Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
i
POWER SYSTEM DESIGN OF SUPER ABSORBENT POLYMER
PLANT AT AL-JUBAIL, KSA
(REVISED)
By:
Ryan M. Magalang
ii
Letter of Transmittal and Approval
iii
May 31, 2011
Eng’r. Fortunato C. Leynes
Chairman
The Board of Electrical Engineering
Professional Regulation Commission
P. Paredes St., Sampaloc, Manila
Philippines
Subject: PROPOSED TECHNICAL REPORT TITLE AND OUTLINE
Dear Sir,
In accordance with Article IV, Rule 14, Item #8, of the
Implementing Rules and Regulation of Republic Act No. 7920, known as the “New Electrical Engineering Law”; I hereby submit
my proposed technical report entitled “ POWER SYSTEMS DESIGN OF SUPER ABSORBENT POLYMER PLANT AT AL-
JUBAIL, KSA ” including report outline for your evaluation.
I hope you will find this proposed technical report in order and satisfactory to your requirement.
Thank you.
Respectfully Yours,
RYAN M. MAGALANG
REE No. 0038154
PEE Examinee
iv
v
Preface
This Technical Engineering Report is submitted as a requirement for
the Professional Electrical Engineer board examination. It contains
work done from June to July 2011. This report has been made
solely by me; preliminary data however were based on the project
which is the subject of this independent study and I have done my
best to mention this in the report.
I would like to express my sincere gratitude to the three
Professional Electrical Engineers who served as my consultants and
mentors; Engr. Cesar R. Buensuceso Jr., Engr. Charles P. Pante and
Engr. Anthony G. Quiogue.
Finally, I wish to express my greatest thanks to my family, friends
and colleagues who have supported and helped me. To my dearest
Marina I give my especial thanks for her continued support,
understanding and for inspiring me always to achieve greater
heights. Above all, to God Almighty is the glory.
vi
Table of Contents Page
Title Page i
Letter of Transmittal and Approval ii
Preface v
List of Figures vii
Report Executive Summary ix
Chapter 1 – Introduction 1
Chapter 2 – Design Criteria 6
Chapter 3 – Electrical Calculations 7
Part 1 - Short Circuit Calculations 7
Part 2 – Overcurrent Protection Device (OCPD), 16
Primary and Secondary Feeder, Neutral Conductor and
Equipment Grounding Conductor
Part 3 – Time – Current Curve (TCC) Coordination 30
Part 4 – Load Flow Calculations 38
Section 1 – Motor starting Analysis 38
Section 2 – Power Factor Capacitor Sizing 40
Calculations
Section 3 – System Harmonic Analysis and 41
Calculations
Chapter 4 – Auxiliary Systems 46
Part 1 – Fire Pump and Fire Alarm System Diagram 46
Part 2 – Paging System Diagram 50
Part 3 – Telephone and I.T. System Diagram 50
Part 4 – Security System (CCTV) Diagram 50
Chapter 5 – Conclusions / Recommendations 55
References 56
Affidavits 57
Curriculum Vitae 65
vii
List of Figures
Figures
Page
Figure 1 – Super Absorbent Polymer Plant 3D model snapshot 4
Figure 2 – Super Absorbent Polymer Plant Key Single Line
Diagram
5
Figure 3 – System diagram of SAP plant
8
Figure 4 –Equivalent impedance diagram with 1BUS-101A/B as reference faulted bus
10
Figure 5 –Equivalent impedance diagram with 2BUS-101A/B as
reference faulted bus
12
Figure 6 –Equivalent impedance diagram with 2BUS-202 as reference
14
Figure 7 - Schematic Diagram of a Solidly Grounded System
29
Figure 8 - Schematic Diagram of a Resistance Grounded
System
29
Figure 9 – System diagram showing LV, MV and HV bus for the TCC coordination
30
Figure 10 – Equivalent system impedance diagram with utility as sole source and 2BUS-202 as faulted bus
31
Figure 11 – Time-Current Curve Coordination analysis
37
Figure 12 – Motor starting analysis single line diagram
39
Figure 13 – Harmonic analysis single line diagram
42
Figure 14 – The 2.7MVAr capacitor bank
44
Figure 15 – Harmonic filter diagram
45
Figure 16 – Fire Pump Motor Starting diagram
48
viii
Figure 17 – Fire Alarm System Diagram 51
Figure 18 – Paging System Diagram 52
Figure 19 – Telephone System and I.T. Diagram 53
Figure 20 – Security System (CCTV) Diagram
54
ix
Report Executive Summary
The subject of this report is the Super Absorbent Polymer Plant, a
project currently in the design stage being executed by Fluor
Philippines. The plant will be constructed in Al-Jubail, KSA. This is a
manufacturing plant intended to produce super absorbent polymer
resins which are the major components of baby diapers.
Preliminary data were used by the author as the basis of design. This
data includes the key single line diagram of the electrical system
where transformer sizes were already defined during the project’s
front-end engineering design stage. From there, the author made the
calculations necessary in order to size the protective devices, feeders
and buses sizes using the Philippines Electrical Code (PEC) and other
supplementary standards and assumptions.
Part 1 of Chapter 3 is the Short Circuit calculations. Using the key
single line diagram, data and assumptions the result of the calculations
were able to determine that the existing bus 1BUS-101A/B rated 40kA
from Substation 1, where Substation 2 will tap for its power source,
can still handle the additional short circuit current contributions from
the new Substation 2 loads. The bus short circuit ratings for Substation
2 were determined to be 50kA for the MV (4.16kV) bus and 70kA for
the LV (400V) bus.
Part 2 of Chapter 3 is the sizing of Overcurrent Protection Devices,
Primary and Secondary Feeders, Neutral Conductors and Equipment
Grounding Conductors. Using the applicable PEC provisions, the sizes
of the primary and secondary breakers of the two 20MVA, 34.5/4.37kV
transformers were determined to be 1250A, 40kA and 3150A, 50kA
x
respectively. The sizes of the primary and secondary breakers of the
six 2.5MVA, 4.16/0.42kV transformers were determined to be 1250A,
50kA and 4000A, 70kA respectively. The MV and LV bus tie-breakers
ratings were determined to be 1250A, 50kA and 4000A, 70kA
respectively.
The 20MVA transformers primary feeder size were determined to be
two single core conductors per phase of 250mm2 copper and the
secondary feeder to be four single core conductors per phase of
500mm2 copper. For the 2.5MVA transformer primary feeder size were
determined to be two single core conductors per phase of 250mm2
copper and the secondary feeder to be six single core conductors per
phase of 500mm2 copper. The neutral conductor of the 2.5MVA
transformers is the same size as the secondary feeder since the
transformers are supplying non-linear loads. These conductor sizes
were calculated taking into considerations the continuous loads, the
short circuit capability of the cables and the voltage drop.
Also, in this part of the report the Neutral Grounding Resistor (NGR) of
the 20MVA transformers were sized to be 400A, 10sec taking into the
consideration the system capacitive charging. Based on this NGR size
the System Grounding Conductor size was determined to be a single
core 125mm2 copper.
