAL TRACK STRUCTURES FROM TESTLOCATION 2A (TRACK SECTION 2)

Page 71: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

I~

FIGURE 38. REMOVAL OF NONCONVENTIONAL TRACK STRUCTURES FROMTEST LOCATION (TRACK SECTION 7)

55

Page 72: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 2. PLATE B~ARING TEST RESqLTS

Track k "Inelastic ResponseSection Location E£!. %of Total Respbnse

1 Sta 8524+75 38() 62(south rail)

2A Sta 8531+62 303 58(south rail)

2B Sta 8535tl~ 317 60(north rail)

3A Sta 8542+49 229 60(south rail)

3B Sta 8540+20 294 44(n~rth rail)

4 Sta 8551+50 217 48(north rail)

5 Sta 8558+20 88 45(center)

5 Sta 8558+10 232 43(center)

5- Sta 8562+05 317 47(center) , -~,

7 Sta 8576+41 338 65(s outh rail)

8 Sta 8587+08 ""261 52(north rail)

9 Sta 8595+33 203 31

Mean = 265 51

56

Page 73: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 39. TYPICAL LOAD-DEFLECTION CURVE FROM30-IN.-DIAM PLATE BEARING ~ESTS ON THEBALLAST BENEATH THE TRACK STRUCTURES, KANSAS TEST TRACK SECTION 2B,CROSSTIE NORTH RAIL'

-r~\".:.:/,(.-::r.,_

[~~

. \~:'

PRELOAD'

NOTE:, SEATING L.OAD = 5 PSIPREL.OAD =2.5 PSI10 PSI DEFL.ECTION =0.0315K = 317 PCI

ELASTIC RESPONSE

OV I I I I I I I I I ,o 0.01 .0.02 0.03 0.04 0.05 - -- - -- - -- - -- - .

OEFL'ECTION, IN;

5

30

20

10

15

25

iiiQ..11.1t-o(.JQ.

~0(

0•zV1

0~

PI

Z000(

0.J

Page 74: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

VICD

FIGURE 40. SUBGRADE IRREGULARITIES FOUND AT THE BALLAST-SUBGRADE INTERFACE, TEST PIT 1(TPACK SECTION 1)

Page 75: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

rail seats of the ties. An example of the profiles and cross-section

data taken at the subgrade surface is shown in Figure 41; these data

were obtained in Test Pit 2B, Track Section 2. Maximum absolute and

relative deformations of the subgrade in each test .pit, from construc­

tion and postmortem survey data, are summarized in Table 3. Both abso­

lute (survey) and differential (pit cross section or profile maximum)

deformations are shown in Table 3. However, the absolute deformations

shown in Table 3 are not believed to be accurate because (1) finished

subgrade elevations were established only at four points over the length

of the KTT, none of which corresponded with any pit location,9 and (2)

the embankment heaved differentially between 1971 and 1974 and settled

differentially under traffic in the period October 1974 through April

1975. 6 Consequently, the beginning subgrade elevation at each.test pit

is not well defined. The accuracy of vertical deformatl.on measurements

is questionable when main array deformations exceeded ~l in. from

mechanical zero, and only the postmortem survey measurements provide

detailed profile and cross-section elevations within each test pit area.

The postmortem data are·presented in more detail in Volume II.

Water content, CBR, and field density tests were conducted at

depths of 0, 6, 12, 24, and 36 in. as the test pits were advanced.

These tests were patterned to typify conditions at various locations

beneath the structures. In Test Pit 1, tests were conducted und,er two

ties and between two ties at each of the ,five specified depths. Since

there was no significant difference in results obtained at similar

locations beneath or adjacent to the ties, only one tie and crib area

was tested in the remaining test pits in conventional track sections.

Summary plots of CBR, water content, and density results for Test Pits

1, 2A, 2B, 3A, 3B, 4, 5, 7, 8, and 9 are shown in Figures 42 through 51,

respectively. FigUre 52 shows the mean and standard deviation curves­

for all the CBR, water content, and density data obtained versus depth

in the embankment.

Two undisturbed subgrade samples of dimensions 12 by 12 by 12 in.

each were obtained from each test pit for later laboratory testing. One

sample was taken from 0 to 12 in. below the ballast-subgrade interface~

59

Page 76: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

-,

1414.0j-D-'---T--.....:T----T..:....--!;!---..!;!.--~UI

E II......T~j;

IOU I

TEST SECTIOII ZI

• R/. fAST

14U.6.....~ 1412.1;:

~oJ

'"

~!!!..•

TOP OF TIES

~!!!..I

s'"j;

..J'-. NOIrT" RAIL

141U

NORTH RAIL

14U.4

14U.l L-__...L.__---1L...-__..L__--JL__..1..-:._.....J

·~..'I

.....DISTAIICE, '1.

14IU6Dr----r---;r----iDr-----~--~!...,;.-~1oO

1412J~__...L.._____Jl.-__..J.._____JL__..L__....J

CROSS SECTION UIIlER TIE m

FIGURE 41. SURVEY CROSS SECTION ANDPROFILES OBTAINED AT THE BALLAST­SUBQRADE INTERFACE, TEST PIT 2A(TRACK SECTION 2)

60

Page 77: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

. TABLE 3. MAXIMUM VERTICAL DEFORMATIONS UNDER THE TRACKSTRUCTURES (}~URED AT THE BALLAST~SUBGRADE INTERFACE)

As-Built toTrack Postmortem· Differential Deformation

Section Deformation, ft* Within Pit Location, ft

1 0.10 0.26

. 2A 0.44 0.17

2B 0.50 0.34

3A 0.15 0.24

3B 0.16 0.22

4 0.08 0.17

5 +0.06 0.09

7 +0.03 0.24

8 0.21 0.24

9 0.04 0~30

* Absolute measurements are not believed to be accurate.See text.

61

Page 78: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o 5 10WATER CONTENT, PERCENT

15 20 25 30 35 40

r I I I I I t I IDENSITY, PCF

60 70 80 90 100 110 120 130 140

LEGEND

o 0 caR~--o DENSITY

I::r---.~ WATER CONTENT

,~II~I,j

r I I I .I I I I IcaR

o ·5 10 15 20, 25 30 ·'35 40

:A I I-,.0 I //'"I ---+---r-'~ I I ",'"- I ~ '"o I I r'"

I

IIIIIIII

1,,\,,A

30

\0

0'\I\)

Z

.1:.... 20Il.1IJ0

,.

40

FIGURE 42. AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TEST RESULTS VERSUS DEPTH IN THE EMBANKMENT,TEST PIT 1 (TRACK SECTION 1)

. !.'

.--~ '~ \

. '-'j

,--

Page 79: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o s 10WATER CONTENT, PERCENT

1S 20 25 30 3S

•40

r , II I I I I IDENSITY, PCF

60 70 80 -- 90 -100 110 120 130 140

r I 1 I I I , t iCBR

o 5 10 15 20 25 30 35 40

.0 i ,Q: i Q' i i 6 I t i

10

0'\LV

Z.

Z~ 20n.1IJ0

30

40

><\

\\IIj

I/

I(",,

).~

/

~'~

// .

~~

~~

tf~I,IIIIIIA

LEGEND

o 0 CBR

O--~ DENSITY

t---~ WATER CONTENT. - I

. i

FIGURE 43. AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TEST RESULTS VERSUS DEPTH IN THE EMBANK-MENT, TEST PIT 2A (TRACK SECTION 2) .

Page 80: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

c 5 10WAT,ER CONTENT •.PERCENT

'5 20 25 30 35 40

~.

r r I I J I I IIDENSITY. PCF

60 70 80 90 100 110 120 130 140

I . I I I II I I .. 1

10

0\~

Z

-:I:~ 20IIW0

30

oCSR

5 '0 15 20 . 25 30 35 40

- . - I I I I ,

"- ,"",,'"

) If'

/{ f\

II

I

\ II

} I

\ LEGEND

I \ 0 o CSR\\ ~-o{] DENSITY

I \ b----A WATER CONTENT, \,h

40

FIGURE. 44. AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TEST RESULTS VERSUS DEPTH IN THE EMBANK­

MENT, TEST PIT 2B (TRACK SECTION 2)

Page 81: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o 5 10WATER CONTENT. PE~CENT

15 20 25 30 35 40

I , I I I I , I IDENSITY. PCF

60 70 80 ,90 100 110 120 130 140

I , I I , I I IICBR

o 5 10 ' 15 20 25 30 35 40

01 i Q i Q:. i i fJ, i i- i

10

0'\VI

Z.

1:... 2011.I&J0

30

40

-">/

'\\/

/,

//

/<,"" ",

'I1,

I1

1/

I

~

\\\~

LEGEND

o 0 CBR

~--o DENSITY

tr---~ WATER CONTENT,

l"IGlJRE]+5., AVERAGE WATER CONTENT, DRY DENSITY, AND CBRTEST RESULTS VERSUS DEPTH IN THE EMBANK­MENT, TEST PIT 3A (TRACK SECTION 3)

Page 82: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o 5 10WATER CONTENT, PERCENT.

15 20 25 30 35 40

14013012011090eo70

J J I .I I . I J, I IDENSITY. PCF

10060

I I I' . I 1 .1 . . I I Io 5 10'" 15

CBR20 25 30 35 40

01 i to:::: i .==-0 i , 11 i i

o 0 CBR

~~ DENSITY

lr--~ WATER CONTENT30

)

\\\II!

....",....." ....,,,...."

\\

,},/,/,

(IIIIIIA

LEGEND

!

40

FIGURE 46. AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TEST RESULTS VERSUS DEPTH IN THE EMBANK- .}ffiNT, TEST PIT 3B (TRACK SECTION 3)

Page 83: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o S 10WATER CONTENT. PERCENT

1S ·20 2S 30 3S 40

r . f I I I I I I ,DENSITY. PCF

60 70 80 90 100 110 120 130 140

r , I I J I J J I

30

oCSR

S 10 15 20 25 30 35 40

~ . r I I //Jj

'" //

Y/ ,

,('I

} \/

,"

/,,

\\

{ ,> ~ND

/

\ //' 0 o CSR

~~ DENSITY

\ /~__~ WATER CONTENT

\,,

~

40

FIGURE 47. AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TE$T _RESQLTS .vERSUS DEP~H IN THE EMBANK­MENT, TEST PIT 4 (TRACK SECTION 4)

Page 84: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

4035

LEGEND

o 0 CBR

G--~ DENSITY

lP---ii WATER CONTENT

30

II

~\\

;

II

I/

fIIIIIII~

25

\

)~\\

\\\

. WATER CONTENT, PERCENT

o 5 10 . 15 20 25 30 35 40

r [I 1 , 1 I I IDENSITY, PCF

60 70 80 90 100 110 120 130 140

I I I 1 , I I I 1CBR

o 5 10 15 20

o

30

10

C\0::>

Z.

