Upload
trinhkien
View
214
Download
0
Embed Size (px)
Citation preview
PRE- FEASIBILITY REPORT
OF
BAGRI GRANITE MINING PROJECT
(REFRENCE NO. 201810000613)
PROJECT
FOR
ENVIRONMENTAL CLEARANCE
At
VILLAGE– BAGRI
TEHSIL – MALPURA, DISTRICT- TONK
Lease Area : 2.8950 Hect.
Category of Project : „B2‟
Capacity : 152297 TPA OF GRANITE
Name of Project Proponent : SHRI JAGDISH KUMAR JEENGAR
Project In Charge : SHRI JAGDISH KUMAR JEENGAR
ADDRESS : R/o Amba Bhawan, Near Sainath School,
Gandi Nagar, Tehsil- Kishangarh,
District - Ajmer (Raj)
E-mail address : [email protected]
Mobile No : 9772211355
Project Cost : Rs. 79 Lacs
Date of issue of Work Order : 01/11/2018
Prepared By:
Nimish Singhwi (Mining Engineer & RQP)
Reg. No. RQP/SME/(UDAI-CIRCLE)/2012/07,
R/o- 15, New Glass Factory Colony Sunderwas, Udaipur-313001
Tel. No. 0294 – 2492060, 94141-10360
E-mail - [email protected]
1.0 EXECUTIVE SUMMARY
1.1 Executive Summary
The letter of intention (L.O.I.) in favour of Shri Jagdish Kumar Jeengar S/o Shri
Amba Lal R/o - Amba Bhawan, Near Sainath School, Gandhi Nagar, Tehsil -
Kishangarh, District - Ajmer (Raj) for Mineral Granite was issued by
Superintend Mining Engineer Department of Mines & Geology Jaipur vide order
no. Kha/Jai/Tonk/Ref. No. -201810000613/P-13/2018/205 dated 05/10/2018.
This mining project falls under Category “B2” as per EIA Notifications 2006
and amended thereof.
1.2 Salient features of the project
Project Name Bagri (Reference No. 201810000613)
Granite Mining Project
Location of mine Village - Bagri,
Tehsil - Malpura,
District - Tonk
State - Rajasthan
Latitude N- 260 28‟ 05.2” to 260 28‟ 12.1”
Longitude E- 750 11‟ 05.4” to 750 11‟ 57.9”
Topo sheet number 45 N/03
Minerals of mine Granite
Total Mineable reserves 754429 Tonnes
Proposed production of mine 152297 TPA of Granite
Method of mining Opencast Mechanized
No of working days 300 days
Water demand Total water requirement is about 4.4 KLD =
0.9 KLD (Drinking & Domestic Uses) + 1.3
KLD (Plantation) + 1.1 KLD (Dust
Suppression) & 1.1 KLD Wire Saw Cutting..
Sources of water Water will be supplied from nearby sources
near the mine site.
Man power 15
Nearest railway station Kishangarh Railway Station (About 50 Km
in NW direction).
Nearest State highway/national
highway
RJ- SH-12
About 10.0 Km in SE direction.
Nearest airport Jaipur International Airport (About 83 KM
in NE direction) .
Seismic zone Zone II
1.3 Proposed Planning
Mining method - Opencast Mechanized
Project cost - Rs. 79 Lacs
Production - 152297 TPA of Granite
The land use pattern around Bagri village is Pvt. Land.
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of Project and Project Proponent:
The letter of intention (L.O.I.) in favour of Shri Jagdish Kumar Jeengar S/o Shri
Amba Lal R/o - Amba Bhawan, Near Sainath School, Gandhi Nagar, Tehsil -
Kishangarh, District - Ajmer (Raj) for Mineral Granite was issued by
Superintend Mining Engineer Department of Mines & Geology Jaipur vide order
no. Kha/Jai/Tonk/Ref. No. -201810000613/P-13/2018/205 dated 05/10/2018.
2.2 Brief Information about the Project
The project has been proposed for mining of 152297 TPA of Granite by Opencast
Mechanized Method. The ML area is 2.8950 Hect. Water requirement for the
proposed project for drinking use, dust suppression and other use will be 4.4 KLD,
which will be taken from nearby source.