The determined sizes of primary and secondary Equipment Grounding
Conductors (EGC) for both the 20MVA and 2.5MVA transformers are
100mm2 copper and 80mm2 copper respectively. These sizes were
based on the applicable provisions of the PEC.
xi
Part 3 of Chapter 3 is the Time-Current Curve Coordination. Here the
author presented a possible scheme of coordination of protective
devices. Four breakers from LV to HV bus were coordinated using the
IEC Extremely Inverse Curve of ABB RXIDK 4 relays. Only the through
fault current or short circuit contributions from the utility/source was
considered in the relay coordination calculations. The result of the
calculations was able to set the Time Overcurrent and Instantaneous
settings of the relays such that they would operate correctly. The relay
curves, transformer damage curves and inrush currents were plotted
(see Figure 11, page 37) to show the results of the calculations.
Part 4 of Chapter 3 is the Load Flow Calculations. This part of the
chapter covers the Motor starting Analysis, Power Factor Capacitor
Sizing Calculations and the System Harmonic Analysis and
Calculations.
The subject of the Motor Starting Analysis is the largest motor rated
1239kW connected to the MV bus. Scenario and assumptions were
made to determine if the motor will start in the worst possible system
condition. The result of the calculations showed that there will be no
problem starting the motor.
Power Factor Capacitor sizing calculations were conducted to
determine the size of the capacitor bank needed to improve the
system power factor from an assumed value of 80% to 96%. The
result of the calculations suggested installing two banks of 2.7MVAr,
3-Phase capacitors.
xii
In the System Harmonic Analysis, calculations were made to
determine if a problem brought about by the VSD driven motors would
exist. The calculations showed that the probability of harmonic
problem is low since the calculated Short Circuit Ratio (SCR) is greater
than 20. However a possible parallel resonance might occur in the
order of 7th harmonic therefore a harmonic filter tuned to this
frequency might be needed to be installed. A harmonic filter for the 5th
order harmonic, which has larger harmonic current contributions
compared with the 7th order harmonic, was designed in this part of the
report. The filter is a series combination of an inductor and a capacitor.
The filter was designed in such a way that the Power Factor Capacitor
was used as part of the filter making the capacitor dual purpose
equipment.
Chapter 4 is the Auxiliary Systems. This chapter shows Fire Alarm
System Diagram, Paging System Diagram, Telephone and I.T. System
Diagram, Security System (CCTV) Diagram. These diagrams were
based on the design philosophy developed by Fluor Philippines Control
Systems Department.
In Section 1 of Chapter 4 the author presented a guideline for the
calculations of feeder and breaker size, power supply and other
considerations in the installation of fire pump based on the provisions
of the PEC. An estimated pump motor size of 120kW, 400V, 3Phase
was used as an example in sizing the breaker and conductors. Voltage
drop during motor starting and running at 115% of full load conditions
were also evaluated and the results showed that there will be no
problem installing a fire pump in the LV bus.
1
Chapter 1 – Introduction
Power system study is necessary for every project in order to make
a design which is reliable, efficient and cost effective. Every design
is expected to meet the requirements mandated by the governing
codes and standards that the specific project follows.
Project Background and Description
Super Absorbent Polymer (SAP) plant is located in Al-Jubail,
Kingdom of Saudi Arabia. As the name implies, its products are
super absorbent polymer resins which are the major components in
making baby diapers.
The plant is composed of main production building which is a seven
storey building, a warehouse, a Central Control Room and a
substation. Refer to Figure 1, page 4 for the 3D model view of the
plant.
The electrical system of SAP plant is based on the following
concept:
1. One new dedicated substation (Substation 2),
34.5/4.16/0.4kV for the SAP facilities.
2. Substation 2 will be powered from two 34.5kV spare circuit
breakers available from existing Substation 1.
3. For Substation 2 the following setup will apply:
a. Medium Voltage (MV) distribution switchgear is
2BUS-101A/B radial, 100% redundant transformers.
b. Low Voltage (LV) switchgear/MCC, 2BUS-201A/B is
radial, 100% redundant transformers.
c. Four (4) LV switchgear /MCCs for process units, each
corresponding to one process unit. Each of the
process LV switchgear/MCCs is fed from single
transformer and has one incoming feeder from the
2
stand-by transformer 2TR-206. The purpose of the
stand-by transformer 2TR-206 is to take over the
load from any single transformer when this is out of
operation. The load transfer will be done manually.
The parallel conditions are insured at the MV
switchgear which in normal operation has the bus-
coupler normally closed.
4. All bus-couplers will be operated manually.
5. Typical General Feeders include at least the following
panels supply:
a. Lighting Panel
b. Convenience Outlet Panel
c. Heat Tracing Panel
d. Main Distribution Panels
6. An Interlock between ACB1/B, ACB2/B, ACB3/B and
ACB4/B shall be provided so that the stand-by transformer
2TR-206 shall be connected only to one process LV
SWITCHGEAR / MCC at a time.
Refer to Figure 2, page 5, for the single line diagram.
Project Objectives
This technical report will present a power system design of the
Super Absorbent Polymer Plant based on engineering principles and
applicable codes. For this report, the primary code that will be used
as the basis of the design is the Philippine Electrical Code (PEC).
The intent of this report is to present a power system design for the
project in such a way that the plant is assumed to be constructed in
the Philippines and because of that this independent study is
conducted using the PEC as the new basis in sizing the buses,
3
feeders, breakers and all the components of the electrical system of
the SAP plant.
Scope and Delimitation
This technical report covers power system design of Super
Absorbent Polymer Plant. The design covers the following:
1. Main bus and feeder size calculations.
2. Breaker sizing using short circuit calculations.
3. Neutral Grounding Resistor (NGR) sizing
4. Load flow analysis and calculations.
5. Motor starting analysis.
6. Power factor capacitor sizing.
7. System harmonics analysis
8. Time-Current Curve coordination.
9. Fire pump motor circuit design.
All of the calculations pertaining to the scope of the design will be
based on the preliminary data from the project. These data includes
the transformer sizes, system frequency, voltages and single line
diagram showing the transformers’ connections as per the client’s
requirements. These parameters form part of the design
delimitations.
Auxiliary systems, namely; paging system, fire alarm system,
telephone system and security systems will be presented in this
report as adherence to the National Building code that mandates
the inclusion of such auxiliary systems plan drawings along with the
submission of electrical plan drawings.
This report does not cover and discuss maintenance of the electrical
equipments.
4
Figure 1 – Super Absorbent Polymer Plant 3D model snapshot.
5
Figure 2 – Super Absorbent Polymer Plant Key Single Line Diagram
6
Chapter 2 – Design Criteria
Basic Design Codes
Although the actual project is located in Al-Jubail, KSA, a territory
outside Philippines, for the purpose of this report all calculations
pertaining to the design will adhere to the PEC. Other supporting
standards that the PEC recognizes shall be used such as IEC, NEC,
IEEE, NEMA and ANSI standards will be considered as
supplementary codes.
System Frequency and Voltage
The system frequency is 60Hz. There are three utilization voltage
levels, namely 34.5kV for the high voltage (HV), 4.16kV for the
medium voltage (MV) and 400V for the low voltage (LV) system.
