Safety Precautions
To ensure safety of humans and the equipment, pay attention to the safety symbols on the equipment
and all the safety instructions in this document. The "NOTE", "CAUTION", and "WARNING" marks in
other documents do not represent all the safety instructions. They are only supplements to the safety
instructions. When operating Huawei equipment, in addition to following the general precautions in this
document, follow the specific safety instructions given by Huawei. Huawei will not be liable for the
consequences that are caused by the violation of the safety operation regulations and design,
production, and usage standards.
Local Safety Regulations
When operating Huawei equipment, you must follow the local laws and regulations. The safety
instructions in this document are only supplements to the local laws and regulations.
Personnel Requirements
Only trained and qualified personnel are allowed to install, operate, and maintain Huawei equipment.
You can modify default parameters only after being granted approval from Huawei technical support.
Symbols
■
Alerts you to a potentially hazardous situation that could, if not avoided, result in equipment damage,
data loss, performance deterioration, or unanticipated results.
Provides additional information to emphasize or supplement important points of the main text.
■
■
■
Precautions
Human Safety
To prevent electric shock, get tools insulated and wear electrostatic discharge (ESD) gloves when
connecting cables.
To prevent dust inhalation or contact with the eyes, take adequate preventive measures when drilling
holes.
■
Installation Tools
Flat-head screwdriver (M3 and M4)
Phillips screwdriver (M3 and M4) Adjustable wrench Claw hammer Diagonal pliers
COAX crimping tool
Wire stripper Hydraulic pliers Fuse extracting unit PVC insulation tape Electrician's knife
Hammer drill Heat gun
Socket wrench Marker Heat shrink tubing
ESD gloves
Cable tie
Clamp meter
Crane (with a capacity of greater than 2 t)
Hoist cable (7 m or 22.97 ft)
Antitheft wrench
Protective gloves Insulation gloves
Removable gantry (consisting of two triangle supports, one guide beam,
and one lever block) Torque wrench
2
Power Cube Architecture and Network Diagram
Outdoors
Mandatory Device
Device only used in the
Scenario with a New
D.G.
Device only used
in the
Scenario with
a Reused
D.G.
Optional Device
ECC ESC-1D(DCB) EPS-10G The backup
D.G.
The reused D.G. Mains
suppiy
ESPS48200B DC ammeter
New D.G.
New D.G. +
Mains
New D.G. +
External D.G.
New D.G. +
Solar
New D.G. +
Solar+ Mains
New D.G. +
Solar+ Back
up D.G.
Reused D.G.
Reused D.G. +
Mains
1. ECC and ESC-1D is Mandatory Device.
2. EPS-10G only used in the scenario with new diesel generators provide main power supply. The reused D.G. used in the scenario with
new diesel generators provide backup power, and it is also called backup D.G.. The reused D.G. used in the scenario without new D.G.
provide main power supply.
3. Indoor DC air conditioner only used in indoor scenario.
4. The backup D.G., Mains supply, ESPS48200B, DC ammeter, is optional.
Scenario
Device
3
Power Cube
EPS-10G
ECC
ESC-1D
Power Cube
Power Cube Architecture and Network Diagram
HPMU
Power system
DC
air c
on
ditio
ne
r/na
tura
l ve
ntila
tion
DCB d1
d2
s1
s3
s2
(d1) DC power cable to the DC air conditioner or natural
ventilation in the ESC
(d2) DC power cable between the DCB and the power system
(s1) Signal cable to the DC air conditioner or natural
ventilation in the ESC for alarm generation
(s2) Signal cable to the battery temperature sensor in the ESC
(s3) Signal cable to the door status sensor in the ESC
Power Cube architecture
a
ECC ESC-1D
DC power cable (d)
Signal cable (s)
AC power cable (a)
Optional
Do
or s
tatu
s
se
nso
r
Batte
ry
tem
pera
ture
sen
so
r
4
Network diagram
b
(a1) AC input power cable to the external D.G
(a2) AC input power cable for mains supply
(d1) DC power cable to the DC-powered load
(d2) DC power cable between PV modules and the junction box
(d3) DC power cable between the ESPS48200B and the junction box
(d4) DC power cable to indoor DC air conditioner 1
(d5) DC power cable to indoor DC air conditioner 2
(s1) Signal cable between the OMU and the transport network . (Optional, Global System for Mobile Communications (GSM)
antenna is required when the OMU is connected to the transport network by GPRS.)
