Luni River
Luni Bridge
Guide Bund Guide Bund
Luni Bridge
Project Details
1. Location : NH-15 (Jaisalmer-Barmer-Sanchore Section) Km. 258 - 259 (0/0 at Jaisalmer)
2. Length : Major Bridge – 754 Mtr.
3. Sanctioned Amount : 710.24 Lacs
4. Scope of Work : Rehabilitation of Luni Bridge including RCC jacketing to piers and pier caps, replacement of expansion joints, wearing coat, damaged railing and epoxy painting etc.
5. Period of Completion : 8 Months
History of Luni Bridge
1. Year of Construction : I Phase – 1970 (12 Spans)II Phase – 1977 (12 Spans)
2. Total Length 754 m
3. Total Spans 24 (32.24 m)
4. Nature of major damages a. Wide Cracks in piers and pier capsb. Cracks in Deck Slabc. Expansion joints – completely non
functionald. RCC Wearing Coat Damaged e. Railing Damagedf. Scouring Near Piers
Technical Proposals
1. Wide Cracks in piers and pier caps
: 25 cm. RCC Jacketing.
2. Cracks in Deck Slab : Repair with epoxy grout and applying apoxy mortar.
3. Expansion joints – completely non functional
: Replacement of expansion joints by strip seal joints.
4. RCC Wearing Coat Damaged
: BC with mastic asphalt.
5. Railing Damaged : Replacement with steel railing
6. Scouring Near Piers : Boulders / Quarry stone apron
List of Plant & Equipment to be deployed on Contract Work
SI. Type of EquipmentMaximum age as
on 1/1/2010
Contract Package Size
Upto Rs. 50Million
Rs. 51-200Million
Rs.201-500Million
Rs. 501-1000 Million &
Above
1 Tipper Trucks 5-7 5
2 Motor Grader 5 1
3 Front end Loader 5 1
4 Smooth Wheeled Roller 5 2
5 Vibratory Roller 5 1
6Hot Mix Plant with Electronic
Controls (Minimum 40-60 TPH Capacity)
5 1
7 Paver Finisher 5 1
8 Water Tanker 5 3
9 Bitumen Sprayer 5-7 1
10Concrete Mixes with Integral
Weigh Batching facility5 1
11Concrete Batching and Mixing
Plant (Minimum. Capacity - 15m3/hour)
5 1
Total 25As per MoRTH Circular Dt.
27.11.2009
CONSTRUCTION PROGRAME OF PROJECT
1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2Sept '10 Oct '10
S.N. 3 3 5 6
9Stone pitching on slopes
10 Byepass-Earth Work/GSB and WBM
7 Structural steel work
8Boulder/ quarry stone apron
RCC Grade M-35 for jacketing
Applying two coats of epoxy
6 Slab seal type of expansion joint
2
3
Mar '11Dec '10 Jan '11
1
7 8
Guinting on Concrete
5Mastic asphalt wearing course
4Removal of existing wearing coat
2Nov '10 Feb '11
13 Miscellaneous Work
ITEM / DESCRIPTION
9 M O N T H S1
Aug. '10
11Byepass - Carpet
12 Singages and marking etc
S.N. Major Item BSR Rate Rate as per
present market Difference
in % Remark
1 Guinting on Concrete 1057.00 p/sqm 1477.00 p/sqm 39.73 Higher rate due to distant location and
specialized nature of work
2 25mm Mastic Asphalt 420.00 p/sqm 504.00 p/sqm 20.00 Due to increase in cost of mastic
asphalt and remote location of bridge
3M-30 Grade concrete for jacketing
3779.00 p/cum 4775.00 p/cum 26.35
More lead of material, remote location, less quantum of work, more cost of shuttering and specialized nature of
work
4 Stone Masonry 2353.00 p/cum 2701.00 p/cum 14.78 More lead of material stone and bajri
5Boulders / quarry stone apron
1253.00 p/cum 1544.00 p/cum 23.22 More lead of stones
6 Stone Pitching 628.00 p/cum 947.00 p/cum 50.70 More lead of stones
7 WBM 727.00 p/cum 1067.00 p/sqm 46.76 More lead of all materials
Variation in BSR & Present Market AnalysisVariation in BSR & Present Market Analysis
Amount of Unbalanced BID
Cost of Work as per Rate Analysis = 713.19 Lacs
Cost of Work offered by Bidder = 644.84 Lacs
Unbalance Bid Amount = 68.35 Lacs
% difference between lowest offer and Rate Analysis Amount
= 9.58%