Design Assumptions
Assumptions will be made in some parts of the calculations. These
assumptions will be mentioned in the specific parts of this report
where they are needed.
7
Chapter 3 – Electrical Calculations
This chapter is divided into three major parts namely;
Part 1 - Short Circuit Calculations
Part 2 – Overcurrent Protection Device (OCPD), Primary and
Secondary Feeder, Neutral Conductor and Equipment Grounding
Conductor
Part 3 - Time-Current Curve Coordination
Part 4 - Load Flow Calculations
Part 1 - Short Circuit Calculations
The results of the short circuit calculations will determine the sizes
of the buses, feeders, breakers and the Neutral Grounding Resistor.
Case 1: For 1BUS-101A and 1BUS-101B
Verify if the existing bus can still handle the short circuit currents
when the new substation is to be served by the spare breakers.
Assumptions:
1. As per project design basis document assume that about 80%
or 16MVA of the total plant load consists of motor loads.
2. Assume that the two 20MVA transformers 2TR-101A&B are
running in parallel during the fault occurrence.
3. Assume that 80% or 2MVA of the load of each of the six
transformers 2TR-201A, 201B, 202, 203, 204 and 205 are
motor loads with 0.25 per unit reactance based on the
combined (2MVA) rating as per IEEE Std 141.
4. As per project design basis document neglect the cable
impedance and treat all transformer and motor impedance to
be purely reactance. This will provide more conservative
results.
8
5. Transformer 2TR-206 is excluded in the computation since its
purpose is a back-up power for the four LV transformers.
Calculations:
Based on the assumptions, compute for the induction motor loads
that are not served by any of the six transformers connected to bus
2BUS-101A&B. These motors are directly connected to the MV bus.
Let IM-1 be the composite induction motors directly connected to
the MV bus,
MVAIM-1 = 16 – 2(6) = 4MVA
Use 0.25 per unit reactance for IM-1.
Let IM-201A, IM-201B, IM-202, IM-203, IM-204 and IM-205 be the
composite induction motors connected to 2TR-201A, 2TR-201B,
2TR-202, 2TR-203, 2TR-204 and 2TR-205 respectively.
Using the Per-Unit Method, calculate for the fault current at the bus.
1. Draw system diagram. Refer to Figure 3 below for the
simplified system diagram based on Figure 2 and the
assumptions.
Figure 3 – System diagram of SAP plant.
9
2. Select MVA base. Use the 20MVA transformer rating as the
MVA base and the following base voltages:
For HV Bus: 34.5kV
For MV Bus: 4.37kV
For LV Bus: 0.441kV4.16
0.424.37 =
3. Compute for the PU impedance of Utility/Source.
0.01063pu1882
20ZU =
=
4. Compute for the PU impedance of the transformers.
1 101B-2TR101A-2TR 0.14puZZ ==
2201A-2TR 0.435pu
4.37
4.16
2.5
20
100
6Z =
=2
5. Compute for the PU impedance of the motors.
1.1327pu4.37
4.16
4
200.25Z 1-IM =
=2
3201A-IM 2.056pu
0.441
0.4
2
200.25Z =
=2
1 Value is typical to the two HV transformers. 2 Value is typical to the six LV transformers. 3 Value is typical to the six LV motor loads.
Equation 1
Equation 2
Equation 4
Equation 3
Equation 5
10
6. Compute for the short circuit currents.
a. Draw impedance diagram.
b. Draw simplified diagram with values. Compute for the
total impedance (ZT) at the fault point.
c. Compute short circuit currents, ISC, (symmetrical)
d. If Asymmetrical values of short circuit currents are
needed, multiply the symmetrical values by 1.25 for LV
and 1.6 for MV/HV systems.
a. For impedance diagram refer to Figure 4 below.
Figure 4 –Equivalent impedance diagram with
1BUS-101A/B as reference faulted bus.
b. Compute for ZT
HGAT Z
1
Z
1
Z
6
Z
1 +
++
+=
−−− 111
14.0
1
14.0
1
ZA = ZB = ZC = ZD = ZE = ZF
2.4917pu0.4352.056ZA =+=
Equation 6
Equation 7
11
Solving for ZT,
0.01063
1
0.14
1
0.14
1
1.1327
1
2.4917
6
Z
1
T
+
++
+=−− 11
0.01034puZT =
c. Compute for the fault current,
voltage base3
10 MVA base
Z pu
voltage puI
6
T
SC ×××=
1pu34.5
34.5voltage pu ==
RMS 32,369A345003
10 20
0.01034
1I
6
SC =×
××=
Results:
Based on the short circuit calculations, the bus can still handle the
additional load since it is rated at 40kA.
Equation 8
12
Case 2: For 2BUS-101A and 2BUS-101B
Assumptions:
For the purpose of this calculation, all assumptions made for Case 1
will apply.
a. For impedance diagram refer to Figure 5 below.
Figure 5 –Equivalent impedance diagram with
2BUS-101A/B as reference faulted bus.
b. Compute for ZT
HGFEDCBAT Z
1
Z
1
Z
1
Z
1
Z
1
Z
1
Z
1
Z
1
Z
1 +++++++=
From Equation 7 page 10, 2.4917puZA =
0.08063pu0.01063Z
-
H =
++=1
14.0
1
14.0
1
Equation 9
Equation 10
13
Solving for ZT,
0.08063
1
1.1327
1
2.4917
1
Z
1
T
++
= 6
0.06327puZT =
c. Compute for the fault current,
voltage base3
10 MVA base
Z pu
voltage puI
6
T
SC ×××=
0.9519pu4.37
4.16voltage pu ==
RMS 40,149A43703
10 20
0.06327
0.9519I
6
SC =×××=
d. Compute for the bus current rating. The bus must be
able to carry the full load current of the transformer.
2775.7A41603
1020I
6
B =××=
Say, 3150A.
Results:
Based on the short circuit calculations, the bus rating for 2BUS-
101A and 2BUS-101B should be greater than or equal to the ISC,
40,149A RMS. Say, 50,000A or 50kA RMS Symmetrical. For the
withstand time, use 1sec.
Case 3: For 2BUS-201A, 2BUS-201B, 2BUS-202, 2BUS-203,
2BUS-204, 2BUS-205 and 2BUS-206
Assumptions:
For the purpose of this calculation, all assumptions made for Case 1
will apply.
Equation 11
Equation 12
14
Calculations:
Since the seven buses are served by two MV buses connected in
parallel via a Normally Closed (N.C.) tie breaker and having
identical impedances, we can assume that they have the same
magnitude of fault currents. We only need to compute for the fault
at one bus. Let’s take 2BUS-202 as the reference faulted bus.
Using the same MVA base, base voltages and the per unit
impedances of utility/source, transformers and motors from Case 1,
compute for the short circuit current.
a. Draw the system impedance diagram using 2BUS-202 as
the reference bus. Refer to Figure 6 below.
Figure 6 –Equivalent impedance diagram
with 2BUS-202 as reference.
