Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Power and drainage works along Fogarty Avenue In preparation for works to widen the West Gate Freeway between the M80 Ring Road and Williamstown Road, the West Gate Tunnel Project will be carrying out power and drainage construction work along Fogarty Avenue.
August 2018
Two lattice towers along Fogarty Avenue will be replaced with monopoles, reducing visual impact and footings
Our teams will start with the power works, and then follow with the new drainage installation underground.
These works will take approximately 12 months to complete.
During this time there will be closures on Fogarty Ave and changes to how people access their houses.
Replacing existing lattice towers with monopoles
Lattice towers are the large freestanding power lines that transmit high voltage power around Australia’s network.
The lattice towers that run adjacent to Fogarty Avenue support two different power voltages, high voltage 220kVs and lower voltage 66kVs.
We are replacing two of the lattice towers along Fogarty Avenue with monopoles.
Monopoles are an alternative high voltage transmission structure that have less visual impact and a smaller footprint.
Hockey Club Drainage
Wembley Avenue DrainageTenterden Street Drainage
Highgate Street DrainageBehind the Noise Wall Drainage
Initial Drainage
Initial Drainage
Stony Creek Drainage
The Blvd
The Avenue
Watson Street
The Avenue
The Avenue
Ste
el S
tree
t
Gre
ene
Str
eet
Ver
no
n S
tree
t
Ker
no
t S
tree
t
Ferg
uso
n S
tree
t
Mu
ir S
tree
t
Ab
bo
tt S
tree
t
Str
on
g S
tree
t
An
dre
ws
Str
eet
Der
ha
m S
tree
t
Hic
k S
tree
t
Ver
nie
r S
tree
t
Cu
llen
Co
urt
Le
Fevr
e S
tree
t
Fogarty Avenue
Cra
nb
roo
k S
tree
t
Ten
terd
en S
tree
t
Wem
ble
y A
ven
ue
Hig
hg
ate
Str
eet
Del
ewa
re S
t
Eir
ene
Str
eet
Love Street
Benbow Street
Mill Avenue
Ben
a S
tree
t
Thomas Street
Salisbury Street
Gordon Parade
Me
lbo
urn
e R
oa
d
Will
iam
sto
wn
Ro
ad
Donald McLean Reserve
Stony CreekWEST GATE FREEWAY
McIvor Reserve
EdwardsReserve
FOGARTY AVENUE POWER AND DRAINAGE WORKS
Power works
NEW monopoles
Drainage works
LEGEND
Existing towers to be removed
Federation Trail detour
Federation Trail closed
Access to Fogarty Avenue
• To ensure these works can be carried out safely and efficiently, small sections of Fogarty Avenue will be closed during excavation.
Road closures and local detour routes
• Alternative vehicle accessto Fogarty Avenue will beavailable at all times, soplease observe all signageand detours in place anddrive safely.
• Access to Wembley Primary School and Wembley Street shops via Fogarty Avenue will be affected during some of the works with a detour in place.
Access to driveways and footpaths
• The footpaths along Fogarty Avenue will remain open during these works.
• Some driveways on Fogarty Avenue may be blocked for short periods, with parking provided in side streets. If our works have a direct access impact on your driveway, we will be in touch with you before works start to provide information on where to park, and how long the work will take.
How will the lattice towers be replaced?
• To do this, we need to relocate the lower voltage 66kVs power lines that currently run along the lattice towers and put them underground. The high voltage 220kVs lines will then be transferred to the new monopoles.
• To put the 66kVs power lines underground, we will be digging trenches in stages along Fogarty Avenue and laying the cables underground. This work will be carried out in stages to minimise disruption.
• To install the monopoles, we will excavate and pour new concrete foundations. These foundations will need 28 days to set.
• Once this is done, the top sections of the monopoles will be craned in to place and the220kVs lines progressively transferred from the existing lattice towers to the new monopoles.
• The lattice towers will then be dismantled and the old footings removed.
• Works will take place mainly during the day and footpath access will be maintained.
Installing a new underground drainage line
We are installing a new drainage line under Fogarty Avenue which will protect Stony Creek from any spills from the West Gate Freeway.
How will the new drainage be installed?
• To install the drain, we need to dig trenches along Fogarty Avenue which may be up to 6 metres deep.
• Once the trenches are in place, new drainage pipes will be laid and the trenches backfilled.
Bus route diversion
• During the works, PTV bus route 432 will be diverted.
• The north and south-bound diversions vary slightly.
• Please see www.ptv.vic.gov.au/live-travel-updates for details of the diversions once in place.
Fogarty Avenue – power and drainage works
What will happen to the Shared Use Paths during these works?
• There will be detours of the Federation Trail during these works. Please observe the signage in place.
• The Muir Street and Stony Creek pedestrian bridges at the eastern end of the work zone will remain open.
What about my waste collection?
Maribyrnong Council has provided the following advice for rubbish collection when sections of Fogarty Ave are closed:
• Residents on Fogarty Avenue are asked to place their bins in the adjacent side streets for collection when the power line and drainage works are taking place in front of their properties.
• These residents are asked to place their bins on the west side (away from the CBD) of the side streets.
• When works on Fogarty Avenue block access to a side street, residents on both sides of this side street will be asked to place their bins on the west side of the street (see map below). Bins left on the east side of the road will not be emptied.
• We will be in touch with residents in advance of these changes.
Contact us
Do you have a question about the project? If you need more information or would like to provide feedback, please get in touch.
westgatetunnelproject.vic.gov.au
1800 105 105
facebook.com/westgatetunnelproject
@westgatetunnel
West Gate Tunnel Project GPO Box 4509, Melbourne Victoria 3001
Interpreter service: 13 14 50
If you are deaf, or have a hearing or speech impairment, contact us through the National Relay Service. For more information, visit: www.relayservice.gov.au.