PRE-FEASIBILITY
REPORT
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
2
1.0 EXECUTIVE SUMMARY
1.1 Introduction
The proposed mining area of 1.40 acres (0.566 ha.) in Sy.No. 291/15-2 Goli Village,
Rentachintala Mandal, Guntur District, Andhra Pradesh. has been allotted to Sri. D. Bangaru
Reddy for a period of 10years by Assistant Director of Mines and Geology, Guntur.
The proposed area is not fit for agriculture and the Department of Mines and Geology
indicate that the subject area has mineral deposits for extraction. The salient features of the
project are given Table 1.1.
Table 1.1
The Salient Features of the Project
Project Name Proposed Napa slabs (Block) Quarry
of Sri. D. Bangaru Reddy
Mining Lease Area 1.40 acres (0.566 ha.)
Location of Mine Goli Village , Rentachintala Mandal,
Guntur District, Andhra Pradesh.
Toposheet number 56P/10
Minerals of mine Napa Slabs (Black)
Proposed production of
mine 1,600 Tons/Annum
Method of mining Opencast semi mechanized mining
Drilling/Blasting Controlled Blasting and drilling is proposed.
No. of working days 250 days
Water demand 5.0 KLD
Sources of water Water will be supplied from nearby village through
tankers.
Man power 21
Nearest railway station Nadikudu Railway Station - 21 km (E)from the lease
area.
Nearest airport Vijayavada Airport is about 136.07 km due ESE from the
lease area.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
3
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
2.1 Identification of Project and Project Proponent
The Quarrying area for Building Stone has been allotted to Sri. D. Bangaru Reddy in
Goli Village, Rentachintala Mandal, Guntur District, Andhra Pradesh by the
department of Mines & Geology, over an extent of 2.96 Acres for a period 10 years.
M/s.Sri. D. Bangaru Reddy is headed by Sri. D. Bangaru Reddy they are into stone
crushing business from 10 years.
2.2 Brief Information about the Project
The mining lease area of 1.40 acres is located in Government land. Open cast semi
mechanized mining is followed and it has been proposed to produce approximately
45000 Tons/annum of building stone material. The nearest habitation from the
proposed project is at a distance of 0.53 km towards SSW direction i.e. Goli village.
2.3 Need for the Project and Its Importance to the Country or Region
Crushed stone or angular rock is a form of construction aggregate, typically produced
by mining a suitable rock deposit and breaking the removed rock down to the desired
size using crushers. The demand for road metal has increased due to rapid
industrialization and growth in infrastructure. Due to the State bifurcation there will
be rapid development in infrastructure sector.
As per EIA notification 2006 project proponent is submitting the proposal to get
Clearance for production capacity of 45000 Tons/ annum of from State Level
Environmental Appraisal Committee/State level Impact Assessment Authority of
Karnataka constituted by MoEF, GOI for the purpose of grant of quarry lease for
which Notification is issued.
2.4 Demands-Supply Gap
There is huge demand since the material is used extensively in Construction,
Railways, Roadways and many other sectors. This project will help in reducing the
Demand-Supply gap in the area.
2.5 Domestic/ Export Markets
The material is used in the domestic market and in there is no scope for exporting the
material.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
4
2.6 Employment Generation
Proposed mining is semi mechanized method and this project operation will provide
livelihood to the 21 workers. It will provide employment to the people residing in
vicinity.
3.0 PROJECT DESCRIPTION
3.1 Type of Project Including Interlinked and Interdependent Projects, If Any.
The proposed mine area is of 1.45 acre area, No interlinked projects are associated with
this project.
3.2 Location of the project
The mining lease area is located in Sy.No. 291/15-2, Goli Village , Rentachintala
Mandal, Guntur District, Andhra Pradesh . The mine lease area falls in Survey of
India Top sheet No.: 56P/10. The latitude and longitude of the mine lease area is -
16°35'50.40""North & 79°31 '32. 73"East.