15
b. Compute for ZT,
RIT Z
1
Z
1
Z
1 +=
M
1
QPJ
R ZZ
1
Z
1
Z
15Z +
++
=
−
From Equation 7 page 10 and Equation 10 page 12,
ZJ = ZA = 2.4917pu
ZQ = ZH = 0.08063pu
0.5pu0.4350.08063
1
1.1327
1
2.4917
15Z
1
R =+
++
=−
0.402pu0.5
1
2.056
1Z
1
T =
+=−
c. Compute for the short circuit current,
voltage base3
10 MVA base
Z pu
voltage puI
6
T
SC ×××=
0.9070pu0.441
0.4voltage pu ==
RMS 59,076A4413
10 20
0.402
0.9070I
6
SC =×××=
d. Compute for the bus current rating. The bus must be able
to carry the full load current of the transformer.
3608.4A4003
102.5I
6
B =××=
Say, 4000A.
Results:
Based on the short circuit calculations, the bus rating for 2BUS-
201A, 2BUS-201B, 2BUS-202, 2BUS-203, 2BUS-204, 2BUS-205 and
2BUS-206 should be greater than or equal to the ISC, 59,076A RMS.
Equation 13
Equation 14
Equation 15
16
Say, 70,000A or 70kA RMS Symmetrical. For the withstand time,
use 1sec.
Part 2 – Overcurrent Protection Device (OCPD), Primary and
Secondary Feeder, Neutral Conductor and Equipment
Grounding Conductor
In general, calculations for the OCPD, feeder conductors, neutral
conductors and equipment grounding conductors shall comply with
the following:
1. Calculations for the size of primary and secondary overcurrent
protection devices must comply with PEC Art 4.50.1.3.
2. Calculations for the size of primary and secondary feeder
conductors must comply with “PEC Art 2.40.1.4, conductors
shall be protected against overcurrent in accordance with their
ampacities specified in 3.10.1.15”.
Feeder conductors must be sized such that the voltage drop is
limited to 3% as per Art 2.15.1.2(1)(3) FPN No. 2 and 3.
The estimated length of primary feeders for 2TR-101A and
2TR-101B is 70m while the length of secondary feeders of the
same transformers including the length of primary and
secondary feeders of the other seven MV transformers (i.e.
2TR-202) are estimated to be 15m.
3. Calculations for the size of neutral conductors of MV
transformers must comply with “PEC Art 2.20.3.22(c)(2),
where the neutral conductor of a 3-phase, 4-wire system is
supplying nonlinear loads no reduction in ampacity is
required”.
4. Calculations for the size of system grounding conductor must
comply with PEC Art 2.50.2.17 for the impedance grounded
system applicable to the HV transformers 2TR-101A and 2TR-
17
101B. For the solidly grounded system of MV transformers
(i.e. 2TR-202), calculations must comply with PEC Art
2.50.2.1(b)1.
5. Calculations for the size of main equipment grounding
(bonding) conductors must comply with PEC Art 2.50.6.13
and Art 2.50.2.9(d) where applicable.
Section 1 – Primary and Secondary Overcurrent Protection
Device
The determining factor in sizing the interrupting rating of all the
circuit breakers is the short circuit rating of the bus where they are
connected. In general,
a. All breakers connected to the MV bus must be rated 50kA
RMS Symmetrical.
b. All breakers and disconnect switches connected to the LV bus
must be rated 70kA RMS Symmetrical.
Case 1: For transformers 2TR-101A and 2TR-101B.
a. Primary Overcurrent Protection Device.
Determine primary full load current (FLA).
334.7A345003
1020I
6
P =×
×=
The spare breaker used as primary OCPD which is 1250A is
300% of the primary FLA. Based on Table 4.50.1.3(a) and
note 1 of the same table, this is permitted.
b. Secondary protection.
Based on Table 4.50.1.3(a), where the primary OCPD is 300%
of primary current the secondary conductor is considered
protected and does not require secondary OCPD.
Equation 16
18
Although secondary OCPD is not required in this situation, we
are required to install OCPD for the protection of panelboards
located downstream of secondary conductor.
Where a feeder supplies continuous loads, the rating of the
secondary OCPD may not be less than 125% of the
continuous load as per PEC Art 2.15.1.3.
Determine secondary full load current.
2775.7A41603
1020I
6
s =××=
125% x 2775.7 = 3469.63A
Say, 3150A.
The choice of 3150A is logical since all loads were assumed to
be continuous, which is not the case in the actual operation of
the plant.
Case 2: For transformers 2TR-201A, 2TR-201B, 2TR-202,
2TR-203, 2TR-204, 2TR-205 and 2TR-206.
a. Primary Overcurrent Protection Device.
Determine primary full load current (FLA).
346.97A41603
102.5I
6
P =×
×=
From Table 4.50.1.3(a), we can use 300% as the multiplying
factor for the primary current.
300% x primary FLA
300% x 346.97 = 1040.91A
Say, 1250A.
Equation 18
Equation 17
19
b. Secondary protection.
The same rules applies here as with the case of MV
transformers. Secondary OCPD is not required since primary
OCPD is size at 300% of the primary current.
However OCPD is required for the panelboards connected to
the transformer secondary.
Determine secondary full load current.
3608.4A4003
1020I
6
s =××=
125% x secondary FLA
125% x 3608.4 = 4510.5A
Say, 4000A.
Case 3: For Tie Breakers.
The tie breakers must be rated to be the same as the bus rating.
a. The bus tie breaker of 2BUS-101A and 2BUS-101B should
have a rating of 3150A, 50kA.
b. The bus tie breaker of 2BUS-201A and 2BUS-201B should
have a rating of 4000A, 70kA.
Case 4: For Breakers of Typical Motors and the Spare
Breakers at 2BUS-101A and 2BUS-101B.
For the simplicity and flexibility of the design it is advisable to size
all the other breakers to be the same as the transformer breaker.
Usually switchgear are manufactured by vendors in standard sizes
and buying one with customize sizes oftentimes more costly that’s
why it is advisable to maximize the sizes of the needed equipment.
Equation 19
20
Section 2 – Primary and Secondary Feeder
Sizing the feeder conductors does not only involve determining its
continuous current carrying capacity but also taking into
consideration its capacity to withstand the high magnitude of
currents during fault or short circuit.
Calculations for the size of primary and secondary feeder
conductors must comply with “PEC Art 2.40.1.4, conductors shall be
protected against overcurrent in accordance with their ampacities
specified in Art 3.10.1.15”. Feeder conductors should be protected
by an overcurrent device. The conductor ampacity shall not be less
than the overcurrent device setting or rating.
Derating factors for cables rated 2001V or over shall comply with
PEC Art 3.92.1.13. For feeder cables rated 2000V or less derating
factors shall comply with PEC Art 3.92.1.11.
To insure proper functioning of utilization equipment, it is
recommended that feeder conductors be sized such that the voltage
drop is limited to 3% as per Art 2.15.1.2(1)(3) FPN No. 2 and 3.
The estimated length of primary feeders for 2TR-101A and 2TR-
101B is 70m while the length of secondary feeders of the same
transformers including the length of primary and secondary feeders
of the other seven MV transformers (i.e. 2TR-202) are estimated to
be 15m.
21
Case 1: Feeder Size for Transformers 2TR-101A and 2TR-
101B
a. Primary Feeder (34.5kV).