:r~ 20Q.

·w0

40

FIGURE 48. AVERAGE WATER CONTENT, DRY DENSITY, AND CBR TEST RESULTS VERSUS DEPTH IN THE EMBANK~MENT,TEST PIT 5 (TRACK SECTION 5)

Page 85: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

13012011090

10

80

5

70

oWATER CONTENT, PERCENT

15 20 25 30 35 40

I . I I I I I I I IDENSITY. PCF

10060

r I I I I I I I I

LEGEND

o 0 CSR

~--o DENSITY

~---6 WATER CONTENT

")I/

{\\

105oCSR

15 20 25 30 35 40 .

oI I =1 I I I ~>....., ....~, 'T . --<J

~ f ~------".,.--­,-~-\\\\\\\

~/I

III

IL!

30

.t'.;;

.\-

40

FIGURE ,49. AVERAGE WATER CONTENT" DRY DENSITY, AND CBR TEST RES\JLTS VERSUS DEPTH IN, THE EMBANK­

MENT, TEST PIT 7 (TRACK SECTION 7)

Page 86: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o 5 .10WATER CONTENT '. PERCENT

15 20 25 30 35 40

40353015105

r I I II I I I' I. DENSiTY. PCF

60 70 8el 90 100110 120 130 140

r I I I I I·I I ICBR

20 25

LEGEND

o '0 CBR

~~ DENSITY

t:r----6 WATER CONTENT30

"'\

\}I1

",'

",'"",,,,~

y"I

II

/Jf'

,,",,",,""

,,"""r"

\\\\\\~

40

FIGURE 50. AVERAGE WATER CONTENT, DRY DENSITY, AND CBRTEST RESULTS VERSUS DEPTH IN THE EMBANK-MENT, TEST PIT 8 (TRACK SECTION 8) .

Page 87: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o 5 10WATER CONTENT, PERCENT,

,IS ' 20 25 30 35 40

r r I I I I 'I I 1DENSITY. PCF

60 70 80 90 100 110 120 130 140 ,

~ I I I I I I 1 ~ICBR

0 5 10 15 20 25 30 35 40 '

o i , Il:::: , f ~ , , ,I ",,'"

",'"

",,"

11"'"/

/10 t-- \.

\/

/

/p-"'I "f-' \ "~ ",/

\ "X ' ,

... 20 "Q. ,/

lAJ

),/,/

0 ,I(\ ~ND

\\ 0 o CBR

30 ~ I I\ 0----0 DENSITY

\ l:r----6. WATER CONTENT

J \ I

~III

40 '

FIGilllli 51. AVERAGE WATER CONTENT, DRY DENSITY .. AND CBR TEST RESULTS VERSUS DEPTH IN THE EMBANK-MENT, TEST PIT 9 (TRACK SECTION 9)-' "

Page 88: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

WATER CONTENTo 5 10 15 20 25 30 35 40

r I I II I I I I. DENSITY

60 70 80 90 100 110 120 130 140

r I I I I I I I ICBR

0 5 10 .15 20 ' 2S 30 35 40

o I );;9 ~ OZ ~ 'I _-T /,/'\ --

/ , .--,..---- . / // '- .:..-~ -- / // --, ,tfQ q---- '? ? t(

\ /\ \ \ , \ /\ \

10 t- \ \ \, \ /

~ \ q ~. .f tf\ \ , \ I

-.l \ \ / If\) · \\ ,

/ Iz \ , \· \ / I· \ , \X \ \ \ / I... 20 \ \ , /Q.

\ \ III.l \ , I0 \

,? q 9 4 I~ ~ LEGEND\ \ \ , \

I -\ ,

\ , \ I 0 o CBR

\ I \ I \I 0 o DENSITY

30 ~ \ , \ I, \ 6 6 WATER CONTENT\ , \ I ±l a, , ----\ , \ \\ b

\ ,. ~' At> a 0

40· '--

F'rGURE 52. MEAN AND STANDARD DEVIATION CURVES FOR AVERAGE WATER CONTENT, DRY DENSITY, AND CBRDATA FROM ALL TEST PITS VERSUS DEPTH IN THE EMBANKMENT

. ,I.'

Page 89: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

and. the other sample. was taken from 12 to 24 in. in depth from that, > ·':~1-.·:·~;,"··1.~""'~ .. >;;,;.:·';~::'~~'~¢:::ij7:~'~'

interface. These samples were sealed into wood boxes with wax. Dis-

turbed (bag) samples were also obtained for laboratory material property

tests. Laboratory results are described in a following section.'~

Embankment Instrumentation

The embankment instrumentation investigation was carried out by

an electronics engineer. 'In the first phase of this work, a field check

was mad~ to'determin~ insulation values for the pre~sure, moisture, tem-

,peratUre~ ~nd -.main array vertical extensometer circuitry. Figure 53

shows this work in progress. Typical results of the field insulation

checks are ,summarized in Table 4. In general, 100 megohms or higher

values ofinsulatlon resistance to ground are desired for relatively

noise-free electricai measurements. Usable electronic signals'can, of

course, be obtained with insulation values less than optimum; but below

10'megoruns insulation resistance, the signal to noise ratio decreases

rapidly and noise levels tend to affect measurement precision. Approxi-: j '~~

mately ~O percent of the insulation values recorded for the vertical

extensometersand pressure cells in Track Section 2 were less than

10 megohms, as shown in Table 4. Circuits of the moisture-temperaturo?\

cells connect through the sensor to ground, so relatively low values of

insulation are to be expected when readings are made .at the cable

terminals. Final readings of the vertical extenspmeters were also made,

and these readings are tabulated in Table 5.The next phase in the field work involved excavation of the embank­

ment instrumentation in Test Pits 2B, 7,'and9. 'Time and fUnding con­

straints limited this effort to three pits and to a depth of 3 ft into

the embankment. However, these excavations exposed the bulk of the main

array instrumentation, including the vertical extensometer' heads, upper

and lower soil pressure 'cells, moisture':"temperature gages, and as­

sociated wiring, as shown in Figure 54. Conditions in each pit were

similar and are summarized as follows:

73

Page 90: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 53. FIELD CHECK OF MAIN ARRAY INSTRUMENTATION READOUTS

74

Page 91: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

~', __ ..:: :. r. t. _.".:.

TABLE 4. TYPICAL RESULTS OF FIELD INSULATION MEASUREMENTSINSULATION TO GROUND TEST SECTION 2, 20 MAY 1976

Ga.!e A 1! f. D E F G H J .If- k M !!. p !!. §. T .Y. V w ! y z ~ ~ctor

21101-1 >20M >20M >20M >201-1 >20M 1

2/,01-2 105M 1. 5M 100K 100K 100K 1

2401-4 lOOK 120K 120K 120K 285K 1

2402-1 20M 1M 20M 20M 1M I 2

21,02-2 20M 720K BOOK BOOK 120K 2

2402-4 >20M >20M >20M >20M >20M 2

2403-1 20M 20M 20M 20M 20M 3

2403-2 >20H >20M >20M >20M >20K 3

2403-4" 1M 1M 500K 500K 230K 3

2201 1M 5M 3M >20M >20M 5M 4

2202 1M 1M 350K 720K 20M 120K 4

2203 20M 20M 20M 20M 20M 20M 4

2301 10K 'K °8K 5

--..J 2302 19K 15K 19K 5Vl

2303 20K 17K 19K 5

:?304 17K 14K 14K 5

2305 18K 14K 15K 5

23IJo 10K . 90K 40K 5

2307 30K 26K 30K 5

23J8 30K 13K 17K 5

2309 15K 15K 12K 6

2310 80K lOOK 3M 6

2311 40K 25K !10K 6

2312 40K 25K 40K 6

2313 15K 10K -15K 6

j{ = 1,000 ohmsM • 1,000,000 ohms

Page 92: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

76

Page 93: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 54. TYPICAL EXCAVATION OF MAIN ARRAY INSTRUMENTATION,TEST PIT 7 (TRACK SECTION 7)

77

Page 94: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

1. Heads of the vertical deflectometers were found to be tilted,sometimes severely so.

2. The upper pair of deflectometer anchor prongs appeared to bewell seated and in intimate contact with the surrounding soil.

3. In every case the surfaces of the main array soil pressurecells appeared to be in intimate contact with the s6il.

4. The excavated moisture-temperature cells were plated to a darkcolor, as if they had been anodized.

Figure 55 illustrates the extensometer tilt observed in Test Pit 9,

. ~rack Section 9. In this example the extensometer was not centered

beneath the crosstie, and tilting resulted. Tilt,ing usually occurred

when the large (16-in.-diam)extensometer heads followed sharp differ­

ential settlements in the KTT subgrade. The tilting phenomenon was also

noticed in excavations to expose the Carlson pressure cells installed by

PCA (just beneath the ballast-subgrade interface). A typical example of

this condition is shown in Figure 56; however, studies of these instru­

ments were not included in the current scope of work. Table 6 summa­

rizes the internal mechanical condition of the vertical extensometers,

and Figure 57 illustrates the internal damage which typically resulted"i

from overranging as the subgrade settled. In Figure 57, note the broken

fittings which had been attached to the LVDT rods. In some instances,

mud and/or water was found inside the heads, presumably caused by

infiltration.

Calibration valves for the LVDT's in the main array vertical

extensometers of Track Sections 2, 7, and 9 were also verified in the

field. Res~ts of the field ve~ification are shown in Table 7.

The calibration history of the soil pressure cells was also

researched;,results of this study are presented in Table 8. Detailed

descriptions of the test procedures and eQuipment used onsite and in the

limited series of verification tests carried out at the WES may be found

in Appendix E, Volume II, of this report.

78

r~

Page 95: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

-1\0

FIGURE 55. VERTICAL EXTENSOMETER TILT OBSERVED IN TEST PIT 9 (TRACK SECTION 9)

Page 96: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

();Jo

FIGURE 56. CONDITION OF PCA PRESSURE CELLS (LOCATION JUST BENEATH THE BALLASTSUBGRADE INTERFACE, TRACK SECTION 3)

Page 97: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 6. POSTMORTEM CONDITION OF E:;cr:ENSOMETER LVDT ASSEMBLY

Anchor/Transducer Support LVD1' Core Extension Rod Leaks Pumping Core Resting

Location Broken Bent Jammed Broken Water Mud on Bottom

1401-1 X

1401-2 X

1401-4 X

1402-1 X1402-2 X1402-4 X •2401-1 X X X

2401-2 X X

2401-4 X

2402-1 X X X X

2402-2 X X X X X

2402-4 X X X X

3401-1 X

3401-2 X X

3401-4. X

3402-1 X X

3402-2 X X

3402-4 X,~ .