Google map is given in Figure - 1.Location of the mining lease in Guntur District is
shown in Figure 2.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
5
Figure 1
Google Map Showing the Mine Lease Area
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
6
Figure 2
Location Map
Andhra Pradesh
MINE SITE
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
7
3.3 Details of Alternate Sites
No alternate site was considered as the project is mineral specific and site specific.
3.4 Size or magnitude of operation
The proposed mine has lease over an area of 1.40 acre and the production rate is 1600
tons/annum. The lease follows open cast semi mechanized mining.
3.5 Geology and Reserves
3.5.1 Topography
The Topography of the area consists of Grey Granite Gneiss ridges and slopes towards S-
E.The general height of the mounds ranges/hill ranges from 113metres to 120 metres above
MSL. The nallas flows towards S-E direction and acts as channels during the rainy season.
3.5.2 Geology
Guntur is bounded by Nalgonda in the North, Prakasham in the South, Mahabubnagar in the
West, Krishna in the East. The district comprises older metamorphic of presumably Archean
age, Dhawwar super group of Archean to lower Proterzoic age post- Dharwar intrusive,
sedimentary rocks of cuddapahj super group and cuddalore formation of middle Miocene age
and Laterite/alluvium of quaternary age.
3.5.3 Exploration
Since this is an existing mine work has been done.
3.5.4 Reserves
Reserves = 61760 Tons
3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS
3.6.1 Method of Mining
The quarrying in the sanctioned area is of open cast method by semi-mechanized way.
Considering the technical parameters like surface topography, quality variations, geo-
technical aspects are required for production and extraction of building material in the area.
It is proposed to work from the deposit by adopting benches formations with ultimate pit
slope of 45°. Only Jack Hammer, drilling is required for controlled blasting to break the
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
8
insitive sheet rock. The benches height and the width will be maintained as specified by
D.G.M.S. The width of the working benches shall not be less than the height. The year wise
production and development plan indicates the site for disposal of waste, site for afforestation
as shown in map. The plan showing position of the working pit proposed for extension etc.
Due care has to be taken in designing the benches and advancing the benches for production.
The ground water table is much below the proposed working level.
The machinery used to carry out the mining operations are given Table 3.3
Table 3.3
Mining Machinery
1 Excavator with breakers (Tata 210 LC) 2 Nos.
2 Air Compressor (Atlas Cop) 2 Nos.
3 Tractor Moulded Compressor 2 Nos.
4 JCBs for loading 2 No
5 Jack hammer 3 Nos.
6 Tippers 3 Nos.
7 Tractor for water supply 1 No.
3.7 Raw Material Required Along With Estimated Quantity, Likely Source,
Marketing Area of Final Product/S, Mode of Transport of Raw Material and
Finished Product
No raw material will be required in the proposed project. The operation involves the
extraction of material and dumping in stock yard. Loading of the building stone
material will be done mechanically by tippers of 10 Tons capacity and transported
from the quarry to the required site. The rejected material will be dumped separately.
3.7.1 Use of Mineral
The extracted material will be used in Construction, Railways, Road ways and many
other sectors
3.7.2 Processing
No processing at site is involved.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
9
3.8 Resource Optimization/ Recycling and Reuse
Not envisaged.
3.9 Availability of Water Its Source, Energy/ Power Requirement and Source
3.9.1 Water Requirement
Water is required only for drinking purposes and dust suppression. The number of
working people is around 21 so the total water requirement will be around 5.0 KLD.
About 2.5 KLD will be required for dust suppression and greenbelt. This water will be
supplied from bore wells of nearby area.
3.10 Quantity of Wastes to be Generated (Liquid and Solid) And Scheme for their
Management/ Disposal
3.10.1 Solid Waste Generation& its Disposal
In this type of extraction the recovery factor is as high as 80 % so only 20% comes
out as waste. This waste shall be stacked in the dump yard to reuse for reclamation
purpose. The waste will be dumped along the southwest border of QL area.