1. Size according to OCPD.
Primary feeder ampacity rating shall not be less than the
rating of its OCPD which is 1250A.
From PEC Table 3.10.1.69, a single insulated copper
conductor size 250mm2, XLPE (Type MV-90), 15001-
35000V has an ampacity of 680A.
Use two (2) conductors per phase. Install in a single layer
in an uncovered cable tray maintaining a space not less
than one cable diameter between individual conductors in
accordance with PEC Art 3.92.1.13(b)(2).
2. Size according to short circuit current.
Using the thermal equation of a copper conductor
determine the minimum size of feeder that can handle the
short circuit current passing through the transformer
primary side.
++
×=
i
f10
5
2
SC
T234.5
T234.5log101.18t
A
I
Where: ISC = Short circuit current in amperes
A = Size of cable in mm2
t = Tripping time of the protective device in
seconds
Tf = Short circuit current temperature rating of
the cable in OC (250 OC for XLPE)
Ti = Continuous temperature rating of the
cable in OC (90 OC for XLPE)
Equation 20
22
The maximum amount of short circuit current that the
primary feeder can be subjected to is the same as the
fault current at the bus where it is connected. Therefore,
let us use the short circuit current rating of 1BUS-101A.
++×=
90234.5
250234.5log101.181
A
4000010
5
2
A=279.09mm2
Since the value determined from the first calculation is
larger than this, then the requirement is satisfied.
b. Secondary Feeder (4.16kV).
1. Size according to OCPD.
Secondary feeder ampacity rating shall not be less than
the rating of its OCPD which is 3150A.
From PEC Table 3.10.1.67, a single insulated copper
conductor size 500mm2, XLPE (Type MV-90), 2001-5000V
has an ampacity of 870A.
870 x 4 = 3180A
Use four (4) conductors per phase. Install in a square
formation maintaining free air space not less than 2.15
times the diameter (2.15 x O.D.) of the cable in
accordance with PEC Art 3.92.1.13(b)(3).
2. Size according to short circuit current.
Using the available fault current at the 2BUS-101A
calculate for the minimum size of feeder that can handle
23
the short circuit current passing through the transformer
secondary side.
++×=
90234.5
250234.5log101.181
A
5000010
5
2
A=348.86mm2
The requirement is already satisfied from the first
calculation.
3. Voltage drop calculation.
Per PEC Table 9.1.1.8, the DC resistance of a single
500mm2 copper conductor at 75OC is 0.0132 ohm/305m.
3lengthresistance4
FLA secondaryVD ×××=
0.78V315305
0.0132
4
2775.7VD =×××=
%VD = 0.78/4160 x 100 = 0.019%
Cable reactance is not considered in the calculation but
results shows that even if it is included the voltage drop is
likely to be below 3%.
Equation 21
24
Case 2: Feeder size for transformers 2TR-201A, 2TR-201B,
2TR-202, 2TR-203, 2TR-204, 2TR-205 and 2TR-206
a. Primary feeder (4.16kV).
1. Size according to OCPD.
Primary feeder ampacity rating shall not be less than the
rating of its OCPD which is 1250A.
From PEC Table 3.10.1.69, a single insulated copper
conductor size 250mm2, XLPE (Type MV-90), 2001-5000V
has an ampacity of 695A.
Use two (2) conductors per phase. Install in a single layer
in an uncovered cable tray maintaining a space not less
than one cable diameter between individual conductors in
accordance with PEC Art 3.92.1.13(b)(2).
2. Size according to short circuit current rating.
The minimum size of primary feeder conductor that can
handle the short circuit current passing through the
transformer primary side is the same size with the
secondary conductor of 2TR-101A which is 348.86mm2 as
determined from Equation 21 page 23. And since this is
smaller than the size from the first calculation then this
requirement is satisfied.
b. Secondary Feeder (400V).
1. Size according to OCPD.
Secondary feeder ampacity rating shall not be less than
the rating of its OCPD which is 4000A.
25
From PEC Table 3.10.1.17, a single insulated copper
conductor size 500mm2, XLPE (Type XHHW-2), 0-2000V
has an ampacity of 995A.
Applying adjustment factor from Art 3.92.1.11(b)(1).
6 x 995 x 0.75 = 4477.5A
Use six (6) conductors per phase. Install in accordance
with the provisions of Art 3.92.1.11(b)(1) and
requirements of Art 3.92.1.10.
2. Size according to short circuit current rating.
Using the available fault current at the 2BUS-202 (similar
to all seven MV transformer) calculate for the minimum
size of feeder that can handle the short circuit current
passing through the transformer secondary side.
++×=
90234.5
250234.5log101.181
A
7000010
5
2
A=488.41mm2
The requirement is already satisfied from the first
calculation.
3. Voltage drop calculation.
Per PEC Table 9.1.1.8, the DC resistance of a single
500mm2 copper conductor at 75OC is 0.0132 ohm/305m.
3lengthresistance6
FLA secondaryVD ×××=
26
0.68V315305
0.0132
6
3608.4VD =×××=
%VD = 0.68/400 x 100 = 0.17%
Cable reactance is not considered in the calculation but
results shows that even if it is included the voltage drop is
likely to be below 3%.
Section 3 -Neutral Grounding Resistor, Neutral Grounding
Conductor, System Grounding Conductor and Equipment
Grounding Conductor
Case 1: For transformers 2TR-101A and 2TR-101B
a. Neutral Grounding Resistor
Sizing the neutral grounding resistor (NGR) is dependent on
the decision of the design engineer. The common practice is
to use a 200A or 400A NGR for a medium voltage system.
Other consideration is to size the NGR higher than the
capacitive charging current of the system to avoid transient
overvoltage
“Every system has a capacitance value, mostly due to the
system's cables and surge arresters/capacitors. The general
rule of thumb for estimating this charging current is to use 1A
per 1,000kVA (Excerpt from www.ecmweb.com)”.
Let us calculate for the estimated capacitive charging current.
20A1000kVA
20000kVAIC ==
27
Since the recommended NGR rating is much higher than the
capacitive charging current then there would be no problem.
Let’s choose 400A, 10sec.
b. System Grounding Conductor
The system (neutral) grounding conductor must be able to
carry the ground fault current which is 400A.
From PEC Table 3.10.1.69, a single insulated copper
conductor size 125mm2, XLPE (Type MV-90), 2001-5000V
with an ampacity of 435A can be used. The conductor must
also have an insulation level as the phase conductors as per
PEC Art 2.50.10.7(b).
c. Equipment Grounding Conductor
1. Primary. Size the equipment grounding (bonding)
conductor for the transformer primary based on the size of
primary OCPD, per PEC Table 2.50.6.13.
For a 1250A OCPD, the recommended equipment
grounding size conductor is a 100 mm2 copper.
2. Secondary. Size the equipment grounding (bonding)
conductor in accordance with Table 2.50.3.17. The total
area of secondary conductor is 2000mm2 (4 x 500mm2)
copper.
Based on the table, the recommended system grounding
and bonding conductor size is an 80 mm2 copper.