X3403-13403-2

;

3403-46401-16401-26401-36401-46402-1 X X

6402-2 X

6402-3 X X

6402-4 X X

7401-17401-27401-47402-1 X X

7402-2 X X

7.402-4 X X X X

8401-18401-28401-48402-1 I

X

8402-2 IX ,

8402-4 I X

9401-19401-2 X

9401-49402-1 X

I9402-2 X X

I9402-3 X

9402- 1j I IX I

81

Page 98: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

CDrv

FIGURE 57. EXAMPLE OF INTERNAL DAMAGE TO MAIN ARRAY VERTICAL EXTENSOMETER(TRACK SECTION 2)

Page 99: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

"

TABLE 7. EXTENSOMETER IN SITU CALIBRATION RESPONSE TO,TO I-IN. DISPLACEMENT,' 20 'MAY 1976

• Gage

2402~l'**

'24017'"2

2'401-4

·2402~1*·* ,,'

, 2'402-2*~

2402-4

7401-1t.

7401~2, ,

7401~~t , '

7402.,.1

7402-2

7402-4,. . I"'

9401":1,

9401-2 '

9401-3 "

9401-4tt

9402-1**

9402'-2

9402-:3

9402-4 ','

TR7'"lOOInci:tt,!ition ~"

,l.lR (up)

Q.97:R

.(

, 0.95R

"1. 05R4' .....

0.97R "

, 1. 05R

1.05R

1. 05R ,',

Lb5R

1.05R

l'c5R

'l.06R

, 1. 05R

1. 05R

. . . .

LVDT Sensitivity*'Inv/v/in.' , .

378.2

372.3

'318.0

380.'0·

374,0

, 371'.3

377;3

380.2

:377.3

376.5

376.3, •

. 381.0,

374.0

" Disp18.cement'" in inches

1.02R

0.91R

0.8eR'

O.-'98R

0.98R'

0.98R'

0.98R ", .

,O.98R,

o.97.If

0.98R

L4R, \ ..

0.99R

0.97R

0.99R

** '*', See Reference, 3.,

Rod 'j ammed tube. " ,,t Could not loosen LVDT core fromreferehcett This calibrati~nwa~ done:'twi~e. "

83,\

.' ~

assembly.'

Page 100: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 8. CALIBRATION HISTORY OF MAIN INSTRUMENTATIONARRAY PRESSURE CELLS

Sensitivityin mv/v/psi

Cell Range Slope Indicator WES CalibrationNUmber in psia Company Calibration* o ft of cable 30 ft of cable

2201 25 8.667 ** **

2202 50 4.263 ** **

2203 100 2.225 2.211 2.288

7201 50 3.120 3.070 3.110

7202 50 4.303 4.254 4.400-

7203 100 1.802 1. 787 1.839

9201 25. 8.693 8.137 8.680

9202 50 4.086 3.991 4.190

9203 100 2.000 t t

* See Reference 3.** Defective cell

t Leads and air tube cut too short for calibration vessel.

84

Page 101: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

LABORATORY INVESTIGATION: '

Detailed descriptions of the sampling and laboratory test pro­

cedures and the original data plots are presented in Appendix D,

Volume II, of this report.

Ballast Tests

Laboratory sieve analysis tests were performed on all the ballast

samples. This sampling was intended to determine the amount and, if

possible, the origin of fines present in the ballast.

For purposes of a preliminary evaluation, ballast samples from

Track Sections 1, 4, and 9 were tested first. These preliminary tests

consisted of sieve analyses and, if sufficient fines were collected,

Atterberg limit tests. Samples from the other test pits were testedI

later. Summary plots showing the range in gradation of (under struc-

ture) "top" and "bottom" ballast samples are presented in Figures 58

and 59, respectively. The range in gradation of the shoulder ballast

samples is, shown in the summary plot in Figure 60.

Embankment Material Property Tests

The disturbed (bag) samples taken at· 0 to 12 in. in depth and at

12 to 24 in. in depth iLl each test pit were subjected to sieve analyses

and Atterberg limit tests. Results of these tests are summarized in

Table 9. All but one of the samples were classified as highly plastic

clay, CH, according to the Unified Soil Classification System. 13 The

only exception was the lower sample from Pit 3B, Track Section 3, which

classified as a lean clay (CL).

Laboratory compaction and CBR tests ,were conducted on specimens

remolded from the bag samples. These specimens were prepared using the

same modified American Association of State Highway Officials (AASHO),

compactive effort specified for similar tests made while the embankment

was ,under construction. 6 CBR tests were 'conducted on the as-molded

85

Page 102: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

():)0'\

u.s. STANDARD SIEVE OPENING IN INCHES U.S. STANDARD SIEVE NUMBERS HYOROMfTER6 A 3 'II I % 'II % 3 • 6 8 lOlA 16 20 30 .0 50 70 100 lAO 200

l00! ! I II ""{~~I I I I I I I I I I 0I

\90

;\10

80\ 20

') \70

\ 30 ...\ z:.. 2z:\Q ...

i 60 AO ~~•>-• or...

or50 50 ::1...z «

;;0: 0

Z \ .uI 60 ZU AO -

.. ...or U... 1\ •...

70 t30\

I \ r--,~8020 I, \

~ --:......c~ -

\ - '"10 90

0 100500 100 50 10 5 1 O.S 0.1 0.05 0.01 0.005 0.001

GRAIN SIZE MilliMETERSI GRAVEl I SAND I SILT 01 CLAYCOULESI CO..-s~ I ,..( I COAIUI I MEDIUM I 'INl I

5_"11 NO tUV OR tfl'TH QAS511'CATIQN NAT W~ U '" "o to l) in. Ballast""JECT Kansas Test Track

Postmortem Investigation

,uu 'T'nn RAllA",t ~"Mnlp;" ..

IlO«ING NO.

G:tADATIOH CURVES OAT'!!

FIGURE 58.~GE IN GRADATION OF "TOP" BALLAST SAMPLES

~ t·

Page 103: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

'\) y !

.':i-r·'

OJ-J

U.S. STANDARD SIEVl OPfNING IN INCHES U.S. STANDARD SIM NUM8ERS HYDROMETER6 4 3 Y2 1 '.4 Ys ~ 3 4 6 8 10 1416 20 30 40 SO 70 100140 200 ;

100 I ~ III ,~~II

I III r II I I I I I I I I I I 0

II ,}.\ 111\ "90 - - 10,\

10 \ :zo\ -..

70 \30 S

~ \~

Q40 ~~ 60

~

>- - .... •'"

...z so i\.sO :

~~ 0Z 1\ v

I 60 Ztl 40 - i\ I\~ ...'" V....

\ i'- •"-70 t30

\ .......

----20I \ 80:

10 "'D..- 90""V-I---

0 100500 100 SO 10 5 I 0.5 0.1 0.05 0.01 0.005 0.001

GRAIN SIZE MILLIMETERS.I G....Vfl I SAND I

COUlES sIn oi ClAYI CO.usf I ,N( I COARS( I O<fOIUM I ,IN! I

SAM"'l NO (IIY 01 Of"" ClASSIPICATION .....'w'X, U '" " 'IOJfO' TF Test Trar-k8 to 18 in ",,,1-1 ""t

Postmortem Investigation

"'fA Bottom Ballast Samples

BOlING NO

GRADATIGH CURVES DAn

FIGURE 59. RANGE IN GRADATION OF "BOTTOM". BALLAST SAMPLES

"',

Page 104: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

OJOJ

".U.S. ST...."'OARD SIEVf OPENING IN INCHES U.S. STANDARD SIEVE NUMBERS HyDttOMETEIl

6 A 3 YJ 1 " y,~ 3 A 6 8 lOlA 16 20 30 ·AO .50 70 100 lAO 200100 I ,~I I :1 I I I I I I I 0

90 " \ 101\ \80

rT- \20

\I I \ 30 ~70

\~"%

%\

52Q

AO ~) 60~•~• . ""...

:: .50 50 ~z -<il: 02 v

I60 Ze: AO

~ 1\ ..."" V... . •L 1\ 70 r31J

"~

I "- 8020: I \ ~ ......

\ -10 I 90I "

- -0 I I 100.500 100 .50 10 5 1 0. .5 0.1 0.0.5 0"01 0.00.5 0.001

GRAIN SIZE MILLIMETERS

""COIIlESI GRAVEL I "SANO I SILT 011 CLAYI COAne I 'Nf I COAUl! I /o\fOtu.. I "NE I

S.....l'll NO fLlY 01 0("" ClASSIF'CATION NATW-x, u I'l " "IOJfC1 KAnSAS 'I'pst. 'I'r!!C'ko to 1 in R.<.ll <1st

Postmortem Investigation

AllfA !':hrml npl" .RAll 'lst !':"Tf'nl PC:

IOIING NO"

GRADATION CURVr.:S D..ll

FIGURE 60. RANGE IN GRADATION OF "SHOULDER" BALLAST SAMPLES

) j

t>

Page 105: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

...--"

TABLE 9: LABORATORY CLAsSIFICATION TESTS ON SUBGRADE SAMPLES

Depth PercentFrom USGS Finer Than

Pit Top of C1assl~ No. 200No. Subgrade fication LL PL PI Sieve Color

1 0-12 CH 57 28 34 . 93 Brown1 24-36 CH 62 23 39 ... 912A 0-12 CH 62 24 38 952A 24-36 CH 61 24 37 962B 0-12 CH 59 23. 36 952B 24-36 CH 63 23 40 953A 0-12 CH 59 23 36 943A .24-36 . CH 60 22 38 943B 0-12 CH 53 23 30 933B 24-36 CL 46 20 26 694 0-12 CH 61 24 37 944 24-36 CH 66 24 42 955 0-12 CH 63 20 43 895 24-36 CH 59 25 34 . 92 .7 0-12 CH 58 24 34 917 24-36 CH 60 19 41 918 0-12 CH 56 23 33 938 24-36 CH 58 19 39 909 0-12 CH 62 24 38 97 Brown9 24-36 CH 55 21 34 95 Reddish-

Brown".'.,

';

Page 106: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

specimens and on specimens which had soaked in water for 4 d~s. Typi~

cal CBR and compaction test results from Track Section 1 are shown in

FigUre 61. By averaging all the compaction test resUlts, an optimum.' ;'

water content of 16.6 percent and a maximum dry density of 111.7 pcf

were determined to be representativ~ values for the embankment clay:

It should be noted for future reference (Figure 61) that the'

soaked specimens had little strength.

Embankment Strength Tests

Unconfined compression tests were conducted on 1.4-in.-diam by

3.0-in.-high specimens trimmed from the undisturbed samples obtained in

each test pit. These tests were conducted for comparison with resuit's

of similar tests made during construction of the KTT embankment. '. ,"

~' >:·'.11

"

12 ft in the embankment, respectively. At 0.75 tsf confining pressure,"

Results of the uncOIlfined compression tests, including mbisture:contents-?<• • ' _h' - ,.. ,,:,: - ... '"-' ,-' ..'-,

:"0-

1',: f:'.'