(s2) Signal cable for controlling the external D.G.
(s3) Signal cable to indoor DC air conditioner 1 for alarm generation
(s4) Signal cable to indoor DC air conditioner 2 for alarm generation
With a New
D.G.(Outdoors)
DC-powered load
D.G.
Fuel tank
ECC
ESC
-1D
GPRS/IP
Network NetEco
Back up D.G.
Junction box PV modules Power Cube
a1
a2
d1
d2
d3
s1
s2 Mains supply
5
Installation Procedure
This document takes New D.G. + DCB as the basic scenario, please
installing other scenarios according to the basic scenario.
1.New D.G.+DCB (Outdoors)
a. Securing the Power Cube
b. Switching Off All Power Circuit
Breakers of the Power Cube
c Adding Diesel Fuel, Engine Oil,
and Water to the EPS
d. Installing DCBs
a. Connecting a Ground Cable to
the ECC
b. Connecting Cables Between the
ECC and Both the DC Air
Conditioner and Door Status
Sensor
c. Connecting Cables Between the
ESC and the ECC
d. Connecting a Ground Cable to
the ESC
e. Connecting a Power Cable to
the D.G. Storage Battery
f. Connecting DC Power Cables to
DC-powered Loads
g. Connecting Communications
Cables to the HPMU
i. Checking Cable Connections
a. Powering On Batteries
b. Set parameters on the HPMU
c. Powering On the D.G.
d. Powering On Loads
1) Installing Devices
2) Installing Cables
3) Powering On and
Commissioning the Power Cube
h. (Optional, only used without
NetEco) Connecting Signal
Cables to the HPMU
6
New D.G.+DCB (Outdoors)
1. Installing Devices
Securing the Power Cube a
Route hoist cables through the four lifting holes at the bottom of the Power Cube and secure them at the base of the energy
plant system (EPS). Then hoist the EPS and the ECC to the installation place using a crane.
1.To avoid friction between the hoist cables and the
cabinet when hoisting the Power Cube, place foamed
plastics where the hoist cables contact the cabinet.
2.For disassemble the Power Cube into the ECC, D.G.,
and base fuel tank, and then install them, please see the
Removing and Installing the Power Cube Quick
Installation Guide.
If paint flakes off during transportation, repaint the
areas devoid of paint. The cabinet bottom is the
particular place to the focused on, because the bottom
fuel tank may leak if it rusts.
Install expansion bolts in the mounting holes to secure the cabinet.
Φ: 16 mm
(0.63 in.)
M12x60 (4 pcs)
55–60 mm
(2.17–2.36 in.)
Marker
If the concrete base is to small , please install the expansion bolt inside the Power Cube.
Unit: mm
7
Determine the place for installing the ESC using a marking-off template and install expansion bolts.
Ф 16
Socket wrench
Bolt Spring washer Flat washer Expansion tube
M12x60 (4 pcs)
55–60 mm
(2.17–2.36 in.)
Fasten hoist cables to the lifting eyes on the ESC top and hoist the ESC to the installation place.
Securing the ESC using expansion bolts.
Antitheft
bolt
OFF
OFF
Power system
BC
Switching Off All Power Circuit Breakers of the Power Cube b
Switch off the AC, BAT1–, BAT2–, BLVD, and
LLVD circuit breakers in the power distribution
unit (PDU) of the power system in the ECC and
turn off the BC power switch.
Switch the DG INPUT, MAINS INPUT, and AC output circuit
breakers as well as the auto mains failure (AMF) power switch of
the Integrated Automatic Transfer Switch (IATS) to the OFF
position. Press the EMERGENCY STOP button.