2.3 Need for the Project and Its Importance to the Country or Region:
The mining project falls in the Tonk District of Rajasthan, the area is devoid of
industrial growth. The earning sources of the region are limited. Most of the people are
dependent upon agriculture only. Mineral wealth of the state Rajasthan provides the
employment opportunity to the people of the state as well as region also. Mining is one
of the major core sector industries which play a crucial role in the process of country
economic development. The mineral Granite finds extensive use in the construction
and infrastructural works. The basic objective of the project is the effective utilization
of Material in the country or region. Granite is the world's most commonly used
material in construction of road, railway track construction etc. Granite will help in
the economic growth of the country or region.
2.4 Demands-Supply Gap
There is a large demand of Granite for roads, railway tracks, building construction
etc.
2.5 Imports vs. Indigenous Production
Development needs will be met only through indigenous produced minerals against
the high cost of imported material.
2.6 Export Possibility
There is no proposal to export the minerals. However, mineral produced from the
mine will fulfill the needs of the region and surplus if any, will be considered for
export.
2.7 Domestic/ Export Markets
Domestic Market
Mineral excavated will be used for domestic consumption.
Export Market
The proposed mining activity is for indigenous consumption only there is no
proposal for export.
2.8 Employment Generation
The proposed mining activity will provide employment to workers. The workers will
be hired mostly from the nearby village
3.0 PROJECT DESCRIPTION
3.1 Type of Project Including Interlinked and Interdependent Projects, If Any.
It is an open cast Mechanized Mining project over an area of 2.8950 Hect., with a
proposed production is 152297 TPA of Granite. This is an independent mining
project and there are no interlinked projects involved.
3.2 Location
The location of the proposed ML area is detailed below:
Village and
Tehsil
District and
State
Toposheet No. Area Ownership
category
Bagri,
Malpura
Tonk
Rajasthan
45 N/03 2.8950 Hect. Pvt. Land
Total 2.8950 Hect.
Late./Long.:-
Latitude N- 260 28‟ 05.2” to 260 28‟ 12.1”
Longitude E- 750 11‟ 05.4” to 750 11‟ 57.9”
The applied mining lease area is situated near village – Bagri, Tehsil - Malpura
District- Tonk (Raj.), the shortest distance from Bagri to Granite mine is 1.2 Km NE
direction.
3.3 Details of Alternate Sites
Mining is site specific so no alternative site is proposed.
3.4 Size or magnitude of operation
The ML area has been granted over an area of 2.8950 Hect. During five year total
production of Granite shall be approximately 453308 Tonnes. The average
number of working days in the year would be 300.
3.5 Regional Geology-
The area mainly forms a part of Tonk district, and a part of Bundi district in the
southeastern part. Duin is the main town in the area. The area is approachable by
Jaipur – Tonk and devil – Bundi State Highway, which run almost in NE- SW
direction.
The area forms partly a peniplain and partly hilly area occupied by the rocks of the
Jahazpur and the Hindoli group and the mangalwar Complex. The hillocks treands
mainly NE-SW. the northern part of the area in dreained by the banas river. Several
nallas join the Banas river and form dendritic drainage pattern.
The northern part of the area is mainly occupied by the rocks of the Mangalwar
Complex represented by migmatite –gneiss and dolomite / calc silicate belonging to
the Kekri formation, where as the middle part of the area is occupied mainly by mica
schist with dolomite of the potla formation. The southern part of the area is occupied
by the rock of the Sujanpura Formation of the Hindoli Group. The rocks area phyllites
and meta-graywacke.
These rocks are intruded by dolerite/amphibolite and quartz veins.The Jahazpur
group of rocks are confined in western and southeastern part of the area. The rocks
are conglomerate, gritty quartzite and dolomite with Banded iron formation (BIF).
Era/Period
Geological
Cycle
Group
Sub formation Lithology
Arc
hae
an t
o P
alae
o-P
rote
rozo
ic
Bhilwara
Supergroup
Jahajpur
Group
Ummedpura
Formation
a. Dolomite with B/F
b. Conglomerate, grit, quartzite
Intrusives
Quartzite
Dolomite/
Amphibolites
Hindoli
Group
Sujanpura
Formation
Meta
Greywack/Phyllite
Phyllite+ Garnet
Mangalwar
Complex
Kekri
Formation
Garnet-bearing
mica schist
Quartzite
Potla
Formation
Dolomite/Calc
silicate
Migmatite gniss
Local Geology-
Super Group Group Lithology
Bhilwara Super Group Mangalwar Complex Granite gneiss
3.7 Project description with process details
3.7.1 Proposed Method of Mining
The ML applied for Granite will be developed by mechanized mining. The mineral is
exposed to the surface therefore open cast mining has been proposed.