: '.'.~.

~ ....

Hence, the triaxial resultsare presented o~iy>iJ:l

these tests showed only a slight average increase in strength above::

unconfined results.

Appendix D, Volume II, of this report.

. ,

and densities, are summarized in Table 10. Unconsolidated"undrained

triaXial tests were also made on samples from Test Pits 1, 4, and 9;

Test data were obtained, at confining pressures of 0.25, 0.'5" and>,'0.75 tsf to simulate in situ pressures at depths of about 4,'8, and

',-.'-

... ' , I., ';

, '., ,",- " . .~

':-....

90

Page 107: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

'00

TRACK SECTION 1

110

II: &0IDUQIIII-UIIIII:II:

8 .0

20

SOAKED CaR

o L----L.~:::c::~c:::=~~:::;:::~:______:!AO '2 '" ,& '8 20 22 2.

_WATER CONTENT, PERCENT OF DRy WEIGHT

"2

'J.;" \. ~

\110

\\I.

~1b,.uQ.

~. \LI-iii '08

. ~.ZIIIQ

~II:

\Q

'06 \

,.. 1fi 18

WATER CONTENT, PERCENT OF DRY WEIGHT

'2

'0. ~ ......J"-_......,.._~ -I.. ....L.. ""--_-:-__'- _

.0

FIGURE 61. TYPICAL LABORATORY CBR AND COMPACTION TEST RESULTS(.oN SPECIMENS REMOLDED FROM BAG SAMPLE OBTAINED IN TEST PIT 1,TRACK SECTION 1)

91

Page 108: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 10, UNCONFINED COMPRESSION TEST RESULTSON SUBGRADE SAMPLES

" - - -

UnconfinedWater Dry Compression

Pit Content Density Strength1!2.:.. % peF TSF

1T 27.9 94.9 1.151B 27.2 95.7 2.25

, 2AT 28.3 90.7 2.332AB 28.0 93.4 3.032BT 27.7 95.7 2.062BB 25.8 95.5 2.42JAT 30.1 89.9 1.18'3AB 31.7 88.8 1.263BT 27.4 93.0 5.213BB 30.1 91.0 1.504T 29.2 . 93.3 1.274B 26.8 93.8 1.305T 29.4 ' 90.2 3.945B 28.2 ' 94.2 1.207T 27.0 ' 95.2 1.217B 25.0 99.2 2.348T 32.4 83.7 2.028B 25.0 98.1 . 2~05

9T 27.0 95.4 0.999B 25.8 ' 96,4 0.96

92

"

Page 109: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

ANALYSIS OF RESULTS

Structures

The s~atic and dynamic load-deflection tests carried out in Track

Sec~ion 4 were primarily intended to provide data for validation of an

existing analytical model. Results of the study have already been.10reported by others, but the test prooedures, equipment, and static

test data are documented in Appendix A, Volume II, of this report. Im-. . ' 8

pedance test results have also been reported separately. However, both

the load-defiection and impedance studies contain information that is

relevant to the postmortem investigation and will be briefly summ~rized.

Analyses of the load-deflection tests indicate that the twin beams

in Track Section 4 behaved essentially as rigid plates and thatappre­

ciable relative motion occurred at the control joints between beams. lO

This motion caused the cracking and spalling illustrated in Figure 2.

Plate bearing tests, conducted on the thin (typically 2-3 in. deep)

ballast layer beneath north rail Beam 16, showed a variation in ball~st­

subgrade stiffness (k = 195 Ib/in. 3 in the middle of the beam and about

175 Ib/in. 3 at either end) over the length of the beam. The condition

of reduced support stiffness beneath control joints and other highly

stressed areas will-be explored more fully in following discussions.10The twin beams in Track Sections 4 and 7 also acted as water traps.

This and other aspects of KTT drainage will also be treated in detail

later in this report.

Impedance test results provide a means for ranking KTT track sec­

tions aceording to their initial. dynamic .stiffness for bothpretraffic

and posttraffic conditions. Such a ranking is shown in Figur.e 62. A

precondition for the posttraffic (October 1975) testing was the re­

creation of pumping con~itions (becember 1974 'through April 1975) at.

each test location. To that end, up to 16,000 gal of water and 600 .

passes .of a captive train were applied to some test locations. Surface

indications of pumping were achieved only in'Track Sections 1, 2, and 3.

The impedance results in Figure 62 show that this approach resulted in a

93

Page 110: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o

o

e 3B

/.,e 2A

l/l-l/lQ)e

-Ct-<'r-!....,l/l

<)

.r-!

-~

~~:;j 105'r-!cH

C'r-!---.~..

1 2 3 4 5 6 7 8 9

Track Section

o Pretraffic results (1973)

• Posttraffic results (1975)• Io Not considered to be representative of _performarice

under traffic; see text

FIGURE 62. RANKING OF THE KTT TRACK SECTIONS ACCORDING TO THEIRINITIAL DYNAMIC STIFFNESS IN PRETRAFFIC AND POSTTRAFFIC IM­PEDANCE TESTS

Page 111: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

reduction of stiffness (posttraffic) of Track Sect~ons 2,. 3,·4,5,8, .

and 9. Track Sect ions 6 and 7 were not tested for r.easons given

earlier. However, the attempt to re-create pumping did not succeed in

all instances, because Track Section 1 actually exhibited an increase

in stiffness and Track Section 4 did not exhibit the degree of softening, ' '..,' ' , . ' " '" '.. , . 8

expected from pretest judgments of performance under traffic. A rela-

tive stiffness ranking of KTT track sections was developed by other

investigators14 from tests conducted in December 1974 (when the KTT

subgrade was in distress and pumping under traffic) . Results of this

testing are shoWn in Figure 63 and ~re believed to accurately reflect

structure, ballast, and, most important, subgrade conditions'existing in­

December 1974.

Among the'more significant results of the structures testing are'

the fol19wing:

1. While the nonconventional track structures suffered somedistress, such as cracking and spalling of the concrete, theseand the conventional (t;i.e).structures remained essentiallyintact throughout the brief life of the KTT.

2. The twin beams in Track Sections 4 and 7 were noted as beingeffective water traps, to the detriment of ballast!subgradedrainage.'

3. Relative motion occurring at control joints between adjacentbeams and slabs was linked to softening of subgrade supportat these locales of relatively high stress.

4. The nonconventional structures were to have been founded on a6-in.-thick ballast layer. In fact, ballast thickness wasgenerally found to be 2 in. or less under the twin beams inTrack Sections 4 and 7.

5. The beams in Track Section 4, north rail, were found to haverotatedoutward,'away from the track center line.

The behavior of the track structures .and the heavy pumping ob~

served under traffic had focused attention on ballast!subgradesupport

conditions. These conditions will be discussed next.

Ballast

Results of the ballast tests indicated the presence of a large

95

Page 112: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

t }.25 ODD

Pass 411

error. limits

1 2 3 4 5 6 7 8 9

Track Section

FIGURE 63. RANKING OF THE KTT TRACK SECTIONS ACCORDING TO THEIR REL­ATIVE STIFFNESS UNDER TRAFFIC (FROM TRACK GEOMETRY CAR MEASUREMENTSBYENSCO, DECEMBER 1974)

96

Page 113: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

- ,,_.

amount of fines (15 or more percent by weight passing the 200'sieve) in

the lower ballast level. The control (shoulder) sample gradation tests

indicated less than 7 percent passing the 200 sieve. Atterberg limit

tests were performed on the lower ballast fines; however, these test

resu.lts were inconclusive bec,ause, of- small rock 'parti'cles which were

present in the material. ~hese particles probably originated as

(1) fines originally present in the ballast, (2) the products of ballast

abrasion, (3) concrete particles resulting from ballast-tie abrasion, or,

more likely, (4) a combination of all of these processes. ,The raw data

and statistical analyses indicated that a slightly greater amount of

fines was typically present under the north rail than under the south

rail. While this difference was not statistically significant, the raw

data do support the argument that pumping conditions were probably worse

under the north rail.

The ballast fines (pumped material) were characterized from visual

observations and photographs as predominantly brown or reddish-brown

clay with occasional traces of gray material near the concrete struc­

tures. The black and white photograph shown in Figure 64 was reproduced~ '

from a color photograph taken in Test Pit 8, Track Section 8. Figure 64

clearly illustrates that the subgrade material pumped upward, filling

the lower 11 in; of the 15-in.-thick slag ballast. Little or no traces

of pumped material were present in the upper 4 in. of ballast. A fine

white powder, which does not show clearly in Figure 64, coated the slag

ballast that contacted the concrete crosstie. On its bottom surface and

edges the crosstie itself was slightly pitted, a condition which is

illustrated in Figure 64. The above conditions of tie pitting and white

powder at the tie-ballast .interface were characteristic of every loca­

tion examined in Track Sections 1 through 3. In fact, the photograph in

Figure 65' shows that when the ballast was graded'off prior to testing,

the seating area of the concrete ties in Track Sections 1 through 3 was

clearly defined by white p~tches on the otherwise reddish-brown fouled

ballast. The gray-colored material, which was noted as pumping at some

locations under traffic, was undoubtedly a mixture of abrasion products

(tie and ballast) and muddy wate~,

97

Page 114: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

Reproduced frombest available copy.

FIGURE 64. ILLUSTRATION OF SUBGRADE MATERIALS PUMPED 11 IN.UPWARD INTO THE 15-IN.-T~ICK BALLAST OF TRACK SECTION 8. NOTRACES OF SOIL (PUMPED) MATERIAL wERE DETECTED IN THE TOP 4IN. OF BALLAST AT THIS LOCATION (TEST PIT 8). NOTE ALSOSLIGHT PITTING OF THE CROSSTIE AS A RESULT OF BALLAST ABRASION

Page 115: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

\ "

\0\0

FIGURE 65: ABRASION PRODUCTS, IN THE FORM OF FINE WHITE POWDER ON THE BALLAST, WHICH TYPI-CALLY DEFINED THE SEATING AREA OF CONCRETE CROSSTIES. NOTE ALSO THE EVIDENCE OF (DRIED)

PUMPED MATERIAL

Page 116: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

There were other studies of interest, such as degree of ballast

abrasion, and severity of pumping according to locale, which could not

be pursued for the following reasons:

1. Any changes in ballast gradation under the structures as aresult of abrasion were well within the range of gradationin shoulder ballast samples and so could not be detected.

2. Further attempts to assess ballast fines according to theirorigin would have required physical and .chemical tests thatwould have far exceeded the scope of this study in number andcost. Facts already in evidence prove that the bulk of thefines present in the fouled ballast· originated from thesubgrade.