OFF OFF
OFF
Notes: Please must
do it and fasten
battery cabin.
8
Adding Diesel Fuel, Engine Oil, and Water to the EPS c
Add 800 to 1000 liters of diesel fuel at the diesel fuel filler port.
Add 6 liters of engine oil at the oil pan filler port and 37 liters of engine oil at the auxiliary engine oil filler port.
Yanmar and Kubota can be in EPS-10G, the operation must according to actual conditions.
Diesel fuel
filler port
Yanmar
Please use manual
pump to add engine oil
at the oil pan filler port.
Oil pan filler port
Auxiliary
engine oil
filler port
Yanmar
Notes: Please do not
reuse a water pipe or
oil pipe to instead
diesel oil pipe.
Notes: Please do not
reuse a water pipe or
diesel oil pipe to
instead oil pipe.
9
Add about 14 liters of water at the water filler port.
Water filler port
Installing DCBs
d
Switch the circuit breaker in the ESC to the OFF position. The battery baffle should be rotate 90 degree for the ESC-1D
with DC air conditioner.
90 °
ESC-1D (DC air
Conditioner)
DC air conditioner and natural Ventilation can be used in the door of ESC-1D, the operation must according to actual
conditions.
Battery baffle
Notes: Please do not
reuse a oil pipe or
diesel oil pipe to
instead water pipe.
10
- 48V
RTN+
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
(connect negative
terminal of battery) + - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
Install DCBs and connect cables between them. Connect DCBs and the ESC busbar.
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
+ - + - + -
1. DCBs must be placed in strict accordance with the following figure. Otherwise, you will not be able to connect cables to the
DCBs or the DCBs will short circuit.
2. When connecting cables to DCBs, wear protective gloves and use insulated tools (such as a wrench with its handle wrapped
with PVC insulation tape).
3. Partially tighten bolts first. After all cables are connected to DCBs, tighten the bolts on DCBs. The reference torque for
tightening bolts is 20–25 N.m (177.02–221.27 lbf.in.).
4. Before connecting a cable to a DCB, remove the protective lid from the DCB and then reinstall it after connecting the cable.
2. Connecting Cables
Cord end
terminal
OT terminal Heat shrink
tubing
COAX crimping tool Hydraulic
pliers
Heat gun
Prepare terminals as required before connecting cables. Cabling of the PowerCube.
- 48V
(connect to the
electrical control
cabinet)
No. Cable One End Appearance The Other End
1
Positive power
cable to the DC
air conditioner
RTN port on the ESC
transfer busbar
RTN+ busbar of the PDU in the
power system of the ECC
2
–48 V DC power
cable to the DC
air conditioner
–48V port on the ESC
transfer busbar
DC output LLVD F14 (20A) circuit
breaker of power system in the ECC
3
Signal cable to the
DC air conditioner
for alarm
generation
ALM port on the ESC
transfer busbar
DI6 port on the analog digital
input/output (ADIO) of the HPMU in
the ECC
4 Signal cable to the
door status sensor
GATE port on the ESC
transfer busbar
DI5 port on the ADIO of the HPMU in
the ECC
11
Connecting a Ground Cable to the ECC a
Site ground bar
ECC ground bar
The cross-sectional area of the ground cable is 25 mm2 (0.98 in.2).
b Connecting Cables Between the ECC and Both the DC Air Conditioner and Door Status Sensor
Notes: Please make the
connected cable and the
label at the two ports of
cable , that named ‘site
ground’.
12
Connecting Cables Between the ESC and the ECC c
No. Cable One End Appearance The Other End
1 Positive output DC power cable to storage batteries
Positive busbar of the ESC
BAT1+ port on the battery transfer busbar in the ECC
2 Negative output DC power cable to storage batteries
Negative busbar of the ESC
BAT1– port on the battery transfer busbar in the ECC
3 Signal cable to the battery temperature sensor
Battery temperature sensor
TEM_BAT port of the CPMU01 in the ECC
GATE ALM RTN -48V
DI5 DI6
+ -
1
1
2
3 4
2
3 4
F14(20A)
- +
-
+
+ + + - - -
Please install the cable of
the ESC-1D (natural
ventilation) according to
ESC-1D (DC air
conditioner), the
installation method is the
same.