28
Case 2: For transformers 2TR-201A, 2TR-201B, 2TR-202,
2TR-203, 2TR-204, 2TR-205 and 2TR-206
a. System Grounding and Bonding Conductor
The system grounding and bonding conductor must be size in
accordance with Table 2.50.3.17. The total area of secondary
conductor is 3000mm2 (6 x 500mm2) copper.
Based on the table, the recommended system grounding and
bonding conductor size is an 80 mm2 copper.
b. Neutral Conductor
As per PEC Art 2.20.3.22(c)(2), where the neutral conductor
of a 3-phase, 4-wire system is supplying nonlinear loads no
reduction in ampacity is required.
We have to size the neutral conductor to have an ampacity
equal to the ampacity of phase conductors. Therefore the
neutral conductor is also six 500mm2 copper.
c. Equipment Grounding Conductor
1. Primary. Size the equipment grounding (bonding)
conductor for the transformer primary based on the size of
primary OCPD, per PEC Table 2.50.6.13.
For a 1250A OCPD, the recommended equipment
grounding conductor size is a 100 mm2 copper.
2. Secondary. The secondary side equipment grounding
conductor is size in the same manner as the system
grounding (bonding) conductor. Therefore the size is also
an 80 mm2 copper.
29
Section 4 –Miscellaneous Electrical Details
Grounded conductors (neutral) should be identified as white or gray
(PEC Art 2.0.1.6) and equipment grounding/bonding conductors
shall be identified as green or green with yellow stripes (PEC Art
2.50.6.10). Phase or ungrounded conductors on the other hand
must be readily identifiable with other colors.
The color identification scheme below for the phase conductors is a
common practice in the USA, using Black, Red and Blue for Phase A,
Phase B and Phase C respectively.
a. Figure 7 - Schematic Diagram of a Solidly Grounded
System
b. Figure 8 - Schematic Diagram of a Resistance Grounded
System
30
Part 3 – Time – Current Curve (TCC) Coordination
For the purpose of our analysis and calculations, let us consider the
possible scheme of coordination and settings of the protective
devices from the 34.5kV HV bus down to the 400V LV bus. Refer to
Figure 9 below for the illustration.
The four circuit breakers CB1, CB2, CB3 and CB4 are to be
coordinated to achieve selective coordination. These breakers
should operate progressively from LV bus up to the HV bus should a
fault occurs at the LV bus. Another objective is that whenever a
fault occurs, the immediate breaker located to the upstream of the
fault should be the one to operate first in order to clear the
downstream fault.
Figure 9 – System diagram showing LV, MV
and HV bus for the TCC coordination.
31
Short Circuit Calculations:
For a simpler analysis let us consider the utility to be the sole
source of fault current, neglect contributions from motor loads.
Refer to Figure 10 below for the system impedance diagram.
Figure 10 – Equivalent system impedance diagram
with utility as sole source and 2BUS-202 as faulted bus
The fault currents per bus are:
1. For 2BUS-202.
0.58563pu0.4350.140.01063ZT =++=
RMS 40.5kA4413
10 20
0.58563
0.9070I
6
SC =×××=
2. For 2BUS-101A/B
0.15063pu0.140.01063ZT =+=
RMS 16.7kA43703
10 20
0.15063
0.9519I
6
SC =×××=
The Extremely Inverse Time-Current Curve
The Extremely Inverse TCC is best selected when the application is
transformer protection because it matches the transformer damage
curve profile. Below is the equation of the Extremely Inverse TCC.
=1-I
80TDt
2
32
Where: t = tripping time of relay in sec
I = multiple of Setting Current
TD = Time Dial
Setting for CB1 Relay
a. Time Overcurrent (TOC) Setting
1. Tap Setting.
Assume setting = 125% IS
TAP = 1.25 x 3608.44 (1/4000)
= 1.13A
Use: TAP = 1.2A
2. Time Dial (TD).
Use: TD = 0.1
3. Compute for relay tripping time (t) for a fault at 2BUS-202.
( )[ ] 0.114sec1-40001.21040.5
800.1t
23=
×÷×=
The calculated time seems a good setting. This will give
enough time for the protective devices (MCCBs) of the loads
connected to 2BUS-202. The estimated clearing time of
MCCBs is 0.025sec (1.5cycles).
b. Instantaneous Setting
This function should be disabled in order to achieve selectivity
for faults on outgoing lines from 2BUS-202.
Refer to Figure 11 page 37 for the TCC of CB1 Relay using
ABB RXIDK 4 relay set to Extremely Inverse curve
characteristic.
33
Setting for CB2 Relay
a. Time Overcurrent (TOC) Setting
1. Tap Setting.
Assume setting = 200% IP
TAP = 2 x 346.96 (1/400)
= 1.73A
Use: TAP = 1.7A
2. Time Dial (TD).
The Time Dial must be coordinated with transformer 2TR-
202 magnetizing inrush and its damage curve. It must also
have at least 0.3sec margin above CB1 Relay allowing the
later to trip first before it can operate. Using the TCC
equation, calculate for TD.
( )
×÷×=+
1-4001.7)4160
420(1040.5
80TD0.3)(0.114
2
3
TD = 0.1819
Use: TD = 0.2
b. Instantaneous Setting
This setting should be above the calculated fault at 2BUS-202
so that it will allow CB1 Relay to operate first for a fault at the
mentioned bus.
Setting = 175% IF(2BUS-202) (1/TR ratio)
= 1.75 x 40,500 (1/400)(0.42/4.16)
= 17.89A
34
For the Multiple (M) of TOC setting:
M = 17.89/1.7
= 10.52
Use: 11
Refer to Figure 11 page 37 for the TCC of CB2 Relay using
ABB RXIDK 4 relay set to Extremely Inverse curve
characteristic and the Instantaneous Pick-up set to 20.
Setting for CB3 Relay
a. Time Overcurrent (TOC) Setting
1. Tap Setting.
Assume setting = 125% IS
TAP = 1.25 x 2775.7 (1/3000)
= 1.16A
Use: TAP = 1.2A
2. Time Dial (TD).
A Time Dial must be selected to allow at least 0.3sec delay
for a fault at 2BUS-101A/B since large motors are
connected here and uses relays as tripping unit for their
OCPDs.
( )[ ]
×÷×=
1-30001.21016.7
80TD(0.3)
23
TD = 0.0769
Use: TD = 0.1
3. Compute for relay tripping time (t) for a fault at 2BUS-
101A/B.
( )[ ] 0.39sec1-30001.21016.7
800.1t
23=
×÷×=
35
b. Instantaneous Setting
This function should be disabled in order to achieve selectivity
for faults on outgoing lines from 2BUS-101A/B.
Refer to Figure 11 page 37 for the TCC of CB3 Relay using
ABB RXIDK 4 relay set to Extremely Inverse curve
characteristic.
Setting for CB4 Relay
a. Time Overcurrent (TOC) Setting
1. Tap Setting.
Assume setting = 180% IP
TAP = 1.8 x 334.7 (1/400)
= 1.51A
Use: TAP = 1.5A
2. Time Dial (TD).
The Time Dial must be coordinated with transformer 2TR-
101A magnetizing inrush and its damage curve. It must
also have at least 0.3sec margin above CB3 Relay allowing
the later to trip first before it can operate.