Embanlanent

Based .on the postmortem cone p~netrometer results summarized in

Figure 36, the KTT embankment is characterized as having had reasonably

uniform properties in terms of strength versus depth. In general, the

remanent lime-stabilized surface layer (presumed to be 6 in. thick,at

the time of placement) exhibited a relatively high strength, but the

soil from 0.5 to 1.0 ft in depth was much softer. From 0.5 to 3 ft in

depth, the embankment strength increased; from 3 to about 4.5 ft in

depth, the embankment had virtually the same strength; and below 4.5 ft

in depth, soil strength decreased. Thus, for the postmortem (post­

traffic) test condition, the embankment was softest just beneath the

lime-stabilized surface layer, and some softening was indicated in the

1.5- to 2-ft-thick zone just above limestone bedrock.

The postmortem vibroseismic and penetrometer results show very

similar trends, as· illustrated by the summary plots of vibroseismic and

penetrometer data presented in Figure 66. Figure 66 demonstrates a

particularly good correlation between modulus (derived from.vibroseismic

tests) and cone point penetration resistance as a function of depth in

the embankment. Since the cone penetrometer direct index of strength

and the vibroseismic (indirect index of strength) results are in excel­

lent agreement for the. posttraffic test condition, it is also instruc­

tive to compare the pretraffic and posttraffic ~ibroseismic results to

identify time-induced and/or traffic-induced changes in response. This

, 100

Page 117: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

- -.- _._---- .-"---, --,- --Dutch conepenetrat ion resistance, tsf

10 28 30 40 50 60 70 80, I , I ! , , .MODULI , 103 PSI

8 " 24 32

Q

oO;-:...-.,--__-T- .,----,r-__~-....----......,

, .

E Modulus

Dutch cone.

2

4

.5

~ G Modulus...

1L.- ~L_.L_'_ -"Il9~_~____'''_'_.,__--......

FIGURE 66. AVERAGE CURVES FOR ELAsTIC MODULI ANDPENETRATION RESISTANCE VERSUS DEPTH IN THE EMBANK­MENT FROM ALL VIBROSEISMIC AND PENETROMETER DATA,RESPECTIVELY

101

Page 118: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

comparison is presented in Figure 67. Both the E and G moduli plots in

this .figure indicate a softening in the upper and lower 1.5 to 2 ft of

the embankment in the time interval (1972-1975) between pretraffic and

posttraffic tests. These trends, i.e., softening in the upper and lower

levels of the embankment, are also confirmed by the main array (built­

in) instrumentation results which have been analyzed by other investiga­

tors. 9 Embankment vertical deformation as a function of time, from

Reference 9, is summarized in Figure 68. Figure 68 shows that embank­

ment heave occurred from 1971 until OctOber 1974 when, under traffic,

rapid settlement took place. The initial heave was .attributed to an

increase ·in moisture content above construction levels, and the heave6occurred primarily in the upper 1.5 ft of the embankment. The increase

in moisture content (with attendant heave) is stressed as an important

factor in assessing embankment behavior and performance.

Based on the average postmortem field moisture content, density,

and CBR test results presented in Figure 52, the embankment is also

characterized as having high-surface and near-surface moistur~ contents

which tend to decrease with depth. The postmortem (1976) average

moisture contents to a depth of 3 ft exceed the average (1971) embank.-'

. memt construction moisture content of 24.3 percent. 6 The CBR curves in

Figures 52 and 61 illustrate that strength decreases in the embankment

clay as water content increases. However, and as expected, the remanent

lime:-stabilized surface layer provided higher CBR values than the under­

lying clay. The CBR test locations, which were patterned 'to typify con­

ditions at points of interest beneath the structures, were statistically

analyzed with the results shown fn Table 11. The "F" (variance) and

Student "t" (mean) statistical tests were used to assess the CBR results.

At the 90 percent confidence level, the means.were not equal in only two

st.atistical cases. There is then a 90 percent probability that:

1. At the surface, the subgrade under the north rail was softerthan the subgrade under the south rail. At depth, the differ­ences are muchless' s~gnificant.

2.. The top of the subgrade under the rail seats was softer thanthe top of the subgrade beneath the middle of the crib.

With less statistical confidence, it can also be argued from the data

102

Page 119: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

oo

5

.."'--;- .-'-;~

MODULI, 103 ,PSI

0 8 \I 24 -, 320

0 SHEAR, G

0 COMPRESSION, [

0 X COINCIDENT POINtS

n0

0 0

20

0 00

0Q

t-...~ (J)

~

J::t r CDX 3t- O 8 0 0L 0!AI0 0 0 0

0 0 0 I

0 0CD

4 00

0 0"

6L----~.........--'----.......- ........---_:_-----

SHEAR, G PRETRAF'F'ICo C SHEAR, G POSTTRAF'F'IC

- - C()MPRESSION, E PRETRAF'F'ICo O' COMPRESSION, E POSTTRAFFIC

X COINCIDENT POINTS

FIGURE 67. COMPARISON OF PRETRAFFIC AND POSTTRAFFICVIBROSEISMIC DATA TO DETERMINE TIME AND TRAFFIC­RELATED CHANGES IN STRENGTH AS A FUNCTION OF DEPTHIN THE EMBANKMENT

103

Page 120: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

10;71 3172 12172 11/73 10174 4/75

~ 05

..J...JUJ;=rJl

SYMBOL SECTION.~

'1z' 05 "0 •v; •rJlUJcr[l.