Notes: Please make the
connected cables and
the label at the two
ports of every cable ,
that named:
1. ‘RTN-air con’.
2. ‘-48V-air con’.
3. ‘ALM+’
‘ALM-’…AS the
figure DI5.
4. ‘GATE+’.
‘GATE-’ …AS the
figure DI6.
13
Connecting a Ground Cable to the ESC d
ECC ground bar
ESC ground bar
BAT1+
BAT1-
RTN
-48V
1
2
1
2
3
3
TEM_BAT
Protective covers must be removed from the positive busbar of the ESC, negative busbar of the ESC, and battery transfer busbar in the ECC
before cable connection and must be reinstalled after cable connection.
Notes: Please make the
connected cables and
the label at the two
ports of every cable ,
that named:
1. ‘RTN-BAT1+’.
2. ‘-48V-BAT1-’.
Notes: Please make the
connected cables and
the label at the two
ports of every cable ,
that named: ‘ESC
ground’.
DC-powered load
1
2
BLVD LLVD
14
Connecting a Power Cable to the D.G. Storage Battery e
No. Cable One End Appearance The Other End
1 Power cable to the D.G.
storage battery
Negative terminal of the D.G.
storage battery Generator (connected)
Remove the protective lid from the negative terminal of the D.G. storage battery.
Push back the protective lid of the negative cable to expose the wiring terminal.
Connect the negative cable to the negative terminal of the D.G. storage battery. Reinstall the protective lid to the wiring terminal.
Connecting DC Power Cables to DC-powered Loads f
No. Cable One End Appearance The Other End
1 Positive DC power cable to
the DC-powered load
RTN+ busbar of the
Power system
DC input positive terminal of
the DC-powered load
2 Negative DC power cable to
the DC-powered load
DC output circuit breaker
of the Power system
DC input negative terminal of
the DC-powered load
- +
The pictures are for reference
only. The operation must be in
accordance with the actual
conditions.
When Connect the negative cable to the negative terminal of the
D.G. storage battery, the reference torque for tightening bolts is
5 N·m.
Step1
Step2
Step3
Notes: Please make the
connected cable and the
label at the two ports of
cable , that named :
1.XX+
XX-;
… about the loads.
15
Connecting Communications Cables to the HPMU g
1 Install the subscriber identity model (SIM) card.
(Optional: only installing when OMU is used) Out-of-Band Communication
SIM
Install the SIM card.
Remove the model card. Step 1
Step 2
2 Install the Global System for Mobile Communications (GSM) antenna.
GSM antenna
RF
The GSM antenna is
installed in the
upper part of the
side panel of the
ESC cabinet.
Cable One End Appearance
GSM antenna (Optional) RF port of the OMU
IP Network
ETH
Transmission equipment that supports TCP/IP
Cable One End Appearance The Other End
(Optional) Communications cable
between the OMU and the Ethernet ETH port of the OMU IP network
mo
de
l ca
rd
Scenario 1: Communication over the GPRS
Scenario 2: Communication over the Ethernet
If the GSM antenna base has a plastic shell,
remove the plastic shell to ensure a good
magnetic attachment.
16
In-Band Communication (over the HPMU)
Prepare a cable as shown in the following figure.
View A
T+
1 8
Pin Number of the
RJ45 Connector to
the MON Port of
the UMTS13.0 or
GBSS12.0
Pin
Identification
of the
Connector to
the COM_OUT
Port of the
HPMU
1 T+
2 T-
4 R+
5 R-
T- R+ R-
Scenario 1: UMTS13.0 and GBSS12.0 (excluding the BTS3900E)
1
Connect the communications cable.