The following mining parameters are proposed
Type of working : Opencast, Mechanized Mining
Bench height : 6 m
Bench width : 6 m
Production details
The Proposed Production of Granite in next five year is shown below:
Years Total excavation In MT
Total saleable Minerals in MT
Waste in MT
First Year 233150 60274 172876
Second Year 221643 70438 151205
Third Year 237518 80245 157273
Fourth Year 284592 90054 194538
Fifth Year 304594 152297 152297
Total 1281497 453308 828189
3.8 Raw Material Required Along With Estimated Quantity, Likely Source,
Marketing
Area of Final Product/s, Mode of Transport of Raw Material and Finished Product
No raw material will be required for production of proposed minerals. The mine
mineral shall be collected and dispatch to various industries through trucks.
3.9 Resource Optimization/ Recycling and Reuse
Not envisaged.
3.10 Availability of Water Its Source, Energy/ Power Requirement and
Source
3.10.1 Water Requirement
Total water requirement is about 4.4 KLD = 0.9 KLD (Drinking & Domestic Uses) +
1.3 KLD (Plantation) + 1.1 KLD (Dust Suppression) & 1.1 KLD Wire Saw Cutting.
Water for Drinking, dust suppression and plantation will be collected from nearby
villages.
3.10.2 Power
Electric power supply does not exist at mine site and it is proposed to take
connection.
3.11 Quantity of wastes to be generated (Liquid and solid) and Scheme for their
Management/Disposal
3.11.1 Solid Waste Generation & its Disposal
No solid Waste will be generated. Top Soil collected will be used for plantation at
the end of the lease period.
3.11.2 Liquid Effluent
Not applicable.
4.0 SITE ANALYSIS
4.1 Connectivity
The applied mining lease area is situated near village – Bagri, Tehsil - Malpura District
– Tonk (Raj.), the shortest distance from Bagri to Granite mine is 1.2 Km NE
direction..
4.2 Landform, Land use and Land ownership:
Land Use Pattern Near Village Khatedari Land Total
Non Utilized Bagri 2.8950 Hect. 2.8950 Hect. The applied ML area is as per revenue detail is a Pvt. Land.
4.3 Topography
The area falls in G.T. sheet no. 45 N/03.
4.4 Existing land Use Pattern
The ML area is as per revenue detail is a Govt. Land. There is no River/ Canal/Port in
the existing area. There is no village or human settlement in the lease area. There is
no public road passing through the area
4.0Existing Infrastructure
No existing infrastructure within ML area.
4.6 Soil Classification
Average 0.5 m Cover Has been considered as soil.
4.7 Climate data from Secondary Sources:
The climate of the area is dry with extreme temperature variation i. e. in summer as
high as 440 C, whereas in winter it lowers to 60C or even less. Most of the rain falls
during the period of June to September. Maximum and minimum rain fall varies
(500mm- 200mm).
4.8 Social Infrastructure available:
1) The ML area is not facilitated with power line.
2) The ground water table is 60m-70m from the surface.
3) The state transport buses and private buses are available up to village and
mine site.
4) The nearest police station applicable is at Malpura.
5) Mobile Phone connectivity is available at the ML site.
6) Medical facility is available at Lamba Harisingh.
7) No National Park/sanctuary falls within 10 km of the ML area.
5.0 PLANNING BRIEF
5.1 Planning Concept:
The ML for Granite will be developed by mechanized mining. The mineral is exposed to
the surface therefore open cast mining Ha has been proposed. Drilling will be carried
out only of any big hard rock is encountered.
Water diversion Channel shall be made along the periphery of the working pit, so
water will not be accumulated in the pits in quantity. The mineral produced from the
pit will be bought at a spot outside the pit and then loaded into the trucks and
dumpers by excavator for onwards transportation.
5.2 Land use Planning
At the end of the life of mine area will be covered by water reservoir.
5.3 Assessment of Infrastructure demand (Physical & Social)
On the basis of the preliminary site visit, the infrastructure demand in the village was
assessed on the basis of need and priority.