~ 1.00U

1510 20 30 50

TIME, MONTHS

SECTIONS1, 2, AND 3

SECTION

•·VtJ

SYMBOL

I I - I I I

n-~~~~\.'

~~~

~»../"P'

:'0".....\

r'~

'\

10171 31721.0

o

1 5

~

~ 0.5;=rJl

~z' 05ov;rJlUJcr[l.

~ 1.0oU

. 10 20 30TIME. MONTHS

,SECTIONS 4, 5, AND 7

40 50

66

9

SECTION

.0C0.

ROCK --ANCHORS POSSIBLYBOTTOMED OUT AND .DEFORMATIONS ARE PROBABLYLARGER THAN THAT STONE.

NOTE:DEFORMATIONS St;lOWN ARE

" FOR RAIL EXTENSOMETER TOROCK

SYMBOL

10174 4175"173'21720 I I I I I

.--.t.-::::s:-

R~-~ ':" ,'- '--tr-'-

.-1 ,

0

t'..

,5

\,0 \ '.

1

~

:f 0.5UJ

~

15

:Zzov;rJlUJcr~ 1oU

10171 3/721

10 20 30

TIME, MONTHS

SECTIONS 6, 8, AND 9

40 50

FIGURE 68. ,EMRANKMENTVERTICAL DEFORMATION AS AiFUNC'TION OF TIME(RE-PRINTED FROM FRA-ORD-76~258) . .

104

Page 121: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 11. RESULTS OF STATISTICAL F AND T TESTS ON MEAN CBR'S ATDIFFERENT LOCATIONS

90% confidenceARE ARE

Variances' Means·Test Location Equal ? . Equal? X X

north southNorth versus Surface yes no 12.25 16.86

south rail 6 in. yes· yes 4.97 4.5912.in. yes yes 6.20 6.7324 in. yes yes 10.53 10.1036 in. yes yes 10.27 11.16

All combined no yes 9.20 10.57

under betweenUnder versus Surface yes yes 13.81 15.59

between ties 6 in. yes yes 5.23 5.7912 in. yes yes 7 •.40 6.7024 in. yes yes 11.06 11.5036 in. yes yes 10.92 11.10

All combined no yes 10.23 10.85Comb surface,

6 in. &: 12 in. no yes 9.82 -10.61

joint middle.Joints versus Surface yes yes . 25.27 28.48

middle '. 6 in. yes yes 3.05 2.7312 in. yes yes 6.20 6.6824 in. yes no 4.78 7.4336 in. no yes, 9.40 7.95

All combined yes yes 9.74 10.66All combined

less surface yes yes 5.86 6.20

comb.N&S middleCombined rails Surface yes no 14.59 19.28

versus middle 6 in. yes yes 4.77 5.0912 in. no yes 6.47 7.0924 in. yes ' yes 10.31 . 9.2236 in. yes yes 10.73 11.n

All combined no yes 9.90 11.27

105

Page 122: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

that the subgrade was softer under the joints of the nonconventional

structures than Under the middle. While anyone data set may be statis­

tically inconclusive in this regard, the fact remains that the pene­

trometer (Figure 35), CBR (Table 11), plate bear~ng test results from

Track Section 4, and analytical model results all support the argument,

although the differences in strength are generally small.

Average CBR and plate bearing test results are shown in Figure 69.These results show generally similar trends; however, some variations

are to be expected because of the relatively shallow depth of influence

(approximately 3 to 4 in.) of the CBR tests and the appreciably greater

depth of influence (approximately 45 to 60 in.) of the plate bearing

tests. The high stiffness values recorded for Track Section "7 (Pit 7)

are attributed primarily· to the thickness and strength of the lime­

stabilized layer in that section (the highest surface strength measured. .

in any track section)~ A relatively stiff response was also recorded in

Track Section 1. This response may partly explain the anomalously high

stiffness recorded for that section in imped~~ce testing. S

In. order to assess embankment performance the following factors

must be considered:

1. The relationship between density, moisture content, andstrength in the embankment clay.

2. The effects of time-dependent fluctuations in moisture content.··

3. The source of the moisture content increases noted in December1974 and in the postmortem tests.

4. A rationale which correlates 1 through 3 above with tracksystem performance and· other data. - .

The embankment construction data6 and postmortem test data were

used to develop the desired relationship between moisture content,

density, and strength of the embankment clay. The unconfined compres­

sion test results obtained during construction and in postmortem. lab­

oratory testing were converted to shear strength using the equation

.- .

S = Quu 2

106

(1)

Page 123: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

40014

35012

300

10

290I

8

i 200~~..I-' :.::

I 6,0-.l

150

ILEGEND-

4

0 o CBR100~. I

0----0 K. pCi :.

f'

50' 2'

o 0' I I I I I , I I I I, _ 1 _

Test pit .'number

FIGURE 69. AVERAGE CBR AND PLATE BEARING TEST RESULTS BY TRACK SECTION

Page 124: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

'where

Qu = unconfined compressive strength, tsf

S =' Undrained shear strengthu

All of the construction and postmortem unconfined compressive strength

data were used to develop the density, moisture content, and shear

strength plot shown in Figure 70; Postmortem test specimens that had

an appreciable lime content are identified in Figure 70. They were not

considered in formulating the various curves shown because the intent

of the· plot was to illustrate behavior of the subgrade clay rather than

the lime-stabilized sur.face layer material. Accordingly, the upper and

lower bound strength and density curves shown in Figure 70 were fit to

the subgrade clay density and strength .data. Also shown in Figure 70

are (1) the average embankment conditions during construction in 1971,6

(2) average conditions in 1976 from the .postmortem trenching data, and

(3) conditions in December 1974 (under traffic) at shallow depths in

the subgrade. The December 1974 envelope was developed from moisture

cqnt~nts measured by other investigators in Track Sections 4 and 9,9 and

relates to sUbgrade conditions just beneath the lime-stabilized surface

layer. In the zone from 6 to 24 in. in depth, the postmortem average·

field dry density was 3.5. pcf less than t~e average density recorded for

postmortem laboratory specimens (Which were obtained from comparable

depths). However, field and laboratory moisture contents were in good

agreement. The average values for density and moisture content were:

AveragesDry' Density -Water Content

yd, pcf W, percent

.-

FieldLaboratory

90.894.3

-. 27.127.7

The density-moisture content-strength relationship shown in Fig­

ure 70 represents a conservative case,since field results ind~cate a

_lower average value of in situ density.

The effects of moistUre content variations in the subgradeclay

- are clearly illustrated in Figure 70. From 1971 to Octob~r 1974, as

moisture contents increased, the embankment heaved, primarily in the top

108

Page 125: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

o

-' . ,

,lol! 0

10~

-102

100...u 98ll.;.

96-C1'--

t911

'"zw0 90

>'. a:: BB0

B6

. B~

B2

0,0

83.0

.0

20

o

4

2.4.3

WATER CONTENT w, "25 )0

4

o

o

o4

o

o

4

4

o

o

o

o 0/o /o

Io

....

o SHAJIIl05. \/ILSOn DATA (00_=05 RXPORTJ4 lIES DATA (POSn<ORTDl).. DEIIO'ml lIES SAMPLES rRQI IJFPEll 6 IIICllES OP

SUIlORADE (RElATIVELY BYGS LIME COllTEllT)

o

FIGURE 70. RELATIONSHIP BETWEEN DRY DENSITY, MOISTURE CONTENT,AND SHEAR STRENGTH DERIVED FROM CONSTRUCTION (1971) AND POST­MORTEM (1976) STRENGTH TEST RESULTS

109

Page 126: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

1.5 ft of the 8ubgrade. Figure 10 shows that this increase in moisture

content was accompanied by a decrease in the strength of the subgrade

clay. By December 1914 moisture contents in the subgrade (just beneath

the lime-stabilized layer) h&d increased from 32 to 38 percent. In this

~ange of moisture contents, the KTT embankment clay was nearly saturated;

and strength in the upper layer of sUbgrade must have decreased drasti­

cally, as indicated by the strength curves in Figure 10. Postmortem em'­

bankment testing was performed in 1916, when the sUbgrade had. partially

recovered from traffic conditions (postmortem moisture contents 6

,to 12 in. into the subgrade of Track Sections 4 and 9 had decreased from

those measured in December 1914). Figure 11 shows rainfall amounts in

the period 1911 to 1916 from the Cassoday, Kansas, gage. Although a

weather station was located onsite, these records were incomplete;

whereas the Cassoday gage, only 3 miles away, could provide continuous

data. The rainfall records indicate that KTT.received more rainfall

(12.4 in.) in the traffic period of OCtober 1914 to April 1915 than the

rainfall (10.6 in.) recorded for the period from October 1975 to April

1976, which preceded postmorteJ? embankment testing.

Based on data presented in Ta.ble 9, the KTT embankment. soil has

been characterized as a highly plastic clay (CH). Average Atterberg

.limit values for this clay (from Table 9) are LL = 60 and PI = 37.

These values may be used to estimate the potential swell (heave, expan~

sion) characteristics of the KTT embankment clay based on recent WES

studies of expansive clay from which the following criteria were

developed: 15 .

PotentialPotential Swell

LL, Percent PI, Percent Swell, Percent Classification

>60 >35 >1. 5, High50-60 25-35 0.5-1. 5 Marginal

<50 <25 <0.5 Low

The KTT'claywas obviously susceptible to swelling in the presence of

water, and the degree of swell may have ranged from moderate to .high.

In 1971, the KTT embankment clay was placed at water contents wet

of optimum;6 however, Table 12 shows that all the track sections still

110

'"

Page 127: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

"

10

-~

IS."SI MEAN RAINfALL

C] ACT MONTHLY RAINFALL

It

! 8

oJI-' oJ..I-' ..

zI-' " ~a:

..

J

2

rCMBANKJlCNTr---'"-1 CONSTRUCTION

,- TIfAITIC 'IPOST_reM

TCSTING~

oJ F M A .. J J AS, 0 N 0 J F .. A W J J _ A SON 0 J F W A .. oJ J A SON 0 J F .. A M J J A SON 0 J F M A M J J A SON 0 J F .. A WI, ~ J, A .5 0 N 0

UI1I 11172 1173 1117.4 II7!t "'178

FIGURE 71. ,AVERAGE RAINFALL AT THE CASSODAY. KA:"fSAS, GAGE LOCA'l'ION C3 MILES EAST OF THE KTT}

IN THE PERIOD 1971-1976

Page 128: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

. ':,.

TABLE 12. CUMULATIVE DEFORMATION, UPPER 1. 5 FT OF KTT EMBANKMENT,1971-0CTOBER 1974 (FROM FRA-ORD-76-258)

Embankment Deformation, Inches Average DeformationsTrack Q;) North G> JlIorth oq; +~ +Q>

Section Shoulder ® Centerline Ra.il 3Inches

1 00.30* 0.18* -'0.28* 0.07*

2 0.25 0.13 0.13 0.17

3 0.43 0.32 ,-0.01 0.25

4 0.44 0.46 0.15 0.35

5 0.36 0.35 0.35 0.35

6 0.70 . 0.06 0.20 0.33

7 00.10 0.37 ,0.25 0.24

8. 0.28 0.13 0.08 0.16

9 0.19 0.12 ':'0.12 0.06

:,~.: -,

* Positive values indicate swell (heave); negative values indicatesettlement.

112

-','.

. . <,~ .

Page 129: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

.,.', experienced spme swelling _in the petiodfrom 1971 to October 1974. An

interesting fact is that Track Sections 4: 5, and 6 exPerienced the

highest average sw~ll in this_period. Track Sections 4 and 6 later

pumped heavily under traffic and were also deemed to have poor perfor­

mance .. Tr-ack Section 5 also pumped, tilt its physical- size (full width

slab) also resulted in lower top of subgrade stresses. Equally inter­

esting is the relativeiy high swell recorded for the center line in

Track Sections 4 and 7, where these twin beam structures had been noted

as trapping water. 10 The uniform swelling recorded for Track Section 5

suggests that this full-width track structure. tended to retain moisture

beneath it once moisture contents increased. Track Section 6 had very

high swell at the embankment north shoulder but much less swell under

the structure. Track Section 1, which had the highest strength lime­

stabilized surface layer tested, also swelled appreciably and later

pumped under traffic. It will be noted from Table 13 that Track

Sections 8 and 9 had less average swell than Track Sections 2 through 7,

which lay upslope~ This pattern is significant and will be discussed

next.

A survey of drainage conditions was also made as part of theKTT

trenching program, since pretest analyses bad suggested possible prob­

lems in this area.: Two drainage ditches had been provided during

embankment construction6 (Figure 5). The largest of these, located one

access-road-width north of the KTT embankment toe, afforded adequate

parallel drainage on the north side of the track. The remaining ditch

was centered between the KTT embankment and the Santa Fe mainline track.

This ditch did not serve its purpose of draining surface water from the

top of the KTT and ATSF embankments. Poor drainage of the embankment

top is illustrated by photographs (Figures 72, 73, and 74) that were

taken during the 1976 (Phase II) postmorte~ investigations. Figure 72

is a view looking eastward toward Track Section 7 and was taken from the

KTT grade crossing in Track Section 8. Figures 73 and 74 show details

of the drainage culvertp located under and near the grade crossing, re­

spectively. Figure 75 shows the top of subgrade and. ditch bottom pro­

files along the length of KTT. At its east end the ditch bottom was

.113 .

Page 130: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

TABLE 13. SUMMARY OF INSTRUMENTATION DEFECTS BY TRACK SECTION ANDAND DATA ACQUISITION PERIOD*

a. Faulty Extensometer Channels

Nov 14 Dec 14/Jan 14 Apr 15Test Main Main Main