2
Scenario 2: GBSS12.0 (pole-mounted BTS3900E)
COM_OUT
MON1 BBU
HPMU
T+ T- R+ R-
Prepare a cable as shown in the following figure.
Pin Number
of the DB15
Connector to
the MON Port
of the
BTS3900E in
the
GBSS12.0
Pin
Identificat
ion of the
Connecto
r to the
COM_OU
T Port of
the
HPMU
11 R-
12 R+
13 T-
14 T+
1
COM_OUT
Cable One End Appearance The Other End
(Optional) Communications cable
between the UTMS13.0 and the HPMU MON1 port of the base band
unit (BBU)
COM_OUT port
of the HPMU
Connect the communications cable. 2
COM_OUT
MON port of the BTS3900E in the GBSS12.0
HPMU
T+ T- R+ R-
Please check that OMU-B is not installed over the In-Band Communication, if OMU-B is installing, please remove it.
17
(Optional, only used without NetEco) Connecting SignalCables to the HPMU h
The following table describes the signal cables connection to the HPMU.
Port Default Settings (only used after software Version 827 of the
HPMU)
DO1 D.G. run.
When DO_1 is closed, an alarm is generated.
(connect to communication equipment )
-
DO2 Reset D.G. 1. (connect to the EPS-10G or the reuse D.G. ) D.G. fault.
When DO_2 is closed, an alarm is generated.
DO_2 can be set to report alarm for D.G. fault.
(connect to communication equipment )
DO3 Reset D.G. 2. (only used in two diesel generators
scenario, connect to the backup D.G.)
DO_3 can be set to report alarm to no mains.(connect
to communication equipment )
DO4 Starts or stops D.G. 2 (DG2_On/Off). (only used in two
diesel generators scenario, connect to the backup D.G.)
-
ADIO Backup DO2
DG Reset
ADIO Backup DO3
DG Reset
Back up DI 1
Normal open
Back up DI 2
Normal open
Enter
Enter
Alarm Set
Critical Point
Dry Node Setting
Clr Hist Alarm
Enter Enter
Enter
2. The user password is 0#, the engineer password is 1#, both the user password and the engineer password can be reset on the menu.
3. Information on the liquid crystal display (LCD) described on page 17 is for reference only.
1. After software Version 827 of the HPMU, DO2 and DO3 can be used as dry contact, by setting the default parameters of
ADIO Backup DO2 and ADIO Backup DO3 to Alarm close.
Checking Cable Connections i
No. Check Item
1 Ensure that the cabinets are securely installed and cables are securely installed.
2 Use a clamp meter to verify that the cables are connected properly.
3 No short circuit occurs between the –48 V power cable and any of the ground bar, positive bus bar, three-phase live wire, neutral
wire, and ground cable. No short circuit occurs between the three-phase live wire, the neutral wire, and the ground cable.
Enter Enter 2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Enter password
end with #:
>#
Settings
Scene Set
System Set
Alarm Set
Enter MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
0#
ADIO Backup DO2
Alarm close
ADIO Backup DO3
DG Reset
ADIO Backup DO2
Alarm close
ADIO Backup DO3
DG Reset
ADIO Backup DO2
Alarm close
ADIO Backup DO3
Alarm close
18
3. Powering On and Commissioning the Power Cube
Check the AMF power switch is set to
the OFF position.
OFF OFF
Switch the battery circuit breakers of the ESC and the BAT1– ,BAT2–, F2
circuit breaker of the Power system to the ON position.
Power system
ON
BAT1- BAT2- F2
ON
1. The user password is 0#, the engineer password is 1#, both the user password and the engineer password can be reset on the menu.
2. The following table describes the buttons on the HPMU panel.
3. Information on the liquid crystal display (LCD) described on pages 18– 23 is for reference only.
Check that the Product Set is PowerCube 1000 (only used after software Version 827 of the HPMU).Set basic
parameters on the HPMU (System Type, Zone, Date, Time, Batt1 Cap, Batt2 Cap, Install Date).
