PRE-BID MEETING AND SITE WALK
D6 Hayward, Elevated Solar Photovoltaic Project1758 Sabre StreetHayward, CA
AC Transit
Joe Callaway AC Transit, Senior Project Manager Christina Ebojo AC Transit, Project Coordinator Chae Kang AC Transit, Contract Specialist Stan Nusom AC Transit, Facilities Maintenance
Supervisor Tim Dawkins, AC Transit, Maintenance
Superintendent Bob Desautels ATI, Construction Manager Steve Stretchberry ATI, Design Manager Donna Foster ATI, Construction Coordinator
[email protected](925) 648-8800 x1260
Introductions
◦Please Sign-In◦Indicate Prime versus Sub on sign in sheet
◦Provide your contact information. An e-mail address is REQUIRED
Make it Official!
Base Bid: 350 Kwp PV power plant system on two elevated steel trellis structures – totaling approximately 27,900 square feet. Included in the Base Bid are:◦ Electrical equipment associated with PG&E interconnect◦ Site lighting under the trellis structures◦ Grounding of the PV System and structures◦ New striping◦ New protective bollards◦ Re-location of one fire hydrant and associated piping◦ Selective demolition of existing site infrastructure◦ Start-up and commissioning ◦ Stocking of spare parts◦ Basic maintenance and monitoring of the system for one year following start-up.
Additive Alternate #1: additional 75 Kwp PV power system on extended elevated trellis structure – totaling approximately 6,000 square feet.
Additive Alternate #2: Extended basic maintenance of PV power plant for an additional 4 years past the base bid maintenance period (years 2-5)
Scope of Work
CAREFULLY REVIEW the Invitation for Bid (IFB) and Construction Documents ◦87 PAGES in Invitation for Bid◦26 DRAWING SHEETS◦166 page Project Manual, including
Technical Specifications and Geotechnical Report in Appendix A
Bid submittals must be done in accordance with the IFB Documents
Scope of Work
Site Layout
Building
Building
Building
Base Bid PV
Base Bid PV
Add Alt #1PV
Trellis Section
Trellis Structure Rendering
BID & AWARD SCHEDULETask: Date:
Pre-Bid Meeting, 10:00 AM July 11, 2013 – Thursday
First Addendum Issued: July 12, 2013 – Friday
Last Day for Bid Questions: July 15,2013 – Monday
Final Addenda Issued: July 24,2013 – Wednesday
Bids Due, 02:00 pm: August 1, 2013 – Thursday
Bid and Qualifications Review: Tentative - July 31 – Wednesday
Notice of Award to Contractor: Tentative - August 30 – Friday
Pre-Contract Meeting, 10:00 AM: Tentative - September 4 – Wednesday
Contracts, bonds, Licenses, Certificates of Insurance, etc. to District:
Tentative - September 4 – Wednesday
Notice to Proceed: Tentative - September 6 – Friday
Pre-Construction Meeting: Tentative - September 9 - Monday
Construction Complete: December 31 – Tuesday
THE BID & AWARD SCHEDULE
Questions…Questions regarding the IFB must be submitted in
writing to the District Contract Specialist, Chae Kang◦ Email: [email protected]◦ 1600 Franklin Street, 8th Floor◦ Oakland, CA 94612◦ (510) 891-5498
Questions will be answered, if appropriate, by written addenda to the IFB. Upon posting or delivery, such addenda will become a part of the bid documents and binding on all eligible bidders. ◦
BIDS DUE:
14:00 pm, August 1, 2013At the Offices of the AC Transit
Procurement and Materials Director,1600 Franklin Street, 8th Floor
Oakland, CA 94612, Attn: Chae Kang, Contract Specialist
Late Submittals will not be opened!
THE BID & AWARD SCHEDULE