3.10.2 Liquid Effluent
No liquid effluent will be generated at the mine site. The domestic wastewater
generated will be sent to septic tanks followed by soak pits.
4.0 SITE ANALYSIS
4.1 Connectivity
4.1.1 Nearest Railway Station
Nadikudu Railway Station is about 21 km distance towards E direction from the mine
area.
4.1.2 Nearest Airport
Vijayawada Airport is about 136.07 km ESE distance from mine site.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
10
4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP
The notified area is Government land. It is barren with boulders and followed sheet
rock is exposed in the area and also sheet rock is seen in the surface level with soil
cover. The proposed land use is given below.
4.3 Topography
Entire lease area of 0.566 ha land shall be utilized for quarrying only. The
Topography of the area consists of Grey Granite Gneiss ridges and slopes towards S-
E. The general height of the mounds ranges/hill ranges from 114 meters to 110 meters
above MSL.
4.4 Climatic data from secondary sources
The average rainfall is about 658.2 mm/annum. The observed maximum temperature
is 45.30C in summer season and minimum temperature is 13.2
0C in winter seasons.
The rainfall does not disturb the mining activities. Moderate wind velocities,
prevailed in north east to south west direction.
5.0 PLANNING BRIEF
5.1 Planning Concept
The quarrying in the sanctioned area is of open cast method by semi-mechanized way.
Considering the technical parameters like surface topography, quality variations, geo-
technical aspects are required for production and extraction of building material in the
area. It is proposed to work from the deposit by adopting benches formations with
ultimate pit slope of 45°. Only Jack Hammer, drilling is required for controlled
blasting to break the insitive sheet rock. The benches height and the width will
bemaintained as specified by D.G.M.S. The width of the working benches shall not
be less than the height. The year wise production and development plan indicates the
site for disposal of waste, site for afforestation as shown in map. The plan showing
position of the working pit proposed for extension etc. Due care has to be taken in
designing the benches and advancing the benches for production. The ground water
table is much below the proposed working level.
5.2 Population projection
The project will employ mostly workers from nearby villages. There will not be any
increase in population due to the project.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
11
5.3 Land use planning
The project site is Government land. There will be change in landuse as the material is
excavated.
5.4 Assessment of Infrastructure Demand (Physical & Social)
On the basis of the preliminary site visit, the infrastructure demand in the villages was
assessed on the basis of need and priority. The existing infrastructure is satisfactory
but the approach road has to be maintained regularly.
5.5 Amenities/Facilities
Site Services like Work shed, First Aid, Drinking water as required will be provided
within the leased area.
6.0 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
No infrastructure is proposed.
6.2 Residential Area (Non Processing Area)
As the local persons will be given employment, no residential area/ housing is
proposed within the mining lease area.
6.3 Green Belt
Green belt will be developed along the boundaries of mine lease area.
6.4 Water Management
About 2.5 KLD will be required dust suppression and greenbelt purpose and about 1.0
KLD for drinking therefore total water requirement is 5.0 KLD. This water will be
supplied from bore wells of the nearby area.
6.5 Sewerage System
The domestic wastewater generated will be sent to septic tanks followed by soak pits.
6.6 Industrial Waste Management
Not applicable.
PROJECT: Napa Slabs (Black) Quarry PRE-FEASIBILITY REPORT APPLICANT: Sri D. Bangaru Reddy
12
6.7 Solid Waste management
The waste generated which is about 20% will stacked in the dump yard proposed in
the mine area.
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
Not Applicable.
8.0 PROJECT SCHEDULE & COST ESTIMATES
The Total cost of project would be around Rs. 15 lakhs.
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1 Financial and Social Benefits with Special Emphasis on the Benefit to the Local
People Including Tribal Population, If Any, In the Area.
The extraction of the material will be done in semi mechanized manner so local
labour will be used. Supporting ancillary facilities will help the local people once the
project commences.
***********