Section Array Total A;rray Total Array Total

1 3 3 5 5 6 9

2 3 3 3 4 6 8

3 3 3 1 2 6 1

4 1 3 1 2 6 8

5 1 1 l' 1 2 3

6 2 2 2 3 1 9

1 0 1 2 2 3 4

8 2 2 1 2 3 4

9 3 4 2 3 5 6

May 76Main"

Array.

6

·5

4

3

1

2"

b. ' Faulty Main Array Pressure Cell Channels

TestSection Nov 14 Dec 74/Jan 15 Apr 75 May 76

1 3 1 0

2 3 2 2 2

3 2 0 0

4 1 0 0

5 2 0 0 ~, .;

6 2 2 2

1 1 0 0 0

8 2 1 1',J ".

9 1 0 1 0

* The number of faulty channels from one period to the next does,notnecessarily include the same channels.

114

Page 131: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 72. PONDING OF SURFACE WATER IN THE DRAINAGE DITCH BETWEEN THEKTT AND ATSF MAINLINE TRACK (VIEW LOOKING EASTWARD TOWARD TRACKSECTION 7)

115

Page 132: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

FIGURE 73. LATERAL DRAINAGE CULVERT· (TRACK SECTION 8, ADJACENT TOGRADE CROSSING). NOTE LOCATION OF INLET WITH RESPECT TO DITCH

116

Page 133: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

I-'I-'--l

· :~-::: ~/~:. '. 7h-

FIGURE 74. DRAINAGE CULVERT UNDER TRACK SECTION 8 (NOTE PARTIAL CLOSURETHROUGH SILTING)

Page 134: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

KTT TRACK SECTIONS -

1 - " ,- . 2 3 4 5 6 7 8 '9

I '.." ·',H', I II 'I II II I I I I

TOP OF SUBGRADE

9000+008590+ 00

""'" -........ --... --"" ..................~

_I I II ,_8580 + 00

w~

SLOPE = 0,39% --- TEST PIT---- DITCH

,_--J.I__I--L..-_l._~,J I_.--L8540 + 00 8550 + 00 8560 + 00 8570 + 00

STATION. FT

-...::::

I I

~

~

8530 +00

FIGURE 75. TOP OF SUBGRADE AND DITCH BOTTOM (BETWEEN TRACKS) PROFILES ALONG THE LENGTH OF THE KTT

.~}

Page 135: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

about 6 in .. below the top of the KTT embankment and dipped toward the. , : " . ,

west with a 0.4 percent slope. It should be stressed that any water

present in the ditch was thus in direct. contact with the top of the KTT

subgrade along its southern flank, and that overflow conditions (easily

achieved in the upper reaches of the ditches) would flood water over the

top of the KTT embankment. Either condition was most undesirable and

would have been aggravated by the ponding (channel storage) conditions

which .are obvious in Figures 72 through 74. It is also likely that the

preventive measures taken during construction, i.e., the thin (sprayed)

asphalt membrane and the (nominally)6-in.~thicklime-stabilized layer,

did not provide an effective barrier to .water migration. Lime­

stabilized soil typically develops tensile cracks upon curing, and the

KTT asphaltic membrane appeared to be no more than 1/16 in. thick from

field observations. Also, the. lime-stabilized material would have a

higher permeability than the intact clay.

Other drainage conditions, such as the tendency of the twin beams

in Track Sections 4 and 7 to t~ap water, must have contributed to the

subgrade problem. Once traffic-induced pockets had. formed beneath the

rail seats of the crossties, these depressions must also have served. to

trap vater and to accelerate the process of subgradedeterioration. In

Track Section 6 the ballast stabilization treatment left puddles of

treatment material.at theballast-subgrade interface, which formed v~ry

effective water, traps (from postmortem field observations during removal

.of the peA subgrade prebsure cells) .. Track Sections 8 and 9 also pumped

Under traffic but not with the severity of other track sections. It is'. • r

instructive to note.that Track Section 8 had the thickest (15 in.) bal-

last o.f any conventional track section and that Track Sections 8 and 9

were located where the middle drainage ditch was. deepest and where at

least some of the runoff water was diverted by an upstream lateral drain.

These favorable conditions must .have benefited performance under traffic.

Instrumentation

The built-in (main array) instrumentation will be. discussed in

the following order:

119

Page 136: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

· ,_ ....~ ,. ';' .

;.;..

1. Da.ta a.CCluisition procedures

2. Vertical extensorncters (deflectometers)

3. Soil pressure cells

4. Moisture-temperature cells

Detailed,descriptions'of the test prpcedures, eCluipment, and original'

data appear in Appendix' E'~Volume'II" ,of 'this report.

The'main array instrumentation was installed during construction

of 'the embankment ~,6 Data acquisitio~ tasks were performed by the PCA. 9

DiE;cussiohs betweenWES .and PCA representatives indicate that' a credit.;.,', , 16

able effort was made to record these and other data. The infiltration

of pumped material into most sensor locations must certainly be classed '

as adverse operating conditions. Mud infiltration must ,have caused at

least some of the low insulation values recorded in Table 4. Low values

,of ifl,sulation frequently result 'in low "signal 'to noise ratios (noisy

data) and ground loops. Problems of this sort were noted by PCA

t t ' 16represen a ~ves.

The verticaL extensometers (deflectometers) experienced some, .mechanical failures as a result of the Unexpectedly large embankment

displacements. Both embankment heave and settlement were measured, and

mechanical failures typically occurred. when displacements exceeded the

+1 in. travel limit of the extensometers. These conditions are sum­

marized in Table 6. Extensometer heads were usually found to be tilted

to conform with the undulating surface at the ballast-subgrade interface.'

There were also instances of mud infiltration into theextensometer head,, '

presumably through construction joints, since the head seals were intact

in all instruments opened for inspection. However, the primary problem ;

with the extensometer installation was that unexpectedly large displace-,

ments caused internal mechanical damage. If overranged, the extensom.;.

eter became either inoperative or erratic in behavior (phase reversals~

etc.). A summary of defectiveextensometers, according to track section

and data aCCluisition periods,9 is shown in Table 13. ,Soil pressure

cells are included in Table 13. \-The soil pressure cells (upper and lower) installed in the main

array fared better than the other transdu "rs (Table 13). The six

120

Page 137: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

,.'i"

pressure cells calibrated at the WES exhibited good linearity, and the

differences in calibration values shown in Table 8 could be a result of

the type and "length of cable used during calibratiori. All six of the

excavated pressure cells. were well seated in the subgrade, .but cables

.and conduits installed in their vicinity (Figure 55 ) may have influenced:

stress distribution in the soil, hence measurement accuracy.>

Temperature and moisture sensors were located in the same cell.

The temperature sensors appeared to. function properly; however, the

moisture meters were found to be undependable and inaccurate. 9 The

. moisture sensor used is basically a device to measure conductivity,

which usually increases with moistur.e content in the surrounding soil;

however, chemical impurities can also .influence the sensor output.·

Conversations between the WES and the sensor manufacturer revealed that

the reconunendedmeasurement procedure is to match the required number. of

sensors according to their internal resistance (to eliminate individual

calibrations). Calibrations should be then performed in the same soil

in which measurements are to be made. Unfortunately, chemical impuri"':'

ties, such as organ1c matter and dissolved salts, could still· affeCt·

the accuracy of the readings. Since organic material was found in the

sensing mesh of KTT moisture sensors, the data derived from these

instruments are certainly questionable, if not worthless. It is prob­

able that the cumulative effect of the organic matter on moistUre

sensors buried since 1971 would have rendered them·inaccurate before.

KTT testing. began in October 1974.

121

Page 138: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

CONCLUSIONS

No single event prompted closure of the KTT. Progressive deteriora~

tion of the sUbgrade, excessive maintenance, the prohibitive cost ·of

.rehabilitation, and potential safety hazards were' all considered in

reaching the decision. The KTT "failure" must be viewed in this

context.

Mechanism of Failure

The KTT operational problems stemmed primarily from a loss of

strength in the upper 12 to 18 in. (immediately below the lime­

stabilized surface layer) of the highly plastic clay embankment as: a

result of moisture ccmtent .increases in the subgrade. Inadequate

. surface drainage of the top of subgrade was the principal cause of the

moisture. content increases. There were other contributing factors whose

influence will be assessed in" the sections to follow.,! ,.,

Structures

Analyses of structural behavior are beyond the scope of this

report, and, in the case of the nonconventional track structures, have·

already been accomplished by other investigators,. However, some gener-.

alizations are in order, because structural behavior has an important"

influence on the structure-ballast-subgrade interaction processes that

govern track. system performance. Among the more important conclusions

regarding KTT track structures are the following:

1. Although KTT track structures suffered some distress, boththe conventional and nonconventional track structures wereessentially intact when traffic was terminated.

2. The .twin beam structures in Track Sections 4 and 7 behaved as. efficient traps for. surface water, to the detriment of thesubgrade. The north ra;i.l beamS .in Track' Section 4 were ~observed to tilt toward the north side of the track as thesubgrade softened.

3. Track Sections 5 and 7 exhibited the highest stiffness. .

122

.f.

Page 139: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

recorded in the midchord offset traffic testso.fb~.cemoer'1974.Track S~ction 4, although virtually identical to Track ,Se.c-,tion7 in physical characterist:lcs, had a much lower stiff­ness in the same tests.

4. All of the track structures set~led appreciably under traffic;and all showed evidence of pumping (Track Sections 8 and 9pumped but hot to the top of baliast as in the other tracksections) .

" ,

Ballast

Ballast test results l~d to the following conclusions:"

1. Ballast thickness under the nonconventional structures wastY])ically 1 to 2 in., which was inadequate in terms of eitherdrainage or load distribution to the subgrade.

2. Ballast gradation tests showed that more fines were presentunder the .north rail, which indicates that pumping was moresevere under this rail.

'-~ I

3.

, , ., 4.'

5.

Data scatter in the gradation test results prevented .anassessment of ballast deterioration under traffic, bU~ some 'deterioration undoubtedly occurred.

. ."

The ballast in Track Section 8 was 15 in. thick,and subgrad~ ,pumping filled only the bottom 11 in. of this material. In­creases in. ballast~thickness obviously serve to reducestresses on the subgrade, increase stiffness, and improveperformance. However, it is also likely that practical in­creases in ballast thickness (up to say 36 in. under thecrossties) would only postpone complete fouling (in the caseof KTT or similar subgrade conditions).

r

The ballast treatment (elastometric polymer) used in TrackSection .6 acted as a most effective water trap, and thissection's performance under traffic was very poor.

Embankment ..

;.

The KTT embankment was built of a locally available residual

highly plastic clay which was moderately. to highly susceptible to sweil~

ing in the presence of water. Swelling in this material results. from an

increase in moisture content and is accompanied bya marked reduction

in strength.

As a result of poor site drainage conditions., the KTT embankment

123

Page 140: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

swelled up to 1 in. in the period from 1971 to October 1974. The most

detrimental swelling occurred in the upper 1.5 ft of the embankment;

however, swelling was also recorded in the lower level of the embankment

(Just above the embankment-limestone interface).

All KTT track structures settled rapidly and pumped under traffic;

however, Track Sections_8 and 9 performed somewhat better than other_KTT

track systems. This result is attributed to:

1. Better drainage condition in Track Sections 8 and 9.

_2. The thickness (15 in.) of ballast in Track Section 8 and the-tie spacing (19.5 in. C-C) in Track Section 9, which resultedin relatively low top of subgrade stress levels.

The KTT was conceived as a means to .evaluate track-systemperfor­

mance under actual revenue traffic in which various track structure

design variables wouldb.e utilized t.o p~6v:hde a basis for comparisons •. _

In fact, KTT subgrade support conditions proved to be the prime test .

-variable, and track system behavior had to be rationalized accordingly.