The health infrastructure of the study area requires improvement. The lack of medical
facilities needs improvement. Medical facilities will be provided by mine owner during
mining.
5.4 Amenities/Facilities
Workshop
For maintenance of vehicles it is proposed to establish a workshop nearby to mine site
welding, puncture etc.
Power supply
Electric power supply does not exist at mine site and it is proposed to take connection.
Water Supply
A tractor mounted tanker is proposed for supply of water to mining work, spraying,
watering the plants and drinking purposes.
First Aid
A first aid facility is proposed at Mines office.
Rest Shelter
Rest shelter is proposed near mine site.
5.4.1 Budget for facilities provided to Labours
Sl. No. Scheme Cost (in Rs)
1. Drinking water facility 12,000 2. Shelter and sanitation facility 13,000 3. Health facility 14,000
4. Fuel for cooking 10,000
Total 49,000
6.1 Industrial Area (Processing Area)
No infrastructure is proposed.
6.2 Residential Area (Non Processing Area)
As local workers from nearby areas will be engaged for the mining activity, no
residential area/ housing are proposed.
6.3 Green Belt
Total area of green belt would be 33% of ML and surrounding area. As the mine lease
area is 2.8950 Ha so plantation would be around 0.955 Hect.
It is proposed to plant 50 plants per year in ML and surrounding area.
Programme for Plantation
The plantation shall be done at the following places:-
At the boundary of the ML area.
Both site of the transportation road
6.4 Social Infrastructure
The Lessee shall spend 2% of profit for the development of the area i.e. treatment of
poor, schools, and other social work.
6.4.1. Budget for Environmental Social Responsibility (ESR)
The Applicant shall spend 2% of profit for the development of the area i.e. treatment of
poor, schools, temples and other social work.
Budget for Environment Social Responsibility for ESR per year
SI. No. Activity ESR
1 . Provide drinking water facility in surrounding villages and schools by Hand pump/dug well/water tank or
funds for Ambulance. 24,000
2 . Health camps and free medicine 20,000
3 . Clothes distribution to poor villagers 14,000
4. Ladies toilet 13,000
TOTAL 71,000
6.5 Sewerage System
Domestic waste water will be treated into septic tank followed by soak pit
6.6 Industrial Waste Management
Not applicable
6.7 Solid Waste management
The waste overburden in the area is only soil, which will be mined out separately
and will be preserved for reuse in plantation
6.8 Generation of Top Soil:
No top soil will be generated, the mineral is exposed to the surface.
6.9 Power Requirement & Supply/Source
The electricity facility is not available at ML area. It is proposed to connect the
applied ML area with the power supply connection from nearby villages. Only
diesel equipment will be used.
6.10 Environmental Management Plan
The environmental management plan consists of the set of mitigation,
management, monitoring and institutional measures to be taken during the
implementation and operation of the project, to eliminate adverse environmental
impacts or reduce them to acceptable levels. The present environmental
management plan addresses the components of environment, which are likely to
be affected by the different operations in the mine area.
Budget Allotted for the EMP
SI. No. Measures Cost (in Rs.)
1. Pollution Control
i) Dust Suppression 23,000
2.
Pollution Monitoring
i) Air pollution
ii) Water pollution
16,000
3. Green Belt 40,000
Total 79,000
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
As no personnel are expected to be migrated due to mining in the ML area and the
adjoining region is also having a good mineral potential, the rehabilitation of the
employees is not going to be a problem. The workers and other staff can get job in
the neighboring areas after the end of life of mine. The lessee shall also try for
employment of the workers.
8.0 PROJECT SCHEDULE & COST ESTIMATES
8.1 Likely Date of Start of Construction and Likely Date of Completion
No construction activities are proposed. The mining activity will commence only
after receiving environmental clearance and other statutory clearance.
8.2 Estimated Project Cost along with analysis in Terms of Economic Viability of
the Project
Estimated project cost is Rs. 79 Lacs. The lessee has all the mining equipments
used for the scientific mining. The mine is Eco-Friendly. Economically the ore is
mineable as compared to overburden thickness.
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
The proposed mine will bring economical benefits to the state by the way of Royalty
for mineral and to the local people by way of direct and secondary employment
opportunities. Proposed minerals are used for a variety of structural and decorative
purposes. The material is in high demand at the local market for real estate
industry.
The project will bring about socio-economic improvement of the area and will prove
beneficial to the area.