Powering On Batteries a
Set parameters on the HPMU
b
Button Function
or Allows you to view menu items and set the value of a menu item.
Cancel Returns to the previous menu without saving the settings of the current menu item.
Enter Enters the main menu from the standby screen, enters a submenu from the main menu, or saves the settings of
a submenu item.
Parameter Setting on the HPMU
Parameter Value Parameter Value Parameter Value
Scene Set (only used after software
Version 827 of the HPMU)
System Set Battery Set
Zone
Set based on
actual
requirements
Batt 1 Cap Set based on actual
requirements
Product Set PowerCube 1000 Install Date
Set based on actual
requirements
Date
Set based on
actual
requirements Application Set
Cable L Set based on actual
requirements System Type Solar&DG&Batt
Time
Set based on
actual
requirements Battery Type DCB Cabel S Set based on actual
requirements
Step 1: Set application parameters.
a. Initial power-on
Please Select
System Type:
Solar & DG
Please Select
System Type:
Solar&DG&Batt
or
19
Enter Enter
Enter
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Enter password
end with #:
>#
Settings
Scene Set
System Set
Alarm Set
Settings
Battery Set
DG Set
Application Set
System Type
Solar&DG&Batt
Battery Type:
DCB
b. Non-initial power-on
Step 3: Set system parameters.
Date:
2009-07-06
Time: 13:27
Zone: GMT+8:00
Enter Enter
Enter
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Local Address: 1
Lang: English
Disp Contrast: 5
Modify User PWD
Date:
2009-07-06
Time: 13:27
Zone: GMT+8:00
Date:
2009-07-06
Time: 13:27
Zone: GMT+8:00
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Step 4: Set battery parameters.
0#
Timing BC:
Enable
BC Duration:
30 days
Install Date:
2009-01-01
BMU Number:
0 Piece
Batt 1 Cap:
600Ah
Batt 2 Cap:
Enter Enter
Enter Max Discharge:
Disable
Max Disch Time:
24 h
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Enter
System Type
Solar&DG&Batt
Battery Type:
DCB
Limit-Curr Coef
0.3 C
Cable L: 5m
Cabel S: 35mm^2
Limit-Curr Coef
0.3 C
Cable L: 5m
Cabel S: 35mm^2
Set communication parameters on the HPMU.
For GPRS networking, the SIM card needs to support voice services (over circuit switching) and data servcies (over packet
switching).
Step2: Check that the Product Set is PowerCube 1000 (only used after software Version 827 of the HPMU).
Product Set
Para Will Init
ENTER: Continue
CANCEL: Quit
Product Set
Please Select:
PowerCube 1000
Enter
Enter Enter 2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Enter password
end with #:
>#
Settings
Scene Set
System Set
Alarm Set
Enter MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
1#
0# Enter
Settings
Scene Set
System Set
Alarm Set
0# Enter
Settings
Scene Set
System Set
Alarm Set
Settings
Battery Set
DG Set
Application Set
Settings
Battery Set
DG Set
Application Set
20
A. (Optional: only setting when OMU is used) Set communication parameters on the HPMU.
Scenario 1: GPRS+SMS or SMS networking
Parameter Setting on the HPMU (GPRS+SMS)
Item Value Item Value
System Set NetEco Num Number of the SIM card in the short message
service (SMS) modem on the NetEco side
Server IP Address Obtained from the EMS User1 to User5
Phone Num Set based on actual requirements
Server IP Backup Obtained from the EMS SMS Test Num Set based on actual requirements
APN Name Obtained from the survey table
Net Para Set APN Number
Comm Method GPRS+SMS (if the SMS modem
is configured) User Name Obtained from the survey table
SMC Num Obtained from the survey table User Password
User name for accessing the GPRS (specified if
the APN is used or left blank if the APN is not used)
Password for accessing the GPRS (specified if the
APN is used or left blank if the APN is not used)
Parameter Setting on the HPMU (SMS)
Item Value Item Value
Comm Method SMS (if the SMS modem is
configured) NetEco Num
Number of the SIM card in the short message
service (SMS) modem on the NetEco side
SMC Num Obtained from the survey table
User1 to User5
Phone Num Set based on actual requirements
SMS Test Num Set based on actual requirements
Step 1: Set system parameters.