( )
×÷
×
=+
1-4001.51016.7
80TD0.3)(0.39
2
3
5.34
37.4
TD = 0.0985
Use: TD = 0.1
36
b. Instantaneous Setting
This setting should be above the calculated fault at 2BUS-
101A so that it will allow CB3 Relay to operate first for a fault
at the mentioned bus.
Setting = 175% IF(2BUS-101A) (1/TR ratio)
= 1.75 x 16,700 (1/400) (4.37/34.5)
= 9.25A
For the Multiple (M) of TOC setting:
M = 9.25/1.5
= 6.17
Use: 7
Refer to Figure 11 page 37 for the TCC of CB4 Relay using
ABB RXIDK 4 relay set to Extremely Inverse curve
characteristic and the Instantaneous Pick-up set to 20.
37
Figure 11 – Time-Current Curve Coordination analysis.
38
Part 4 – Load Flow Calculations
Load flow calculations are divided into the following sections:
Section 1 – Motor starting Analysis
Section 2 – Power Factor Capacitor Sizing Calculations
Section 3 – System Harmonic Analysis and Calculations
Section 1 – Motor starting Analysis
The subject of our analysis is the 1239kW motor connected to the
MV bus since it is the largest motor.
The required voltage across the motor terminal should be at least
80% of the motor rated voltage during starting.
Assumptions/conditions:
1. The motor is to be started when the 20MVA transformer is
loaded to about 80% of its rating, excluding the motor itself.
2. Only one (1) – 20MVA transformer is operating at the time
when the motor is started. This will provided the greatest
voltage drop since transformer impedance is greatest in this
condition.
3. The motor and loading profile is as follows:
a. Motor – 1239kW, 4160V, 90% efficiency, 80% power
factor and 600% LRC.
b. Other load (composite) – 16MVA, 4160V and 80% power
factor.
39
Solution:
Refer to Figure 12 below for the equivalent single line diagram.
Figure 12 – Motor starting analysis single line diagram.
1. At 1882MVA power base; 34.5kV and 4.37kV voltage bases;
ZU = j1pu
j13.174pu20
188214ZTR =
= .0
pu j63.9685.274.37
4.16
36.8716
1882Z
2
L +=
°−∠=
( ) pu j99.11132.146
1
4.37
4.16
36.870.90.81.239
1882Z
2
M +=
°−∠÷÷=
Since Load and Motor impedances are in parallel, hence,
pu j38.8751.83ZZ
ZZ
ML
ML +=
+•
40
pu 45.9774.57
1
13.74j1j38.8751.83
1
puZ
pu VI
T ∠=
+++==
Then the starting voltage (VST) is,
pu 0.873 45.9774.57
9013.174 9011VST =
∠∠+∠−=
VST = 4370 (0.873) = 3815.01V
91.71% 4160
3815.01 =
Based on the result, there will be no problem starting the
motor.
Section 2 – Power Factor Capacitor Sizing Calculations
Given the following data calculate for the size of capacitor needed to
improve the average power factor from 80% (typical value if data is
not available) to 96% (Client requirements).
The following data were based on the plant load list:
a. Motors on continuous duty.
11,200kW (Duty Factor = 100%)
b. Motors on intermittent duty.
167kW (Duty Factor = 30%)
c. Motors on standby duty.
1979kW (Duty Factor = 10%)
The total active load is,
11,200(100%) + 167(30%) + 1979(10%) = 11,448kW
°== − 36.87 0.8cosPFθ 1OLD
41
°== − 16.26 0.96cosPFθ 1NEW
Calculate for the rating of the capacitor,
( ) ( )[ ]NEWOLDC PFθtanPFθtanPowerMVAr −=
( )°−°= tan16.26tan36.8711.448MVArC
MVArC = 5.247
Install two (2) banks of 2.7MVAr, 3-phase capacitor having 900kVAr
per phase each. Install one (1) for 2BUS-101A and one (1) for
2BUS-101B.
Section 3 – System Harmonic Analysis and Calculations
The possibility of harmonic problem is present due to the fact that
many of the motor loads are driven by Variable Speed Drives
(VSD). Variable Speed Drives are known contributors of 5th and 7th
order harmonics. Of the two, the 5th order harmonic has the largest
contribution of harmonic currents. This section will present an
analysis of the system harmonics and a design of single tuned
harmonic filter for the 5th order harmonic.
Data and assumptions:
1. Based on the load list about 3200kW of the motors used for
process areas are driven by variable speed drives (VSD).
2. In addition to the 3200kW harmonic power source coming
from VSD driven motors, let’s assume a 300kW harmonic
power source coming from lighting and computer loads.
42
Analysis and design:
1. Determine Short Circuit Ratio (SCR).
The SCR is a ratio of the short circuit MVA to the harmonic
power source at the Point of Common Coupling (PCC). “If the
SCR is less than 20, and there is a parallel resonance
condition near to a characteristic harmonic of the non-linear
load, there will probably a problem. A study should be made
to determine the possible addition of harmonic filters to
eliminate any problem (excerpt from Power System Design by
Benigno S. Jimenez, PEE)”.
Refer to Figure 13 below for the equivalent single line diagram
showing harmonic power source.
Figure 13 – Harmonic analysis single line diagram.
43
H
SC
MW
MVASCR =
From Equation 12 page 13, ISC = 40,149A.
82.65103.5
4014941603
MW
MVASCR
6H
SC =×
××==
Since the SCR is greater than 20, the probability of harmonic
problem is low. However, try to evaluate for possible
resonance problem.
2. Evaluate for the possibility of parallel resonance.
Parallel resonance occurs when the system inductive
reactance and capacitive reactance are equal at some
frequency. If the combination of capacitor banks and the
system inductance result in parallel resonance near one of the
characteristic harmonics generated by the non-linear loads,
that harmonic current will excite the system, thereby causing
an amplified current to oscillate between the energy at the
inductance and the energy in the capacitance. This high
oscillating current can cause excessive voltage distortion.
To determine whether the possibility of harmonic problem
exists, the formula can be used:
C
SCP
MVAr
MVAH =
7.325.4
289.29HP == (Near 7th order harmonic)
Result of the calculation shows that a possible parallel
resonance might occur in the 7th order harmonic frequency.
44
Earlier it was mentioned that VSDs are contributor of 7th order
harmonic. Though majority of its contribution is in the 5th
order harmonics but analysis shows that additional filter tuned
to the 7th order harmonics might be needed if investigation
during the plant operation shows problems caused by this
order of harmonic.
3. Details of the 2.7MVAr capacitor.
Figure 14 – The 2.7MVAr capacitor bank.