In recognition of this fact, it is concluded that:- " .

L Subgiade support conditions were the primary factor influenc­ing KTT track system performance.

2. Subgrade support conditions varied with time, according tomoisture content fluctuations in the subgrade.

3. Distress of KTT structures (other_ than the pulled-out studs),maintenance problems, and operational hazards were effectswhich were caused primarily by subgrade problems.

4. Preventive measures, such as the KTT _lime-stabilized surfacelayer and the sprayed asphaltic membrane, were beneficial. butcould not compensate for the embankment softening caused by.inadequate drainage.

5. Increased thickness of ballast and smaller tie spacings tendto reduce top of subgrade stresses and thus serve to enhancetrack system performance arid durability, as might be eXpected.In the case of a very soft subgrade, such as in the KTT, how­ever, these features may only serve to postpone the inevitableproblem.

6. Track structural features, such as the "water-trapping" twinbeams in Track Sections 4 and 7, can cause subgrade problems.

7. Finally, and most important, the KTT embankment study-illus­trates that any railroad track is a complex system whose·

124

~"

'._

, ':'.;."

Page 141: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

performance is governed by structure-ballast-s'libg~ade ,interaction processes. If a balanced design is not produced,for whatever cause, component incompatibility will result inpremature failure. It is' through studies such as the KTTpostmortem investigation and ongoing acceler~ted service teststhat the necessary insight andunderstanding of track behaviorwill be secured.

Instrumentation

In this study only the instrumentation installed below the top of

subgrade was evaluated, and findings were as follows:

1.

2.

Apparently, contractual arrangements did not provide fortroubleshoo~ing defective sensors of any type. Hence, datawere obtained only from those instruments which were func­tiqning properly during each recording session, and no repairscould be made between sessions.

The KTT moisture sensors proved to be very unreliable; 6 how­ever, the temperature sensors (located in the same cell)ap­parently gave reliable results. The organic matter presentin KTT embankment clay is believed to have adversely affectedmoisture measurements.

3. Many of the vertical extensometers failed when embankment de­formations exceeded the nominal ~l in. range of the LVDTsensors. The KTT multiple vertical extensometers were rela­tively bulky; and the large soil mass displaced by the verti­cal and horizontal ~xtensometers in the main array may have,to some degree, influenced behavior of the' surrounding soil.The combination of relatively large-size,vertic~landhorizon­tal measurement devices was, in this sense, undesirable.

4. While the soil pressure cells used in the main array· generallybehaved well, the WEB-developed soil pressure cell is pre­ferred because it was designed and developed specifically foruse in soil masses. 17 ..

5. The data acquisition system used was adequate for recordingdynamic data, but it did not provide enough capability torecord all channels simultaneously in a format suited toautomatic data processing., Hence, data had to be recorded'from different train passes, complicating the analyses andlimiting comparability.

125

Page 142: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

RECOMMENDATIONS

The KTT was unique in terms of its configuration and approach to

tmck structure performance comparisons; however, contrary to the origi-

. nul design concept, the KTT sUbgrade turned out to be the primary test

variable. The highway and railroad literature are replete with examples

of 5ubgrade pumping similar to that observed at the KTT. The following

ballast and embankment recommendations should be generally applicable to

other track systems founded on clay material.

Ballast

Railroad ballast primarily serves to reduce top of subgrade

stresses by distributing structural loads apd also acts to provide free

drainage of surface water. In keeping with these functions it is

suggested that:

1. Ballast materials which satisfy railroad criteria forstrength, abrasion resistance, etc., should be placed in

. thicknesses compatible with lower bound subgrade strengths(seasonal variations in strength may be expected with loweststrengths generally occurring in the wet spring months). Ingeneral, experience with highway and railroad foundationsproves that long-term maintenance costs arising from inade­quate ballast thickness will greatly exceed any initial sav­ings during construction.

2. Ballast layers, graded in pl;3.rticle size from top (coarse) tobottom (fine), are recommended as a·measure to protect againstsubgrade pumping., The bottom subballast layer' should besufficiently thick (minimum 6to 8 in.) to cushion the sub­grade against coarse ballast intrusion and should have particlesizes on the order of concrete sand to act as a filter to pre-:vent pumping of the subgrade fines.

3. Other filter materials, such as cloth membranes, should beinvestigated for possible usage to prevent pumping.

Embankment

The KTTembankment was built of locally available clay that was

, susceptible·to swelling in the presence of water. Inadequate draiEage·

i2G

, ,

Page 143: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

was responsible for most of the KTTsubgradeproblems and was a direct

,cause of the subgrade pumpin~ which occurred. Accordingly, it is

recommended that:

1. Particular attention be given to basic drainage design forrailroad tracks founded on clay embankments,and provisions bemade to. maintain such drainage systems in good working order.Inadequate drainage will result in increased ballast and sub­grade maintenance or possibly failure,:Ln extreme cases.

2. Measures such as the KTT lime-stabilized surface layer can,provide beneficial increases in foundation strength and sta­bility under seasonal fluctuations in moisture content. Limestabilization is, therefore, a recommended treatment whEm thefoundation clay is susceptible to swelling. However, forrailroad applications, str~ngth and stability are primaryconcerns; and a thicker (say 12 to 18 in.) stabilized layerwould better serve the purpose. Lime stabilization shouldnot be viewed as a means of providing a moisture barrier,since the lime-stabilized layer will generally have greaterpermeability than the intact clay.

3. Recent moist'ure barrier technology, including membranes,rubberized asphalt, and the like, should be investigated todetermine their applicability to, railroad foundationproblems.

Instrument'at ion

The following recommendations should be considered in future

designs of railroad instrumentation arrays:

1. The attempt to measure moisture contents in the KTT embankmentwas laudable; however, the moisture sensors used were ineffec­tive bec~use of contamination by organic matter. Research todevelop improved moisture sensors is now Under way, and thisapproach should not be abandoned, in future planning. 18 "Piezometers could also be used to determine pore water pres­sures. Nuclear moisture-density measurements in the subgrade(through preinstalled tUbes) might also prove to be practical.

2. Every effort should be made to reduce the physical size ofrailway embankment instrumentation. Large inclusions in anysoil mass tend to influence its behavior, and relativelylarge devices such as the KTT vertical extensometers should beavoided for this reason. Also, large reference plates (suchas the 16-in.-diarn heads of the KTT'extensometers) cannoteasily conform to sharp differential settlements such asoccurred at KTT.

127

Page 144: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

3. Given the accuracy possible with current LVDT's and thefoun­dation settlements experienced at KTT, nominal ranges forvertical deformation in this instance should have been atleast ~3 in. rather than the 1.1 in. range specified, depend... 'ingupon the subgrade '," Circumstances will dictate futurechoices; however, it would be well to emphasize adequaterange and serviceability as primary design criteria.

4. If at all possible, simultaneous recording and a format suit­able for automatic data processing should be incorporated infuture data acquisition procedures. '

5. Future instrumentation responsibility should be vested in ~organization with ~ project officer in control, and contrac­tualarrangernents should provide for onsite and laboratorymaintenance of installed instrumentation as' needed'.

128

Page 145: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

REFERENCES

1. Staff. Rail Technical Division. "Kansas Test Track." Final Report.·. Report No. FRA-RT-72-08. Oct 1973. Federal Railway Administration.

Washington. D.C. .. ..

! ~

. I.,

2. Meacham. H. C. et a1.. "Study of. New Track Structure Design:·Phase I." Report No. FRA-RT-72-l2 •. Sep 1966. Battelle MemorialInstitute; Prepared for the u. S. Department of Transportation.Federal Rail Administration. Office of High Speed Ground Trans­portation. Washington. D. C.

3. Meacham. H. C. et a1.. "Study of New Track Structure Design:Phase II." Report No. FRA-RT-72-15. Aug 1968. Battelle MemorialInstitute; Prepared for theU. S. Department of Transportation.Federal Rail Administration. Office of High Speed Ground Trans-portation. Washington. D. C.

McLean. F. G. et al. "Kansas Test Track: Nonconventional TrackStructures. Design Report." Report No.F'RA-RT....72..:9.· Sep :1974.Westenhoffand Novick. Inc .• Chicago. Ill. .

Dietrich. R. J. and Salley. J. R.• "Embankment Support for a Rail­road Test .Track: Design Studies." Report No. FRA-RT-72":7. A~g 1971.Shannon and Wilson. Inc.; Prepared for the U. S. Department ofTransportation. Federal Rail Administration. Office of High Speed··Ground Transportation. Washington. D.C .

Dietrich. R. J. and Salley. J. R.. "Embankment Support for a Rail-. road Test Track. Construction Report." Report No. FRA-RT-73-10~

Apr 197.2. Shannon and Wilson. Inc.; Prepared for the Department ofTransportation. Federal Railway Administration. Office of Research.Development. and Demonstration. Washington. D. C.

Curro. J. R.• "Vibroseismic.Survey. Railroad Test Embankment.Aikman. Kansas. 1I Miscellaneous Paper No. S-72-36. Jun 1972. U. S.Army Engineer. Wate~ways Experiment Station. CE. Vicksburg. Miss.

Cqoper. S. S .• "Mechanical Impedance Evaluations of the Kansas Test;·. .Track: Pretraffic and Posttraffic Tests." Report No. FRA-ORD:-79110J ,c'r~~

Oct 1978 • U. S. Army Engineer Waterways ~~eriment Station. CE.·Vicksburg. Miss.; Prepared for the U. S. Department of Trans­portation. Office of Rail Safety Research. Washington. D.C~

Dietrich. R. J. and Salley. J. R.• "Embankment Support for Kansas.Test Track. Analysis of Embankment Instrument Data." Report No.FRA-ORD-76-258. Feb 1976, Shannon and Wilson. Inc.; Prepared forthe Department of Transportation. Federal. Rail Administration.. .Office of High Speed Ground Transportation. Washington. D. C.

4.

7.

6.

8.

10. Anderes. J. R.• IIAnalysis of- Kansas Test Track Beam Response. ,i

Report No. FRA":'77-31. Jun 1977. Department of Transportation.Federal Railroad Administration. Washington. D. C.

129

Page 146: POSTMORTEM INVESTIGATION OF THE KANSAS. TEST TRACK

11. Sanglerat, G., The. Penetrometer and Soil Exploration; Vol 1.Developments in Geotechnical Engineering, Elsevier Publishing Co.,

,New York, 1972.

12.

13.

,L 14.

American Society for Testing and Materials, "Standard Method forNonrepetitive Static Plate Load Tests of Soils and Flexible Pave-,

'ment Components and, for Use in Evaluation and Design of Airport .and Highway Pavements," Designation: Dl196, 1913 Annual Book ofASTMStandards, Part 11, Philadelphia,Pa., 1973.

Headquarters, Department of the Army, "Military Standards Unified'Soil Classifi2ation System for Roads, Airfields, Embankments andFoundations," Report No. MIL-STD-619B, Washington, D. C.

Talapatra, D. C., Corbin,J. C., Oct 1975, "A Feasibility Study ofa Method for Observing Track Stiffness from Mid-Chord Offset andProfilometer Measurements,n ENSCO, Inc., Springfield,. Va .. ' ,

15., Snethen, D. R., Johnson, L. D., Patrick, D. M., "An Evaluation ofExpedient Methodology for Identification of Potentially ExpansiveSoils," Report No; FHWA-RD-77-94, Jun 1977, Federal Highway.Admin­istration,Office of Research and Development, Washington, D. C.

16. Greer, H. C., Memorand'um for Record, Subj ect : Trip to PortlandCement Association at Skokie, Illinois, May 1976,U. S. ArmyEngineer Waterways Experiment Station,. CE, Vicksburg, Miss.

,17 .. woodman, E. H., '''Pressure Cells for Field Use," Bulletin. No. 40,'Jan 1955, U. S. Army Engineer Waterways Experiment Station, CE,VicksbUrg, Miss.

, .

,j 18.iI,

Matzkanin, G. A. and Selig, K. T., "Instrumentation for MoistureMeasurement in Bases, Subgrades and Earth Materials," report in

,preparation' for the Research Results Digest, Jun 1977.

(-,

130