Date:
2009-07-06
Time: 13:27
Zone: GMT+8:00
Enter Enter
Server IP Addr:
0.0.0.0
Server IP Backup:
0.0.0.0
Enter
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Local Address: 1
Lang: English
Disp Contrast: 5
Modify User PWD
Server IP Addr:
0.0.0.0
Server IP Backup:
0.0.0.0
Step 2: Set network parameters.
Enter
User1 Phone Num
>
SMS Test Num
>
APN Name
>
APN Number
>
User Name
> User Password
>
Neteco Num
>
SMC Num
>
Comm Method
GPRS+SMS
Dial Up/Down
Dial up
Enter Enter 2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Settings
Engineer Set
Net Para Set
Disconection Set
User2 Phone Num
> User3 Phone Num
>
User4 Phone Num
>
User5 Phone Num
>
Settings
Scene Set
System Set
Alarm Set
0# Enter
0#
Enter Settings
Scene Set
System Set
Alarm Set
Settings
Battery Set
DG Set
Application Set
21
Step3:The dialup service is successful if both the GPRS and SMS are used in networking, the value of GPRS IP Addr is not
0.0.0.0, If the RUN indicator on the OMU01 panel is blinking slowly (on for 1s and then off for 1s), the HPMU is successfully
connected to the NetEco and the NetEco has obtained the correct site information.
If only the SMS is used in networking, check the validity of the SMS test number on the LCD and then test the SMS function.
If the number receives 210231***************, the settings related to the SMS are correctly set on the HPMU.
OMU IP Addr:
0.0.0.0
GPRS IP Addr:
0.0.0.0
2009-6-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Before performing the SMS test, ensure that the SMS
test number is valid.
0#
Caution:
Start Sms Test?
ENTER: Continue
CANCEL: Quit
Enter Enter Enter
Enter
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Enter password
end with #:
>#
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Scenario 2: Communication over the Ethernet
Parameter Setting on the HPMU
Item Value Item Value
Net Para Set System Set
Comm Method ETH Server IP Address Obtained from the EMS
Server IP Backup Obtained from the EMS
OMU IP Set according to the network plan
OMU Mask IP Set according to the network plan
Gateway IP Set according to the network plan
Step 1: Set network parameters.
Enter Comm Method
GPRS+SMS
Dial Up/Down
Dial up
Enter Enter 2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Comm Method
GPRS+SMS
Dial Up/Down
Dial up
Enter Comm Method
ETH
Dial Up/Down
Dial up
Step 2: Set system parameters.
Date:
2009-07-06
Time: 13:27
Zone: GMT+8:00
Enter Ente
r
Server IP Addr:
0.0.0.0
Server IP Backup:
0.0.0.0
Ente
r
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Local Address: 1
Lang: English
Disp Contrast: 5
Modify User PWD
Server IP Addr:
0.0.0.0
Server IP Backup:
0.0.0.0
OMU Mask IP
0.0.0.0
OMU Mask IP
0.0.0.0
Gateway IP
0.0.0.0
Site ID:
>
OMU IP
0.0.0.0
OMU Mask IP
0.0.0.0
Ente
r
Maintenance
Reset HPMU
Sms Test
DG Test
Maintenance
Reset HPMU
Sms Test
DG Test
0#
Enter Settings
Scene Set
System Set
Alarm Set
Settings
Engineer Set
Net Para Set
Disconection Set
Settings
Battery Set
DG Set
Application Set
Settings
Scene Set
System Set
Alarm Set
0# Enter
22
a. Switch the DG INPUT and AC output circuit breakers of the IATS to the ON position.
b. Flip the AMF power switch to the ON position and check that the EMERGENCY STOP button is ejected.