The current per phase is,
347.72A41603
102.7I
6
C =×
×=
The reactance per phase is,
j6.91Ω347.72
34160/XC −==
45
4. Size the reactor and design the filter for 5th harmonic.
Figure 15 – Harmonic filter diagram.
j0.276Ω5
6.91
H
XX
22
CL ===
362.04Aj6.91-j0.276
34160/
XX
EI
CL
T ==+
=
The 5th harmonic current is,
97.15A34160
103.5
5
1
3V
Power
H
1I
6
L
5 =
×=
=
The voltage across the capacitor is,
+=H
XIXIV C5CTC
( ) 2635.96V5
6.9197.156.91362.04VC =
+=
Allowing a factor of 1.2 for the filter,
2
5
2
TFILTER RMS II1.2 I +=
449.82A97.15362.041.2 I 22FILTER RMS =+=
Use: 450A, 2.7kV Reactor, in series with the 900kVAr
capacitor in each phase.
46
Chapter 4 – Auxiliary Systems
This chapter is divided into four (4) parts namely;
Part 1 – Fire Pump and Fire Alarm System Diagram
Part 2 – Paging System Diagram
Part 3 – Telephone and I.T. System Diagram
Part 4 – Security System (CCTV) Diagram
Part 1 – Fire Pump and Fire Alarm System
Section 1- Fire Pump Motor
The fire pump motor circuit protection, conductor size, power
source and installation must comply with PEC Art 6.95. The fire
pump motor size that will be used in this section is an estimated
size based on the common practice in the industry. Should the final
size of the pump as determined by the responsible discipline differ
from what is presented here, the calculation method presented here
shall in turn serve as a guide. A motor used to drive a 1000gpm at
150psi fire pump has the following specifications:
120kW, 400V, 3Phase, 60Hz, 0.8Power Factor, 90% Efficiency
Power Source (Art 6.95.1.4). The power source for the fire pump
motor shall provide continuity of power. For a 120kW, 400V motor,
the possible power source can be any of the six LV MCC bus since
all of them provides redundancy of power source.
Disconnecting Means (Art 6.95.1.4). The disconnecting means
must:
1. Be identified as suitable for use as service equipment.
2. Be lockable in the closed position.
47
3. Not be located within equipment that feeds loads other than
the fire pump.
4. Be located sufficiently remote from other building or other
fire pump source disconnecting means.
5. Be marked “Fire Pump Disconnecting Means.” The letters
must be at least 25mm in height and be visible without
opening enclosure doors or covers.
Power Wiring (Art 6.95.1.6). Route the supply conductors outside
buildings, where possible. When this is not possible, install in
accordance with Art 6.95.1.4(b). In either case, install these
conductors as service entrance conductors in accordance with Art
2.30.
Overcurrent Protection (Art 6.95.1.5). Overcurrent protection
devices (OCPDs) must be sized to carry the sum of the locked-rotor
current of the fire pump and pressure maintenance pump motor(s)
indefinitely, and 100% of the ampere rating of the fire pump's
accessory equipment. For a 120kW, 400V, 0.8pf and 0.9Eff.,
240.6A0.90.84003
120,000I =
×××=
6 x 240.6 = 1443.6A
Use: 1600A Breaker
Voltage Drop. The voltage at the line terminals of the controller,
when the motor starts (locked-rotor current), must not drop more
than 15% below the controller's rated voltage. The voltage at the
motor terminals must not drop more than 5% below the voltage
rating of the motor when the motor operates at 115% of the fire
pump full-load current rating.
48
a. Evaluate the voltage drop during starting.
1. The conductor size is 125% x full load current.
1.25 x 240.6 = 301A
Use: 250mm2 (Table 3.10.1.16)
2. The estimated conductor length is 150m. The resistance
from Table 9.1.1.8 is 0.0265ohm/305m.
3. The fault current at LV bus is 59076A at 400V from
Equation 15 page 15.
4. Refer to Figure 16 below for the equivalent impedance
diagram.
Figure 16 – Fire Pump Motor Starting diagram.
Calculate for the starting current (Is) using per unit method:
The short circuit MVA at the bus is,
40.93590764003
MVABUS =××=610
At 40.93MVA base; 400V base voltage;
pu j1 ZBUS =
pu j20.4652
40.93 ZL ==
49
pu j24.5632.746
1
36.87-0.9)0.8(0.12
40.93 ZM +=
°∠÷÷=
3.33pu59076)3(400/
1500.0265/305 ZCABLE =
÷×=
Since Load and Motor impedances are in parallel, hence,
pu j14.804.54ZZZ
)Z(ZZ
MCABLEL
MCABLEL +=
+++•
pu j15.804.54
1
j1 j14.804.54
1
puZ
pu VI
T +=
++==
Then the starting voltage (VST) is,
pu 0.9416 73.9716.44
9011VST =
∠∠−=
VST = 400 (0.9416) = 377V
94.25% 400
377 =
Based on the result, there will be no problem starting the
motor.
b. Evaluate the voltage drop (VD) at 115% FLA.
( )R1.15I 3VD FL=
( )( ) 6.25V1500.0265/305240.61.153VD =××=
98.44% 400
6.25-400 =
50
Section 2 - Fire Alarm System Diagram
The Fire Alarm System Diagram in Figure 17 page 51 is based on
the design philosophy developed by Fluor Philippines Control
Systems Department. Some modifications were made in order to
suit the just needed requirement of this report.
Part 2 – Paging System Diagram
The Paging System Diagram in Figure 18 page 52 is based on the
design philosophy developed by Fluor Philippines Control Systems
Department. Some modifications were made in order to suit the just
needed requirement of this report.
Part 3 – Telephone and I.T. System Diagram
The Telephone System and I.T. Diagram shown in Figure 19 page
53 is based on the design philosophy developed by Fluor Philippines
Control Systems Department. Some modifications were made in
order to suit the just needed requirement of this report.
Part 4 – Security System (CCTV) Diagram
The Security System (CCTV) Diagram shown in Figure 20 page 54 is
based on the design philosophy developed by Fluor Philippines
Control Systems Department. Some modifications were made in
order to suit the just needed requirement of this report.
51
Figure 17 – Fire Alarm System Diagram
52
Figure 18 – Paging System Diagram
53
Figure 19 – Telephone System and I.T. Diagram
54
Figure 20 – Security System (CCTV) Diagram
55
Chapter 5 – Conclusions / Recommendations
After conducting all the calculations, analysis and design, the author
have the following observations and recommendations:
1. An additional harmonic filter for the 7th order harmonic must
be installed after verifying that a parallel resonance occur in
this frequency and may cause problems.
2. Providing an emergency generator can be a good idea in order
to provide continuity of power to the fire pump.
3. The production area is of considerable distance from the
substation. A better way of providing power to the loads
located is this area is to install distribution boards and MCCs
inside the building. This will result in a huge reduction of cable
trays needed to be routed since only panelboards and MCC
feeders are coming directly from the substation. This will also
minimize the available fault in the load side of the motors and
reduce voltage drop.
56
References
The following are the references used by the author:
1. Philippine Electrical Code (PEC).
2. National Electrical Code (NEC).
3. International Electrotechnical Commission (IEC)
4. National Electrical Manufacturers Association Standard
(NEMA).
5. Institute of Electrical and Electronics Engineers Standards
(IEEE).
6. Other references, books, engineering articles in the World
Wide Web.
57
Affidavits
1. Affidavit of Sole Authorship.
2. Affidavits of the three vouching PEEs.
58
59
60
61
62
63
64
65
Curriculum Vitae
66
67
68
69
70
71