OFF
ON
c. Switch the AC circuit breaker of the Power system and the BC power switch to the ON position.
Powering On the D.G.
c
B. In-Band Communication (over the HPMU)
Parameter Setting on the HPMU
Item Value
System Set
Local Address 27 Enter
Enter
Enter
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Local Address: 27
Lang: English
Disp Contrast: 5
Modify User PWD
Before starting the D.G., ensure that the fuel tank,
engine oil tank, and water tank are filled.
The D.G. starts to charge DCBs. Check whether the information on the HPMU standby screen matches the actual
configurations. If yes, proceed to step 6. If no, check cable connections and part configurations.
HPMU
Batt1: 10.0A
Batt2: 0.0A
Batt Tmp: 0°C
Board Tmp: 27°C
SDG Batt: 0.0V
DG1 Batt: 0.0V
Fuel1 Lev: 0cm
Fuel2 Lev: 0cm
System Type:
DG & DCB
Alarm Status:
Exist Alarm
Batt Remain Cap:
100%
Batt Backup Time:
86.5h
Current Batt:
Batt1
Batt Status:
Discharge
OMU IPAddr:
0.0.0.0
GPRS IPAddr:
0.0.0.0
SIMOnline Stat:
Dis Online
GSMReg Stat:
Unregister
GPRS Dial Pro:
No Dial
GSM Sig Quality:
Phase A: 215.7 V
Phase B: 216.2 V
Phase C: 215.7 V
Ambient: 25°C
2009–06–16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
ON ON
DG INPUT 63A
ON
BC
ON
AC
Power system
Settings
Scene Set
System Set
Alarm Set
0# Enter
23
Powering On the Load d
On the HPMU standby screen, choose Status > Maintenance > Reset HPMU > DG Test > Enter: Continue and press
Enter. The Power Cube stops the running D.G. After that, the Power Cube starts the smart diesel generator (SDG) and
then stops it. Finally, the HPMU displays SDG test: Pass.
Test Result
Mains: Off
SDG test: Pass
0# Maintenance
Reset HPMU
Sms Test
DG Test
Close all DG
Please wait
Enter Enter
Enter Test open SDG
Please wait
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
Enter password
end with #:
>#
Enter
Caution:
Start DG Test?
ENTER: Continue
CANCEL: Quit
Enter Test close SDG
Please wait
2009–06–16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Maintenance
Reset HPMU
Sms Test
DG Test
On the HPMU standby screen, choose Status > Maintenance > Reset HPMU > Oil-Clean Test > ENTER: Continue and press
Enter. If the DG-M indicator (green) on the IATS is steady on, the test succeeds.
Enter
0# Enter Enter Enter password
end with #:
>#
Enter Maintenance
Reset HPMU
Sms Test
DG Test
Maintenance
Oil-Clean Test
Control Mode:
Auto
Caution:
Oil Clean Test?
ENTER: Continue
CANCEL: Quit
MAIN MENU
Status
Maintenance
Settings
MAIN MENU
Status
Maintenance
Settings
2009-06-16
Batt1 Volt: 52.3 V
Batt2 Volt: 50.6 V
Supplier: SDG
Check whether the values on the HPMU standby screen are the same as the actual configurations. If there is an alarm from
the HPMU, CPMU01 and the AMF25, rectify the fault by referring to the PowerCube 1000 Maintenance Guide (V300R001).
Switch on the DC-powered load connecting to the power system and the AC-powered load connecting to the IATS. Check
that the circuit breakers of F1,(for FAN),F14(for DC air condition),F3(for BC) is set to ON.
If no alarm is generated after the Power Cube runs for five minutes, the commissioning is successful. Then take fireproof mud
out of the packaging box in the cabinet base to block cable holes. After that, reinstall the plate, close all cabinet doors, and
hand the keys over to the persons in charge.
HUAWEI TECHNOLOGIES CO., LTD. Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People’s Republic of China
www.huawei.com